atrapamiento de sarta de perforación.pdf
DESCRIPTION
Pozo sihilTRANSCRIPT
-
Atrapamiento de sarta de perforacio n
Horas de Atrapamiento 286.00
Das 11.92 Clasificacin General Problemas Operativos Compaa Halliburton Etapa 5 (21/01/10 22/02/10)
E5 18:30-22:30 (N) CON PERSONAL DE CIA. HALLIBURTON ARMO BNA. GEOBIT 8 1/2" PDC. -FMF 3743Z
#11334605 Y HTS. DIRECCIONALES EQ. C/GEOPILOT C/ABG /FLEX COLLAR 6 3/4" /DOBLE
PIN ESTAB. 8 3/8" -/LWD FE COLLAR 6 3/4". (DGR-PWD-EWR ) -/ MWD TM/DM COLLAR
CORTO 6 3/4" 650 SYS -/ VCP. 6 3/4" .- PROGRAMANDO MISMA
22:30-23:30 (N) BAJO BNA. GEOBIT 8 1/2" Y HTAS.DIRECCIONALES SARTA NAV. DE CIA.HALLIB. A 59
MTS.. DONDE PROBO HTA.DIRECCIONAL C/62 EPM. - Q.=304 GPM. .- P.B.= 950 PSI.
SATISFACTORIAMENTE.
23:30-24:00 (N) CONTINUA BAJANDO BNA. A 140 MTS.
22/01/10
E5 00:00-05:00 (N) ***CONTINUA BAJANDO BNA. GEOBIT 8 1/2" PDC. -FMF 3743Z #11334605 Y SARTA
ROT.NAV. GEOPILOT C/ABG , EQ. C/ ( DGR-PWD-EWR.) DE CIA. HALLIBURTON A 2503M.
LLENANDO INT. DE TP. C/500 M. Y ROMPIENDO CIRCULACION C/1000. DESPLAZANDO
NORMAL. PREVIA PLAT. DE SEG. OPERN .IND.LIMPIA,SSPA,META CERO , POLITICA Y
PRINC. AL PERS. DE PEMEX,Y CIAS. ELABORO A.S.T. TEMA = PRUEBA DE BOPS. CON TOP
DRIVE ,VALV. DE PIE Y C.S.C.- CLAVE- PE-EP-OP-009-2008
05:00-05:30 (N) CONTINUA BAJANDO A 2525 M OBSERVANDO RESISTENCIAS PUENTEADAS VENCIENDIO MISMAS
CON ROTACION Y BOMBEO.
05:30-09:00 (N) CIRCULA POZO HOMOGENEIZANDO LODO E.I. A 1.30 GR/CC CON MOVIMIENTOS RECIPROCANTES
DE SARTA
09:00-14:00 (N) PERFORO CON BNA 8 1/2" Y SARTA ROT.-NAV. GEOPILOT C/ABG EQ. C/ (DGR- PWD -EWR.
), DE 2525M A 2550 M, 25 M EN 1:56 HRS, PSB 2-3 TON RPM 120, AMP=505/654,
ULTIMOS 3-3-4 MIN. OBSERVANDO REPRESIONAMIENTOS HASTA 3500 PSI E INCREMENTO DE
TORQUE, ASI COMO RESISTENCIAS A 2529 M REPASANDO MISMAS EN REPETIDAS OCASIONES
PERSISTIENDO MISMAS. **NOTA EFECTUO JUNTA DE SEGURIDAD, OPERACION, SSPA META
CERO ACCIDENTES, POLITICA Y PRINCIPIOS A PERS. DE PEMEX, Y CIAS ELABORO AST,
TEMA= PRUEBA DE BOPS CON TOP DRIVE, VALVULA DE PIE Y CONEXIONES SUPERFICIALES DE
CONTROL CLAVE PE-SS-OP-009-2008
14:00-18:00 (N) LEVANTA BNA 8 1/2", SARTA NAVEGABLE A 2503 M Y CIRCULA ACONDICIONANDO LODO DE
1.30 GR/CC A 1.33 GR/CC
18:00-20:00 (N) BAJO A 2527.5 M. DONDE CHECO RESISTENCIA FRANCA C/ 6 TONS. INTENTO VENCER MISMA
EN REPETIDAS OCASIONES S/E POR PERSISTIR RESISTENCIA FRANCA Y REPRESIONAMIENTOS
HASTA 2900 PSI. Y FRICCIONES DE HASTA 10 TONS.
20:00-23:00 (N) LEVANTA BNA 8 1/2", SARTA NAVEGABLE A 2503 M Y CIRCULA HOMOGENIZANDO LODO DE
1.33 GR/CC A 1.35 GR/CC
23:00-24:00 (N) BAJO A 2522 M. DONDE CHECO RESISTENCIA FRANCA C/ 5 TONS. DONDE REPASO CON
ROTACION Y BBEO. EN REPETIDAS OCASIONES HASTA 2532M. OBS.REPRESIONAMIENTOS DE
HASTA 2900 PSI.
-
23/01/10
E5 00:00-03:30 (P) C/ BNA 8 1/2" Y SARTA ROT.-NAV. GEOPILOT C/ABG EQ. C/ (DGR- PWD -EWR. ) CONTINUA
REPASANDO DE 2532M. A 2541M. CON ROTACION Y BBEO. EN REPETIDAS OCASIONES,
OBSERVANDO REPRESIONAMIENTOS DE 2000 PSI. A 2950 PSI.VENCIENDO RESISTENCIA,
LEVANTO SARTA A 2522M. BAJO A 2535 M.DONDE ENCONTRO RESISTENCIA FRANCA C/8
TONS. INTENTO VENCER MISMA EN REPETIDAS OCASIONES S/E POR PERSISTIR RESISTENCIA
FRANCA Y REPRESIONAMIENTOS HASTA 2900 PSI. Y FRICCIONES DE HASTA 10 TONS. ****
PREVIA PLAT. DE SEG. OPERN .IND.LIMPIA,SSPA,META CERO , POLITICA Y PRINC. AL
PERS. DE PEMEX,Y CIAS. ELABORO A.S.T. TEMA =PROBAR BOPS. Y CSC. CON PROBADOR
SOLIDO Y PROBADOR DE COPAS.- CLAVE- PE-PP-OP-009-2008
03:30-10:00 (P) LEVANTA BNA 8 1/2" Y SARTA ROTATORIA A 28M. BBEANDO. X E.A. VOL DE ACERO
EXTRAIDO C/ 3 LING. CON CARGO A CIA.HALLIBURTON
10:00-11:30 (P) CON BNA 8 1/2" Y HTTA ROTATORIA A 28 MTS PERS. DE HALLIBURTON RECUPERO
INFORMACION.
11:30-14:30 (P) LEVANTO SARTA A SUPERFICIE REVISANDO HTTAS, OBSERVANDO GEOPILOT CON LIGERO
APLASTAMIENTO EN LA PERIFERIA DE LA PARTE INFERIOR DE LA CAMISA, ANILLOS DE LA
PARTE INTERNA DE FLECHA FUERA DE SU POSICION ORIGINAL (SUELTOS), ASI COMO UNA
EXCESIVA FLEXION EN PARTE MOVIL DE GEOPILOT,A SU VEZ OBSERVO BNA 8 1/2" GEOBIT
SIN DAOS NI DESGASTE ALGUNO, POSIBLE FALLA DE HTTA, DESMANTELA SARTA NAVEGABLE
Y BNA 8 1/2".**NOTA EFECTUO JUNTA DE SEGURIDAD, OPERACION, SSPA META CERO
ACCIDENTES, POLITICA Y PRINCIPIOS A PERS. DE PEMEX, Y CIAS ELABORO AST, TEMA=
CAMBIO DE ARIETES DE PREVENTORES CLAVE-PE-CC-014-2008
14:30-17:30 (P) C/PERSONAL DE CIA. HALLIBURTON ARMO BNA 8 1/2" PDC Y SARTA NAV. EQ. C/ M. DE
FONDO C/VCP. DE 6 3/4" 1.5 #11111810 .- PONY COLLAR 6 3/4" #SC6508 .-
CONTINGENCY SUB 6 3/4" #1083140 .- D.PIN ESTAB.@8 3/8" #1334826 . -LWD FE
COLLAR 6 3/4" (DGR-PWD-EWR ) # MX90234985 H1WGV2R6 .- TM/DM COLLAR 63/4"
LARGO #10917730 .-, PROGRAMO HTA.DIRECC. Y GRADUO MISMA
17:30-18:00 (P) BAJO BNA. PDC. DE 8 1/2" Y SARTA NAV. A63M. Y CON PERSONAL DE CIA.HALLIBURTON
PROBO HTA. DIRECCIONAL C/62 EPM. .- Q=300 GPM. PB.= 1200 PSI.
SATISFACTORIAMENTE.
18:00-24:00 (P) CONTINUA BAJANDO BNA.PDC 8 1/2" Y SARTA NAV. A 2298 M.LLENANDO INT DE TP.
C/500M. Y ROMPIENDO CIRC.C/1000M.DESPLAZANDO NORMAL.
24/01/10
E5 00:00-01:00 (P) CON CARGO A CIA.HALLIBURTON ,CONTINUA BAJANDO BNA.PDC 8 1/2" Y SARTA NAV. A
2504 M.LLENANDO INT DE TP. C/500M. Y ROMPIENDO CIRC.C/1000M.DESPLAZANDO
NORMAL.**** PREVIA PLAT. DE SEG. OPERN .IND.LIMPIA,SSPA,META CERO , POLITICA Y
PRINC. AL PERS. DE PEMEX,Y CIAS. ELABORO A.S.T. TEMA = INSTALACION Y
DESINSTALACION DE CHAROLA ECOLOGICA - CLAVE- PE-EP-OP-014-2008
01:00-02:00 (P) CON CARGO A CIA.HALLIBURTON ,CON PERSONAL DE CIA. GOIMAR DESLIZO 175 M. DE
CABLE DE 1 1/2" AL TAMBOR PRINCIPAL DEL MALACATE
02:00-05:00 (P) CON CARGO A CIA.HALLIBURTON ,CON. BNA. DE 8 1/2" PDC. Y SARTA NAV. DE CIA.
HALLIBURTON REPASA DE 2505 M. A 2550 M. CON ROTACION Y BBEO. EN REPETIDAS
OCACIONES C/ 70 EPM. - Q=343 GPM. - PB.= 2180 PSI. RPM.= 70 .- AMP.= 416/595
05:00-06:30 (P) CON CARGO A CIA.HALLIBURTON , CON MOVIMIENTOS RECIPROCANTES DE SARTA CIRCULO
06:30-12:00 (N) C/ BNA 8 1/2" PDC Y SARTA NAV. EQ. C/ M. DE FONDO 1.5 C/VCP. DE 6 3/4" 1.5
#11111810 .- PONY COLLAR 6 3/4" #SC6508 .- CONTINGENCY SUB 6 3/4" #1083140 .-
D.PIN ESTAB.@8 3/8" #1334826 . -LWD FE COLLAR 6 3/4" (DGR-PWD-EWR ) #
MX90234985 H1WGV2R6 .- TM/DM COLLAR 63/4" LARGO #10917730 . DE CIA.
