16
  LAPORAN KULIA H KERJA PRAKTEK ( KKP ) PEMBANGKIT LISTRIK TENAGA UAP (PLTU ) JENEPONTO JENEPONTO COAL FIRED STEAM POWER PLANT 2X125 MW Disusun Oleh: BAHARUDDIN ( 105 82 254 0 ) FARDILLAH AMIR ( 105 82 !08 0 ) FAKULT AS TE KNIK JURUSAN ELEKTRO UNI"ERSITAS MUHAMMADI#AH MAKASSAR 201!

Upload: charles

Post on 01-Nov-2015

219 views

Category:

Documents


0 download

DESCRIPTION

ddd

TRANSCRIPT

TUGAS

LAPORAN KULIAH KERJA PRAKTEK ( KKP )PEMBANGKIT LISTRIK TENAGA UAP (PLTU ) JENEPONTOJENEPONTO COAL FIRED STEAM POWER PLANT 2X125 MW

Disusun Oleh:BAHARUDDIN ( 105 82 254 09 )FARDILLAH AMIR ( 105 82 308 09 )FAKULTAS TEKNIK

JURUSAN ELEKTRO

UNIVERSITAS MUHAMMADIYAH MAKASSAR

2013LAMPIRAN

Siklus PLTU

Diagram PLTU JenepontoTURBIN HOUSE

ESP(Electrostatic Precipitator)

GENERATOR TRANSFORMER

START UP STAND BY TRANSFORMER(SST)

UNIT AUXILIARY TRANSFORMER (UAT)

BOTTOM ASH

FLY ASH

KONDENSOR

KONDENSAT PUMP

KONVEYOR

COAL YARD

CENTRAL CONTROL ROOM(CCR)