rab bangunan dan tanah
TRANSCRIPT
-
7/30/2019 Rab Bangunan Dan Tanah
1/18
No Uraian Pekerjaan Vol. Pek SatuanAnalisa Harga
SatuanJumlah
A PEKERJAAN TANAH -
1 Pembersihan Lapangan 500 m3 15,000.00 7,500,000.00
2 Galian Tanah utk Pondasi 200 m3 100,000.00 20,000,000.00
2 Urugan/ Timbunan Tanah 200 m3 100,000.00 20,000,000.00
47,500,000.00
B PEKERJAAN PASANGAN
1 Pasangan pondasi Batu Kali 200 m3 100,000.00 20,000,000.00
2 Pasangan Dinding Bata 200 m3 100,000.00 20,000,000.00
2 Neut Pada Kusen2 200 m3 100,000.00 20,000,000.00
3 Plesteran Dinding 200 m3 100,000.00 20,000,000.00
3 Laburan Dinding 200 m3 100,000.00 20,000,000.00
4 Laburan Langit-Langit 200 m3 100,000.00 20,000,000.00
120,000,000.00
C PEKERJAAN KAYU
1 Kusen-kusen Pintu dan Jendela 200 m3 100,000.00 20,000,000.00
2 Daun Pintu dan Jendela 200 m3 100,000.00 20,000,000.00
3 Listplank 200 m3 100,000.00 20,000,000.00
4 Kuda-kuda, Gording, Muurplat Kayu, Nook, Jure 200 m3 100,000.00 20,000,000.00
5 Rangka Atap (Kasau, Reng) 200 m3 100,000.00 20,000,000.006 Rangka Langit-langit (Plafond) 200 m3 100,000.00 20,000,000.00
120,000,000.00
D PEKERJAAN ATAP
1 Atap Genteng 200 m2 100,000.00 20,000,000.00
2 Bubungan atap, Nok June 200 m2 100,000.00 20,000,000.00
2 Talang Air 200 m2 100,000.00 20,000,000.00
3 Pipa Pembuangan 200 m2 100,000.00 20,000,000.00
80,000,000.00
E PEKERJAAN LANTAI
1 Urugan Pasir Bawah Lantai 200 m3 100,000.00 20,000,000.00
2 Pemasangan Keramik 200 m3 100,000.00 20,000,000.00
40,000,000.00
F PEKERJAAN MENGECAT -
1 Cat Kusen/ Pintu Jendela 200 m3 100,000.00 20,000,000.002 Cat Listplank 200 m3 100,000.00 20,000,000.00
120,000,000.00
G PEKERJAAN GANTUNGAN
1 Pasangan kaca pintu Jendela 200 m2 100,000.00 20,000,000.00
2 Engsel Pintu 200 bh 100,000.00 20,000,000.00
3 Pemasangan Kaca 200 bh 100,000.00 20,000,000.00
4 Slot Pintu Jendela 200 m2 100,000.00 20,000,000.00
5 Kunci Tanam 200 bh 100,000.00 20,000,000.00
6 Closet Jongkok 200 bh 100,000.00 20,000,000.00
7 Sumur/ Bak Air 200 bh 100,000.00 20,000,000.00
8 Instalasi Listrik 200 Titik 100,000.00 20,000,000.00
160,000,000.00
H PEKERJAAN LAIN-LAIN
1Pembesian Sengkang Balok/ Kolom, Angkur,Mur, Baut dll 200 kg 100,000.00 20,000,000.00
2 Roaster pada Ventilasi 200 bh 100,000.00 20,000,000.00
3 Direksi Keet 200 m2 100,000.00 20,000,000.00
4 Pembersihan Lahan 200 m2 100,000.00 20,000,000.00
5 Penjaga Malam : 1 org x 2 bulan x 33 Perw 66 org 1,500,000.00 99,000,000.00