HALLIBURTON , PERFORA A 2585 M. RECORD .=35 MTS.=3 HRS.= 56 MIN. .-
ULT.4-6 - 7 MIN, PSB 4/5, 60 RPM, 416/535 AMP.
-
12:00-24:00 (N) C/ BNA 8 1/2" PDC Y SARTA NAV. EQ. C/ M. DE FONDO C/VCP. DE 6 3/4" 1.5 . DE
CIA.HALLIBURTON , PERFORA ROTANDO Y DESLIZANDO A 2661 M.- 111 M EN 12:12 HRS,
ULTIMOS 4-3-4 , TOMANDO SURVEY,. ULTIMO = A 2648M ,- ANG.= 24.05 ,- RBO.= N
35.13 W .,-PV=. 2547.05M ,- DESPLAZ.= 595.49M. . AGREGANDO 10 KG/M3 DE CACO3
FINO, Y 10 KG/M3 DE CACO3 MEDIO A TODO EL SISTEMA.**NOTA EFECTUO JUNTA DE
SEGURIDAD, OPERACION, SSPA META CERO ACCIDENTES, POLITICA Y PRINCIPIOS A PERS.
DE PEMEX, Y CIAS ELABORO AST, TEMA= INSTALACION Y DESINSTALACION DE CHAROLA
ECOLOGICA CLAVE-PE-OP-014-2008**NOTA2 SIENDO LAS 14:00 HRS EFECTUO SIMULACRO DE
HOMBRE AL AGUA, Y A LAS 14:30 HRS EFECTUO SIMULACRO DE DERRAMES EN AREA DE
PRESAS**
25/01/10
E5 00:00-01:30 (N) C/ BNA 8 1/2" PDC Y SARTA NAV. EQ. C/ M. DE FONDO 1.5 C/VCP. DE 6 3/4" - DE
CIA. HALLIBURTON , PERFORA ROTANDO Y DESLIZANDO A 2671 M.- **** PREVIA PLAT.
DE SEG. OPERN .IND.LIMPIA,SSPA,META CERO , POLITICA Y PRINC. AL PERS.DE TURNO
DE PEMEX,Y CIAS. ELABORO A.S.T. TEMA =CAMBIO DE VALV.MAESTRA Y/O LATERALES PARA
PZOS CON INYECCION DE BN. - CLAVE- PE-PP-OP-011-2008
01:30-03:00 (N) CIRCULO LIMPIANDO POZO Y MOVIMIENTOS RECIPROCANTES DE SARTA . EN INTER ARMA TP-
5"
03:00-12:00 (N) CONTINUA PERFORANDO C/ BNA 8 1/2" PDC Y SARTA NAV. EQ. C/ M. DE FONDO C/VCP.
DE 6 3/4" 1.5 , DE CIA. HALLIBURTON ,- ROTANDO Y DESLIZANDO A 2744M.
12:00-13:00 (N) CON BNA 8 1/2" PDC Y SARTA NAV EQ. C/ LWD/DGR/PWD. DE CIA.HALLIB. A 2740M,
CIRCULA LIMPIANDO POZO CON MOVIMIENTOS RECIPROCANTES DE SARTA. .**NOTA EFECTUO
JUNTA DE SEGURIDAD, OPERACION, SSPA META CERO ACCIDENTES, POLITICA Y PRINCIPIOS
A PERS. DE PEMEX, Y CIAS ELABORO AST, TEMA= CAMBIO DE VALVULA MAESTRA Y/O
LATERALES PARA POZOS CON INYECCION DE B.N.CLAVE-PE-PP-OP-011-2008
13:00-24:00 (N) CONTINUA PERFORANDO CON BNA 8 1/2" PDC Y SARTA NAV. EQ. C/ LWD/DGR/PWD. DE
CIA.HALLIB. ROTANDO , DESLIZANDO Y TOMANDO SURVEY . A 2824 M,- RECORD.= 274
MTS EN 27:42 HRS,- ULTIMOS(3).- 3- 4- 4- MIN.
26/01/10
E5 00:00-01:30 (N) CON BNA 8 1/2" PDC Y SARTA NAV EQ. C/ LWD/DGR/PWD. DE CIA.HALLIB. A 2824 M,
CIRCULA LIMPIANDO POZO CON MOVIMIENTOS RECIPROCANTES DE SARTA. **** PREVIA
PLAT. DE SEG. OPERN .IND.LIMPIA,SSPA,META CERO , POLITICA Y PRINC. AL PERS.DE
TURNO DE PEMEX,Y CIAS. ELABORO A.S.T. TEMA =INSTALACION Y CALIBRACION DE LA
VALVULA DE SEGURIDAD MARCA CAMERON TIPO B DE 3". - CLAVE- PE-MA-OP-030-2008
01:30-24:00 (N) CONTINUA PERFORANDO ROTADO Y DELIZADO CON BNA 8 1/2" PDC Y SARTA NAV. EQ.C/
LWD/DGR/PWD . DE CIA.HALLIB.. A 2941 M, -RECORD= 391 MTS.- EN 43:05 HRS,
ULTIMOS (3).- 15146 MIIN.
27/01/10
E5 00:00-10:00 (N) EFECT PLAT. DE SEG., OPN, INDUSTRIA LIMPIA, PRINCIPIOS DE SSPA, PROCEDIMIENTOS
CRITICOS QUE SALVAN VIDAS. TEMA.- ESCAREAR TR EN CASCADA C/ DOS O TRES
ESCAREADORES Y ELABORACION DE FORMATO AST C/ PERS INVOLUCRADO. *** CONTINUA
PERFORANDO ROTADO Y DELIZADO C/ BNA PDC 8 1/2" Y SARTA NAV DE CIA HALLIB (MOTOR
FDO. C/ LWD/DGR/PWD) A 2985 MTS.
10:00-11:00 (N) CIRCULA LIMPIANDO POZO CON MOVIM. DE SARTA.
11:00-24:00 (N) CONT. PERFORANDO ROTADO Y DESLIZANDO, CON BNA DE 8 1/2" Y HTAS. DE CIA
HALLIBURTON M. FONDO, C/ LWD/DGR/PWD A 3029 MTS, RECORD= 479 MTS, HRS= 62.35,
ULTIMOS 3= 45-36-39 MIN
28/01/10
E5 00:00-24:00 (N) EFECT PLAT. DE SEG., OPN, INDUSTRIA LIMPIA, PRINCIPIOS DE SSPA, PROCEDIMIENTOS
-
CRITICOS QUE SALVAN VIDAS. TEMA.-" RECUPERACION DE POZOS TAPONADOS" Y
ELABORACION DE FORMATO AST C/ PERS INVOLUCRADO. *** CONTINUA PERFORANDO ROTADO Y
DELIZADO C/ BNA PDC 8 1/2" Y SARTA NAV DE CIA HALLIB (MOTOR FDO. C/
LWD/PWD/MWD) A 3116 MTS C/ RECORD DE 566 MTS EN 80:20 HRS, ULT= 27-20-18
MIN.DESLIZADOS.
29/01/10
E5 00:00-24:00 (N) EFECT PLAT. DE SEG., OPN, INDUSTRIA LIMPIA, PRINCIPIOS DE SSPA, PROCEDIMIENTOS
CRITICOS QUE SALVAN VIDAS. TEMA.-" INSTALACION Y DESMANTELAMIENTO DE EQ. DE
REGISTROS" Y ELABORACION DE FORMATO AST C/ PERS INVOLUCRADO. *** CONTINUA
PERFORANDO ROTADO Y DESLIZADO C/ BNA PDC 8 1/2" Y SARTA NAV DE CIA HALLIB (MOTOR
FDO. C/ LWD/PWD/MWD) A 3232 MTS C/ RECORD DE 682 MTS EN 100:18 HRS, ULT=
7-46-32 MIN
30/01/10
E5 00:00-21:30 (N) EFECT PLAT. DE SEG., OPN, INDUSTRIA LIMPIA, PRINCIPIOS DE SSPA, PROCEDIMIENTOS
CRITICOS QUE SALVAN VIDAS. TEMA.-" PRUEBA DE TUBERIA DE REVESTIMIENTO" Y
ELABORACION DE FORMATO AST C/ PERS INVOLUCRADO. *** CONTINUA PERFORANDO ROTADO Y
DESLIZADO C/ BNA PDC 8 1/2" Y SARTA NAV DE CIA HALLIB (MOTOR FDO. C/
LWD/PWD/MWD) A 3306 MTS C/ RECORD DE 756 MTS EN 114:28 HRS, ULT= 12-15-14
MIN. DONDE SUSPENDE POR MALAS COND CLIM.NOTA : EFECTUO CAMBIO DE PERSL.
SINDICALIZADO ( 07:30-- 08:30 )
E5 21:30-24:00 (N) CIRCULA LIMPIANDO POZO.
31/01/10
00:00-03:00 (N) EFECT PLAT. DE SEG., OPN, INDUSTRIA LIMPIA, PRINCIPIOS DE SSPA, PROCEDIMIENTOS
CRITICOS QUE SALVAN VIDAS. TEMA.-" MOLER ACCS Y CEMENTO" Y ELABORACION DE
FORMATO AST C/ PERS INVOLUCRADO. ***SUSPENDE OPERACIONES POR PRESENCIA DE FRENTE
FRIO # 28, SACO BNA PDC 8 1/2" Y SARTA NAV DE CIA HALLIB A 2498 MTS LIBRE,
LLENANDO EL VOL DE ACERO EXTRAIDO C/ 5 LING (VIENTOS DE 58-60 KM/HR).
03:00-08:00 (N) CON BNA. PDC 8 1/2" Y SARTA NAVEG. A 2498 M. (ZAP. DE TR 9 5/8") ESPERA MEJORES
CONDIC. CLIMATOLOGICAS (RACHAS DE VIENTO DE +/- 55 KM/HR) PARA REANUDAR
OPERACIONES DE PERFN. POR NO PODER MOVER GRUA PARA CAMBIO DE CAJAS DE RECORTE.
NOTA= EN INTER SE DENSIFICARON 40 M3. DE LODO DE E.I. DE 1.34 X 70 GR/CC.
08:00-09:00 (N) CON PNAL DE CIA. GOIMAR EFECTUO REVISION DE TOP DRIVE Y A SISTEMA DE FRENADO DE
MALACATE PRINCIPAL.
