bab 1 lantai kendaraan
DESCRIPTION
Tugas Besar Perhitungan Pelat Lantai Kendaraan JembatanTRANSCRIPT
![Page 1: Bab 1 Lantai Kendaraan](https://reader035.vdokumen.com/reader035/viewer/2022081722/577c808f1a28abe054a933f5/html5/thumbnails/1.jpg)
ASPAL PELAT BETON
d4 = 0.05 m
d3 = 0,2 m
b1 = 2 mBALOK MEMANJANG
TUGAS BESAR STRUKTUR JEMBATAN Dosen Asistensi : Afif Navir Refani S.T, M.T.
BAB 1
PLAT LANTAI KENDARAAN
1.1 Perencanaan Tebal Plat Lantai Kendaraan
Tebal plat lantai (BMS ps. 2.2.3.2 dan ps. 6.7.1.2)plat beton d3 ≥ 200 mm
d3 ≥ 100 + 40 . b1
≥ 100 + 40 . 2 ≥ 180 mm
dipakai d3 = 200 mm = 20 cm Aspal d4 = 5 s/d 8 cm
dipakai d4 = 5 cm
lylx
=5,22
=2,6>2
Plat 1 arah ( tertumpu menerus pada balok memanjang )
HANDARU ALFIANSYAH P 3113041096
1 m Iy = λ = 5,2 m
Iy = b1 = 2 m
![Page 2: Bab 1 Lantai Kendaraan](https://reader035.vdokumen.com/reader035/viewer/2022081722/577c808f1a28abe054a933f5/html5/thumbnails/2.jpg)
TUGAS BESAR STRUKTUR JEMBATAN Dosen Asistensi : Afif Navir Refani S.T, M.T.
1.2 Perencanaan Beban Plat Lantai Kendaraan Beban mati
Ƴc = 24 kN/m …(Tabel 3 RSNI T-02-2005)Ƴb = 22 kN/m- berat plat = d3 . Ƴc . 1 = 0,2 . 24 . 1 = 4,8 KN/m- berat aspal = d4 . Ƴb . 1 = 0,05 . 22 . 1 = 1,1 KN/m
qm = 5,9 KN/m
Momen maksimum ( momen negatif )jika plat lantai kendaraan dianggap terjepit elastic pada tumpuan dan terletak bebas pada ujung tumpuan maka factor momen yang terjadi adalah :
Faktor beban : beton di cor di tempat Kunas = 1,3 …(Tabel 2 RSNI T-02-2005)
Mqm = 110 ( qm . Ku
nas ) . b12
= 110 ( 5,9 . 1,3 ) . 22
= 3,068 KNm
Beban hidup TBeban truk T = 112,5 KN … Ps 6.4.1 RSNI T-02-2005FBD untuk pembebanan truk = 0,3 … Ps 6.6.4 RSNI T-02-2005T = T ( 1 + DLA )
= 112,5 ( 1 + 0,3 )= 146,25 KN
Faktor beban : muatan truk KuTT = 1,8 …(Tabel 2 RSNI T-02-2005)
MT = 0,8 . s+0,610 . KuTT . T
= 0,8 . 2+0,610 . 1,8 . 146,25
= 54,756 KNm= 54756000 Nmm
Mu = Mqm + MT
= 3,068 + 54,756= 57,824 KNm= 57824000 Nmm
HANDARU ALFIANSYAH P 3113041096
-1/10-1/10
-1/10 -1/10 -1/10
-1/10 -1/10
-1/10
-1/10
![Page 3: Bab 1 Lantai Kendaraan](https://reader035.vdokumen.com/reader035/viewer/2022081722/577c808f1a28abe054a933f5/html5/thumbnails/3.jpg)
TUGAS BESAR STRUKTUR JEMBATAN Dosen Asistensi : Afif Navir Refani S.T, M.T.