6 Pelaksana 200 100,000.00 20,000,000.00
199,000,000.00
TOTAL 886,500,000.00
33 Perwakilan 33 29,254,500,000.00
RENCANA ANGGARAN BIAYA
BANGUNAN SEDERHANA 2 LANTAI, TANAH 500 M
-
7/30/2019 Rab Bangunan Dan Tanah
2/18
1 Design Gambar 33 25,000,000.00 825,000,000.00
2 Konsultan Perencana 33 30,000,000.00 990,000,000.00
3 Konsultan Pengawas 33 30,000,000.00 990,000,000.00
4 Biaya Perijinan 33 15,000,000.00 495,000,000.00
5 VSAT 33 30,000,000.00 990,000,000.00
6 Server 33 60,000,000.00 1,980,000,000.00
7 AC 99 6,100,000.00 603,900,000.00
8 Meubelair 33 17,500,000.00 577,500,000.009 Personal Computer 2 unit x 33 Perwakilan 66 5,500,000.00 363,000,000.00
10 Kendaraan Dinas Roda 4 33 246,000,000.00 8,118,000,000.00
11 Tanah 33 Perw x 500 m2 16,500 4,000,000.00 66,000,000,000.00
###############
-
7/30/2019 Rab Bangunan Dan Tanah
3/18
NO URAIAN PEKERJAAN SATUAN INDEKS
I PEKERJAAN PERSIAPAN
1 PEMBERSIHAN LAHAN
Pekerja 10m 0.75
Mandor 10m 0.025
TOTAL
2
Papan dan Pancang m 0.01
Paku m 0.1
Tukang Kayu m 0.8
Kepala Tukang Kayu m 0.08
Pekerja m 0.28
Mandor m 0.014
TOTAL
3
Pekerja m 0.75
Mandor m 0.025
TOTAL
4
Pasir m 1.2Pekerja m 0.3
Mandor m 0.01
TOTAL
5
Pasir m 1.2
Pekerja m 0.3
Mandor m 0.01
TOTAL
6Pekerja m 0.75
Mandor m 0.025
TOTAL
7
Pekerja m 0.75
Mandor m 0.025
TOTAL
DAFTAR HARGA SATUAN PEKERJAAN
KEGIATAN : PROYEK PEMBANGUNAN RUMAH
PEKERJAAN : KONSTRUKSI RUMAH
LOKASI : JAKARTA
TAHUN ANGGARAN : 2008
PEMASANGAN BOUWPLANK
GALIAN TANAH U/ PONDASI
URUGAN PASIR BWH PONDASI
URUGAN PASIR BWH LANTAI
URUGAN TANAH KEMBALI SISI PONDASI
URUGAN TANAH PENINGGIAN LANTAI
-
7/30/2019 Rab Bangunan Dan Tanah
4/18
NO URAIAN PEKERJAAN SATUAN INDEKS
II PEKERJAAN PONDASI
1 PONDASI BATU KALI
Batu Kali m 1.2
Semen m 4.26
Pasir Pasang m 0.34
Tukang Batu m 0.6
Kepala Tukang Batu m 0.06
Pekerja m 1.5
Mandor m 0.015
TOTAL
III PEKERJAAN BETON
1 SLOOF BETON
Upah Pembesian m 0.75
Kepala tukang batu m 0.039
Pekerja m 0.781
Mandor m 0.078
TOTAL
2 KOLOM BETON
Upah Pembesian m 0.75
Kepala tukang batu m 0.039
Pekerja m 0.781
Mandor m 0.078TOTAL
3 RING BALK BETON
Upah Pembesian m 0.75
Kepala tukang batu m 0.039
Pekerja m 0.781
Mandor m 0.078
TOTAL
4 MEJA DAPUR
Semen m 8.5Pasir beton m 0.54
Kerikil m 0.82
Tukang batu m 1
Pekerja m 3
Mandor m 0.1
TOTAL
5 LIST PLANK
-
7/30/2019 Rab Bangunan Dan Tanah
5/18
Semen m 8.5
Pasir beton m 0.54
Kerikil m 0.82
Tukang batu m 1
Pekerja m 3
Mandor m 0.1
TOTAL
NO URAIAN PEKERJAAN SATUAN INDEKS
6 TOPI TERAS