09:00-12:00 (N) BAJO BNA. PDC 8 1/2" Y SARTA NAVEG. A 3306 M. LLENANDO Y ROMPIENDO CIRCULACION
CADA 400 M. LIBRE.
12:00-24:00 (N) PERFORA A 3341 M. ROTANDO Y DESLIZANDO, C/ BNA PDC 8 1/2" Y SARTA NAV DE CIA
HALLIB( MOTOR FDO, L-MWD,PWD)C/ CIRCULACION NORMAL, NOTA.- EN INTER SE EFEC
SIMULACRO DE HOMBRE AL AGUA Y HOMBRE LESIONADO
01/02/10
E5 00:00-21:30 (N) EFECT PLAT. DE SEG., OPN, INDUSTRIA LIMPIA, PRINCIPIOS DE SSPA, PROCEDIMIENTOS
CRITICOS QUE SALVAN VIDAS. TEMA.-" RECUPERAR TR S/ SIST MUD-LINE P/ PLAT A.E."
Y ELABORACION DE FORMATO AST C/ PERS INVOLUCRADO. *** CONTINUA PERFORANDO
ROTANDO Y DESLIZANDO C/ BNA PDC 8 1/2" Y SARTA NAV DE CIA HALLIB (MOTOR FDO. C/
LWD/PWD/MWD) A 3375 MTS C/ RECORD DE 825 MTS EN 144:57 HRS, ULT 3= 33-33-102,
(ROTADOS).DONDE OBSERVO REPRESION CON UNA DIF. DE 700 PSI Y SUSPENDE POR
INCREMENTO EN LOS TIEMPOS DE PERF.
21:30-24:00 (N) CIRCULA LIMPIANDO AGUJERO.
02/02/10
E5 00:00-08:00 (N) EFECT PLAT. DE SEG., OPN, INDUSTRIA LIMPIA, PRINCIPIOS DE SSPA, PROCEDIMIENTOS
-
CRITICOS QUE SALVAN VIDAS. TEMA.-" RECUPERAR TR S/ SIST MUD-LINE P/ PLAT A.E."
Y ELABORACION DE FORMATO AST C/ PERS INVOLUCRADO. *** SACO BNA PDC 8 1/2" Y
SARTA NAV DE CIA HALLIB A SUPERF. PARA REVISION DE MISMA; LLENANDO POR E.A. EL
VOL DE ACERO EXTRAIDO. DESGASTE DE BNA. 1-3-WT-NT-X-I-NO-PR. OBSERVANDO UN
DESGASTE DE 1/16" DEL CALIBRE DEL M. DE FONDO.
08:00-09:00 (N) CON APOYO DE PNAL DE CIA. HALLIB. RECUPERO INFORMACION DEMEMORIA DE M/LWD.
09:00-10:00 (N) DESMANTELO SARTA NAVEG. Y ELIMINO MOTOR DE FDO. 6 3/4".
10:00-14:00 (N) CON PERSONAL DE CIA. HALLIBURTON ARMO SARTA NAVEG. CON BNA. GEOBIT 8 1/2" PDC.
N/S= 11334605, CON 4 TOBS. DE 12/32", GEOPILOT 7600 6 3/4", FLEX COLLAR 6 3/4",
DOBLE PION ESTAB. 8 3/4", LWD FE COLLAR (DGR-PWD-EWR), MWD TM/DM COLLAR CORTO
650 SYS, / VCP. 6 3/4", DRILL COLLAR, PROGRAMO HTAS. Y BAJO A 200 M. CONECTANDO
6 TMS. DE TP HW 5", MARTILLO 6 3/4", 11 TMS. DE TP HW 5".
14:00-14:30 (N) CONECTO TOP DRIVE Y CON SUPERVISION DE PNAL. DE CIA. HALLIB. PROBO GEOPILOTO
7600 6 3/4" CON 65 EPM, 360 GPM. LEVANTANDO UNA PRESION DE 1100 PSI; PRUEBA
SATISFACTORIA.
14:30-24:00 (N) CONTINUO BAJANDO BNA. PDC 8 1/2" Y STA.ROT. A 3113 MTS LLENANDO INT DE TP C/ 500
MTS Y ROMPIENDO CIRC C/ 1000 M, DONDE OBSERVO RESISTENCIA, CHECANDO C/ 8 TONS Y
VENCIENDO MISMA C/ROT Y BBEO.
03/02/10
E5 00:00-04:00 (N) EFECT. PLAT. DE SEG, OPN, INDUSTRIA LIMPIA, PRINCIPIOS DE SSPA, PROCEDIMIENTOS
CRITICOS QUE SALVAN VIDAS, TEMA.-" PROTECCION A LAS MANOS" Y ELABORACION DE
FORMATO AST C/PERS INVOLUCRADO EN CADA CAMBIO DE TURNO. *** CONTINUA METIENDO
BNA GEOBIT 8 1/2" Y SARTA ROT DE CIA HALLIB ( GEOPILOT C/ AVG, EQ LWD,
DGR-PWD-EWR, MWD TM/DM) A 3349 MTS DONDE ENCONTRO RESISTENCIA, CHECO C/ 8 TONS Y
REPASO C/ ROT Y BBEO HASTA 3375 MTS VERIFICANDO LIBRE.
04:00-12:30 (N) CONTINUA PERFORANDO CON BNA PDC 8 1/2" Y SARTA NAVEG. DE CIA HALLIB (GEOPILOT C/
LWD/PWD/MWD) A 3402 M. CIRCULACION NORMAL.
12:30-13:30 (N) CIRCULO T.A. LIMPIANDO AGUJERO CON 75 E.P.M. Y Q= 368 GPM; P.BBEO= 2450 PSI.
13:30-24:00 (N) CONTINUO PERFORANDO CON BNA PDC 8 1/2" Y SARTA NAVEG. DE CIA HALLIB (GEOPILOT C/
LWD/PWD/MWD) A 3433 M
04/02/10
E5 00:00-09:30 (N) EFECT. PLAT. DE SEG, OPN, INDUSTRIA LIMPIA, PRINCIPIOS DE SSPA, PROCEDIMIENTOS
CRITICOS QUE SALVAN VIDAS, TEMA.-" PREVENCION DE ACCIDENTES" Y ELABORACION DE
FORMATO AST C/PERS INVOLUCRADO *** CONTINUA PERFORANDO C/ BNA GEOBIT 8 1/2" Y
SARTA ROT DE CIA HALLIB ( GEOPILOT C/ AVG, EQ LWD, DGR-PWD-EWR, MWD TM/DM) A
3472MTS. TOMANDO SURVEY C/30 MTS. Y SUSPENDE POR FALLA DE BBA. NO. 2.
09:30-10:30 (N) CAMBIO A BBA. NO. 1 OBSERVANDO FALLA EN MISMA; LEVANTO SARTA DE 3471 M. A 3461
M. OBSERVANDO INTENTO DE ATRAPAMIENTO DE SARTA TENSIONANDO A 150 TONS. 25 TONS.
S.S.PESO. METIO BBA. Y LEVANTO SARTA; LIBRE.
10:30-11:00 (N) CON BBA. NO. 1 Y BNA. A 3472 M. PNAL DE CIA. HALLIB. INTENTO MANDAR COMANDO SIN
EXITO. EN INTER; PNAL. DE CIA. GOIMAR REPARO BBA. NO. 2 Y PROBO; SATISFACT.
11:00-24:00 (N) CONTINUO PERFORANDO C/ BNA GEOBIT 8 1/2" Y SARTA ROT DE CIA HALLIB ( GEOPILOT C/
AVG, EQ LWD, DGR-PWD-EWR, MWD TM/DM) A 3514 MTS. AUMENTANDO GRADUALMENTE LA
DENSIDAD DE 1.33 GR/CC. A 1.35 GR/CC. Y CONCENTRACION DE 10 KG/M3. A 20 KG/M3.
DE CARBONATO DE CALCIO FINO Y MEDIO.
05/02/10
E5 00:00-09:30 (N) EFECT. PLAT. DE SEG, OPN, IND LIMPIA, PRI NCIPIOS DE SSPA, PROCEDS CRITICOS QUE
SALVAN VIDAS, TEMA.-" RECIBIR TUBERIA DE REVESTIMIENTO( PE-LP-OP-009-2008)" Y
ELABORACION DE AST C/ PERSONAL DE AMBAS GDIAS DE PMX. Y CIAS. DE SE RVI CIOS ***
CONTINUA PERFORANDO C/ BNA GEOBIT 8 1/2" Y SARTA ROT DE CIA HAL LIB ( GEOPILOT
UsuarioResaltado
-
C/ AVG, EQ LWD, DGR- PWD-EWR, MWD TM/DM) A 3540MTS. CON PERDIDA PARCIAL DE 2 - 6
M3/HRA. CONC. DE OBTURANTES= 20 KG/M3 DE CACO3 FINO Y MEDIO.
09:30-11:30 (N) PERS. DIRECC. DE CIA. HALLIB. MAND COMANDO AL GEOPILOT SIN RECIBIR RES
PUESTA. CON BBEO. Y SIN ROTAR OBSERV TENSIN DE 200 TON.(70 TON. S.S.P.). CON
ROTACIN Y BBEO. ESTAB ILIZ AGUJERO Y CIRCUL T.A. LIMPIANDO MISMO.
11:30-24:00 (N) CONT. PERFORANDO C/BNA. GEOBIT 8" PDC Y SARTA ROTATORIA C/GEOPILOT A 3557 MTS.
C/PERDIDA PARCIAL DE 3 M3/HRA DONDE OBS PARO DE ROTARIA E INCREMENTO DE
PRESION, TRABAJO SARTA C/ MOVIMIENTOS RECIPROCANTES HASTA 3540 M LIBERANDO
TORSIONEN Y PRESION EN MISMA.NOTA.-DURANTE EL TURNO, C/ QUIM DE CIA GLOBAL
GENERO 40 M3 DE LODO EN PRESAS.
06/02/10
E5 00:00-02:00 (N) EFECT. PLAT. DE SEG, OPN, IND LIMPIA, PRI NCIPIOS DE SSPA, PROCEDS CRITICOS QUE
SALVAN VIDAS, TEMA.-" CARGA Y DESCARGA DE HTAS Y TUBERIA" Y ELABORACION DE AST
C/ PERSONAL INVOLUCRADO *** CIRCULA LIMPIANDO AGUJERO.
02:00-16:00 (N) CONTINUA PERFORANDO C/ BNA GEOBIT 8 1/2" Y SARTA ROT DE CIA HALLIB (GEOPILOT C/
AVG, EQ LWD, DGR- PWD-EWR, MWD TM/DM) A 3631 MTS. CON PERDIDA PARCIAL DE CIRCN.
