Harga Barang dan Upah Hal. 1 DAFTAR HARGA SATUAN BAHAN DAN UPAH BULAN JANUARI 2013 A. Harga Satuan Bahan NO NAMA BARANG SATUAN 1 2 3 FINISHING 1 Amplas lbr 2 Cat besi kg 3 Cat dasar kg 4 Cat emco kg 5 Cat menie besi kg 6 Cat menie kayu kg 7 Cat tembok Decolith kg 8 Cat tembok Dulux kg 9 Cat tembok Emco kg 10 Cat tembok Paragon kg 11 Cat tembok Toyopaint kg 12 Cat tembok Vinilex kg 13 Cat tembok Vinippaint kg 14 Dempul ltr 15 Kuas bh 16 Mild zak 17 Minyak cat ltr 18 Plamir kayu kg 19 Plamir tembok kg 20 Politur ultra ltr 21 Politur vernis ltr 22 Thiner A Bonanza ltr 23 Thiner B Spesial ltr PENUTUP ATAP 24 Alang-alang panjang 2,4 meter lbr 25 Alluminium foil m2 26 Asbes Bubungan lbr 27 Asbes Gelombang 1,80 m x 0,80 m x 5 mm lbr 28 Asbes Gelombang 2,4 m x 1,05 m x 4 mm lbr 29 Asbes Rata 2 m x 1 m x 4 mm lbr 30 Atap metal Toratora 1 x 4 Extra m2 31 Atap metal Toratora 1 x 4 Premium m2 32 Atap metal Toratora 2 x 4 Extra m2 33 Atap metal Toratora 2 x 4 Premium m2 34 Atap metal Toratora 3 x 4 Extra m2 35 Atap metal Toratora 3 x 4 Premium m2 36 Atap metal Toratora 4 x 4 Extra m2 37 Atap metal Toratora 4 x 4 Premium m2 38 Bentala paras bh 39 Bentala tanah liat bh 40 Besi profil WF kg 41 Besi strip kg 42 Bubungan Biasa bj 43 Bubungan Karang Pilang (glazur) isi 3,5/m bj 44 Bubungan Karang Pilang isi 3,5/m bj 45 Bubungan Ngalayur isi 3,5/m bj 46 Bubungan Plentong bj 47 Bubungan Utama isi 3,5/m bj 48 Genteng Kanmuri (glazur) isi 14/m2 bj 49 Genteng Kodok Karang Pilang (Bambe) isi 20/m2 bj 50 Genteng Kodok Karang Pilang (Bisma) isi 20/m2 bj 51 Genteng Kodok Karang Pilang (Good Year) isi 20/m2 bj 52 Genteng Morando Abadi isi 18/m2 bj

Upload: gustubatigol

Post on 30-Nov-2015

297 views

Category:

Documents


16 download

TRANSCRIPT

Page 1: Analisa Sni 2002 & 2008.Dck Januari 2013

Harga Barang dan Upah Hal. 1

DAFTAR HARGA SATUAN BAHAN DAN UPAH

BULAN JANUARI 2013A. Harga Satuan Bahan

NO NAMA BARANG HARGA SATUAN

1 2 3 4

FINISHING1 Amplas lbr 4,100.00 2 Cat besi kg 70,500.00 3 Cat dasar kg 43,600.00 4 Cat emco kg 55,000.00 5 Cat menie besi kg 22,000.00 6 Cat menie kayu kg 22,000.00 7 Cat tembok Decolith kg 33,000.00 8 Cat tembok Dulux kg 38,800.00 9 Cat tembok Emco kg 38,000.00

10 Cat tembok Paragon kg 10,000.00 11 Cat tembok Toyopaint kg 18,500.00 12 Cat tembok Vinilex kg 20,600.00 13 Cat tembok Vinippaint kg 17,000.00 14 Dempul ltr 29,000.00 15 Kuas bh 16,800.00 16 Mild zak 12,000.00 17 Minyak cat ltr 26,000.00 18 Plamir kayu kg 42,000.00 19 Plamir tembok kg 30,000.00 20 Politur ultra ltr 47,000.00 21 Politur vernis ltr 59,000.00 22 Thiner A Bonanza ltr 22,000.00 23 Thiner B Spesial ltr 12,000.00

PENUTUP ATAP24 Alang-alang panjang 2,4 meter lbr 12,500.00 25 Alluminium foil m2 29,000.00 26 Asbes Bubungan lbr 24,000.00 27 Asbes Gelombang 1,80 m x 0,80 m x 5 mm lbr 29,000.00 28 Asbes Gelombang 2,4 m x 1,05 m x 4 mm lbr 36,000.00 29 Asbes Rata 2 m x 1 m x 4 mm lbr 50,000.00 30 Atap metal Toratora 1 x 4 Extra m2 84,000.00 31 Atap metal Toratora 1 x 4 Premium m2 125,000.00 32 Atap metal Toratora 2 x 4 Extra m2 74,000.00 33 Atap metal Toratora 2 x 4 Premium m2 108,500.00 34 Atap metal Toratora 3 x 4 Extra m2 72,000.00 35 Atap metal Toratora 3 x 4 Premium m2 105,000.00 36 Atap metal Toratora 4 x 4 Extra m2 70,000.00 37 Atap metal Toratora 4 x 4 Premium m2 105,000.00 38 Bentala paras bh 68,000.00 39 Bentala tanah liat bh 52,000.00 40 Besi profil WF kg 15,000.00 41 Besi strip kg 8,000.00 42 Bubungan Biasa bj 2,700.00 43 Bubungan Karang Pilang (glazur) isi 3,5/m bj 7,200.00 44 Bubungan Karang Pilang isi 3,5/m bj 10,000.00 45 Bubungan Ngalayur isi 3,5/m bj 7,000.00 46 Bubungan Plentong bj 6,000.00 47 Bubungan Utama isi 3,5/m bj 4,200.00 48 Genteng Kanmuri (glazur) isi 14/m2 bj 6,500.00 49 Genteng Kodok Karang Pilang (Bambe) isi 20/m2 bj 3,000.00 50 Genteng Kodok Karang Pilang (Bisma) isi 20/m2 bj 2,800.00 51 Genteng Kodok Karang Pilang (Good Year) isi 20/m2 bj 3,500.00 52 Genteng Morando Abadi isi 18/m2 bj 2,800.00

SATUAN

Page 2: Analisa Sni 2002 & 2008.Dck Januari 2013

Harga Barang dan Upah Hal. 2

NO NAMA BARANG HARGA SATUAN

1 2 3 4

SATUAN

53 Genteng Morando Jatiwangi isi 18/m2 bj 2,900.00 54 Genteng Morando Ngalayur isi 20/m2 bj 2,800.00 55 Genteng Plentong bj 1,300.00 56 Genteng plentong dicat bj 1,400.00 57 Genteng Plentong Jatiwangi isi 24/m2 bj 1,350.00 58 Ijuk kg 2,500.00 59 Ikut celedu paras bh 62,000.00 60 Ikut celedu tanah liat bh 49,000.00 61 Murda paras bh 75,000.00 62 Murda tanah liat bh 61,000.00 63 Seng BJLS 0,20 gelombang lbr 43,500.00 64 Seng BJLS 0,25 gelombang lbr 42,000.00 65 Seng BJLS 0,28 gelombang lbr 42,500.00 66 Seng BJLS 0,32 gelombang lbr 47,000.00 67 Seng Plat 3" x 6" BJLS 28 lbr 46,500.00 68 Sirap Jati bh 8,500.00 69 Tali Ijuk kg 34,000.00 70 Tali pengikat alang-alang ikat 9,500.00

PENGGANTUNG71 Engsel kupu-kupu ps 49,000.00 72 Engsel nylon ps 27,000.00 73 Espagnoleth set 100,000.00 74 Grendel biasa bh 15,500.00 75 Grendel hararo bh 22,000.00 76 Kaca 3 mm bening m2 97,000.00 77 Kaca 5 mm bening m2 102,000.00 78 Kaca 6 mm bening m2 167,000.00 79 Kaca 8 mm bening m2 212,000.00 80 Kaca 10 mm bening m2 305,000.00 81 Kaca 12 mm bening m2 375,000.00 82 Kaca Es/Kapur 3 mm m2 87,000.00 83 Kaca Es/Kapur 5 mm m2 117,000.00 84 Kaca nako daun 15,000.00 85 Kaca nako teralis bening m2 117,000.00 86 Kaca ryben 3 mm m2 122,000.00 87 Kaca ryben 5 mm m2 127,000.00 88 Kait angin biasa bh 22,000.00 89 Kunci pintu TOP bh 60,000.00 90 Kunci pintu Union bh 72,000.00 91 Kunci pintu Vanesa bh 109,000.00 92 Kunci pintu Yale bh 115,000.00 93 Kunci pintu YURI bh 132,000.00 94 Kunci slot bh 100,000.00 95 Kunci tanam 2 slag bh 105,000.00

KAYU DAN PLAFOND96 Bambu besar Ukuran 4 m btg 11,000.00 97 Bambu sedang Ukuran 4 m btg 9,000.00 98 Bambu kecil Ukuran 4 m btg 7,000.00 99 Celling teak (0,62 x 2,40) m2 lbr 70,000.00 100 Eternit lbr 47,000.00 101 Formika lbr 80,000.00 102 Gedeg kulit kelas I m2 20,000.00 103 Gypsum Old lbr 63,500.00 104 Hard board MDF lbr 107,000.00 105 Kalsiboard 4,5 mm lbr 72,000.00 106 Kayu bekesting m3 2,250,000.00 107 Kayu bingkirai m3 12,000,000.00 108 Kayu bingkirai papan m3 13,500,000.00 109 Kayu dolken (pekerjaan sementara) btg 90,000.00 110 Kayu jati m3 20,000,000.00

Page 3: Analisa Sni 2002 & 2008.Dck Januari 2013

Harga Barang dan Upah Hal. 3

NO NAMA BARANG HARGA SATUAN

1 2 3 4

SATUAN

111 Kayu jati papan m3 30,000,000.00 112 Kayu kamper balok m3 8,300,000.00 113 Kayu kamper usuk/reng m3 6,500,000.00 114 Kayu kamper papan m3 9,000,000.00 115 Kayu kruing balok m3 5,000,000.00 116 Kayu kruing usuk/reng m3 6,000,000.00 117 Kayu kruing papan m3 6,000,000.00 118 Kayu meranti balok m3 2,500,000.00 119 Kayu meranti usuk/reng m3 3,000,000.00 120 Kayu meranti papan m3 6,000,000.00 121 Kayu merbau m3 13,000,000.00 122 Kayu merbau papan m3 13,200,000.00 123 Kayu profil m1 12,250.00 124 Kayu seseh balok m3 2,264,750.00 125 Kayu seseh dolken m3 2,750,000.00 126 Lem Aibond kg 33,000.00 127 Lem Kayu ltr 12,500.00 128 List Gypsum standar m' 17,000.00 129 Minyak bekisting ltr 15,000.00 130 Multiplek 12 mm lbr 135,000.00 131 Multiplek 18 mm lbr 200,000.00 132 Multiplek 6 mm lbr 62,000.00 133 Multiplek 9 mm lbr 98,700.00 134 Plywood 12 mm lbr 127,000.00 135 Plywood 3 mm lbr 36,000.00 136 Plywood 4 mm lbr 47,000.00 137 Plywood 6 mm lbr 67,000.00 138 Plywood 9 mm lbr 105,500.00 139 Plywood aluminium lbr 75,000.00 140 Teak wood (0,9x2,20) m2 lbr 56,000.00 141 Teak wood (1,20x2,40) m2 lbr 62,000.00

KERAMIKIKAD

142 Ikad (Keramik) Kw. I 10 x 20 cm m2 51,500.00 143 Ikad (Keramik) Kw. I 20 x 20 cm m2 42,000.00 144 Ikad (Keramik) Kw. I 20 x 30 cm m2 52,000.00 145 Ikad (Keramik) Kw. I 30 x 30 cm m2 40,000.00 146 Ikad (Keramik) Kw. I 40 x 40 cm m2 48,000.00 147 Ikad (Keramik) Kw. II 10 x 20 cm m2 38,000.00 148 Ikad (Keramik) Kw. II 20 x 20 cm m2 40,000.00 149 Ikad (Keramik) Kw. II 20 x 30 cm m2 47,000.00 150 Ikad (Keramik) Kw. II 30 x 30 cm m2 42,500.00 151 Ikad (Keramik) Kw. II 40 x 40 cm m2 52,000.00

INESA152 Keramik 30 x 30 Kelas I (Onyx Phyrus Ruby Jade, P) m2 191,000.00 153 Keramik 30 x 30 Kelas I (Onyx Phyrus Ruby Jade, UP) m2 154,000.00 154 Keramik 30 x 30 Kelas I (Pearl Ghita Cat Eye, P) m2 180,000.00 155 Keramik 30 x 30 Kelas I (Pearl Ghita Cat Eye, UP) m2 143,000.00 156 Keramik 30 x 30 Kelas I (Sand Wheat Spruce Clay Charcoal, R) m2 165,000.00 157 Keramik 40 x 40 Kelas I (Corypha Roystonea Raphia, P) m2 209,000.00 158 Keramik 40 x 40 Kelas I (Onyx Phyrus Ruby Jade, P) m2 209,000.00 159 Keramik 40 x 40 Kelas I (Onyx Phyrus Ruby Jade, UP) m2 160,000.00 160 Keramik 40 x 40 Kelas I (Pearl Ghita Cat Eye, P) m2 197,000.00 161 Keramik 40 x 40 Kelas I (Pearl Ghita Cat Eye, UP) m2 149,000.00 162 Keramik 60 x 60 Kelas I (Corypha Roystonea Raphia, P) m2 248,500.00

Page 4: Analisa Sni 2002 & 2008.Dck Januari 2013

Harga Barang dan Upah Hal. 4

NO NAMA BARANG HARGA SATUAN

1 2 3 4

SATUAN

ESSENZA163 Keramik 30 x 30 Kelas I (Black Orchid, Coral Bell, P) m2 210,000.00 164 Keramik 30 x 30 Kelas I (Black Orchid, Coral Bell, UP) m2 189,500.00 165 Keramik 30 x 30 Kelas I (Pepper Grey Price Rubert Silver star, P m2 150,700.00 166 Keramik 30 x 30 Kelas I (Pepper Grey Price Rubert Silver star, m2 107,800.00 167 Keramik 40 x 40 Kelas I (Pepper Grey Price Rubert Silver star, P m2 222,900.00 168 Keramik 40 x 40 Kelas I (Pepper Grey Price Rubert Silver star, m2 194,900.00 169 Keramik 60 x 60 Kelas I (Pepper Grey Price Rubert Silver star, P m2 273,500.00 170 Keramik Kelas I Domus m2 286,500.00 171 Keramik Kelas I Granity Imperiali m2 262,500.00 172 Keramik Kelas I Lavagna m2 249,900.00 173 Keramik Kelas I Mountain Peak m2 337,000.00

ROMAN174 Keramik 20 x 20 tekstur kasar m2 57,750.00 175 Keramik 25 x 33 kelas I m2 70,500.00 176 Keramik 25 x 45 motif halus kelas I m2 88,750.00 177 Keramik 30 x 30 standard m2 72,500.00 178 Keramik 30 x 30 kelas I T. 1cm m2 95,000.00 179 Keramik 20 x 60 kelas I T. 1cm m2 114,900.00 180 Keramik 20 x 40 kelas I Motif standard m2 76,900.00 181 Keramik 30 x 60 kelas I Motif Dasar Muda m2 175,900.00 182 Keramik 40 x 40 kelas I krem m2 76,100.00 183 Keramik 40 x 40 kelas I white m2 76,100.00 184 Keramik 50 x 50 kelas I warna muda m2 92,900.00

PLATINUM185 Keramik 25 x 33 kelas I m2 61,500.00 186 Keramik 25 x 40 kelas II m2 40,000.00 187 Keramik 30 x 60 kelas II bulgari m2 40,900.00 188 Keramik 40 x 40 kelas I brown m2 57,500.00

GRANIT189 Granit star white L.60 m2 315,000.00 190 Granit BGYD red L.60 m2 425,000.00 191 Granit crystal pink L. 60 m2 320,000.00 192 Granit mongol black L. 60 m2 825,000.00 193 Granit gold black L. 60 m2 825,000.00

MARMER194 Marmer cream BA 60 x 60 m2 335,000.00 195 Marmer cream BA 40 x 40 m2 260,000.00 196 Marmer cream BA 30 x 30 m2 215,000.00

MOZAIK197 Mozaik keramik zehn crystal glass 30 x 30 biji 41,000.00 198 Mozaik batu alam 30 x 30 biji 21,500.00

ASIA199 Keramik 20 x 30 kelas I warna muda m2 55,500.00 200 Keramik 30 x 30 kelas I warna muda m2 39,000.00 201 Keramik 30 x 30 kelas I warna tua m2 45,000.00 202 Keramik 40 x 40 kelas I warna muda m2 52,000.00 203 Keramik 10 x 20 kelas II m2 45,000.00 204 Keramik 20 x 20 kelas II m2 35,000.00 205 Keramik 20 x 30 kelas II m2 37,000.00 206 Keramik 30 x 30 kelas II m2 37,000.00 207 Keramik 40 x 40 kelas II m2 40,000.00

Page 5: Analisa Sni 2002 & 2008.Dck Januari 2013

Harga Barang dan Upah Hal. 5

NO NAMA BARANG HARGA SATUAN

1 2 3 4

SATUAN

MULIA208 Keramik 10 x 20 cm kelas I m2 41,000.00 209 Keramik 20 x 20 cm kelas I m2 43,000.00

Page 6: Analisa Sni 2002 & 2008.Dck Januari 2013

Harga Barang dan Upah Hal. 6

NO NAMA BARANG HARGA SATUAN

1 2 3 4

SATUAN

210 Keramik 20 x 30 cm kelas I m2 56,000.00 211 Keramik 30 x 30 cm kelas I m2 40,000.00 212 Keramik 40 x 40 cm kelas I m2 48,000.00 213 Keramik 10 x 20 cm kelas II m2 38,500.00 214 Keramik 20 x 20 cm kelas II m2 40,000.00 215 Keramik 20 x 30 cm kelas II m2 53,500.00 216 Keramik 30 x 30 cm kelas II m2 36,500.00 217 Keramik 40 x 40 cm kelas II m2 46,000.00

SANITAIR203 Bak mandi fibre glass 70x70x66 cm bh 230,000.00 204 Bak mandi keramik 50x50 bh 170,000.00 205 Floor Drain " TOTO TypeTx 1 Bv 1 " Square Flange " bh 225,000.00 206 Floor drain plastik bh 15,000.00 207 Floor drain stainless bh 45,000.00 208 Kloset duduk INA Komplit bh 1,300,000.00 209 Kloset duduk Amerika Standar bh 955,000.00 210 Kloset duduk " TOTO Type AVANTE CW 821 PJ / SW 821JP C bh 1,500,000.00 211 Kloset duduk " TOTO Type AVANTE CW 821J"/ SW 821JP CO bh 5,610,000.00 212 Kloset duduk " TOTO Type AVANTE CW 823 J bh 5,600,000.00 213 Kloset duduk " TOTO Type CW 660J bh 610,000.00 214 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT bh 1,365,000.00 215 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT WA bh 1,491,000.00 216 Kloset duduk " TOTO Type CW 660J WARNA COMPLIT bh 670,000.00 217 Kloset duduk " TOTO Type CW 661JT1 BODI COMPLIT bh 2,800,000.00 218 Kloset duduk " TOTO Type CW 661JT1" / SW 661JP COMPLIT bh 2,200,000.00 219 Kloset duduk " TOTO Type CW 661JT1" / SW 784JP COMPLIT bh 1,800,000.00 220 Kloset jongkok " TOTO Type CE 6 COMPLIT bh 355,000.00 221 Kloset jongkok " TOTO Type CE 7 COMPLIT bh 165,000.00 222 Kloset porselin jongkok Kia (standar) bh 145,000.00 223 Kloset porselin jongkok Ina (standar) bh 135,000.00 224 Kran biasa bh 18,000.00 225 Kran SunEi bh 110,500.00 226 Kran TOTO T 205 LCSC bh 220,500.00 227 Kran TOTO T 205 MC bh 165,000.00 228 Kran TOTO T 23 B13 bh 140,000.00 229 Kran TOTO T 23 B13V7N bh 142,000.00 230 Kran TOTO T 26 - 13 bh 187,000.00 231 Kran TOTO TX 109 LH bh 410,000.00 232 Penyekat Urinoir " TOTO " Type A 100 " bh 835,000.00 233 Shower Spray " TOTO Tx 403SPIV ( Pastel Ivory ) bh 235,000.00 234 Soap holder " TOTO " Type S 6 N " bh 48,000.00 235 Seal tape bh 2,600.00 236 Urinoir " TOTO U 57 M bh 1,052,000.00 237 Urinoir " TOTO U 57 M BODI bh 849,000.00 238 Urinoir " TOTO UW 447 JT 1 " bh - 239 Urinoir " TOTO UW 447 JT 1 BODI bh - 240 Urinoir " TOTO UW 447 JT 1,M " bh - 241 Urinoir " TOTO UW 447 JT 1,M "BODI bh - 242 Wastagel KIA Standard bh 185,000.00 243 Wastagel KIA Warna bh 235,000.00 244 Wastafel Komplit " TOTO Tx " Type L 521V1A " bh 1,135,000.00 245 Wastafel Komplit top Counter" TOTO " Type CERABO LW 523 bh 735,000.00

