forecast-based rizki amalia putri 1106153990

21
SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia 1 Consumption-based Planning: Forecast-based SAP Username GBI-230 Name Rizki Amalia Putri When consumption-based planning is configured using reorder-point planning, the SAP system creates a planned order or purchase requisition whenever the inventory level for the material falls below the reorder point, and the reorder point must be determined by the user. In addition to requiring the user to determine the reorder point manually, the reorder point method will not perform particularly well when there is a change in the demand for the materialfor example if there is seasonal variation in the material demand, or demand for the material is increasing or decreasing over time. To address this problem, consumption-based planning can be configured to use forecasts of material demand to estimate consumption, and this estimated demand can be used to create planned orders. 2.1 Create Forecasting View for Raw Material To use forecast-based planning, it is first necessary to create the forecasting view for the material. To do this, follow the menu path: Menu Path Logistics Production Master Data Material Master Material Create (Special) Raw Material Trans Code MMR1

Upload: mathias-kevin-phanama-tobing

Post on 18-Jul-2016

25 views

Category:

Documents


2 download

DESCRIPTION

Wawasan

TRANSCRIPT

Page 1: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

1

Consumption-based Planning: Forecast-based

SAP Username GBI-230

Name Rizki Amalia Putri

When consumption-based planning is configured using reorder-point planning, the SAP system creates a planned order or purchase requisition whenever the inventory level for the material falls below the reorder point, and the reorder point must be determined by the user. In addition to requiring the user to determine the reorder point manually, the reorder point method will not perform particularly well when there is a change in the demand for the material—for example if there is seasonal variation in the material demand, or demand for the material is increasing or decreasing over time. To address this problem, consumption-based planning can be configured to use forecasts of material demand to estimate consumption, and this estimated demand can be used to create planned orders.

2.1 Create Forecasting View for Raw Material To use forecast-based planning, it is first necessary to create the forecasting view for the material. To do this, follow the menu path:

Menu Path Logistics Production Master Data Material Master Material Create (Special) Raw Material

Trans Code MMR1

Page 2: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

2

Enter RAW-230 for material and select Retail for Industry Sector then click on Select view(s). The material RAW-230 already exists, and we want to add the Forecasting view for this material. In the SAP system, we do this by creating the view rather than changing the material. When we enter RAW-230 for material, the system will find this (existing) material, then create the new views we select.

Page 3: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

3

Select the Forecasting view, then click on enter icon ( ) and another pop-up window will appear.

Enter DL00 for Plant, then click on enter icon ( ) and the SAP system will create a Forecasting view for your material:

Page 4: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

4

Click on Consumption vals icon ( ), which will produce the following

screen:

Page 5: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

5

Note that the use (consumption) of 330 raw materials from the first consumption-based planning exercise have been recorded. An advantage of an integrated information system like SAP is that material usage is automatically recorded for forecasting purposes. Note that the figure under Total consumption is presented with a grey background. This figure is updated by the SAP system as material is issued. As a result, SAP does not want the user to adjust this figure. However, in forecasting it is common to want to make an adjustment to historical sales figures to produce a better forecast. It may be that sales were low in a particular period because of a random occurrence like bad weather. In this case, a better forecast could probably be obtained by correcting the sales value that was low due to an event that was unlikely to occur in the future. To accommodate this, SAP provides a Corrected value column where the user can enter a value other than the actual usage (consumption) for forecasting purposes.

Click on the Main data icon ( ) icon to return to the Forecasting view.

Note that usage of 330 raw materials

from the first consumption-based

planning exercise have been recorded.

Note that monthly data is being

recorded.

Page 6: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

6

Enter J for the Forecast model. This choice will let the SAP system select the forecasting model after it analyzes the historical data to determine whether trend or seasonal patterns exist. Our consumption data is currently being collected on a monthly basis. This choice was made because of a default setting on the MRP 2 view of the material master when we created the material in the first consumption-based planning exercise. Monthly data is probably not a sufficiently small time increment for our purposes. Change the entry from M (monthly) to W (weekly) so that data is collected on a weekly basis. Click on the enter icon ( ), which will send these new values to the SAP server and produce the following message:

Click on the exclamation mark icon to get more information:

Click on the exclamation mark icon

Enter J for Forecast model (automatic model

selection) and change the Period Indicator to

W (weekly), then click on the Enter icon

Page 7: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

7

Messages with an exclamation mark ( ) are warnings, which means we can ignore them if we choose. That doesn’t mean that we aren’t making a mistake, but the SAP system will let us proceed. In this case, the warning message lets us know that we are changing the time period for consumption data AND consumption data already exists. It also lets us know that we can correct consumption values—that is, we can enter manually correct the consumption values. Close the

Performance Assistant, then click on the Consumption vals icon ( )

again. This will produce another error message about existing consumption values:

Click on the enter icon ( ), which will take us back to the consumption values screen, only this time we can enter values:

Page 8: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

8

Enter 10 weeks of Total consumption values as shown above, then click on the save icon ( ).

