Kuliah Rekayasa Pondasi 2 nim : 13011004
Tugas asistensi responsi 1 (Kapasitas Aksial Pondasi Tiang), UNIKOM 1
10 m
0.25 m
Silty Clay
= 15 kN/m3
sat
= 16 kN/m3
’ = 0 ˚
c’ = 35 kN/m2
6 m
0.50 m
Silty Sand
= 16 kN/m3
sat = 17 kN/m
3
= 28 ˚
Silty Clay
= 15 kN/m3
sat = 16 kN/m3
c = 30 kN/m2 8 m
Gambar 1
Gambar 2
5 m
M.A.T
-
8/18/2019 Distribusi Tegangan 13011004
2/3
Kuliah Rekayasa Pondasi 2 nim : 13011004
Tugas asistensi responsi 1 (Kapasitas Aksial Pondasi Tiang), UNIKOM 2
8 m
0.25 m
Silty Sand
= 16 kN/m3
sat = 17 kN/m3
’ = 25 ˚
c’ = 0 kN/m2
Gambar 3
5 m
0.50 m
Silty Clay
= 15 kN/m3
sat = 16 kN/m3
c = 27 kN/m2
8 m
Gambar 4
3 m
Stiff Clay
= 17 kN/m3
sat = 18 kN/m3
c = 35 kN/m2
Clayey Silt
= 15 kN/m3
sat = 16 kN/m3
c = 216 m
M.A.T
-
8/18/2019 Distribusi Tegangan 13011004
3/3
Kuliah Rekayasa Pondasi 2 nim : 13011004
Tugas asistensi responsi 1 (Kapasitas Aksial Pondasi Tiang), UNIKOM 3
1.
Berdasarkan Gambar 1, 2, 3 dan 4 tentukan kapasitas dukung ijin pondasi tiang pancang
beton (SF = 3)
2.
Berdasarkan Gambar 4 hitung kapasitas dukung ijin pondasi tiang pancang beton dengan
menggunakan metode Alfa ()
3.
Berdasarkan Gambar 2 hitung kapasitas dukung ijin pondasi tiang pancang beton dengan
menggunakan metode Lamda ()
4.
Berdasarkan Gambar 4, jika Q allowable yang disyaratkan adalah 133 kN dengan SF = 3.
Tentukan dimensi tiang pancang.