PAKU246 Paku 10 cm kg 14,000.00 247 Paku kalsiboard kg 24,000.00 248 Paku list SQ kg 17,000.00 249 Paku pancing 60 x 230 kg 20,000.00

Page 7: Analisa Sni 2002 & 2008.Dck Januari 2013

Harga Barang dan Upah Hal. 7

NO NAMA BARANG HARGA SATUAN

1 2 3 4

SATUAN

250 Paku reng/usuk SQ kg 13,000.00 251 Paku seng kg 21,000.00

Page 8: Analisa Sni 2002 & 2008.Dck Januari 2013

Harga Barang dan Upah Hal. 8

NO NAMA BARANG HARGA SATUAN

1 2 3 4

SATUAN

252 Paku seng import bj 45,000.00 253 Paku skrup 1/2" kg 18,000.00 254 Paku skrup 2" kg 18,000.00 255 Paku skrup 3.5" kg 26,500.00 256 Paku sumbat 1/2" kg 15,000.00

PASIR, BATU, KERIKIL, BATA DAN PARAS257 Bata gosok ex Tulikup bj 1,980.00 258 Bata Merah 5 x 11 x 22 cm bj 1,300.00 259 Batako kelas I bj 2,200.00 260 Batu kali /batu bulat 15/20 cm m3 180,000.00 261 Batu karang m3 131,000.00 262 Batu lahar Singaraja m3 170,000.00 263 Batu pecah 5-7 cm (manual) m3 150,000.00 264 Batu pipih Singaraja m3 155,000.00 265 Bata riyan ( abble ) bj 2,500.00 266 Roster Keramik bh 50,000.00 267 Koral Beton m3 170,000.00 268 Limestone m3 85,000.00 269 Paras Batik bh 17,000.00 270 Paras Buahan bh 10,000.00 271 Paras Karang Bukit bh 8,500.00 272 Paras Kerobokan Tebal 5 bh 9,500.00 273 Paras Malem bh 13,000.00 274 Paras Putih Bukit bh 4,000.00 275 Paras Silakarang tebal bh 14,500.00 276 Paras Silakarang tipis bh 12,000.00 277 Paras untuk pondasi bh 12,500.00 278 Batu alam RTM hijau 10 x 20 halus m2 75,000.00 279 Batu alam RTM hijau 20 x 20 halus m2 90,000.00 280 Batu alam RTS hijau 10 x 20 kasar m2 70,000.00 281 Batu pilah Jember 30 x 30 m2 55,000.00 282 Batu pilah Jember 20 x 30 m2 55,000.00 283 Batu pilah Jember 40 x 40 m2 65,000.00 284 Batu pilah Singaraja 30 x 30 m2 65,000.00 285 Batu pilah Singaraja 20 x 20 m2 60,000.00 286 Batu hitam Jember 5 x 20 halus m2 55,000.00 287 Batu hitam Jember 20 x 40 halus m2 55,000.00 288 Batu hitam Jember 15 x 30 halus m2 55,000.00 289 Batu hitam Singaraja 15 x 30 halus m2 60,000.00 290 Batu hitam Singaraja 20 x 40 halus m2 65,000.00 291 Batu AND 60 x 60 abu m2 190,000.00 292 Batu AND 50 x 50 hitam m2 190,000.00 293 Batu AND 40 x 40 hitam bkr m2 140,000.00 294 Batu AND 30 x 60 hitam bkr m2 140,000.00 295 Batu AND 40 x 60 hitam kilap m2 160,000.00 296 Batu AND 30 x 40 abu SS m2 100,000.00 297 Batu marmer kuning 10 x 20 m2 75,000.00 298 Batu marmer kuning PB1 10 x 20 m2 90,000.00 299 Batu marmer kuning PB2 10 x 20 m2 70,000.00 300 Batu marmer kuning 15 x 30 m2 100,000.00 301 Batu kuning serat 30 x 30 m2 70,000.00 302 Batu kuning serat 20 x 30 m2 70,000.00 303 Batu palimanan cirebon 20 x 30 m2 80,000.00 304 Batu palimanan cirebon 20 x 40 m2 80,000.00 305 Batu paras Jogja 60 x 60 m2 120,000.00 306 Batu candi hitam 60 x 60 m2 75,000.00 307 Batu candi hitam 20 x 20 m2 70,000.00 308 Batu candi hitam 30 x 30 m2 75,000.00

Page 9: Analisa Sni 2002 & 2008.Dck Januari 2013

Harga Barang dan Upah Hal. 9

NO NAMA BARANG HARGA SATUAN

1 2 3 4

SATUAN

309 Batu candi hitam 40 x 40 T.5cm m2 185,000.00 310 Batu candi hitam 20 x 30 m2 75,000.00

Page 10: Analisa Sni 2002 & 2008.Dck Januari 2013

Harga Barang dan Upah Hal. 10

NO NAMA BARANG HARGA SATUAN

1 2 3 4

SATUAN

311 Batu Bali green gelombang 20 x 40 m2 105,000.00 312 Batu Bali green kombinasi 20 x 40 m2 100,000.00 314 Batu serayu 20 x 60 m2 90,000.00 315 Pasir beton m3 141,000.00 316 Pasir pasang m3 158,000.00 317 Pasir urug m3 130,000.00 318 Sirtu m3 125,000.00 319 Tanah urug m3 80,000.00

PIPA320 Pipa Galvanis 1/2" m1 27,125.00 321 Pipa Galvanis 3/4" m1 35,000.00 322 Pipa Galvanis 1 1/4" m1 70,625.00 323 Pipa Galvanis 1 1/2" m1 81,125.00 324 Pipa Galvanis 1" m1 38,000.00 325 Pipa Galvanis 1,5 BSA m1 58,000.00 326 Pipa Galvanis 2" m1 77,500.00 327 Pipa Galvanis 3" m1 175,000.00 328 Pipa Maspion AW 1 ljr 32,000.00 329 Pipa Maspion AW 1/2 ljr 22,000.00 330 Pipa Maspion AW 10 ljr 112,000.00 331 Pipa Maspion AW 1-1/2 ljr 59,480.00 332 Pipa Maspion AW 1-1/4 ljr 45,000.00 333 Pipa Maspion AW 12 ljr 1,550,000.00 334 Pipa Maspion AW 14 ljr 1,900,000.00 335 Pipa Maspion AW 16 ljr 2,400,000.00 336 Pipa Maspion AW 2 ljr 89,000.00 337 Pipa Maspion AW 2-1/2 ljr 103,000.00 338 Pipa Maspion AW 3 ljr 140,000.00 339 Pipa Maspion AW 3/4 ljr 25,000.00 340 Pipa Maspion AW 4 ljr 225,000.00 341 Pipa Maspion AW 5 ljr 373,000.00 342 Pipa Maspion AW 6 ljr 494,000.00 343 Pipa Maspion AW 8 ljr 768,000.00 344 Pipa Maspion C 1 ljr 14,700.00 345 Pipa Maspion C 1-1/2 ljr 19,500.00 346 Pipa Maspion C 1-1/4 ljr 16,500.00 347 Pipa Maspion C 2 ljr 35,000.00 348 Pipa Maspion C 2-1/2 ljr 45,000.00 349 Pipa Maspion C 3 ljr 50,000.00 350 Pipa Maspion C 3/4 ljr 10,000.00 351 Pipa Maspion C 4 ljr 63,000.00 352 Pipa Maspion C 5/8 ljr 5,500.00 353 Pipa Maspion D 10 ljr 784,000.00 354 Pipa Maspion D 1-1/2 ljr 32,000.00 355 Pipa Maspion D 1-1/4 ljr 28,000.00 356 Pipa Maspion D 12 ljr 1,270,000.00 357 Pipa Maspion D 14 ljr 1,650,000.00 358 Pipa Maspion D 16 ljr 1,877,568.00 359 Pipa Maspion D 2 ljr 42,000.00 360 Pipa Maspion D 2-1/2 ljr 62,000.00 361 Pipa Maspion D 3 ljr 86,000.00 362 Pipa Maspion D 4 ljr 120,000.00 363 Pipa Maspion D 5 ljr 209,000.00 364 Pipa Maspion D 6 ljr 254,000.00 365 Pipa Maspion D 8 ljr 449,000.00

SEMEN & AIR CAMPURAN BETON366 Semen Bosowa 50 kg zak 60,000.00

Page 11: Analisa Sni 2002 & 2008.Dck Januari 2013

Harga Barang dan Upah Hal. 11

NO NAMA BARANG HARGA SATUAN

1 2 3 4

SATUAN

367 Semen Gresik 40 kg zak 51,000.00 368 Semen Gresik 50 kg zak 61,000.00 369 Semen Tiga Roga 50 kg zak 60,000.00 370 Semen Tonasa 50 kg zak 60,000.00 371 Semen warna/semen grouting kg 12,500.00 372 Air Campuran Beton ltr 50.00

BESI BETON DAN PAGAR373 Besi beton kg 8,427.00 374 Kawat berduri roll 85,000.00 375 Kawat beton RRT kg 16,000.00 376 Pagar BRC asli T.120 diameter 6mm m' 170,000.00 377 Pagar BRC asli T.150 diameter 6mm m' 178,000.00 378 Pagar BRC asli T.175 diameter 7mm m' 251,000.00 379 Pagar BRC asli T.190 diameter 7mm m' 268,000.00 380 Pagar BRC asli T.90 diameter 6mm m' 137,000.00 381 Pagar HotDip Galvanized T.120 diameter 6mm m' 140,000.00 382 Pagar HotDip Galvanized T.150 diameter 7mm m' 191,000.00 383 Pagar HotDip Galvanized T.175 diameter 7mm m' 205,000.00 384 Pagar HotDip Galvanized T.190 diameter 7mm m' 220,000.00 385 Pagar HotDip Galvanized T.90 diameter 6mm m' 120,000.00 386 Tiang BRC asli T. 120 diameter 1 1/2" bh 167,000.00 387 Tiang BRC asli T. 150 diameter 2" bh 215,000.00 388 Tiang BRC asli T. 175 diameter 2" bh 245,000.00 389 Tiang BRC asli T. 190 diameter 2" bh 250,000.00 390 Tiang BRC asli T. 90 diameter 1 1/2" bh 140,000.00 391 Tiang HotDip Galvanized T. 120 diameter 1 1/2" bh 147,000.00 392 Tiang HotDip Galvanized T. 150 diameter 2" bh 172,000.00 393 Tiang HotDip Galvanized T. 175 diameter 2" bh 190,000.00 394 Tiang HotDip Galvanized T. 190 diameter 2" bh 200,000.00 395 Tiang HotDip Galvanized T. 90 diameter 1 1/2" bh 127,000.00

BAHAN LISTRIK396 Saklar (Broco) bh 12,700.00 397 Stop Kontak bh 16,000.00 398 Fitting bh 6,000.00 399 Steker bh 30,000.00 400 Coaxial cable 5C - 75 ohm commscof m1 6,000.00 401 Kabel NYM 3 x 2.5 mm ex. Supreme m1 12,000.00 402 Kabel NYM 4 mm m1 6,000.00 403 Kabel telephone m1 4,000.00 404 Lampu pijar 10 Watt (Philip) bh 6,000.00 405 Lampu pijar 15 Watt (Philip) bh 7,000.00 406 Lampu pijar 25 Watt (Philip) bh 8,000.00 407 Lampu TL 10 Watt (10 Watt) bh 27,500.00 408 Lampu TL 20 Watt (10 Watt) bh 35,000.00 409 Lampu TL 25 Watt (10 Watt) bh 34,000.00 410 Pipa clipsal 20 mm bt 12,000.00 411 Pipa flexible clipsal 20 mm m1 10,500.00 412 Sock clipsal 20 mm bj 2,000.00 413 Tee dos clipsal 20 mm bh 7,000.00 414 Klem clipsal 20 mm bj 750.00 415 Inbow dos plastik clipsal E 157 P bj 10,000.00

BUIS BETON416 Buis beton 10 x 75 bh 31,000.00 417 Buis beton 15 x 75 bh 39,000.00 418 Buis beton 20 x 75 bh 40,000.00 419 Buis beton 25 x 75 bh 43,000.00

Page 12: Analisa Sni 2002 & 2008.Dck Januari 2013

Harga Barang dan Upah Hal. 12

NO NAMA BARANG HARGA SATUAN

1 2 3 4

SATUAN

420 Buis beton 30 x 75 bh 54,000.00 421 Buis beton 50 x 75 bh 75,000.00

Page 13: Analisa Sni 2002 & 2008.Dck Januari 2013

Harga Barang dan Upah Hal. 13

NO NAMA BARANG HARGA SATUAN

1 2 3 4

SATUAN

PAVING422 Paving 10 x 20 cm tebal 6 cm K225 m2 55,000.00 423 Paving 10 x 20 cm tebal 6 cm K350 m2 63,000.00 424 Paving 10 x 20 cm tebal 8 cm K225 m2 63,000.00 425 Paving 10 x 20 cm tebal 8 cm K350 m2 68,000.00 426 Paving 10 x 20 cm tebal 8 cm K425 m2 75,500.00 427 Paving 20 x 20 cm tebal 6 cm K225 m2 55,000.00 428 Paving 20 x 20 cm tebal 6 cm K350 m2 63,000.00 429 Paving 20 x 20 cm tebal 8 cm K225 m2 63,000.00 430 Paving 20 x 20 cm tebal 8 cm K350 m2 68,000.00 431 Paving 20 x 20 cm tebal 8 cm K425 m2 75,500.00 432 Paving 20 x 20 cm tebal 10 cm K225 m2 66,500.00 433 Paving 20 x 20 cm tebal 10 cm K350 m2 76,000.00 434 Paving 20 x 20 cm tebal 10 cm K425 m2 85,000.00 435 Paving Tiga Berlian tebal 6 cm K225 m2 53,000.00 436 Kanstein Bulat (P:50,T:30,La:10,Lb:16 cm K225) m1 58,000.00 437 Kanstein Jumbo (P:50,L:15,T:30 cm K225) m1 66,000.00 438 Kanstein Segi Lima Jumbo (P:50,L:15, T:40 cm K225) m1 69,000.00 439 Grass Block 36 X 54 cm tebal 9 cm K 225 m2 55,000.00 440 Koral Sikat zak/10 kg 35,000.00

LAIN-LAIN441 Wall papper 29 x 29 lembar 22,000.00 442 Wall papper 70 x 100 lembar 80,000.00 443 Wall papper 50 x 70 lembar 99,000.00 444 Wall papper 30 x 60 lembar 35,000.00 445 Glass block bj 25,000.00 446 Dugul batu hitam 50 x 50 x 200 unit 3,800,000.00 447 Dugul batu hitam 60 x 70 x 250 unit 4,100,000.00 448 Dugul batu hitam 70 x 70 x 250 unit 4,300,000.00 449 Padmasari batu hitam 50 x 50 x 200 unit 3,800,000.00 450 Padmasari batu hitam 65 x 75 x 255 unit 4,100,000.00 451 Padmasari batu hitam 70 x 70 x 250 unit 4,300,000.00

Mangupura, Januari 2013Kepala Dinas Cipta Karya

Kabupaten Badung

Ir. Ni Luh Putu Dessy Dharmayanty, M.T Pembina Tk.I

NIP. 196110101994032001

Page 14: Analisa Sni 2002 & 2008.Dck Januari 2013

DAFTAR HARGA SATUAN UPAHBULAN JANUARI TAHUN 2013

NO NAMA BARANG SPESIFIKASI SATUANHARGA

(Rp.)1 2 3 4 5

1 Mandor Hari 68,000.00

2 Kepala Tukang Hari 60,000.00

3 Tukang Politur Hari 42,000.00

4 Tukang Batu Hari 45,000.00

5 Tukang kayu Hari 55,000.00

6 Tukang Besi Hari 50,000.00

7 Tukang cat Hari 40,000.00

8 Tukang gali Hari 40,000.00

9 Tukang Listrik Hari 45,000.00

10 Tukang Pipa/ Tukang Ledeng Hari 50,000.00

11 Tukang Aspal Hari 43,000.00

12 Tukang masak Aspal Hari 44,000.00

13 Pekerja Hari 40,000.00

14 Tukang Ukir Hari 75,000.00

15 Operator Hari 50,000.00

16 Pembantu Operator Hari 40,000.00

17 Mekanik Hari 50,000.00

18 Pembantu Mekanik Hari 45,000.00

19 Pasang Atap Alang-Alang Hari 45,000.00

20 Pasang Bata Gosok Dua Muka M2 270,000.00

21 Pasang Bata Gosok Satu Muka M2 145,000.00

22 Pasang Batu Paras Diukir M2 288,500.00

23 Pasang Patu Paras Siap Diukir M2 250,000.00

24 Tukang Bongkar Begesting Hari 40,000.00

Catatan :1. Harga - harga belum termasuk PPn 10 %;2. Harga - harga hanya sebagai pedoman / pendukung

dalam perhitungan konstruksi ( tidak mengikat ).

