REKAP TOTAL ADDENDUM I PEMBANGUNAN VENUE FUTSAL PADA KEGIATAN PON XVIII TEMBILAHAN - KABUPATEN INDRAGIRI HILIR N0 JENIS PEKERJAAN KONTRAK PEKERJAAN TAMBAH PEKERJAAN KURANG ADDENDUM I I PEKERJAAN PERSIAPAN II PEKERJAAN BANGUNAN UTAMA Rp 1,351,769,553.37 Rp 46,854,016.99 Rp 336,390,655.91 Rp 1,062,232,914.44 III PEKERJAAN RUMAH GENSET Rp 1,022,980,191.81 Rp 211,735,869.29 Rp 364,656,454.05 Rp 870,059,607.05 IV PEKERJAAN RUANG POMPA Rp 105,024,496.85 Rp 1,400,033.84 Rp 1,698,260.29 Rp 104,726,270.40 V PEKERJAAN HYDRANT Rp 308,225,757.98 Rp 7,711,178.84 Rp 1,307,585.00 Rp 314,629,351.82 JUMLAH Rp 2,788,000,000 Rp 267,701,099 Rp 704,052,955 Rp 2,351,648,144 Check Rp (436,351,856.30) Rp (436,351,856.30) ok

Upload: achmad-al-sidik

Post on 09-Aug-2015

41 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: Kontak

REKAP TOTAL ADDENDUM I

PEMBANGUNAN VENUE FUTSAL PADA KEGIATAN PON XVIII

TEMBILAHAN - KABUPATEN INDRAGIRI HILIR

N0 JENIS PEKERJAAN KONTRAK PEKERJAAN TAMBAH PEKERJAAN KURANG ADDENDUM I

I PEKERJAAN PERSIAPAN

II PEKERJAAN BANGUNAN UTAMA Rp 1,351,769,553.37 Rp 46,854,016.99 Rp 336,390,655.91 Rp 1,062,232,914.44

III PEKERJAAN RUMAH GENSET Rp 1,022,980,191.81 Rp 211,735,869.29 Rp 364,656,454.05 Rp 870,059,607.05

IV PEKERJAAN RUANG POMPA Rp 105,024,496.85 Rp 1,400,033.84 Rp 1,698,260.29 Rp 104,726,270.40

V PEKERJAAN HYDRANT Rp 308,225,757.98 Rp 7,711,178.84 Rp 1,307,585.00 Rp 314,629,351.82

JUMLAH Rp 2,788,000,000 Rp 267,701,099 Rp 704,052,955 Rp 2,351,648,144

Check Rp (436,351,856.30) Rp (436,351,856.30) ok

Page 2: Kontak

REKAPITULASI ADDENDUM I

PEMBANGUNAN VENUE FUTSAL PADA KEGIATAN PON XVIII

TEMBILAHAN - KABUPATEN INDRAGIRI HILIR

N0 JENIS PEKERJAAN KONTRAK PEKERJAAN TAMBAH PEKERJAAN KURANG ADDENDUM I

JUMLAH TOTAL JUMLAH TOTAL JUMLAH TOTAL JUMLAH TOTAL

II PEKERJAAN BANGUNAN UTAMA

- Pekerjaan Mekanikal dan Elektrikal Rp 1,351,769,553.37 Rp 46,854,016.99 Rp 336,390,655.91 Rp 1,062,232,914.44

TOTAL PEKERJAAN BANGUNAN UTAMA Rp 1,351,769,553.37 Rp 46,854,016.99 Rp 336,390,655.91 Rp 1,062,232,914.44

III PEKERJAAN RUMAH GENSET

- Pekerjaan Mekanikal dan Elektrikal Rp 1,022,980,191.81 Rp 211,735,869.29 Rp 364,656,454.05 Rp 870,059,607.05

TOTAL PEKERJAAN RUMAH GENSET Rp 1,022,980,191.81 Rp 211,735,869.29 Rp 364,656,454.05 Rp 870,059,607.05

IV PEKERJAAN RUANG POMPA

- Pekerjaan Mekanikal dan Elektrikal Rp 105,024,496.85 Rp 1,400,033.84 Rp 1,698,260.29 Rp 104,726,270.40

TOTAL PEKERJAAN RUANG POMPA Rp 105,024,496.85 Rp 1,400,033.84 Rp 1,698,260.29 Rp 104,726,270.40

V PEKERJAAN HYDRANT

- Pekerjaan Mekanikal dan Elektrikal Rp 308,225,757.98 Rp 7,711,178.84 Rp 1,307,585.00 Rp 314,629,351.82

TOTAL PEKERJAAN HYDRANT Rp 308,225,757.98 Rp 7,711,178.84 Rp 1,307,585.00 Rp 314,629,351.82

JUMLAH Rp 2,788,000,000.01 Rp 267,701,098.95 Rp 704,052,955.25 Rp 2,351,648,143.71

PPN 10 % Rp 278,800,000.00 Rp 26,770,109.90 Rp 70,405,295.52 Rp 235,164,814.37

TOTAL Rp 3,066,800,000.01 Rp 294,471,208.85 Rp 774,458,250.77 Rp 2,586,812,958.08

DIBULATKAN Rp 3,066,000,000.00 Rp 294,000,000.00 Rp 774,000,000.00 Rp 2,586,000,000.00

Page 3: Kontak

PROYEK : PEMBANGUNAN VENUE FUTSAL PADA KEGIATAN PON XVIIIDISPORA-Kab. INDRAGIRI HILIR

KONTRAKTOR :

PEMILIK PROYEK DIREKSI TEKNIS PT WIJAYA KARYA (Persero) Tbk

DISPORA-Kab. INDRAGIRI HILIR DIVISI BANGUNAN GEDUNG

LOKASI : INDRAGIRI HILIR, Tembilahan MINGGUSUB BAGIAN : Prestasi Pekerjaan

4NO. KONTRAK :

TANGGAL : 28-Dec-11 21-Dec-11 S/D 27-Dec-11

NO

URAIAN RENCANA Progress minggu 4 REALISASI

s/d Minggu lalu Progress s/d minggu 3 Progress minggu 4 Progress s/d Bulan Ini s/d Minggu ini bobot prestasi Bobot Bobot Bobot Prestasi (%) bobot prestasi

REKAPITULASI

A PEMBAYARAN LUMP SUMP

1. PERSIAPAN #REF! - #REF! #REF! #REF! #REF! #REF! #REF!2. BANGUNAN UTAMA #NAME? - Err:509 Err:509 Err:509 Err:509 Err:509 Err:5093. RUANG GENSET #NAME? - - 4. RUANG POMPA #NAME? - - 5. HYDRANT #NAME?

PENJUMLAHAN #REF! 0.15 0.15 #REF! #REF! #REF! #REF! #REF! #REF!

MONITORING PROGGRES

MINGGU PRESTASI RENCANA REALISASIper minggu kumulatif Mobilisasi dan Demobilisasi

1 0.1491 0.149 0 Pembuatan Direksi Keet prestasi s/d minggu lalu = 14.91%2 0.1491 0.298 0 Pembuatan Bedeng Buruh dan Los Kerja3 0.1491 0.447 0 Pembuatan Gudang Material prestasi minggu ini = #REF!4 0.1491 0.597 #REF! Pembersihan dan Streching Lokasi5 0.1491 0.746 Pengukuran dan Pemasangan Bowplank prestasi s/d minggu ini = #REF!6 0.2491 0.995 Pasir Urug Area Bangunan 7 0.4491 1.444 Geotekstil Woven prestasi sesuai schedule = 14.91%8 0.6491 2.093 Keamanan Proyek Selama Proyek Berjalan9 1.1491 3.242 Pekerjaan Pembongkaran dan Relokasi deviasi = #REF!10 1.6491 4.891 Izin Mendirikan Bangunan11 1.6491 6.541 Pagar Proyek12 1.6491 8.19013 1.6491 9.839

Tembilahan 1 Februari 200914 2.1108 11.95015 2.1590 14.10916 2.7211 16.830

DIBUAT OLEH17 2.9650 19.79518 3.7118 23.50619 3.1495 26.656 Kontraktor20 3.6537 30.310

PT. WIJAYA KARYA (persero) Tbk21 3.5414 33.85122 3.4400 37.29123 4.1334 41.42424 2.6713 44.09625 2.7611 46.85726 3.3640 50.22127 3.4237 53.64428 3.5848 57.229

M. Ikhsan Sabri29 3.8099 61.03930 4.0834 65.123

Manajer Proyek31 4.6252 69.74832 4.4545 74.20233 3.8635 78.06634 3.6535 81.719

DIPERIKSA OLEH35 1.2664 82.98636 1.0819 84.06837 0.0000 84.068 Direksi Teknis38 0.0000 84.06839 0.7827 84.85040 1.1888 86.03941 1.0483 87.08742 1.1040 88.19143 1.1531 89.34444 0.8508 90.19545 0.8567 91.05246 0.7081 91.76047 0.4530 92.21348 0.4262 92.63949 0.4888 93.12850 0.3012 93.42951 0.1354 93.565

Pejabat Pelaksana Teknis Kegiatan52 0.1761 93.74153 0.1761 93.91754 0.1354 94.052

Hanadi S, ST

DISETUJUI OLEH

Pejabat Pembuat Komitmen

R. Arliansyah, SST

Bobot % Prestasi

(%) Prestasi

(%)

1 2 3 4 50

5

10

15

0.15 0.30 0.45 0.60 0.750.00 0.00 0.00 0.00 0.00

KURVA 'S'

REALISASI RENCANA Linear (RENCANA)

TIME

PRO

GRES

S

Page 4: Kontak

PROYEK : PEMBANGUNAN VENUE FUTSAL PADA KEGIATAN PON XVIIIDISPORA-Kab. INDRAGIRI HILIR

KONTRAKTOR :

PEMILIK PROYEK DIREKSI TEKNIS PT WIJAYA KARYA (Persero) Tbk

DISPORA-Kab. INDRAGIRI HILIR DIVISI BANGUNAN GEDUNG

LOKASI : INDRAGIRI HILIR, Tembilahan MINGGUSUB BAGIAN : Prestasi Pekerjaan

8NO. KONTRAK :

TANGGAL : 21-Jan-12 27-Dec-11 S/D 20-Jan-12

NO

URAIAN RENCANA Progress minggu 8 REALISASI

s/d Minggu lalu Progress s/d minggu 3 Progress minggu 8 Progress s/d Bulan Ini s/d Minggu ini bobot prestasi Bobot Bobot Bobot Prestasi (%) bobot prestasi

REKAPITULASI

A PEMBAYARAN LUMP SUMP

1. PERSIAPAN #REF! - #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!2. BANGUNAN UTAMA #NAME? - Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:5093. RUANG GENSET #NAME? - - 4. RUANG POMPA #NAME? - - 5. HYDRANT #NAME?

PENJUMLAHAN #REF! 0.15 0.15 #REF! #REF! #REF! #REF! #REF! #REF!