Semen m 8.5
Pasir beton m 0.54
Kerikil m 0.82
Tukang batu m 1
Pekerja m 3
Mandor m 0.1
TOTAL
7 LANTAI KERJA
Semen m 8.5
Pasir beton m 0.54
Kerikil m 0.82
Tukang batu m 1
Pekerja m 3
Mandor m 0.1
TOTAL
IV PEKERJAAN PASANGAN DINDING DAN PLESTERAN1
Batu bata merah m 80
Semen m 0.52
Pasir pasang m 0.042
Tukang batu m 0.16
Kepala T. Batu m 0.016
Pekerja m 0.48
Mandor m 0.048
TOTAL
2Batu bata merah m 475
Semen m 2.4
Pasir pasang m 0.416
Tukang batu m 1.5
Kepala T. Batu m 0.15
Pekerja m 3
Mandor m 0.15
TOTAL
PASANGAN DINDING BATA MERAH ( 1:2 )
PASANGAN BATU ROLLAG ( 1:4 )
-
7/30/2019 Rab Bangunan Dan Tanah
6/18
3
Semen m 0.2368
Pasir pasang m 0.019
Tukang batu m 0.214
Kepala T. Batu m 0.021
Pekerja m 0.4
Mandor m 0.02
TOTAL
NO URAIAN PEKERJAAN SATUAN INDEKS
V PEKERJAAN LANTAI DAN DINDING
1
Ubin keramik 30x30 m 1.05
Pasir pasang m 0.03
Semen m 0.2
Semen warna m 0.07
Tukang batu m 0.4
Kepala T. Batu m 0.075
Pekerja m 0.2
Mandor m 0.02
TOTAL
Ubin keramik 20x20 m 1.05
Pasir pasang m 0.03
Semen m 0.2Semen warna m 0.1
Tukang batu m 0.4
Kepala T. Batu m 0.075
Pekerja m 0.2
Mandor m 0.02
TOTAL
2
Ubin keramik 20x25 m 1.05
Pasir pasang m 0.03
Semen m 0.2Semen warna m 1
Tukang batu m 0.5
Kepala T. Batu m 0.1
Pekerja m 0.25
Mandor m 0.025
TOTAL
3 PLIN KERAMIK
PLESTERAN DAN ACI ( 1:2, TEBAL 15 mm )
LANTAI KERAMIK ( 30X30 CM )
LANTAI KERAMIK ( 20X20 CM)
DINDING KERAMIK ( 20X25 CM )
-
7/30/2019 Rab Bangunan Dan Tanah
7/18
Plin keramik m 1.01
Semen m 0.025
Pasir pasang m 0.03
Tukang batu m 0.1
Kepala T. Batu m 0.01
Pekerja m 0.15
Mandor m 0.01
TOTAL
VI PEKERJAAN ATAP
1
Balok kayu bengkirai m 1.1
Paku kg 3
Besi strip kg 15
Tukang Kayu org/hr 15
Kepala Tukang Kayu org/hr 1.5
Pekerja org/hr 5
Mandor org/hr 0.25
2 GORDING KAYU
Balok kayu bengkirai m 1.1
Paku kg 2.9
Tukang Kayu org/hr 4.5
Kepala Tukang Kayu org/hr 0.45
Pekerja org/hr 1.5
Mandor org/hr 0.075
3 KASO DAN RENGKaso m 0.012
Reng m 0.0053
Paku Rata-rata kg 0.15
Tukang Kayu org/hr 0.1
Kepala Tukang Kayu org/hr 0.01
Pekerja org/hr 0.1
Mandor org/hr 0.005
4 LISTPLANK KAYU 3/20
Papan kayu Samarinda m 0.007Paku Rata-rata kg 0.05
Tukang Kayu org/hr 0.2
Kepala Tukang Kayu org/hr 0.02
Pekerja org/hr 0.1
Mandor org/hr 0.005
5 PASANG ATAP GENTENG PRESS BETON
KUDA-KUDA ATAP RUMAH
-
7/30/2019 Rab Bangunan Dan Tanah
8/18
Genteng Press Beton bh 11.1
Tukang Batu org/hr 0.1
Kepala Tukang Batu org/hr 0.01
Pekerja org/hr 0.2
Mandor org/hr 0.01
6