Mangupura, Januari 2013Kepala Dinas Cipta Karya

Kabupaten Badung

Ir. Ni Luh Putu Dessy Dharmayanty, M.TPembina Tk. I

NIP. 196110101994032001

Page 15: Analisa Sni 2002 & 2008.Dck Januari 2013

DAFTAR ANALISA PEKERJAANBULAN JANUARI TAHUN 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6

I PEKERJAAN PERSIAPAN (SNI 03-2835-2002)1

1.2500 btg Bambu Sedang 9,000.00 11,250.00 2.5000 kg Semen Portland 1,220.00 3,050.00 1.2000 lbr Seng gelombang 3" - 5" 43,500.00 52,200.00 0.0050 m3 Pasir Beton 141,000.00 705.00 0.0090 m3 Koral beton 170,000.00 1,530.00 0.0720 m3 Kayu Meranti Usuk 5/7 3,000,000.00 216,000.00 0.0600 kg Paku biasa 2" - 5" 13,000.00 780.00 0.4500 kg Meni Besi 22,000.00 9,900.00 0.2000 oh Tukang Kayu 55,000.00 11,000.00 0.4000 oh Pekerja 40,000.00 16,000.00 0.0200 oh Kepala Tukang 60,000.00 1,200.00 0.0200 oh Mandor 68,000.00 1,360.00

Total : 29,560.00 295,415.00 324,975.00

2 1 M1 PENGUKURAN DAN PEMASANGAN BOWPLANK 0.0120 m3 Kayu Usuk Meranti 5/7 3,000,000.00 36,000.00 0.0200 kg Paku Biasa 2" - 5" 13,000.00 260.00 0.0070 m3 Kayu Papan Meranti 3/20 6,000,000.00 42,000.00 0.1000 oh Tukang Kayu 55,000.00 5,500.00 0.1000 oh Pekerja 40,000.00 4,000.00 0.0100 oh Kepala Tukang 60,000.00 600.00 0.0050 oh Mandor 68,000.00 340.00

Total : 10,440.00 78,260.00 88,700.00

3

1.2500 btg Dolken Kayu Ø 8 - 10/4m 90,000.00 112,500.00 0.1800 m3 Kayu Meranti 2,500,000.00 450,000.00 0.8500 kg Paku Biasa 2" - 5" 13,000.00 11,050.00 1.1000 kg Besi Strip 8,000.00 8,800.00 35.0000 kg Semen Portland 1,220.00 42,700.00 0.1500 m3 Pasir Pasang 158,000.00 23,700.00 0.1000 m3 Pasir Beton 141,000.00 14,100.00 0.1500 m3 Koral Beton 170,000.00 25,500.00 30.0000 bh Bata Merah 1,300.00 39,000.00 0.2500 lbr Seng Plat 46,500.00 11,625.00 2.0000 bh Jendela Nako 15,000.00 30,000.00 0.0800 m2 Kaca Polos 102,000.00 8,160.00 0.1500 bh Kunci Tanam 105,000.00 15,750.00 0.0600 lbr Plywood 4 mm 47,000.00 2,820.00 2.0000 oh Tukang Kayu 55,000.00 110,000.00 1.0000 oh Tukang Batu 45,000.00 45,000.00 2.0000 oh Pekerja 40,000.00 80,000.00 0.3000 oh Kepala Tukang 60,000.00 18,000.00 0.0500 oh Mandor 68,000.00 3,400.00

Total : 256,400.00 795,705.00 1,052,105.00

4 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT 1.7000 btg Bambu Sedang 9,000.00 15,300.00 0.2100 m3 Kayu Meranti 2,500,000.00 525,000.00 0.3000 kg Paku Biasa 2" - 5" 13,000.00 3,900.00 10.5000 kg Semen Portland 1,220.00 12,810.00 0.0300 m3 Pasir Beton 141,000.00 4,230.00 0.0500 m3 Koral Beton 170,000.00 8,500.00 1.5000 lbr Seng gelombang BJLS 28 42,500.00 63,750.00 2.0000 oh Tukang Kayu 55,000.00 110,000.00 1.0000 oh Pekerja 40,000.00 40,000.00 0.2000 oh Kepala Tukang 60,000.00 12,000.00 0.0500 oh Mandor 68,000.00 3,400.00

Total : 165,400.00 633,490.00 798,890.00

5 1 M2 PEMBUATAN RUMAH JAGA/KONSTRUKSI KAYU 3.0000 btg Bambu Sedang 9,000.00 27,000.00 0.2760 m3 Kayu Meranti 2,500,000.00 690,000.00 0.7000 kg Paku biasa 2" - 5" 13,000.00 9,100.00 1.5000 lbr Seng gelombang BJLS 28 42,500.00 63,750.00 1.5000 oh Tukang Kayu 55,000.00 82,500.00 1.0000 oh Pekerja 40,000.00 40,000.00 0.1500 oh Kepala Tukang 60,000.00 9,000.00 0.0500 oh Mandor 68,000.00 3,400.00

Total : 134,900.00 789,850.00 924,750.00

1 M1 PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 METER

1 M2 PEMBUATAN KANTOR SEMENTARA, DENGAN LANTAI PLESTERAN

Page 16: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6

6 1 M2 MEMBERSIHKAN LAPANGAN DAN PERATAAN 0.1000 oh Pekerja 40,000.00 4,000.00 0.0500 oh Mandor 68,000.00 3,400.00

Total : 7,400.00 7,400.00

7 1 M2 PEMBUATAN BEDENG BURUH 1.2500 btg Bambu Sedang 9,000.00 11,250.00 0.1860 m3 Kayu Meranti 2,500,000.00 465,000.00 0.3000 kg Paku Biasa 2" - 5" 13,000.00 3,900.00 18.0000 kg Semen Portland 1,220.00 21,960.00 0.0300 m3 Pasir Beton 141,000.00 4,230.00 0.0500 m3 Koral Beton 170,000.00 8,500.00 1.5000 lbr Seng gelombang BJLS 28 42,500.00 63,750.00 1.3500 lbr Plywood 4 mm 47,000.00 63,450.00 2.0000 oh Tukang Kayu 55,000.00 110,000.00 1.0000 oh Pekerja 40,000.00 40,000.00 0.2000 oh Kepala Tukang 60,000.00 12,000.00 0.0500 oh Mandor 68,000.00 3,400.00

Total : 165,400.00 642,040.00 807,440.00

8 1 M2 PEMBUATAN BAK ADUKAN UKURAN (40X50X20) CM 0.0360 m3 Kayu Terentang 2,500,000.00 90,000.00 0.0800 kg Paku Biasa 2" - 5" 13,000.00 1,040.00 1.0000 btg Kaso 5/7 84,000.00 84,000.00 0.3000 oh Tukang kayu 55,000.00 16,500.00 0.0015 oh Mandor 68,000.00 102.00

Total : 16,602.00 175,040.00 191,642.00

9 1 M2 PEMBUATAN STEGGER DARI BAMBU 1.0000 btg Bambu 7,000.00 7,000.00 0.2500 kg Tali Ijuk 34,000.00 8,500.00 0.0170 oh Tukang Kayu 55,000.00 935.00 0.0020 oh Pekerja 40,000.00 80.00 0.2500 oh Kepala Tukang 60,000.00 15,000.00 0.0130 oh Mandor 68,000.00 884.00

16,899.00 15,500.00 32,399.00

10 1 M2 PEMBUATAN JALAN SEMENTARA 0.1500 m3 Batu Kali / Batu Bulat 15/20 180,000.00 27,000.00 0.0900 m3 Batu Pecah 5 - 7 150,000.00 13,500.00 0.0100 m3 Pasir Pasang 158,000.00 1,580.00 1.0000 oh Pekerja 40,000.00 40,000.00 0.0500 oh Mandor 68,000.00 3,400.00

Total : 43,400.00 42,080.00 85,480.00

11 1 M3 BONGKARAN BETON BERTULANG 6.6670 oh Pekerja 40,000.00 266,680.00 0.3330 oh Mandor 68,000.00 22,644.00

Total : 289,324.00 289,324.00

12 1 M3 BONGKARAN DINDING TEMBOK BATA MERAH 6.6670 oh Pekerja 40,000.00 266,680.00 0.0330 oh Mandor 68,000.00 2,244.00

Total : 268,924.00 268,924.00

II PEKERJAAN TANAH (SNI 2835 : 2008)

1 1 M3 GALIAN TANAH BIASA DALAM 1 METER 0.7500 oh Pekerja 40,000.00 30,000.00 0.0250 oh Mandor 68,000.00 1,700.00

Total : 31,700.00 31,700.00 2 1 M3 GALIAN TANAH BIASA DALAM 2 METER

0.9000 oh Pekerja 40,000.00 36,000.00 0.0450 oh Mandor 68,000.00 3,060.00

Total : 39,060.00 39,060.00

3 1 M3 GALIAN TANAH BIASA DALAM 3 METER 1.0500 oh Pekerja 40,000.00 42,000.00 0.0670 oh Mandor 68,000.00 4,556.00

Total : 46,556.00 46,556.00

4 1 M3 GALIAN TANAH KERAS DALAM 1METER 1.0000 oh Pekerja 40,000.00 40,000.00 0.0320 oh Mandor 68,000.00 2,176.00

Total : 42,176.00 42,176.00

5 1 M3 GALIAN TANAH CADAS DALAM 1 METER 1.5000 oh Pekerja 40,000.00 60,000.00 0.0600 oh Mandor 68,000.00 4,080.00

Total : 64,080.00 64,080.00

Page 17: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6

6 1 M3 GALIAN TANAH LUMPUR DALAM 1 METER 1.2000 oh Pekerja 40,000.00 48,000.00 0.0450 oh Mandor 68,000.00 3,060.00

Total : 51,060.00 51,060.00

7 1 M2 PEKERJAAN STRIPPING SETINGGI 1 METER 0.0500 oh Pekerja 40,000.00 2,000.00 0.0050 oh Mandor 68,000.00 340.00

Total : 2,340.00 2,340.00

8 1 M3 PEMBUANGAN TANAH SEJAUH 15 METER 0.3300 oh Pekerja 40,000.00 13,200.00 0.0100 oh Mandor 68,000.00 680.00

Total : 13,880.00 13,880.00

9 1 M3 URUGAN KEMBALI Mengurug Kembali 1 m3 galian dihitung dari 1/3 kali dari indeks pekerjaan galian

10 1 M3 PEMADATAN TANAH ( Per 20 Cm ) 0.5000 oh Pekerja 40,000.00 20,000.00 0.0500 oh Mandor 68,000.00 3,400.00

Total : 23,400.00 23,400.00

11 1 M3 URUGAN PASIR 1.2000 m3 Pasir Urug 130,000.00 156,000.00 0.3000 oh Pekerja 40,000.00 12,000.00 0.0100 oh Mandor 68,000.00 680.00

Total : 12,680.00 156,000.00 168,680.00

12 1 M3 PEMASANGAN LAPISAN IJUK TEBAL 10 CM 6.0000 m3 Ijuk 2,500.00 15,000.00 0.1500 oh Pekerja 40,000.00 6,000.00 0.0150 oh Mandor 68,000.00 1,020.00

Total : 7,020.00 15,000.00 22,020.00

13 1 M3 URUGAN SIRTU PADAT Untuk Peninggian Lantai Bangunan 1.2000 m3 Sirtu 125,000.00 150,000.00 0.2500 oh Pekerja 40,000.00 10,000.00 0.0250 oh Mandor 68,000.00 1,700.00

Total : 11,700.00 150,000.00 161,700.00

14 1 M3 URUGAN TANAH PILIHAN DIPADATKAN 1.2000 m3 Tanah Urug 80,000.00 96,000.00 0.5000 oh Pekerja 40,000.00 20,000.00 0.0500 oh Mandor 68,000.00 3,400.00

Total : 23,400.00 96,000.00 119,400.00 15 1 M3 URUGAN LIMESTONE PADAT

1.2000 m3 Limestone 85,000.00 102,000.00 0.2500 oh Pekerja 40,000.00 10,000.00 0.0250 oh Mandor 68,000.00 1,700.00

Total : 11,700.00 102,000.00 113,700.00

III PEKERJAAN PONDASI (SNI 2836 : 2008)

1 1 M3 BATU KALI CAMP. 1 PC : 3 PS 1.2000 m3 Batu Kali / Batu Bulat 15/20 180,000.00 216,000.00 202.0000 kg Semen Portland 1,220.00 246,440.00 0.4850 m3 Pasir Pasang 158,000.00 76,630.00 1.5000 oh Pekerja 40,000.00 60,000.00 0.7500 oh Tukang Batu 45,000.00 33,750.00 0.0750 oh Kepala Tukang 60,000.00 4,500.00 0.0750 oh Mandor 68,000.00 5,100.00

Total : 103,350.00 539,070.00 642,420.00

2 1 M3 BATU KALI CAMP. 1 PC : 4 PS 1.2000 m3 Batu Kali / Batu Bulat 15/20 180,000.00 216,000.00 163.0000 kg Semen Portland 1,220.00 198,860.00 0.5200 m3 Pasir Pasang 158,000.00 82,160.00 1.5000 oh Pekerja 40,000.00 60,000.00 0.7500 oh Tukang Batu 45,000.00 33,750.00 0.0750 oh Kepala Tukang 60,000.00 4,500.00 0.0750 oh Mandor 68,000.00 5,100.00

Total : 103,350.00 497,020.00 600,370.00

Page 18: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6

3 1 M3 BATU KALI CAMP. 1 PC : 5 PS 1.2000 m3 Batu Kali / Batu Bulat 15/20 180,000.00 216,000.00 136.0000 kg Semen Portland 1,220.00 165,920.00 0.5440 m3 Pasir Pasang 158,000.00 85,952.00 1.5000 oh Pekerja 40,000.00 60,000.00 0.7500 oh Tukang Batu 45,000.00 33,750.00 0.0750 oh Kepala Tukang 60,000.00 4,500.00 0.0750 oh Mandor 68,000.00 5,100.00

Total : 103,350.00 467,872.00 571,222.00

4 1 M3 BATU KALI CAMP. 1 PC : 6 PS 1.2000 m3 Batu Kali / Batu Bulat 15/20 180,000.00 216,000.00 117.0000 kg Semen Portland 1,220.00 142,740.00 0.5610 m3 Pasir Pasang 158,000.00 88,638.00 1.5000 oh Pekerja 40,000.00 60,000.00 0.7500 oh Tukang Batu 45,000.00 33,750.00 0.0750 oh Kepala Tukang 60,000.00 4,500.00 0.0750 oh Mandor 68,000.00 5,100.00

Total : 103,350.00 447,378.00 550,728.00

5 1 M3 BATU KALI CAMP. 1 PC : 8 PS 1.2000 m3 Batu Kali / Batu Bulat 15/20 180,000.00 216,000.00 91.0000 kg Semen Portland 1,220.00 111,020.00 0.5840 m3 Pasir Pasang 158,000.00 92,272.00 1.5000 oh Pekerja 40,000.00 60,000.00 0.7500 oh Tukang Batu 45,000.00 33,750.00 0.0750 oh Kepala Tukang 60,000.00 4,500.00 0.0750 oh Mandor 68,000.00 5,100.00

Total : 103,350.00 419,292.00 522,642.00

6 1 M3 PASANGAN PONDASI SIKLOP, 40% BATU KALI 0.4800 m3 Batu Kali / Batu Bulat 15/20 180,000.00 86,400.00 194.0000 kg Semen Portland 1,220.00 236,680.00 0.3120 m3 Pasir Beton 141,000.00 43,992.00 0.4680 m3 Koral Beton 170,000.00 79,560.00 126.0000 kg Besi Beton 8,427.00 1,061,802.00 1.8000 kg Kawat Beton 16,000.00 28,800.00 3.4000 oh Pekerja 40,000.00 136,000.00 0.8500 oh Tukang Batu 45,000.00 38,250.00 0.0850 oh Kepala Tukang 60,000.00 5,100.00 0.1700 oh Mandor 68,000.00 11,560.00

190,910.00 1,537,234.00 1,728,144.00

7 1 M3 PASANGAN PONDASI SUMURAN DIAMETER 1 M 0.4500 m3 Batu Kali / Batu Bulat 15/20 180,000.00 81,000.00 194.0000 kg Semen Portland 1,220.00 236,680.00 0.3120 m3 Pasir Beton 141,000.00 43,992.00 0.4680 m3 Koral Beton 170,000.00 79,560.00 2.4000 oh Pekerja 40,000.00 96,000.00 0.8000 oh Tukang Batu 45,000.00 36,000.00 0.0800 oh Kepala Tukang 60,000.00 4,800.00 0.1190 oh Mandor 68,000.00 8,092.00

Total : 144,892.00 441,232.00 586,124.00

8 1 M3 PASANGAN BATU KOSONG 1.2000 m3 Batu Kali / Batu Bulat 15/20 15/20 180,000.00 216,000.00 0.4320 m3 Pasir Urug 130,000.00 56,160.00 0.7800 oh Pekerja 40,000.00 31,200.00 0.3900 oh Tukang Batu 45,000.00 17,550.00 0.0390 oh Kepala Tukang 60,000.00 2,340.00 0.0390 oh Mandor 68,000.00 2,652.00

Total : 53,742.00 272,160.00 325,902.00

SNI 03-2836-20029 1 M1 Pembuatan Tiang Pancang 35 cm x 35 cm Beton Bertulang

0.0160 m3 Pasir Urug 130,000.00 2,080.00 0.0800 m3 Pasir Beton 141,000.00 11,280.00 0.1250 m3 Koral Beton 170,000.00 21,250.00 49.0000 kg Semen Portland 1,220.00 59,780.00 34.5000 kg Besi Beton 8,427.00 290,731.50 0.7000 kg Kawat beton 16,000.00 11,200.00 0.0270 m3 Kayu Bekesting 2,250,000.00 60,750.00 0.1200 kg Paku Reng SQ 13,000.00 1,560.00 0.2000 kg Plamir Tembok 30,000.00 6,000.00 0.0900 lt Minyak Bekisting 15,000.00 1,350.00 0.8000 oh Pekerja 40,000.00 32,000.00 0.5000 oh Tukang Batu 45,000.00 22,500.00 0.0500 oh Kepala Tukang 60,000.00 3,000.00 0.0400 oh Mandor 68,000.00 2,720.00

Total : 60,220.00 465,981.50 526,201.50 10 1 M1 Pembuatan Tiang Pancang 40 cm x 40 cm Beton Bertulang

0.0190 m3 Pasir Urug 130,000.00 2,470.00

Page 19: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6 0.0940 m3 Pasir Beton 141,000.00 13,254.00 0.1500 m3 Koral Beton 170,000.00 25,500.00 60.5000 kg Semen Portland 1,220.00 73,810.00 45.0000 kg Besi Beton 8,427.00 379,215.00 0.9000 kg Kawat beton 16,000.00 14,400.00 0.0320 m3 Kayu Bekesting 2,250,000.00 72,000.00 0.1200 kg Paku Reng SQ 13,000.00 1,560.00 0.2400 kg Plamir Tembok 30,000.00 7,200.00 0.0900 lt Minyak Bekisting 15,000.00 1,350.00 1.0000 oh Pekerja 40,000.00 40,000.00 0.6700 oh Tukang Batu 45,000.00 30,150.00 0.0670 oh Kepala Tukang 60,000.00 4,020.00 0.0500 oh Mandor 68,000.00 3,400.00

Total : 77,570.00 590,759.00 668,329.00

IV PEKERJAAN DINDING (SNI 6897 : 2008)

11 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 2 PS

140.0000 bh Bata Merah 5 x 11 x 22 cm 1,300.00 182,000.00 43.5000 kg Semen Portland 1,220.00 53,070.00 0.0800 m3 Pasir Pasang 158,000.00 12,640.00 0.6000 oh Pekerja 40,000.00 24,000.00 0.2000 oh Tukang Batu 45,000.00 9,000.00 0.0200 oh Kepala Tukang 60,000.00 1,200.00

0.0300 oh Mandor 68,000.00 2,040.00

36,240.00 247,710.00 283,950.00

2 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 3 PS 140.0000 bh Bata Merah 5 x 11 x 22 cm 1,300.00 182,000.00 32.9500 kg Semen Portland 1,220.00 40,199.00 0.0910 m3 Pasir Pasang 158,000.00 14,378.00 0.6000 oh Pekerja 40,000.00 24,000.00 0.2000 oh Tukang Batu 45,000.00 9,000.00 0.0200 oh Kepala Tukang 60,000.00 1,200.00 0.0300 oh Mandor 68,000.00 2,040.00

36,240.00 236,577.00 272,817.00

3 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 4 PS 140.0000 bh Bata Merah 5 x 11 x 22 cm 1,300.00 182,000.00 26.5500 kg Semen Portland 1,220.00 32,391.00 0.0930 m3 Pasir Pasang 158,000.00 14,694.00 0.6000 oh Pekerja 40,000.00 24,000.00 0.2000 oh Tukang Batu 45,000.00 9,000.00 0.0200 oh Kepala Tukang 60,000.00 1,200.00 0.0300 oh Mandor 68,000.00 2,040.00

36,240.00 229,085.00 265,325.00

4 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 5 PS 140.0000 bh Bata Merah 5 x 11 x 22 cm 1,300.00 182,000.00 22.2000 kg Semen Portland 1,220.00 27,084.00 0.1020 m3 Pasir Pasang 158,000.00 16,116.00 0.6000 oh Pekerja 40,000.00 24,000.00 0.2000 oh Tukang Batu 45,000.00 9,000.00 0.0200 oh Kepala Tukang 60,000.00 1,200.00 0.0300 oh Mandor 68,000.00 2,040.00