MONITORING PROGGRES

MINGGU PRESTASI RENCANA REALISASIper minggu kumulatif Mobilisasi dan Demobilisasi

1 0.1491 0.149 - Pembuatan Direksi Keet prestasi s/d minggu lalu = 14.91%2 0.1491 0.298 - Pembuatan Bedeng Buruh dan Los Kerja3 0.1491 0.447 - Pembuatan Gudang Material prestasi minggu ini = #REF!4 0.1491 0.597 #REF! Pembersihan dan Streching Lokasi5 0.1491 0.746 4.41 Pengukuran dan Pemasangan Bowplank prestasi s/d minggu ini = #REF!6 0.2491 0.995 4.41 Pasir Urug Area Bangunan 7 0.4491 1.444 4.41 Geotekstil Woven prestasi sesuai schedule = 2.09%8 0.6491 2.093 #REF! Keamanan Proyek Selama Proyek Berjalan9 1.1491 3.242 Pekerjaan Pembongkaran dan Relokasi deviasi = #REF!10 1.6491 4.891 Izin Mendirikan Bangunan11 1.6491 6.541 Pagar Proyek12 1.6491 8.19013 1.6491 9.839

Tembilahan 1 Februari 200914 2.1108 11.95015 2.1590 14.10916 2.7211 16.830

DIBUAT OLEH17 2.9650 19.79518 3.7118 23.50619 3.1495 26.656 Kontraktor20 3.6537 30.310

PT. WIJAYA KARYA (persero) Tbk21 3.5414 33.85122 3.4400 37.29123 4.1334 41.42424 2.6713 44.09625 2.7611 46.85726 3.3640 50.22127 3.4237 53.64428 3.5848 57.229

M. Ikhsan Sabri29 3.8099 61.03930 4.0834 65.123

Manajer Proyek31 4.6252 69.74832 4.4545 74.20233 3.8635 78.06634 3.6535 81.719

DIPERIKSA OLEH35 1.2664 82.98636 1.0819 84.06837 0.0000 84.068 Konsultan Pengawas38 0.0000 84.068

PT. WASTITA KREASI39 0.7827 84.85040 1.1888 86.03941 1.0483 87.08742 1.1040 88.19143 1.1531 89.34444 0.8508 90.19545 0.8567 91.05246 0.7081 91.760

EDO TAHARA47 0.4530 92.21348 0.4262 92.639

Team Leader49 0.4888 93.12850 0.3012 93.42951 0.1354 93.565

Pejabat Pelaksana Teknis Kegiatan52 0.1761 93.74153 0.1761 93.91754 0.1354 94.052

Hanadi S, ST

Direksi Teknis

Rony F

DISETUJUI OLEH

Pejabat Pembuat Komitmen

R. Arliansyah, SST

Bobot % Prestasi

(%) Prestasi

(%)

1 2 3 4 5 6 7 8 9 10 11 12 130

3

6

9

12

15

0.15 0.30 0.45 0.60 0.75 0.991.44

2.09

3.24

4.89

6.54

8.19

9.84

0.00 0.00 0.00 0.00

4.41 4.41 4.41

0.00 0.00 0.00 0.00 0.00 0.00

KURVA 'S'

REALISASI RENCANA Linear (RENCANA)

TIME

PRO

GRES

S

Page 5: Kontak
Page 6: Kontak

PROYEK : PEMBANGUNAN VENUE FUTSAL PADA KEGIATAN PON XVIIIDISPORA-Kab. INDRAGIRI HILIR

KONTRAKTOR :

PEMILIK PROYEK DIREKSI TEKNIS PT WIJAYA KARYA (Persero) Tbk

DISPORA-Kab. INDRAGIRI HILIR DIVISI BANGUNAN GEDUNG

LOKASI : INDRAGIRI HILIR, Tembilahan MINGGUSUB BAGIAN : Prestasi Pekerjaan

12NO. KONTRAK :

TANGGAL : 14-Feb-12 20-Jan-12 S/D 13-Feb-12

NO

URAIAN RENCANA Progress minggu 8 REALISASI

s/d Minggu lalu Progress s/d minggu 3 Progress minggu 8 Progress s/d Bulan Ini s/d Minggu ini bobot prestasi Bobot Bobot Bobot Prestasi (%) bobot prestasi

REKAPITULASI

A PEMBAYARAN LUMP SUMP

1. PERSIAPAN #REF! - #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!2. BANGUNAN UTAMA #NAME? - Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:5093. RUANG GENSET #NAME? - - 4. RUANG POMPA #NAME? - - 5. HYDRANT #NAME?

PENJUMLAHAN #REF! 0.15 0.15 #REF! #REF! #REF! #REF! #REF! #REF!

MONITORING PROGGRES

MINGGU PRESTASI RENCANA REALISASIper minggu kumulatif Mobilisasi dan Demobilisasi

1 0.1491 0.149 - Pembuatan Direksi Keet prestasi s/d minggu lalu = 14.91%2 0.1491 0.298 - Pembuatan Bedeng Buruh dan Los Kerja3 0.1491 0.447 - Pembuatan Gudang Material prestasi minggu ini = #REF!4 0.1491 0.597 #REF! Pembersihan dan Streching Lokasi5 0.1491 0.746 4.41 Pengukuran dan Pemasangan Bowplank prestasi s/d minggu ini = #REF!6 0.2491 0.995 4.41 Pasir Urug Area Bangunan 7 0.4491 1.444 4.41 Geotekstil Woven prestasi sesuai schedule = 2.09%8 0.6491 2.093 #REF! Keamanan Proyek Selama Proyek Berjalan9 1.1491 3.242 5.62 Pekerjaan Pembongkaran dan Relokasi deviasi = #REF!10 1.6491 4.891 5.62 Izin Mendirikan Bangunan11 1.6491 6.541 5.62 Pagar Proyek12 1.6491 8.190 #REF!13 1.6491 9.839

Tembilahan 1 Februari 200914 2.1108 11.95015 2.1590 14.10916 2.7211 16.830

DIBUAT OLEH17 2.9650 19.79518 3.7118 23.50619 3.1495 26.656 Kontraktor20 3.6537 30.310

PT. WIJAYA KARYA (persero) Tbk21 3.5414 33.85122 3.4400 37.29123 4.1334 41.42424 2.6713 44.09625 2.7611 46.85726 3.3640 50.22127 3.4237 53.64428 3.5848 57.229

M. Ikhsan Sabri29 3.8099 61.03930 4.0834 65.123

Manajer Proyek31 4.6252 69.74832 4.4545 74.20233 3.8635 78.06634 3.6535 81.719

DIPERIKSA OLEH35 1.2664 82.98636 1.0819 84.06837 0.0000 84.068 Konsultan Pengawas38 0.0000 84.068

PT. WASTITA KREASI39 0.7827 84.85040 1.1888 86.03941 1.0483 87.08742 1.1040 88.19143 1.1531 89.34444 0.8508 90.19545 0.8567 91.05246 0.7081 91.760

EDO TAHARA47 0.4530 92.21348 0.4262 92.639

Team Leader49 0.4888 93.12850 0.3012 93.42951 0.1354 93.565

Pejabat Pelaksana Teknis Kegiatan52 0.1761 93.74153 0.1761 93.91754 0.1354 94.052

Hanadi S, ST

Direksi Teknis

Rony F

DISETUJUI OLEH

Pejabat Pembuat Komitmen

R. Arliansyah, SST

Bobot % Prestasi

(%) Prestasi

(%)

1 2 3 4 5 6 7 8 9 10 11 12 130

3

6

9

12

15

0.15 0.30 0.45 0.60 0.75 0.991.44

2.09

3.24

4.89

6.54

8.19

9.84

0.00 0.00 0.00 0.00

4.41 4.41 4.41

0.00

5.62 5.62 5.62

0.00 0.00

KURVA 'S'

REALISASI RENCANA Linear (RENCANA)

TIME

PRO

GRES

S

Page 7: Kontak
Page 8: Kontak

DAFTAR KUANTITAS DAN HARGA

PEKERJAAN #REF!

SUB PEKERJAAN : BANGUNAN UTAMA

LOKASI : TEMBILAHAN - INDRAGIRI HILIR

NO. PEKERJAAN ADDENDUM I

BOBOT. Minggu lalu Minggu ini S/D Minggu ini

VOLUME SAT % Bobot % Bobot % Bobot

1 2 15 16

III ELEKTRIKAL

1 PEKERJAAN PANEL GEDUNG

- SDP-BANGUNAN UTAMA 1.00 Unit 0.01 90% 0.01 10% 0.00 100% 0.01

- LP- EXTERIOR 1.00 Unit 0.01 90% 0.01 10% 0.00 100% 0.01

( Penerangan sisi luar, system auto manual

- LP - SPORT AREA 2.00 Unit 0.01 45% 0.01 55% 0.01 100% 0.01

( Penerangan lampu utama khusus lapangan

- LP - 1A ( Panel Penerangan, Stop Kontak & AC 1.00 Unit 0.00 90% 0.00 10% 0.00 100% 0.00

- LP - 1B ( Panel Penerangan, Stop Kontak & AC 1.00 Unit 0.00 90% 0.00 10% 0.00 100% 0.00

- LP - 2A ( Panel Penerangan, Stop Kontak & AC 1.00 Unit 0.00 90% 0.00 10% 0.00 100% 0.00

- LP - 3A ( Panel Penerangan, Stop Kontak & AC 1.00 Unit 0.00 90% 0.00 10% 0.00 100% 0.00

- Grounding system 1.00 Lot 0.01 90% 0.01 10% 0.00 100% 0.01

2 PEKERJAAN KABEL FEEDER GEDUNG

dari SDP GEDUNG ke :

a LP - EXTERIOR

- NYY 4 x 35 mm2 95.00 m 0.77 29% 0.22 66% 0.51 95% 0.73

b LP - SPORT AREA

- NYY 4 x 35 mm2 95.00 m 0.77 28% 0.21 67% 0.51 95% 0.73

c LP - 1A

- NYY 4 x 50 mm2 111.00 m 1.33 27% 0.36 68% 0.90 95% 1.26

d LP - 1B

- NYY 4 x 50 mm2 95.00 m 1.14 28% 0.32 67% 0.76 95% 1.08

e LP - 2A

- NYY 4 x 10 mm2 115.00 m 0.32 31% 0.10 64% 0.20 95% 0.30

f LP - 3A

- NYY 4 x 6 mm2 125.00 m 0.23 32% 0.07 63% 0.14 95% 0.22

3 PEKERJAAN INTALASI PENERANGAN

a Lantai.1

ARMATURE

- LP. DOWN LIGHT 36 WATT, PL-C 162.00 bh 0.06 94% 0.05 6% 0.00 100% 0.06

- LP. SPOT LIGHT PAR 22.00 bh 0.01 71% 0.01 29% 0.00 100% 0.01

- ML 2 x 18 WATT 53.00 bh 0.02 69% 0.01 31% 0.01 100% 0.02

Page 9: Kontak

NO. PEKERJAAN ADDENDUM I

BOBOT. Minggu lalu Minggu ini S/D Minggu ini

VOLUME SAT % Bobot % Bobot % Bobot

1 2 15 16

- LP. LAMPU GMS 1 X 36 WATT 2.00 bh 0.00 33% 0.00 67% 0.00 100% 0.00

- LP GANTUNG STELLO GLOBE 1 x 36 WATT 32.00 bh 0.23 76% 0.17 24% 0.05 100% 0.23

- Lampu Kolom type minimalis 36 watt 68.00 bh 0.02 89% 0.02 11% 0.00 100% 0.02

- Lampu EXIT 7.00 bh 0.00 100% 0.00 0% - 100% 0.00

INSTALASI

- Instalasi Penerangan NYM 3 x 2,5 mm + pipa 346.00 ttk 3.63 84% 3.06 11% 0.40 95% 3.46

b. Lantai.2

ARMATURE

- LP. DOWN LIGHT 36 WATT, PL-C 51.00 bh 0.02 80% 0.01 20% 0.00 100% 0.02

- ML 2 x 18 WATT 6.00 bh 0.00 67% 0.00 33% 0.00 100% 0.00

- LP. LAMPU GMS 1 X 36 WATT 8.00 bh 0.00 100% 0.00 0% - 100% 0.00

- LP. LAMPU BARET 36 WATT - bh - 0% - 100% - 100% -

- DIGITAL SCORE BOARD ( 210 x 120 ) 2.00 UNIT 0.02 0% - 100% 0.02 100% 0.02

INSTALASI

- Instalasi Penerangan NYM 3 x 2,5 mm + pipa 67.00 ttk 0.70 92% 0.65 8% 0.06 100% 0.70

c. Lantai.3

ARMATURE

- LP. Lampu Sorot HPI-T 400 WATT 100.00 bh 0.05 83% 0.04 17% 0.01 100% 0.05

- LP. DOWN LIGHT 36 WATT, PL-C 91.00 bh 0.03 10% 0.00 90% 0.03 100% 0.03

- ML 2 x 18 WATT 15.00 bh 0.01 100% 0.01 0% - 100% 0.01

- Lampu Kolom type minimalis 36 watt 14.00 bh 0.00 54% 0.00 46% 0.00 100% 0.00

- LP. LAMPU GMS 1 X 36 WATT 8.00 bh 0.00 100% 0.00 0% - 100% 0.00

- Instalasi Penerangan NYM 3 x 2,5 mm + pipa 128.00 ttk 2.67 65% 1.74 30% 0.80 95% 2.54

