  • Harga Barang dan Upah Hal. 1

    DAFTAR HARGA SATUAN BAHAN DAN UPAHBULAN JANUARI TAHUN 2011

    A. Harga Satuan Bahan

    NO NAMA BARANG SATUAN HARGA SATUAN

    1 2 3 4

    FINISHING1 Amplas lbr 3,000.00 2 Cat besi kg 43,000.00 3 Cat dasar kg 25,000.00 4 Cat emco kg 45,000.00 5 Cat menie besi kg 18,500.00 6 Cat menie kayu kg 18,500.00 7 Cat tembok Decolith kg 35,000.00 8 Cat tembok Dulux kg 40,000.00 9 Cat tembok Emco kg 40,000.00 10 Cat tembok Paragon kg 30,000.00 11 Cat tembok Toyopaint kg 26,500.00 12 Cat tembok Vinilex kg 30,000.00 13 Cat tembok Vinippaint kg 30,000.00 14 Dempul ltr 26,235.00 15 Kuas bh 6,000.00 16 Mild zak 10,000.00 17 Minyak cat ltr 17,000.00 18 Plamir kayu kg 19,000.00 19 Plamir tembok kg 28,000.00 20 Politur ultra ltr 43,000.00 21 Politur vernis ltr 39,000.00 22 Thiner A Bonanza ltr 20,000.00 23 Thiner B Spesial ltr 7,000.00

    PENUTUP ATAP24 Alang-alang panjang 2,4 meter lbr 9,000.00 25 Alluminium foil m2 27,500.00 26 Asbes Bubungan lbr 23,667.00 27 Asbes Gelombang 1,80 m x 0,80 m x 5 mm lbr 28,000.00 28 Asbes Gelombang 2,4 m x 1,05 m x 4 mm lbr 35,000.00 29 Asbes Rata 2 m x 1 m x 4 mm lbr 15,000.00 28 Atap metal Toratora 1 x 4 Extra m2 82,368.00 29 Atap metal Toratora 1 x 4 Premium m2 120,120.00 30 Atap metal Toratora 2 x 4 Extra m2 72,930.00 31 Atap metal Toratora 2 x 4 Premium m2 107,250.00 32 Atap metal Toratora 3 x 4 Extra m2 69,784.00 33 Atap metal Toratora 3 x 4 Premium m2 102,960.00 34 Atap metal Toratora 4 x 4 Extra m2 68,640.00 35 Atap metal Toratora 4 x 4 Premium m2 100,386.00 36 Bentala paras bh 66,000.00 37 Bentala tanah liat bh 49,500.00 38 Besi profil WF kg 13,750.00 39 Besi strip kg 6,050.00 40 Bubungan Biasa bj 4,000.00 41 Bubungan Karang Pilang (glazur) isi 3,5/m bj 22,500.00 42 Bubungan Karang Pilang isi 3,5/m bj 12,500.00 43 Bubungan Ngalayur isi 3,5/m bj 6,000.00 44 Bubungan Plentong bj 6,000.00 45 Bubungan Utama isi 3,5/m bj 4,000.00 46 Genteng Kanmuri (glazur) isi 14/m2 bj 6,500.00 47 Genteng Kodok Karang Pilang (Bambe) isi 20/m2 bj 2,700.00 48 Genteng Kodok Karang Pilang (Bisma) isi 20/m2 bj 2,700.00 49 Genteng Kodok Karang Pilang (Good Year) isi 20/m2 bj 2,800.00 50 Genteng Morando Abadi isi 18/m2 bj 2,700.00 51 Genteng Morando Jatiwangi isi 18/m2 bj 2,700.00 52 Genteng Morando Ngalayur isi 20/m2 bj 2,700.00 53 Genteng Plentong bj 1,200.00 54 Genteng plentong dicat bj 1,125.00 55 Genteng Plentong Jatiwangi isi 24/m2 bj 1,125.00 56 Ijuk kg 1,500.00

  • Harga Barang dan Upah Hal. 2

    NO NAMA BARANG SATUAN HARGA SATUAN

    1 2 3 457 Ikut celedu paras bh 55,000.00 58 Ikut celedu tanah liat bh 45,000.00 59 Murda paras bh 75,000.00 60 Murda tanah liat bh 60,000.00 61 Seng BJLS 0,20 gelombang lbr 40,000.00 62 Seng BJLS 0,25 gelombang lbr 38,000.00 63 Seng BJLS 0,28 gelombang lbr 40,000.00 64 Seng BJLS 0,32 gelombang lbr 45,000.00 65 Seng Plat 3" x 6" BJLS 28 lbr 45,000.00 66 Sirap Jati bh 7,900.00 67 Tali Ijuk kg 33,000.00 68 Tali pengikat alang-alang ikat 7,700.00

    PENGGANTUNG69 Engsel kupu-kupu ps 15,000.00 70 Engsel nylon ps 13,000.00 71 Espagnoleth set 35,000.00 72 Grendel biasa bh 9,350.00 73 Grendel hararo bh 18,425.00 74 Kaca 3 mm bening m2 70,000.00 75 Kaca 5 mm bening m2 90,000.00 76 Kaca 6 mm bening m2 120,000.00 77 Kaca 8 mm bening m2 185,000.00 78 Kaca 10 mm bening m2 250,000.00 79 Kaca 12 mm bening m2 300,000.00 80 Kaca Es/Kapur 3 mm m2 75,000.00 81 Kaca Es/Kapur 5 mm m2 105,000.00 82 Kaca nako daun 12,500.00 83 Kaca nako teralis bening m2 113,300.00 84 Kaca ryben 3 mm m2 100,000.00 85 Kaca ryben 5 mm m2 110,000.00 86 Kait angin biasa bh 16,000.00 87 Kunci pintu TOP bh 40,000.00 88 Kunci pintu Union bh 65,000.00 89 Kunci pintu Vanesa bh 107,000.00 90 Kunci pintu Yale bh 112,500.00 91 Kunci pintu YURI bh 125,000.00 92 Kunci slot bh 88,000.00 93 Kunci tanam 2 slag bh 104,500.00

    KAYU DAN PLAFOND94 Bambu besar Ukuran 4 m btg 16,000.00 95 Bambu sedang Ukuran 4 m btg 14,000.00 96 Bambu kecil Ukuran 4 m btg 12,000.00 97 Celling teak (0,62 x 2,40) m2 lbr 65,000.00 98 Eternit lbr 47,000.00 99 Formika lbr 80,000.00

    100 Gedeg kulit kelas I m2 32,000.00 101 Gypsum Old lbr 62,500.00 102 Hard board MDF lbr 105,000.00 103 Kalsiboard 4,5 mm lbr 70,000.00 104 Kayu bekesting m3 2,000,000.00 105 Kayu bingkirai m3 9,000,000.00 106 Kayu bingkirai papan m3 10,000,000.00 107 Kayu dolken (pekerjaan sementara) btg 90,000.00 108 Kayu jati m3 20,000,000.00 109 Kayu jati papan m3 30,000,000.00 110 Kayu kamper balok m3 7,700,000.00 111 Kayu kamper usuk/reng m3 5,700,000.00 112 Kayu kamper papan m3 7,900,000.00 113 Kayu kruing balok m3 4,200,000.00 114 Kayu kruing usuk/reng m3 4,000,000.00 115 Kayu kruing papan m3 6,000,000.00 116 Kayu meranti balok m3 2,000,000.00 117 Kayu meranti usuk/reng m3 1,700,000.00 118 Kayu meranti papan m3 4,000,000.00 119 Kayu merbau m3 9,700,000.00 120 Kayu merbau papan m3 10,000,000.00 121 Kayu profil m1 12,250.00

  • Harga Barang dan Upah Hal. 3

    NO NAMA BARANG SATUAN HARGA SATUAN

    1 2 3 4122 Kayu seseh balok m3 2,264,750.00 123 Kayu seseh dolken m3 2,750,000.00 124 Lem Aibond kg 33,000.00 125 Lem Kayu ltr 12,500.00 126 List Gypsum standar m' 17,000.00 127 Minyak bekisting ltr 15,000.00 128 Multiplek 12 mm lbr 126,000.00 129 Multiplek 18 mm lbr 172,000.00 130 Multiplek 6 mm lbr 58,000.00 131 Multiplek 9 mm lbr 82,000.00 132 Plywood 12 mm lbr 126,000.00 133 Plywood 3 mm lbr 35,000.00 134 Plywood 4 mm lbr 46,000.00 135 Plywood 6 mm lbr 66,550.00 136 Plywood 9 mm lbr 105,250.00 137 Plywood aluminium lbr 74,000.00 138 Teak wood (0,9x2,20) m2 lbr 55,000.00 139 Teak wood (1,20x2,40) m2 lbr 61,000.00

    KERAMIKIKAD

    140 Ikad (Keramik) Kw. I 10 x 20 cm m2 51,480.00 141 Ikad (Keramik) Kw. I 20 x 20 cm m2 41,900.00 142 Ikad (Keramik) Kw. I 20 x 30 cm m2 51,800.00 143 Ikad (Keramik) Kw. I 30 x 30 cm m2 39,500.00 144 Ikad (Keramik) Kw. I 40 x 40 cm m2 47,900.00 145 Ikad (Keramik) Kw. II 10 x 20 cm m2 37,500.00 146 Ikad (Keramik) Kw. II 20 x 20 cm m2 39,500.00 147 Ikad (Keramik) Kw. II 20 x 30 cm m2 46,500.00 148 Ikad (Keramik) Kw. II 30 x 30 cm m2 37,500.00 149 Ikad (Keramik) Kw. II 40 x 40 cm m2 45,900.00

    INESA150 Keramik 30 x 30 Kelas I (Onyx Phyrus Ruby Jade, P) m2 190,696.00 151 Keramik 30 x 30 Kelas I (Onyx Phyrus Ruby Jade, UP) m2 153,367.50 152 Keramik 30 x 30 Kelas I (Pearl Ghita Cat Eye, P) m2 179,080.00 153 Keramik 30 x 30 Kelas I (Pearl Ghita Cat Eye, UP) m2 142,175.00 154 Keramik 30 x 30 Kelas I (Sand Wheat Spruce Clay Charcoal, R) m2 164,560.00 155 Keramik 40 x 40 Kelas I (Corypha Roystonea Raphia, P) m2 208,846.00 156 Keramik 40 x 40 Kelas I (Onyx Phyrus Ruby Jade, P) m2 208,846.00 157 Keramik 40 x 40 Kelas I (Onyx Phyrus Ruby Jade, UP) m2 159,720.00 158 Keramik 40 x 40 Kelas I (Pearl Ghita Cat Eye, P) m2 196,504.00 159 Keramik 40 x 40 Kelas I (Pearl Ghita Cat Eye, UP) m2 148,467.00 160 Keramik 60 x 60 Kelas I (Corypha Roystonea Raphia, P) m2 248,171.00

    ESSENZA161 Keramik 30 x 30 Kelas I (Black Orchid, Coral Bell, P) m2 165,000.00 162 Keramik 30 x 30 Kelas I (Black Orchid, Coral Bell, UP) m2 122,100.00 163 Keramik 30 x 30 Kelas I (Pepper Grey Price Rubert Silver star, P) m2 150,700.00 164 Keramik 30 x 30 Kelas I (Pepper Grey Price Rubert Silver star, UP) m2 107,800.00 165 Keramik 40 x 40 Kelas I (Pepper Grey Price Rubert Silver star, P) m2 222,900.00 166 Keramik 40 x 40 Kelas I (Pepper Grey Price Rubert Silver star, UP) m2 194,900.00 167 Keramik 60 x 60 Kelas I (Pepper Grey Price Rubert Silver star, P) m2 273,500.00 168 Keramik Kelas I Domus m2 286,500.00 169 Keramik Kelas I Granity Imperiali m2 262,500.00 170 Keramik Kelas I Lavagna m2 249,900.00 171 Keramik Kelas I Mountain Peak m2 337,000.00