DE 1-3 M3/HR, AGREGANDO AL LODO UNA CONCENTRACION DE OBTURANTE DE 20 KG/M3 DE
CACO3 FINO Y MEDIO. *** NOTA= DE 13:30 A 13:45 HRS. SE EFECTUO SIMULACRO DE
CONTROL DE BROTES Y PRESENCIA DE H2S.
16:00-18:00 (P) LEVANTA BNA. 8" Y SARTA ROT. A 3627 M. PARA CONFORMAR AGUJERO Y CIRCULAR PARA
LIMPIAR MISMO DONDE OBSERV PARO DE ROTARIA Y ATRAPAMIENTO DE SARTA. TRABAJ
SARTA CON GOLPES DE MARTILLO(16 GOLPES) HACIA ARRIBA Y TENSIN DE 220 TON.(70
TON. S.S.P.) Y CARGANDO 50 TON. BAJO SU PESO SIN LOGRAR LIBERAR, CIRCULA C/PERD.
DE 1 M3/HRA.***EN INTER PREPAR BACHE DE 8 M3 DE DIESEL CON DESPEGADOR DE
TUBERIA(ECO FREE) CONC. 165 LTS./M3 ***
18:00-18:30 (P) CON BNA. 8" A 3627 M. BBEO. 8 M3 DE DIESEL CON DESPEGADOR DE TUBERIA Y
DESPLAZ MISMO CON 28.2 M3 DE LODO E.I. DE 1.38 GR/CC. LONG. CUBIERTA= 334 M
POR E. ANUL.
18:30-24:00 (P) REPOSA BACHE DESPEGADOR
07/02/10
E5 00:00-04:00 (P) EFECT. PLAT. DE SEG, OPN, IND LIMPIA, PRI NCIPIOS DE SSPA, PROCEDS. CRITICOS QUE
SALVAN VIDAS, TEMA:" INSTALACION Y PBA. DE PREVENTORES CON O SIN POZO ADYACENTE
EN P/A; PE-PP-OP-007-2008" Y ELABORACION DE AST C/ PERSONAL INVOLUCRADO DE
AMBAS GUARDIAS *** TRABAJ SARTA ATRAPADA A 3627 MTS C/ 94 GOLPES DE MARTILLO
HACIA ARRIBA, TENSIN DE 220 TON.(70 TON. S.S.P.) Y TORSIN DE 650 AMPS.
LIBERANDO MISMA.
04:00-15:30 (P) LEVANTA BNA. 8" PDC Y SARTA ROT. DE CIA. HALLIB. DE 3627 A 3490 MTS. CON
ARRASTRE DE 70 TON. S.S.P. Y DE 3490 A 2500 MTS.(ZAP. 9 5/8") LIBRE Y LEVANT
BNA. A SUP. REVISANDO TUBERIA(ENCONTR 15 T.T.P. 5" E-75, 15 T.T.P. 5" X-95
CHUECOS), BNA. EN BUENAS CONDS.***DE 14:00-14:20 HRS. EFECTU SIMULACROS DE
COMBATE DE INCENDIO MAYOR Y ABANDONO DE PLATAFORMA; EMBARCACIONES DE APOYO: BCO.
C. INC. MIRAMAR, DON FAUSTO A 15 MINS. CABO ROJO A 25 MINS. L. ESTELA A 25
MINS.****
15:30-17:30 (P) PERSONAL DIRECC. DE CIA. HALLIB. BAJ INFORMACIN DE MEMORIA DE GEOPILOT, LWD Y
MWD.
17:30-19:30 (P) CON SUPERVISIN DE PERS. DIRECC. CIA. HALLIB. ELIMIN COLLAR CORTO MWD TM/DM,
LWD FE COLLAR, D. PION ESTAB. 8 3/4", FLEX COLLAR 6 3/4" Y GEOPILOT TODO EN
BUENAS CONDICIONES.
19:30-21:30 (N) C/ PERSONAL DE CIA GOIMAR CORTO 34.5 MTS DE CABLE 1 1/2" Y DESLIZO 17 MTS AL
TAMBOR DE MALACTE PRINCIPAL.
UsuarioResaltado
UsuarioResaltado
-
21:30-22:30 (N) ARMO PESCANTE P/ BUJE DE DESGASTE Y RECUPERO MISMO
22:30-24:00 (N) ARMO PROBADOR SOLIDO 13 5/8" Y ALOJO MISMO EN CABEZAL, EN PREP P/ EFECT PBA DE
BOPS.
08/02/10
E5 00:00-06:00 (N) EFECT. PLAT. DE SEG, OPN, IND LIMPIA, PRI NCIPIOS DE SSPA, PROCEDS. CRITICOS QUE
SALVAN VIDAS, TEMA:" MANEJO DE GUSANO PARA RECORTES" Y ELABORACION DE AST C/
PERSONAL INVOLUCRADO DE AMBAS GUARDIAS. ***CON U. DE ALTA Y OPERADOR DE CIA.
PEMSA, EFECTU PBA. DE BOPS 16 3/4" 5M Y C.S.C. DE 2" 15M, PSI Y ARBOL DE
ESTRANG. C/ 3500 PSI, VALVS. DEL STAND PIPE CON 2500 PSI. OK
06:00-07:00 (N) ARM TAPON SOLIDO DE PBA. E INSTAL BUJE DE DESGASTE.
07:00-08:00 (N) ARM BNA. 8" PDC Y SARTA ROTARIA COMPUESTA DE: GEOPILOT 7600 TL181 7.625", FLEX
DRILL COLLAR 6 3/4", D. PION ESTAB. 6 3/4" X 8 3/8", LWD FE COLLAR 6
3/4"(DGR-PWD-EWR) 6 3/4", MWD.TM/DM 6 3/4" CORTO Y V.C.P. 6 3/4"; LOG.= 21.92 M.
08:00-10:00 (N) PERS. DE CIA. HALLIB. PROGRAM HTAS.(GEOPILOT, LWD Y MWD)
10:00-11:30 (N) TERMIN DE ARMAR SARTA ROT. DE CIA. HALLIB. AGREGANDO 1 D. COLLAR 6" Y METI A
59 MTS. DONDE PROB HTAS. DIRECCIONALES CON 350 GPM, PB= 1250 PSI, 350 GPM, PB=
1300 PSI. EN BBAS. # 1 Y 2 OK, CALIBR PROFUNDIDAD.
11:30-22:00 (N) CONTINUA METIENDO BNA. 8" PDC Y SARTA ROTATORIA C/GEOPILOT, LWD Y MWD DE CIA.
HALLIB. A 3000 MTS. ELIMINANDO 15 T.T.P. 5" E-75 + 18 T.T.P 5" X 95 DAADOS
(CHUECOS), LLENANDO SARTA C/ 500 MTS. C/LODO E.I. DE 1.38 X 70 Y ROMP. CIRC.
C/1000 MTS.
22:00-24:00 (N) CIRCULA HOMOGENIZANDO COLUMNAS
09/02/10
E5 00:00-12:00 (N) EFECT. PLAT. DE SEG, OPN, IND LIMPIA, PRI NCIPIOS DE SSPA, PROCEDS. CRITICOS QUE
SALVAN VIDAS, TEMA:"MANEJO DE RECORTES EN EL EQ DE PERFORACION" Y ELABORACION
DE AST C/ PERSONAL INVOLUCRADO DE AMBAS GUARDIAS. **CONTINUA METIENDO SARTA ROT
DE CIA HALLIB( GEOPILOT CON ABG, RG, DGR-PWD-EWR, MWD TM/DM) A 3149 MTS DONDE
OBS. RESISTENCIA C/8 TONS Y CONTINU METIENDO C/ ROT Y BBEO. HASTA 3574 MTS.****
NOTA: REVIZ CABLE DE 1" DEL MALACATE PRINCIPAL(PRIMER CAMA EN EL TAMBOR
OBSERVANDO VARIOS HILOS DE LOS TORONES FISURADOS).
12:00-14:00 (N) CIRCUL T.A. PARA LIMPIEZA DE AGUJERO.
14:00-17:00 (N) LEVANT BNA. 8" PDC Y SARTA ROTATORIA DE 3574 M. A 2500 M. ( DE 3574 A 3546
M.C/ ROT. Y BBEO. Y DE 3546 A 3489 M. CON ARRASTRE DE 32 TON. Y POSTERIORMENTE
LIBRE A LA ZAPATA )..
17:00-20:00 (N) CON PERSONAL DE CIA. COLS-GOIMAR CORTO 97 MTS. Y DESLIZO 65 M. DE CABLE DE 1
1/2" AL TAMBOR DEL MALACATE PRINCIPAL Y DA MANTTO. AL TOP DRIVE.
20:00-24:00 (N) BAJA BNA. PDC DE 8 1/2" CON SARTA ROTATORIA C/GEOPILOT LWD/MWD E CIA. HLB A 3432
MTS.
10/02/10
E5 00:00-01:00 (N) EFECTUO PLATICA DE SEGURIDAD OPN, INDUSTRIA LIMPIA PRI NCIPIOS DEL SSPA,
PROCEDIMIENTOS CRITICOS CON EL TEMA: "MANEJO DE RECORTES EN EL EQ DE
PERFORACION" Y ELABORACION DE AST C/ PERSONAL INVOLUCRADO. CONTINUA BAJANDO A
3489 MTS.
01:00-02:00 (P) CONTINUA BAJANDO REPASANDO CADA LINGADAA 3602 MTS. AL CONECTARSE LA SIGUIENTE
LINGADA OBS. SARTA ATRAPADA INTENTO TRABAJAR MARTILLO S/E. HASTA 70 TONS SSP.
(WB= 105 TONS.)
02:00-04:00 (P) CON SARTA ATRAPADA A 3602 MTS. Y SARTA TENSIONADA A 175 TONS, ( 30 TONS.. SSP )
PREPARO Y BBEO. 9 M3. BACHE DESPEGADOR DIESEL- ECOFREE CON UNA CONCENTRACION
DE 170 LTS/M3. DESPLAZANDO MISMO C/ 72 EPM. Y PB. =2500 PSI. C/ 1594 EMB. (
7827 GAL.) QUEDANDO BACHE DE 3602M . A 3212M. CUBRIENDO 390 M. LINEALES.
UsuarioResaltado
-
04:00-08:00 (P) CON SARTA TENSIONADA REPOSO BACHE DESPEGADOR
08:00-10:30 (P) TRABAJO SARTA ATRAPADA TENSIONANDO HASTA 245 TONS. E INTENTO CARGAR MARTILLO EN
REPETIDAS OCACIONES S/E. COLOCO SARTA EN SU PESO APLICO TORQUE ( 500 AMP.) E
INICIO BBEO. EN DIRECTO CIRCULANDO BACHE ,TENSIONO HASTA 135 TONS. OBSERVANDO
ROTACION DE SARTA Y CAIDA DE PRESION DE 2200 PSI. HASTA 1200 PSI. LEVANTO SARTA
OBSERVANDO PERDIDA DE PESO DE +- 40 TONS.
