Pekerjaan : Pembangunan Gedung Sentra Pengembangan Potensi Pemuda Lokasi : Kalukubula Kecamatan Sigi Biromaru Kabupaten Sigi Tahun : 2012 NO JENIS UPAH / BAHAN HARGA SATUAN ( Rp ) 1 2 3 I. UPAH K E R J A : 1 Tukang 40,000.00 2 Kepala Tukang 50,000.00 3 Pekerja 35,000.00 4 Mandor 45,000.00 II. B A H A N : 1 Batu Kali 85,000.00 2 Kerikil pecah 2-3 Cm 100,000.00 3 Pasir Pasang 65,000.00 4 Pasir Urug 65,000.00 5 Tanah Urug 55,000.00 6 Pasir Beton 65,000.00 7 Batu Bata 700 8 Batako 2,500.00 9 Paving Block 1,200.00 10 Kapur/milk 8,500.00 11 Semen Portland 58,000.00 12 Semen Warna 10,000.00 13 Kayu Kelas II 1,700,000.00 14 Kayu Kelas III 1,250,000.00 15 Tripleks 3 mm 29,500.00 16 Tripleks 6mm 65,000.00 17 Eternit asbes 9,500.00 18 Wood paper + pasang dan perlengkapan 25,000.00 19 lem wood paper 40,000.00 18 Teakwood 4 mm 65,000.00 19 Papan Fiber Semen 18 mm 140,000.00 20 Papan Fiber Semen 4 mm 35,000.00 21 Papan Gipsum 6 mm 47,500.00 22 Papan Gipsum 9 mm 67,500.00 23 Plester gipsum 6,500.00 24 Les Plafond Profil gipsum + pasang 17,500.00 25 Les Plafond Profil 4,500.00 26 Kac Bening 5 mm 75,000.00 27 Kaca Bening 3 mm 40,000.00 28 Kaca Rayband 5 mm 85,000.00

Upload: tamsis-sis

Post on 22-Dec-2015

21 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Gedung Pemuda.xls

Pekerjaan : Pembangunan Gedung Sentra Pengembangan Potensi Pemuda Lokasi : Kalukubula Kecamatan Sigi Biromaru Kabupaten Sigi Tahun : 2012

NO JENIS UPAH / BAHANHARGA SATUAN

SATUAN( Rp )

1 2 3 4I. UPAH K E R J A :

1 Tukang 40,000.00 Org/Hari2 Kepala Tukang 50,000.00 Org/Hari3 Pekerja 35,000.00 Org/Hari4 Mandor 45,000.00 Org/Hari

II. B A H A N :1 Batu Kali 85,000.00 m32 Kerikil pecah 2-3 Cm 100,000.00 m33 Pasir Pasang 65,000.00 m34 Pasir Urug 65,000.00 m35 Tanah Urug 55,000.00 m36 Pasir Beton 65,000.00 m37 Batu Bata 700 Bh8 Batako 2,500.00 Bh9 Paving Block 1,200.00 Bh

10 Kapur/milk 8,500.00 Kg11 Semen Portland 58,000.00 Zak12 Semen Warna 10,000.00 Kg13 Kayu Kelas II 1,700,000.00 m314 Kayu Kelas III 1,250,000.00 m315 Tripleks 3 mm 29,500.00 Lbr.16 Tripleks 6mm 65,000.00 Lbr.17 Eternit asbes 9,500.00 m218 Wood paper + pasang dan perlengkapan 25,000.00 m219 lem wood paper 40,000.00 btl18 Teakwood 4 mm 65,000.00 Lbr.19 Papan Fiber Semen 18 mm 140,000.00 Lbr.20 Papan Fiber Semen 4 mm 35,000.00 Lbr.21 Papan Gipsum 6 mm 47,500.00 Lbr.22 Papan Gipsum 9 mm 67,500.00 Lbr.23 Plester gipsum 6,500.00 Rool24 Les Plafond Profil gipsum + pasang 17,500.00 m'25 Les Plafond Profil 4,500.00 m'26 Kac Bening 5 mm 75,000.00 m227 Kaca Bening 3 mm 40,000.00 m228 Kaca Rayband 5 mm 85,000.00 m2

Page 2: Gedung Pemuda.xls

NO JENIS UPAH / BAHANHARGA SATUAN

SATUAN( Rp )