- Instalasi Penerangan NYM 3 x 2,5 mm + pipa 100.00 ttk 2.08 83% 1.74 12% 0.25 95% 1.99

4 DIGITAL SCORE BOARD

- DIGITAL SCORE BOARD 2.00 UNIT 0.14 67% 0.09 33% 0.05 100% 0.14

Terdiri dari :

- 1 unit main board display ukuran 240 x 120 x 12

- 2 unit personal fouls display ukuran 70 x 120 x 12

- 2 unit shoot clock display ukuran 30 x 35 x 8 + timing

- 2 unit controler

- 1 unit moving sign display ukuran 240 x 30 x 8

- 1 unit keyboard

- Bell

- Pengkabelan

- Aksesoris, Gantungan, bracket, dll

5 PEKERJAAN SAKLAR & STOP KONTAK

Page 10: Kontak

NO. PEKERJAAN ADDENDUM I

BOBOT. Minggu lalu Minggu ini S/D Minggu ini

VOLUME SAT % Bobot % Bobot % Bobot

1 2 15 16

a Lantai.1

- Saklar Tunggal 60.00 bh 0.03 86% 0.03 14% 0.00 100% 0.03

- Saklar Ganda 30.00 bh 0.02 92% 0.02 8% 0.00 100% 0.02

- Saklar Hotel 2.00 bh 0.00 50% 0.00 50% 0.00 100% 0.00

- Stop Kontak 250 VA, 13 A 40.00 bh 0.03 89% 0.03 11% 0.00 100% 0.03

- Instalasi Stop Kontak NYM 3 x 2,5 mm + pipa 40.00 ttk 0.53 89% 0.47 11% 0.06 100% 0.52

b. Lantai.2

- Saklar Tunggal 14.00 bh 0.01 72% 0.01 28% 0.00 100% 0.01

- Saklar Ganda 9.00 bh 0.01 50% 0.00 50% 0.00 100% 0.01

- Saklar Hotel 2.00 bh 0.00 50% 0.00 50% 0.00 100% 0.00

- Stop Kontak 250 VA, 13 A 6.00 bh 0.01 38% 0.00 62% 0.00 100% 0.01

- Instalasi Stop Kontak NYM 3 x 2,5 mm + pipa 6.00 ttk 0.08 38% 0.03 62% 0.05 100% 0.08

C. Lantai.3

- Saklar Tunggal 7.00 bh 0.00 41% 0.00 59% 0.00 100% 0.00

- Saklar Ganda 9.00 bh 0.01 50% 0.00 50% 0.00 100% 0.01

- Saklar Hotel 2.00 bh 0.00 14% 0.00 86% 0.00 100% 0.00

- Stop Kontak 250 VA, 13 A 8.00 bh 0.01 5% 0.00 95% 0.01 100% 0.01

- Instalasi Stop Kontak NYM 3 x 2,5 mm + pipa 8.00 bh 0.11 5% 0.01 95% 0.10 100% 0.11

6 PEKERJAAN AIR CONDITIONER

Lantai.1

- AC Split Komplit set , 5 PK - unit - 0% - 100% - 100% -

- AC Split Komplit set , 2 PK LT.1 10.00 unit 0.19 40% 0.07 60% 0.11 100% 0.19

- AC Split Komplit set , 1.5 PK LT.1 2.00 unit 0.03 80% 0.03 20% 0.01 100% 0.03

- AC Split Komplit set , 1 PK LT.1 6.00 unit 0.08 80% 0.07 20% 0.02 100% 0.08

- AC Split Komplit set , 0.5 PK LT.1 3.00 unit 0.04 50% 0.02 50% 0.02 100% 0.04

- Instalasi Stop Kontak AC NYM 3 x 2,5 mm + p 21.00 ttk 0.28 100% 0.28 0% - 100% 0.28

- Outlet Stop Kontak AC 21.00 ttk 0.03 100% 0.03 0% - 100% 0.03

Lantai.2

- AC Split Komplit set , 1 PK LT.1 3.00 unit 0.04 67% 0.03 33% 0.01 100% 0.04

- Instalasi Stop Kontak AC NYM 3 x 2,5 mm + p 3.00 ttk 0.04 100% 0.04 0% - 100% 0.04

- Outlet Stop Kontak AC 3.00 ttk 0.00 100% 0.00 0% - 100% 0.00

Lantai.3

- AC Split Komplit set , 1 PK LT.1 6.00 unit 0.08 83% 0.07 17% 0.01 100% 0.08

- AC Split Komplit set , 2 PK LT.1 2.00 unit 0.04 0% - 100% 0.04 100% 0.04

- AC Split Komplit set , 0,5 PK LT.1 1.00 unit 0.01 0% - 100% 0.01 100% 0.01

Page 11: Kontak

NO. PEKERJAAN ADDENDUM I

BOBOT. Minggu lalu Minggu ini S/D Minggu ini

VOLUME SAT % Bobot % Bobot % Bobot

1 2 15 16

- Instalasi Stop Kontak AC NYM 3 x 2,5 mm + p 8.00 ttk 0.11 83% 0.09 17% 0.02 100% 0.11

- Outlet Stop Kontak AC 8.00 ttk 0.01 83% 0.01 17% 0.00 100% 0.01

7 PEKERJAAN EXHOUST FAN

- Exhaust Fan, 300 CFM, 8 ", 18 W, FV-20TGU1 64.00 unit 0.11 53% 0.06 47% 0.05 100% 0.11

- Instalasi Exhoustfan 3 x 2,5 mm + pipa condu 64.00 ttk 0.84 53% 0.45 47% 0.39 100% 0.84

- pemipaan exhaust fan menggunakan pipa pv 373.00 m 1.14 0% - 100% 1.14 100% 1.14

8 PEKERJAAN KABEL TRAY

- Standard Tray Ukuran 30 cm x 10 cm 255.00 m 5.28 76% 4.00 24% 1.27 100% 5.26

9 TESTING COMMISSIONING 1.00 lot 0.14 0% - 100% 0.14 100% 0.14

10 SOUND SYSTEM

a PERALATAN UTAMA

- Power Amplfier 600 watt 1.00 unit 0.00 90% 0.00 10% 0.00 100% 0.00

- DVD PLAYER + MP3 1.00 unit 0.00 90% 0.00 10% 0.00 100% 0.00

- Equalizer 1.00 unit 0.00 90% 0.00 10% 0.00 100% 0.00

- Cabinet Rack 1.00 Set 0.01 90% 0.01 10% 0.00 100% 0.01

- Mic Amplifier w/ Chime tipe 1.00 bh 0.00 90% 0.00 10% 0.00 100% 0.00

- Mixer Amplifier 240 Watt w/ 5-Zone Selector 1.00 bh 0.00 90% 0.00 10% 0.00 100% 0.00

- Instalasi 1.00 ls 0.02 90% 0.02 10% 0.00 100% 0.02

b UHF WIRELESS MICROPHONE SYSTEM

Wireless Microphone Handheld 2.00 bh 0.00 45% 0.00 55% 0.00 100% 0.00

UHF Head Set Microphone 4.00 bh 0.00 22% 0.00 77% 0.00 100% 0.00

Wireless Receiver space diversity 16CH 1.00 bh 0.00 90% 0.00 10% 0.00 100% 0.00

Wireless Antenna 1.00 bh 0.00 90% 0.00 10% 0.00 100% 0.00

c Kabel distribusi dari peralatan utama ke :

- TBS-1 ( Terminal box sound system LT.1 )

NYMHY 2 ( 3 x 2,5 mm ) + pipa conduit 210.00 m 0.47 19% 0.09 81% 0.38 100% 0.47

- TBS-1 ( Terminal box sound system LT.1 )

NYMHY 2 ( 3 x 2,5 mm ) + pipa conduit 220.00 m 0.49 16% 0.08 84% 0.42 100% 0.49

- TBS-1 ( Terminal box sound system LT.1 )

NYMHY 2 ( 3 x 2,5 mm ) + pipa conduit 230.00 m 0.52 13% 0.07 87% 0.45 100% 0.52

d LANTAI.1

- Horn Speaker 25 watt ( untuk sisi luar & hala - bh - 0% - 100% - 100% -

- Column Speaker 20 watt 10.00 bh 0.00 40% 0.00 60% 0.00 100% 0.00

Page 12: Kontak

NO. PEKERJAAN ADDENDUM I

BOBOT. Minggu lalu Minggu ini S/D Minggu ini

VOLUME SAT % Bobot % Bobot % Bobot

1 2 15 16

- Ceiling Speaker 3 Watt 44.00 bh 0.02 70% 0.01 30% 0.01 100% 0.02

- Volume Control Speaker 12.00 bh 0.01 58% 0.00 42% 0.00 100% 0.01

- Accesories 1.00 ls 0.03 30% 0.01 70% 0.02 100% 0.03

- TBS-1 ( Terminal box sound system LT.1 ) 1.00 bh 0.01 90% 0.01 10% 0.00 100% 0.01

- Instalasi Sound System NYMHY 3 x 1,5 mm + 54.00 bh 0.70 78% 0.55 22% 0.15 100% 0.70

e LANTAI.2

- Ceiling Speaker 3 Watt 19.00 bh 0.01 100% 0.01 0% - 100% 0.01

- Volume Control Speaker 1.00 bh 0.00 100% 0.00 0% - 100% 0.00

- Accesories 1.00 ls 0.01 100% 0.01 0% - 100% 0.01

- TBS-2 ( Terminal box sound system LT.2 ) 1.00 bh 0.01 100% 0.01 0% - 100% 0.01

- Instalasi Sound System NYMHY 3 x 1,5 mm + 19.00 bh 0.25 100% 0.25 0% - 100% 0.25

f LANTAI.3

- Column Speaker 20 watt 18.00 bh 0.01 83% 0.01 17% 0.00 100% 0.01

- Ceiling Speaker 3 Watt 7.00 bh 0.00 86% 0.00 14% 0.00 100% 0.00

- Volume Control Speaker 4.00 bh 0.00 100% 0.00 0% - 100% 0.00

- Accesories 1.00 ls 0.01 100% 0.01 0% - 100% 0.01

- TBS-3 ( Terminal box sound system LT.3 ) 1.00 bh 0.01 100% 0.01 0% - 100% 0.01

- Instalasi Sound System NYMHY 3 x 1,5 mm + 25.00 bh 0.33 100% 0.33 0% - 100% 0.33

g TESTING COMMISSIONING 1.00 LOT 0.02 0% - 100% 0.02 100% 0.02

11 PEKERJAAN TELEPON

a PERALATAN UTAMA

PABX kapasitas 3/30 ext lengkap dengan : 1.00 set 0.00 100% 0.00 0% - 100% 0.00

- Main Distribution Frame 100 pair

- Operator Console

- Back Up Battery

- Monitor + Billing System

- Peralatan Bantu

- Accessories

b LANTAI.1

- Instalasi Telepon Saluran Langsung + Outlet 2.00 ttk 0.02 50% 0.01 50% 0.01 100% 0.02