    GARUDA172 Keramik 20 x 20 kelas I Emboss Dasar Muda m2 43,000.00 173 Keramik 20 x 20 kelas I Emboss Dasar Tua m2 45,000.00 174 Keramik 20 x 20 kelas I Tesia m2 45,000.00 175 Keramik 20 x 20 kelas II Emboss Dasar Muda m2 43,000.00 176 Keramik 20 x 20 kelas II Emboss Dasar Tua m2 44,000.00 177 Keramik 20 x 20 kelas II Tesia m2 43,000.00 178 Keramik 20 x 25 kelas I Motif Dasar Medium m2 46,000.00 179 Keramik 20 x 25 kelas I Motif Dasar Muda m2 46,000.00 180 Keramik 20 x 25 kelas I Nuri Dark m2 48,000.00

  • Harga Barang dan Upah Hal. 4

    NO NAMA BARANG SATUAN HARGA SATUAN

    1 2 3 4181 Keramik 20 x 25 kelas I Polos m2 40,000.00 182 Keramik 30 x 30 kelas I Granity m2 45,000.00 183 Keramik 30 x 30 kelas I Motif Embose m2 45,000.00 184 Keramik 30 x 30 kelas II Granity m2 43,000.00 185 Keramik 30 x 30 kelas II Motif Embose m2 43,000.00 186 Keramik 40 x 40 kelas I Motif Dasar Muda m2 48,000.00 187 Keramik 40 x 40 kelas I Motif Dasar Muda m2 48,000.00 188 Keramik 40 x 40 kelas I Motif Embose m2 50,050.00 189 Keramik 40 x 40 kelas I Motif Granity Tua m2 55,000.00 190 Keramik 40 x 40 kelas I Motif Medium Color m2 45,000.00 191 Keramik 40 x 40 kelas I Motif Spesial Color m2 44,550.00 192 Keramik 50 x 50 kelas I m2 70,000.00

  • Harga Barang dan Upah Hal. 5

    NO NAMA BARANG SATUAN HARGA SATUAN

    1 2 3 4ASIA

    193 Keramik 10 x 20 kelas I warna muda m2 49,500.00 194 Keramik 20 x 20 kelas I warna muda m2 34,500.00 195 Keramik 20 x 20 kelas I warna tua m2 36,500.00 196 Keramik 20 x 25 kelas I warna tua m2 39,000.00 197 Keramik 20 x 30 kelas I warna muda m2 55,000.00 198 Keramik 30 x 30 kelas I warna muda m2 34,500.00 199 Keramik 30 x 30 kelas I warna tua m2 38,500.00 200 Keramik 40 x 40 kelas I warna muda m2 40,500.00 201 Keramik 10 x 20 kelas II m2 44,440.00 202 Keramik 20 x 20 kelas II m2 34,500.00 203 Keramik 20 x 30 kelas II m2 36,500.00 204 Keramik 30 x 30 kelas II m2 36,500.00 205 Keramik 40 x 40 kelas II m2 39,500.00

    MULIA206 Keramik 10 x 20 cm kelas I m2 40,000.00 207 Keramik 20 x 20 cm kelas I m2 42,500.00 208 Keramik 20 x 30 cm kelas I m2 55,000.00 209 Keramik 30 x 30 cm kelas I m2 38,500.00 210 Keramik 40 x 40 cm kelas I m2 47,500.00 211 Keramik 10 x 20 cm kelas II m2 38,000.00 212 Keramik 20 x 20 cm kelas II m2 39,500.00 213 Keramik 20 x 30 cm kelas II m2 52,000.00 214 Keramik 30 x 30 cm kelas II m2 36,500.00 215 Keramik 40 x 40 cm kelas II m2 45,500.00

    SANITAIR201 Bak mandi fibre glass 70x70x66 cm bh 225,000.00 202 Bak mandi keramik 50x50 bh 165,000.00 203 Floor Drain " TOTO TypeTx 1 Bv 1 " Square Flange " bh 222,900.00 204 Floor drain plastik bh 12,500.00 205 Floor drain stainless bh 35,000.00 206 Kloset duduk INA Komplit bh 1,100,000.00 207 Kloset duduk Amerika Standar bh 890,000.00 208 Kloset duduk " TOTO Type AVANTE CW 821 PJ / SW 821JP COMPLIT bh 1,420,000.00 209 Kloset duduk " TOTO Type AVANTE CW 821J"/ SW 821JP COMPLIT bh 5,610,000.00 210 Kloset duduk " TOTO Type AVANTE CW 823 J bh 5,600,000.00 211 Kloset duduk " TOTO Type CW 660J bh 602,800.00 212 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT bh 1,365,000.00 213 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT WARNA bh 1,491,000.00 214 Kloset duduk " TOTO Type CW 660J WARNA COMPLIT bh 653,000.00 215 Kloset duduk " TOTO Type CW 661JT1 BODI COMPLIT bh 2,796,200.00 216 Kloset duduk " TOTO Type CW 661JT1" / SW 661JP COMPLIT bh 2,190,000.00 217 Kloset duduk " TOTO Type CW 661JT1" / SW 784JP COMPLIT bh 1,734,700.00 218 Kloset jongkok " TOTO Type CE 6 COMPLIT bh 345,000.00 219 Kloset jongkok " TOTO Type CE 7 COMPLIT bh 153,900.00 220 Kloset porselin jongkok Kia (standar) bh 135,300.00 221 Kloset porselin jongkok Ina (standar) bh 125,000.00 222 Kran biasa bh 13,000.00 223 Kran SunEi bh 99,000.00 224 Kran TOTO T 205 LCSC bh 220,500.00 225 Kran TOTO T 205 MC bh 156,900.00 226 Kran TOTO T 23 B13 bh 134,500.00 227 Kran TOTO T 23 B13V7N bh 140,500.00 228 Kran TOTO T 26 - 13 bh 183,900.00 229 Kran TOTO TX 109 LH bh 407,900.00 230 Penyekat Urinoir " TOTO " Type A 100 " bh 832,000.00 231 Shower Spray " TOTO Tx 403SPIV ( Pastel Ivory ) bh 233,500.00 232 Soap holder " TOTO " Type S 6 N " bh 45,900.00 233 Seal tape bh 2,000.00 234 Urinoir " TOTO U 57 M bh 1,052,000.00 235 Urinoir " TOTO U 57 M BODI bh 849,000.00 236 Urinoir " TOTO UW 447 JT 1 " bh - 237 Urinoir " TOTO UW 447 JT 1 BODI bh - 238 Urinoir " TOTO UW 447 JT 1,M " bh - 239 Urinoir " TOTO UW 447 JT 1,M "BODI bh - 240 Wastagel KIA Standard bh 181,800.00

  • Harga Barang dan Upah Hal. 6

    NO NAMA BARANG SATUAN HARGA SATUAN

    1 2 3 4241 Wastagel KIA Warna bh 228,900.00 242 Wastafel Komplit " TOTO Tx " Type L 521V1A " bh 1,130,000.00 243 Wastafel Komplit top Counter" TOTO " Type CERABO LW 523 " bh 728,000.00

  • Harga Barang dan Upah Hal. 7

    NO NAMA BARANG SATUAN HARGA SATUAN

    1 2 3 4PAKU

    244 Paku 10 cm kg 12,000.00 245 Paku kalsiboard kg 19,000.00 246 Paku list SQ kg 15,000.00 247 Paku pancing 60 x 230 kg 18,750.00 248 Paku reng/usuk SQ kg 12,000.00 249 Paku seng kg 17,500.00 250 Paku seng import bj 45,000.00 251 Paku skrup 1/2" kg 16,500.00 252 Paku skrup 2" kg 16,500.00 253 Paku skrup 3.5" kg 24,167.00 254 Paku sumbat 1/2" kg 13,750.00

    PASIR, BATU, KERIKIL, BATA DAN PARAS255 Bata gosok ex Tulikup bj 1,980.00 256 Bata Merah 5 x 11 x 22 cm bj 1,000.00 257 Batako kelas I bj 2,300.00 258 Batu kali /batu bulat 15/20 cm m3 140,000.00 259 Batu karang m3 110,000.00 260 Batu lahar Singaraja m3 138,000.00 261 Batu pecah 5-7 cm (manual) m3 150,000.00 262 Batu pipih Singaraja m3 150,000.00 263 Glass block bj 17,500.00 264 Roster Keramik bh 48,000.00 265 Koral Beton m3 150,000.00 266 Limestone m3 79,000.00 267 Paras Batik bh 15,000.00 268 Paras Buahan bh 6,600.00 269 Paras Karang Bukit bh 7,700.00 270 Paras Kerobokan Tebal 5 bh 8,000.00 271 Paras Malem bh 12,870.00 272 Paras Putih Bukit bh 3,300.00 273 Paras Silakarang tebal bh 13,860.00 274 Paras Silakarang tipis bh 11,000.00 275 Paras untuk pondasi bh 12,000.00 276 Pasir beton m3 140,000.00 277 Pasir pasang m3 150,000.00 278 Pasir urug m3 80,000.00 279 Sirtu m3 100,000.00 280 Tanah urug m3 70,000.00

    PIPA281 Pipa Galvanis 1/2" m1 23,000.00 282 Pipa Galvanis 3/4" m1 27,000.00 283 Pipa Galvanis 1 1/4" m1 46,000.00 284 Pipa Galvanis 1 1/2" m1 61,000.00 285 Pipa Galvanis 1" m1 38,000.00 286 Pipa Galvanis 1,5 BSA m1 - 287 Pipa Galvanis 2" m1 69,000.00 288 Pipa Galvanis 3" m1 175,000.00 289 Pipa Maspion AW 1 ljr 32,000.00 290 Pipa Maspion AW 1/2 ljr 22,000.00 291 Pipa Maspion AW 10 ljr 109,200.00 292 Pipa Maspion AW 1-1/2 ljr 56,000.00 293 Pipa Maspion AW 1-1/4 ljr 43,000.00 294 Pipa Maspion AW 12 ljr 1,550,000.00 295 Pipa Maspion AW 14 ljr 1,900,000.00 296 Pipa Maspion AW 16 ljr 2,400,000.00 297 Pipa Maspion AW 2 ljr 89,000.00 298 Pipa Maspion AW 2-1/2 ljr 103,000.00 299 Pipa Maspion AW 3 ljr 140,000.00 300 Pipa Maspion AW 3/4 ljr 25,000.00 301 Pipa Maspion AW 4 ljr 225,000.00 302 Pipa Maspion AW 5 ljr 373,000.00 303 Pipa Maspion AW 6 ljr 494,000.00 304 Pipa Maspion AW 8 ljr 768,000.00 305 Pipa Maspion C 1 ljr 14,700.00 306 Pipa Maspion C 1-1/2 ljr 19,500.00

  • Harga Barang dan Upah Hal. 8

    NO NAMA BARANG SATUAN HARGA SATUAN

    1 2 3 4307 Pipa Maspion C 1-1/4 ljr 16,500.00 308 Pipa Maspion C 2 ljr 35,000.00 309 Pipa Maspion C 2-1/2 ljr 45,000.00 310 Pipa Maspion C 3 ljr 50,000.00 311 Pipa Maspion C 3/4 ljr 10,000.00 312 Pipa Maspion C 4 ljr 63,000.00 313 Pipa Maspion C 5/8 ljr 5,500.00 314 Pipa Maspion D 10 ljr 784,000.00 315 Pipa Maspion D 1-1/2 ljr 32,000.00 316 Pipa Maspion D 1-1/4 ljr 28,000.00 317 Pipa Maspion D 12 ljr 1,877,568.00 318 Pipa Maspion D 14 ljr 1,270,000.00 319 Pipa Maspion D 16 ljr 1,650,000.00 320 Pipa Maspion D 2 ljr 42,000.00 321 Pipa Maspion D 2-1/2 ljr 62,000.00 322 Pipa Maspion D 3 ljr 86,000.00 323 Pipa Maspion D 4 ljr 120,000.00 324 Pipa Maspion D 5 ljr 209,000.00 325 Pipa Maspion D 6 ljr 254,000.00 326 Pipa Maspion D 8 ljr 449,000.00