1 2 3 429 Kaca Rayband 3 mm 75,500.00 m230 Kaca Blok 17,500.00 Bh31 Besi Beton 10,500.00 Kg32 Besi L. 70.70.7 panjang 6 m 7,250.00 Kg33 Besi L. 70.70.9 panjang 6 m 9,250.00 Kg34 Besi plat tebal 10 mm 1,000.00 Kg35 Aluminium rangka kusen 4" panjang 6 m' 40,000.00 Btg36 Aluminium rangka daun jendela 2" 40,000.00 Btg37 Tralis besi 100,000.00 m238 Kawat Beton 8,000.00 Kg39 Paku Tripleks 15,000.00 Kg40 Paku Biasa Ukuran 2" s/d 4" 8,500.00 Kg41 Paku Seng 21,000.00 Kg42 Paku Gypsum 17,500.00 Kg43 Paku Asbes 250.00 bh

Baut diameter 12 mm panjang 5 cm 650.00 bh44 Baut Seng 750.00 bh45 Kunci Tanam 2 Slaag Yale 250,000.00 Bh46 Engsel Pintu 50,000.00 Psg.47 Grendel Pintu 50,000.00 Bh48 Engsel Pintu angin 50,000.00 psg49 Engsel Jendela 25,000.00 Psg.50 Grendel Jendela 25,000.00 Bh51 Tarikan Jendela 25,000.00 Bh52 Hak Angin Baut Mur 25,000.00 Bh53 Titik Mata Lampu 75,000.00 ttk54 Lampu Tl 20 Watt 40,000.00 Bh55 Lampu Tl 1x 40 Watt model bambu 150,000.00 Bh56 Lampu Tl 1x 20 Watt model bambu 85,000.00 Bh57 Lampu Tl 2x 40 Watt RM 250,000.00 Bh58 Lampu Tl 2x 20 Watt 210,000.00 Bh59 Lampu Pijar 40 Watt 15,000.00 Bh60 Lampu Pijar 25 Watt 15,000.00 Bh61 Lampu SL 25 Watt Phlips 80,000.00 Bh62 Fiting lampu 25,000.00 Bh63 Down light phlips komplit 110,000.00 Bh64 Saklar Tunggal kualitas Buroco 15,000.00 Bh65 Saklar Ganda kualitas Buroco 25,000.00 Bh66 Stop Kontak kualitas buroco 20,000.00 Bh67 Sekring Box Komplit 300,000.00 Unit68 Ctop Kontak AC 75,000.00 Bh69 Kabel BC 50 mm2 30,000.00 Kg70 Kepala penangkal petir 30,000.00 Bh71 Kabel NYA 1x1,5 mm ( 50 m ) 85,000.00 Rol72 Kabel NYA 1 x 2,5 mm ( 50 m ) 125,000.00 Rol

Page 3: Gedung Pemuda.xls

NO JENIS UPAH / BAHANHARGA SATUAN

SATUAN( Rp )

1 2 3 473 Kabel NYM 2 x 2,5 mm ( 50 m ) 175,000.00 Rol74 Keramik 40 x 40 45,000.00 Dos75 Granito 40 x 40 75,000.00 Dos76 Keramik 20 x 20 32,500.00 Dos77 Buis beton 30 cm panjang 1m' 65,000.00 M'78 Kertas Pasir 6,500.00 Lbr.79 Dempul Kayu 8,500.00 Kg80 Plamur Tembok 7,500.00 Kg81 Cat Menie 15,000.00 Kg82 Cat Tembok 15,000.00 Kg83 Plamir kayu 7,500.00 Kg84 Cat Kayu 22,000.00 Kg85 Minyak Cat 8,500.00 Ltr86 Teer Residu 5,000.00 Ltr87 Cat atap Seng 10,000.00 kg88 Kran Air 17,500.00 Bh89 Wastafel Ex ina 200,000.00 Set90 Floor Drain 7,500.00 Bh91 Closet Jongkok Ex ina 90,000.00 Bh92 Urinoir Ex Ina 200,000.00 Bh93 Kloset duduk biasa 350,000.00 Bh94 Kloset duduk / monoblok 1,500,000.00 Bh95 Bak Mandi traso 130,000.00 bh96 Septik Tank & Bak Peresapan 4,500,000.00 Unit97 Triplex Lapis Aluminium Bergaris 50,000.00 Lbr.98 Roster 30 x 30 2,000.00 Bh99 Kitchen aluminium 400,000.00 Bh