36,240.00 225,200.00 261,440.00

5 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 6 PS 140.0000 bh Bata Merah 5 x 11 x 22 cm 1,300.00 182,000.00 18.5000 kg Semen Portland 1,220.00 22,570.00 0.1220 m3 Pasir Pasang 158,000.00 19,276.00 0.6000 oh Pekerja 40,000.00 24,000.00 0.2000 oh Tukang Batu 45,000.00 9,000.00 0.0200 oh Kepala Tukang 60,000.00 1,200.00 0.0300 oh Mandor 68,000.00 2,040.00

36,240.00 223,846.00 260,086.00

6 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 2 PS 70.0000 bh Bata Merah 5 x 11 x 22 cm 1,300.00 91,000.00 18.9500 kg Semen Portland 1,220.00 23,119.00 0.0380 m3 Pasir Pasang 158,000.00 6,004.00 0.3000 oh Pekerja 40,000.00 12,000.00 0.1000 oh Tukang Batu 45,000.00 4,500.00 0.0100 oh Kepala Tukang 60,000.00 600.00 0.0150 oh Mandor 68,000.00 1,020.00

18,120.00 120,123.00 138,243.00

Page 20: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 67 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 3 PS

70.0000 bh Bata Merah 5 x 11 x 22 cm 1,300.00 91,000.00 14.3700 kg Semen Portland 1,220.00 17,531.40 0.0400 m3 Pasir Pasang 158,000.00 6,320.00 0.3000 oh Pekerja 40,000.00 12,000.00 0.1000 oh Tukang Batu 45,000.00 4,500.00 0.0100 oh Kepala Tukang 60,000.00 600.00 0.0150 oh Mandor 68,000.00 1,020.00

Total : 18,120.00 114,851.40 132,971.40

8 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 4 PS 70.0000 bh Bata Merah 5 x 11 x 22 cm 1,300.00 91,000.00 11.5000 kg Semen Portland 1,220.00 14,030.00 0.0430 m3 Pasir Pasang 158,000.00 6,794.00 0.3000 oh Pekerja 40,000.00 12,000.00 0.1000 oh Tukang Batu 45,000.00 4,500.00 0.0100 oh Kepala Tukang 60,000.00 600.00 0.0150 oh Mandor 68,000.00 1,020.00

Total : 18,120.00 111,824.00 129,944.00

9 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 5 PS 70.0000 bh Bata Merah 5 x 11 x 22 cm 1,300.00 91,000.00 9.6800 kg Semen Portland 1,220.00 11,809.60 0.0450 m3 Pasir Pasang 158,000.00 7,110.00 0.3000 oh Pekerja 40,000.00 12,000.00 0.1000 oh Tukang Batu 45,000.00 4,500.00 0.0100 oh Kepala Tukang 60,000.00 600.00 0.0150 oh Mandor 68,000.00 1,020.00

Total : 18,120.00 109,919.60 128,039.60 10 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 6 PS

70.0000 bh Bata Merah 5 x 11 x 22 cm 1,300.00 91,000.00 8.3200 kg Semen Portland 1,220.00 10,150.40 0.0490 m3 Pasir Pasang 158,000.00 7,742.00 0.3000 oh Pekerja 40,000.00 12,000.00 0.1000 oh Tukang Batu 45,000.00 4,500.00 0.0100 oh Kepala Tukang 60,000.00 600.00 0.0150 oh Mandor 68,000.00 1,020.00

Total : 18,120.00 108,892.40 127,012.40

11 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 8 PS 70.0000 bh Bata Merah 5 x 11 x 22 cm 1,300.00 91,000.00 6.5000 kg Semen Portland 1,220.00 7,930.00 0.0500 m3 Pasir Pasang 158,000.00 7,900.00 0.3000 oh Pekerja 40,000.00 12,000.00 0.1000 oh Tukang Batu 45,000.00 4,500.00 0.0100 oh Kepala Tukang 60,000.00 600.00 0.0150 oh Mandor 68,000.00 1,020.00

Total : 18,120.00 106,830.00 124,950.00

12 1 M2 PASANGAN DINDING HOLLOWBLOCK (HB. 10) 12.5000 bh Batako 2,200.00 27,500.00 7.5000 kg Semen Portland 1,220.00 9,150.00 0.0270 m3 Pasir Pasang 158,000.00 4,266.00 1.9500 kg Besi Beton 8 mm 8,427.00 16,432.65 0.3200 oh Pekerja 40,000.00 12,800.00 0.1000 oh Tukang Batu 45,000.00 4,500.00 0.0100 oh Kepala Tukang 60,000.00 600.00 0.0150 oh Mandor 68,000.00 1,020.00

Total : 18,920.00 57,348.65 76,268.65

13 1 M2 PASANGAN DINDING HOLLOWBLOCK (HB. 10) TANPA BESI 12.5000 bh Batako 2,200.00 27,500.00 7.5000 kg Semen Portland 1,220.00 9,150.00 0.0270 m3 Pasir Pasang 158,000.00 4,266.00 0.3200 oh Pekerja 40,000.00 12,800.00 0.1000 oh Tukang Batu 45,000.00 4,500.00 0.0100 oh Kepala Tukang 60,000.00 600.00 0.0150 oh Mandor 68,000.00 1,020.00

Total : 18,920.00 40,916.00 59,836.00

14 1 M2 PASANGAN DINDING Terawang/Roster (12 x 11 x 24) CM 30.0000 bh Roster Keramik 50,000.00 1,500,000.00 11.0000 kg Semen Portland 1,220.00 13,420.00 0.0350 m3 Pasir Pasang 158,000.00 5,530.00 0.3000 oh Pekerja 40,000.00 12,000.00 0.1000 oh Tukang Batu 45,000.00 4,500.00 0.0100 oh Kepala Tukang 60,000.00 600.00 0.0150 oh Mandor 68,000.00 1,020.00

Total : 18,120.00 1,518,950.00 1,537,070.00

15 1 M2 PASANGAN DINDING BEDEG, RANGKA KAYU 1.5000 m2 Bedeg/Bilik Bambu Kelas I 20,000.00 30,000.00

Page 21: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6 0.0140 m3 Kayu kamper usuk/reng 6,500,000.00 91,000.00 0.0120 kg Paku Biasa 13,000.00 156.00

Page 22: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6 0.0030 m3 List Kayu 2/4 6,500,000.00 19,500.00 0.1000 oh Pekerja 40,000.00 4,000.00 0.0500 oh Tukang Kayu 55,000.00 2,750.00 0.0050 oh Kepala Tukang 60,000.00 300.00 0.0020 oh Mandor 68,000.00 136.00

Total : 7,186.00 140,656.00 147,842.00

V PEKERJAAN PLESTERAN (SNI 2837 : 2008)

1 1 M2 PLESTERAN CAMP. 1 PC : 1 PS TEBAL 15 MM 15.5040 kg Semen Portland 1,220.00 18,914.88 0.0160 m3 Pasir Pasang 158,000.00 2,528.00 0.3000 oh Pekerja 40,000.00 12,000.00 0.1500 oh Tukang Batu 45,000.00 6,750.00 0.0150 oh Kepala Tukang 60,000.00 900.00 0.0150 oh Mandor 68,000.00 1,020.00

Total : 20,670.00 21,442.88 42,112.88 2 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 15 MM

10.2240 kg Semen Portland 1,220.00 12,473.28 0.0200 m3 Pasir Pasang 158,000.00 3,160.00 0.3000 oh Pekerja 40,000.00 12,000.00 0.1500 oh Tukang Batu 45,000.00 6,750.00 0.0150 oh Kepala Tukang 60,000.00 900.00 0.0150 oh Mandor 68,000.00 1,020.00

Total : 20,670.00 15,633.28 36,303.28

3 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 15 MM 7.7760 kg Semen Portland 1,220.00 9,486.72 0.0230 m3 Pasir Pasang 158,000.00 3,634.00 0.3000 oh Pekerja 40,000.00 12,000.00 0.1500 oh Tukang Batu 45,000.00 6,750.00 0.0150 oh Kepala Tukang 60,000.00 900.00 0.0150 oh Mandor 68,000.00 1,020.00

Total : 20,670.00 13,120.72 33,790.72

4 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 15 MM 6.2400 kg Semen Portland 1,220.00 7,612.80 0.0240 m3 Pasir Pasang 158,000.00 3,792.00 0.3000 oh Pekerja 40,000.00 12,000.00 0.1500 oh Tukang Batu 45,000.00 6,750.00 0.0150 oh Kepala Tukang 60,000.00 900.00 0.0150 oh Mandor 68,000.00 1,020.00

Total : 20,670.00 11,404.80 32,074.80

5 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 15 MM 5.1840 kg Semen Portland 1,220.00 6,324.48 0.0260 m3 Pasir Pasang 158,000.00 4,108.00 0.3000 oh Pekerja 40,000.00 12,000.00 0.1500 oh Tukang Batu 45,000.00 6,750.00 0.0150 oh Kepala Tukang 60,000.00 900.00 0.0150 oh Mandor 68,000.00 1,020.00

Total : 20,670.00 10,432.48 31,102.48

6 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 15 MM 4.4160 kg Semen Portland 1,220.00 5,387.52 0.0270 m3 Pasir Pasang 158,000.00 4,266.00 0.3000 oh Pekerja 40,000.00 12,000.00 0.1500 oh Tukang Batu 45,000.00 6,750.00 0.0150 oh Kepala Tukang 60,000.00 900.00 0.0150 oh Mandor 68,000.00 1,020.00

Total : 20,670.00 9,653.52 30,323.52

7 1 M2 PLESTERAN CAMP. 1 PC : 8 PS TEBAL 15 MM 3.4560 kg Semen Portland 1,220.00 4,216.32 0.0290 m3 Pasir Pasang 158,000.00 4,582.00 0.3000 oh Pekerja 40,000.00 12,000.00 0.1500 oh Tukang Batu 45,000.00 6,750.00 0.0150 oh Kepala Tukang 60,000.00 900.00 0.0150 oh Mandor 68,000.00 1,020.00

Total : 20,670.00 8,798.32 29,468.32

8 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 20 MM 13.6320 kg Semen Portland 1,220.00 16,631.04 0.0270 m3 Pasir Pasang 158,000.00 4,266.00 0.4000 oh Pekerja 40,000.00 16,000.00 0.2000 oh Tukang Batu 45,000.00 9,000.00 0.0200 oh Kepala Tukang 60,000.00 1,200.00 0.0220 oh Mandor 68,000.00 1,496.00

Total : 27,696.00 20,897.04 48,593.04

9 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 20 MM 10.3680 kg Semen Portland 1,220.00 12,648.96

Page 23: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6 0.0310 m3 Pasir Pasang 158,000.00 4,898.00 0.4000 oh Pekerja 40,000.00 16,000.00

Page 24: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6 0.2000 oh Tukang Batu 45,000.00 9,000.00 0.0200 oh Kepala Tukang 60,000.00 1,200.00 0.0220 oh Mandor 68,000.00 1,496.00

Total : 27,696.00 17,546.96 45,242.96

10 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 20 MM 8.3200 kg Semen Portland 1,220.00 10,150.40 0.0320 m3 Pasir Pasang 158,000.00 5,056.00 0.4000 oh Pekerja 40,000.00 16,000.00 0.2000 oh Tukang Batu 45,000.00 9,000.00 0.0200 oh Kepala Tukang 60,000.00 1,200.00 0.0220 oh Mandor 68,000.00 1,496.00

Total : 27,696.00 15,206.40 42,902.40 11 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 20 MM

6.9120 kg Semen Portland 1,220.00 8,432.64 0.0350 m3 Pasir Pasang 158,000.00 5,530.00 0.4000 oh Pekerja 40,000.00 16,000.00 0.2000 oh Tukang Batu 45,000.00 9,000.00 0.0200 oh Kepala Tukang 60,000.00 1,200.00 0.0220 oh Mandor 68,000.00 1,496.00

Total : 27,696.00 13,962.64 41,658.64

12 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 20 MM 5.8880 kg Semen Portland 1,220.00 7,183.36 0.0360 m3 Pasir Pasang 158,000.00 5,688.00 0.4000 oh Pekerja 40,000.00 16,000.00 0.2000 oh Tukang Batu 45,000.00 9,000.00 0.0200 oh Kepala Tukang 60,000.00 1,200.00 0.0220 oh Mandor 68,000.00 1,496.00

Total : 27,696.00 12,871.36 40,567.36

13 1 M2 PLESTERAN SKONING 1 PC : 2 PS, TEBAL 10 MM 0.5000 kg Semen Portland 1,220.00 610.00 0.0130 m3 Pasir Pasang 158,000.00 2,054.00 0.0800 oh Pekerja 40,000.00 3,200.00 0.4000 oh Tukang Batu 45,000.00 18,000.00 0.0400 oh Kepala Tukang 60,000.00 2,400.00 0.0040 oh Mandor 68,000.00 272.00

Total : 23,872.00 2,664.00 26,536.00

14 1 M2 PLESTERAN CIPRAT 1 PC : 2 PS 4.3200 kg Semen Portland 1,220.00 5,270.40 0.0060 m3 Pasir Pasang 158,000.00 948.00 0.3000 oh Pekerja 40,000.00 12,000.00 0.1000 oh Tukang Batu 45,000.00 4,500.00 0.0100 oh Kepala Tukang 60,000.00 600.00 0.0150 oh Mandor 68,000.00 1,020.00

Total : 18,120.00 6,218.40 24,338.40

15

3.1080 kg Semen Portland 1,220.00 3,791.76 0.1500 oh Pekerja 40,000.00 6,000.00 0.0750 oh Tukang Batu 45,000.00 3,375.00 0.0080 oh Kepala Tukang 60,000.00 480.00 0.0080 oh Mandor 68,000.00 544.00

Total : 10,399.00 3,791.76 14,190.76

16

1.6000 kg Semen Portland 1,220.00 1,952.00 0.0700 oh Pekerja 40,000.00 2,800.00 0.0350 oh Tukang Batu 45,000.00 1,575.00 0.0040 oh Kepala Tukang 60,000.00 240.00 0.0040 oh Mandor 68,000.00 272.00

Total : 4,887.00 1,952.00 6,839.00

171 M2 FINISHING SIAR PASANGAN BATU KALI ADUKAN 1PC : 2 PS

6.3400 kg Semen Portland 1,220.00 7,734.80 0.0120 m3 Pasir Pasang 158,000.00 1,896.00 0.3000 oh Pekerja 40,000.00 12,000.00 0.1500 oh Tukang Batu 45,000.00 6,750.00 0.0150 oh Kepala Tukang 60,000.00 900.00 0.0150 oh Mandor 68,000.00 1,020.00

Total : 20,670.00 9,630.80 30,300.80

18 1 M2 PEKERJAAN ACIAN 3.2500 zak Semen Portland 50 Kg 1,220.00 3,965.00 0.2000 oh Pekerja 40,000.00 8,000.00 0.1000 oh Tukang Labur/Cat 40,000.00 4,000.00 0.0100 oh Kepala Tukang 60,000.00 600.00

1 M2 FINISHING SIAR PASANGAN DINDING BATA MERAH (=20 M')

1 M2 FINISHING SIAR PASANGAN DINDING CONBLOCK EKSPOSE (= 8 M')

Page 25: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6 0.0100 oh Mandor 68,000.00 680.00

Total : 5,280.00 3,965.00 9,245.00

Page 26: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6

VI PEKERJAAN KAYU (SNI 3434 : 2008)

1

1.1000 m3 Balok Kayu Kamper 8,300,000.00 9,130,000.00 1.2500 Kg Paku 10 Cm 14,000.00 17,500.00 1.0000 Kg Lem Kayu 12,500.00 12,500.00 7.0000 oh Pekerja 40,000.00 280,000.00 21.0000 oh Tukang Kayu 55,000.00 1,155,000.00 2.1000 oh Kepala Tukang 60,000.00 126,000.00 0.3500 oh Mandor 68,000.00 23,800.00

Total : 1,584,800.00 9,160,000.00 10,744,800.00

2

1.2000 m3 Balok Kayu kruing 5,000,000.00 6,000,000.00 1.2500 Kg Paku 10 Cm 14,000.00 17,500.00 1.0000 Kg Lem Kayu 12,500.00 12,500.00 6.0000 oh Pekerja 40,000.00 240,000.00 18.0000 oh Tukang Kayu 55,000.00 990,000.00 1.8000 oh Kepala Tukang 60,000.00 108,000.00 0.3000 oh Mandor 68,000.00 20,400.00

Total : 1,358,400.00 6,030,000.00 7,388,400.00

3

0.0400 m3 Papan Kayu Kamper 9,000,000.00 360,000.00 0.0500 Kg Paku 5-7 Cm 14,000.00 700.00 0.3500 oh Pekerja 40,000.00 14,000.00 1.0500 oh Tukang Kayu 55,000.00 57,750.00 0.1050 oh Kepala Tukang 60,000.00 6,300.00 0.0180 oh Mandor 68,000.00 1,224.00

Total : 79,274.00 360,700.00 439,974.00

4

0.0400 m3 Papan Kayu Kruing 6,000,000.00 240,000.00 0.0500 Kg Paku 5-7 Cm 14,000.00 700.00 0.3500 oh Pekerja 40,000.00 14,000.00 1.0500 oh Tukang Kayu 55,000.00 57,750.00 0.1050 oh Kepala Tukang 60,000.00 6,300.00 0.0180 oh Mandor 68,000.00 1,224.00

Total : 79,274.00 240,700.00 319,974.00

5

0.0400 m3 Papan Kayu Kamper 9,000,000.00 360,000.00 0.5000 Kg Lem Kayu 12,500.00 6,250.00 1.0000 oh Pekerja 40,000.00 40,000.00 3.0000 oh Tukang Kayu 55,000.00 165,000.00 0.3000 oh Kepala Tukang 60,000.00 18,000.00 0.0500 oh Mandor 68,000.00 3,400.00

Total : 226,400.00 366,250.00 592,650.00

6

0.0240 m3 Papan Kayu Kamper 9,000,000.00 216,000.00 0.3000 Kg Lem Kayu 12,500.00 3,750.00 0.8000 oh Pekerja 40,000.00 32,000.00 2.4000 oh Tukang Kayu 55,000.00 132,000.00 0.2400 oh Kepala Tukang 60,000.00 14,400.00 0.0400 oh Mandor 68,000.00 2,720.00

Total : 181,120.00 219,750.00 400,870.00

7

0.0640 m3 Papan Kayu Kamper 9,000,000.00 576,000.00 0.5000 Kg Lem Kayu 12,500.00 6,250.00 1.0000 oh Pekerja 40,000.00 40,000.00 3.0000 oh Tukang Kayu 55,000.00 165,000.00 0.3000 oh Kepala Tukang 60,000.00 18,000.00 0.0500 oh Mandor 68,000.00 3,400.00

Total : 226,400.00 582,250.00 808,650.00 8

0.0250 m3 Papan Kayu Kamper 9,000,000.00 225,000.00 0.0300 Kg Paku 1-2,5 Cm 14,000.00 420.00 0.5000 Kg Lem Kayu 12,500.00 6,250.00 1.0000 Lbr Plywood 4 mm 47,000.00 47,000.00 1.0000 oh Pekerja 40,000.00 40,000.00 3.0000 oh Tukang Kayu 55,000.00 165,000.00

MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS I

MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS II/III

MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP STANDAR KAYU KELAS II

MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP SEDERHANA KAYU KELAS III

MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL KAYU KELAS I/II

MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA, KAYU KELAS I/II

MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA JALUSI, KAYU KELAS I/II

MEMBUAT 1 M2 DAUN PINTU PLYWOOD RANGKAP RANGKA TERTUTUP, KAYU KELAS II (Lebar Sampai 90 Cm)

Page 27: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6 0.3000 oh Kepala Tukang 60,000.00 18,000.00 0.0500 oh Mandor 68,000.00 3,400.00

Total : 226,400.00 278,670.00 505,070.00

Page 28: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6

9

0.0256 m3 Papan Kayu Kamper 9,000,000.00 230,400.00 0.0300 Kg Paku 1-2,5 Cm 14,000.00 420.00 0.5000 Kg Lem Kayu 12,500.00 6,250.00 1.0000 Lbr Plywood 4 mm 47,000.00 47,000.00 0.8000 oh Pekerja 40,000.00 32,000.00 2.4000 oh Tukang Kayu 55,000.00 132,000.00 0.2400 oh Kepala Tukang 60,000.00 14,400.00 0.0400 oh Mandor 68,000.00 2,720.00