    SEMEN327 Semen Bosowa 50 kg zak 60,000.00 328 Semen Gresik 40 kg zak 50,000.00 329 Semen Gresik 50 kg zak 60,000.00 330 Semen Tiga Roga 50 kg zak 63,000.00 331 Semen Tonasa 50 kg zak 60,000.00 332 Semen warna/semen grouting kg 8,000.00

    BESI BETON DAN PAGAR333 Besi beton kg 7,111.00 334 Kawat berduri roll 80,000.00 335 Kawat beton RRT kg 15,000.00 336 Pagar BRC asli T.120 diameter 6mm m' 161,700.00 337 Pagar BRC asli T.150 diameter 6mm m' 172,000.00 338 Pagar BRC asli T.175 diameter 7mm m' 249,000.00 339 Pagar BRC asli T.190 diameter 7mm m' 267,000.00 340 Pagar BRC asli T.90 diameter 6mm m' 134,000.00 341 Pagar HotDip Galvanized T.120 diameter 6mm m' 136,000.00 342 Pagar HotDip Galvanized T.150 diameter 7mm m' 187,000.00 343 Pagar HotDip Galvanized T.175 diameter 7mm m' 203,000.00 344 Pagar HotDip Galvanized T.190 diameter 7mm m' 218,000.00 345 Pagar HotDip Galvanized T.90 diameter 6mm m' 118,000.00 346 Tiang BRC asli T. 120 diameter 1 1/2" bh 160,000.00 347 Tiang BRC asli T. 150 diameter 2" bh 209,000.00 348 Tiang BRC asli T. 175 diameter 2" bh 240,000.00 349 Tiang BRC asli T. 190 diameter 2" bh 246,000.00 350 Tiang BRC asli T. 90 diameter 1 1/2" bh 136,000.00 351 Tiang HotDip Galvanized T. 120 diameter 1 1/2" bh 142,000.00 352 Tiang HotDip Galvanized T. 150 diameter 2" bh 169,000.00 353 Tiang HotDip Galvanized T. 175 diameter 2" bh 185,000.00 354 Tiang HotDip Galvanized T. 190 diameter 2" bh 197,000.00 355 Tiang HotDip Galvanized T. 90 diameter 1 1/2" bh 123,000.00

    BAHAN LISTRIK356 Saklar (Broco) bh 12,500.00 357 Stop Kontak bh 15,500.00 358 Fitting bh 4,500.00 359 Steker bh 5,500.00 360 Coaxial cable 5C - 75 ohm commscof m1 5,700.00 361 Kabel NYM 3 x 2.5 mm ex. Supreme m1 11,500.00 362 Kabel NYM 4 mm m1 5,500.00 363 Kabel telephone m1 3,500.00 364 Lampu pijar 10 Watt (Philip) bh 4,500.00 365 Lampu pijar 15 Watt (Philip) bh 5,500.00 366 Lampu pijar 25 Watt (Philip) bh 6,000.00 367 Lampu TL 10 Watt (10 Watt) bh 27,500.00 368 Lampu TL 20 Watt (10 Watt) bh 34,000.00

  • Harga Barang dan Upah Hal. 9

    NO NAMA BARANG SATUAN HARGA SATUAN

    1 2 3 4369 Lampu TL 25 Watt (10 Watt) bh 31,900.00 370 Pipa clipsal 20 mm bt 10,000.00 371 Pipa flexible clipsal 20 mm m1 9,000.00 372 Sock clipsal 20 mm bj 1,500.00 373 Tee dos clipsal 20 mm bh 6,000.00 374 Klem clipsal 20 mm bj 650.00 375 Inbow dos plastik clipsal E 157 P bj 9,000.00

  • Harga Barang dan Upah Hal. 10

    NO NAMA BARANG SATUAN HARGA SATUAN

    1 2 3 4BUIS BETON

    376 Buis beton 10 x 75 bh 27,500.00 377 Buis beton 15 x 75 bh 35,000.00 378 Buis beton 20 x 75 bh 37,500.00 379 Buis beton 25 x 75 bh 40,000.00 380 Buis beton 30 x 75 bh 50,000.00 381 Buis beton 50 x 75 bh 72,500.00

    PAVING382 Paving 10 x 20 cm tebal 6 cm K225 m2 46,000.00 383 Paving 10 x 20 cm tebal 6 cm K350 m2 54,500.00 384 Paving 10 x 20 cm tebal 8 cm K225 m2 53,500.00 385 Paving 10 x 20 cm tebal 8 cm K350 m2 60,000.00 386 Paving 10 x 20 cm tebal 8 cm K425 m2 69,500.00 387 Paving 20 x 20 cm tebal 6 cm K225 m2 46,000.00 388 Paving 20 x 20 cm tebal 6 cm K350 m2 54,500.00 389 Paving 20 x 20 cm tebal 8 cm K225 m2 53,500.00 389 Paving 20 x 20 cm tebal 8 cm K350 m2 60,000.00 390 Paving 20 x 20 cm tebal 8 cm K425 m2 69,500.00 391 Paving 20 x 20 cm tebal 10 cm K225 m2 60,500.00 392 Paving 20 x 20 cm tebal 10 cm K350 m2 70,000.00 393 Paving 20 x 20 cm tebal 10 cm K425 m2 79,000.00 394 Paving Tiga Berlian tebal 6 cm K225 m2 47,000.00 395 Kanstein Bulat (P:50,T:30,La:10,Lb:16 cm K225) m1 52,000.00 396 Kanstein Jumbo (P:50,L:15,T:30 cm K225) m1 58,000.00 397 Kanstein Segi Lima Jumbo (P:50,L:15, T:40 cm K225) m1 62,000.00 398 Grass Block 36 X 54 cm tebal 9 cm K 225 m2 47,500.00 399 Koral Sikat zak/10 kg 30,000.00

    LAIN-LAINDugul batu hitam 50 x 50 x 200 unit 2,725,000.00

    1 Dugul batu hitam 60 x 70 x 250 unit 3,550,000.00 2 Dugul batu hitam 70 x 70 x 250 unit 3,650,000.00 3 Padmasari batu hitam 50 x 50 x 200 unit 2,675,000.00 4 Padmasari batu hitam 70 x 70 x 250 unit 3,275,000.00 5 Padmasari batu hitam 65 x 75 x 225 unit 2,550,000.00

    Mangupura, Januari 2011Kepala Dinas Cipta Karya

    Kabupaten Badung

    Ir. Ni Luh Putu Dessy Dharmayanty, M.TPembina

    NIP. 196110101994032001

  • Harga Barang dan Upah Hal. 11

    DAFTAR HARGA SATUAN BAHAN TAMBAHANBULAN APRIL TAHUN 2010

    A. Harga Satuan Bahan

    NO NAMA BARANG SATUAN HARGA SATUAN

    1 2 3 4

    BATUBatu Candi

    1 20x20x2 m2 78,000.00 2 15x30x2 m2 78,000.00 3 20x30x2 m2 78,000.00 4 20x40x2 m2 80,000.00 5 30x30x2 m2 80,000.00 6 40x40x2 m2 105,000.00 7 30x60x2 m2 115,000.00 8 20x40x3 m2 135,000.00 9 30x30x3 m2 135,000.00 10 30x30x5 m2 165,000.00 11 40x40x5 m2 185,000.00

    Palimanan putih1 20x20x2 m2 65,000.00 2 20x30x2 m2 67,000.00 3 20x40x2 m2 68,000.00 4 20x40x3 m2 110,000.00 5 30x30x3 m2 110,000.00

    Palimanan Serat Kuning1 20x30 m2 75,000.00 2 20x40 m2 75,000.00 3 15x30 m2 75,000.00

    Palimanan Cirebon1 15x30x2 m2 72,000.00 2 20x30x2 m2 73,000.00 3 20x40x2 m2 75,000.00 4 30x30x2 m2 80,000.00

    Alur Bali Green Lurus1 20x30 m2 105,000.00 2 20x40 m2 105,000.00

    Alur Bali Green Cukil1 20x30 m2 105,000.00 2 20x40 m2 105,000.00 3 20x20 m2 105,000.00

    Batu Bali Green1 15x30 m2 75,000.00 2 20x30 m2 75,000.00 3 20x40 m2 75,000.00 4 40x40 m2 80,000.00

    PARASParas Kerobokan

    1 20x40x3 Bj 6,000.00 2 20x40x5 Bj 8,000.00

    Paras Kelating1 20x40x3 Bj 6,000.00 2 20x40x5 Bj 8,000.00

    Alur Andesit Lurus1 20x40 m3 135,000.00 2 30x60 m3 140,000.00

    Alur and cukil

  • Harga Barang dan Upah Hal. 12

    NO NAMA BARANG SATUAN HARGA SATUAN

    1 2 3 41 20x40 m2 135,000.00 2 15x30 m2 135,000.00

    Alur And Gelombang m2 140,000.00 Alur And Gelombang lurus m2 140,000.00

    Random Singaraja m2 25,000.00 Random Cirebon m2 65,000.00 Random Jember m2 45,000.00

  • DAFTAR HARGA SATUAN UPAHBULAN JANUARI TAHUN 2011

    NO NAMA BARANG SPESIFIKASI SATUANHARGA

    (Rp.)1 2 3 4 5

    1 Mandor Hari 90,000.00 2 Kepala Tukang Hari 85,000.00 3 Tukang Politur Hari 80,000.00 4 Tukang Batu Hari 80,000.00 5 Tukang kayu Hari 80,000.00 6 Tukang Besi Hari 80,000.00 7 Tukang cat Hari 80,000.00 8 Tukang gali Hari 80,000.00 9 Tukang Listrik Hari 80,000.00

    10 Tukang Pipa/ Tukang Ledeng Hari 80,000.00 11 Tukang Aspal Hari 80,000.00 12 Tukang masak Aspal Hari 80,000.00 13 Pekerja Hari 70,000.00 14 Tukang Ukir Hari 80,000.00 15 Operator Hari 80,000.00 16 Pembantu Operator Hari 70,000.00 17 Mekanik Hari 80,000.00 18 Pembantu Mekanik Hari 70,000.00 19 Pasang Atap Alang-Alang Hari 70,000.00 20 Pasang Bata Gosok Dua Muka M2 320,000.00 21 Pasang Bata Gosok Satu Muka M2 160,000.00 22 Pasang Batu Paras Diukir M2 325,000.00 23 Pasang Patu Paras Siap Diukir M2 275,000.00 24 Tukang Bongkar Begesting Hari 70,000.00

    Catatan :1. Harga - harga belum termasuk PPn 10 %;2. Harga - harga hanya sebagai pedoman / pendukung

    dalam perhitungan konstruksi ( tidak mengikat ).