100 Seng Plat Bjls 20 35,000.00 Lbr101 Seng Gelombang Sakura Roof 75,000.00 Lbr102 Genteng mira 6,000.00 bh103 Bumbungan Genteng 10,500.00 Bh104 Plastik gelombang besar 17,500.00 lbr105 Pipa Listrik/paralon 3,500.00 Btg.106 Pipa galvanis 1/2 " 100,000.00 Btg.107 Pipa galvanis 3/4 " 120,000.00 Btg.108 Pipa galvanis 1 " 135,000.00 Btg.109 Pipa galvanis 1 1/4 " 150,000.00 Btg.110 Pipa PVC 1/2" Panjang 4 m' 9,500.00 Btg.111 Pipa PVC 3/4" Panjang 4 m' 12,750.00 Btg.112 Pipa PVC 2" Panjang 4 m' 45,000.00 Btg.113 Pipa PVC 3" 72,500.00 Btg.114 Pipa PVC 4" 115,000.00 Btg.115 Pipa Talang PVC 8" 12,500.00 m'116 Handreel tangga dari Stainlees steel 200,000.00 m'117 Handreel Selasar dari Stainlees steel 100,000.00 m'

Page 4: Gedung Pemuda.xls

NO JENIS UPAH / BAHANHARGA SATUAN

SATUAN( Rp )

1 2 3 4

Page 5: Gedung Pemuda.xls

( ENGINEERS ESTIMATE )

Pekerjaan : Pembangunan Gedung Sentra Pengembangan Potensi Pemuda Lokasi : Kalukubula Kecamatan Sigi Biromaru Kabupaten Sigi

Provinsi Sulawesi TengahTahun : 2012

Harga JumlahNo. Uraian Pekerjaan Satuan Volume Satuan Harga

(Rp) (Rp)

I Pekerjaan Persiapan

1 Pembuatan direksi Keet ls 1.00 15,000,000.00 15,000,000.00

2 Pembersihan Lokasi Ls 1.00 10,000,000.00 10,000,000.00

5 Pembuatan papan nama proyek ls 1.00 250,000.00 250,000.00

6 Pengukuran / pasangan bowplank Ls 1.00 5,000,000.00 5,000,000.00

30,250,000.00

II Pekerjaan Tanah

1 Galian pondasi poer dan batu batu kali 440.00 27,375.00 12,045,000.00

2 Urugan kembali bekas galian 220.00 7,575.00 1,666,500.00

3 Timbunan tanah pilihan 680.00 76,950.00 52,326,000.00

4 Urugan pasir dibawah pondasi dan lantai 43.20 88,950.00 3,842,640.00

69,880,140.00

III Pekerjaan Beton

1 Beton 1 : 3 : 5 (lantai kerja) 31.20 619,475.00 19,327,620.00

2 Pondasi poer plat ( BB = 150 Kg ) K.225 22.65 4,169,227.50 94,433,002.88

3 kolom dimensi 40x40 Cm ( BB = 225 Kg) K.300 28.41 5,422,541.25 154,054,396.91

4 kolom 15 x 15 (BB=150 Kg ) K.175 6.73 4,199,127.50 28,260,128.08

5 Sloof 30 x 60 (BB = 200 Kg ) K.225 23.92 5,004,770.00 119,714,098.40

6 Sloof 15 x 25 (BB = 200 Kg ) K.125 9.49 5,004,770.00 47,495,267.30

7 Balok lantai 20x35 (BB = 150 kg ) K. 225 10.36 4,169,227.50 43,193,196.90

8 Balok lantai 30 x 60 ( BB = 135 kg ) K. 225 26.08 3,918,564.75 102,196,168.68

9 Ringbalk 15 x 25 ( BB = 200 Kg ) K. 225 5.34 4,169,227.50 22,263,674.85

10 Ringbalk 20 x 35 ( BB = 150 Kg ) K. 225 13.36 4,169,227.50 55,700,879.40

11 Plat lantai tebal 12 cm (BB = 150 Kg) K.225 64.20 4,169,227.50 267,664,405.50

12 Sun Screan ( BB = 150 Kg ) K. 175 5.44 4,199,127.50 22,843,253.60

13 Beton Tangga ( BB = 150 Kg ) K. 225 9.82 4,169,227.50 40,941,814.05

1,018,087,906.54

IV Pekerjaan Pasangan

1 Pasangan batu kosong 40.32 157,750.00 6,360,480.00

2 Pasangan pondasi batu kali 128.00 473,025.00 60,547,200.00

3 Batu bata 1 : 2 35.20 758,255.00 26,690,576.00

4 Batu bata 1 : 5 108.00 739,315.00 79,846,020.00

5 Plesteran dinding ,dan beton 1: 2 378.00 30,511.00 11,533,158.00

6 Plesteran batu bata 1 : 5 1,528.00 26,092.50 39,869,340.00

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m2

m2

Page 6: Gedung Pemuda.xls

Harga JumlahNo. Uraian Pekerjaan Satuan Volume Satuan Harga

(Rp) (Rp)