Total : 181,120.00 284,070.00 465,190.00

10 MEMASANG 1 M2 JALUSI KUSEN, KAYU KELAS I/II

0.0600 m3 Papan Kayu Kamper 9,000,000.00 540,000.00 0.1500 Kg Paku 1-2,5 Cm 14,000.00 2,100.00 0.6700 oh Pekerja 40,000.00 26,800.00 2.0000 oh Tukang Kayu 55,000.00 110,000.00 0.2000 oh Kepala Tukang 60,000.00 12,000.00 0.3350 oh Mandor 68,000.00 22,780.00

Total : 171,580.00 542,100.00 713,680.00

11

0.0256 m3 Papan Kayu Kamper 9,000,000.00 230,400.00 0.0300 Kg Paku 1-2,5 Cm 14,000.00 420.00 0.5000 Kg Lem Kayu 12,500.00 6,250.00 1.0000 Lbr Teakwood 4 mm uk 90x220 cm 56,000.00 56,000.00 0.8000 oh Pekerja 40,000.00 32,000.00 2.4000 oh Tukang Kayu 55,000.00 132,000.00 0.2400 oh Kepala Tukang 60,000.00 14,400.00 0.0400 oh Mandor 68,000.00 2,720.00

Total : 181,120.00 293,070.00 474,190.00

12

0.0250 m3 Papan Kayu Kamper 9,000,000.00 225,000.00 0.0300 Kg Paku 1-2,5 Cm 14,000.00 420.00 0.8000 Kg Lem Kayu 12,500.00 10,000.00 1.0000 Lbr Teakwood 4 mm uk 90x220 cm 56,000.00 56,000.00 0.5000 Lbr Formika 80,000.00 40,000.00 0.8000 oh Pekerja 40,000.00 32,000.00 2.4000 oh Tukang Kayu 55,000.00 132,000.00 0.2400 oh Kepala Tukang 60,000.00 14,400.00 0.0400 oh Mandor 68,000.00 2,720.00

Total : 181,120.00 331,420.00 512,540.00

13

1.1000 m3 Balok Kayu Kamper 8,300,000.00 9,130,000.00 15.0000 Kg Besi Strip Tebal 5 cm 8,000.00 120,000.00 5.6000 Kg Paku 12 Cm 14,000.00 78,400.00 4.0000 oh Pekerja 40,000.00 160,000.00 12.0000 oh Tukang Kayu 55,000.00 660,000.00 1.2000 oh Kepala Tukang 60,000.00 72,000.00 0.2000 oh Mandor 68,000.00 13,600.00

Total : 905,600.00 9,328,400.00 10,234,000.00

14

1.2000 m3 Balok Kayu Kamper 8,300,000.00 9,960,000.00 15.0000 Kg Besi Strip Tebal 5 cm 8,000.00 120,000.00 5.6000 Kg Paku 12 Cm 14,000.00 78,400.00 6.7000 oh Pekerja 40,000.00 268,000.00 20.1000 oh Tukang Kayu 55,000.00 1,105,500.00 2.0100 oh Kepala Tukang 60,000.00 120,600.00 0.3350 oh Mandor 68,000.00 22,780.00

Total : 1,516,880.00 10,158,400.00 11,675,280.00

15 MEMASANG 1 M3 KONSTRUKSI GORDENG, KAYU KELAS II

1.1000 m3 Balok Kayu Kamper 8,300,000.00 9,130,000.00 15.0000 Kg Besi Strip Tebal 5 cm 8,000.00 120,000.00 3.0000 Kg Paku 12 Cm 14,000.00 42,000.00 2.4000 oh Pekerja 40,000.00 96,000.00 7.2000 oh Tukang Kayu 55,000.00 396,000.00 0.7200 oh Kepala Tukang 60,000.00 43,200.00 0.1200 oh Mandor 68,000.00 8,160.00

Total : 543,360.00 9,292,000.00 9,835,360.00

MEMBUAT 1 M2 DAUN PINTU PLYWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS I/II

MEMBUAT 1 M2 TEAKWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS I

MEMBUAT 1 M2 TEAKWOOD RANGKAP LAPIS FORMIKA RANGKA EXPOSE, KAYU KELAS II

MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KELAS I,II,III Bentang 6 M'

MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA EXPOSE, KAYU KELAS I

Page 29: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6

16

0.0140 m3 Kaso-Kaso ( 5 x 7 ) Cm 3,000,000.00 42,000.00 0.0036 m3 Reng ( 2 x 3 ) Cm 6,500,000.00 23,400.00 0.2500 Kg Paku 5 Cm dan 10 Cm 14,000.00 3,500.00 0.1000 oh Pekerja 40,000.00 4,000.00 0.1000 oh Tukang Kayu 55,000.00 5,500.00 0.0100 oh Kepala Tukang 60,000.00 600.00 0.0050 oh Mandor 68,000.00 340.00

Total : 10,440.00 68,900.00 79,340.00

17

0.0140 m3 Kaso-Kaso ( 5 x 7 ) Cm 3,000,000.00 42,000.00 0.0072 m3 Reng ( 2 x 3 ) Cm 6,500,000.00 46,800.00 0.2500 Kg Paku 5 Cm dan 10 Cm 14,000.00 3,500.00 0.1000 oh Pekerja 40,000.00 4,000.00 0.1000 oh Tukang Kayu 55,000.00 5,500.00 0.0100 oh Kepala Tukang 60,000.00 600.00 0.0050 oh Mandor 68,000.00 340.00

Total : 10,440.00 92,300.00 102,740.00

18 MEMASANG 1 M2 RANGKA ATAP SIRAP, KAYU KELAS II

0.1650 m3 Balok Kayu Kamper 8,300,000.00 1,369,500.00 0.2000 Kg Paku 5 Cm dan 10 Cm 14,000.00 2,800.00 0.1200 oh Pekerja 40,000.00 4,800.00 0.1200 oh Tukang Kayu 55,000.00 6,600.00 0.0120 oh Kepala Tukang 60,000.00 720.00 0.0060 oh Mandor 68,000.00 408.00

Total : 12,528.00 1,372,300.00 1,384,828.00

19

0.0154 m3 Kaso-Kaso ( 5 x 7 ) Cm 3,000,000.00 46,200.00 0.2000 Kg Paku 7 Cm dan 10 Cm 14,000.00 2,800.00 0.1500 oh Pekerja 40,000.00 6,000.00 0.3000 oh Tukang Kayu 55,000.00 16,500.00 0.0300 oh Kepala Tukang 60,000.00 1,800.00 0.0750 oh Mandor 68,000.00 5,100.00

Total : 29,400.00 49,000.00 78,400.00

20

0.0163 m3 Kaso-Kaso ( 5 x 7 ) Cm 3,000,000.00 48,900.00 0.2500 Kg Paku 7 Cm dan 10 Cm 14,000.00 3,500.00 0.2000 oh Pekerja 40,000.00 8,000.00 0.3000 oh Tukang Kayu 55,000.00 16,500.00 0.0300 oh Kepala Tukang 60,000.00 1,800.00 0.0100 oh Mandor 68,000.00 680.00

Total : 26,980.00 52,400.00 79,380.00

21

0.0108 m3 Papan Kayu Kamper 9,000,000.00 97,200.00 0.1000 Kg Paku 5 Cm dan 7 Cm 14,000.00 1,400.00 0.1000 oh Pekerja 40,000.00 4,000.00 0.2000 oh Tukang Kayu 55,000.00 11,000.00 0.0200 oh Kepala Tukang 60,000.00 1,200.00 0.0050 oh Mandor 68,000.00 340.00

Total : 16,540.00 98,600.00 115,140.00

22

0.0110 m3 Papan Kayu Kamper 9,000,000.00 99,000.00 0.0500 Kg Paku 5 Cm dan 7 Cm 14,000.00 700.00 0.1000 oh Pekerja 40,000.00 4,000.00 0.2000 oh Tukang Kayu 55,000.00 11,000.00 0.0200 oh Kepala Tukang 60,000.00 1,200.00 0.0050 oh Mandor 68,000.00 340.00

Total : 16,540.00 99,700.00 116,240.00

MEMASANG 1 M2 RANGKA ATAP GENTENG KERAMIK, KAYU KELAS II

MEMASANG 1 M2 RANGKA ATAP GENTENG BETON, KAYU KELAS II

MEMASANG 1 M2 RANGKA LANGIT-LANGIT (50 X 100), KAYU KELAS II/III

MEMASANG 1 M2 RANGKA LANGIT-LANGIT (60 X 60) CM, KAYU KELAS II/III

MEMASANG 1 M' LISPLANK UKURAN (3 X 20) CM, KAYU KELAS I/II

MEMASANG 1 M' LISPLANK UKURAN (3 X 30) CM, KAYU KELAS I/II

Page 30: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6

23

0.0280 m3 Balok Kayu Kamper 8,300,000.00 232,400.00 0.1500 Kg Paku 5 Cm dan 7 Cm 14,000.00 2,100.00 0.1500 oh Pekerja 40,000.00 6,000.00 0.4500 oh Tukang Kayu 55,000.00 24,750.00 0.0450 oh Kepala Tukang 60,000.00 2,700.00 0.0080 oh Mandor 68,000.00 544.00

Total : 33,994.00 234,500.00 268,494.00

24

0.0280 m3 Balok Kayu Kamper 8,300,000.00 232,400.00 0.1500 Kg Paku 5 Cm dan 7 Cm 14,000.00 2,100.00 0.8600 Lbr Teakwood 4 mm uk 90x220 cm 56,000.00 48,160.00 0.5600 Kg Lem Kayu 12,500.00 7,000.00 0.1500 oh Pekerja 40,000.00 6,000.00 0.4500 oh Tukang Kayu 55,000.00 24,750.00 0.0450 oh Kepala Tukang 60,000.00 2,700.00 0.0080 oh Mandor 68,000.00 544.00

Total : 33,994.00 289,660.00 323,654.00

25

0.0280 m3 Balok Kayu Kamper 8,300,000.00 232,400.00 0.1500 Kg Paku 5 Cm dan 7 Cm 14,000.00 2,100.00 0.8600 Lbr Plywood tebal 4 mm uk 120 x 240 cm 47,000.00 40,420.00 0.5600 Kg Lem Kayu 12,500.00 7,000.00 0.2000 oh Pekerja 40,000.00 8,000.00 0.6000 oh Tukang Kayu 55,000.00 33,000.00 0.0600 oh Kepala Tukang 60,000.00 3,600.00 0.0100 oh Mandor 68,000.00 680.00

Total : 45,280.00 281,920.00 327,200.00

26 MEMASANG 1 M2 LAMBRIZIRING DARI PAPAN KAYU KELAS I

0.0070 m3 Papan Kayu Kamper 9,000,000.00 63,000.00 0.1000 Kg Paku 5 Cm dan 10 Cm 14,000.00 1,400.00 0.1500 Kg Paku Skrup 10 cm 18,000.00 2,700.00 0.6000 oh Pekerja 40,000.00 24,000.00 1.8000 oh Tukang Kayu 55,000.00 99,000.00 0.1800 oh Kepala Tukang 60,000.00 10,800.00 0.0300 oh Mandor 68,000.00 2,040.00

Total : 135,840.00 67,100.00 202,940.00

27

0.4000 Lbr Plywood tebal 4 mm uk 120 x 240 cm 47,000.00 18,800.00 0.0500 Kg Paku 1 Cm dan 2.5 Cm 14,000.00 700.00 0.0250 oh Pekerja 40,000.00 1,000.00 0.0750 oh Tukang Kayu 55,000.00 4,125.00 0.0080 oh Kepala Tukang 60,000.00 480.00 0.0010 oh Mandor 68,000.00 68.00

Total : 5,673.00 19,500.00 25,173.00

VII PEKERJAAN BETON ( SNI 7394:2008)1

247.0000 kg Semen Portland 1,220.00 301,340.00 869.0000 kg Pasir Beton 100.71 87,516.99 999.0000 kg Koral Beton 92.59 92,497.41 215.0000 lt Air 25.00 5,375.00 1.6500 oh Pekerja 40,000.00 66,000.00 0.2750 oh Tukang Batu 45,000.00 12,375.00 0.0280 oh Kepala Tukang 60,000.00 1,680.00 0.0830 oh Mandor 68,000.00 5,644.00

85,699.00 486,729.40 572,428.40

2 276.0000 kg Semen Portland 1,220.00 336,720.00 828.0000 kg Pasir Beton 100.71 83,387.88 1,012.0000 kg Koral Beton 92.59 93,701.08 215.0000 lt Air 25.00 5,375.00 1.6500 oh Pekerja 40,000.00 66,000.00 0.2750 oh Tukang Batu 45,000.00 12,375.00 0.0280 oh Kepala Tukang 60,000.00 1,680.00 0.0830 oh Mandor 68,000.00 5,644.00

Total : 85,699.00 519,183.96 604,882.96

MEMASANG 1 M2 RANGKA DINDING PEMISAH (60 X 120) CM, KAYU KELAS II/III

MEMASANG 1 M2 RANGKA DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA KAYU KELAS II

MEMASANG 1 M2 RANGKA DINDING PEMISAH PLYWOOD RANGKAP, RANGKA KAYU KELAS II

MEMASANG 1 M2 LAMBRIZIRING DARI PLYWOOD UKURAN (120 X 240) CM

MEMBUAT 1 M³ BETON MUTU f'C= 7,4 Mpa (K100), Slump (12 ± 2)cm, w/c = 0,87

MEMBUAT 1 M³ BETON MUTU f'C= 9,8 Mpa (K125), Slump (12 ± 2)cm, w/c = 0,78

Page 31: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6

3 299.0000 kg Semen Portland 1,220.00 364,780.00 799.0000 kg Pasir Beton 100.71 80,467.29 1,017.0000 kg Koral Beton 92.59 94,164.03 215.0000 lt Air 25.00 5,375.00 1.6500 oh Pekerja 40,000.00 66,000.00 0.2750 oh Tukang Batu 45,000.00 12,375.00 0.0280 oh Kepala Tukang 60,000.00 1,680.00 0.0830 oh Mandor 68,000.00 5,644.00

Total : 85,699.00 544,786.32 630,485.32

4 326.0000 kg Semen Portland 1,220.00 397,720.00 760.0000 kg Pasir Beton 100.71 76,539.60 1,029.0000 kg Koral Beton 92.59 95,275.11 215.0000 lt Air 25.00 5,375.00 1.6500 oh Pekerja 40,000.00 66,000.00 0.2750 oh Tukang Batu 45,000.00 12,375.00 0.0280 oh Kepala Tukang 60,000.00 1,680.00 0.0830 oh Mandor 68,000.00 5,644.00

Total : 85,699.00 574,909.71 660,608.71

5 352.0000 kg Semen Portland 1,220.00 429,440.00 731.0000 kg Pasir Beton 100.71 73,619.01 1,031.0000 kg Koral Beton 92.59 95,460.29 215.0000 lt Air 25.00 5,375.00 1.6500 oh Pekerja 40,000.00 66,000.00 0.2750 oh Tukang Batu 45,000.00 12,375.00 0.0280 oh Kepala Tukang 60,000.00 1,680.00 0.0830 oh Mandor 68,000.00 5,644.00

Total : 85,699.00 603,894.30 689,593.30 6

371.0000 kg Semen Portland 1,220.00 452,620.00 698.0000 kg Pasir Beton 100.71 70,295.58 1,047.0000 kg Koral Beton 92.59 96,941.73 215.0000 lt Air 25.00 5,375.00 1.6500 oh Pekerja 40,000.00 66,000.00 0.2750 oh Tukang Batu 45,000.00 12,375.00 0.0280 oh Kepala Tukang 60,000.00 1,680.00 0.0830 oh Mandor 68,000.00 5,644.00

Total : 85,699.00 625,232.31 710,931.31 7

384.0000 kg Semen Portland 1,220.00 468,480.00 692.0000 kg Pasir Beton 100.71 69,691.32 1,039.0000 kg Koral Beton 92.59 96,201.01 215.0000 lt Air 25.00 5,375.00 1.6500 oh Pekerja 40,000.00 66,000.00 0.2750 oh Tukang Batu 45,000.00 12,375.00 0.0280 oh Kepala Tukang 60,000.00 1,680.00 0.0830 oh Mandor 68,000.00 5,644.00

Total : 85,699.00 639,747.33 725,446.33 8

406.0000 kg Semen Portland 1,220.00 495,320.00 684.0000 kg Pasir Beton 100.71 68,885.64 1,026.0000 kg Koral Beton 92.59 94,997.34 215.0000 lt Air 25.00 5,375.00 1.6500 oh Pekerja 40,000.00 66,000.00 0.2750 oh Tukang Batu 45,000.00 12,375.00 0.0280 oh Kepala Tukang 60,000.00 1,680.00 0.0830 oh Mandor 68,000.00 5,644.00

Total : 85,699.00 664,577.98 750,276.98 9

413.0000 kg Semen Portland 1,220.00 503,860.00 681.0000 kg Pasir Beton 100.71 68,583.51 1,021.0000 kg Koral Beton 92.59 94,534.39 215.0000 lt Air 25.00 5,375.00 1.6500 oh Pekerja 40,000.00 66,000.00 0.2750 oh Tukang Batu 45,000.00 12,375.00 0.0280 oh Kepala Tukang 60,000.00 1,680.00 0.0830 oh Mandor 68,000.00 5,644.00

Total : 85,699.00 672,352.90 758,051.90 10

439.0000 kg Semen Portland 1,220.00 535,580.00 670.0000 kg Pasir Beton 100.71 67,475.70 1,006.0000 kg Koral Beton 92.59 93,145.54 215.0000 lt Air 25.00 5,375.00 1.6500 oh Pekerja 40,000.00 66,000.00 0.2750 oh Tukang Batu 45,000.00 12,375.00 0.0280 oh Kepala Tukang 60,000.00 1,680.00 0.0830 oh Mandor 68,000.00 5,644.00

MEMBUAT 1 M³ BETON MUTU f'C= 12,2 Mpa (K150), Slump (12 ± 2)cm, w/c = 0,72

MEMBUAT 1 M³ BETON MUTU f'C= 14,5 Mpa (K175), Slump (12 ± 2)cm, w/c = 0,66

MEMBUAT 1 M³ BETON MUTU f'C= 16,9 Mpa (K200), Slump (12 ± 2)cm, w/c = 0,61

MEMBUAT 1 M³ BETON MUTU f'C= 19,3 Mpa (K225), Slump (12 ± 2)cm, w/c = 0,58

MEMBUAT 1 M³ BETON MUTU f'C= 21,7 Mpa (K250), Slump (12 ± 2)cm, w/c =0,56

MEMBUAT 1 M³ BETON MUTU f'C= 24,0 Mpa (K275), Slump (12 ± 2)cm, w/c =0,53

MEMBUAT 1 M³ BETON MUTU f'C= 26,4 Mpa (K300), Slump (12 ± 2)cm, w/c =0,52

MEMBUAT 1 M³ BETON MUTU f'C= 28,8 Mpa (K325), Slump (12 ± 2)cm, w/c =0,49

Page 32: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6Total : 85,699.00 701,576.24 787,275.24

Page 33: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 611

448.0000 kg Semen Portland 1,220.00 546,560.00 667.0000 kg Pasir Beton 100.71 67,173.57 1,000.0000 kg Koral Beton 92.59 92,590.00 215.0000 lt Air 25.00 5,375.00 1.6500 oh Pekerja 40,000.00 66,000.00 0.2750 oh Tukang Batu 45,000.00 12,375.00 0.0280 oh Kepala Tukang 60,000.00 1,680.00 0.0830 oh Mandor 68,000.00 5,644.00

Total : 85,699.00 711,698.57 797,397.57

12 PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR 10.5000 kg Besi Beton (Polos/ Ulir) 8,427.00 88,483.50 0.1500 kg Kawat Beton 16,000.00 2,400.00 0.0700 oh Pekerja 40,000.00 2,800.00 0.0700 oh Tukang Besi 50,000.00 3,500.00 0.0070 oh Kepala Tukang 60,000.00 420.00 0.0040 oh Mandor 68,000.00 272.00