    Mangupura, Januari 2011Kepala Dinas Cipta Karya

    Kabupaten Badung

    Ir. Ni Luh Putu Dessy Dharmayanty, M.TPembina

    NIP. 196110101994032001

  • DAFTAR ANALISA PEKERJAANBULAN JANUARI TAHUN 2011

    NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

    (Rp) (Rp) (Rp) (Rp)1 2 3 4 5 6

    I PEKERJAAN PERSIAPAN (SNI 03-2835-2002)1

    1.2500 btg Bambu Sedang 14,000.00 17,500.00 2.5000 kg Semen Portland 1,200.00 3,000.00 1.2000 lbr Seng gelombang 3" - 5" 40,000.00 48,000.00 0.0050 m3 Pasir Beton 140,000.00 700.00 0.0090 m3 Koral beton 150,000.00 1,350.00 0.0720 m3 Kayu Meranti Usuk 5/7 1,700,000.00 122,400.00 0.0600 kg Paku biasa 2" - 5" 12,000.00 720.00 0.4500 kg Meni Besi 18,500.00 8,325.00 0.2000 oh Tukang Kayu 80,000.00 16,000.00 0.4000 oh Pekerja 70,000.00 28,000.00 0.0200 oh Kepala Tukang 85,000.00 1,700.00 0.0200 oh Mandor 90,000.00 1,800.00

    Total : 47,500.00 201,995.00 249,495.00

    2 1 M1 PENGUKURAN DAN PEMASANGAN BOWPLANK 0.0120 m3 Kayu Usuk Meranti 5/7 1,700,000.00 20,400.00 0.0200 kg Paku Biasa 2" - 5" 12,000.00 240.00 0.0070 m3 Kayu Papan Meranti 3/20 4,000,000.00 28,000.00 0.1000 oh Tukang Kayu 80,000.00 8,000.00 0.1000 oh Pekerja 70,000.00 7,000.00 0.0100 oh Kepala Tukang 85,000.00 850.00 0.0050 oh Mandor 90,000.00 450.00

    Total : 16,300.00 48,640.00 64,940.00

    3

    1.2500 btg Dolken Kayu 8 - 10/4m 90,000.00 112,500.00 0.1800 m3 Kayu Meranti 2,000,000.00 360,000.00 0.8500 kg Paku Biasa 2" - 5" 12,000.00 10,200.00 1.1000 kg Besi Strip 6,050.00 6,655.00 35.0000 kg Semen Portland 1,200.00 42,000.00 0.1500 m3 Pasir Pasang 150,000.00 22,500.00 0.1000 m3 Pasir Beton 140,000.00 14,000.00 0.1500 m3 Koral Beton 150,000.00 22,500.00 30.0000 bh Bata Merah 1,000.00 30,000.00 0.2500 lbr Seng Plat 45,000.00 11,250.00 2.0000 bh Jendela Nako 12,500.00 25,000.00 0.0800 m2 Kaca Polos 90,000.00 7,200.00 0.1500 bh Kunci Tanam 104,500.00 15,675.00 0.0600 lbr Plywood 4 mm 46,000.00 2,760.00 2.0000 oh Tukang Kayu 80,000.00 160,000.00 1.0000 oh Tukang Batu 80,000.00 80,000.00 2.0000 oh Pekerja 70,000.00 140,000.00 0.3000 oh Kepala Tukang 85,000.00 25,500.00 0.0500 oh Mandor 90,000.00 4,500.00

    Total : 410,000.00 682,240.00 1,092,240.00

    4 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT 1.7000 btg Bambu Sedang 14,000.00 23,800.00 0.2100 m3 Kayu Meranti 2,000,000.00 420,000.00 0.3000 kg Paku Biasa 2" - 5" 12,000.00 3,600.00 10.5000 kg Semen Portland 1,200.00 12,600.00 0.0300 m3 Pasir Beton 140,000.00 4,200.00 0.0500 m3 Koral Beton 150,000.00 7,500.00 1.5000 lbr Seng gelombang BJLS 28 40,000.00 60,000.00 2.0000 oh Tukang Kayu 80,000.00 160,000.00 1.0000 oh Pekerja 70,000.00 70,000.00 0.2000 oh Kepala Tukang 85,000.00 17,000.00 0.0500 oh Mandor 90,000.00 4,500.00

    Total : 251,500.00 531,700.00 783,200.00

    5 1 M2 PEMBUATAN RUMAH JAGA/KONSTRUKSI KAYU 3.0000 btg Bambu Sedang 14,000.00 42,000.00 0.2760 m3 Kayu Meranti 2,000,000.00 552,000.00 0.7000 kg Paku biasa 2" - 5" 12,000.00 8,400.00 1.5000 lbr Seng gelombang BJLS 28 40,000.00 60,000.00 1.5000 oh Tukang Kayu 80,000.00 120,000.00 1.0000 oh Pekerja 70,000.00 70,000.00 0.1500 oh Kepala Tukang 85,000.00 12,750.00 0.0500 oh Mandor 90,000.00 4,500.00

    Total : 207,250.00 662,400.00 869,650.00

    1 M1 PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 METER

    1 M2 PEMBUATAN KANTOR SEMENTARA, DENGAN LANTAI PLESTERAN

  • NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

    (Rp) (Rp) (Rp) (Rp)1 2 3 4 5 6

    6 1 M2 MEMBERSIHKAN LAPANGAN DAN PERATAAN 0.1000 oh Pekerja 70,000.00 7,000.00 0.0500 oh Mandor 90,000.00 4,500.00

    Total : 11,500.00 11,500.00

    7 1 M2 PEMBUATAN BEDENG BURUH 1.2500 btg Bambu Sedang 14,000.00 17,500.00 0.1860 m3 Kayu Meranti 2,000,000.00 372,000.00 0.3000 kg Paku Biasa 2" - 5" 12,000.00 3,600.00 18.0000 kg Semen Portland 1,200.00 21,600.00 0.0300 m3 Pasir Beton 140,000.00 4,200.00 0.0500 m3 Koral Beton 150,000.00 7,500.00 1.5000 lbr Seng gelombang BJLS 28 40,000.00 60,000.00 1.3500 lbr Plywood 4 mm 46,000.00 62,100.00 2.0000 oh Tukang Kayu 80,000.00 160,000.00 1.0000 oh Pekerja 70,000.00 70,000.00 0.2000 oh Kepala Tukang 85,000.00 17,000.00 0.0500 oh Mandor 90,000.00 4,500.00

    Total : 251,500.00 548,500.00 800,000.00

    8 1 M2 PEMBUATAN BAK ADUKAN UKURAN (40X50X20) CM 0.0360 m3 Kayu Terentang 2,000,000.00 72,000.00 0.0800 kg Paku Biasa 2" - 5" 12,000.00 960.00 1.0000 btg Kaso 5/7 56,000.00 56,000.00 0.3000 oh Tukang kayu 80,000.00 24,000.00 0.0015 oh Mandor 90,000.00 135.00

    Total : 24,135.00 128,960.00 153,095.00

    9 1 M2 PEMBUATAN STEGGER DARI BAMBU 1.0000 btg Bambu 12,000.00 12,000.00 0.2500 kg Tali Ijuk 33,000.00 8,250.00 0.0170 oh Tukang Kayu 80,000.00 1,360.00 0.0020 oh Pekerja 70,000.00 140.00 0.2500 oh Kepala Tukang 85,000.00 21,250.00 0.0130 oh Mandor 90,000.00 1,170.00

    23,920.00 20,250.00 44,170.00

    10 1 M2 PEMBUATAN JALAN SEMENTARA 0.1500 m3 Batu Kali / Batu Bulat 15/20 140,000.00 21,000.00 0.0900 m3 Batu Pecah 5 - 7 150,000.00 13,500.00 0.0100 m3 Pasir Pasang 150,000.00 1,500.00 1.0000 oh Pekerja 70,000.00 70,000.00 0.0500 oh Mandor 90,000.00 4,500.00

    Total : 74,500.00 36,000.00 110,500.00

    11 1 M3 BONGKARAN BETON BERTULANG 6.6670 oh Pekerja 70,000.00 466,690.00 0.3330 oh Mandor 90,000.00 29,970.00

    Total : 496,660.00 496,660.00

    12 1 M3 BONGKARAN DINDING TEMBOK BATA MERAH 6.6670 oh Pekerja 70,000.00 466,690.00 0.0330 oh Mandor 90,000.00 2,970.00

    Total : 469,660.00 469,660.00

    II PEKERJAAN TANAH (SNI 2835 : 2008)

    1 1 M3 GALIAN TANAH BIASA DALAM 1 METER 0.7500 oh Pekerja 70,000.00 52,500.00 0.0250 oh Mandor 90,000.00 2,250.00

    Total : 54,750.00 54,750.00 2 1 M3 GALIAN TANAH BIASA DALAM 2 METER

    0.9000 oh Pekerja 70,000.00 63,000.00 0.0450 oh Mandor 90,000.00 4,050.00

    Total : 67,050.00 67,050.00

    3 1 M3 GALIAN TANAH BIASA DALAM 3 METER 1.0500 oh Pekerja 70,000.00 73,500.00 0.0670 oh Mandor 90,000.00 6,030.00

    Total : 79,530.00 79,530.00

    4 1 M3 GALIAN TANAH KERAS DALAM 1METER 1.0000 oh Pekerja 70,000.00 70,000.00 0.0320 oh Mandor 90,000.00 2,880.00

    Total : 72,880.00 72,880.00

    5 1 M3 GALIAN TANAH CADAS DALAM 1 METER 1.5000 oh Pekerja 70,000.00 105,000.00 0.0600 oh Mandor 90,000.00 5,400.00

    Total : 110,400.00 110,400.00

  • NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

    (Rp) (Rp) (Rp) (Rp)1 2 3 4 5 6

    6 1 M3 GALIAN TANAH LUMPUR DALAM 1 METER 1.2000 oh Pekerja 70,000.00 84,000.00 0.0450 oh Mandor 90,000.00 4,050.00

    Total : 88,050.00 88,050.00

    7 1 M2 PEKERJAAN STRIPPING SETINGGI 1 METER 0.0500 oh Pekerja 70,000.00 3,500.00 0.0050 oh Mandor 90,000.00 450.00

    Total : 3,950.00 3,950.00

    8 1 M3 PEMBUANGAN TANAH SEJAUH 15 METER 0.3300 oh Pekerja 70,000.00 23,100.00 0.0100 oh Mandor 90,000.00 900.00

    Total : 24,000.00 24,000.00

    9 1 M3 URUGAN KEMBALI Mengurug Kembali 1 m3 galian dihitung dari 1/3 kali dari indeks pekerjaan galian

    10 1 M3 PEMADATAN TANAH ( Per 20 Cm ) 0.5000 oh Pekerja 70,000.00 35,000.00 0.0500 oh Mandor 90,000.00 4,500.00

    Total : 39,500.00 39,500.00

    11 1 M3 URUGAN PASIR 1.2000 m3 Pasir Urug 80,000.00 96,000.00 0.3000 oh Pekerja 70,000.00 21,000.00 0.0100 oh Mandor 90,000.00 900.00

    Total : 21,900.00 96,000.00 117,900.00

    12 1 M3 PEMASANGAN LAPISAN IJUK TEBAL 10 CM 6.0000 m3 Ijuk 1,500.00 9,000.00 0.1500 oh Pekerja 70,000.00 10,500.00 0.0150 oh Mandor 90,000.00 1,350.00

    Total : 11,850.00 9,000.00 20,850.00

    13 1 M3 URUGAN SIRTU PADAT Untuk Peninggian Lantai Bangunan 1.2000 m3 Sirtu 100,000.00 120,000.00 0.2500 oh Pekerja 70,000.00 17,500.00 0.0250 oh Mandor 90,000.00 2,250.00

    Total : 19,750.00 120,000.00 139,750.00

    14 1 M3 URUGAN TANAH PILIHAN DIPADATKAN 1.2000 m3 Tanah Urug 70,000.00 84,000.00 0.5000 oh Pekerja 70,000.00 35,000.00 0.0500 oh Mandor 90,000.00 4,500.00

    Total : 39,500.00 84,000.00 123,500.00 15 1 M3 URUGAN LIMESTONE PADAT

    1.2000 m3 Limestone 79,000.00 94,800.00 0.2500 oh Pekerja 70,000.00 17,500.00 0.0250 oh Mandor 90,000.00 2,250.00

    Total : 19,750.00 94,800.00 114,550.00

    III PEKERJAAN PONDASI (SNI 2836 : 2008)