7 Acian dinding 1Pc : 7 Kpr 1,906.00 11,156.00 21,263,336.00

8 Acian Lantai beton dengan saus semen 124.87 7,120.00 889,074.40

9 Plesteran pondasi batu kali 129.50 61,022.00 7,902,349.00

10 Pas. lantai keramik 40 x 40 786.00 160,079.00 125,822,094.00

11 Dinding Keramik 40 x40 78.60 160,079.00 12,582,209.40

393,305,836.80

V Pekerjaan Kayu / Kap

1 Kuda-kuda Taso / Galvalum 568.00 155,000.00 88,040,000.00

2 Mur baut diameter 12 mm ls 1.00 7,500,000.00 7,500,000.00

3 Lisplank papan 134.00 89,780.00 12,030,520.00

4 Atap Sakuraroof 568.00 101,010.00 57,373,680.00

5 BumbunganAtap Metal m' 69.60 23,471.00 1,633,581.60

6 Pekerjaan rangka plafon 637.60 19,214.50 12,251,165.20

7 Pekerjaan plafon gypsum 9 mm 637.60 75,080.00 47,871,008.00

226,699,954.80

VI Pek. Kusen Pintu dan Jendela

1 Rangka Kusen m3 11.49 2,972,485.00 34,144,935.20

2 Ventilasi Jalusi Kayu 117.03 162,325.00 18,996,894.75

3 Pintu doble teakwood 44.00 448,480.00 19,733,120.00

4 Pintu Doble Teakwood lapis seng 6.60 473,180.00 3,122,988.00

5 Pintu Panil Kaca 45.10 325,400.00 14,675,540.00

6 Jendela Kaca bingkai 81.30 325,400.00 26,455,020.00

7 Kaca Mati 5 mm 50.59 136,950.00 6,928,300.50

8 Ventilasi kaca 8.97 136,950.00 1,228,441.50

125,285,239.95

VII Pekerjaan Sanitair

1 Kloset jongkok Bh 8.00 212,110.00 1,696,880.00

2 Wastafel Ex ina lengkap Bh 4.00 343,610.00 1,374,440.00

3 Urinoir Ex ina lengkap Bh 4.00 309,960.00 1,239,840.00

4 Pipa galfanis 3/4 ' m' 175.00 71,155.00 12,452,125.00

5 Pipa PVC tipe AW 2" m' 60.00 36,405.00 2,184,300.00

6 Pipa PVC tipe AW 3" m' 36.00 52,869.50 1,903,302.00

7 Floor Drain Bh 9.00 12,000.00 108,000.00

8 Kran air m' 9.00 24,320.00 218,880.00

9 Septictank + peresapan Bh 2.00 4,500,000.00 9,000,000.00

28,480,887.00

VIII Pekerjaan Mecanikal dan Elektrikal

1 Titik mata lampu ttk 47.00 75,000.00 3,525,000.00

2 Titik stop kontak bh 23.00 24,000.00 552,000.00

3 Lampu TL 2 x 40 watt bh 24.00 150,000.00 3,600,000.00

4 Lampu pijar 40 watt bh 23.00 4,500.00 103,500.00

5 Saklar ganda kualitas buroco bh 30.00 25,000.00 750,000.00

6 Saklar tunggal kualitas buroco bh 35.00 15,000.00 525,000.00

7 Panel Box komplit (2 Grop ) bh 6.00 300,000.00 1,800,000.00

8 Kabel NYM 2 x 2,5 mm ( 50 m ) Roll 10.00 175,000.00 1,750,000.00

12,605,500.00

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

C54
Fatek:
Page 7: Gedung Pemuda.xls

Harga JumlahNo. Uraian Pekerjaan Satuan Volume Satuan Harga

(Rp) (Rp)