Total : 6,992.00 90,883.50 97,875.50

13 1 M2 PASANG BEKISTING UNTUK PONDASI 0.0400 m3 Kayu Kelas III 2,500,000.00 100,000.00 0.3000 kg Paku Biasa 5' - 10' 13,000.00 3,900.00 0.1000 ltr Minyak Bekisting 15,000.00 1,500.00 0.5200 oh Pekerja 40,000.00 20,800.00 0.2600 oh Tukang Kayu 55,000.00 14,300.00 0.0260 oh Kepala Tukang 60,000.00 1,560.00 0.0260 oh Mandor 68,000.00 1,768.00

Total : 38,428.00 105,400.00 143,828.00

14 1 M2 PASANG BEKISTING UNTUK SLOOF 0.0400 m3 Kayu Kelas III 2,500,000.00 100,000.00 0.3000 kg Paku Biasa 5' - 10' 13,000.00 3,900.00 0.1000 ltr Minyak Bekisting 15,000.00 1,500.00 0.5200 oh Pekerja 40,000.00 20,800.00 0.2600 oh Tukang Kayu 55,000.00 14,300.00 0.0260 oh Kepala Tukang 60,000.00 1,560.00 0.0260 oh Mandor 68,000.00 1,768.00

Total : 38,428.00 105,400.00 143,828.00

15 1 M2 PASANG BEKISTING UNTUK KOLOM 0.0400 m3 Kayu Kelas III 2,500,000.00 100,000.00 0.4000 kg Paku Biasa 5' - 12' 13,000.00 5,200.00 0.2000 ltr Minyak Bekisting 15,000.00 3,000.00 0.0150 m3 Kayu Usuk 4/6 6,000,000.00 90,000.00 0.3500 lbr Plywood 9 mm 105,500.00 36,925.00 2.0000 btg Dolken Kayu 8" - 10"/4 m 90,000.00 180,000.00 0.6600 oh Pekerja 40,000.00 26,400.00 0.3300 oh Tukang Kayu 55,000.00 18,150.00 0.0330 oh Kepala Tukang 60,000.00 1,980.00 0.0330 oh Mandor 68,000.00 2,244.00

Total : 48,774.00 415,125.00 463,899.00

16 1 M2 PASANG BEKISTING UNTUK BALOK 0.0400 m3 Kayu Kelas III 2,500,000.00 100,000.00 0.4000 kg Paku Biasa 5' - 12' 13,000.00 5,200.00 0.2000 ltr Minyak Bekisting 15,000.00 3,000.00 0.0180 m3 Kayu Usuk 4/6 6,000,000.00 108,000.00 0.3500 lbr Plywood 9 mm 105,500.00 36,925.00 2.0000 btg Dolken Kayu 8" - 10"/4m 90,000.00 180,000.00 0.6600 oh Pekerja 40,000.00 26,400.00 0.3300 oh Tukang Kayu 55,000.00 18,150.00 0.0330 oh Kepala Tukang 60,000.00 1,980.00 0.0330 oh Mandor 68,000.00 2,244.00

Total : 48,774.00 433,125.00 481,899.00

17 1 M2 PASANG BEKISTING UNTUK LANTAI 0.0400 m3 Kayu Kelas III 2,500,000.00 100,000.00 0.4000 kg Paku Biasa 5' - 12' 13,000.00 5,200.00 0.2000 ltr Minyak Bekisting 15,000.00 3,000.00 0.0150 m3 Kayu Usuk 4/6 6,000,000.00 90,000.00 0.3500 lbr Plywood 9 mm 105,500.00 36,925.00 6.0000 btg Dolken Kayu 8" - 10"/4m 90,000.00 540,000.00

0.6600 oh Pekerja 40,000.00 26,400.00 0.3300 oh Tukang Kayu 55,000.00 18,150.00 0.0330 oh Kepala Tukang 60,000.00 1,980.00 0.0330 oh Mandor 68,000.00 2,244.00

Total : 48,774.00 775,125.00 823,899.00

MEMBUAT 1 M³ BETON MUTU f'C= 31,2 Mpa (K350), Slump (12 ± 2)cm, w/c =0,48

Page 34: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6

18 1 M2 PASANG BEKISTING UNTUK DINDING

0.0300 Kayu Kelas III 2,500,000.00 75,000.00 0.4000 Kg Paku Biasa 5' - 12' 13,000.00 5,200.00 0.2000 Ltr Minyak Bekisting 15,000.00 3,000.00

0.0200 Kayu Usuk 4/6 6,000,000.00 120,000.00 0.3500 Lbr Plywood 9 mm 105,500.00 36,925.00 3.0000 Btng Dolken Kayu 8" - 10"/4m 90,000.00 270,000.00 4.0000 Bh Formite/penjaga jarak bekisting/spacer 2,000.00 8,000.00 0.6600 Oh Pekerja 40,000.00 26,400.00 0.3300 Oh Tukang Kayu 55,000.00 18,150.00 0.0330 Oh Kepala Tukang 60,000.00 1,980.00 0.0330 Oh Mandor 68,000.00 2,244.00

48,774.00 518,125.00 566,899.00

19 1 M2 PASANG BEKISTING UNTUK TANGGA 0.0300 m3 Kayu Kelas III 2,500,000.00 75,000.00 0.4000 kg Paku Biasa 5' - 12' 13,000.00 5,200.00 0.1500 ltr Minyak Bekisting 15,000.00 2,250.00 0.0150 m3 Kayu Usuk 4/6 6,000,000.00 90,000.00 0.3500 lbr Plywood 9 mm 105,500.00 36,925.00 2.0000 btg Dolken Kayu 8" - 10"/4m 90,000.00 180,000.00 0.6600 oh Pekerja 40,000.00 26,400.00 0.3300 oh Tukang Kayu 55,000.00 18,150.00 0.0330 oh Kepala Tukang 60,000.00 1,980.00 0.0330 oh Mandor 68,000.00 2,244.00

Total : 48,774.00 389,375.00 438,149.00

20 1 M2 PASANG JEMBATAN UNTUK PENGECORAN BETON 0.0264 m3 Kayu Kelas III (Papan) 2,500,000.00 66,000.00 0.6000 kg Paku Biasa 5' - 12' 13,000.00 7,800.00 0.5000 btg Dolken Kayu 8" - 10"/4m 90,000.00 45,000.00 0.1500 oh Pekerja 40,000.00 6,000.00 0.0500 oh Tukang Kayu 55,000.00 2,750.00 0.0050 oh Kepala Tukang 60,000.00 300.00 0.0080 oh Mandor 68,000.00 544.00

Total : 9,594.00 118,800.00 128,394.00

21 1 M3 MEMBUAT PONDASI BETON BERTULANG (150 KG BESI + BEKISTING) 0.2000 m3 Kayu Kelas III 2,500,000.00 500,000.00 1.5000 kg Paku Biasa 5' - 12' 13,000.00 19,500.00 0.4000 ltr Minyak Bekisting 15,000.00 6,000.00 157.0000 kg Besi Beton 8,427.00 1,323,039.00 2.2500 kg Kawat Beton 16,000.00 36,000.00 336.0000 kg Semen Portland 1,220.00 409,920.00 0.5400 m3 Pasir Beton 141,000.00 76,140.00 0.8100 m3 Koral Beton 170,000.00 137,700.00 5.3000 oh Pekerja 40,000.00 212,000.00 0.2750 oh Tukang Batu 45,000.00 12,375.00 1.3000 oh Tukang Kayu 55,000.00 71,500.00 1.0500 oh Tukang Besi 50,000.00 52,500.00 0.2620 oh Kepala Tukang 60,000.00 15,720.00 0.2650 oh Mandor 68,000.00 18,020.00

Total : 382,115.00 2,508,299.00 2,890,414.00

22 1 M3 MEMBUAT SLOOF BETON BERTULANG (200 KG + BEKISTING) 0.2700 m3 Kayu Kelas III 2,500,000.00 675,000.00 2.0000 kg Paku Biasa 5' - 12' 13,000.00 26,000.00 0.6000 ltr Minyak Bekisting 15,000.00 9,000.00 210.0000 kg Besi Beton 8,427.00 1,769,670.00 3.0000 kg Kawat Beton 16,000.00 48,000.00 336.0000 kg Semen Portland 1,220.00 409,920.00 0.5400 m3 Pasir Beton 141,000.00 76,140.00 0.8100 m3 Koral Beton 170,000.00 137,700.00 5.6500 oh Pekerja 40,000.00 226,000.00 0.2750 oh Tukang Batu 45,000.00 12,375.00 1.5600 oh Tukang Kayu 55,000.00 85,800.00 1.4000 oh Tukang Besi 50,000.00 70,000.00 0.3230 oh Kepala Tukang 60,000.00 19,380.00 0.2830 oh Mandor 68,000.00 19,244.00

Total : 432,799.00 3,151,430.00 3,584,229.00

M3

M3

Page 35: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6

23

0.4000 m3 Kayu Kelas III 2,500,000.00 1,000,000.00 4.0000 kg Paku Biasa 5' - 12' 13,000.00 52,000.00 2.0000 ltr Minyak Bekisting 15,000.00 30,000.00 315.0000 kg Besi Beton 8,427.00 2,654,505.00 4.5000 kg Kawat Beton 16,000.00 72,000.00 336.0000 kg Semen Portland 1,220.00 409,920.00 0.5400 m3 Pasir Beton 141,000.00 76,140.00 0.8100 m3 Koral Beton 170,000.00 137,700.00 0.1500 m3 Kayu Kelas II balok 5,000,000.00 750,000.00 3.5000 lbr Plywood 9 mm 105,500.00 369,250.00 20.0000 btg Dolken Kayu 8" /4 m 90,000.00 1,800,000.00 7.0500 oh Pekerja 40,000.00 282,000.00 0.2750 oh Tukang Batu 45,000.00 12,375.00 1.6500 oh Tukang Kayu 55,000.00 90,750.00 2.1000 oh Tukang Besi 50,000.00 105,000.00 0.4030 oh Kepala Tukang 60,000.00 24,180.00 0.3530 oh Mandor 68,000.00 24,004.00

Total : 538,309.00 7,351,515.00 7,889,824.00

24

0.3200 m3 Kayu Kelas III 2,500,000.00 800,000.00 3.2000 kg Paku Biasa 5' - 12' 13,000.00 41,600.00 1.6000 ltr Minyak Bekisting 15,000.00 24,000.00 210.0000 kg Besi Beton 8,427.00 1,769,670.00 3.0000 kg Kawat Beton 16,000.00 48,000.00 336.0000 kg Semen Portland 1,220.00 409,920.00 0.5400 m3 Pasir Beton 141,000.00 76,140.00 0.8100 m3 Koral Beton 170,000.00 137,700.00 0.1400 m3 Kayu Kelas II balok 5,000,000.00 700,000.00 2.8000 lbr Plywood 9 mm 105,500.00 295,400.00 16.0000 btg Dolken Kayu 8" /4 m 90,000.00 1,440,000.00 6.3500 oh Pekerja 40,000.00 254,000.00 0.2750 oh Tukang Batu 45,000.00 12,375.00 1.6500 oh Tukang Kayu 55,000.00 90,750.00 1.4000 oh Tukang Besi 50,000.00 70,000.00 0.3330 oh Kepala Tukang 60,000.00 19,980.00 0.3180 oh Mandor 68,000.00 21,624.00

Total : 468,729.00 5,742,430.00 6,211,159.00 25

0.3200 m3 Kayu Kelas III 2,500,000.00 800,000.00 3.2000 kg Paku Biasa 5' - 12' 13,000.00 41,600.00 1.6000 ltr Minyak Bekisting 15,000.00 24,000.00 157.5000 kg Besi Beton 8,427.00 1,327,252.50 2.2500 kg Kawat Beton 16,000.00 36,000.00 336.0000 kg Semen Portland 1,220.00 409,920.00 0.5400 m3 Pasir Beton 141,000.00 76,140.00 0.8100 m3 Koral Beton 170,000.00 137,700.00 0.1200 m3 Kayu Kelas II balok 5,000,000.00 600,000.00 2.8000 lbr Plywood 9 mm 105,500.00 295,400.00 32.0000 btg Dolken Kayu 8" /4 m 90,000.00 2,880,000.00 5.3000 oh Pekerja 40,000.00 212,000.00 0.2750 oh Tukang Batu 45,000.00 12,375.00 1.3000 oh Tukang Kayu 55,000.00 71,500.00 1.0500 oh Tukang Besi 50,000.00 52,500.00 0.2650 oh Kepala Tukang 60,000.00 15,900.00 0.2650 oh Mandor 68,000.00 18,020.00

382,295.00 6,628,012.50 7,010,307.50 26

0.2400 m3 Kayu Kelas III 2,500,000.00 600,000.00 3.2000 kg Paku Biasa 5' - 12' 13,000.00 41,600.00 1.6000 ltr Minyak Bekisting 15,000.00 24,000.00 157.0000 kg Besi Beton 8,427.00 1,323,039.00 2.2500 kg Kawat Beton 16,000.00 36,000.00 336.0000 kg Semen Portland 1,220.00 409,920.00 0.5400 m3 Pasir Beton 141,000.00 76,140.00 0.8100 m3 Koral Beton 170,000.00 137,700.00 0.1600 m3 Kayu Kelas II balok 5,000,000.00 800,000.00 2.8000 lbr Plywood 9 mm 105,500.00 295,400.00 24.0000 btg Dolken Kayu 8" /4 m 90,000.00 2,160,000.00 5.3000 oh Pekerja 40,000.00 212,000.00 0.2750 oh Tukang Batu 45,000.00 12,375.00 1.3000 oh Tukang Kayu 55,000.00 71,500.00 1.0500 oh Tukang Besi 50,000.00 52,500.00 0.2620 oh Kepala Tukang 60,000.00 15,720.00 0.2650 oh Mandor 68,000.00 18,020.00

382,115.00 5,903,799.00 6,285,914.00

1 M3 MEMBUAT KOLOM BETON BERTULANG (300 KG BESI + BEKISTING)

1 M3 MEMBUAT BALOK BETON BERTULANG (200 KG BESI + BEKISTING)

1 M3 MEMBUAT PLAT BETON BERTULANG (150 KG BESI + BEKISTING

1 M3 MEMBUAT DINDING BETON BERTULANG (150 KG BESI + BEKISTING)

Page 36: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6

27

0.2500 m3 Kayu Kelas III 2,500,000.00 625,000.00 3.0000 kg Paku Biasa 5' - 12' 13,000.00 39,000.00 1.2000 ltr Minyak Bekisting 15,000.00 18,000.00 210.0000 kg Besi Beton 8,427.00 1,769,670.00 3.0000 kg Kawat Beton 16,000.00 48,000.00 336.0000 kg Semen Portland 1,220.00 409,920.00 0.5400 m3 Pasir Beton 141,000.00 76,140.00 0.8100 m3 Koral Beton 170,000.00 137,700.00 0.1050 m3 Kayu Kelas II balok 5,000,000.00 525,000.00 2.5000 lbr Plywood 9 mm 105,500.00 263,750.00 14.0000 btg Dolken Kayu 8" /4 m 90,000.00 1,260,000.00 5.6500 oh Pekerja 40,000.00 226,000.00 0.2750 oh Tukang Batu 45,000.00 12,375.00 1.5600 oh Tukang Kayu 55,000.00 85,800.00 1.4000 oh Tukang Besi 50,000.00 70,000.00 0.3230 oh Kepala Tukang 60,000.00 19,380.00 0.2830 oh Mandor 68,000.00 19,244.00

432,799.00 5,172,180.00 5,604,979.00

28

0.0020 m3 Kayu Kelas III 2,500,000.00 5,000.00 0.0100 kg Paku Biasa 5' - 12' 13,000.00 130.00 3.0000 kg Besi Beton 8,427.00 25,281.00 0.0450 kg Kawat Beton 16,000.00 720.00 4.0000 kg Semen Portland 1,220.00 4,880.00 0.0060 m3 Pasir Beton 141,000.00 846.00 0.0090 m3 Koral Beton 170,000.00 1,530.00 0.1800 oh Pekerja 40,000.00 7,200.00 0.0200 oh Tukang Batu 45,000.00 900.00 0.0200 oh Tukang Kayu 55,000.00 1,100.00 0.0200 oh Tukang Besi 50,000.00 1,000.00 0.0060 oh Kepala Tukang 60,000.00 360.00 0.0090 oh Mandor 68,000.00 612.00

Total : 11,172.00 38,387.00 49,559.00 29

0.0030 m3 Kayu Kelas III 2,500,000.00 7,500.00 0.0200 kg Paku Biasa 5' - 12' 13,000.00 260.00 3.6000 kg Besi Beton 8,427.00 30,337.20 0.0500 kg Kawat Beton 16,000.00 800.00 5.5000 kg Semen Portland 1,220.00 6,710.00 0.0090 m3 Pasir Beton 141,000.00 1,269.00 0.0150 m3 Koral Beton 170,000.00 2,550.00 0.2970 oh Pekerja 40,000.00 11,880.00 0.0330 oh Tukang Batu 45,000.00 1,485.00 0.0330 oh Tukang Kayu 55,000.00 1,815.00 0.0330 oh Tukang Besi 50,000.00 1,650.00 0.0100 oh Kepala Tukang 60,000.00 600.00 0.0150 oh Mandor 68,000.00 1,020.00

Total : 18,450.00 49,426.20 67,876.20

VIII PEKERJAAN PENUTUP ATAP (SNI 03-3436-2002)

1 1 M2 PEKERJAAN ATAP GENTENG PLENTONG 25.0000 bh Genteng Plentong 1,300.00 32,500.00 0.1500 oh Pekerja 40,000.00 6,000.00 0.0600 oh Tukang Kayu 55,000.00 3,300.00 0.0060 oh Kepala Tukang 60,000.00 360.00 0.0080 oh Mandor 68,000.00 544.00

Total : 10,204.00 32,500.00 42,704.00

2 1 M2 PEKERJAAN ATAP GENTENG PLENTONG DI CAT 25.0000 bh Genteng Plentong Dicat 1,400.00 35,000.00 0.1500 oh Pekerja 40,000.00 6,000.00 0.0600 oh Tukang Kayu 55,000.00 3,300.00 0.0060 oh Kepala Tukang 60,000.00 360.00 0.0080 oh Mandor 68,000.00 544.00

Total : 10,204.00 35,000.00 45,204.00

3 1 M1 PASANG BUBUNGAN GENTENG PLENTONG 5.0000 bh Bubungan Plentong 6,000.00 30,000.00 8.0000 kg Semen Portland 1,220.00 9,760.00 0.0320 m3 Pasir Pasang 158,000.00 5,056.00 0.4000 oh Pekerja 40,000.00 16,000.00 0.2000 oh Tukang Kayu 55,000.00 11,000.00 0.0200 oh Kepala Tukang 60,000.00 1,200.00 0.0020 oh Mandor 68,000.00 136.00

Total : 28,336.00 44,816.00 73,152.00

1 M3 MEMBUAT DINDING BETON BERTULANG (200 KG BESI + BEKISTING)

1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (11 X 11 CM)

1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (10 X 15 CM)

Page 37: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 64 1 M2 PASANG ATAP GENTENG ASBES GELOMBANG 1.8 M X 0.92 M X 5 MM

0.7500 lbr Asbes Gelombang 1.8 mx0.92mx5mm 29,000.00 21,750.00 0.1200 kg Paku Pancing 60 x 230 20,000.00 2,400.00 0.1400 oh Pekerja 40,000.00 5,600.00 0.0700 oh Tukang Kayu 55,000.00 3,850.00 0.0070 oh Kepala Tukang Kayu 60,000.00 420.00 0.0070 oh Mandor 68,000.00 476.00

Total : 10,346.00 24,150.00 34,496.00

5 1 M1 PASANG BUBUNGAN STEL GELOMBANG 0.92 M 2.4000 lbr Bubungan Stel Gelombang 24,000.00 57,600.00 6.0000 kg Paku Skrup 3,5" 26,500.00 159,000.00 0.0840 oh Pekerja 40,000.00 3,360.00 0.1250 oh Tukang Kayu 55,000.00 6,875.00 0.0130 oh Kepala Tukang 60,000.00 780.00 0.0040 oh Mandor 68,000.00 272.00