- Instalasi Telepon Tak Langsung / Extention 16.00 ttk 0.19 78% 0.15 22% 0.04 100% 0.19

- Pesawat Telepon 18.00 bh 0.00 0% - 100% 0.00 100% 0.00

- TB-1 ( Terminal Box - LT.1 ) 1.00 unit 0.00 90% 0.00 10% 0.00 100% 0.00

- Accessories 1.00 ls 0.01 90% 0.01 10% 0.00 100% 0.01

Page 13: Kontak

NO. PEKERJAAN ADDENDUM I

BOBOT. Minggu lalu Minggu ini S/D Minggu ini

VOLUME SAT % Bobot % Bobot % Bobot

1 2 15 16

c LANTAI.2

- Instalasi Telepon Tak Langsung / Extention 1.00 ttk 0.01 80% 0.01 20% 0.00 100% 0.01

- Pesawat Telepon 1.00 bh 0.00 0% - 100% 0.00 100% 0.00

- TB-2 ( Terminal Box - LT.2 ) 1.00 unit 0.00 90% 0.00 10% 0.00 100% 0.00

- Accessories 1.00 ls 0.01 90% 0.01 10% 0.00 100% 0.01

d LANTAI.3

- Instalasi Telepon Tak Langsung / Extention 5.00 ttk 0.06 100% 0.06 0% - 100% 0.06

- Pesawat Telepon 5.00 bh 0.00 0% - 100% 0.00 100% 0.00

- TB-3 ( Terminal Box - LT.3 ) 1.00 unit 0.00 100% 0.00 0% - 100% 0.00

- Accessories 1.00 ls 0.01 100% 0.01 0% - 100% 0.01

e Kabel dari MDF ke :

- TB-1 ( Terminal Box - LT.1 )

ITC 20 x 2 x 0,6 mm2 210.00 m' 0.33 10% 0.03 90% 0.30 100% 0.33

- TB-2 ( Terminal Box - LT.2 )

ITC 4 x 2 x 0,6 mm2 220.00 m' 0.07 10% 0.01 90% 0.06 100% 0.07

- TB-3 ( Terminal Box - LT.3 )

ITC 10 x 3 x 0,6 mm2 230.00 m' 0.27 10% 0.03 90% 0.24 100% 0.27

f TESTING COMMISSIONING 1.00 LOT 0.02 0% - 100% 0.02 100% 0.02

12 PENANGKAL PETIR

a Penangkal petir Ionisasi system rad.100 m 1.00 unit 0.71 100% 0.71 0% - 100% 0.71

b 210.00 m' 0.78 48% 0.37 52% 0.41 100% 0.78

c Lampu Obstruction 60 Watt + Photo Cell 1.00 bh 0.01 0% - 100% 0.01 100% 0.01

d Pentanahan terdiri dari : 1.00 lot 0.31 0% - 100% 0.31 100% 0.31

- Bak Kontrol 40 x 40 x 40 cm

- Copper rod 5/8" x 5 meter, Tahanan Pentanahan maks. 5 ohm

- Material Bantu

- Klem-klem

e Tiang sepanjang 5 meter di atas gedung + klem s 1.00 lot 0.02 0% - 100% 0.02 100% 0.02

f Aksesories 1.00 lot 0.01 80% 0.01 20% 0.00 100% 0.01

g TESTING COMMISSIONING 1.00 LOT 0.07 0% - 100% 0.07 100% 0.07

Pekerjaan Elektrikal

IV MEKANIKAL

1 PEKERJAAN INTALASI PEMIPAAN .

Kabel NYY 70 mm2 dan Peralatan Bantu

Page 14: Kontak

NO. PEKERJAAN ADDENDUM I

BOBOT. Minggu lalu Minggu ini S/D Minggu ini

VOLUME SAT % Bobot % Bobot % Bobot

1 2 15 16

LANTAI.1

a. Pemipaan Air Bersih

Pipa GIP Medium Class

- dia. 2" 385.00 m 1.54 46% 0.71 54% 0.83 100% 1.54

- dia. 1" 235.00 m 0.46 77% 0.36 23% 0.11 100% 0.46

- dia. 3/4" 215.00 m 0.28 42% 0.12 58% 0.16 100% 0.28

- dia. 1/2" 435.00 m 0.43 100% 0.43 0% - 100% 0.43

- Fitting & Accessories 1.00 lot 0.57 80% 0.45 20% 0.11 100% 0.57

Gate Valve

- dia. 1" 16.00 bh 0.09 100% 0.09 0% - 100% 0.09

b. Pemipaan Air Kotor, Bekas & Vent

Pipa PVC Class AW

- dia. 6" 245.00 m 1.57 10% 0.15 90% 1.41 100% 1.57

- dia. 4" 220.00 m 0.67 85% 0.57 15% 0.10 100% 0.67

- dia. 3" 280.00 m 0.55 86% 0.47 14% 0.08 100% 0.55

- dia. 2" 240.00 m 0.26 85% 0.23 15% 0.04 100% 0.26

- dia. 1 1/2" 135.00 m 0.11 85% 0.10 15% 0.02 100% 0.12

Fitting & Accessories 1.00 lot 0.65 85% 0.55 15% 0.10 100% 0.65

c Septic Tank + resapan

Capasitas 24 m3 - unit - 0% - 100% - 100% -

Capasitas 8 m3 - unit - 0% - 100% - 100% -

Bioseptic Capasitas 15 m3 2.00 unit 0.12 0% - 100% 0.12 100% 0.12

Bioseptic Capasitas 5 m3 2.00 unit 0.03 0% - 100% 0.03 100% 0.03

Bioseptic Capasitas 3 m3 2.00 unit 0.01 0% - 100% 0.01 100% 0.01

LANTAI.2

a. Pemipaan Air Bersih

Pipa GIP Medium Class

- dia. 2" 112.00 m 0.45 89% 0.40 11% 0.05 100% 0.45

- dia. 1" 133.00 m 0.26 53% 0.14 47% 0.12 100% 0.26

- dia. 1/2" 142.00 m 0.14 70% 0.10 30% 0.04 100% 0.14

- Fitting & Accessories 1.00 lot 0.18 75% 0.13 25% 0.04 100% 0.18

Gate Valve

- dia. 1" 4.00 bh 0.02 100% 0.02 0% - 100% 0.02

b. Pemipaan Air Kotor, Bekas & Vent

Pipa PVC Class AW

- dia. 6" 86.00 m 0.55 71% 0.39 29% 0.16 100% 0.55

- dia. 4" 76.00 m 0.23 80% 0.19 20% 0.05 100% 0.23

- dia. 2" 62.00 m 0.07 80% 0.05 20% 0.01 100% 0.07

- dia. 1 1/2" 110.00 m 0.09 30% 0.03 70% 0.07 100% 0.09

Fitting & Accessories 1.00 lot 0.20 30% 0.06 70% 0.14 100% 0.20

Page 15: Kontak

NO. PEKERJAAN ADDENDUM I

BOBOT. Minggu lalu Minggu ini S/D Minggu ini

VOLUME SAT % Bobot % Bobot % Bobot

1 2 15 16

LANTAI.3

a. Pemipaan Air Bersih

Pipa GIP Medium Class

- dia. 2" 142.00 m 0.57 80% 0.45 20% 0.11 100% 0.57

- dia. 1" 125.00 m 0.25 80% 0.20 20% 0.05 100% 0.25

- dia. 1/2" 117.00 m 0.12 80% 0.09 20% 0.02 100% 0.12

- Fitting & Accessories 1.00 lot 0.20 80% 0.16 20% 0.04 100% 0.20

Gate Valve

- dia. 1" 1.00 bh 0.01 80% 0.00 20% 0.00 100% 0.01

b. Pemipaan Air Kotor, Bekas & Vent

Pipa PVC Class AW

- dia. 6" 45.00 m 0.29 0% - 100% 0.29 100% 0.29

- dia. 4" 36.00 m 0.11 80% 0.09 20% 0.02 100% 0.11

- dia. 2" 45.00 m 0.05 80% 0.04 20% 0.01 100% 0.05

- dia. 1 1/2" 97.00 m 0.08 80% 0.07 20% 0.02 100% 0.08

Fitting & Accessories 1.00 lot 0.11 80% 0.09 20% 0.02 100% 0.11

b. Pekerjaan Tangki

- Tangki Fiber 1500 L 12.00 unit 0.20 100% 0.20 0% - 100% 0.20

- Bantalan Tanki (dg besi UNP.100 ) 2.00 unit 0.06 100% 0.06 0% - 100% 0.06

- Pompa Air Jet Pump + Aksesoris 2.00 unit 0.03 0% - 100% 0.03 100% 0.03

- gate valve 2" 4.00 unit 0.06 0% - 100% 0.06 100% 0.06

- floating valve 2" 2.00 unit 0.05 0% - 100% 0.05 100% 0.05

Pemipaan Air Hujan

- Pipa PVC Class AW dia 4" 914.00 m 2.79 98% 2.75 2% 0.06 100% 2.81

- Pipa PVC Class AW dia 2" 123.00 m 0.14 0% - 100% 0.14 100% 0.14

- Roof Drain 4" 52.00 bh 0.35 69% 0.24 31% 0.11 100% 0.35

- Roof Drain 2" 8.00 bh 0.05 0% - 100% 0.05 100% 0.05

- Fitting & Accessories 1.00 lot 0.56 100% 0.56 0% - 100% 0.56

- Bak kontrol (500 x 500 x 700 mm) - unit - 0% - 100% - 100% -

3 PEMADAM API RINGAN

- Fire Extinguisher, kap. 5 Kg, (Dry Chemical 15.00 bh 0.02 80% 0.01 20% 0.00 100% 0.02

Pekerjaan Mekanikal

Pekerjaan ME 45.17 28.45 11.71 40.16

Page 16: Kontak

LAPORAN PRESTASI PEKERJAAN

KONTRAKTOR :

DINAS PEMUDA DAN OLAH RAGA DIREKSI TEKNIS PT WIJAYA KARYA (Persero) Tbk

PEMERINTAH KABUPATEN INDRAGIRI HILIR DIVISI BANGUNAN GEDUNG

KEGIATAN #REF!

PEKERJAAN #REF!

