83148736 copy of a rab total bangunan pabrik

5
PROYEK PEMBANGUNAN PABRIK LIMA DOLLAR KUNINGAN Pekerjaan : Lokasi : REKAPITULASI I. PEK. PERSIAPAN 20,460,600 II. PEKERJAAN SIPIL PONDASI GEDUNG PABRIK 35X21 m 185,907,676.71 III. PEKERJAAN KONTRUKSI BAJA DAN BETON (KOMPOSIT) 1,343,168,908.20 IV. PEKERJAAN ATAP 127,248,000.00 V. PEKERJAAN SIPIL 139,460,400.46 VI. PEKERJAAN KONSEN PINTU DAN JENDELA VII. PEKERJAAN CAT VIII.PEKERJAAN MEKANIKAL/ELEKTRIKAL Terbilang Sub Total 1,816,245,585.37 Dua Milyar Dua puluh lima juta rupiah PPN 10% 208,868,242.32 Jumlah Total 2,025,113,827.69 Dibulatkan 2,025,000,000.00

Upload: arisemail

Post on 28-Nov-2015

793 views

Category:

Documents


192 download

DESCRIPTION

rab

TRANSCRIPT

Page 1: 83148736 Copy of a RAB Total Bangunan Pabrik

PROYEK PEMBANGUNAN PABRIK LIMA DOLLAR KUNINGAN

Pekerjaan :Lokasi :

REKAPITULASI

I. PEK. PERSIAPAN 20,460,600II. PEKERJAAN SIPIL PONDASI GEDUNG PABRIK 35X2 185,907,676.71III. PEKERJAAN KONTRUKSI BAJA DAN BETON (KOMPO 1,343,168,908.20IV. PEKERJAAN ATAP 127,248,000.00V. PEKERJAAN SIPIL 139,460,400.46VI. PEKERJAAN KONSEN PINTU DAN JENDELAVII. PEKERJAAN CATVIII. PEKERJAAN MEKANIKAL/ELEKTRIKAL

Terbilang Sub Total 1,816,245,585.37Dua Milyar Dua puluh lima juta rupiah PPN 10% 208,868,242.32

Jumlah Total 2,025,113,827.69Dibulatkan 2,025,000,000.00

Page 2: 83148736 Copy of a RAB Total Bangunan Pabrik

BILLS OF APPROXIMATE QUANTITYPABRIK LIMA DOLAR KUNINGANKUNINGAN JAWA BARAT

No. Item Pekerjaan Unit Qty Remark

A PEKERJAAN PERSIAPAN1 Pembersihan lahan m2 735.00 5,000 3,675,0002 Pengukuran dan Bouwplank m1 262.00 48,800 12,785,6003 Peralatan,Air ,listrik kerja ls 1.00 1,500,000 1,500,0004 Peralatan keselamatan kerja ls 1.00 2,500,000 2,500,000

Sub Jumlah Pekerjaan Persiapan Rp. 20,460,600

B PEKERJAAN SIPIL PONDASI GEDUNG PABRIK 35X21 m1 Galian Pondasi telapak 150*150*150 m3 81.00 51,100 4,139,1002 Galian Sloof m3 174.00 51,100 8,891,4003 Galian pondasi batu kali + saluran m3 57.60 51,100 2,943,3604 Urugan kembali lobang pondasi m3 88.64 25,550 2,264,6245 Urugan Pasir padat tebal 10 cm m3 137.70 119,100 16,400,0706 Sloof beton bertulang 25 * 40 m3 30.00 4,198,196 125,945,8947 Pondasi batu kali m3 35.28 557,600 19,672,1288 Pasangan bata merah 1/2 bata tinggi 35 cm m2 39.00 92,400 3,603,6009 Plester,aci m2 39.00 52,500 2,047,500

sub jumlah pek. Sipil Pondasi pendukung utama Rp. 185,907,677C. PEKERJAAN KONTRUKSI BAJA DAN BETON (KOMPOSIT)

1 1 Berat baja Kolom dan Balok kg 81,904.70 14,750 1,208,094,3252 Base plate 370x195x12 mm kg 50.00 18,700 935,0003 Angkur dia.19 mm bh 150.00 38,000 5,700,0004 Shear Conector dia. 7/8 bh 6,348.00 13,500 85,698,0005 Shear Conector dia. 3/4 bh 1,625.00 15,000 24,375,0006 Plat simpul 630x150x12mm kg 356.08 18,200 6,480,5837 Pengaku L 50.50.5 kg 450.00 18,200 8,190,0008 Baud span dia.3/4" bh 480.00 7,700 3,696,000 1,343,168,908

sub jumlah pek. Konstruksi 1,343,168,908

Unit Price (Rp.)

Total Price ( Rp)

Page 3: 83148736 Copy of a RAB Total Bangunan Pabrik

No. Item Pekerjaan Unit Qty Remark

Pindahan hal 1. Rp. 1,549,537,185D PEKERJAAN ATAP

1 Atap Allumunium 0.4 mm m2 1,132.00 78,000 88,296,0002 Nok Allumunium 0.4 mm m1 51.00 118,000 6,018,0003 Baud roofing bh 6,528.00 1,250 8,160,0004 Talang datar Zincalum 0.4 mm m1 102.00 115,000 11,730,0005 Lisplank plat 1.2 mm m1 64.00 84,000 5,376,0006 Talang PVC 4" m1 144.00 36,000 5,184,0007 Corong talang bh 18.00 40,000 720,0009 Knee 4" bh 72.00 24,500 1,764,000

sub jumlah pekerjaan atap 127,248,000

E PEKERJAAN SIPIL a 1 Kolom pengaku dinding 15 * 25 m3 6.75 4,198,196 28,337,826

2 Balok pengaku 15*25 m3 5.40 4,198,196 22,670,2613 Ring balok 15 * 20 m3 6.48 4,198,196 27,204,313

4 Pasang dinding conblock 19*19*38 m2 960.00 63,800 61,248,000sub jumlah pek. Sipil Rp. 139,460,400

Sub Jumlah Rp. 1,816,245,585PPN & PPH 11,5 % 208,868,242

Total Rp. 2,025,113,828Grand total dibulatkan Rp. 2,025,000,000

2,755,102 per m2

Unit Price (Rp.)

Total Price ( Rp)