Download - 7.1c Contoh RMK Kontraktor
CONSULTING SERVICES FOR ROAD REHABILITATION (SECTOR) PROJECT UNDER ADB LOAN NO
PAGE
BALAI BESAR PELAKSANAAN JALAN NASIONAL III
DIREKTORAT JENDERAL BINA MARGANo. Hlm: 16 dari 17
No. Urut: 04/Trnsp/07
Rev. : 00 Tgl: 27 Apr 07
No. Dokumen : BBPJN.III/ RM.000-000RENCANA MUTU KONTRAK LEVEL 3
Tgl Berlaku : Agustus 07 Revisi : 00
RENCANA MUTU KONTRAK
PENINGKATAN JALAN PRABUMULIH MA. ENIMKONTRAK NO. 138/SNVT-PEMB/PROP.SUMSEL/04/07
TGL 26 APRIL 2007PERSETUJUANORIGINATORMENYETUJUIMENGETAHUI
JABATANGENERAL SUPERINTENDANT
DIREKTUR
PT. SUPER BANGUNPEJABAT PEMBUAT KOMITMEN
TANDA TANGAN
NAMAIr. JoniIr. HoniIr. Polan
TANGGAL27-04-0727-04-0727-04-07
Daftar Distribusi Dokumen :
NoPenerimaTanda-tanganTanggal
1Wakil Manajemen BBPJN-III
2Kepala SNVT Pembangunan Prop Sumsel
3Project Officer
4
5
6
Riwayat Dokumen
NoTanggalRevisi keDisposisi PerubahanDiperiksaDisetujui
127-04-0700RMK diterbitkan perdana
PT. SUPER BANGUNC O N T R A C T O RJl. Samudra Indah No 23, PalembangTel (0711) 424535, Fax (0711) 424353, Email: [email protected]
1. DAFTAR ISI
JUDUL / LEMBAR PENGESAHAN / DISTRIBUSI dan RIWAYAT DOKUMEN121.DAFTAR ISI
32.KEBIJAKAN MUTU DAN SASARAN MUTU
43.INFORMASI PROYEK
54.PIHAK YANG TERLIBAT
65.STRUKTUR ORGANISASI PROYEK
76.TUGAS, TANGGUNGJAWAB DAN WEWENANG
97.BAGAN ALIR KEGIATAN POKOK
108.JADUAL PELAKSANAAN PEKERJAAN
119.JADUAL TENAGA KERJA
1210.JADUAL MATERIAL
1311.JADUAL PERALATAN
1412.JADUAL INSPEKSI UJI DAN TEST
1513.DAFTAR KEBERTERIMAAN
1614.DAFTAR PROSEDUR DAN INSTRUKSI KERJA
1715.DAFTAR SIMAK
2. KEBIJAKAN MUTU DAN SASARAN MUTU
KEBIJAKAN MUTU :
Manajemen dan Karyawan PT. Super Bangun memberdayakan sistem manajemen mutu dalam memenuhi tuntutan kontrak demi efisiensi dan efektivitas pekerjaan.SASARAN MUTU :
1. Menyelesaikan pekerjaan tepat waktu dalam 5,5 bulan 2. Menyelesaikan setiap keluhan Pengguna Jasa tanpa mengganggu target waktu3. Memenuhi persyaratan mutu yang ditetapkan dalam kontrak dan spesifikasi.3. INFORMASI PROYEK
1.Nama Proyek:Peningkatan Jalan Prabumulih Muara Enim2.Pemilik:SNVT Pembangunan Jalan dan Jembatan Propinsi Sumatera Selatan3.No. Kontrak:138/SNVT-PEMB/PROP.SUMSEL/04/07 tgl 26 April 20074.Nilai Kontrak:Rp. 12.323.452.0005.Sistem Kontrak:Fixed Unit Price6.Pembayaran:Angsuran / Termijn7.Lokasi Proyek:Sumatera Selatan8.Masa Pelaksanaan:5,5 bulan9.Uraian Lingkup Proyek:
Peningkatan Jalan Propinsi Ruas Jalan Prabumulih Muara Enim (12,00 km)
Lebar Perkerasan:6,00 m pelebaran 1 m (kiri) + 1 m (kanan)Bahu Jalan:1,00 m
Konstruksi:Laston Lapis Aus (AC-WC t=4 cm)
Lapis Antara AC-BC t=5 cm
Aggr. Klas A = 15cm
Aggr. Klas B = 20 cm
Bahu Jalan Aggr Kls B t = 10 cm
Marka Jalan
Patok Km, Damija, dll
Pengupasan Tebing batu
Saluran Drainase
Turap penahan timbunan (Pasangan Batu)10.Peta Lokasi Proyek: (terlampir)4. PIHAK YANG TERLIBAT
SKEMA ORGANISASI PROYEK
Pengguna Jasa :
SNVT Pembangunan Jalan dan Jembatan Prov. SumSel Ir. Junaidi, MTJl. . . .