SUB PEKERJAAN : BANGUNAN UTAMA

LOKASI : TEMBILAHAN - INDRAGIRI HILIR

NO. PEKERJAAN VOLUME SAT Bobot %

Progress minggu 8

Progress sebelumnya Progress minggu 8 Progress s/d Bulan Ini1 2 3 4 Volume Bobot Volume Bobot Volume Bobot

I PEKERJAAN STRUKTURAL

1 Pengadaan Tiang Pancang Dia. 35 13,140.00 m¹ 141.307 Err:509 Err:509 Err:509 657.0 7.07 5% Err:509 Err:509 Err:5092 Unloading Tiang Pancang dari ponton ke Stocking 2,190.00 btg 8.079 Err:509 Err:509 Err:509 109.5 0.40 5% Err:509 Err:509 Err:5093 Transport Tiang Pancang dari Stocking ke Site 2,190.00 btg 9.251 Err:509 Err:509 Err:509 109.5 0.46 5% Err:509 Err:509 Err:5094 Pemancangan Tiang Pancang 13,140.00 m¹ 71.822 - - 0% - - 0%5 Penyambungan Tiang Pancang 1,825.00 joint 12.504 - - 0% - - 0%6 Pemotongan Kepala Tiang Pancang 365.00 ttk 2.047 - - 0% - - 0%7 PDA Test 2.00 ttk 1.140 - - 0% - - 0%8 Cerucuk Bakau 714.00 btg 0.939 - - 0% - - 0%9 Galian Tanah Pondasi 162.94 m³ 0.313 - - 0% - - 0%

10 Urugan Tanah Kembali 108.63 m³ 0.070 - - 0% - - 0%11 Urugan Pasir Pondasi 162.94 m³ 0.531 - - 0% - - 0%12 Lantai Kerja Beton K 100 162.94 m³ 4.058 - - 0% - - 0%13 Rolag Bata 131.03 m² 0.951 - - 0% - - 0%14 Beton Isian Tiang Pancang

- Beton K 300 11.31 m³ 0.374 - - - - 0% - Pembesian 2,431.70 kg 0.837 - - - - 0% - Bekisting 22.61 m² 0.089 - - - - 0%

15 Pile Cap Tipe P1

- Beton K 300 106.11 m³ 3.509 - - - - 0% - Pembesian 27,057.61 kg 9.317 - - - - 0% - Bekisting 339.55 m² 1.565 - - - - 0%

16 Pile Cap Tipe P2

- Beton K 300 218.34 m³ 7.221 - - - - 0% - Pembesian 55,676.24 kg 19.171 - - - - 0% - Bekisting 698.68 m² 3.220 - - - - 0%

17 Pondasi Lajur

- Beton K 300 123.85 m³ 4.096 - - - - 0% - Pembesian 29,104.39 kg 10.022 - - - - 0% - Bekisting 247.70 m² 1.142 - - - - 0%

18 Sloof B2 30/60

- Beton K 300 37.08 m³ 1.226 - - - - 0% - Pembesian 8,714.59 kg 3.001 - - - - 0% - Bekisting 74.17 m² 0.363 - - - - 0%

19 Sloof B3 25/45

- Beton K 300 100.02 m³ 3.308 - - - - 0% - Pembesian 23,505.84 kg 8.094 - - - - 0% - Bekisting 200.05 m² 0.979 - - - - 0%

20 Kolom K1 40/100

- Beton K 300 265.38 m³ 8.777 - - - - 0% - Pembesian 67,671.86 kg 23.302 - - - - 0% - Bekisting 796.14 m² 8.114 - - - - 0%

21 Kolom K2 40/80

- Beton K 300 51.96 m³ 1.718 - - - - 0% - Pembesian 13,249.44 kg 4.562 - - - - 0% - Bekisting 155.88 m² 1.589 - - - - 0%

22 Kolom K3 40/40

- Beton K 300 25.98 m³ 0.859 - - - - 0% - Pembesian 6,364.93 kg 2.192 - - - - 0% - Bekisting 77.94 m² 0.794 - - - - 0%

23 Kolom K4 40/40

- Beton K 300 30.73 m³ 1.016 - - - - 0% - Pembesian 7,528.41 kg 2.592 - - - - 0% - Bekisting 92.18 m² 0.940 - - - - 0%

24 Kolom K5 40/40

- Beton K 300 9.22 m³ 0.305 - - - - 0% - Pembesian 2,258.52 kg 0.778 - - - - 0% - Bekisting 27.66 m² 0.282 - - - - 0%

25 Kolom K6 40/40

- Beton K 300 6.98 m³ 0.231 - - - - 0% - Pembesian 1,711.00 kg 0.589 - - - - 0% - Bekisting 20.95 m² 0.214 - - - - 0%

26 Kolom K7 40/40

- Beton K 300 17.32 m³ 0.573 - - - - 0% - Pembesian 4,243.28 kg 1.461 - - - - 0% - Bekisting 51.96 m² 0.530 - - - - 0%

27 Kolom K8 40/40

- Beton K 300 13.97 m³ 0.462 - - - - 0% - Pembesian 3,422.00 kg 1.178 - - - - 0% - Bekisting 41.90 m² 0.427 - - - - 0%

28 Kolom K9 40/40

- Beton K 300 7.33 m³ 0.243 - - - - 0% - Pembesian 1,796.55 kg 0.619 - - - - 0% - Bekisting 22.00 m² 0.224 - - - - 0%

29 Kolom Praktis

- Beton K 300 5.89 m³ 0.195 - - - - 0% - Pembesian 1,149.03 kg 0.396 - - - - 0% - Bekisting 11.78 m² 0.12 - - - - 0%

Prestasi (%)

Prestasi (%)

Prestasi (%)

Page 17: Kontak

KEGIATAN #REF!

PEKERJAAN #REF!

SUB PEKERJAAN : BANGUNAN UTAMA

LOKASI : TEMBILAHAN - INDRAGIRI HILIR

NO. PEKERJAAN VOLUME SAT Bobot %

Progress minggu 8

Progress sebelumnya Progress minggu 8 Progress s/d Bulan Ini1 2 3 4 Volume Bobot Volume Bobot Volume Bobot

Prestasi (%)

Prestasi (%)

Prestasi (%)

30 Balok Tipe B1 30/70

- Beton K 300 23.79 m³ 0.787 - - - - 0% - Pembesian 5,898.92 kg 2.031 - - - - 0% - Bekisting 80.87 m² 0.864 - - - - 0%

31 Balok Tipe B2 30/60

- Beton K 300 104.41 m³ 3.453 - - - - 0% - Pembesian 25,894.86 kg 8.916 - - - - 0% - Bekisting 355.01 m² 3.793 - - - - 0%

32 Balok Tipe B3 25/45

- Beton K 300 152.66 m³ 5.049 - - - - 0% - Pembesian 37,860.76 kg 13.037 - - - - 0% - Bekisting 519.06 m² 5.546 - - - - 0%

33 Plat Lantai Dasar

- Beton K 300 654.62 m³ 21.651 - - - - 0% - Pembesian 75,280.75 kg 25.922 - - - - 0% - Bekisting 785.54 m² 3.620 - - - - 0%

34 Plat Lantai Satu

- Beton K 300 78.44 m³ 2.594 - - - - 0% - Pembesian 9,805.09 kg 3.376 - - - - 0% - Bekisting 313.76 m² 1.446 - - - - 0%

35 Plat Lantai Dua

- Beton K 300 50.32 m³ 1.664 - - - - 0% - Pembesian 6,290.55 kg 2.166 - - - - 0% - Bekisting 201.30 m² 0.928 - - - - 0%

35 Tribun

- Beton K 300 556.97 m³ 18.421 - - - - 0% - Pembesian ### kg 44.302 - - - - 0% - Bekisting 2,227.89 m² 23.529 - - - - 0%

36 Tangga

- Beton K 300 18.14 m³ 0.600 - - - - 0% - Pembesian 4,589.72 kg - Err:509 - Err:509 0% - Bekisting 90.71 m² 0.872 - - - - 0%

37 Baja Profil 11,831.60 kg 7.626 - - - - 0%38 Angkur 12.00 titik 0.635 - - - - 0%

Pekerjaan Struktur 598.65 Err:509 Err:509

Page 18: Kontak

LAPORAN PRESTASI PEKERJAAN

DINAS PEMUDA DAN OLAH RAGA DIREKSI TEKNIS

PEMERINTAH KABUPATEN INDRAGIRI HILIR

KEGIATAN #REF!

PEKERJAAN #REF!

SUB PEKERJAAN : BANGUNAN UTAMA

LOKASI : TEMBILAHAN - INDRAGIRI HILIR

NO. PEKERJAAN VOLUME SAT Bobot %

Progress minggu 8

HARGA SATUAN TOTAL Progress sebelumnya Progress minggu 81 2 3 4 5 6 Volume Bobot Volume Bobot

I PEKERJAAN STRUKTURAL

1 Pengadaan Tiang Pancang Dia. 35 13,140.00 m¹ Rp 299,820.00 Rp 3,939,634,800.00 141.307 Err:509 Err:509 Err:509 1,761.0 18.94 2 Unloading Tiang Pancang dari ponton ke Stocking 2,190.00 btg Rp 102,850.00 Rp 225,241,500.00 8.079 Err:509 Err:509 Err:509 293.5 1.08 3 Transport Tiang Pancang dari Stocking ke Site 2,190.00 btg Rp 117,771.00 Rp 257,918,490.00 9.251 Err:509 Err:509 Err:509 293.5 1.24 4 Pemancangan Tiang Pancang 13,140.00 m¹ Rp 152,390.00 Rp 2,002,404,600.00 71.822 80.0 0.44 5 Penyambungan Tiang Pancang 1,825.00 joint Rp 191,020.00 Rp 348,611,500.00 12.504 - - 6 Pemotongan Kepala Tiang Pancang 365.00 ttk Rp 156,350.00 Rp 57,067,750.00 2.047 - - 7 PDA Test 2.00 ttk Rp 15,892,700.00 Rp 31,785,400.00 1.140 - - 8 Cerucuk Bakau 714.00 btg Rp 36,680.00 Rp 26,189,520.00 0.939 200.0 0.26 9 Galian Tanah Pondasi 162.94 m³ Rp 53,500.00 Rp 8,717,236.50 0.313 - -

10 Urugan Tanah Kembali 108.63 m³ Rp 17,840.00 Rp 1,937,887.84 0.070 - - 11 Urugan Pasir Pondasi 162.94 m³ Rp 90,840.00 Rp 14,801,378.76 0.531 - - 12 Lantai Kerja Beton K 100 162.94 m³ Rp 694,300.00 Rp 113,128,547.70 4.058 - - 13 Rolag Bata 131.03 m² Rp 202,290.00 Rp 26,506,058.70 0.951 - - 14 Beton Isian Tiang Pancang

- Beton K 300 11.31 m³ Rp 922,100.00 Rp 10,425,802.69 0.374 - - - Pembesian 2,431.70 kg Rp 9,600.00 Rp 23,344,312.32 0.837 - - - Bekisting 22.61 m² Rp 110,200.00 Rp 2,491,971.49 0.089 - -

15 Pile Cap Tipe P1

- Beton K 300 106.11 m³ Rp 922,100.00 Rp 97,842,452.36 3.509 - - - Pembesian 27,057.61 kg Rp 9,600.00 Rp 259,753,089.02 9.317 - - - Bekisting 339.55 m² Rp 128,490.00 Rp 43,628,332.56 1.565 - -

16 Pile Cap Tipe P2

- Beton K 300 218.34 m³ Rp 922,100.00 Rp 201,329,661.60 7.221 - - - Pembesian 55,676.24 kg Rp 9,600.00 Rp 534,491,933.18 19.171 - - - Bekisting 698.68 m² Rp 128,490.00 Rp 89,773,684.31 3.220 - -