Total : 11,287.00 216,600.00 227,887.00 6 1 M2 PEKERJAAN ATAP SIRAP

60.0000 bh Genteng Sirap 8,500.00 510,000.00 0.2000 kg Paku Biasa 1/2" - 1" 14,000.00 2,800.00 0.1660 oh Pekerja 40,000.00 6,640.00 0.2500 oh Tukang Kayu 55,000.00 13,750.00 0.0250 oh Kepala Tukang 60,000.00 1,500.00 0.0080 oh Mandor 68,000.00 544.00

Total : 22,434.00 512,800.00 535,234.00

7 1 M2 PEKERJAAN ATAP NOK SIRAP 0.4000 lbr Seng plat 3" x 6" BJLS 28 46,500.00 18,600.00 0.0600 kg Paku biasa 1/2" - 1" 14,000.00 840.00 0.0500 kg Paku biasa 2" - 5" 13,000.00 650.00 0.0040 m3 Kayu papan 3 cm 9,000,000.00 36,000.00 0.1250 oh Pekerja 40,000.00 5,000.00 0.2500 oh Tukang kayu 55,000.00 13,750.00 0.0250 oh Kepala Tukang 60,000.00 1,500.00 0.0080 oh Mandor 68,000.00 544.00

Total : 20,794.00 56,090.00 76,884.00

8 1 M2 PASANG ATAP ALANG-ALANG 3 M1 6.5000 lbr Alang - alang 12,500.00 81,250.00 0.5000 glg Tali pengikat 9,500.00 4,750.00 0.2000 oh Pekerja 40,000.00 8,000.00 0.0100 oh Mandor 68,000.00 680.00

Total : 8,680.00 86,000.00 94,680.00

9 1 M2 PEKERJAAN ATAP SENG GELOMBANG 0.7000 lbr Seng Gelombang 3" x 6" BJLS 28 42,500.00 29,750.00 0.0200 kg Paku Biasa 1/2" - 1" 14,000.00 280.00 0.1200 oh Pekerja 40,000.00 4,800.00 0.0600 oh Tukang Kayu 55,000.00 3,300.00 0.0060 oh Kepala Tukang 60,000.00 360.00 0.0060 oh Mandor 68,000.00 408.00

Total : 8,868.00 30,030.00 38,898.00

10 1 M2 PASANGAN LAPISANG ALUMINIUM FOIL 1.0500 m2 Aluminium Foil 29,000.00 30,450.00 0.1500 oh Pekerja 40,000.00 6,000.00 0.0500 oh Tukang Kayu 55,000.00 2,750.00 0.0050 oh Kepala Tukang 60,000.00 300.00 0.0080 oh Mandor 68,000.00 544.00

Total : 9,594.00 30,450.00 40,044.00

11 1 M1 PASANG NOK SENG GELOMBANG 0.3000 lbr Seng Plat 3" x 6" BJLS 28 46,500.00 13,950.00 0.0400 kg Paku biasa 1/2" - 1" 14,000.00 560.00 0.1500 oh Pekerja 40,000.00 6,000.00 0.0700 oh Tukang Kayu 55,000.00 3,850.00 0.0080 oh Kepala Tukang 60,000.00 480.00 0.0060 oh Mandor 68,000.00 408.00

Total : 10,738.00 14,510.00 25,248.00

IX PEKERJAAN LANGIT - LANGIT (SNI 2839-2008)

1

1.1000 lbr Asbes semen 47,000.00 51,700.00 0.0100 kg Paku Biasa 1/2" - 1" 14,000.00 140.00 0.0300 oh Pekerja 40,000.00 1,200.00 0.0700 oh Tukang Kayu 55,000.00 3,850.00 0.0070 oh Kepala Tukang 60,000.00 420.00 0.0040 oh Mandor 68,000.00 272.00

Total : 5,742.00 51,840.00 57,582.00

MEMASANG 1 M2 LANGIT-LANGIT ASBES SEMEN, TEBAL 4 MM, 5 MM DAN 6 MM

Page 38: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6

2 1 M2 PASANG LANGIT-LANGIT TRIPLEKS 120X240 CM/6MM 0.3750 lbr TRIPLEKS 47,000.00 17,625.00 0.0300 kg Paku Biasa 1/2" - 1" 14,000.00 420.00 0.1000 oh Pekerja 40,000.00 4,000.00 0.1000 oh Tukang Kayu 55,000.00 5,500.00 0.0100 oh Kepala Tukang 60,000.00 600.00 0.0050 oh Mandor 68,000.00 340.00

Total : 10,440.00 18,045.00 28,485.00

3 1 M2 PASANG LANGIT-LANGIT LAMBRIZIRING 0.0150 m3 Kayu Papan 9,000,000.00 135,000.00 0.0100 kg Paku Biasa 1/2" - 1" 14,000.00 140.00 0.8000 oh Pekerja 40,000.00 32,000.00 0.8000 oh Tukang Kayu 55,000.00 44,000.00 0.0800 oh Kepala Tukang 60,000.00 4,800.00 0.0400 oh Mandor 68,000.00 2,720.00

Total : 83,520.00 135,140.00 218,660.00

4 1 M1 PASANG LIST LANGIT-LANGIT KAYU PROFIL 1.0500 m1 List Kayu Profil 12,250.00 12,862.50 0.1000 kg Paku list SQ 15,840.00 1,584.00 0.0500 oh Pekerja 40,000.00 2,000.00 0.0500 oh Tukang Kayu 55,000.00 2,750.00 0.0050 oh Kepala Tukang 60,000.00 300.00 0.0030 oh Mandor 68,000.00 204.00

Total : 5,254.00 14,446.50 19,700.50

5 1 M2 PASANG LANGIT-LANGIT ASBES + RANGKA 0.0120 m3 Kamper Usuk 4/6 cm 9,000,000.00 108,000.00 0.0600 kg Paku Biasa 2" - 5" 15,840.00 950.40 1.1000 lbr Asbes 47,000.00 51,700.00 0.1800 oh Pekerja 40,000.00 7,200.00 0.3200 oh Tukang Kayu 55,000.00 17,600.00 0.0320 oh Kepala Tukang 60,000.00 1,920.00 0.0090 oh Mandor 68,000.00 612.00

Total : 27,332.00 160,650.40 187,982.40

6 1 M2 PASANG LANGIT-LANGIT GYPSUM BOARD UKURAN (1200X2400X9) MM 0.1100 kg Paku Sekrup 18,000.00 1,980.00 0.3640 lbr Gypsum Board (120x240x9) 63,500.00 23,114.00 0.1000 oh Pekerja 40,000.00 4,000.00 0.0500 oh Tukang Kayu 55,000.00 2,750.00 0.0050 oh Kepala Tukang 60,000.00 300.00 0.0050 oh Mandor 68,000.00 340.00

Total : 7,390.00 25,094.00 32,484.00

7 1 M2 PASANG LANGIT-LANGIT KALSIBOARD 4.5 MM 0.1100 kg Paku Sekrup 18,000.00 1,980.00 0.3640 lbr Kalsiboard 4.5 mm 72,000.00 26,208.00 0.1000 oh Pekerja 40,000.00 4,000.00 0.0500 oh Tukang Kayu 55,000.00 2,750.00 0.0050 oh Kepala Tukang 60,000.00 300.00 0.0050 oh Mandor 68,000.00 340.00

Total : 7,390.00 28,188.00 35,578.00

X PEKERJAAN SANITASI ( SNI 2002 )1 MEMASANG 1 BUAH KLOSET DUDUK/MONOBLOK

1.0000 bh Kloset duduk/ monoblok 1,365,000.00 1,365,000.00 6% x harga kloset Perlengkapan 81,900.00 3.3000 oh Pekerja 40,000.00 132,000.00 1.1000 oh Tukang batu 45,000.00 49,500.00 0.0010 oh Kepala Tukang 60,000.00 60.00 0.1600 oh Mandor 68,000.00 10,880.00

Total : 192,440.00 1,446,900.00 1,639,340.00

2 MEMASANG 1 BUAH KLOSET JONGKOK PORSELIN 1.0000 bh Kloset jongkok porselen 135,000.00 135,000.00 6.0000 kg Semen Portland 1,220.00 7,320.00 0.0100 m3 Pasir Pasang 158,000.00 1,580.00 1.0000 oh Pekerja 40,000.00 40,000.00 1.5000 oh Tukang batu 45,000.00 67,500.00 1.5000 oh Kepala Tukang 60,000.00 90,000.00 0.1600 oh Mandor 68,000.00 10,880.00

Total : 208,380.00 143,900.00 352,280.00

Page 39: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6

3 MEMASANG 1 BUAH URINOIR 1.0000 bh Urinoir 1,052,000.00 1,052,000.00 6% x harga Urin Perlengkapan 63,120.00 6.0000 kg Semen Portland 1,220.00 7,320.00 0.0100 m3 Pasir Pasang 158,000.00 1,580.00 1.0000 oh Pekerja 40,000.00 40,000.00 1.0000 oh Tukang batu 45,000.00 45,000.00 0.1000 oh Kepala Tukang 60,000.00 6,000.00 0.1000 oh Mandor 68,000.00 6,800.00

Total : 97,800.00 1,124,020.00 1,221,820.00

4 MEMASANG 1 BUAH WASHTAFEL KIA 1.0000 bh Washtafel 185,000.00 185,000.00 12% x harga wast Perlengkapan 22,200.00 6.0000 kg Semen Portland 1,220.00 7,320.00 0.0100 m3 Pasir Pasang 158,000.00 1,580.00 1.2000 oh Pekerja 40,000.00 48,000.00 1.4500 oh Tukang batu 45,000.00 65,250.00 0.1500 oh Kepala Tukang 60,000.00 9,000.00 0.1000 oh Mandor 68,000.00 6,800.00

Total : 129,050.00 216,100.00 345,150.00

5 MEMASANG 1 BUAH BAK MANDI FIBREGLASS, VOLUME 0,30 M3 1.0000 bh Bak Fibreglass 230,000.00 230,000.00 18% x harga wast Perlengkapan 41,400.00 1.8000 oh Pekerja 40,000.00 72,000.00 2.7000 oh Tukang batu 45,000.00 121,500.00 0.5400 oh Kepala Tukang 60,000.00 32,400.00 0.1100 oh Mandor 68,000.00 7,480.00

Total : 233,380.00 271,400.00 504,780.00

6 1.2000 m1 Pipa galvanis 38,000.00 45,600.00 35% x harga pipa Perlengkapan 13,300.00 0.0540 oh Pekerja 40,000.00 2,160.00 0.0900 oh Tukang Pipa 50,000.00 4,500.00 0.0090 oh Kepala Tukang 60,000.00 540.00 0.0270 oh Mandor 68,000.00 1,836.00

Total : 9,036.00 58,900.00 67,936.00

7 1.2000 M' Pipa galvanis 175,000.00 210,000.00 35% x harga pipa Perlengkapan 61,250.00 0.1080 Oh Pekerja 40,000.00 4,320.00 0.1800 Oh Tukang Pipa 50,000.00 9,000.00 0.0180 Oh Kepala Tukang 60,000.00 1,080.00 0.0054 Oh Mandor 68,000.00 367.20

Total : 14,767.20 271,250.00 286,017.20

8 1.2000 m1 Pipa PVC 14,870.00 17,844.00 35% x harga pipa Perlengkapan 5,204.50 0.0360 oh Pekerja 40,000.00 1,440.00 0.0600 oh Tukang Pipa 50,000.00 3,000.00 0.0060 oh Kepala Tukang 60,000.00 360.00 0.0018 oh Mandor 68,000.00 122.40

Total : 4,922.40 23,048.50 27,970.90

9 1.2000 m1 Pipa PVC 22,250.00 26,700.00 35% x harga pipa Perlengkapan 7,787.50 0.0540 oh Pekerja 40,000.00 2,160.00 0.0900 oh Tukang Pipa 50,000.00 4,500.00 0.0090 oh Kepala Tukang 60,000.00 540.00 0.0027 oh Mandor 68,000.00 183.60

Total : 7,383.60 34,487.50 41,871.10

10 1.2000 m1 Pipa PVC 56,250.00 67,500.00 35% x harga pipa Perlengkapan 19,687.50 0.0810 oh Pekerja 40,000.00 3,240.00 0.1350 oh Tukang Pipa 50,000.00 6,750.00 0.0135 oh Kepala Tukang 60,000.00 810.00 0.0041 oh Mandor 68,000.00 278.80

Total : 11,078.80 87,187.50 98,266.30

MEMASANG 1 M1 PIPA GALVANIS f 0,5" - 1 "

MEMASANG 1 M1 PIPA GALVANIS f 1,5" - 3"

MEMASANG 1 M1 PIPA PVC TYPE AW f 0,5" - 1,5"

MEMASANG 1 M1 PIPA PVC TYPE AW f 2"

MEMASANG 1 M1 PIPA PVC TYPE AW f 3" - 4"

Page 40: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6

11 1.0000 bh Kran air 18,000.00 18,000.00 0.0250 bh Seal tape 2,600.00 65.00 0.0100 oh Pekerja 40,000.00 400.00 0.1000 oh Tukang Pipa 50,000.00 5,000.00 0.0100 oh Kepala Tukang 60,000.00 600.00 0.0050 oh Mandor 68,000.00 340.00

Total : 6,340.00 18,065.00 24,405.00

XI

1 1 KG PASANG RANGKA ATAP BAJA 1.1500 kg Besi Profil WF 15,000.00 17,250.00 0.0060 oh Pekerja 40,000.00 240.00 0.0600 oh Tukang besi 50,000.00 3,000.00 0.0060 oh Kepala Tukang 60,000.00 360.00 0.0003 oh Mandor 68,000.00 20.40

Total : 3,620.40 17,250.00 20,870.40

2 1 M2 PASANG JENDELA NAKO 1.1000 m2 Rangka + Kaca Nako 117,000.00 128,700.00 10.0000 bh Paku biasa 1 cm - 2,5 cm 18,000.00 180,000.00 7.0000 m' Besi strip 8,000.00 56,000.00 0.2000 oh Pekerja 40,000.00 8,000.00 0.2000 oh Tukang besi 50,000.00 10,000.00 0.0200 oh Kepala Tukang 60,000.00 1,200.00 0.0010 oh Mandor 68,000.00 68.00

Total : 19,268.00 364,700.00 383,968.00

3 1 M1 PASANG TALANG DATAR, SENG BJLS 28 1.0500 lbr Seng plat 46,500.00 48,825.00 0.0150 kg Paku biasa 0,5" - 1" 18,000.00 270.00 0.0190 m3 Kayu papan kelas II/III 9,000,000.00 171,000.00 0.1500 oh Pekerja 40,000.00 6,000.00 0.4000 oh Tukang besi 50,000.00 20,000.00 0.0250 oh Kepala Tukang 60,000.00 1,500.00 0.0013 oh Mandor 68,000.00 88.40

Total : 27,588.40 220,095.00 247,683.40

XII PEKERJAAN KUNCI DAN KACA (SNI 2002)1 1 BH PASANG KUNCI TANAM BIASA

1.0000 bh Kunci tanam biasa 105,000.00 105,000.00 0.0100 oh Pekerja 40,000.00 400.00 0.5000 oh Tukang besi 50,000.00 25,000.00 0.0100 oh Kepala Tukang 60,000.00 600.00 0.0050 oh Mandor 68,000.00 340.00

Total : 26,340.00 105,000.00 131,340.00

2 1 PS PASANG ENGSEL PINTU 1.0000 ps Engsel pintu 27,000.00 27,000.00 0.0150 oh Pekerja 40,000.00 600.00 0.1500 oh Tukang besi 50,000.00 7,500.00 0.0150 oh Kepala Tukang 60,000.00 900.00 0.0008 oh Mandor 68,000.00 54.40

Total : 9,054.40 27,000.00 36,054.40

3 1 PS PASANG ENGSEL JENDELA KUPU-KUPU 1.0000 ps Engsel jendela 49,000.00 49,000.00 0.0100 oh Pekerja 40,000.00 400.00 0.1000 oh Tukang besi 50,000.00 5,000.00 0.0100 oh Kepala Tukang 60,000.00 600.00 0.0005 oh Mandor 68,000.00 34.00

Total : 6,034.00 49,000.00 55,034.00

4 1 BH PASANG KAIT ANGIN 1.0000 ps Kait angin 22,000.00 22,000.00 0.0150 oh Pekerja 40,000.00 600.00 0.1500 oh Tukang besi 50,000.00 7,500.00 0.0150 oh Kepala Tukang 60,000.00 900.00 0.0008 oh Mandor 68,000.00 54.40

Total : 9,054.40 22,000.00 31,054.40

5 1 BH PASANG KUNCI SLOT 1.0000 bh Kunci slot 100,000.00 100,000.00 0.0200 oh Pekerja 40,000.00 800.00 0.2000 oh Tukang besi 50,000.00 10,000.00 0.0200 oh Kepala Tukang 60,000.00 1,200.00 0.0010 oh Mandor 68,000.00 68.00

Total : 12,068.00 100,000.00 112,068.00

MEMASANG 1 BUAH KRAN f 0,75" ATAU 0,5"

PEKERJAAN BESI DAN ALUMINIUM (SNI 7393:2008)

Page 41: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6

6 1 M2 PASANG KACA, TEBAL 3 - 5 MM 1.1000 bh Kaca 102,000.00 112,200.00 0.0150 oh Pekerja 40,000.00 600.00 0.1500 oh Tukang besi 50,000.00 7,500.00 0.0150 oh Kepala Tukang 60,000.00 900.00 0.0008 oh Mandor 68,000.00 54.40

Total : 9,054.40 112,200.00 121,254.40

XIII

1 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM 11.8700 bh Keramik 30 x 30 cm 4,090.91 48,559.09 10.0000 kg Semen Portland 1,220.00 12,200.00 0.0450 m3 Pasir Pasang 158,000.00 7,110.00 1.5000 kg Semen warna/semen grouting 12,500.00 18,750.00 0.7000 oh Pekerja 40,000.00 28,000.00 0.3500 oh Tukang batu 45,000.00 15,750.00 0.0350 oh Kepala Tukang 60,000.00 2,100.00 0.0350 oh Mandor 68,000.00 2,380.00

Total : 48,230.00 86,619.09 134,849.09

2 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM 26.5000 bh Keramik 20 x 20 cm 8,600.00 227,900.00 10.4000 kg Semen Portland 1,220.00 12,688.00 0.0450 m3 Pasir Pasang 158,000.00 7,110.00 1.6200 kg Semen warna/semen grouting 12,500.00 20,250.00 0.7000 oh Pekerja 40,000.00 28,000.00 0.3500 oh Tukang batu 45,000.00 15,750.00 0.0350 oh Kepala Tukang 60,000.00 2,100.00 0.0350 oh Mandor 68,000.00 2,380.00

Total : 48,230.00 267,948.00 316,178.00

3 1 M1 PASANG PLIN KERAMIK 10 X 30 CM 3.3300 bh Keramik 30 x 30 cm 4,090.91 13,622.73 1.1400 kg Semen Portland 1,220.00 1,390.80 0.0030 m3 Pasir Pasang 158,000.00 474.00 0.1000 kg Semen warna/semen grouting 12,500.00 1,250.00 0.0900 oh Pekerja 40,000.00 3,600.00 0.0900 oh Tukang batu 45,000.00 4,050.00 0.0090 oh Kepala Tukang 60,000.00 540.00 0.0050 oh Mandor 68,000.00 340.00

Total : 8,530.00 16,737.53 25,267.53

4 1 M2 PASANG DINDING KERAMIK 20 X 20 CM 26.5000 bh Keramik 20 x 20 cm 8,600.00 227,900.00 9.3000 kg Semen Portland 1,220.00 11,346.00 0.0180 m3 Pasir Pasang 158,000.00 2,844.00 1.9400 kg Semen warna/semen grouting 12,500.00 24,250.00 0.9000 oh Pekerja 40,000.00 36,000.00 0.4500 oh Tukang batu 45,000.00 20,250.00 0.0450 oh Kepala Tukang 60,000.00 2,700.00 0.0450 oh Mandor 68,000.00 3,060.00