Palembang
Tel . . . Fax . . . Email . . .
Pejabat Pembuat Komitmen (PPK)Ir. PolanJl. . . .
Palembang
Tel . . . Fax . . . Email . . .
Penyedia Jasa :
PT. SUPER BANGUN Contractor
Jl. Samudra Indah No 23, Palembang
Tel (0711) 424535, Fax (0711) 424353, Email: [email protected] :
PT. Arteri Cipta Rencana
Kebayoran Baru Mall B-26, Jl. Kebayoran Baru 9-10, Jakarta Selatan 12120
Tel (021) 739 5552, Fax (021) 720 2483 , Email : [email protected]
SNVT P2JJ Prop Sumsel
Ir. Marsudi, MTJl. RE Martadinata Komplek RBO Bina Marga 2 Ilir, Palembang - 30118Tel (0711) 712 768, 711 0135. STRUKTUR ORGANISASI PROYEK
6. TUGAS, TANGGUNGJAWAB DAN WEWENANG
GENERAL SUPERINTENDANT :Tugas :
Memimpin dan mengendalikan kegiatan proyek agar efisien dan efektif mencapai hasil optimal dari segi kualitas dan pencapaian laba
Memahami seluruh aspek teknik pekerjaan dan berperan aktif membina sumber daya sesuai dengan kebutuhan proyek
Membina keamanan dan menciptakan ketenangan kerja di lingkungan proyek dan masyarakat sekitarnya
Menganalisa kebutuhan material, tenaga kerja, peralatan dan overhead, serta menyusun jadwal kebutuhannya
Membuat Rencan Mutu Kontrak
Tanggungjawab :
Bertanggungjawab atas kelancaran kegiatan proyek saejak masa persiapan hingga penyerahan
Bertanggungjawab atas pelaksanaan tertib administrasi internal, data material, data peralatan, data keuangan termasuk pengihan dan data pendukungnya
Bertanggungjawab atas pengendalian mutu hasil pekerjaan di proyek
Wewenang :
Memutuskan strategi pelaksanaan proyek yang berkaitan dengan pengendalian mutu proyek
Menyetujui pengeluara-pengeluaran langsung yang diperlukan kegiatan Proyek.
SITE MANAGERTugas:
Mengatur dan mengawasi jadual kerja harian para pelaksana dan memonitor jadwal kedatangan material, memeriksa volume dan kualitas serta mengatur penempatannya
Memeriksa hasil pekerjaan para pelaksana agar dapat dimonitor bobot kemajuan dalam kaitannya dengan opname kemajuan pekerjaan, laporan upah dan mengesahkan kepada pengguna jasa
Membaca, memahami dan mengarahkan setiap kegiatan proyek yang dilaksanakan oleh mandor, tukang, dan pekerjaan yang telibat dengan mutu
Tanggungjawab:
Bertanggungjawab selaku koordinator pelaksanaan di lapangan sesuai dengan gambar kerja
Mengawasi teknis pelaksanaan semua pekerjaan di lapangan agar supaya memenuhi ketentuan-ketentuan teknis yang benar dan tidak menyimpang dari anggaran yang ditetapkan
Menggunakan material dengan kualitas dan volume yang benar
Menggunakan peralatan dan tenaga kerja secara efisien
Memenuhi jadual waktu yang telah ditetapkan
Wewenang:
Menyeleksi mandor yang direkomendasikan dapat bekerja dengan baik dan menerbitkan surat perintah kerja kepada mandor yang dipilih
Memeriksa dan mensyahkan opname hasil pekerjaan yang diajukan oleh mandor setelah diperiksa kesesuaiannya oleh pelaksana
Menyetujui pengeluaran-pengeluaran langsung yang diperlukan kegiatan proyek sebatas anggaran yang ditetapkan.