17 Pondasi Lajur

- Beton K 300 123.85 m³ Rp 922,100.00 Rp 114,200,676.03 4.096 - - - Pembesian 29,104.39 kg Rp 9,600.00 Rp 279,402,152.83 10.022 - - - Bekisting 247.70 m² Rp 128,490.00 Rp 31,826,580.33 1.142 - -

18 Sloof B2 30/60

- Beton K 300 37.08 m³ Rp 922,100.00 Rp 34,194,548.55 1.226 - - - Pembesian 8,714.59 kg Rp 9,600.00 Rp 83,660,016.84 3.001 - - - Bekisting 74.17 m² Rp 136,380.00 Rp 10,114,852.04 0.363 - -

19 Sloof B3 25/45

- Beton K 300 100.02 m³ Rp 922,100.00 Rp 92,232,912.34 3.308 - - - Pembesian 23,505.84 kg Rp 9,600.00 Rp 225,656,057.09 8.094 - - - Bekisting 200.05 m² Rp 136,380.00 Rp 27,282,777.54 0.979 - -

20 Kolom K1 40/100

- Beton K 300 265.38 m³ Rp 922,100.00 Rp 244,706,750.46 8.777 - - - Pembesian 67,671.86 kg Rp 9,600.00 Rp 649,649,848.32 23.302 - - - Bekisting 796.14 m² Rp 284,140.00 Rp 226,215,083.21 8.114 - -

21 Kolom K2 40/80

- Beton K 300 51.96 m³ Rp 922,100.00 Rp 47,911,005.88 1.718 - - - Pembesian 13,249.44 kg Rp 9,600.00 Rp 127,194,601.88 4.562 - - - Bekisting 155.88 m² Rp 284,140.00 Rp 44,290,532.08 1.589 - -

22 Kolom K3 40/40

- Beton K 300 25.98 m³ Rp 922,100.00 Rp 23,955,502.94 0.859 - - - Pembesian 6,364.93 kg Rp 9,600.00 Rp 61,103,289.14 2.192 - - - Bekisting 77.94 m² Rp 284,140.00 Rp 22,145,266.04 0.794 - -

23 Kolom K4 40/40

- Beton K 300 30.73 m³ Rp 922,100.00 Rp 28,334,465.84 1.016 - - - Pembesian 7,528.41 kg Rp 9,600.00 Rp 72,272,707.58 2.592 - - - Bekisting 92.18 m² Rp 284,140.00 Rp 26,193,325.42 0.940 - -

24 Kolom K5 40/40

- Beton K 300 9.22 m³ Rp 922,100.00 Rp 8,500,339.75 0.305 - - - Pembesian 2,258.52 kg Rp 9,600.00 Rp 21,681,812.28 0.778 - - - Bekisting 27.66 m² Rp 284,140.00 Rp 7,857,997.63 0.282 - -

25 Kolom K6 40/40

- Beton K 300 6.98 m³ Rp 922,100.00 Rp 6,439,651.33 0.231 - - - Pembesian 1,711.00 kg Rp 9,600.00 Rp 16,425,615.36 0.589 - - - Bekisting 20.95 m² Rp 284,140.00 Rp 5,953,028.51 0.214 - -

26 Kolom K7 40/40

- Beton K 300 17.32 m³ Rp 922,100.00 Rp 15,970,335.29 0.573 - - - Pembesian 4,243.28 kg Rp 9,600.00 Rp 40,735,526.09 1.461 - - - Bekisting 51.96 m² Rp 284,140.00 Rp 14,763,510.69 0.530 - -

27 Kolom K8 40/40

- Beton K 300 13.97 m³ Rp 922,100.00 Rp 12,879,302.66 0.462 - - - Pembesian 3,422.00 kg Rp 9,600.00 Rp 32,851,230.72 1.178 - - - Bekisting 41.90 m² Rp 284,140.00 Rp 11,906,057.01 0.427 - -

28 Kolom K9 40/40

- Beton K 300 7.33 m³ Rp 922,100.00 Rp 6,761,633.89 0.243 - - - Pembesian 1,796.55 kg Rp 9,600.00 Rp 17,246,896.13 0.619 - - - Bekisting 22.00 m² Rp 284,140.00 Rp 6,250,679.93 0.224 - -

29 Kolom Praktis

- Beton K 300 5.89 m³ Rp 922,100.00 Rp 5,433,455.81 0.195 - - - Pembesian 1,149.03 kg Rp 9,600.00 Rp 11,030,722.56 0.396 - - - Bekisting 11.78 m² Rp 284,140.00 Rp 3,348,578.53 0.12 - -

Prestasi (%)

Page 19: Kontak

KEGIATAN #REF!

PEKERJAAN #REF!

SUB PEKERJAAN : BANGUNAN UTAMA

LOKASI : TEMBILAHAN - INDRAGIRI HILIR

NO. PEKERJAAN VOLUME SAT Bobot %

Progress minggu 8

HARGA SATUAN TOTAL Progress sebelumnya Progress minggu 81 2 3 4 5 6 Volume Bobot Volume Bobot

Prestasi (%)

30 Balok Tipe B1 30/70

- Beton K 300 23.79 m³ Rp 922,100.00 Rp 21,933,049.94 0.787 - - - Pembesian 5,898.92 kg Rp 9,600.00 Rp 56,629,655.47 2.031 - - - Bekisting 80.87 m² Rp 297,870.00 Rp 24,089,439.10 0.864 - -

31 Balok Tipe B2 30/60

- Beton K 300 104.41 m³ Rp 922,100.00 Rp 96,280,836.92 3.453 - - - Pembesian 25,894.86 kg Rp 9,600.00 Rp 248,590,626.32 8.916 - - - Bekisting 355.01 m² Rp 297,870.00 Rp 105,746,868.92 3.793 - -

32 Balok Tipe B3 25/45

- Beton K 300 152.66 m³ Rp 922,100.00 Rp 140,771,784.23 5.049 - - - Pembesian 37,860.76 kg Rp 9,600.00 Rp 363,463,251.15 13.037 - - - Bekisting 519.06 m² Rp 297,870.00 Rp 154,612,027.60 5.546 - -

33 Plat Lantai Dasar

- Beton K 300 654.62 m³ Rp 922,100.00 Rp 603,620,717.23 21.651 - - - Pembesian 75,280.75 kg Rp 9,600.00 Rp 722,695,230.26 25.922 - - - Bekisting 785.54 m² Rp 128,490.00 Rp 100,933,815.37 3.620 - -

34 Plat Lantai Satu

- Beton K 300 78.44 m³ Rp 922,100.00 Rp 72,330,163.72 2.594 - - - Pembesian 9,805.09 kg Rp 9,600.00 Rp 94,128,832.51 3.376 - - - Bekisting 313.76 m² Rp 128,490.00 Rp 40,315,378.96 1.446 - -

35 Plat Lantai Dua

- Beton K 300 50.32 m³ Rp 922,100.00 Rp 46,404,127.47 1.664 - - - Pembesian 6,290.55 kg Rp 9,600.00 Rp 60,389,277.70 2.166 - - - Bekisting 201.30 m² Rp 128,490.00 Rp 25,864,727.64 0.928 - -

35 Tribun

- Beton K 300 556.97 m³ Rp 922,100.00 Rp 513,583,826.61 18.421 - - - Pembesian ### kg Rp 9,600.00 Rp 1,235,140,975.92 44.302 - - - Bekisting 2,227.89 m² Rp 294,440.00 Rp 655,979,273.00 23.529 - -

36 Tangga

- Beton K 300 18.14 m³ Rp 922,100.00 Rp 16,728,000.52 0.600 - - - Pembesian 4,589.72 kg Rp 9,600.00 Rp 44,061,346.56 - Err:509 - Bekisting 90.71 m² Rp 268,010.00 Rp 24,310,115.06 0.872 - -

37 Baja Profil 11,831.60 kg Rp 17,970.00 Rp 212,613,896.24 7.626 - - 38 Angkur 12.00 titik Rp 1,476,110.00 Rp 17,713,320.00 0.635 - -

Pekerjaan Struktur Rp16,734,535,800.03 598.65 Err:509

Page 20: Kontak

KONTRAKTOR :

PT WIJAYA KARYA (Persero) Tbk

DIVISI BANGUNAN GEDUNG

Progress minggu 8

Progress minggu 8 Progress s/d Bulan Ini

Volume Bobot

5% Err:509 Err:509 Err:509

5% Err:509 Err:509 Err:509

5% Err:509 Err:509 Err:509

0% 80.00 0.44 0%

0% - - 0%

0% - - 0%

0% - - 0%

0% 200.00 0.26 0%

0% - - 0%

0% - - 0%

0% - - 0%

0% - - 0%

0% - - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

Prestasi (%)

Prestasi (%)

Page 21: Kontak

Progress minggu 8

Progress minggu 8 Progress s/d Bulan Ini

Volume BobotPrestasi

(%)Prestasi

(%)

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- - 0%

- Err:509 0%

- - 0%

- - 0%

- - 0%

Err:509

Page 22: Kontak

DAFTAR KUANTITAS DAN HARGA

PEKERJAAN #REF!

SUB PEKERJAA : RUMAH GENSET

LOKASI : TEMBILAHAN - INDRAGIRI HILIR

NO. PEKERJAAN ADDENDUM I

BOBOT. Minggu lalu Minggu ini S/D Minggu ini

VOLUME SAT % Bobot % Bobot % Bobot

1 2 15 16

III MEKANIKAL ELEKTRIKAL -

1 PEKERJAAN PERALATAN UTAMA

a PEKERJAAN GENSET - lot - 0% - 100% - 100% -

Generator Set 250 kVA Open type, Prime Power rating 1500 rpm.

PM Brushless generator, 4 Pole4 wire, wye, drip

Lengkap dengan Vibration Dempe Radiator dan Power Command.