10:30-24:00 (P) LEVANT SARTA A SUP. OBSERVANDO DEGOLLADO EL PION DEL TRAMO. # 3 DE LA LING. #
26 DE T.P. 5" E-75, QUEDANDO COMO PEZ ( BNA. GEOBIT 8 1/2"+GEOPILOT+ FLEX
COLLAR 6 3/4+D.PIN.ESTAB.6 3/4"+LWD -DGR-PWD-EWR+MWD-TM/DM+VCP.+1 D.COLLAR +6
T.HW.+1MARTILLO+11 T.TP.HW.+( 77 TRAMOS DE TP. E-75. 25.6 #. LONGITUD TOTAL DE
PEZ= 934.21 M. BOCA DE PEZ TEORICA = 2667.79 M., BBEANDO. POR E.A.VOL. DE
ACERO EXTRAIDO . REVISANDO JUNTAS EN CADA LINGADA POR PERSONAL DE INSPECCION
TUBULAR. ELIMINANDO 31 TRAMOS DE TP.5" E.75 25.6 # Y BAJA TP FRANCA 5" X-95 A
978 MTS. ELIMINANDO 6 LINGS. (18 TRAMOS DE TP.X-95 - 25.6 # EN MAL ESTADO.
11/02/10
E5 00:00-15:00 (P) EFECTUO PLATICA DE SEGURIDAD OPN, IND. LIMPIA PRINC. DEL SSPA, PROC. CRITICOS,
TEMA: "PROC. PARA PRUEBA DE PREVENTORES CON TOP DRIVE, VALV. DE PIE Y C.S.C." .
ELAB.AST C/ PERS.DE PEMEX Y CIAS. Y CONTINUA BAJANDO A 1120 MTS. ELIMINANDO 33
TRAMOS DAADOS DE TP.5" X-95 25.6 #= Y ARMO 14 LINGS.(42 TMS.) TP.5" G-105
-25.6 #, MIDIENDO, CALIBRANDO C/ 2 1/2" . HASTA 1321 MTS. Y POSTERIORMENTE
LEVANTO TP FCA. A 500 MTS.
15:00-24:00 (P) CON TP FRANCA A 500 MTS. ESPERA TUBERIA DE PERFORACION.
12/02/10
E5 00:00-14:00 (S) EFECTUO PLATICA DE SEGURIDAD OPN, IND. LIMPIA PRINC. DEL SSPA, PROC. CRITICOS,A
PERSONAL DE PEMEX Y CIAS. Y ELABORO AST. TEMA: "PROC. PARA PRUEBA DE
PREVENTORES CON PROBADOR SOLIDO Y/O PROBADOR DE COPAS.CLAVE= PE-PP-OP-009-2008 .
Y CON TP FRANCA DE 5" ESTACIONADA A 500 MTS. ESPERA MEJORES CONDICIONES
CLIMATOLOGICAS
14:00-15:30 (S) EN ESPERA DE MEJORES CONDICIONES CLIMATOLOGICAS , PARA RECIBIR TUBERIA DE
PERFORACION Y HW. 5" . PROCEDENTE DE D.BOCAS . LEVANTA TP.FRANCA A SUPERFICIE.
15:30-24:00 (P) ARMA MOLINO PLANO DE 8 12" T-MCMP NO. 750940 5 ALETAS CON 5 ORIFICIOS DE 15/16",
3 DC DE 6 1/2", 12 TRAMOS DE TP DE 5" X-95, MARTILLO DE 6 3/4"X 23/4" NO. DE
SERIE 675591SEGUIDO DE TP DE 5" X-95 Y G-105 A 2491 MTS. VERIFICO PESOS 102 -
93 - 93 TONS. CONTINUA BAJANDO CON BBEO. Y ROTACION A 2127 MTS DONDE OBSERVA
INCREMENTO DE TORQUE DE 150 A 500 AMPS REPASA INTERVALO EN 6 OCACIONES DE 2521 A
2527 MTS. CONTINUA BAJANDO REPASANDO CON BBEO Y ROTACION A 2577 MTS. LIBRE.
13/02/10
E5 00:00-03:30 (P) EFECTUO PLATICA DE SEGURIDAD OPN, IND. LIMPIA PRINC. DEL SSPA, PROC. CRITICOS,
TEMA: "CAMBIO DE ARIETES DE PREVENTORES" CLAVE= PE-CS-OP-014-2008 .,ELABORO AST
C/ PERS. DE PEMEX/ CIAS. Y CONTINUA BAJANDO CON MOLINO DE 8 1/2" REPASANDO CON
ROTACION Y BBEO. HASTA 2667.15 MTS. DONDE TOCO B. DE PEZ CON 3 TONS. VERIFICO
TOCANDO BOCA CON 20 RPM Y 300 AMPS. Y LEVANTO A 2666.80 MTS.
03:30-05:00 (P) CON MOLINO DE 8 1/2" T-MCMP 5 ALETAS Y 5 ORIFICIOS DE 7/8" A 2666.80 MTS.
CIRCULA CON MANGUERA AUXILIAR CON 70 EPM Y 900 PSI. Y REACOMODA 6 LINGADAS EN
CHANGUERA
05:00-06:30 (P) LEVANTA MOLINO DE 8 1/2" CON ROTACION Y BBEO.DE 2667 A 2558 MTS . OBSERVANDO
FRICCIONES DE 5 A 10 TONS. . Y DE 2595 A 2588 MTS. DE 15 TONS. POSTERIORMENTE
DE 2577 A 2505 MTS. LIBRE.
06:30-08:30 (P) CON MOLINO DE 8 1/2" EN LA ZAPATA CIRCULA CON MANGUERA AUXILIAR CON 70 EPM Y PB=
-
1180 PSI. Y TERMINA DE REACOMADAR 15 LINGS. EN PEINES DE CHANGUERA.
08:30-11:30 (P) CONTINUA LEVANTANDO MOLINO DE 8 1/2" A 1240 M. BBEANDO. POR E.A . VOL. DE ACERO
EXTRAIDO ,C/5 LING.
11:30-12:00 (P) EFECTUO CAMBIO DE GUARDIA DE PERSONAL SINDICALIZADO
12:00-12:30 (P) EFECTUO PLATICA DE SEGURIDAD, OPN, IND. LIMPIA PRINC. DEL SSPA, META CERO ,
PROC. CRITICOS,A PERSONAL DE PEMEX Y CIAS. ELABORO AST. TEMA: "CAMBIO DE ARIETES
DE PREVENTORES" CLAVE= PE-CS-OP-014-2008
12:30-16:00 (P) LEVANTO MOLINO DE 8 1/2" A SUP. BBEANDO. POR E.A . VOL. DE ACERO EXTRAIDO C/5
LING. OBSERVANDO HUELLAS DE TRABAJO EN AREA DE ATAQUE Y ELIMINO MISMO
16:00-22:00 (P) ARMO PESCANTE BOWEN O.S. 8 1/8"O.D. S-150 N 759190 DE CIA. WEATHERFORD C/ CUAS
DE CANASTA 6 3/8" N NP9272 C/ CONTROL 6 3/8" Y MARTILLO 6 3/4" SOBRE 12
TRAMO DE T.P 5" X-95 , Y METIO A 2666.15 M. ( 1 M ARRIBA DE BOCA DE PEZ. )
22:00-23:00 (P) CIRCULO LIMPIANDO BOCA DE PEZ C/ 60 E.PM. P.B= 800 PSI.Y CHECO PARAMETROS ARRIBA
105 TON, ABAJO = 96 TON , ESTATICA 96 TON. CON 20 E.P.M P.B = 200 PSI., 10 RPM.
Y 200 AMP.
23:00-24:00 (P) OPERO PESCANTE BAJANDO A 2667.15 M CON BOMBEO DE 20 E.P.M Y P.B = 200 PSI. Y 10
RPM. Y 200 AMP. ENCHUFANDO MISMO HASTA 2667.60 M. OBSERVANDO INCREMENTO DE
PRESION HASTA 995 PSI.CARGANDO 3 TON. SUSPENDIENDO ROTACION Y BOMBEO,TENSIONO
VERIFICANDO AGARRE DE PEZ HASTA 175 TON ( 65 TON SSP.) DONDE OBSERVO GOLPE DE
MARTILLO CON PERDIDA DE PESO Y CAIDA DE PRESION A 200 PSI.
14/02/10
E5 00:30-01:00 (P) BAJO PESCANTE EN 4 OCASIONES MAS ENCONTRANDO BOCA DE PEZ A 2669.77 M DESLIZADA
2.62 M ) OPERO MISMO CARGANDO DE 3 A 5 TON. OBSERVANDO AGARRE DE PEZ CON
INCREMENTO DE PRESION DE 500 A 1970 PSI. CON 61 E.P.M OBTENIENDO SEAL EN HTAS
DE CIA. HALIBURTON Y CIRCULACION NORMAL. SUSPENDIO BOMBEO Y TENSIONO SARTA HASTA
145 TON. ( 35 TON. SSP.) DESPRENDIENDOSE EL PEZ QUEDANDO SARTA EN PESO
INICIAL( 110 TON)
01:00-02:00 (P) ENCHUFO PESCANTE EN BOCA DE PEZ , BOMBEO Y DESPLAZO BACHE DESPEGADOR DE 9 M3
DIESEL - ECO FREE CONC. DE 200 L/ M3 CON 29 M3 DE LODO 70 E.P.M. P.B. = 2000
PSI. E.I. 1.38 X 70 CUBRIENDO 390 M DE LONG. EN E.A.
02:00-04:00 (P) TENSIONO SARTA HASTA 145 TONS TRABAJANDO MARTILLO Y OBS. DESPRENDIMIENTO DE PEZ,
INTENTO CONECTARSE CON 5 RPM Y 10 EPM, PB= 25 PSI Y TORQ= 150 AMPS. HASTA
2669.77 MTS INCREMENTANDOSE PB= DE 25 A 350 PSI, PAR ROT. CARGO 2 TONS. Y
TENSIONO A 140 TONS.(30 TON. SSP) Y OBSERV DESPRENDIMIENTO DE PEZ REPITIO EN
TRES OCACIONES S/E.
04:00-12:00 (P) SAC PESCANTE B.O.S., S-150 DE 8 1/8" A SUP. Y ELIMIN MISMO, REVISO ,
OBSERVANDO FRACTURADO EN 3 PARTES EL CONTROL FRESADOR , CUERDAS DE GUIA
LAVADAS Y ROTO EL O RING . ****NOTA - DE 09:30- A - 10:00 HRS. EFECTUO CAMBIO
DE GUARDIA DE PERSONAL DE CIAS.