1.3 Penulangan PlatData perencanaan f’c = 40 MPa Selimut beton = 40 mmFy = 390 MPa Tebal plat = 200 mmFaktor reduksi Ø=0,8 b1 = 0,85 x (f’c -10) = 0,77 ; sebab f’c > 30 … SNI 2002 12.2.7.3
ρbalance0,85 .b1 . f ' c
fy = ( 600600+ fy )
= 0,85.0,77 .40
390 ( 600600+390 )
= 0,040684
ρmin = 1,4fy =
1,4390 = 0,00359
ρmax = 0,75 . ρbalance = 0,75 . 0.040684 = 0.030513
Mu = 57,824 KNm Direncanakan diameter tulangan Ø (Arah X) = 20 mm
dx = t – selimut beton – 0,5 . d= (20 – 4 – 0,5 . 2) cm= 15 cm
Direncanakan diameter tulangan Ø (Arah Y) = 16 mmdy = t – selimut beton –D. tul bawah - 0,5.D.tul Atas
= (20 – 4 – 1,6 – 0,5 . 2) cm= 13,4 cm
Mnperlu = MuØ =
57,8240,8 = 72,28 KNm = 72280000 Nmm
Tulangan arah melintang ( x )
Rn = Mu
Ø .b .dx2
= 57824000
0,85.1000 .1502
= 3,02347 MPa
m = fy
0,85 . f ' c
HANDARU ALFIANSYAH P 3113041096
![Page 4: Bab 1 Lantai Kendaraan](https://reader035.vdokumen.com/reader035/viewer/2022081722/577c808f1a28abe054a933f5/html5/thumbnails/4.jpg)
TUGAS BESAR STRUKTUR JEMBATAN Dosen Asistensi : Afif Navir Refani S.T, M.T.
= 390
0,85 .40
= 11.4706
ρ perlu = 1m
¿
= 1
11.4706¿
= 0,015505
ρ min < ρ perlu < ρ max OK!!!
Asperlu = ρ . b . dx
= 0,015505. 1000 . 150
= 2325,752 mm2
As x = Ø20 = ¼ . П. d2 = 0,25 . П . 202 = 314 mm2
n = As perluAs x
=2325,752314 = 7,406 8 buah tulangan
S = 10008
=125mm
As pasang = 8. 314 = 2512 mm2 > 2325,752 mm2 OK !!
Maka digunakan tulangan Ø20 - 125 cm
Tulangan arah memanjang ( y )
Ay = tulangan susut
Assusut ( arah y ) = ρmin . b . dy = 0,00359 . 2000 . 134 = 962,0513 mm2
Asy = ¼ . П . 162 = 200,96 mm2
n = As susutAsy
=962,0513200,96 = 4,787 Dipasang 4 buah Tulangan
HANDARU ALFIANSYAH P 3113041096
![Page 5: Bab 1 Lantai Kendaraan](https://reader035.vdokumen.com/reader035/viewer/2022081722/577c808f1a28abe054a933f5/html5/thumbnails/5.jpg)
TUGAS BESAR STRUKTUR JEMBATAN Dosen Asistensi : Afif Navir Refani S.T, M.T.
S = As susutn
=721,58354 = 192,413 mm2
As pasang = Asy . n = 200,96 . 5 = 1004,87 mm2 > 962,0513 mm2 OK !! Maka diunakan tulangan D16-180 mm
1.4 Kontrol Geser Pons
Keliling kritis :U = 2 ( b0 + d0 )
= 2 [ ( 0,5 ( 20 + 5 ) + 0,5 ( 20 + 5 ) ) + (0,5 ( 20 + 5 ) + 20 + 0,5 ( 20 + 5 ) ) ]= 2 [ ( 25 + 50 ) + ( 25 + 20 ) ]= 2 [ 75 + 45 ]= 240 cm
Luas kritis :A = 240 . ( d4 + d3 )
= 240 . ( 5 + 20 )= 6000 cm2
Gaya geser Ultimate :Vn = KuTT . 100 . ( 1 + DLA )
HANDARU ALFIANSYAH P 3113041096
![Page 6: Bab 1 Lantai Kendaraan](https://reader035.vdokumen.com/reader035/viewer/2022081722/577c808f1a28abe054a933f5/html5/thumbnails/6.jpg)
TUGAS BESAR STRUKTUR JEMBATAN Dosen Asistensi : Afif Navir Refani S.T, M.T.
= 2,0 . 100 . ( 1 + 0,3 ) = 260 KN
Vuc = ( 1 + 2β ) . ( √ f ' c
6 ) . A dimana β =
5020 = 2,5
= ( 1 + 22,5 ) . ( √40
6 ) . 600000 mm2
= 1138420 N= 1134,42 KN
Vc = √ f ' c3
. A
= √403
. 600000 mm2
= 2190890,23 N= 2190,89 KN
Kuat penampang pada geser harus memenuhi :i. Vn ≤ Vuc ii. Vc > Vuc
260 KN ≤ 1134,42 KN ( ok ) 2190,89 KN > 1134,42 KN ( ok )
HANDARU ALFIANSYAH P 3113041096
![Page 7: Bab 1 Lantai Kendaraan](https://reader035.vdokumen.com/reader035/viewer/2022081722/577c808f1a28abe054a933f5/html5/thumbnails/7.jpg)
TUGAS BESAR STRUKTUR JEMBATAN Dosen Asistensi : Afif Navir Refani S.T, M.T.
HANDARU ALFIANSYAH P 3113041096