IX Pekerjaan Pengecatan

1 Pengecatan tembok 1,906.00 18,445.00 35,156,170.00

2 Pengecatan plafon 637.60 18,445.00 11,760,532.00

3 Pengecatan kayu 621.40 36,555.00 22,715,094.22

4 Meni kayu 725.23 8,071.50 5,853,661.66

5 Pengacatan dengan teer ( residu ) 1,488.70 5,475.00 8,150,632.50

83,636,090.38

XI Pekerjaan Lain-Lain

1 Kunci pintu 2 slag bh 18.00 250,000.00 4,500,000.00

2 Engsel pintu 4" ( 3 bh per daun pintu ) psg 21.00 50,000.00 1,050,000.00

3 Grendel tanam pintu psg 3.00 25,000.00 75,000.00

4 Engsel jendela psg 40.00 25,000.00 1,000,000.00

5 Tarikan jendela bh 40.00 25,000.00 1,000,000.00

6 Grendel Jendela bh 40.00 25,000.00 1,000,000.00

7 Hak Angin Psg 40.00 25,000.00 1,000,000.00

8 Handreel tangga dan voide dari besi holo m' 18.00 1,173,650.00 21,125,700.00

10 Pekerjaan Profile Beton Ls 1.00 20,000,000.00 20,000,000.00

50,750,700.00

SIGI, 21 Januari 2012SEKERTARIS KOMITE DIRENCANAKAN

Drs. SALIM, M.Si. T A M S I S, ST.

KETUA KOMITE

ILYAS NAWAWI, S.Sos.

m2

m2

m2

m2

m2

Page 8: Gedung Pemuda.xls

( ENGINEER ESTIMATE )

Pekerjaan : Pembangunan Gedung Sentra Pengembangan Potensi Pemuda Lokasi : Kalukubula Kecamatan Sigi Biromaru Kabupaten Sigi

Provinsi Sulawesi TengahTahun : 2012

No. Uraian Pekerjaan JUMLAH HARGA( Rp)

I Pekerjaan persiapan 30,250,000.00

II Pekerjaan tanah 69,880,140.00

III Pekerjaan Beton 1,018,087,906.54

IV Pekerjaan pasangan 393,305,836.80

V Pekerjaan Kayu , dan Atap 226,699,954.80

VI Pek. Kusen pintu dan jendela 125,285,239.95

VIII Pekerjaan sanitair 28,480,887.00

IX Pekerjaan Elektrikal 12,605,500.00

X Pekerjaan Pengecatan 83,636,090.38

XI Pekerjaan lain-lain 50,750,700.00

Biaya Kontruksi Non Standar 2,038,982,255.47

Biaya Perencanaan Teknis (6,4%) 130,494,864.35

Biaya Pengawasan Teknis (3,6%) 73,403,361.20

Biaya Pengelolaan Teknis (1,5%) 30,584,733.83

2,273,465,214.85

PPn 10% 227,346,521.49

Jumlah 2,500,811,736.34

DIBULATKAN 2,500,000,000.00

SIGI, 21 Januari 2012SEKERTARIS KOMITE DIRENCANAKAN

Drs. SALIM, M.Si. T A M S I S, ST.

KETUA KOMITE

ILYAS NAWAWI, S.Sos.

Terbilang: * Dua Milyar Lima Ratus Juta Rupiah *

Page 9: Gedung Pemuda.xls

12 18 21615 12 18012 18 21615 12 18012 18 216

12.8 35.21008 5,000,000 5,040,000,000.001100 7,500,000 8,250,000,000.00

66 78144 288

48336

Page 10: Gedung Pemuda.xls

Page 10 of 10

Harga JumlahNo. Uraian Pekerjaan Volume Satuan Satuan Harga

(Rp) (Rp)71 10 m2 bongkaran atap seng/ genteng untuk dipergunakan lagi

Pekerja 2.000 Oh 35,000.00 70,000.00Mandor 0.100 Oh 45,000.00 4,500.00

74,500.00Untuk 1 m2 = 43500 / 10 = 7,450.00

72 1 m3 membongkar Kuda kuda dan plafon Pekerja 1.000 Oh 35,000.00 35,000.00Mandor 0.200 Oh 45,000.00 9,000.00Tukang kayu 6.000 Oh 40,000.00 240,000.00Kep. Tukang 0.600 Oh 50,000.00 30,000.00

314,000.00

SIGI, 21 Januari 2012SEKERTARIS KOMITE DIRENCANAKAN

Drs. SALIM, M.Si. T A M S I S, ST.

KETUA KOMITE

ILYAS NAWAWI, S.Sos.