dst . . .7. BAGAN ALIR KEGIATAN POKOK
YA
8. JADUAL PELAKSANAAN PEKERJAAN
NoUraianSatVolBobot
(%)2007Ketr.
MeiJunJulAgsSepOkt
12345678910111213141516171819202122
1MobilisasiLS1,000,3610,0100,0200,0400,0800,0900,121
2Kantor & Fasl. LapanganLS1,000,4280,0210,0210,0210,0210,0210,0210,0220,0220,0220,0220,0220,0220,0220,0220,0210,0210,0210,0210,0210,021
3Drainase
Selokan DrainaseM32.745,000,7610,0510,0630,0630,0630,0630,0630,0630,0630,0630,0630,0630,063
Pasangan BatuM32,65710,9321,2001,2001,2281,2281,2201,2141,2141,2141,214
4Pekerjaan Tanah:
PembersihanM2421,890,0100,0050,005
GalianM315.100,004,9730,7000,7000,7200,7200,7100,7130,710
TimbunanM34.438,002,1960,3130,3140,3140,3140,3140,3140,313
Penyiapan Badan JalanM27.608,000,2310,0460,0460,0470,0460,046
5Bahu JalanM34.560,004,0960,5850,5850,5850,5860,5850,5850,585
6Perkerasan:
Lapis Pondasi Aggr AM3390,000,4110,1370,1370,137
Lapis Pondasi Aggr BM3520,000,4670,1550,1560,156
Pondasi Bawah (Semen)M33.040,0013,6861,2441,2441,2441,2441,2441,2441,2441,2441,2451,2451,244
7Perkerasan Aspal :
Prime CoatL1.300,000,0480,0040,0040,0040,0040,0040,0050,0050,0050,0050,0040,004
Tack CoatL28.305,001,2080,1510,1510,1510,1510,1510,1520,1510,151
LevellingTon5.011,0027,2013,4003,4003,4003,4003,4013,4003,4003,400
ATBM3524,006,5480,5950,5950,5950,5950,5950,5950,5950,5960,5960,5960,595
8Struktur :
Beton K-275M333,000,2630,0870,0880,088
Beton K-225M329,000,2080,0690,0700,069
Beton K-175M367,000,4410,0730,0730,0740,0740,0740,073
Tulangan Baja U32Kg5.220,000,8620,1230,1230,1230,1240,1230,1230,123
Pasangan BatuM35.219,0020,2311,4001,4001,4001,4001,4451,4901,4901,4901,4901,4461,4451,4451,4451,445
9Pekerjaan Rekondisi:
Pondasi Aggr Klas AM324,000,0250,0320,033
Pondasi Aggr Klas BM332,000,0290,0140,015
Aspal Pek. MinorM38,000,1000,100
Marka JalanM22.735,002,5500,9550,9540,641
Rambu JalanBh30,000,1380,138
Patok KM, Damija, dllBh777,001,0190,3500,3500,319
Lampu PeneranganBh4,000,4220,1350,1520,135
10 Pekerjaan harian :
MandorJam69,000,0040,0020,0010,001
Pekerja BiasaJam251,000,0110,0040,0040,003
Dump Truk 4-5 m3Jam28,000,0200,0080,0070,005
Wheel Loader 1-1.6 m3Jam28,000,0370,0100,0170,010
Pengujian DefleksiJam28,000,0330,033
Pengujian CBRjam28,000,0260,026
Jumlah Bobot1000,0100,0790,8173,4833.9335,5075,7736,3146.1055,1438,6928,1836.9266,9266,8657,4496,2025,1061,0952,0391,8311,522
Jumlah Kumulatif0,0100,0890,9064,3898.32213,82919,60225,91632,02137,16445,85654,03960,96567,89174,75682,20588,40793,51394,60896,64798,478100
9. JADUAL TENAGA KERJA
NoPosisiNama2007Ketr.