Nok Genteng Press Beton bh 4.04
Semen zak 0.216
Pasir Beton m 0.032
Papan Ruiter Kamper m 0.003
Tukang Batu org/hr 0.2
Kepala Tukang Batu org/hr 0.02
Pekerja org/hr 0.4
Mandor org/hr 0.02
7 Pekerjaan Talang Datar Seng 0,3 mm + Alas Papan, tebal 2 CmPapan Kamper 2/20 m 0.008
Kaso m 0.002
Seng plat tebal 0,3 mm m' 1.05
Paku Rata-rata kg 0.15
Paku Seng kg 0.15
Timah kg 0.1
Tukang Besi org/hr 0.2
Tukang Kayu org/hr 0.15
Kepala Tukang Besi org/hr 0.02
Pekerja org/hr 0.2
Mandor org/hr 0.01
VII PEKERJAAN PLAFOND
1 Plafond Eternit/Asbes Ukuran eternit 60x120x0,5 cm
Eternit/asbes plat 60x120 lbr 1.4
Paku Rata-rata kg 0.03
Tukang Kayu org/hr 0.16
Kepala Tukang Kayu org/hr 0.016
Pekerja org/hr 0.112
Mandor org/hr 0.006
2 Rangka Plafond Kayu (Grid 60 x 60 Cm)
Balok kayu bengkirai m 0.005
Kaso Kayu m 0.02
Paku Rata-rata kg 0.2
Tukang Kayu org/hr 0.4
Kepala Tukang Kayu org/hr 0.04
Pekerja org/hr 0.28
PASANG NOK GENTENG PRESS BETON
-
7/30/2019 Rab Bangunan Dan Tanah
9/18
Mandor org/hr 0.014
VIII PEKERJAAN KUSEN, PINTU, JENDELA
1 Pekerjaan Kaca (tebal < 10 mm)
Kaca polos m 1.1
Tukang Kayu org/hr 0.24
Kepala Tukang Kayu org/hr 0.024
Pekerja org/hr 0.08
Mandor org/hr 0.004
2 Daun Pintu/ Jendela Jalusi/ Krepyak (Kayu Kamper, tebal 3,5 cm)
Papan kayu Samarinda m 0.064
Paku rata-rata kg 0.2
Lem kayu kg 0.3
List kayu m' 4
Tukang Kayu org/hr 5.4
Kepala Tukang Kayu org/hr 0.54
Pekerja org/hr 1.8
Mandor org/hr 0.09
IX PEKERJAAN CAT
1 Cat Kayu (2 Lapis)
Plamur Kayu kg 0.15
Amplas lbr 0.5
Cat dasar kg 0.15
Cat Kayu kg 0.3
Thinner ltr 0.15
Kuas bh 0.05
Tukang Cat org/hr 0.25
Kepala Tukang Cat org/hr 0.025
Pekerja org/hr 0.2
Mandor org/hr 0.01
2
Plamur Tembok kg 0.2
Amplas lbr 0.5Cat dasar kg 0.1
Cat Tembok kg 0.2
Kuas roll bh 0.015
Tukang Cat org/hr 0.25
Kepala Tukang Cat org/hr 0.025
Pekerja org/hr 0.2
Mandor org/hr 0.01
Termasuk Pekerjaan : Plamur, mengamplas
Cat Dinding Interior (Dinding Baru, 3 Lapis)
-
7/30/2019 Rab Bangunan Dan Tanah
10/18
3
Alkali ICI sebelum pengecatan kg 0.125
Cat tembok ICI Wheathershield kg 0.2
Amplas lbr 0.5
Kuas roll bh 0.015
Tukang Cat org/hr 0.28
Kepala Tukang Cat org/hr 0.03
Pekerja org/hr 0.16
Mandor org/hr 0.01
Cat Dinding Exterior (Dinding Baru, 3 Lapis) ICI
-
7/30/2019 Rab Bangunan Dan Tanah
11/18
WINNER T. F
20307046
3 TB 01
N DAN UPAH (Rp) JUMLAH (Rp)
55,798.00 41,848.50
85,607.00 2,140.18
43,988.68
8,050,000.00 80,500.00
15,000.00 1,500.00
65,734.00 52,587.20
75,671.00 6,053.68