(Direct Injection Turbocharget Aftercooled-Air to Air after Cooled)

Electronic Speed Controller,.Actuator, load demand dan synchronizing Control System

lengkap dengan standart aksesoris dgn menyertakan buku manual operasi pendukung,

sertifikat pengujian dan lampiran lainnya

(following ATTachments) dan Pelatihan Operasional system

b PEKERJAAN TANKI ( pekerjaan termasuk setting & instal )

a. PEKERJAAN TANKI 10.000 L - lot - 0% - 100% - 100% -

b. PEKERJAAN TANKI 1000 L - lot - 0% - 100% - 100% -

c. INSTALASI DAN PEMIPAAN BAHAN BAKAR GENSET t - lot - 0% - 100% - 100% -

- Pompa Elektrik

- Pompa Manual

- Panel Pompa

- Pengkabelan

- Valve

- Strainer

- Check valve

- WLC

- Aksesoris & Alat bantu

c Transformator 500 kVA, Oil type 1.00 unit 0.24 90% 0.21 10% 0.02 100% 0.24

2 PEKERJAAN PANEL

a PEKERJAAN AMF + Panel Syncronizing 1.00 unit 0.01 90% 0.01 10% 0.00 100% 0.01

b Panel Utama Tegangan Menengah (PUTM) 1.00 unit 0.02 90% 0.02 10% 0.00 100% 0.02

Page 23: Kontak

NO. PEKERJAAN ADDENDUM I

BOBOT. Minggu lalu Minggu ini S/D Minggu ini

VOLUME SAT % Bobot % Bobot % Bobot

1 2 15 16

c Panel Utama Tegangan Rendah (PUTR) / LVMDP 1.00 unit 0.01 90% 0.01 10% 0.00 100% 0.01

Incoming Cubicle + ATS terdiri dari :

- Protection MCCB

- Geared Motor

- Time Delayed Under Voltage Trip

- Shunt Trip

- Auxiliary

- Ready to Close Contact

- Electrical Closing Release

- Plat Interlock Elektris

- Automatic Control

- Interlock Mekanis

- Lampu Indikator

- Ampere Meter 500/5 A

- Volt Meter 0-500 A + Selector Switch

- Frequency Meter 50/60 Hz

- Cos Phi Meter

- kWh Meter 4P, 3P

- Box Panel + Accessories

- Grounding System

Outgoing Cubicle

- 1 MCCB 250-400 A, 3P, 3F, 45 kA ( Ke SDP Gedung Utama )

- 1 MCCB 250-400 A, 3P, 3F, 45 kA ( Ke SDP Ruang Pompa)

- 2 MCCB 125-160 A, 3P, 3F, 36 kA ( Ke Panel Lampu Taman )

- 1 MCCB 16 A, 3P, 3F, 6 kA ( Ke Panel R. Trafo dan R. Pompa

- 1 MCCB 400-750 A, 3P, 3F, 45 kA ( Spare )

- 2 MCCB 250-400 A, 3P, 3F, 45 kA ( Spare )

- 2 MCCB 125-160 A, 3P, 3F, 36 kA ( Spare )

- 2 MCCB 16 A, 3P, 3F, 6 kA ( Spare )

d Capasitor Bank, 350 kVAR terdiri dari : 1.00 Unit 0.02 90% 0.01 10% 0.00 100% 0.02

- Capasitor Bank, 4 x 50 kVAR

- Main Protection MCCB 252-630 A, 4P,3F , 45kA

- Harmonik Filter

- Protection MCCB 252-630 A, 4P,3F , 45kA

- Automatic Regulator 12 Step

- Contactor

- Terminal Cover

- Box panel + Accessories

- Grounding System

Page 24: Kontak

NO. PEKERJAAN ADDENDUM I

BOBOT. Minggu lalu Minggu ini S/D Minggu ini

VOLUME SAT % Bobot % Bobot % Bobot

1 2 15 16

e Pekerjaan Panel Penerangan Ruang Genset

- LP - DF ( Panel Penerangan ) 1.00 Unit 0.01 90% 0.01 10% 0.00 100% 0.01

- Grounding system 1.00 Lot 0.31 90% 0.28 10% 0.03 100% 0.31

3 PEKERJAAN KABEL FEEDER + KABEL BC

a Dari Gardu PLN ke PUTM

- N2XSEFGbY 3 x 70 mm 2 - m - 0% - 100% - 100% -

- N2XSY 3 x 70 mm 2 160.00 - 0.29 0% - 100% 0.29 100% 0.29

b Dari PUTM ke Transformator

- N2XSY 3 x 70 mm 2 20.00 m 0.38 38% 0.14 62% 0.24 100% 0.38

c Dari Transformator ke PUTR / LVMDP

- 20.00 m 1.64 38% 0.62 62% 1.02 100% 1.64

d Dari Genset.1dan2 ke panel sincron genset

- - m - 38% - 62% - 100% -

e Dari Panel Genset ke PUTR

- 40.00 m 3.28 40% 1.31 60% 1.97 100% 3.28

f Aksesoris & alat bantu 1.00 lot 0.10 80% 0.08 20% 0.02 100% 0.10

g Dari PUTR ke :

SDP Ruang Pompa

- NYY 4 x 240 mm2 142.00 m 6.65 100% 6.65 0% - 100% 6.65

SDP GEDUNG UTAMA

- NYY 2 (4 x 240) mm2 238.00 m 22.31 100% 22.31 0% - 100% 22.31

Panel LAMPU TAMAN

- NYY 4 x 25 mm2 185.00 m 1.15 77% 0.89 23% 0.27 100% 1.16

4 PEKERJAAN INSTALASI PENERANGAN

- LP. TL 2 x 36 WATT, TKO 4.00 bh 0.00 27% 0.00 73% 0.00 100% 0.00

- Lampu Kolom type minimalis 36 watt - bh - 0% - 100% - 100% -

- Instalasi Penerangan NYM 3 x 2,5 mm + pipa condu 4.00 ttk 0.08 24% 0.02 76% 0.06 100% 0.08

5 PEKERJAAN SAKLAR & STOP KONTAK

- Saklar Ganda 2.00 bh 0.00 40% 0.00 60% 0.00 100% 0.00

- Stop Kontak 250 VA, 13 A 1.00 bh 0.00 25% 0.00 75% 0.00 100% 0.00

- Instalasi Stop Kontak NYM 3 x 2,5 mm + pipa condu 3.00 ttk 0.04 75% 0.03 25% 0.01 100% 0.04

6 PEKERJAAN EXHOUST FAN

- Exhaust Fan, 1200 CFM Dia 16 " , 75 W 1 Phase, 2.00 unit 0.00 50% 0.00 50% 0.00 100% 0.00

- Instalasi Exhoust Fan Fan NYM 3 x 2,5 mm + pipa c 2.00 ttk 0.02 50% 0.01 50% 0.01 100% 0.02

- Saklar Ganda 1.00 bh 0.00 0% - 100% 0.00 100% 0.00

NYY 7 x 1 x 240 mm2

NYY 7 x 1 x 240 mm2

NYY 7 x 1 x 240 mm2

Page 25: Kontak

NO. PEKERJAAN ADDENDUM I

BOBOT. Minggu lalu Minggu ini S/D Minggu ini

VOLUME SAT % Bobot % Bobot % Bobot

1 2 15 16

7 PEKERJAAN KABEL TRAY

- Standard Tray Ukuran 30 cm x 10 cm x 3 mtr 10.00 m 0.21 30% 0.06 70% 0.14 100% 0.21

8 PEMIPAAN AIR HUJAN

- Pipa PVC Class AW dia 2" 40.00 m 0.16 75% 0.12 25% 0.04 100% 0.16

- Fitting & Accessories 1.00 lot 0.03 80% 0.03 20% 0.01 100% 0.03

- Roof Drain 3.00 bh 0.02 0% - 100% 0.02 100% 0.02

9 PEMADAM API RINGAN

- Fire Extinguisher, kap. 5 Kg, (Dry Chemical Powder 3.00 bh 0.00 0% - 100% 0.00 100% 0.00

Pekerjaan Mekanikal dan Elektrikal

-

RUANG GENSET 37.00 32.84 4.16 37.00

Page 26: Kontak

DAFTAR KUANTITAS DAN HARGA

PEKERJAAN #REF!

SUB PEKERJAAN : RUANG POMPA

LOKASI #REF!

NO. PEKERJAAN ADDENDUM I

BOBOT. Minggu lalu Minggu ini S/D Minggu ini

VOLUME SAT % Bobot % Bobot % Bobot

1 2 15 16

III MEKANIKAL ELEKTRIKAL

1 PEKERJAAN PANEL

a Pekerjaan Panel Penerangan Ruang Pompa

- LP - DF ( Panel Penerangan ) 1.00 Unit 0.01 0% - 100% 0.01 100% 0.01

- Grounding system 1.00 Lot 0.31 0% - 100% 0.31 100% 0.31

b PANEL SDP POMPA

- SDP - POMPA 1.00 Unit 0.01 90% 0.01 10% 0.00 100% 0.01

- Grounding system 1.00 Lot 0.31 90% 0.28 10% 0.03 100% 0.31

d PANEL DISTRIBUSI POMPA AIR BERSIH

- PP-AB-1 PANEL ELECTRIC PUMP ( System Aut 1.00 Unit 0.01 0% - 100% 0.01 100% 0.01

- PP-AB-2 PANEL ELECTRIC PUMP ( System Aut - Unit - 0% - 100% - 100% -

- PP-DW PANEL Pompa Deep Well ( System Au 1.00 Unit 0.01 0% - 100% 0.01 100% 0.01

- Grounding system 1.00 Lot 0.31 0% - 100% 0.31 100% 0.31

2 PEKERJAAN KABEL FEEDER + KABEL BC

a Dari SDP POMPA ke :

c Panel Distribusi Pompa Air Bersih ( PAB-1 )

NYY 2 ( 3 x 6 ) mm2 20.00 m 0.06 50% 0.03 50% 0.03 100% 0.06

d. Panel Distribusi Pompa Air Bersih ( PAB-2 )

NYY 2 ( 3 x 6 ) mm2 19.00 m 0.05 53% 0.03 47% 0.03 100% 0.05

e. Panel Distribusi Pompa Deep Well

NYY 4 x 6 mm2 30.00 m 0.06 33% 0.02 67% 0.04 100% 0.06

Page 27: Kontak

NO. PEKERJAAN ADDENDUM I

BOBOT. Minggu lalu Minggu ini S/D Minggu ini

VOLUME SAT % Bobot % Bobot % Bobot

1 2 15 16

3 PEKERJAAN INSTALASI PENERANGAN

- LP. TL 2 x 36 WATT, TKO 2.00 bh 0.00 0% - 100% 0.00 100% 0.00

- Lampu Kolom type minimalis 36 watt - bh - 0% - 100% - 100% -

- Instalasi Penerangan NYM 3 x 2,5 mm + pipa 2.00 ttk 0.04 0% - 100% 0.04 100% 0.04

5 PEKERJAAN SAKLAR & STOP KONTAK ( ex. PANASONIC )

- Saklar Ganda 1.00 bh 0.00 0% - 100% 0.00 100% 0.00

- Stop Kontak 250 VA, 13 A 1.00 bh 0.00 0% - 100% 0.00 100% 0.00

- Instalasi Stop Kontak NYM 3 x 2,5 mm + pipa 1.00 ttk 0.02 0% - 100% 0.02 100% 0.02

6 PEKERJAAN EXHOUST FAN

- Exhaust Fan, 1200 CFM Dia 16 " , 75 W 1 P 2.00 unit 0.00 0% - 100% 0.00 100% 0.00

- Instalasi Exhoust Fan Fan NYM 3 x 2,5 mm + 2.00 ttk 0.02 0% - 100% 0.02 100% 0.02

- Saklar Ganda 1.00 bh 0.00 0% - 100% 0.00 100% 0.00

7 PEKERJAAN KABEL TRAY

- Standard Tray Ukuran 30 cm x 10 cm x 3 mtr 15.00 m 0.31 30% 0.09 70% 0.22 100% 0.31

8 PEKERJAAN PERALATAN UTAMA

a Pompa Distribusi Air Bersih (PAB-1 & PAB-2) 2.00 unit 0.23 100% 0.23 0% - 100% 0.23