12:00-13:00 (P) IMPARTIO PLATICAS DE SEGURIDAD, OPERACION, IND, LIMPIA SSPA , META CERO ,SAFE
STAR A PERSONAL DE PEMEX Y CIA. ELABORO AST. TEMA : INSTALACION Y
DESINSTALACION DE CHAROLA ECOLOGICA PROC: PE-EP-OP-014-2008 Y LIMPIEZA EN PISO
DE PERFORACION.
13:00-18:30 (P) ARMA TP. HW. DE 5" 50 # ,9 TMOS. (3 LING.) MIDIENDO , CALIBRANDO C/ 2 1/2" Y
APRETANDO TXT ,Y BAJA A 500 M.
18:30-22:30 (S) CON TP FRANCA A 500 MTS ESPERA PESCANTE DE 8 1/4".
22:30-24:00 (P) CON PERSONAL DE CIA. WEATHERFOR DESCONECTO Y ARMO PESCANTE B.O.S. DE 8 1/4" NO.
763107 TIPO ESPIRAL PARA TP DE 6 3/8" Y LEVANTA TP FCA. Y HW DE 5" A 118 MTS.
NOTA: RECIBO PESCANTE DE 81/4" DEL BCO. STAVANGER 22:15 HRS.
15/02/10
UsuarioResaltado
-
E5 00:00-01:00 (P) IMPARTIO PLATICAS DE SEGURIDAD, OPERACION, IND, LIMPIA SSPA , CON EL TEMA:
CAMBIO DE VALVULA MAESTRA Y/O LATERALES CON INYECCION DE BN" PE-PP-OP-011-2008.
Y ELABORO AST CON EL PERSONAL DE TURNO PEMEX Y CIA. Y LEVANTO TP FRANCA A
SUPERFICIE.
01:00-07:30 (P) CON PERSONAL DE CIA. WEATHERFORD ARMO PESCANTE B. O. S. S-150, TIPO: FS. DE 8
1/4", # 763107, CON CUAS ESPIRAL 6 3/8", NO. A-5056-204 Y BAJO A: 2669 MTS.
DONDE CHECO BOCA DE PEZ.
07:30-08:00 (P) CON PESCANTE A 2668.5MTS. CIRCULO EN BOCA DE PEZ.
08:00-19:00 (P) CON TEC. DE CIA. WEATHERFORD OPERO PESCANTE DE 8 1/4" SOBRE BOCA DE PEZ
ENCHUFANDO MISMO , VERIFICO AGARRE DE PEZ TENSIONANDO HASTA 165 TONS. CIRCULO
C/ 20 E.P.M. ,Q=98 GPM. , P.B. 120 PSI., SIN OBSERVAR INCREMENTO DE PRESION .
TRABAJA SARTA TENSIONANDO HASTA 265 TONS. 110 TONS. S.S.P. Y CARGANDO HASTA 45
TONS. S.S.P., OPERANDO MARTILLO ( 170 GOLPES HACIA ARRIBA Y 145 HACIA ABAJO
),SIN RECUPERAR PEZ. CON SARTA TENSIONADA A 265 TONS. REACOMOD MATERIALES Y
EQ. DE SERAP EN PATIO DE TUBERIAS.
19:00-24:00 (P) EFECTUA PREPARATIVOS PARA PUNTO LIBRE, ELIMINANDO ELEVADOR DE 5" 18, ELIMINO
GAFAS Y CON PERSONAL DE GOIMAR ELIMINO GRABER DEL TOP DRIVE E INSTALO GAFAS Y
ELEVADOR.
16/02/10
E5 00:00-01:30 (P) EFECTUO PLATICAS DE SEGURIDAD INDUSTRIA LIMPIA Y SSPA CON EL TEMA: INSTALACION Y
CALIBRACION DE LA VALVULA DE SEGURIDAD MARCA CAMERON TIPO "B" DE 3" 5M. Y LLENO
FORMATOS AST. Y CON PERSONAL DE SERAP INSTALO EQUIPO AL 100 %.
01:30-03:30 (P) CON PERSONAL DE SERAP ARMO HTA. CALIBRADORA DE 2.250" Y CONTRAPESO DE 2.125"
CON LONG. DE 2.96 MTS, Y BAJA A 2858 MTS. DONDE OBSERVA RESISTENCIA FCA. Y
LEVANTA A SUPERFICIE.
03:30-05:30 (P) ARMA HTA. CALIBRADORA DE 1.750" CONTRAPESO CON LONG. DE 2.96 MTS, Y BAJA A
2858 MTS. DONDE OBSERVA NUEVAMENTE RESISTENCIA FCA. Y LEVANTA A SUPERFICIE.
05:30-10:00 (P) C/ PERSONAL DE REGISTROS SERAP ,ARMO Y BAJO HTA. FPIT. DE 1.375" PARA
DETERMINAR PUNTO LIBRE CON LONG. DE 4.24 MTS. Y REALIZO ESTACIONES A 2593M. Y
2856 M. DETECTANDO 100 % LIBRE .RECUPERO HTA. A SUPERFICIE Y DESMANTELO MISMA
10:00-11:30 (P) ELIMINO TUBO PONY 5" ,ELEVADOR DE 5" 18 Y GAFAS LARGAS.
11:30-13:30 (P) CON PERSONAL DE CIA. GOIMAR INSTALO GRABER Y DOBLE PION A TOP DRIVE TORQUEANDO
MISMO .**** PREVIA PLATICA DE SEG. OPEN, IND, LIMPIA SSPA , META CERO, SAFE
STAR A PERS. DE PEMEX Y CIA. ELABORO AST. TEMA : DIFUSION DE INCIDENTES Y
ACCIDENTES, PLATF.=ZAAP-A EQ. 4049 RECIO 3335 .- Y PLATF.=EP-01 EQ.9093 RECIO
3294
13:30-15:00 (P) INSTALO GAFAS CORTAS, ELEVADOR DE 5" 18 Y TUBO PONY DE 5" Y CONECTO A TOP
DRIVE.
OPERACION DE STRING SHOT ,
15:30-17:00 (P) REAPRETO TUBERIA C/SARTA TENSIONADA A 125 TONS. 20 TNS. SSP. APLICANDO 8
VUELTAS A LA DERECHA TRANSMITIENDO TORQUE TENSIONANDO SARTA DE 125 A 160 TONS.
BAJO SARTA A 125 TONS. REGRESANDO 5 1/4 DE VUELTA , REPITIO OPERACION EN 3
OCASIONES MAS . TENSIONO SARTA A 150 TONS. Y GIRO 6 VUELTAS A LA IZQ.
TRANSMITIENDO TORQUE REGRESANDO 3/4 DE VUELTA, REPITIENDO EN 3 OCASIONES LA
OPERACION, SENTANDO EN CUAS C/ 125 TONS. SOSTENIENDO TORQUE IZQUIERDO.
17:00-21:00 (P) CON PERSONAL DE SERAP ARMO CARGA DE CORDON DETONANTE EXPLOSIVO RDX 80 GR/FT.
VARILLA C/ 6 HILOS DE 80 GR/FT. = 480 GR/FT. LONG.= 7.36 M. DIAM.MAX. 2.13 "
BAJANDO SONDA A 2849 M. DETONO MISMA Y SACO A SUPERFICIE OBS. CORDON EXPLOSIVO
100 % DISPARADO.
21:00-21:30 (P) TRABAJO SARTA LEVANTO DE 125 A 130 TONS. BAJO A 112 TONS. Y LEVANTO NUEVAMENTE A
-
135 TONS. DONDE OBS. LIBERAMIENTO DE SARTA QUEDANDO EN EL INDICADOR 107 TONS.
ROMPIO CIRCULACION CON 25 EPM Y PB= 55 PSI. OBSERVANDO LIBRE CIRCULACION.
21:30-24:00 (P) LEVANTA PESCANTE DE 8 1/4" A 1638 MTS. REAPRETANDO TRAMO POR TRAMO POR OBSERVAR
JUNTAS FLOJAS.
17/02/10
E5 00:00-07:30 (P) EFECTUO PLATICA DE SEGURIDAD POLITICA, OPERACION, PRINCIPIOS DEL SSPA, IND.
LIMPIA CON EL TEMA: "ESCAREAR TR'S EN CASCADA CON DOS O TRES ESCAREADORES" Y
LLENO FORMATO AST. *** CONTINUA LEVANTANDO PESCANTE B.O.S. S-150 TIPO FS DE 8
1/4" A SUPERFICIE OBS. FALTA DE PESCANTE 1.22 + 6 H.W. DE 5" - 55.65 + MARTILLO
6.45 MTS. = LONG. DE PEZ 63.32 MTS. B. PEZ 2605.94 MTS. APRETANDO TRAMO POR
TRAMO POR VENIR JUNTAS FLOJAS.
07:30-08:30 (P) REALIZO LIMPIEZA EN PISO DE PERFORACION Y CAMBIO DADOS A LLAVES DE FUERZA.
08:30-11:30 (P) BAJA 9 TRAMOS DE T.P.H.W. DE 5" SEGUIDO DE TP DE 5" X-95 -25.6 # A 400 MTS.
REAPRETANDO T X T DE H.W. Y X-95 . PARA STRING SHOT.
11:30-14:00 (P) CON PERSONAL DE CIA. GOIMAR DESLIZO 17.5 MTS. DE CABLE DE 1 1/2" AL TAMBOR DEL
MALACATE PRINCIPAL **** PREVIA PLATICA DE SEG.OPN., POLITICA, PRINCIPIOS
DEL SSPA, IND. LIMPIA,META CERO., ELABORO AST. ***TEMA = PROCEDIMIENTO P/
ESCARIAR TR. EN CASCADA CON DOS O TRES ESCARIADORES" PE-PP-OP-008-2008
15:20-20:30 (P) CONTINUA BAJANDO H.W. 5" FRANCA CON TP 5" X-95 Y G-105 A 2604 MTS. REAPRETANDO
TXT PARA PREPARACION DE STRING SHOT CHECO PESOS ARRIBA 106 EST. 96 ABAJO 106
TONS.
20:30-22:00 (P) CONTINUA BAJANDO A 2605.91 MTS CON 1/2 TONS. DONDE TOCO B. DE PEZ LEVANTO A
2605 MTS. Y CON BBA. DEL EQUIPO BBEA. CON 71 EPM Y PB= 910 PSI. VERIFICO PESOS
ARRIBA 107 EST. 95 ABAJO 97 TONS.