    1 1 M3 BATU KALI CAMP. 1 PC : 3 PS 1.2000 m3 Batu Kali / Batu Bulat 15/20 140,000.00 168,000.00 202.0000 kg Semen Portland 1,200.00 242,400.00 0.4850 m3 Pasir Pasang 150,000.00 72,750.00 1.5000 oh Pekerja 70,000.00 105,000.00 0.7500 oh Tukang Batu 80,000.00 60,000.00 0.0750 oh Kepala Tukang 85,000.00 6,375.00 0.0750 oh Mandor 90,000.00 6,750.00

    Total : 178,125.00 483,150.00 661,275.00

    2 1 M3 BATU KALI CAMP. 1 PC : 4 PS 1.2000 m3 Batu Kali / Batu Bulat 15/20 140,000.00 168,000.00 163.0000 kg Semen Portland 1,200.00 195,600.00 0.5200 m3 Pasir Pasang 150,000.00 78,000.00 1.5000 oh Pekerja 70,000.00 105,000.00 0.7500 oh Tukang Batu 80,000.00 60,000.00 0.0750 oh Kepala Tukang 85,000.00 6,375.00 0.0750 oh Mandor 90,000.00 6,750.00

    Total : 178,125.00 441,600.00 619,725.00

  • NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

    (Rp) (Rp) (Rp) (Rp)1 2 3 4 5 6

    3 1 M3 BATU KALI CAMP. 1 PC : 5 PS 1.2000 m3 Batu Kali / Batu Bulat 15/20 140,000.00 168,000.00 136.0000 kg Semen Portland 1,200.00 163,200.00 0.5440 m3 Pasir Pasang 150,000.00 81,600.00 1.5000 oh Pekerja 70,000.00 105,000.00 0.7500 oh Tukang Batu 80,000.00 60,000.00 0.0750 oh Kepala Tukang 85,000.00 6,375.00 0.0750 oh Mandor 90,000.00 6,750.00

    Total : 178,125.00 412,800.00 590,925.00

    4 1 M3 BATU KALI CAMP. 1 PC : 6 PS 1.2000 m3 Batu Kali / Batu Bulat 15/20 140,000.00 168,000.00 117.0000 kg Semen Portland 1,200.00 140,400.00 0.5610 m3 Pasir Pasang 150,000.00 84,150.00 1.5000 oh Pekerja 70,000.00 105,000.00 0.7500 oh Tukang Batu 80,000.00 60,000.00 0.0750 oh Kepala Tukang 85,000.00 6,375.00 0.0750 oh Mandor 90,000.00 6,750.00

    Total : 178,125.00 392,550.00 570,675.00

    5 1 M3 BATU KALI CAMP. 1 PC : 8 PS 1.2000 m3 Batu Kali / Batu Bulat 15/20 140,000.00 168,000.00 91.0000 kg Semen Portland 1,200.00 109,200.00 0.5840 m3 Pasir Pasang 150,000.00 87,600.00 1.5000 oh Pekerja 70,000.00 105,000.00 0.7500 oh Tukang Batu 80,000.00 60,000.00 0.0750 oh Kepala Tukang 85,000.00 6,375.00 0.0750 oh Mandor 90,000.00 6,750.00

    Total : 178,125.00 364,800.00 542,925.00

    6 1 M3 PASANGAN PONDASI SIKLOP, 40% BATU KALI 0.4800 m3 Batu Kali / Batu Bulat 15/20 140,000.00 67,200.00 194.0000 kg Semen Portland 1,200.00 232,800.00 0.3120 m3 Pasir Beton 140,000.00 43,680.00 0.4680 m3 Koral Beton 150,000.00 70,200.00 126.0000 kg Besi Beton 7,111.00 895,986.00 1.8000 kg Kawat Beton 15,000.00 27,000.00 3.4000 oh Pekerja 70,000.00 238,000.00 0.8500 oh Tukang Batu 80,000.00 68,000.00 0.0850 oh Kepala Tukang 85,000.00 7,225.00 0.1700 oh Mandor 90,000.00 15,300.00

    328,525.00 1,336,866.00 1,665,391.00

    7 1 M3 PASANGAN PONDASI SUMURAN DIAMETER 1 M 0.4500 m3 Batu Kali / Batu Bulat 15/20 140,000.00 63,000.00 194.0000 kg Semen Portland 1,200.00 232,800.00 0.3120 m3 Pasir Beton 140,000.00 43,680.00 0.4680 m3 Koral Beton 150,000.00 70,200.00 2.4000 oh Pekerja 70,000.00 168,000.00 0.8000 oh Tukang Batu 80,000.00 64,000.00 0.0800 oh Kepala Tukang 85,000.00 6,800.00 0.1190 oh Mandor 90,000.00 10,710.00

    Total : 249,510.00 409,680.00 659,190.00

    8 1 M3 PASANGAN BATU KOSONG 1.2000 m3 Batu Kali / Batu Bulat 15/20 15/20 140,000.00 168,000.00 0.4320 m3 Pasir Urug 80,000.00 34,560.00 0.7800 oh Pekerja 70,000.00 54,600.00 0.3900 oh Tukang Batu 80,000.00 31,200.00 0.0390 oh Kepala Tukang 85,000.00 3,315.00 0.0390 oh Mandor 90,000.00 3,510.00

    Total : 92,625.00 202,560.00 295,185.00

    IV PEKERJAAN DINDING (SNI 6897 : 2008)

    11 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 2 PS

    140.0000 bh Bata Merah 5 x 11 x 22 cm 1,000.00 140,000.00 43.5000 kg Semen Portland 1,200.00 52,200.00 0.0800 m3 Pasir Pasang 150,000.00 12,000.00 0.6000 oh Pekerja 70,000.00 42,000.00 0.2000 oh Tukang Batu 80,000.00 16,000.00 0.0200 oh Kepala Tukang 85,000.00 1,700.00 0.0300 oh Mandor 90,000.00 2,700.00

    62,400.00 204,200.00 266,600.00

  • NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

    (Rp) (Rp) (Rp) (Rp)1 2 3 4 5 6

    2 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 3 PS 140.0000 bh Bata Merah 5 x 11 x 22 cm 1,000.00 140,000.00 32.9500 kg Semen Portland 1,200.00 39,540.00 0.0910 m3 Pasir Pasang 150,000.00 13,650.00 0.6000 oh Pekerja 70,000.00 42,000.00 0.2000 oh Tukang Batu 80,000.00 16,000.00 0.0200 oh Kepala Tukang 85,000.00 1,700.00 0.0300 oh Mandor 90,000.00 2,700.00

    62,400.00 193,190.00 255,590.00

    3 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 4 PS 140.0000 bh Bata Merah 5 x 11 x 22 cm 1,000.00 140,000.00 26.5500 kg Semen Portland 1,200.00 31,860.00 0.0930 m3 Pasir Pasang 150,000.00 13,950.00 0.6000 oh Pekerja 70,000.00 42,000.00 0.2000 oh Tukang Batu 80,000.00 16,000.00 0.0200 oh Kepala Tukang 85,000.00 1,700.00 0.0300 oh Mandor 90,000.00 2,700.00

    62,400.00 185,810.00 248,210.00

    4 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 5 PS 140.0000 bh Bata Merah 5 x 11 x 22 cm 1,000.00 140,000.00 22.2000 kg Semen Portland 1,200.00 26,640.00 0.1020 m3 Pasir Pasang 150,000.00 15,300.00 0.6000 oh Pekerja 70,000.00 42,000.00 0.2000 oh Tukang Batu 80,000.00 16,000.00 0.0200 oh Kepala Tukang 85,000.00 1,700.00 0.0300 oh Mandor 90,000.00 2,700.00

    62,400.00 181,940.00 244,340.00

    5 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 6 PS 140.0000 bh Bata Merah 5 x 11 x 22 cm 1,000.00 140,000.00 18.5000 kg Semen Portland 1,200.00 22,200.00 0.1220 m3 Pasir Pasang 150,000.00 18,300.00 0.6000 oh Pekerja 70,000.00 42,000.00 0.2000 oh Tukang Batu 80,000.00 16,000.00 0.0200 oh Kepala Tukang 85,000.00 1,700.00 0.0300 oh Mandor 90,000.00 2,700.00

    62,400.00 180,500.00 242,900.00

    6 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 2 PS 70.0000 bh Bata Merah 5 x 11 x 22 cm 1,000.00 70,000.00 18.9500 kg Semen Portland 1,200.00 22,740.00 0.0380 m3 Pasir Pasang 150,000.00 5,700.00 0.3000 oh Pekerja 70,000.00 21,000.00 0.1000 oh Tukang Batu 80,000.00 8,000.00 0.0100 oh Kepala Tukang 85,000.00 850.00 0.0150 oh Mandor 90,000.00 1,350.00

    31,200.00 98,440.00 129,640.00

    7 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 3 PS 70.0000 bh Bata Merah 5 x 11 x 22 cm 1,000.00 70,000.00 14.3700 kg Semen Portland 1,200.00 17,244.00 0.0400 m3 Pasir Pasang 150,000.00 6,000.00 0.3000 oh Pekerja 70,000.00 21,000.00 0.1000 oh Tukang Batu 80,000.00 8,000.00 0.0100 oh Kepala Tukang 85,000.00 850.00 0.0150 oh Mandor 90,000.00 1,350.00

    Total : 31,200.00 93,244.00 124,444.00

    8 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 4 PS 70.0000 bh Bata Merah 5 x 11 x 22 cm 1,000.00 70,000.00 11.5000 kg Semen Portland 1,200.00 13,800.00 0.0430 m3 Pasir Pasang 150,000.00 6,450.00 0.3000 oh Pekerja 70,000.00 21,000.00 0.1000 oh Tukang Batu 80,000.00 8,000.00 0.0100 oh Kepala Tukang 85,000.00 850.00 0.0150 oh Mandor 90,000.00 1,350.00

    Total : 31,200.00 90,250.00 121,450.00

    9 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 5 PS 70.0000 bh Bata Merah 5 x 11 x 22 cm 1,000.00 70,000.00 9.6800 kg Semen Portland 1,200.00 11,616.00 0.0450 m3 Pasir Pasang 150,000.00 6,750.00 0.3000 oh Pekerja 70,000.00 21,000.00 0.1000 oh Tukang Batu 80,000.00 8,000.00 0.0100 oh Kepala Tukang 85,000.00 850.00 0.0150 oh Mandor 90,000.00 1,350.00

    Total : 31,200.00 88,366.00 119,566.00

  • NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

    (Rp) (Rp) (Rp) (Rp)1 2 3 4 5 6

    10 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 6 PS 70.0000 bh Bata Merah 5 x 11 x 22 cm 1,000.00 70,000.00 8.3200 kg Semen Portland 1,200.00 9,984.00 0.0490 m3 Pasir Pasang 150,000.00 7,350.00 0.3000 oh Pekerja 70,000.00 21,000.00 0.1000 oh Tukang Batu 80,000.00 8,000.00 0.0100 oh Kepala Tukang 85,000.00 850.00 0.0150 oh Mandor 90,000.00 1,350.00

    Total : 31,200.00 87,334.00 118,534.00

    11 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 8 PS 70.0000 bh Bata Merah 5 x 11 x 22 cm 1,000.00 70,000.00 6.5000 kg Semen Portland 1,200.00 7,800.00 0.0500 m3 Pasir Pasang 150,000.00 7,500.00 0.3000 oh Pekerja 70,000.00 21,000.00 0.1000 oh Tukang Batu 80,000.00 8,000.00 0.0100 oh Kepala Tukang 85,000.00 850.00 0.0150 oh Mandor 90,000.00 1,350.00