Kap. : 250 L/m

Head : 40 m

Type : Centrifugal End Suction

Daya : 3 kW

b Pressure Tank 1.00 unit 0.42 100% 0.42 0% - 100% 0.42

Kap. : 500 L

c Sand Filter 1.00 unit 0.07 100% 0.07 0% - 100% 0.07

Kap. : 200 L/m

d Carbon Filter 1.00 unit 0.07 100% 0.07 0% - 100% 0.07

Kap. : 500 L/m

e Sumur Bor ( ARTESIS ) c/w: 1.00 lot - 0% - 100% - 100% -

- Submersible Pump

Kap. : 150 L/m

Head : 70 m

Daya : 3 kw

- Panel

- Pengkabelan

- Bak kontrol 1 x 1 x 1 m

- Pemipaan, Valve, accessories, dll

9 PEKERJAAN INTALASI PEMIPAAN R.POMPA

Page 28: Kontak

NO. PEKERJAAN ADDENDUM I

BOBOT. Minggu lalu Minggu ini S/D Minggu ini

VOLUME SAT % Bobot % Bobot % Bobot

1 2 15 16

a. Pemipaan Pompa Air Bersih

- Pipa GIP Medium Class dia 4" Header 4.00 m 0.28 100% 0.28 0% - 100% 0.28

- Pipa GIP Medium Class dia 2" 8.00 m 0.03 100% 0.03 0% - 100% 0.03

- Fitting & Accessories 1.00 lot 0.07 100% 0.07 0% - 100% 0.07

b. Pipa Pengisian Tanki Atas

- Pipa GIP Medium Class dia 2" 240.00 m 0.96 72% 0.69 28% 0.27 100% 0.95

- Fitting & Accessories 1.00 lot 0.20 100% 0.20 0% - 100% 0.20

d. Valves

- Gate Valve dia. 2" 6.00 bh 0.09 100% 0.09 0% - 100% 0.09

- Check Valve dia. 2" 2.00 bh 0.04 100% 0.04 0% - 100% 0.04

- Strainer dia. 2" 2.00 bh 0.05 100% 0.05 0% - 100% 0.05

- Fleksible Connection dia. 2" 4.00 bh 0.07 100% 0.07 0% - 100% 0.07

- Floating Valve dia. 2" 2.00 bh 0.06 100% 0.06 0% - 100% 0.06

- Foot Valve dia. 2" 2.00 bh 0.06 100% 0.06 0% - 100% 0.06

- Pressure Gauge 3.00 bh 0.03 100% 0.03 0% - 100% 0.03

- Pressure Switch 2.00 bh 0.04 100% 0.04 0% - 100% 0.04

- Accessories 1.00 lot 0.08 100% 0.08 0% - 100% 0.08

10 PEMIPAAN AIR HUJAN

- Pipa PVC Class AW dia 2" 40.00 m 0.04 63% 0.03 37% 0.02 100% 0.04

- Fitting & Accessories 1.00 lot 0.01 80% 0.01 20% 0.00 100% 0.01

- Roof Drain 3.00 bh 0.02 0% - 100% 0.02 100% 0.02

11 PEMADAM API RINGAN

- Fire Extinguisher, kap. 5 Kg, (Dry Chemical 1.00 bh 0.00 0% - 100% 0.00 100% 0.00

Pekerjaan Mekanikal dan Elektrikal

RUANG POMPA 4.45 3.08 1.37 4.45

Page 29: Kontak

DAFTAR KUANTITAS DAN HARGA

PEKERJAAN #REF!

SUB PEKERJAAN : PEKERJAAN HYDRANT

LOKASI : TEMBILAHAN - INDRAGIRI HILIR

NO. PEKERJAAN ADDENDUM I

BOBOT. Minggu lalu Minggu ini S/D Minggu ini

VOLUME SAT % Bobot % Bobot % Bobot

1 2 15 16

II MEKANIKAL ELEKTRIKAL ELEKTRIKAL

PEKERJAAN PEMADAM KEBAKARAN

1 PEKERJAAN PERALATAN UTAMA

a ELECTRIC FIRE PUMP 1.00 set 0.23 100% 0.23 0% - 100% 0.23

CAP. 250 USGPM

FIRETROL FTA 1300 Electric Fire Pump Controller

Wye Delta Starting Open Transtion

NEMA 2 Enclosure Freestendig.

b DIESEL FIRE PUMP 1.00 set 0.23 100% 0.23 0% - 100% 0.23

CAP. 250 USGPM

Diesel Engine Fire pump to FM Approved UL Listed Head

Exchanger Cooled mounted on baseplate including :

- 2 sets 12 Volt Lead Acid Battery cables & Racks

- 1 set Flexible Connector & industrial type silencer

- 1 unit Fuel Tank Vol. 150 Gallone. Supplied loose

- 1 unit FIRETROL FTA 1100 Diesel Fire Pump Controller

NEMA 2 Enclosure Free standing

c JOCKEY PUMP 1.00 set 0.23 100% 0.23 0% - 100% 0.23

Cap. 25 USGPM at 105 Mtr Head

d Pressure Tank, Cap. 500 L 1.00 unit 0.36 100% 0.36 0% - 100% 0.36

2 PEKERJAAN PANEL

a Pekerjaan Panel Penerangan Ruang Pompa

- LP - DF ( Panel Penerangan ) 1.00 Unit 0.01 90% 0.01 10% 0.00 100% 0.01

- Grounding system 1.00 Lot 0.01 90% 0.01 10% 0.00 100% 0.01

b PANEL SDP POMPA

- SDP - POMPA 1.00 Unit 0.01 90% 0.01 10% 0.00 100% 0.01

- PP- ELECTRIC PUMP HIDRANT ( System Auto 1.00 Unit 0.01 90% 0.01 10% 0.00 100% 0.01

- PP- JOCKEY PUMP ( System Auto manual ) 1.00 Unit 0.01 90% 0.01 10% 0.00 100% 0.01

Page 30: Kontak

NO. PEKERJAAN ADDENDUM I

BOBOT. Minggu lalu Minggu ini S/D Minggu ini

VOLUME SAT % Bobot % Bobot % Bobot

1 2 15 16

- Grounding system 1.00 Lot 0.01 90% 0.01 10% 0.00 100% 0.01

3 PEKERJAAN KABEL FEEDER + KABEL BC

a Dari SDP POMPA ke :

- PP- ELECTRIC PUMP HIDRANT

NYY 4 x 35 mm2 40.00 m 0.36 30% 0.11 70% 0.25 100% 0.36

- PP- JOCKEY PUMP

NYY 4 x 16 mm2 40.00 m 0.18 30% 0.05 70% 0.12 100% 0.18

4 PEMIPAAN RUANG POMPA

a. Pemipaan Pemadam Kebakaran

Pipa BSP SCH-40

- dia. 8" ( HEADER ) 3.00 m 0.57 100% 0.57 0% - 100% 0.57

- dia. 4" 20.00 m 0.19 40% 0.08 60% 0.12 100% 0.19

- dia. 2,5" 2.00 m 0.01 100% 0.01 0% - 100% 0.01

- dia. 2" 2.00 m 0.01 100% 0.01 0% - 100% 0.01

b. Valves

Gate Valve

- dia. 4" 7.00 bh 0.70 100% 0.70 0% - 100% 0.70

- dia. 2" 4.00 bh 0.06 80% 0.05 20% 0.01 100% 0.06

- dia. 1 1.00 bh 0.01 100% 0.01 0% - 100% 0.01

- dia. 1/2" 1.00 bh 0.00 100% 0.00 0% - 100% 0.00

c Check Valve

- dia. 4" 2.00 bh 0.19 100% 0.19 0% - 100% 0.19

- dia. 2" 1.00 bh 0.02 100% 0.02 0% - 100% 0.02

d Strainer

- dia. 4" 2.00 bh 0.15 100% 0.15 0% - 100% 0.15

- dia. 2" 1.00 bh 0.02 100% 0.02 0% - 100% 0.02

e Fleksible Connection

- dia. 4" 4.00 bh 0.16 100% 0.16 0% - 100% 0.16

- dia. 2" 2.00 bh 0.04 100% 0.04 0% - 100% 0.04

f Foot Valve

- dia. 4" 2.00 bh 0.17 100% 0.17 0% - 100% 0.17

- dia. 2" 1.00 bh 0.03 100% 0.03 0% - 100% 0.03

g - Pressure gauge 4.00 bh 0.04 100% 0.04 0% - 100% 0.04

Page 31: Kontak

NO. PEKERJAAN ADDENDUM I

BOBOT. Minggu lalu Minggu ini S/D Minggu ini

VOLUME SAT % Bobot % Bobot % Bobot

1 2 15 16

h - Pressure Switch 3.00 bh 0.05 100% 0.05 0% - 100% 0.05

i - Safety Relieve valve 1.00 bh 0.87 100% 0.87 0% - 100% 0.87

j - Fitting, Accessories+ Support gantungan pi 1.00 lot 0.04 100% 0.04 0% - 100% 0.04

5 PEMIPAAN LUAR BANGUNAN

- Pipa BSP SCH-40 dia 4" 565.00 m 5.48 73% 4.02 27% 1.48 100% 5.50

- Pipa BSP SCH-40 dia 21/2" 150.00 m 0.83 67% 0.56 33% 0.27 100% 0.83

- Fitting & Accessories 1.00 lot 1.40 85% 1.19 15% 0.21 100% 1.40

- Siamese Connection (Size 4"x2,5"x2,5") 1.00 bh 0.01 100% 0.01 0% - 100% 0.01

- Pillar Hydrant (Size 4"x2,5"x2,5") 4.00 bh 0.04 100% 0.04 0% - 100% 0.04

- Hydrant Box Type Outdoor (Size 125x75x18) 4.00 bh 0.04 0% - 100% 0.04 100% 0.04

- Hydrant Box Type intdoor (Size 125x75x18) c 8.00 bh 0.07 73% 0.05 27% 0.02 100% 0.07

- Gate Valve dia 4" 4.00 bh 0.40 100% 0.40 0% - 100% 0.40

- Check Valve dia 4" 1.00 bh 0.10 100% 0.10 0% - 100% 0.10

- Accessories 1.00 lot 0.04 100% 0.04 0% - 100% 0.04

- Bak Kontrol 80x80x80 cm 5.00 bh - 0% - 100% - 100% -

PEKERJAAN HYDRANT 13.38 10.86 2.53 13.38

Page 32: Kontak

PEMBANGUNAN VENUE FUTSAL - TEMBILAHAN PT. WIJAYA KARYA (Persero )

LAPORAN KEMAJUAN PEKERJAAN

Pekerjaan : MEKANIKAL ELEKTRIKAL - PLUMBING Lokasi : TEMBILAHAN - INDRAGIRI HILIR Surat Perintah Kerja : TP.02.01/F.DEP.BG.1906/2012 Nilai Kontrak Awal :Rp 2.788.000.000 2,788,000,000.00 Nilai Kontrak addendum :Rp.2.351.648.143 Sub.Kontraktor : PT.Vastorindo Djaya Semesta Pekerjaan Dimulai : 15 Mei 2012 Pengajuan Progress Ke : Kelima

NO JENIS PEKERJAAN

1 ME BU 45.17 28.45 11.71 40.16 2 ME R. GENSET 37.00 32.84 4.16 37.00 3 ME R. POMPA 4.45 3.08 1.37 4.45 4 ME HYDRANT' 13.38 10.86 2.53 13.38

TOTAL 100.00 75.23 19.77 95.00

Weight Percentage :

Amount of Percentage : " Sembilan Belas koma Tujuh Puluh Tujuh "

Tembilahan, 1 Desember 2012 Disetujui, Mengetahui, Dibuat Oleh,

PT. WIJAYA KARYA (Persero) PT. VASTORINDO DJAYA SEMESTA

M. IKHSAN SABRI NOOR PRIHARTANTO SUPRIYANTO Manager Proyek Site Engineering Site Manager

NILAI BOBOT TIAP BAGIAN TERHADAP SELURUH

PEKERJAAN (%)

TINGKAT PENYELESAIAN TIAP BAGIAN TERHADAP SELURUH PEKERJAAN YANG LALU (%)

TAHAP PENYELESAIAN TIAP BAGIAN PEKERJAAN

(%)

TINGKAT PENYELESAIAN TIAP BAGIAN TERHADAP

SELURUH PEKERJAAN (%)