MeiJunJulAgsSepOkt
12345678910111213141516171819202122
ISTAFF
1General SuperintendantIr. Joni
2Site ManagerIr. Sunirno
3Kepala PelaksanaIganov
4Urusan TeknikDwipanto
5Urusan AdministrasiWarsiyo
6 PelaksanaJahadi
7 SurveyorTulimad
8Adminsitrasi TeknikHentris
9Logistik dan PeralatanGumara
10KeuanganSulono
11Umum dan PersonaliaRasta
IIPEKERJA PROYEK
1 Operator
2Mekanik
3 Mandor
4Tukang Batu
5Tukang Kayu
6Pekerja Harian
10. JADUAL MATERIAL
NoJenis MaterialSatVol2007Ketr.
MeiJunJulAgsSepOkt
12345678910111213141516171819202122
1BatuKaliM37.876
2SemenSak1.161
3PasirM37.926
4SplitM3129
5SirtuM33.169,4
6Besi BetonKg5.220
7Plywood BekistingLbr78
8 Kayu BekistingLbr142
9AspalTon300,66
10Aggregat AM3390
11Aggregat BM3245
11. JADUAL PERALATAN
NoJenis PeralatanSatVol2007Ketr.
MeiJunJulAgsSepOkt
12345678910111213141516171819202122
1ExcavatorUnit2
2Asphalt FinisherUnit1
3Asphalt SprayerUnit2
4CompressorUnit1
5Tandem RollerUnit2
6Tire RollerUnit2
7Concrete VibratorUnit2
8Motor GraderUnit1
9 Water TankUnit1
10Vibrator RollerUnit3
11Concrete MixerUnit8
12Core DrillUnit1
13Dump TruckUnit10
12. JADUAL INSPEKSI UJI DAN TEST
NoKodeJenis Pekerjaan2007Ketr.
MeiJunJulAgsSepOkt
12345678910111213141516171819202122
1Q1Inspeksi Rekayasa Lapangan
2Q2Mobilisasi
3Q3Request Kerja
4Q4Galian Tanah
5Q5Pasangan Batu
6Q6Pembesian
7Q7Pengecoran
8Q8Galian Tanah Dasar
9Q9Timbunan
10Q10CTSB
11Q11Prime Coat / Tack Coat
12Q12Hotmix
13. DAFTAR KEBERTERIMAAN
KODEURAIAN PEKERJAANKEBERTERIMAANMETODEPENANGGUNG JAWAB
Q1Rekayasa LapanganKelengkapan DataPerhitungan dan PengukuranSite Manager
Q2MobilisasiKelengkapan Peralatan dan PersonilvisualSite Manager
Q3Request PekerjaanGambar Kerja
Daftar Peralatan
Daftar Tenaga Kerja
Daftar Material
Kondisi CuacaVisualKepala Pelaksana
Q4Galian TanahGambar KerjaPengukuranSurveyor
Q5Pasangan BatuGambar KerjaSampel AdukanPengukuranUji Kuat TekanSurveyorQuality Control
Q6PembesianGambar KerjaVisualKepala Pelaksana
Q7PengecoranSlump Test
Sampel Beton
Concrete Mixer
Concrete VibratorHasil Uji
Hasil Uji
Inspeksi
InspeksiQuality Control
Quality Control
Mekanik
Mekanik
Q8Galian Tanah DasarGambar KerjaInspeksiKepala Pelaksana
Q9Timbunan TanahKepadatanUji Sand ConeQuality Control
Q10CTSBSlump Test
Sample Beton
Concrete Mixer
Concrete VibratorHasil Uji
Hasil Uji
Inspeksi
InspeksiQuality Control
Quality Control
Mekanik
Mekanik
Q11Prime Coat/Tack CoatWaktu PeresapanKetebalanVisualHasil UjiKepala Pelaksana