22:00-24:00 (P) BAJO PION DE H.W. A 2605.91 MTS CON 1/2 TON Y CONECTO A BOCA DE PEZ CON 7
VUELTAS A LA DERECHA Y REAPRETO JUNTA CON 20 000 LBS-P, TRANSMITIO TORQUE DE 25
000 LBS-P CON 6 VUELTAS Y TRABAJO TORSION DE 130 A 175 TONS. REGRESANDO 5.5
VUELTAS, GIRO CON 10.5 VUELTAS Y TORQUE DE 30 000 LBS-P Y TRABAJO TORSION DE 130
A 210 TONS. Y REGRESO 3.5 VUELTAS REPITIO EN 3 OCASIONES SIN ADMITIR. ROMPIO
CIRCULACION E INTENTO CIRCULAR OBSERVANDO REPRESIONAMIENTO CON 13 EPM PB= 1000
PSI.
18/02/10
E5 00:00-01:00 (P) EFECTUO PLATICA DE SEGURIDAD OPERACION, POLITICA PRINCIPIOS DEL SSPA IND. LIMPIA
CON EL TEMA : CRITERIOS TECNICOS PARA APLICAR LA MOTIVACION PROGRESIVA A TRAVEZ
DEL REFORZAMIENTO DE ACTITUDES PREVENTIVAS. PREPARA SARTA PARA STRING SHOT CON
11.5 VUELTAS CON 20 000 LBS-P A LA IZQUIERDA Y TRABAJO SARTA DE 160 A 200
TONS. Y SENTO EN CUAS CON 160 TONS.
01:00-01:30 (P) EFECTUO JUNTA DE SEGURIDAD DE OPERACION DE STRING SHOT CON EL PERSONAL
INVOLUCRADO.
01:30-06:00 (P) CON PERSONAL DE SERAP ARMA HTA. STRING SHOT DE 2 1/8" Y EXPLOSIVO RDX 80 GR/FT
VARILLA CON 6 HILOS DE 80 GR/FT Y LONG. DE 5.54 MTS. BAJO A 2849 MTS. Y EFECTUO
DISPARO Y LEVANTO A SUP. NOTA.: OBSERVA CARGA EXPLOSIVA 100 %. Y ELIMINO EQUIPO
AL 100 %.
06:00-08:30 (P) CONECTO TUBO PONY DE 5" Y TENSIONO SARTA DE 160 TONS. A 175 TONS.DONDE OBSERVA
LIBERAMIENTO DE SARTA ,OBSERVANDO 105 TNS. DE PESO EN EL INDICADOR, BAJO Y
CONECTO NUEVAMENTE CON 15 VUELTAS A LA DERECHA Y REAPRETO CON 6.5 VUELTAS A LA
DERECHA, TRANSMITIENDO TORSION DE 160 TONS. A 225 TONS. SENTO SARTA EN CUAS CON
SARTA TENSIONADA A 175 TONS. Y DESCONECTO TUBO PONY DE 5"
08:30-10:30 (P) CON SARTA TENSIONADA EN 170 TONS. Y PERSONAL DE SERAP ARMO Y BAJO BARRA
CALIBRADORA DE 2 1/4" ( LONG.= 2.96 MTS. PESO = 180 LBS. ) A 2858 MTS. DONDE
-
OBSERVO RESISTENCIA , Y LEVANTO BARRA CALIBRADORA A SUPERFICIE DESMANTELANDO
MISMA.
10:30-23:30 (P) INICIO PREPARATIVOS PARA ARMAR CARGA COLAIDING DE 2 1/8" PARA DISPARO,
TENSIONANDO SARTA A 205 TONS. OBSERVANDO BRINCO DE LA MISMA QUEDANDO PESO EN
INDICADOR 107 TONS. TENSIONO NUEVAMENTE SARTA OBSERVANDO PESO LIBRE EN
INDICADOR DE 125 TONS. (20 TONS. DE PESO RECUPERADO ) CONTINUA LEVANTANDO
PESCANTE A SUPERFICIE ELIMINO CON PERSONAL DE CIA. WEATHERFORD Y RECUPERO 287.06
MTS DE PEZ ( 10 LINGS. E-75). QUEDANDO DE PEZ BNA. 8 1/2" SARTA NAV., 1 DC 6
1/2", 17 H.W., 15 LINGS. Y 2 TRAMOS DE TP 5" E-75 (LONG. 647.15 MTS), B. DE
PEZ A: 2954.85 MTS. OBS. SALIDA DEL TRAMO CON PION DEGOLLADO. LLENANDO POR
E.A. VOL. DE ACERO EXTRAIDO. REVISANDO VISUALMENTE JUNTA POR JUNTA . ***DE 16:20
A 16:50 HRS. EFECTUO SIMULACRO DE PERSONA LESIONADA Y HOMBRE AL AGUA CON APOYO
DE LANCHA LINDA F -EN 30 MIN. Y DERRAME DE HIDROCARBUROS C/APOYO DE ISLA
COZUMEL EN 90 Y BRITANIA EN 40
23:30-24:00 (P) DESPEJO Y LIMPIO AREA DEL PISO DE PERFORACION Y QUEBRO 2 LINGS. DE TP DE 5"
E-75.
19/02/10
E5 00:00-03:30 (P) CONTINUA QUEBRANDO 8 LINGADAS DE TP RECUPERADA DE E-75 DE 25.6 LB/P DESPEJO Y
LIMPIO PISO DE PERFORACION. CON SOLDADOR HABILITO TUBO AGUJA DE 3 MTS DE 5"
E-75 25.6 LB/P. **** PREVIA PLATICA DE SEG.OPN., POLITICA, PRINCIPIOS DEL
SSPA, IND. LIMPIA,META CERO.CON PERSONAL DE PEMEX Y CIAS. Y ELABORO AST.
***TEMA = INSTALACION Y DESMANTELAMIENTO DE EQUIPOS DE REGISTROS .CLAVE-
PE-SP-OP-047-2008.*** NOTA: 1:00 RECIBE DEL BARCO DON RODRIGO COMISARIA
03:30-10:30 (P) BAJO TUBO AGUJA DE 5" A 2715 MTS. ROMPIENDO CIRCULACION
10:30-11:30 (P) CON TUBO AGUJA A 2715 MTS. BBEO. 4 M3.DE BACHE VISCOSO DE 1.38 GR/CC X 302 SEG.
Y DESPLAZO MISMO
11:30-12:00 (P) LEVANTO TUBO AGUJA DE 5" DE 2715 MTS. A 2600 MTS.
12:00-15:00 (P) CON TUBO AGUJA A 2600 MTS. CIRCULO HOMOGENIZANDO COLUMNAS, EN INTER LIMPIO
PRESAS DE BACHE N6 Y LINEAS DE SUCCION Y DESCARGA **** PREVIA PLATICA DE
SEG.OPN., POLITICA, PRINCIPIOS DEL SSPA, IND. LIMPIA,META CERO.CON PERSONAL DE
PEMEX Y CIAS. Y ELABORO AST. ***TEMA = INSTALACION Y DESMANTELAMIENTO DE
EQUIPOS DE REGISTROS .CLAVE- PE-SP-OP-047-2008 ***NOTA = DE 14:00 A 14:30
EFECTUO SIMULACRODE ABANDONO DE PLATAFORMA, CON APOYO DE EMBARCACIONES,
MANTARRAYA EN 5 E ISLA BLANCA EN CERCANIAS.
15:00-15:30 (P) EFECTUO PLATICA DE SEGURIDAD Y OPERACION CON PERSONAL INVOLUCRADO EN LA
CEMENTACION DE T X C.
15:30-16:30 (P) INSTALO VALVULA DE PIE Y LINEA DE 2" VERIFICO FLUJO, CONECTO Y APRETO Y CON
UNIDAD DE ALTA PROBO LINEAS CON 3000 PSI. OK.
16:30-18:30 (P) CON PERSONAL DE CIA. PEMSA PREPARA BACHES EN PRESA NO. 6.
18:30-23:00 (P) BOMBE 4.15 M3 DE BACHE LAVADOR PARA LODO BASE ACEITE CON UNA DENSIDAD DE 1.02
GR/CC Y 5.53 M3 DE BACHE ESPACIADOR PARA LODO BASE ACEITE CON DENSIDAD DE 1.5
GR/CC A 3 BPM. PB= 500 A 450 PSI. MEZCLO Y BOMBEO 53.21 BL , 8.46 M3 (11.74
TONELADAS) DE CEMENTO H SOLO MAS ADITIVOS LIQUIDOS CON UNA DENSIDAD DE 1.95
GR/CC A 3-4 BPM Y PB DE 300-560 PSI UTILIZANDO, 234.80 LITROS DE SISTEMA LIQUIDO
DE CONTROL DE GAS CON UNA TEMPERATURA DE DISEO DE 98C POSTERIORMENTE SE
BOMBEO 1.85 M^3 (11.63 BL) DE BACHE ESPACIADOR PARA LODO BASE ACEITE CON UNA
DENSIDAD DE 1.50 GR/CC A 4.2 BPM CON UNA PB DE 200 PSI, SEGUIDOS DE 1.39 M3
(8.74 BL) DE BACHE LAVADOR CON UNA DENSIDAD DE 1.02 GR/CC A UNA GASTO DE 3-4 BPM
Y UNA PB DE 250 PSI, INICIO DESPLAZAMIENTO CON LODO DE EI DE 1.34 GR/CC A UN
GASTO DE 5 BPM Y UNA PB DE 375 PSI, AL LLEVAR BOMBEADOS 59.17 BL DE VOLUMEN DE
-
DESPLAZAMIENTO SE ROTO LA SARTA A 30 RPM, CONTINUO DESPLAZANDO HASTA 98 BLS LOS
ULTIMOS 18.72 BLS SE BBEO. 10 BLS A UN Q= 2 BPM Y PB= 85 PSI. Y 8.72 BLS C/Q=
0.5 BPM Y PB= 70 PSI. PARO BOMBEO Y ESPER TRES MINUTOS OBSERVO BALANCEO
COMPLETO DE FLUIDO.
23:00-24:00 (P) QUEBR LNEAS DE 2" Y LEVANTO LENTAMENTE DE 2605 A 2174 MTS. Y BOMBEO EN
INVERSA CON 40 EPM Y PB= 400 PSI.
20/02/10
E5 00:00-01:00 (P) EFECTUO PLATICA DE SEG. OPN., POLITICA, PRINCIPIOS DEL SSPA, IND. LIMPIA,
META CERO CON PERSONAL DE PEMEX Y CIAS. Y ELABORO AST CON EL TEMA: PROBAR
TUBERIA DE REVESTIMIENTO. PE-PP-IS-001-2008. Y CONTINUA CIRCULANDO EN INVERSO
CON 2000 EMBS. A UN Q= 40 EMPM Y PB= 400 PSI. Y LEVANTA A 2034 MTS.
01:00-08:30 (P) CON TUBO AGUJA A 2034 MTS. ESPERA FRAGUADO DE CEMENTO. (P/1000 PSI DE
COMPRESIBILIDAD 9 HRS).
