19_8_2011.xls
TRANSCRIPT
PROGRESS LAPANGAN Minggu :Tanggal :
Type 60/105
Blok / Nomor : B21
Mandor TAYO
Jenis Item Pekerjaan Volume Satuan Bobot
A Pekerjaaan Pondasi
1 Bowplank 60 Type 150,000 1.43% 100
2 Galian 4.68 m3 180,000 1.72% 100
3 Pondasi Batu kali 4.68 m3 500,000 4.78% 100
4 Cor sloof 42.5 m' 350,000 3.34% 100
5 Pasang Paralon 3" 12 m' 100,000 0.96% 100
6 Galian Septictank 1 ls 110,000 1.05% 100
7 Urugan elevasi lantai 9.375 m3 120,000 1.15%
B Pekerjaan Dinding 0.00%
1 Dinding Bata 128.65 m2 1,500,000 14.33% 40
2 Kusen + Daun Pintu,Jendela 11.79 m2 300,000 2.87%
3 Plesteran + Acian Dinding 187.71 m2 1,850,000 17.68%
4 Cor Kolom Praktis 30 m' 200,000 1.91%
5 Cor Ring Balk 42.5 m' 250,000 2.39%
7 Rooster 1 ls 100,000 0.96%
8 Dinding Bata Ampig 11.05 m2 300,000 2.87%
9 Cor Topi Panel 0.1 m3 150,000 1.43%
C Pekerjaan Kayu 0.00%
1 Gording 6/12 32 m' 160,000 1.53%
2 Usuk / reng 2/3 58 m2 175,000 1.67%
3 Pasang Genteng Morando 58 m2 300,000 2.87%
4 Nok / Karpusan 6 m' 100,000 0.96%
5 Pasang ListPlank 2/20 20 m' 100,000 0.96%
6 Ban-banan Atap Pembatas 20 m' 100,000 0.96%
7 Pasang Rangka Plafond 54 m2 205,000 1.96%
8 Pasang Plafond Enthernit 54 m2 205,000 1.96%
D Pekerjaaan Pintu & Jendela 0.00%
1 Pasang Engsel Jendela 5 Bh 85,000 0.81%
2 Pasang Engsel Pintu & Kunci 5 Bh 150,000 1.43%
3 Pasang Slot 5 Bh 25,000 0.24%
4 Pasang Hak angin 5 Bh 25,000 0.24%
E Keramik 0.00%
1 Keramik Lantai 40x40 60 m2 700,000 6.69%
2 Keramik Dinding 20x25 6 m2 150,000 1.43%
3 Keramik Lantai Kamar Mandi 2.5 m2 70,000 0.67%
4 Bak mandi Tempel 1 Bh 50,000 0.48%
5 Closed 1 Bh 50,000 0.48%
No.
Pembulatan Kontrak
171.500,-
Prestasi lapangan
6 Pintu Kamar Mandi 1 Bh 70,000 0.67%
7 Saringan Air 1 Bh 10,000 0.10%
8 Intalasi Air Bersih 4 m' 100,000 0.96%
F Pekerjaan Lain - lain 0.00%
1 Carport 5 m' 150,000 1.43%
2 Pemberesan 1 Bh 70,000 0.67%
G Pekerjaan Tambahan 0.00%
1 Canopi Enterance + Topi -topi 1 ls 750,000 7.17%
2 Plesteran + Acian Dinding 1 ls 175,000 1.67%
3 Pengecatan ( Rp.8500 X 60 M2 ) 1 ls 0.00%
4 Pembesian ( Rp. 5500 X 60 M2 ) 1 ls 330,000 3.15% 25
NILAI KONTRAK 10,465,000
Jumlah :
Retensi Pekerjaan ( 100 Hari ) = 5% -
Jumlah Tagihan Progrees Pekerjaan Minggu ini
Jumlah Tagihan Progrees Pekerjaan Minggu lalu
Total Tagihan Progrees Pekerjaan Minggu ini
Bobot minggu lalu =
Diajukan : Bobot minggu ini =
Bobot aktual =
150,000
180,000
500,000
350,000
100,000
110,000
-
600,000
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Jumlah ( Rp )
-
-
-
-
-
-
-
82,500
2,072,500
103,625
1,968,875
988,000
980,875
9.44
18.81
9.37
PROGRESS LAPANGAN Minggu :Tanggal :
Type 60/105
Blok / Nomor : B32
Mandor TAYO
No. Jenis Item Pekerjaan Volume Satuan Bobot
A Pekerjaaan Pondasi
1 Bowplank 60 Type 150,000 1.43%
2 Galian 4.68 m3 180,000 1.72%
3 Pondasi Batu kali 4.68 m3 500,000 4.78%
4 Cor sloof 42.5 m' 350,000 3.34%