Q12HotmixSuhuKondisi Cuaca
KetebalanTestVisual
Core DrillKepala Pelaksana
14. DAFTAR PROSEDUR DAN INSTRUKSI KERJA
NO.KODENO. DOKUMENJUDUL DOKUMEN
1P1IK-SB/001/02 Instruksi Kerja Pengukuran
2P2PR-SB/001/01Prosedur Rekayasa Lapangan
3P3PR-SB/000/01Prosedur Mobilisasi/Demobilisasi
4P4IK-SB/001/01Instruksi Kerja Request Pekerjaan
5P5IK-SB/003/03Instruksi Kerja Pasangan Batu
6P6IK-SB/003/01Instruksi Kerja Galian Tanah
7P7IK-SB/003/02Instruksi Kerja Galian Tanah Dasar
8P8IK-SB/003/04Instruksi Kerja Timbunan
9P9IK-SB/012/01Instruksi Kerja Pembesian
10P10IK-SB/012/02Instruksi Kerja Pengecoran
11P11IK-SB/009/01Instruksi Kerja Prime Coat / Tack Coat
12P12IK-SB/009/02Instruksi Kerja Pekerjaan Hotmix
15. DAFTAR SIMAK
NONO DOKUMENJUDUL DOKUMEN
1SB/Pust/Eng/001 Peraturan Beton Bertulang Indonesia 1971
2SB/Pust/Eng/003 Peraturan Umum Bahan Bangunan 1955
3SB/Pust/Eng/016 AASTHO
4SB/Sumsel-A/001 Gambar-gambar Perencanaan
5IK-SB/001/02 001Daftar Simak Instruksi Kerja Pengukuran
6PR-SB/001/01 005Daftar Simak Prosedur Rekayasa Lapangan
7PR-SB/000/01 001Daftar Simak Prosedur Mobilisasi/Demobilisasi
8IK-SB/001/01 002Daftar Simak Instruksi Kerja Request Pekerjaan
9IK-SB/003/03 001Daftar Simak Instruksi Kerja Pasangan Batu
10IK-SB/003/01 002Daftar Simak Instruksi Kerja Galian Tanah
11IK-SB/003/02 002Daftar Simak Instruksi Kerja Galian Tanah Dasar
12IK-SB/003/04 001Daftar Simak Instruksi Kerja Timbunan
13IK-SB/012/01 018Daftar Simak Instruksi Kerja Pembesian
14IK-SB/012/02 009Daftar Simak Instruksi Kerja Pengecoran
15IK-SB/009/01 002Daftar Simak Instruksi Kerja Prime Coat / Tack Coat
16IK-SB/009/02 001Daftar Simak Instruksi Kerja Pekerjaan Hotmix
Q1
SELESAI
PPK
KONTRAKTOR
KONSULTAN PENGAWAS
General Superintendent
Ir. Joni
HOTMIX (ACL)
Site Manager
Ir. Sunirno
Urusan Teknik
Dwipanto
Kepala Pelaksana
Iganov
Pelaksana
Jahadi
P7
Keuangan
Sulono
PENGUKURAN
Q4
P2JJ Sumsel
Administrasi Teknik
Hentris
SNVT
MOBILISASI
TACK COAT
P12
Pengukuran
Tulimad
P1
REKAYASA LAPANGAN
MULAI
TIDAK
Logistik & Peralatan
Gumara
Umum & Personalia
Rasta
YA
YA
YA
HOTMIX (ATB)
REQUEST KERJA
GALIAN TNH DSR
GALIAN TANAH
TIDAK
Q3
YA
TIDAK
Q2
PASANGAN BATU
YA
TIDAK
Urusan Adminstrasi
Warsiyo
P2
P3
P4
P5
P6
YA
TIDAK
TIDAK
TIDAK
Q12
TIDAK
TIDAK
Q12
YA
Q5
TIDAK
Q8
YA
YA
Q9
TIDAK
Q5
Q11
TIDAK
Q10
TIDAK
Q6
P5
TIDAK
P10
P9
PASANGAN BATU
CTSB
PEMBESIAN
TIDAK
Q7
P8
P11
P10
TIMBUNAN BAHU
PRIME COAT
PENGECORAN
YA
YA
YA
Q11
YA
YA
P12
P11