08:30-13:00 (P) LEVANTO TUBO DIFUSOR DE 5" A SUPERFICIE , EFECTUO LIMPIEZA EN PISO DE
PERFORACION Y ARMO ANDAMIOS EN POZO SIHIL 2 C-5.***PREVIA PLATICA DE SEG.
OPN., POLITICA, PRINCIPIOS DEL SSPA, IND. LIMPIA, META CERO CON PERSONAL DE
PEMEX Y CIAS. Y ELABORO AST CON EL TEMA: PROBAR TUBERIA DE REVESTIMIENTO.
PE-PP-IS-001-2008.
13:00-18:30 (P) ARMO BNA. 8 1/2" TRIC. -T-117 SECURITY -# 10692751 Y SARTA LISA ( D.CAJA LISO
+VCP+3 D.COLLARS+6 T.HW.5"+1 MARTILLO 6 3/4" #11118136+9 T.HW. ) Y BAJA A 1524
M. *** ATENDIENDO EMBARCACIONES.
18:30-21:00 (P) CON PERSONAL DE OPERACION DA APOYO AL ACTIVO PARA INTERVENIR POZO SIHIL 2 COND.
5 ELIMINA BAJANTE DE 1/4" CON AYUDANTE "C", Y CON PERSONAL DE OPERACION PERF'N.
ELIMINO BONETE Y BRIDA DE 7 1/16" 5M DEL MEDIO ARBOL DE PRODUCCION.
21:00-21:30 (N) REALIZO JUNTA DE TRABAJO CON PERSONAL DEL BCO. HOS SAYLOR Y PERSONAL INVOLUCRADO
EN LAS ACTIVIDADES A REALIZAR.
21:30-24:00 (N) CON PERSONAL DEL BARCO HOS SAYLOR CIA HALLIBURTON INSTALO Y PROBO LINEAS CON
4500 PSI. OK.
21/02/10
E5 00:00-00:30 (N) EFECTUO PLATICA DE SEG. OPN., POLITICA, PRINCIPIOS DEL SSPA, IND. LIMPIA,
META CERO CON PERSONAL DE PEMEX Y CIAS. Y ELABORO AST CON EL TEMA: MOLER
ACCESORIOS Y CEMENTO CLAVE: PE-PP-OP-019 -2008.
00:30-03:30 (S) CON EQUIPO A CARGO DEL ACTIVO Y BNA. DE 8 1/2" A 1524 MTS, APOYA A LA
INTERVENCION DEL POZO SIHIL 2, CERRO VALVULA MAESTRA Y ABRIO VALV. DE SONDEO
(0:30 HR) Y BOMBEA EN DIRECTO 2 M3 DE N VER SPACE O Y 2 M3 PAD (HCL AL 15%) Q=
0.7 BPM PB= 125 PSI, ENTREGO POZO A PRODUCCIN. (ABRIO POZO 2:20 HRS) ELIMINO
LINEAS DE 2" Y ELIMIINO BRIDA DE 7 1/16" DEL BARCO HOS SAYLOR. INSTALO BRIDA 7
1/16" 5M.C/BONETE A 1/2 ARBOL DE PRODCC. DE SIHIL-2
03:30-08:30 (S) CON BNA. DE 8 1/2 A 1524 MTS, DA APOYO A LA INTERVENCION DEL POZO SIHIL-1 (C-11)
POR REQUERIMIENTO DEL ACTIVO CANTARELL. INSTALO ANDAMIO EN POZO SIHIL-1 C-11 ,
C/AYTE.C. DE PROD. CERRO VALV. DE SONDEO ,DESFOGO PRESION TP. A "0" ,Y ELIMINO
BRIDA 7 1/16" C/BONETE A 1/2 ARBOL DE SIHIL-1 ,C/PERSONAL DE CIA.HALLIBURTON
INSTALO BRIDA DE 7 1/16" ,LINEAS DE 2" Y PROBO MISMA C/4500 PSI. OK. C/AYTE.C.
DE PROD.CERRO VALVULA MAESTRA Y ABRIO VALV. DE SONDEO.
08:30-09:30 (S) CON BNA. DE 8 1/2 A 1524 MTS, EQUIPO 6024 (COSL-4) DA APOYO A LA INTERVENCION
DEL POZO SIHIL-1 (C-11) POR REQUERIMIENTO DEL ACTIVO CANTARELL. C/PERSONAL DE
CIA.HALLIBURTO DEL BCO. HOS SAYLOR , BOMBEA EN DIRECTO 2 M3 DE N VER SPACE O Y 2
M3 PAD (HCL AL 15%) Q= 0.7 BPM PB= 124 PSI, TERMINO BBEO.Y BARRIO LINEAS
09:30-11:30 (S) CON BNA. DE 8 1/2 A 1524 MTS, EQUIPO 6024 (COSL-4) DA APOYO A LA INTERVENCION
DEL POZO SIHIL-1 (C-11) POR REQUERIMIENTO DEL ACTIVO CANTARELL. ELIMINO LINEAS
-
DE 2" ,BRIDA DE 7 1/16" 5000M. DE CIA.HALLIB. E INSTALO BRIDA DE 7 1/16"
C/BONETE A 1/2 ARBOL DE PRODCC.DE POZO SIHIL-1 , Y C/ AYTE.C .INSTALO TUBING Y
MANOMETRO A TP.
11:30-18:30 (N) EQUIPO 6024 (COSL-4) DA APOYO A LA INTERVENCION DEL POZO SIHIL-3 POR
REQUERIMIENTO DEL ACTIVO CANTARELL. DESMANTELO ANDAMIOS DE POSOS SIHIL-1 , E
INSTALO ANADAMIOS EN POZO SIHIL-3 P/SU INTERVENCION .C/AYTE.C. DE PROD. CERRO
VALV. DE SONDEO ,DESFOGO PRESION A "0"ELIMINO TUBING., MANOMETRO Y BONETE A 1/2
ARBOL DE SIHIL-3, Y CON PERSONAL DE CIA.HALLIBURTON INSTALO BRIDA DE 7
1/16"5M.LINEAS DE 2" DEL BCO.HOS SEYLOR Y PROBO MISMAS C/ 4500 PSI.OK.***. EN
INTER BAJO BNA. DE 8 1/2" A 2429M. DONDE CHECO CIMA DE C EMENTO C/ 5
TONS.CIRCULO Y PROBO C/1000 PSI. OK. C/PREV.ANULAR CERRADO ( CIMA TEORICA
2370M.) CONTINUO BAJANDO C/BBEO.HASTA 2483 M. ACEPTANDO 11 TONS.,Y C/ROT.Y
BBEO.A 2484 M. C/ P/BNA.=3 TNS.- 20 RPM.= AMP.350 .- 50 EPM.- Q=245 PB.=600
PSI. CERRO PERV DOBLE SUP. Y PROBO TR C/ 1000 PSI 15 MIN . EFECTIVOS OK.
***ATENDIENDO EMBARCACIONES.***PREVIA PLATICA DE SEG. OPN., POLITICA,
PRINCIPIOS DEL SSPA, IND. LIMPIA, META CERO CON PERSONAL DE PEMEX Y CIAS. Y
ELABORO AST CON EL TEMA: MOLER ACCESORIOS Y CEMENTO CLAVE: PE-PP-OP-019 -2008.
18:30-20:30 (N) CON BNA. DE 8 1/2" A 2460 MTS, Y PERSONAL DEL BCO. HOS SAYLOR INICIA LIMPIEZA
DE POZO SIHIL-3 C-5 CERRO VALVULA MAESTRA Y ABRIO VALV. DE SONDEO Y BOMBEA EN
DIRECTO 2 M3 ( 40 BLS) DE N VER SPACE O Y 2 M3 PAD (HCL AL 15%) Q= 0.7 BPM PB=
125 PSI, ENTREGO POZO A PRODUCCIN. (ABRIO POZO 20:00 HRS) ELIMINO LINEAS DE
2" Y ELIMIINO BRIDA DE 7 1/16" DEL BARCO HOS SAYLOR. NOTA: BAJO MATERIALES Y SE
RETIRO A LAS 22:45 HRS.
20:30-24:00 (N) INSTALA BRIDA DE 7 1/16" 5M. C/BONETE DEL 1/2 ARBOL DE PRODCCION DEL SIHIL-3
AVANCE 90 %. ESPARRAGOS MUY OXIDADOS.
22/02/10
E5 00:00-00:30 (P) EFECTUO PLATICA DE SEG. OPN., POLITICA, PRINCIPIOS DEL SSPA, IND. LIMPIA,
META CERO CON PERSONAL DE PEMEX Y CIAS. Y ELABORO AST CON EL TEMA: SALUD
OCUPACIONAL "OBESIDAD".
00:30-02:00 (P) CON BNA. DE 8 1/2" A 2460 MTS, EQUIPO 6024 (COSL-4) DA APOYO A LA INTERVENCION
DEL POZO SIHIL-3 POR REQUERIMIENTO DEL ACTIVO CANTARELL. CONTINUA. CON PERSONAL
SINDICALIZADO APRETANDO BIRLOS DE BRIDA DE 7 1/16" Y BONETE DEL MEDIO ARBOL DE
PRODUCCION AL 100 %. (LENTO POR ESTAR MUY CORROIDOS LOS BIRLOS 11 1/4" X 1
1/8").
02:00-17:00 (P) LEVANTA BNA. ASUPERFICIE Y CON PERSONAL DE INSPECCION TUBULAR REVISO JUNTAS
TRAMO POR TRAMO LING.N 28 , 29, N2 Y N 1 DE ( DE LA 27 A LA 3 POR LING.) DE
G-105 25.6# DE 5" Y POSTERIORMENTE T X T DE X-95 25.6# 5", SALIENDO DAADOS
, 3 TRAMOS LING.# 41 ELIMINANDOLOS, 2 T.LING.40, 2 T.DE LA 31, 1 D LA 19 ,
3 D LA 15, 3 D LA 3 ,1 D LA 2 , 3 TRAMOS DE LA LING #1, TRAMO N 4 DE HW 5"
,*** NOTA:SE BAJO AL BCO. JUANITA CANDIES 200 M3 DE LODO E.INV.1.34 GR/CC X
80 SEG.. SOLTO BCO. 11:00 HRS., LAVANDO PRESAS DE LODO Y LINEAS AV.
55%***PREVIA PLATICA (AL PERS. DE 12/24 HRS.) DE SEG. OPN., POLITICA,
PRINCIPIOS DEL SSPA, IND. LIMPIA, META CERO CON PERSONAL DE PEMEX Y CIAS.
ELABORO AST. TEMA-ESCARIAR TR. EN CASCADA CON 2 O 3 ESCARIADORES CLAVE
.PE-PP-OP-008-2008