    Total : 31,200.00 85,300.00 116,500.00

    12 1 M2 PASANGAN DINDING HOLLOWBLOCK (HB. 10) 12.5000 bh Batako 2,300.00 28,750.00 7.5000 kg Semen Portland 1,200.00 9,000.00 0.0270 m3 Pasir Pasang 150,000.00 4,050.00 1.9500 kg Besi Beton 8 mm 7,111.00 13,866.45 0.3200 oh Pekerja 70,000.00 22,400.00 0.1000 oh Tukang Batu 80,000.00 8,000.00 0.0100 oh Kepala Tukang 85,000.00 850.00 0.0150 oh Mandor 90,000.00 1,350.00

    Total : 32,600.00 55,666.45 88,266.45

    13 1 M2 PASANGAN DINDING HOLLOWBLOCK (HB. 10) TANPA BESI 12.5000 bh Batako 2,300.00 28,750.00 7.5000 kg Semen Portland 1,200.00 9,000.00 0.0270 m3 Pasir Pasang 150,000.00 4,050.00 0.3200 oh Pekerja 70,000.00 22,400.00 0.1000 oh Tukang Batu 80,000.00 8,000.00 0.0100 oh Kepala Tukang 85,000.00 850.00 0.0150 oh Mandor 90,000.00 1,350.00

    Total : 32,600.00 41,800.00 74,400.00

    14 1 M2 PASANGAN DINDING Terawang/Roster (12 x 11 x 24) CM 30.0000 bh Roster Keramik 48,000.00 1,440,000.00 11.0000 kg Semen Portland 1,200.00 13,200.00 0.0350 m3 Pasir Pasang 150,000.00 5,250.00 0.3000 oh Pekerja 70,000.00 21,000.00 0.1000 oh Tukang Batu 80,000.00 8,000.00 0.0100 oh Kepala Tukang 85,000.00 850.00 0.0150 oh Mandor 90,000.00 1,350.00

    Total : 31,200.00 1,458,450.00 1,489,650.00

    15 1 M2 PASANGAN DINDING BEDEG, RANGKA KAYU 1.5000 m2 Bedeg/Bilik Bambu Kelas I 32,000.00 48,000.00 0.0140 m3 Kayu kamper usuk/reng 5,700,000.00 79,800.00 0.0120 kg Paku Biasa 12,000.00 144.00 0.0030 m3 List Kayu 2/4 5,700,000.00 17,100.00 0.1000 oh Pekerja 70,000.00 7,000.00 0.0500 oh Tukang Kayu 80,000.00 4,000.00 0.0050 oh Kepala Tukang 85,000.00 425.00 0.0020 oh Mandor 90,000.00 180.00

    Total : 11,605.00 145,044.00 156,649.00

    V PEKERJAAN PLESTERAN (SNI 2837 : 2008)

    1 1 M2 PLESTERAN CAMP. 1 PC : 1 PS TEBAL 15 MM 15.5040 kg Semen Portland 1,200.00 18,604.80 0.0160 m3 Pasir Pasang 150,000.00 2,400.00 0.3000 oh Pekerja 70,000.00 21,000.00 0.1500 oh Tukang Batu 80,000.00 12,000.00 0.0150 oh Kepala Tukang 85,000.00 1,275.00 0.0150 oh Mandor 90,000.00 1,350.00

    Total : 35,625.00 21,004.80 56,629.80 2 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 15 MM

    10.2240 kg Semen Portland 1,200.00 12,268.80 0.0200 m3 Pasir Pasang 150,000.00 3,000.00 0.3000 oh Pekerja 70,000.00 21,000.00 0.1500 oh Tukang Batu 80,000.00 12,000.00 0.0150 oh Kepala Tukang 85,000.00 1,275.00 0.0150 oh Mandor 90,000.00 1,350.00

    Total : 35,625.00 15,268.80 50,893.80

  • NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

    (Rp) (Rp) (Rp) (Rp)1 2 3 4 5 6

    3 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 15 MM 7.7760 kg Semen Portland 1,200.00 9,331.20 0.0230 m3 Pasir Pasang 150,000.00 3,450.00 0.3000 oh Pekerja 70,000.00 21,000.00 0.1500 oh Tukang Batu 80,000.00 12,000.00 0.0150 oh Kepala Tukang 85,000.00 1,275.00 0.0150 oh Mandor 90,000.00 1,350.00

    Total : 35,625.00 12,781.20 48,406.20

    4 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 15 MM 6.2400 kg Semen Portland 1,200.00 7,488.00 0.0240 m3 Pasir Pasang 150,000.00 3,600.00 0.3000 oh Pekerja 70,000.00 21,000.00 0.1500 oh Tukang Batu 80,000.00 12,000.00 0.0150 oh Kepala Tukang 85,000.00 1,275.00 0.0150 oh Mandor 90,000.00 1,350.00

    Total : 35,625.00 11,088.00 46,713.00

    5 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 15 MM 5.1840 kg Semen Portland 1,200.00 6,220.80 0.0260 m3 Pasir Pasang 150,000.00 3,900.00 0.3000 oh Pekerja 70,000.00 21,000.00 0.1500 oh Tukang Batu 80,000.00 12,000.00 0.0150 oh Kepala Tukang 85,000.00 1,275.00 0.0150 oh Mandor 90,000.00 1,350.00

    Total : 35,625.00 10,120.80 45,745.80

    6 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 15 MM 4.4160 kg Semen Portland 1,200.00 5,299.20 0.0270 m3 Pasir Pasang 150,000.00 4,050.00 0.3000 oh Pekerja 70,000.00 21,000.00 0.1500 oh Tukang Batu 80,000.00 12,000.00 0.0150 oh Kepala Tukang 85,000.00 1,275.00 0.0150 oh Mandor 90,000.00 1,350.00

    Total : 35,625.00 9,349.20 44,974.20

    7 1 M2 PLESTERAN CAMP. 1 PC : 8 PS TEBAL 15 MM 3.4560 kg Semen Portland 1,200.00 4,147.20 0.0290 m3 Pasir Pasang 150,000.00 4,350.00 0.3000 oh Pekerja 70,000.00 21,000.00 0.1500 oh Tukang Batu 80,000.00 12,000.00 0.0150 oh Kepala Tukang 85,000.00 1,275.00 0.0150 oh Mandor 90,000.00 1,350.00

    Total : 35,625.00 8,497.20 44,122.20

    8 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 20 MM 13.6320 kg Semen Portland 1,200.00 16,358.40 0.0270 m3 Pasir Pasang 150,000.00 4,050.00 0.4000 oh Pekerja 70,000.00 28,000.00 0.2000 oh Tukang Batu 80,000.00 16,000.00 0.0200 oh Kepala Tukang 85,000.00 1,700.00 0.0220 oh Mandor 90,000.00 1,980.00

    Total : 47,680.00 20,408.40 68,088.40

    9 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 20 MM 10.3680 kg Semen Portland 1,200.00 12,441.60 0.0310 m3 Pasir Pasang 150,000.00 4,650.00 0.4000 oh Pekerja 70,000.00 28,000.00 0.2000 oh Tukang Batu 80,000.00 16,000.00 0.0200 oh Kepala Tukang 85,000.00 1,700.00 0.0220 oh Mandor 90,000.00 1,980.00

    Total : 47,680.00 17,091.60 64,771.60

    10 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 20 MM 8.3200 kg Semen Portland 1,200.00 9,984.00 0.0320 m3 Pasir Pasang 150,000.00 4,800.00 0.4000 oh Pekerja 70,000.00 28,000.00 0.2000 oh Tukang Batu 80,000.00 16,000.00 0.0200 oh Kepala Tukang 85,000.00 1,700.00 0.0220 oh Mandor 90,000.00 1,980.00

    Total : 47,680.00 14,784.00 62,464.00 11 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 20 MM

    6.9120 kg Semen Portland 1,200.00 8,294.40 0.0350 m3 Pasir Pasang 150,000.00 5,250.00 0.4000 oh Pekerja 70,000.00 28,000.00 0.2000 oh Tukang Batu 80,000.00 16,000.00 0.0200 oh Kepala Tukang 85,000.00 1,700.00 0.0220 oh Mandor 90,000.00 1,980.00

    Total : 47,680.00 13,544.40 61,224.40

  • NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

    (Rp) (Rp) (Rp) (Rp)1 2 3 4 5 6

    12 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 20 MM 5.8880 kg Semen Portland 1,200.00 7,065.60 0.0360 m3 Pasir Pasang 150,000.00 5,400.00 0.4000 oh Pekerja 70,000.00 28,000.00 0.2000 oh Tukang Batu 80,000.00 16,000.00 0.0200 oh Kepala Tukang 85,000.00 1,700.00 0.0220 oh Mandor 90,000.00 1,980.00

    Total : 47,680.00 12,465.60 60,145.60

    13 1 M2 PLESTERAN SKONING 1 PC : 2 PS, TEBAL 10 MM 0.5000 kg Semen Portland 1,200.00 600.00 0.0130 m3 Pasir Pasang 150,000.00 1,950.00 0.0800 oh Pekerja 70,000.00 5,600.00 0.4000 oh Tukang Batu 80,000.00 32,000.00 0.0400 oh Kepala Tukang 85,000.00 3,400.00 0.0040 oh Mandor 90,000.00 360.00

    Total : 41,360.00 2,550.00 43,910.00

    14 1 M2 PLESTERAN CIPRAT 1 PC : 2 PS 4.3200 kg Semen Portland 1,200.00 5,184.00 0.0060 m3 Pasir Pasang 150,000.00 900.00 0.3000 oh Pekerja 70,000.00 21,000.00 0.1000 oh Tukang Batu 80,000.00 8,000.00 0.0100 oh Kepala Tukang 85,000.00 850.00 0.0150 oh Mandor 90,000.00 1,350.00

    Total : 31,200.00 6,084.00 37,284.00

    151 M2 FINISHING SIAR PASANGAN DINDING BATA MERAH (=20 M')

    3.1080 kg Semen Portland 1,200.00 3,729.60 0.1500 oh Pekerja 70,000.00 10,500.00 0.0750 oh Tukang Batu 80,000.00 6,000.00 0.0080 oh Kepala Tukang 85,000.00 680.00 0.0080 oh Mandor 90,000.00 720.00

    Total : 17,900.00 3,729.60 21,629.60

    16

    1.6000 kg Semen Portland 1,200.00 1,920.00 0.0700 oh Pekerja 70,000.00 4,900.00 0.0350 oh Tukang Batu 80,000.00 2,800.00 0.0040 oh Kepala Tukang 85,000.00 340.00 0.0040 oh Mandor 90,000.00 360.00

    Total : 8,400.00 1,920.00 10,320.00

    171 M2 FINISHING SIAR PASANGAN BATU KALI ADUKAN 1PC : 2 PS

    6.3400 kg Semen Portland 1,200.00 7,608.00 0.0120 m3 Pasir Pasang 150,000.00 1,800.00 0.3000 oh Pekerja 70,000.00 21,000.00 0.1500 oh Tukang Batu 80,000.00 12,000.00 0.0150 oh Kepala Tukang 85,000.00 1,275.00 0.0150 oh Mandor 90,000.00 1,350.00

    Total : 35,625.00 9,408.00 45,033.00

    18 1 M2 PEKERJAAN ACIAN 3.2500 zak Semen Portland 50 Kg 1,200.00 3,900.00 0.2000 oh Pekerja 70,000.00 14,000.00 0.1000 oh Tukang Labur/Cat 80,000.00 8,000.00 0.0100 oh Kepala Tukang 85,000.00 850.00 0.0100 oh Mandor 90,000.00 900.00

    Total : 23,750.00 3,900.00 27,650.00 VI PEKERJAAN KAYU (SNI 3434 : 2008)

    1

    1.1000 m3 Balok Kayu Kamper 7,700,000.00 8,470,000.00 1.2500 Kg Paku 10 Cm 12,000.00 15,000.00 1.0000 Kg Lem Kayu 12,500.00 12,500.00 7.0000 oh Pekerja 70,000.00 490,000.00 21.0000 oh Tukang Kayu 80,000.00 1,680,000.00 2.1000 oh Kepala Tukang 85,000.00 178,500.00 0.3500 oh Mandor 90,000.00 31,500.00