2.2 Change Planning Method To change from reorder-point planning to forecast-based planning, we need to change planning parameters that were set on the MRP 1 view of the material. To do this, follow the menu path:

Menu Path Logistics Production Master Data Material Master Material Change Immediately

Trans Code MM02

The period gives the week

and year. The current

period is the first listed.

Enter the Total consumption values shown.

Page 9: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

9

Enter RAW-230 for Material, then click on the Select view(s) icon ( ). This will produce the following pop-up window:

Select the MRP 1 view, then click on enter icon ( ) and another pop-up window will appear.

Page 10: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

10

Enter DL00 for plant, then click on the enter icon and the MRP 1 view will appear:

We want to change the MRP Type from VB (Manual reorder point planning) to VV (Forecast-based planning). Enter VV in the MRP Type and click on the enter icon ( ) and the following message will be displayed:

Change MRP type to VV,

then click on the enter icon

Page 11: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

11

The warning message reminds us that the reorder-point is not used with forecast-based planning. While we could leave the value for the reorder-point in the material master, it is a better practice to delete this value (Why? Do you agree?). Click on the save icon ( ) to save the change to the planning method.

2.3 Stock/Requirements List We can review the status of our material by following the menu path:

Menu Path Logistics Materials Management Inventory Management Environment Stock Stock/Requirements List

Trans Code MD04

The material we just created should be entered by default. If not, enter material RAW-230 and plant DL00, then click on the enter icon ( ) and the following screen will appear:

Page 12: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

12

Note the following information message at the bottom of the screen:

Because we want to use forecast-based planning, we need to have a forecast. We will do that after we delete the existing purchase requisition so that we can clearly see how forecast-based planning works. Click on the detail icon ( ) for the Purchase Requisition, which will produce the following pop-up window:

Click on the change icon ( ) to get the following screen:

Click on the detail icon for the Purchase Requisition

Click on the change icon

Page 13: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

13

If the item overview panel is not open, click on the Item overview icon ( ) to open it:

Select the row with the raw material, then click on the delete icon ( ). You will get the following warning:

Click on the Item overview icon

to open the Item overview panel

Click on the row selection icon, then click on the

delete icon to delete this purchase requisition

Page 14: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

14

Click on Yes, then click on the save icon ( ) and you will return to the Stock/requirements list. Click on the refresh icon ( ) and the purchase requisition will be removed.

Page 15: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

15

2.4 Run Forecast Leave the Stock/Requirements list open and create a new session by clicking on the new session icon ( ). We will use the new session to generate a forecast for our material. To do this, follow the menu path:

Menu Path Logistics Production Production Planning Materials Forecast Forecast Individual Forecast Execute

Trans Code MP30

Enter RAW-230 for Material and DL00 for Plant, then click on the enter icon ( ). This will produce the following screen:

Page 16: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

16

Click on the Execute icon ( ) to execute the forecast. This will produce the following pop-up:

Don’t worry about the Last forecast date. Click on the enter icon ( ) and the forecast results will be displayed:

Click on the Execute icon

to execute the forecast

This screen shows us the forecast values that

were entered in the material master, and also

informs us that we don’t have any forecast yet

Page 17: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

17

Click on the save icon ( ) to save these results

then switch to the Stock/Requirements list and click on the refresh icon ( ). The forecast demand for the material will now be displayed:

Page 18: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

18

2.4 Run MRP Planning Now that the forecast has created “demand” for the material, we can generate planned orders using the MRP process. To run the MRP planning process, switch to the other session and follow the menu path:

Menu Path Logistics Production MRP Planning Single-Level, Single-Item

Trans Code MD03

This will call up the following screen:

Note that forecast

requirement for first week is

adjusted based on time left

in the week

Page 19: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

19

Select Display results before they are saved so we can see the planning results immediately, then click on the enter icon ( ) and the following message will appear at the bottom of the screen:

Depending on the situation, production planning can take a lot of computer resources, so SAP is just reminding you to make sure that you have everything set correctly. Click on the enter icon ( ) a second time, and a screen very similar to the Stock/Requirements screen will be displayed:

Use the default planning values, select

Display results before they are saved,

then click on the enter icon

Page 20: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

20

Click on the save icon ( ) to save these results

Then switch to the Stock/Requirements list and click on the refresh icon ( ).

Note that planned orders

have been created to keep

the available quantity

positive

Page 21: Forecast-based Rizki Amalia Putri 1106153990

SCM Gasal 2012/2013 Faculty of Computer Science University of Indonesia

21

With forecast-based planning, material requirements and production/purchase orders are handled in essentially the same manner as finished products planned using MRP. Demand is forecast, then planned orders are generated to meet this demand. Forecast-based planning can be made to run automatically by grouping all materials together that are planned using this method, then generating forecasts and then running MRP for all materials in this group on a regular basis (e.g. weekly). Question:

Is there any situation in which this approach can not be used? Explain!

Answer: Apabila demand level tidak menentu