5 Pasang Paralon 3" 12 m' 100,000 0.96%
6 Galian Septictank 1 ls 110,000 1.05%
7 Urugan elevasi lantai 9.375 m3 120,000 1.15%
B Pekerjaan Dinding 0.00%
1 Dinding Bata 128.65 m2 1,500,000 14.33%
2 Kusen + Daun Pintu,Jendela 11.79 m2 300,000 2.87%
3 Plesteran + Acian Dinding 187.71 m2 1,850,000 17.68%
4 Cor Kolom Praktis 30 m' 200,000 1.91%
5 Cor Ring Balk 42.5 m' 250,000 2.39%
7 Rooster 1 ls 100,000 0.96%
8 Dinding Bata Ampig 11.05 m2 300,000 2.87%
9 Cor Topi Panel 0.1 m3 150,000 1.43%
C Pekerjaan Kayu 0.00%
1 Gording 6/12 32 m' 160,000 1.53%
2 Usuk / reng 2/3 58 m2 175,000 1.67%
3 Pasang Genteng Morando 58 m2 300,000 2.87%
4 Nok / Karpusan 6 m' 100,000 0.96%
5 Pasang ListPlank 2/20 20 m' 100,000 0.96%
6 Ban-banan Atap Pembatas 20 m' 100,000 0.96%
7 Pasang Rangka Plafond 54 m2 205,000 1.96%
8 Pasang Plafond Enthernit 54 m2 205,000 1.96%
D Pekerjaaan Pintu & Jendela 0.00%
1 Pasang Engsel Jendela 5 Bh 85,000 0.81%
2 Pasang Engsel Pintu & Kunci 5 Bh 150,000 1.43%
3 Pasang Slot 5 Bh 25,000 0.24%
4 Pasang Hak angin 5 Bh 25,000 0.24%
E Keramik 0.00%
1 Keramik Lantai 40x40 60 m2 700,000 6.69%
2 Keramik Dinding 20x25 6 m2 150,000 1.43%
3 Keramik Lantai Kamar Mandi 2.5 m2 70,000 0.67%
4 Bak mandi Tempel 1 Bh 50,000 0.48%
5 Closed 1 Bh 50,000 0.48%
6 Pintu Kamar Mandi 1 Bh 70,000 0.67%
7 Saringan Air 1 Bh 10,000 0.10%
8 Intalasi Air Bersih 4 m' 100,000 0.96%
F Pekerjaan Lain - lain 0.00%
Pembulatan Kontrak
171.500,-
1 Carport 5 m' 150,000 1.43%
2 Pemberesan 1 Bh 70,000 0.67%
G Pekerjaan Tambahan 0.00%
1 Canopi Enterance + Topi -topi 1 ls 750,000 7.17%
2 Plesteran + Acian Dinding 1 ls 175,000 1.67%
3 Pengecatan ( Rp.8500 X 60 M2 ) 1 ls 0.00%
4 Pembesian ( Rp. 5500 X 60 M2 ) 1 ls 330,000 3.15%
NILAI KONTRAK 10,465,000
Retensi Pekerjaan ( 100 Hari ) = 5% -
Jumlah Tagihan Progrees Pekerjaan Minggu ini
Jumlah Tagihan Progrees Pekerjaan Minggu lalu
Total Tagihan Progrees Pekerjaan Minggu ini
Bobot minggu lalu =
Diajukan : Bobot minggu ini =
Bobot aktual =
100 150,000
100 180,000
100 500,000
100 350,000
-
-
-
20 300,000
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Prestasi lapangan
Jumlah
( Rp )
-
-
-
-
25 82,500
Jumlah : 1,562,500
78,125
###
788,500
695,875
Bobot minggu lalu = 7.53
Bobot minggu ini = 14.18
Bobot aktual = 6.65
REKAPAN PROGRESS DAN UPAH MANDORMinggu Ke :IITanggal : PT. Persada Bumi Kencana
No Jenis Kontrak Total Tagihan Pembayaran s/d hari ini Pembayaran Minggu ini
1 TAYO1 Rumah B21 10,465,000 9.37 9.44 18.81 2,072,500 103,625 988,000 1,968,875 980,875 2 Rumah B32 10,465,000 6.65 7.53 14.18 1,562,500 78,125 788,500 1,484,375 695,875
1,676,750
Rp 1,676,750
Cikunir, 19 Agustus 2011di Periksa Di Setujui Di Ajukan
Ujang C Mursidi AGUS
Nilai Kontrak
(Rp)
Bobot Aktual %
Bobot s.d minggu lalu
Bobot s.d minggu ini
Retensi 5%
Pembayaran s\d Minggu
lalu