    Total : 2,380,000.00 8,497,500.00 10,877,500.00

    1 M2 FINISHING SIAR PASANGAN DINDING CONBLOCK EKSPOSE (= 8 M')

    MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS I

  • NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

    (Rp) (Rp) (Rp) (Rp)1 2 3 4 5 6

    2

    1.2000 m3 Balok Kayu kruing 4,200,000.00 5,040,000.00 1.2500 Kg Paku 10 Cm 12,000.00 15,000.00 1.0000 Kg Lem Kayu 12,500.00 12,500.00 6.0000 oh Pekerja 70,000.00 420,000.00 18.0000 oh Tukang Kayu 80,000.00 1,440,000.00 1.8000 oh Kepala Tukang 85,000.00 153,000.00 0.3000 oh Mandor 90,000.00 27,000.00

    Total : 2,040,000.00 5,067,500.00 7,107,500.00

    3

    0.0400 m3 Papan Kayu Kamper 7,900,000.00 316,000.00 0.0500 Kg Paku 5-7 Cm 12,000.00 600.00 0.3500 oh Pekerja 70,000.00 24,500.00 1.0500 oh Tukang Kayu 80,000.00 84,000.00 0.1050 oh Kepala Tukang 85,000.00 8,925.00 0.0180 oh Mandor 90,000.00 1,620.00

    Total : 119,045.00 316,600.00 435,645.00

    4

    0.0400 m3 Papan Kayu Kruing 6,000,000.00 240,000.00 0.0500 Kg Paku 5-7 Cm 12,000.00 600.00 0.3500 oh Pekerja 70,000.00 24,500.00 1.0500 oh Tukang Kayu 80,000.00 84,000.00 0.1050 oh Kepala Tukang 85,000.00 8,925.00 0.0180 oh Mandor 90,000.00 1,620.00

    Total : 119,045.00 240,600.00 359,645.00

    5

    0.0400 m3 Papan Kayu Kamper 7,900,000.00 316,000.00 0.5000 Kg Lem Kayu 12,500.00 6,250.00 1.0000 oh Pekerja 70,000.00 70,000.00 3.0000 oh Tukang Kayu 80,000.00 240,000.00 0.3000 oh Kepala Tukang 85,000.00 25,500.00 0.0500 oh Mandor 90,000.00 4,500.00

    Total : 340,000.00 322,250.00 662,250.00

    6

    0.0240 m3 Papan Kayu Kamper 7,900,000.00 189,600.00 0.3000 Kg Lem Kayu 12,500.00 3,750.00 0.8000 oh Pekerja 70,000.00 56,000.00 2.4000 oh Tukang Kayu 80,000.00 192,000.00 0.2400 oh Kepala Tukang 85,000.00 20,400.00 0.0400 oh Mandor 90,000.00 3,600.00

    Total : 272,000.00 193,350.00 465,350.00

    7

    0.0640 m3 Papan Kayu Kamper 7,900,000.00 505,600.00 0.5000 Kg Lem Kayu 12,500.00 6,250.00 1.0000 oh Pekerja 70,000.00 70,000.00 3.0000 oh Tukang Kayu 80,000.00 240,000.00 0.3000 oh Kepala Tukang 85,000.00 25,500.00 0.0500 oh Mandor 90,000.00 4,500.00

    Total : 340,000.00 511,850.00 851,850.00

    8

    0.0250 m3 Papan Kayu Kamper 7,900,000.00 197,500.00 0.0300 Kg Paku 1-2,5 Cm 12,000.00 360.00 0.5000 Kg Lem Kayu 12,500.00 6,250.00 1.0000 Lbr Plywood 4 mm 46,000.00 46,000.00 1.0000 oh Pekerja 70,000.00 70,000.00 3.0000 oh Tukang Kayu 80,000.00 240,000.00 0.3000 oh Kepala Tukang 85,000.00 25,500.00 0.0500 oh Mandor 90,000.00 4,500.00

    Total : 340,000.00 250,110.00 590,110.00

    MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS II/III

    MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP STANDAR KAYU KELAS II

    MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP SEDERHANA KAYU KELAS III

    MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL KAYU KELAS I/II

    MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA, KAYU KELAS I/II

    MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA JALUSI, KAYU KELAS I/II

    MEMBUAT 1 M2 DAUN PINTU PLYWOOD RANGKAP RANGKA TERTUTUP, KAYU KELAS II (Lebar Sampai 90 Cm)

  • NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

    (Rp) (Rp) (Rp) (Rp)1 2 3 4 5 6

    9

    0.0256 m3 Papan Kayu Kamper 7,900,000.00 202,240.00 0.0300 Kg Paku 1-2,5 Cm 12,000.00 360.00 0.5000 Kg Lem Kayu 12,500.00 6,250.00 1.0000 Lbr Plywood 4 mm 46,000.00 46,000.00 0.8000 oh Pekerja 70,000.00 56,000.00 2.4000 oh Tukang Kayu 80,000.00 192,000.00 0.2400 oh Kepala Tukang 85,000.00 20,400.00 0.0400 oh Mandor 90,000.00 3,600.00

    Total : 272,000.00 254,850.00 526,850.00

    10 MEMASANG 1 M2 JALUSI KUSEN, KAYU KELAS I/II 0.0600 m3 Papan Kayu Kamper 7,900,000.00 474,000.00 0.1500 Kg Paku 1-2,5 Cm 12,000.00 1,800.00 0.6700 oh Pekerja 70,000.00 46,900.00 2.0000 oh Tukang Kayu 80,000.00 160,000.00 0.2000 oh Kepala Tukang 85,000.00 17,000.00 0.3350 oh Mandor 90,000.00 30,150.00

    Total : 254,050.00 475,800.00 729,850.00

    11

    0.0256 m3 Papan Kayu Kamper 7,900,000.00 202,240.00 0.0300 Kg Paku 1-2,5 Cm 12,000.00 360.00 0.5000 Kg Lem Kayu 12,500.00 6,250.00 1.0000 Lbr Teakwood 4 mm uk 90x220 cm 55,000.00 55,000.00 0.8000 oh Pekerja 70,000.00 56,000.00 2.4000 oh Tukang Kayu 80,000.00 192,000.00 0.2400 oh Kepala Tukang 85,000.00 20,400.00 0.0400 oh Mandor 90,000.00 3,600.00

    Total : 272,000.00 263,850.00 535,850.00

    12

    0.0250 m3 Papan Kayu Kamper 7,900,000.00 197,500.00 0.0300 Kg Paku 1-2,5 Cm 12,000.00 360.00 0.8000 Kg Lem Kayu 12,500.00 10,000.00 1.0000 Lbr Teakwood 4 mm uk 90x220 cm 55,000.00 55,000.00 0.5000 Lbr Formika 80,000.00 40,000.00 0.8000 oh Pekerja 70,000.00 56,000.00 2.4000 oh Tukang Kayu 80,000.00 192,000.00 0.2400 oh Kepala Tukang 85,000.00 20,400.00 0.0400 oh Mandor 90,000.00 3,600.00

    Total : 272,000.00 302,860.00 574,860.00

    13

    1.1000 m3 Balok Kayu Kamper 7,700,000.00 8,470,000.00 15.0000 Kg Besi Strip Tebal 5 cm 6,050.00 90,750.00 5.6000 Kg Paku 12 Cm 12,000.00 67,200.00 4.0000 oh Pekerja 70,000.00 280,000.00 12.0000 oh Tukang Kayu 80,000.00 960,000.00 1.2000 oh Kepala Tukang 85,000.00 102,000.00 0.2000 oh Mandor 90,000.00 18,000.00

    Total : 1,360,000.00 8,627,950.00 9,987,950.00

    14

    1.2000 m3 Balok Kayu Kamper 7,700,000.00 9,240,000.00 15.0000 Kg Besi Strip Tebal 5 cm 6,050.00 90,750.00 5.6000 Kg Paku 12 Cm 12,000.00 67,200.00 6.7000 oh Pekerja 70,000.00 469,000.00 20.1000 oh Tukang Kayu 80,000.00 1,608,000.00 2.0100 oh Kepala Tukang 85,000.00 170,850.00 0.3350 oh Mandor 90,000.00 30,150.00

    Total : 2,278,000.00 9,397,950.00 11,675,950.00

    15 MEMASANG 1 M3 KONSTRUKSI GORDENG, KAYU KELAS II

    1.1000 m3 Balok Kayu Kamper 7,700,000.00 8,470,000.00 15.0000 Kg Besi Strip Tebal 5 cm 6,050.00 90,750.00 3.0000 Kg Paku 12 Cm 12,000.00 36,000.00 2.4000 oh Pekerja 70,000.00 168,000.00 7.2000 oh Tukang Kayu 80,000.00 576,000.00 0.7200 oh Kepala Tukang 85,000.00 61,200.00 0.1200 oh Mandor 90,000.00 10,800.00

    Total : 816,000.00 8,596,750.00 9,412,750.00

    MEMBUAT 1 M2 DAUN PINTU PLYWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS I/II

    MEMBUAT 1 M2 TEAKWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS I

    MEMBUAT 1 M2 TEAKWOOD RANGKAP LAPIS FORMIKA RANGKA EXPOSE, KAYU KELAS II

    MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KELAS I,II,III Bentang 6 M'

    MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA EXPOSE, KAYU KELAS I

  • NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

    (Rp) (Rp) (Rp) (Rp)1 2 3 4 5 6

    16

    0.0140 m3 Kaso-Kaso ( 5 x 7 ) Cm 1,700,000.00 23,800.00 0.0036 m3 Reng ( 2 x 3 ) Cm 5,700,000.00 20,520.00 0.2500 Kg Paku 5 Cm dan 10 Cm 12,000.00 3,000.00 0.1000 oh Pekerja 70,000.00 7,000.00 0.1000 oh Tukang Kayu 80,000.00 8,000.00 0.0100 oh Kepala Tukang 85,000.00 850.00 0.0050 oh Mandor 90,000.00 450.00

    Total : 16,300.00 47,320.00 63,620.00

    17

    0.0140 m3 Kaso-Kaso ( 5 x 7 ) Cm 1,700,000.00 23,800.00 0.0072 m3 Reng ( 2 x 3 ) Cm 5,700,000.00 41,040.00 0.2500 Kg Paku 5 Cm dan 10 Cm 12,000.00 3,000.00 0.1000 oh Pekerja 70,000.00 7,000.00 0.1000 oh Tukang Kayu 80,000.00 8,000.00 0.0100 oh Kepala Tukang 85,000.00 850.00 0.0050 oh Mandor 90,000.00 450.00

    Total : 16,300.00 67,840.00 84,140.00

    18 MEMASANG 1 M2 RANGKA ATAP SIRAP, KAYU KELAS II

    0.1650 m3 Balok Kayu Kamper 7,700,000.00 1,270,500.00 0.2000 Kg Paku 5 Cm dan 10 Cm 12,000.00 2,400.00 0.1200 oh Pekerja 70,000.00 8,400.00 0.1200 oh Tukang Kayu 80,000.00 9,600.00 0.0120 oh Kepala Tukang 85,000.00 1,020.00 0.0060 oh Mandor 90,000.00 540.00

    Total : 19,560.00 1,272,900.00 1,292,460.00

    19

    0.0154 m3 Kaso-Kaso ( 5 x 7 ) Cm 1,700,000.00 26,180.00 0.2000 Kg Paku 7 Cm dan 10 Cm 12,000.00 2,400.00 0.1500 oh Pekerja 70,000.00 10,500.00 0.3000 oh Tukang Kayu 80,000.00 24,000.00 0.0300 oh Kepala Tukang 85,000.00 2,550.00 0.0750 oh Mandor 90,000.00 6,750.00