55,798.00 15,623.44
85,607.00 1,198.50
157,462.82
55,798.00 41,848.50
85,607.00 2,140.18
43,988.68
180,000.00 216,000.0055,798.00 16,739.40
85,607.00 856.07
233,595.47
180,000.00 216,000.00
55,798.00 16,739.40
85,607.00 856.07
233,595.47
55,798.00 41,848.50
85,607.00 2,140.18
43,988.68
55,798.00 41,848.50
85,607.00 2,140.18
43,988.68
-
7/30/2019 Rab Bangunan Dan Tanah
12/18
HAN DAN UPAH ( JUMLAH (Rp)
160,000.00 192,000.00
52,000.00 221,520.00
160,000.00 54,400.00
65,734.00 39,440.40
75,671.00 4,540.26
55,798.00 83,697.00
85,607.00 1,284.11
596,881.77
1,095,000.00 821,250.00
75,671.00 2,951.17
55,798.00 43,578.24
85,607.00 6,677.35
874,456.75
1,095,000.00 821,250.00
75,671.00 2,951.17
55,798.00 43,578.24
85,607.00 6,677.35874,456.75
1,095,000.00 821,250.00
75,671.00 2,951.17
55,798.00 43,578.24
85,607.00 6,677.35
874,456.75
52,000.00 442,000.00160,000.00 86,400.00
260,000.00 213,200.00
65,734.00 65,734.00
55,798.00 167,394.00
85,607.00 8,560.70
983,288.70
-
7/30/2019 Rab Bangunan Dan Tanah
13/18
52,000.00 442,000.00
160,000.00 86,400.00
260,000.00 213,200.00
65,734.00 65,734.00
55,798.00 167,394.00
85,607.00 8,560.70
983,288.70
HAN DAN UPAH ( JUMLAH (Rp)
52,000.00 442,000.00
160,000.00 86,400.00
260,000.00 213,200.00
65,734.00 65,734.00
55,798.00 167,394.00
85,607.00 8,560.70
983,288.70
52,000.00 442,000.00
160,000.00 86,400.00
260,000.00 213,200.00
65,734.00 65,734.00
55,798.00 167,394.00
85,607.00 8,560.70
983,288.70
260 20,800.00
35,100.00 18,252.00
169,000.00 7,098.00
65,734.00 10,517.44
75,671.00 1,210.74
55,798.00 26,783.04
85,607.00 4,109.14
88,770.35
260 123,500.00
35,100.00 84,240.00
169,000.00 70,304.00
65,734.00 98,601.00
75,671.00 11,350.65
55,798.00 167,394.00
85,607.00 12,841.05
568,230.70
-
7/30/2019 Rab Bangunan Dan Tanah
14/18
35,100.00 8,311.68
169,000.00 3,211.00
65,734.00 14,067.08
75,671.00 1,589.09
55,798.00 22,319.20
85,607.00 1,712.14
51,210.19
N DAN UPAH (Rp) JUMLAH (Rp)
150,000.00 157,500.00
169,000.00 5,070.00
35,100.00 7,020.00
2,210.00 154.7
65,734.00 26,293.60
75,671.00 5,675.33
55,798.00 11,159.60
85,607.00 1,712.14
214,585.37
70,000.00 73,500.00
169,000.00 5,070.00
35,100.00 7,020.002,210.00 221
65,734.00 26,293.60
75,671.00 5,675.33
55,798.00 11,159.60
85,607.00 1,712.14
130,651.67
70,000.00 73,500.00
169,000.00 5,070.00
35,100.00 7,020.002,210.00 2,210.00
65,734.00 32,867.00
75,671.00 7,567.10
55,798.00 13,949.50
85,607.00 2,140.18
144,323.78
-
