rab wc 2 lantai

4
SUB TOTAL TOTAL (RP.) (RP.) I. PEKERJAAN PERSIAPAN 200.000,00 II. PEKERJAAN STANDARD A. PEKERJAAN STRUKTUR 16.438.100,53 B. PEKERJAAN ATAP 2.485.645,17 C. PEKERJAAN ARSITEKTUR 18.855.099,58 E. PEKERJAAN MEKANIKAL & SANITARY 5.022.973,44 TOTAL PEKERJAAN STANDARD 42.801.818,72 JUMLAH TOTAL 43.001.818,72 Terbilang : Tamalanrea, 30 Januari 2014 Dibuat Oleh Konsultan Perencana Coffee Project Engineering …………………….. Direktur utama NO REKAPITULASI RENCANA ANGGARAN BIAYA PEMBANGUNAN WC 2 Lantai URAIAN PEKERJAAN

Upload: muhammad-yahdiman

Post on 21-Oct-2015

30 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: RAB Wc 2 Lantai

SUB TOTAL TOTAL

(RP.) (RP.)

I. PEKERJAAN PERSIAPAN 200.000,00

II. PEKERJAAN STANDARD

A. PEKERJAAN STRUKTUR 16.438.100,53

B. PEKERJAAN ATAP 2.485.645,17

C. PEKERJAAN ARSITEKTUR 18.855.099,58

E. PEKERJAAN MEKANIKAL & SANITARY 5.022.973,44

TOTAL PEKERJAAN STANDARD 42.801.818,72

JUMLAH TOTAL 43.001.818,72

Terbilang :

Tamalanrea, 30 Januari 2014

Dibuat Oleh

Konsultan Perencana

Coffee Project Engineering

……………………..

Direktur utama

NO

REKAPITULASI

RENCANA ANGGARAN BIAYA

PEMBANGUNAN WC 2 Lantai

URAIAN PEKERJAAN

Page 2: RAB Wc 2 Lantai

HARGA

SATUAN

TOTAL JUMLAH

HARGA

(RP.) (RP.)

1 3 4 5 6 = 5 X 3

I. PEKERJAAN PERSIAPAN

1 Pek. Persiapan dan Pembersihan Lahan 1,00 Ls 200.000,00 200.000,00

TOTAL PERSIAPAN 200.000,00

II. PEKERJAAN STANDARDA. PEKERJAAN STRUKTUR 16.438.100,53

I. PEKERJAAN GALIAN & URUGAN

1 Pek. Galian Tanah Pondasi Batu kali menerus 2,00 m3

23.340,86 46.681,72

2 Pek. Urugan Pasir Bawah Pondasi Plat & Sloof t=10cm 1,00 m3

125.095,72 125.095,72

#REF! Pek. Urugan Tanah Kembali bks Galian 0,35 m3

11.184,51 3.914,58

JUMLAH - I 175.692,02

II. PEKERJAAN PONDASI, POER & SLOOF 63

1 Pek. Pondasi Batu kali camp. 1Pc:4Psr 3,00 m3

852.004,36 2.556.013,08

2 Pekerjaan Beton Pondasi Tangga (1,00X1,80X0,4)m 0,72 m3

858.639,45 618.220,41

4 Beton Sloof SL2 15/25 0,30 m3

4.035.423,35 1.210.627,01

JUMLAH - II 4.384.860,49

III. PEKERJAAN BETON

1 Pek Beton Kolom Praktis KP 15/15, Beton K.175,tulangan 168,57 kg/m3 0,48 m'

4.679.526,96 2.261.615,38

2 Pek. Beton Balok B1 10/15 cm, ,Beton K-175,tulangan 151,84 kg/m3 0,12 m3

5.552.811,01 666.337,32

3 Pek. Beton Balok Bordes Tangga B4 20/30 cm, Elv. +1,58,K-175,tulangan.232,21 kg/m3 0,08 m3

4.679.526,96 357.983,81

4 Pek.Beton Plat Lantai 2 t=12 cm , Elevasi +2,80 1,04 m3

4.679.526,96 4.866.708,04

5 Pek Beton Plat , Step Tangga -(1 Unit) ,Beton K-175 0,72 m3

4.679.526,96 3.369.259,41

6 Pek.Beton Plat Bordes Tangga t=12 cm (1 Unit),Beton K-175 0,08 m3

4.679.526,96 355.644,05

JUMLAH - III 11.877.548,01

B. PEKERJAAN ATAP 2.485.645,17

1 Rangka atap Baja Ringan "Zinkalum" 6,77 m2

250.000,00 1.692.500,00

2 Penutup atap Metal roof 6,77 m2

117.155,86 793.145,17

SUB TOTAL ATAP 2.485.645,17

C. PEKERJAAN ARSITEKTUR 18.855.099,58

I. PEKERJAAN DINDING & PLESTERAN

I.a LANTAI BAWAH

1 Pasangan dinding 1/2 bata 1 : 4 15,25 m2

153.500,00 2.340.875,00

2 Pekerjaan Bak Mandi 1/2 bata 1 : 4 4,40 m2

153.500,00 675.400,00

3 Pekerjaan plester dan acian dinding 1 : 4 27,85 m2

37.431,32 1.042.462,13

4 Pekerjaan dinding keramik 20X25 h= 2m 9,98 m2

199.033,57 1.985.558,90

SUB JUMLAH 6.044.296,03

II.b LANTAI ATAS

1 Pasangan dinding 1/2 bata 1 : 4 18,35 m2

153.500,00 2.816.725,00

2 Pekerjaan Bak Mandi 1/2 bata 1 : 4 4,40 m2

153.500,00 675.400,00

3 Pekerjaan plester dan acian dinding 1 : 4 35,25 m2

37.431,32 1.319.453,87

4 Pekerjaan dinding keramik 20X25 h= 2m 9,98 m2

199.033,57 1.985.558,90

5

SUB JUMLAH 6.797.137,76

JUMLAH - I 12.841.433,80

SAT

RINCIAN

2

NO URAIAN PEKERJAAN VOLUME

RENCANA ANGGARAN BIAYA

Page 3: RAB Wc 2 Lantai

HARGA

SATUAN

TOTAL JUMLAH

HARGA

(RP.) (RP.)