    Total : 43,800.00 28,580.00 72,380.00

    20

    0.0163 m3 Kaso-Kaso ( 5 x 7 ) Cm 1,700,000.00 27,710.00 0.2500 Kg Paku 7 Cm dan 10 Cm 12,000.00 3,000.00 0.2000 oh Pekerja 70,000.00 14,000.00 0.3000 oh Tukang Kayu 80,000.00 24,000.00 0.0300 oh Kepala Tukang 85,000.00 2,550.00 0.0100 oh Mandor 90,000.00 900.00

    Total : 41,450.00 30,710.00 72,160.00

    21

    0.0108 m3 Papan Kayu Kamper 7,900,000.00 85,320.00 0.1000 Kg Paku 5 Cm dan 7 Cm 12,000.00 1,200.00 0.1000 oh Pekerja 70,000.00 7,000.00 0.2000 oh Tukang Kayu 80,000.00 16,000.00 0.0200 oh Kepala Tukang 85,000.00 1,700.00 0.0050 oh Mandor 90,000.00 450.00

    Total : 25,150.00 86,520.00 111,670.00

    22

    0.0110 m3 Papan Kayu Kamper 7,900,000.00 86,900.00 0.0500 Kg Paku 5 Cm dan 7 Cm 12,000.00 600.00 0.1000 oh Pekerja 70,000.00 7,000.00 0.2000 oh Tukang Kayu 80,000.00 16,000.00 0.0200 oh Kepala Tukang 85,000.00 1,700.00 0.0050 oh Mandor 90,000.00 450.00

    Total : 25,150.00 87,500.00 112,650.00

    MEMASANG 1 M2 RANGKA ATAP GENTENG KERAMIK, KAYU KELAS II

    MEMASANG 1 M2 RANGKA ATAP GENTENG BETON, KAYU KELAS II

    MEMASANG 1 M2 RANGKA LANGIT-LANGIT (50 X 100), KAYU KELAS II/III

    MEMASANG 1 M2 RANGKA LANGIT-LANGIT (60 X 60) CM, KAYU KELAS II/III

    MEMASANG 1 M' LISPLANK UKURAN (3 X 20) CM, KAYU KELAS I/II

    MEMASANG 1 M' LISPLANK UKURAN (3 X 30) CM, KAYU KELAS I/II

  • NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

    (Rp) (Rp) (Rp) (Rp)1 2 3 4 5 6

    23

    0.0280 m3 Balok Kayu Kamper 7,700,000.00 215,600.00 0.1500 Kg Paku 5 Cm dan 7 Cm 12,000.00 1,800.00 0.1500 oh Pekerja 70,000.00 10,500.00 0.4500 oh Tukang Kayu 80,000.00 36,000.00 0.0450 oh Kepala Tukang 85,000.00 3,825.00 0.0080 oh Mandor 90,000.00 720.00

    Total : 51,045.00 217,400.00 268,445.00

    24

    0.0280 m3 Balok Kayu Kamper 7,700,000.00 215,600.00 0.1500 Kg Paku 5 Cm dan 7 Cm 12,000.00 1,800.00 0.8600 Lbr Teakwood 4 mm uk 90x220 cm 55,000.00 47,300.00 0.5600 Kg Lem Kayu 12,500.00 7,000.00 0.1500 oh Pekerja 70,000.00 10,500.00 0.4500 oh Tukang Kayu 80,000.00 36,000.00 0.0450 oh Kepala Tukang 85,000.00 3,825.00 0.0080 oh Mandor 90,000.00 720.00

    Total : 51,045.00 271,700.00 322,745.00

    25

    0.0280 m3 Balok Kayu Kamper 7,700,000.00 215,600.00 0.1500 Kg Paku 5 Cm dan 7 Cm 12,000.00 1,800.00 0.8600 Lbr Plywood tebal 4 mm uk 120 x 240 cm 46,000.00 39,560.00 0.5600 Kg Lem Kayu 12,500.00 7,000.00 0.2000 oh Pekerja 70,000.00 14,000.00 0.6000 oh Tukang Kayu 80,000.00 48,000.00 0.0600 oh Kepala Tukang 85,000.00 5,100.00 0.0100 oh Mandor 90,000.00 900.00

    Total : 68,000.00 263,960.00 331,960.00

    26 MEMASANG 1 M2 LAMBRIZIRING DARI PAPAN KAYU KELAS I

    0.0070 m3 Papan Kayu Kamper 7,900,000.00 55,300.00 0.1000 Kg Paku 5 Cm dan 10 Cm 12,000.00 1,200.00 0.1500 Kg Paku Skrup 10 cm 16,500.00 2,475.00 0.6000 oh Pekerja 70,000.00 42,000.00 1.8000 oh Tukang Kayu 80,000.00 144,000.00 0.1800 oh Kepala Tukang 85,000.00 15,300.00 0.0300 oh Mandor 90,000.00 2,700.00

    Total : 204,000.00 58,975.00 262,975.00

    27

    0.4000 Lbr Plywood tebal 4 mm uk 120 x 240 cm 46,000.00 18,400.00 0.0500 Kg Paku 1 Cm dan 2.5 Cm 12,000.00 600.00 0.0250 oh Pekerja 70,000.00 1,750.00 0.0750 oh Tukang Kayu 80,000.00 6,000.00 0.0080 oh Kepala Tukang 85,000.00 680.00 0.0010 oh Mandor 90,000.00 90.00

    Total : 8,520.00 19,000.00 27,520.00

    VII PEKERJAAN BETON ( SNI 7394:2008)1 1 M3 MEMBUAT BETON 1 PC : 3 PS : 5 KR

    218.0000 kg Semen Portland 1,200.00 261,600.00 0.5200 m3 Pasir Beton 140,000.00 72,800.00 0.8700 m3 Koral Beton 150,000.00 130,500.00 1.6500 oh Pekerja 70,000.00 115,500.00 0.2500 oh Tukang Batu 80,000.00 20,000.00 0.0250 oh Kepala Tukang 85,000.00 2,125.00 0.0800 oh Mandor 90,000.00 7,200.00

    144,825.00 464,900.00 609,725.00

    2 1 M3 MEMBUAT BETON 1 PC : 2 PS : 4 KR 232.0000 kg Semen Portland 1,200.00 278,400.00 0.5200 m3 Pasir Beton 140,000.00 72,800.00 0.7800 m3 Koral Beton 150,000.00 117,000.00 1.6500 oh Pekerja 70,000.00 115,500.00 0.2500 oh Tukang Batu 80,000.00 20,000.00 0.0250 oh Kepala Tukang 85,000.00 2,125.00 0.0800 oh Mandor 90,000.00 7,200.00

    Total : 144,825.00 468,200.00 613,025.00

    MEMASANG 1 M2 RANGKA DINDING PEMISAH (60 X 120) CM, KAYU KELAS II/III

    MEMASANG 1 M2 RANGKA DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA KAYU KELAS II

    MEMASANG 1 M2 RANGKA DINDING PEMISAH PLYWOOD RANGKAP, RANGKA KAYU KELAS II

    MEMASANG 1 M2 LAMBRIZIRING DARI PLYWOOD UKURAN (120 X 240) CM

  • NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

    (Rp) (Rp) (Rp) (Rp)1 2 3 4 5 6

    3 1 M3 MEMBUAT BETON 1 PC : 2 PS : 3 KR 280.0000 kg Semen Portland 1,200.00 336,000.00 0.4500 m3 Pasir Beton 140,000.00 63,000.00 0.9000 m3 Koral Beton 150,000.00 135,000.00 1.6500 oh Pekerja 70,000.00 115,500.00 0.2500 oh Tukang Batu 80,000.00 20,000.00 0.0250 oh Kepala Tukang 85,000.00 2,125.00 0.0800 oh Mandor 90,000.00 7,200.00

    Total : 144,825.00 534,000.00 678,825.00

    4 PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR 10.5000 kg Besi Beton (Polos/ Ulir) 7,111.00 74,665.50 0.1500 kg Kawat Beton 15,000.00 2,250.00 0.0700 oh Pekerja 70,000.00 4,900.00 0.0700 oh Tukang Besi 80,000.00 5,600.00 0.0070 oh Kepala Tukang 85,000.00 595.00 0.0040 oh Mandor 90,000.00 360.00

    Total : 11,455.00 76,915.50 88,370.50

    5 1 M2 PASANG BEKISTING UNTUK PONDASI 0.0400 m3 Kayu Kelas III 2,000,000.00 80,000.00 0.3000 kg Paku Biasa 5' - 10' 12,000.00 3,600.00 0.1000 ltr Minyak Bekisting 15,000.00 1,500.00 0.5200 oh Pekerja 70,000.00 36,400.00 0.2600 oh Tukang Kayu 80,000.00 20,800.00 0.0260 oh Kepala Tukang 85,000.00 2,210.00 0.0260 oh Mandor 90,000.00 2,340.00

    Total : 61,750.00 85,100.00 146,850.00

    6 1 M2 PASANG BEKISTING UNTUK SLOOF 0.0400 m3 Kayu Kelas III 2,000,000.00 80,000.00 0.3000 kg Paku Biasa 5' - 10' 12,000.00 3,600.00 0.1000 ltr Minyak Bekisting 15,000.00 1,500.00 0.5200 oh Pekerja 70,000.00 36,400.00 0.2600 oh Tukang Kayu 80,000.00 20,800.00 0.0260 oh Kepala Tukang 85,000.00 2,210.00 0.0260 oh Mandor 90,000.00 2,340.00

    Total : 61,750.00 85,100.00 146,850.00

    7 1 M2 PASANG BEKISTING UNTUK KOLOM 0.0400 m3 Kayu Kelas III 2,000,000.00 80,000.00 0.4000 kg Paku Biasa 5' - 12' 12,000.00 4,800.00 0.2000 ltr Minyak Bekisting 15,000.00 3,000.00 0.0150 m3 Kayu Usuk 4/6 4,000,000.00 60,000.00 0.3500 lbr Plywood 9 mm 105,250.00 36,837.50 2.0000 btg Dolken Kayu 8" - 10"/4 m 90,000.00 180,000.00 0.6600 oh Pekerja 70,000.00 46,200.00 0.3300 oh Tukang Kayu 80,000.00 26,400.00 0.0330 oh Kepala Tukang 85,000.00 2,805.00 0.0330 oh Mandor 90,000.00 2,970.00

    Total : 78,375.00 364,637.50 443,012.50

    8 1 M2 PASANG BEKISTING UNTUK BALOK 0.0400 m3 Kayu Kelas III 2,000,000.00 80,000.00 0.4000 kg Paku Biasa 5' - 12' 12,000.00 4,800.00 0.2000 ltr Minyak Bekisting 15,000.00 3,000.00 0.0180 m3 Kayu Usuk 4/6 4,000,000.00 72,000.00 0.3500 lbr Plywood 9 mm 105,250.00 36,837.50 2.0000 btg Dolken Kayu 8" - 10"/4m 90,000.00 180,000.00 0.6600 oh Pekerja 70,000.00 46,200.00 0.3300 oh Tukang Kayu 80,000.00 26,400.00 0.0330 oh Kepala Tukang 85,000.00 2,805.00 0.0330 oh Mandor 90,000.00 2,970.00

    Total : 78,375.00 376,637.50 455,012.50

    9 1 M2 PASANG BEKISTING UNTUK LANTAI 0.0400 m3 Kayu Kelas III 2,000,000.00 80,000.00 0.4000 kg Paku Biasa 5' - 12' 12,000.00 4,800.00 0.2000 ltr Minyak Bekisting 15,000.00 3,000.00 0.0150 m3 Kayu Usuk 4/6 4,000,000.00 60,000.00 0.3500 lbr Plywood 9 mm 105,250.00 36,837.50 6.0000 btg Dolken Kayu 8" - 10"/4m 90,000.00 540,000.00