PT.PLN (PERSERO) PEMBANGKITAN DAN

PENYALURAN SUMATERA BAGIAN UTARA

SEKTOR GLUGUR

DIAGRAM SATU GARIS GARDU INDUK TELE

TARUTUNG SIDIKALANG

ACCR 1x240 mm² ACSR

PS200KVA

TAKAOKATD (10 MVA)

PIRINGTL-1

GARPUTL-4

300/5A

800A16KA

LBS10A

PT:20KV/v3/100V/v3

ACCR 1x240 mm²

ES: 1250A 20KA

800A16KA

800A16KA

800A16KA

300/5A 300/5A 300/5A

SENDOKTL-3

GELASTL-2

PT:150KV/v3/100V/v3

PT:150KV/v3/100V/v3

LA: 10KA LA: 10KALine Trap Line Trap

ES: 1250A 20KA

CT:P=M. 400/5A

CT:P=M. 400/5A

PMT: 1250A 20KA

PMT: 1250A 20KA

PMS: 1250A 20KA

PMS: 1250A 20KA

BUS ACSR 150KV - 1250A

PMS: 800A 16KA

PMT: 800A 16KA

CT:P=M. 100/5A

LA: 10KA

NGR: 40 Ohm 300ACT: 300/5A

CT:P=M. 600/5A

PMT: 1250A 25KA

BUS AL. 20KV - 1250A - MODALEK

PT:20KV/v3/100V/v3

~

TM-120/0,4KV .......KVA

PLTMH. BOHO

UNIT-1 (200KW)

CATATAN CT :M = UNTUK METERINGP = UNTUK PROTEKSI

~PLTMH. AEK SILANG

UNIT-1 (200KW)

TM-121/0,4KV

.1000KVA

~PLTMH. AEK SIBUNDONG

UNIT-1 (750KW)

TM-121/0,4KV

.1000KVA

KWH METER