1 3 4 5 6 = 5 X 3

SAT

2

NO URAIAN PEKERJAAN VOLUME

II. PEK. KUSEN PINTU/JENDELA & PARTISI, LENGKAP ASSESORIES

II.a LANTAI BAWAH

1 Pasang Pintu WC 1,00 Unit 500.000,00 500.000,00

2 Pasang Kusen+jendela 1,00 Unit 250.000,00 250.000,00

SUB JUMLAH 750.000,00

II.b LANTAI ATAS

1 Pasang Kusen+Pintu 1,00 Unit 500.000,00 500.000,00

2 Pasang Kusen+jendela 1,00 Unit 250.000,00 250.000,00

SUB JUMLAH 750.000,00

JUMLAH - II 1.500.000,00

III. PEKERJAAN PLAFOND

III.b LANTAI ATAS

1 Pek. Plafond GRC 5 mm+ Rangka Hollow 40x40 (Toilet+KM) 4,00 m2

44.015,39 176.061,58

SUB JUMLAH 176.061,58

JUMLAH - III 176.061,58

IV. PEKERJAAN LANTAI

IV.a LANTAI BAWAH

1 Urugan pasir bawah lantai t=10 cm 0,40 m3

125.095,72 50.038,29

2 Pekerjaan lantai keramik 40X40 3,20 m2

203.397,87 650.873,17

3 Pekerjaan lantai keramik 30X30 (Tangga) 4,35 m2

192.797,87 838.670,71

5 Pek. Lantai Rabat t = 20 cm 6,00 m2

95.920,05 575.520,27

SUB JUMLAH 2.115.102,44

IV.b LANTAI ATAS

2 Pekerjaan lantai keramik 40X40 3,20 m2

203.397,87 650.873,17

SUB JUMLAH 650.873,17

JUMLAH - IV 2.765.975,61

V. PEKERJAAN FINISHING & PENGECATAN

V.a LANTAI BAWAH

1 Pekerjaan pengecatan dinding Exterior dan interior Watershiel 21,50 m2

21.158,82 454.914,68

2 Pekerjaan pengecatan kusen jendela 0,35 m2

32.397,14 11.339,00

SUB JUMLAH SUB JUMLAH 466.253,67

V.b LANTAI ATAS

1 Pekerjaan pengecatan dinding Exterior dan interior Watershiel 25,67 m2

21.158,82 543.146,96

2 Pekerjaan pengecatan plafond 4,00 m2

21.158,82 84.635,29

3 Pekerjaan pengecatan kusen jendela 0,35 m2

32.397,14 11.339,00

SUB JUMLAH 639.121,25

JUMLAH - V 1.571.628,60

SUB TOTAL ARSITEKTURE 18.855.099,58

E. PEKERJAAN MEKANIKAL & SANITARY 5.022.973,44

I PEKERJAAN INSTALASI AIR BERSIH

1. LANTAI - 1

a. PIPA AIR BERSIH (PPR PN 16)

- PPR dia 3/4 inc 5,00 m 66.102,69 330.513,44

b. Valve (Class 125 psi)

- Gate valve dia 3/4 inc 1,00 unit 100.000,00 100.000,00

SUB JUMLAH 430.513,44

2. LANTAI - 2

a. PIPA AIR BERSIH (PPR PN 16)

- PPR dia 3/4 inc 5,00 m 66.102,69 330.513,44

b. Valve (Class 125 psi)

- Gate valve dia 3/4 inc 1,00 unit 100.000,00 100.000,00

SUB JUMLAH 430.513,44

JUMLAH - I 861.026,87

Page 4: RAB Wc 2 Lantai

HARGA

SATUAN

TOTAL JUMLAH

HARGA

(RP.) (RP.)

1 3 4 5 6 = 5 X 3

SAT

2

NO URAIAN PEKERJAAN VOLUME

II. PEKERJAAN INSTALASI AIR KOTOR

1. LANTAI - 1

c. PIPA AIR KOTOR (PVC Class 10 kg/cm2)

- PVC dia 3 inc 3,00 m 118.335,89 355.007,67

SUB JUMLAH 355.007,67

2. LANTAI - 2

c. PIPA AIR KOTOR (PVC Class 10 kg/cm2)

- PVC dia 3 inc 5,00 m 118.335,89 591.679,45

SUB JUMLAH 591.679,45

JUMLAH - II 946.687,13

III. PEKERJAAN SANITARY

a. LANTAI BAWAH

1 Floor drained "TOTO" 1,00 bh 58.159,90 58.159,90

2 Kran air 3/4" 1,00 bh 49.469,82 49.469,82

3 Closet Duduk "TOTO" 1,00 bh 1.500.000,00 1.500.000,00

SUB JUMLAH 1.607.629,72

b. LANTAI ATAS

1 Floor drained "TOTO" 1,00 bh 58.159,90 58.159,90

2 Kran air 3/4" 1,00 bh 49.469,82 49.469,82

3 Closet Duduk "TOTO" 1,00 unit 1.500.000,00 1.500.000,00

SUB JUMLAH 1.607.629,72

JUMLAH - III 3.215.259,44