7/30/2019 Rab Bangunan Dan Tanah
15/18
17,500.00 17,675.00
35,100.00 877.5
169,000.00 5,070.00
65,374.00 6,537.40
75,671.00 756.71
55,798.00 8,369.70
85,607.00 856.07
40,142.38
8,050,000.00 8,855,000.00
8,000.00 24,000.00
8,900.00 133,500.00
65,374.00 980,610.00
75,671.00 113,506.50
55,798.00 278,990.00
85,607.00 21,401.75
10,407,008.25
8,050,000.00 8,855,000.00
8,000.00 23,200.00
65,374.00 294,183.00
75,671.00 34,051.95
55,798.00 83,697.00
85,607.00 6,420.53
9,296,552.48
6,900,000.00 82,800.00
6,900,000.00 36,570.00
8,000.00 1,200.00
65,374.00 6,537.40
75,671.00 756.71
55,798.00 5,579.80
85,607.00 428.04
133,871.95
9,430,000.00 66,010.008,000.00 400
65,374.00 13,074.80
75,671.00 1,513.42
55,798.00 5,579.80
85,607.00 428.04
87,006.06
-
7/30/2019 Rab Bangunan Dan Tanah
16/18
3,300.00 36,630.00
65,374.00 6,537.40
75,671.00 756.71
55,798.00 11,159.60
85,607.00 856.07
55,939.78
4,000.00 16,160.00
35,100.00 7,581.60
130,000.00 4,160.00
6,900,000.00 20,700.00
65,374.00 13,074.80
75,671.00 1,513.42
55,798.00 22,319.20
85,607.00 1,712.14
87,221.16
6,900,000.00 55,200.00
6,900,000.00 16,560.00
20,000.00 21,000.00
8,000.00 1,200.00
10,000.00 1,500.00
1,500.00 150
65,374.00 13,074.80
65,374.00 9,806.10
75,671.00 1,513.42
55,798.00 11,159.60
85,607.00 856.07132,019.99
27,600.00 38,640.00
8,000.00 240
65,374.00 10,459.84
75,671.00 1,210.74
55,798.00 6,249.38
85,607.00 513.64
57,313.59
8,050,000.00 40,250.00
6,900,000.00 138,000.00
8,000.00 1,600.00
65,374.00 26,149.60
75,671.00 3,026.84
55,798.00 15,623.44
-
7/30/2019 Rab Bangunan Dan Tanah
17/18
85,607.00 1,198.50
225,848.38
5,000.00 5,500.00
65,374.00 15,689.76
75,671.00 1,816.10
55,798.00 4,463.84
85,607.00 342.43
27,812.13
9,430,000.00 603,520.00
8,000.00 1,600.00
8,000.00 2,400.00
27,600.00 110,400.00
65,374.00 353,019.60
75,671.00 40,862.34
55,798.00 100,436.40
85,607.00 7,704.63
1,219,942.97
9,750.00 1,462.50
2,000.00 1,000.00
8,000.00 1,200.00
20,000.00 6,000.00
8,000.00 1,200.00
6,500.00 325
65,374.00 16,343.50
75,671.00 1,891.78
55,798.00 11,159.60
85,607.00 856.07
41,438.45
9,750.00 1,950.00
2,000.00 1,000.0050,000.00 5,000.00
50,000.00 10,000.00
9,000.00 135
65,374.00 16,343.50
75,671.00 1,891.78
55,798.00 11,159.60
85,607.00 856.07
48,335.95
-
7/30/2019 Rab Bangunan Dan Tanah
18/18
50,000.00 6,250.00
20,000.00 4,000.00
2,000.00 1,000.00
9,000.00 135
65,374.00 18,304.72
75,671.00 2,270.13
55,798.00 8,927.68
85,607.00 856.07
41,743.60