Total : 62,010.00 266,340.00 328,350.00

5 1 M2 PASANG BATU ALAM 30 X 30 CM 11.8700 bh Batu alam 30 x 30 cm 6,318.44 74,999.88 10.0000 kg Semen Portland 160.00 1,600.00 0.0450 m3 Pasir Pasang 68,000.00 3,060.00 1.5000 kg Semen warna/semen grouting 34,000.00 51,000.00 0.7000 oh Pekerja 1,220.00 854.00 0.3500 oh Tukang batu 45,000.00 15,750.00 0.0350 oh Kepala Tukang 12,500.00 437.50 0.0350 oh Mandor 68,000.00 2,380.00

Total : 19,421.50 130,659.88 150,081.38

6 1 M1 PASANG PLIN KAYU 2 X 10 CM 0.0030 m3 Papan Kayu Kelas II 9,000,000.00 27,000.00 0.0500 kg Paku sekrup 3,5' 26,500.00 1,325.00 0.1200 oh Pekerja 40,000.00 4,800.00 0.1200 oh Tukang kayu 55,000.00 6,600.00 0.0120 oh Kepala Tukang 60,000.00 720.00 0.0060 oh Mandor 68,000.00 408.00

Total : 12,528.00 28,325.00 40,853.00

XIV PEKERJAAN PENGECATAN (SNI 2002)1 1 M2 PENGECATAN BIDANG KAYU BARU (1 LAPIS PLAMIR,

1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP) 0.2000 kg Cat meni 22,000.00 4,400.00 0.1500 kg Dempul 29,000.00 4,350.00

PEK. PENUTUP LANTAI DAN DINDING (SNI 7395:2008)

Page 42: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6 0.1700 kg Cat dasar 43,600.00 7,412.00 0.2600 kg Cat Penutup 2x 55,000.00 14,300.00

Page 43: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6 0.0700 oh Pekerja 40,000.00 2,800.00 0.0090 oh Tukang cat 40,000.00 360.00 0.0060 oh Kepala Tukang 60,000.00 360.00 0.0025 oh Mandor 68,000.00 170.00

Total : 3,690.00 30,462.00 34,152.00

2 1 M2 PENGECATAN BIDANG KAYU DENGAN VERNIS 0.1500 kg Vernis 59,000.00 8,850.00 0.0500 kg Dempul 29,000.00 1,450.00 0.1000 lbr Amplas 4,100.00 410.00 0.0100 bh Kuas 16,800.00 168.00 0.1600 oh Pekerja 40,000.00 6,400.00 0.1600 oh Tukang cat 40,000.00 6,400.00 0.0160 oh Kepala Tukang 60,000.00 960.00 0.0025 oh Mandor 68,000.00 170.00

Total : 13,930.00 10,878.00 24,808.00 3 1 M2 PENGECATAN TEMBOK BARU (1 LAPIS PLAMIR,

1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP) 0.1000 kg Plamir 30,000.00 3,000.00 0.1000 kg Cat dasar 43,600.00 4,360.00 0.2600 kg Cat Penutup 2x 20,600.00 5,356.00 0.0200 oh Pekerja 40,000.00 800.00 0.0630 oh Tukang cat 40,000.00 2,520.00 0.0063 oh Kepala Tukang 60,000.00 378.00 0.0025 oh Mandor 68,000.00 170.00

Total : 3,868.00 12,716.00 16,584.00

4 1 M2 PENGECATAN TEMBOK LAMA (1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP) 0.1200 kg Cat dasar 43,600.00 5,232.00 0.1800 kg Cat Penutup 2x 20,600.00 3,708.00 0.0280 oh Pekerja 40,000.00 1,120.00 0.0420 oh Tukang cat 40,000.00 1,680.00 0.0042 oh Kepala Tukang 60,000.00 252.00 0.0025 oh Mandor 68,000.00 170.00

Total : 3,222.00 8,940.00 12,162.00

5 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI 0.1000 kg Meni besi 22,000.00 2,200.00 0.0100 lbr Kuas 16,800.00 168.00 0.0200 oh Pekerja 40,000.00 800.00 0.2000 oh Tukang cat 40,000.00 8,000.00 0.0200 oh Kepala Tukang 60,000.00 1,200.00 0.0100 oh Mandor 68,000.00 680.00

Total : 10,680.00 2,368.00 13,048.00

6 1 M2 PENGECATAN PERMUKAAN BAJA, 1 LAPIS DENGAN CAT BESI 0.3000 kg Cat besi 70,500.00 21,150.00 0.0060 oh Pekerja 40,000.00 240.00 0.0600 oh Tukang cat 40,000.00 2,400.00 0.0120 oh Kepala Tukang 60,000.00 720.00 0.0060 oh Mandor 68,000.00 408.00

Total : 3,768.00 21,150.00 24,918.00

7 1 M2 PELABURAN BIDANG KAYU DENGAN POLITUR 0.5220 ltr Politur 47,000.00 24,534.00 2.0000 lbr Amplas 4,100.00 8,200.00 0.0600 oh Pekerja 40,000.00 2,400.00 0.0600 oh Tukang cat 40,000.00 2,400.00 0.0160 oh Kepala Tukang 60,000.00 960.00 0.0025 oh Mandor 68,000.00 170.00

Total : 5,930.00 32,734.00 38,664.00

XV PEKERJAAN TETEMPELAN STYLE BALI

1 1 M2 PASANGAN BATA GOSOK 2 MUKA 110.0000 bh Bata Gosok 1,980.00 217,800.00 8.4000 kg Semen 50 Kg 1,220.00 10,248.00

Upah Kerja ( Lumpsum) 270,000.00 270,000.00 Total : 270,000.00 228,048.00 498,048.00

2 1 M2 PASANGAN PARAS KEROBOKAN 1 MUKA 13.7500 bh Paras Kerobokan 9,500.00 130,625.00 8.4000 kg Semen 50 Kg 1,220.00 10,248.00

Upah Kerja ( Lumpsum) 145,000.00 145,000.00 Total : 145,000.00 140,873.00 285,873.00

3 1 M2 PASANGAN BATA GOSOK 1 MUKA 55.0000 bh Paras Kerobokan 1,980.00 108,900.00 4.2000 kg Semen 50 Kg 1,220.00 5,124.00

Upah Kerja ( Lumpsum) 145,000.00 145,000.00 Total : 145,000.00 114,024.00 259,024.00

Page 44: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6

4 1 M2 PASANGAN PARAS 1 MUKA 18.3333 bh Batu paras 12,000.00 220,000.00 4.2000 kg Semen 50 Kg 1,220.00 5,124.00

Upah Kerja ( Lumpsum) 145,000.00 145,000.00 Total : 145,000.00 225,124.00 370,124.00

5 1 M2 PASANGAN PARAS + BATA GOSOK 1 MUKA 55.0000 bh Bata gosok 1,980.00 108,900.00 4.4917 bh Batu paras 12,000.00 53,900.00 5.2500 kg Semen 50 Kg 1,220.00 6,405.00

Upah Kerja ( Lumpsum) 145,000.00 145,000.00 Total : 145,000.00 169,205.00 314,205.00

6 1 M2 PASANGAN BATA GOSOK DIUKIR 55.0000 bh Bata gosok 1,980.00 108,900.00 4.2000 kg Semen 50 Kg 1,220.00 5,124.00

Upah Kerja ( Lumpsum) 288,500.00 288,500.00 Total : 288,500.00 114,024.00 402,524.00

7 1 M2 PASANGAN PARAS DIUKIR 18.3333 bh Batu paras 12,000.00 220,000.00 4.2000 kg Semen 50 Kg 1,220.00 5,124.00

Upah Kerja ( Lumpsum) 288,500.00 288,500.00 Total : 288,500.00 225,124.00 513,624.00

8 1 M2 PASANGAN PARAS + BATA GOSOK DIUKIR 55.0000 bh Bata gosok 1,980.00 108,900.00 4.4917 bh Batu paras 12,000.00 53,900.00 5.2500 kg Semen 50 Kg 1,220.00 6,405.00

Upah Kerja ( Lumpsum) 280,000.00 280,000.00 Total : 280,000.00 169,205.00 449,205.00

XVI PEKERJAAN LANDSCAPE

1 1 M2 PASANGAN PAVING BETON 10/20 CM TEBAL 6 CM K 225 1.0000 m2 Paving 10 x 20 cm tebal 8 cm K225 55,000.00 55,000.00 0.2500 oh Tukang Batu 45,000.00 11,250.00 0.0250 oh Kepala Tukang 60,000.00 1,500.00 0.5000 oh Pekerja 40,000.00 20,000.00 0.0250 oh Mandor 68,000.00 1,700.00

Total : 34,450.00 55,000.00 89,450.00 2 Paving 10 x 20 cm tebal 6 cm K350 63,000.00 34,450.00 63,000.00 97,450.00 4 Paving 10 x 20 cm tebal 8 cm K225 63,000.00 34,450.00 63,000.00 97,450.00 5 Paving 10 x 20 cm tebal 8 cm K350 68,000.00 34,450.00 68,000.00 102,450.00 5 Paving 10 x 20 cm tebal 8 cm K425 75,500.00 34,450.00 75,500.00 109,950.00 7 Paving 20 x 20 cm tebal 6 cm K225 55,000.00 34,450.00 55,000.00 89,450.00 8 Paving 20 x 20 cm tebal 6 cm K350 63,000.00 34,450.00 63,000.00 97,450.00

10 Paving 20 x 20 cm tebal 8 cm K225 63,000.00 34,450.00 63,000.00 97,450.00 11 Paving 20 x 20 cm tebal 8 cm K350 68,000.00 34,450.00 68,000.00 102,450.00 12 Paving 20 x 20 cm tebal 8 cm K425 75,500.00 34,450.00 75,500.00 109,950.00 14 Paving 20 x 20 cm tebal 10 cm K225 66,500.00 34,450.00 66,500.00 100,950.00 15 Paving 20 x 20 cm tebal 10 cm K350 76,000.00 34,450.00 76,000.00 110,450.00 16 Paving 20 x 20 cm tebal 10 cm K425 85,000.00 34,450.00 85,000.00 119,450.00 18 Paving Tiga Berlian tebal 6 cm K225 53,000.00 34,450.00 53,000.00 87,450.00

19 1 M2 PASANGAN GRASS BLOCK 1.0000 m2 Grass Block 55,000.00 55,000.00 0.0690 m3 Pasir Urug 130,000.00 8,970.00 0.5000 oh Tukang Batu 45,000.00 22,500.00 0.0500 oh Kepala Tukang 60,000.00 3,000.00 1.0000 oh Pekerja 40,000.00 40,000.00 0.0500 oh Mandor 68,000.00 3,400.00

Total : 68,900.00 63,970.00 132,870.00

20 1 M2 PASANGAN KORAL SIKAT 1.2000 zak Koral Sikat 35,000.00 42,000.00 9.2800 zak Semen 1,220.00 11,321.60 0.2000 m3 Pasir pasang 158,000.00 31,600.00 0.2500 oh Tukang Batu 45,000.00 11,250.00 0.0100 oh Kepala Tukang 60,000.00 600.00 0.6250 oh Pekerja 40,000.00 25,000.00 0.0310 oh Mandor 68,000.00 2,108.00

Total : 38,958.00 84,921.60 123,879.60 21 1 M1 KANSTEIN BULAT (50 x 30 x 10 ) CM K225

1.0000 m1 Kanstein Bulat(P:50,T:30,La:10,Lb:16 cm K225 69,000.00 69,000.00 0.4500 zak Semen 50 Kg 1,220.00 549.00 0.0023 m3 Pasir Pasang 158,000.00 363.40 0.3500 oh Tukang Batu 45,000.00 15,750.00 0.0350 oh Kepala Tukang 60,000.00 2,100.00 0.9500 oh Pekerja 40,000.00 38,000.00 0.0950 oh Mandor 68,000.00 6,460.00

Page 45: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6Total : 62,310.00 69,912.40 132,222.40

22 Kanstein Jumbo (P:50,L:15,T:30 cm K225) 55,000.00 62,310.00 97,921.60 160,231.60 23 Kanstein Segi Lima Jumbo (P:50,L:15, T:40 cm K225) 69,000.00 62,310.00 111,921.60 174,231.60

Page 46: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIANHARGA HARGA HARGA HARGASATUAN UPAH BAHAN JUMLAH

(Rp) (Rp) (Rp) (Rp)

1 2 3 4 5 6

24 1 M2 PENGECATAN KANSTEIN 0.2840 kg Cat 70,500.00 20,022.00 0.0710 kg Thiner 12,000.00 852.00 0.0300 oh Tukang Cat 40,000.00 1,200.00 0.0030 oh Kep. Tukang 60,000.00 180.00 0.1500 oh Pekerja 40,000.00 6,000.00 0.0150 oh Mandor 68,000.00 1,020.00

Total : 8,400.00 20,874.00 29,274.00

XVII PEKERJAAN ELEKTRIKAL

1 1 TITIK INSTALASI STOP KONTAK, LAMPU, EXHAUST FAN DAN CEILING FAN 8.0000 m1 Kabel NYM 3 x 2.5 mm ex. Supreme 12,000.00 96,000.00 3.0000 bt Pipa Clipsal 20 mm hitam 12,000.00 36,000.00 2.0000 bh Tee dos clipsal 20 mm hitam 7,000.00 14,000.00 15.0000 bj Klem clipsal 20 mm hitam 750.00 11,250.00 3.0000 bj Sock clipsal 20 mm hitam 2,000.00 6,000.00 1.0000 bj Inbow dos plastik clipsal E 157 P 10,000.00 10,000.00 1.0000 ttk Biaya pasang 25,000.00 25,000.00

Total : 25,000.00 173,250.00 198,250.00

2 1 TITIK INSTALASI AC 10.0000 m1 Kabel NYM 3 x 2.5 mm ex. Supreme 12,000.00 120,000.00 3.0000 bt Pipa Clipsal 20 mm hitam 12,000.00 36,000.00 1.0000 bh Tee dos clipsal 20 mm hitam 7,000.00 7,000.00 15.0000 bj Klem clipsal 20 mm hitam 750.00 11,250.00 4.0000 bj Sock clipsal 20 mm hitam 2,000.00 8,000.00 1.0000 bj Inbow dos plastik clipsal E 157 P 10,000.00 10,000.00 1.0000 m1 Pipa flexible clipsal 20 mm hitam 10,500.00 10,500.00 1.0000 ttk Biaya pasang 25,000.00 25,000.00 25,000.00

Total : 25,000.00 227,750.00 252,750.00

3 1 TITIK INSTALASI TELEPHONE 25.0000 m1 Kabel telephone 4,000.00 100,000.00 8.0000 bt Pipa Clipsal 20 mm putih 12,000.00 96,000.00 1.0000 bh Tee dos clipsal 20 mm putih 7,000.00 7,000.00 25.0000 bj Klem clipsal 20 mm putih 750.00 18,750.00 5.0000 bj Sock clipsal 20 mm putih 2,000.00 10,000.00 1.0000 bj Inbow dos plastik clipsal E 157 P 10,000.00 10,000.00 1.0000 ttk Biaya pasang 25,000.00 25,000.00

Total : 25,000.00 241,750.00 266,750.00

4 1 TITIK INSTALASI MATV 20.0000 m1 Coaxial cable 5C-75 ohm commscof 6,000.00 120,000.00 6.0000 bt Pipa Clipsal 20 mm putih 12,000.00 72,000.00 2.0000 bh Tee dos clipsal 20 mm putih 7,000.00 14,000.00 20.0000 bj Klem clipsal 20 mm putih 750.00 15,000.00 6.0000 bj Sock clipsal 20 mm putih 2,000.00 12,000.00 1.0000 bj Inbow dos plastik clipsal E 157 P 10,000.00 10,000.00 1.0000 ttk Biaya pasang 25,000.00 25,000.00

Total : 25,000.00 243,000.00 268,000.00

Kepala Dinas Cipta KaryaKabupaten Badung

Ir. Ni Luh Putu Dessy Dharmayanty, M.TPembina Tk. I

NIP. 196110101994032001

Page 47: Analisa Sni 2002 & 2008.Dck Januari 2013

REKAPITULASI DAFTAR HARGA SATUAN PEKERJAANBULAN JANUARI TAHUN 2013

NO URAIAN PEKERJAAN HARGA

1 2 3

I PEKERJAAN PERSIAPAN (SNI 03-2835-2002)

1 1 M1 PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 METER Rp. 324,975.00

2 1 M1 PENGUKURAN DAN PEMASANGAN BOWPLANK Rp. 88,700.00

3 1 M2 PEMBUATAN KANTOR SEMENTARA, DENGAN LANTAI PLESTERAN Rp. 1,052,105.00

4 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT Rp. 798,890.00

5 1 M2 PEMBUATAN RUMAH JAGA/KONSTRUKSI KAYU Rp. 924,750.00

6 1 M2 MEMBERSIHKAN LAPANGAN DAN PERATAAN Rp. 7,400.00

7 1 M2 PEMBUATAN BEDENG BURUH Rp. 807,440.00

8 1 M2 PEMBUATAN BAK ADUKAN UKURAN (40X50X20) CM Rp. 191,642.00

9 1 M2 PEMBUATAN STEGGER DARI BAMBU Rp. 32,399.00

10 1 M2 PEMBUATAN JALAN SEMENTARA Rp. 85,480.00

11 1 M3 BONGKARAN BETON BERTULANG Rp. 289,324.00

12 1 M3 BONGKARAN DINDING TEMBOK BATA MERAH Rp. 268,924.00

II PEKERJAAN TANAH (SNI 2835 : 2008)

1 1 M3 GALIAN TANAH BIASA DALAM 1 METER Rp. 31,700.00

2 1 M3 GALIAN TANAH BIASA DALAM 2 METER Rp. 39,060.00

3 1 M3 GALIAN TANAH BIASA DALAM 3 METER Rp. 46,556.00

4 1 M3 GALIAN TANAH KERAS DALAM 1METER Rp. 42,176.00

5 1 M3 GALIAN TANAH CADAS DALAM 1 METER Rp. 64,080.00

6 1 M3 GALIAN TANAH LUMPUR DALAM 1 METER Rp. 51,060.00

7 1 M2 PEKERJAAN STRIPPING SETINGGI 1 METER Rp. 2,340.00

8 1 M3 PEMBUANGAN TANAH SEJAUH 15 METER Rp. 13,880.00

9 1 M3 URUGAN KEMBALI Rp. -

10 1 M3 PEMADATAN TANAH ( Per 20 Cm ) Rp. 23,400.00

11 1 M3 URUGAN PASIR Rp. 168,680.00

12 1 M3 PEMASANGAN LAPISAN IJUK TEBAL 10 CM Rp. 22,020.00

13 1 M3 URUGAN SIRTU PADAT Untuk Peninggian Lantai Bangunan Rp. 161,700.00

14 1 M3 URUGAN TANAH PILIHAN DIPADATKAN Rp. 119,400.00

15 1 M3 URUGAN LIMESTONE PADAT Rp. 113,700.00

III PEKERJAAN PONDASI (SNI 2836 : 2008)

1 1 M3 BATU KALI CAMP. 1 PC : 3 PS Rp. 642,420.00

2 1 M3 BATU KALI CAMP. 1 PC : 4 PS Rp. 600,370.00

3 1 M3 BATU KALI CAMP. 1 PC : 5 PS Rp. 571,222.00

4 1 M3 BATU KALI CAMP. 1 PC : 6 PS Rp. 550,728.00

5 1 M3 BATU KALI CAMP. 1 PC : 8 PS Rp. 522,642.00

6 1 M3 PASANGAN PONDASI SIKLOP, 40% BATU KALI Rp. 1,728,144.00

7 1 M3 PASANGAN PONDASI SUMURAN DIAMETER 1 M Rp. 586,124.00

8 1 M3 PASANGAN BATU KOSONG Rp. 325,902.00

IV PEKERJAAN DINDING (SNI 6897 : 2008)

1 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 2 PS Rp. 283,950.00

2 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 3 PS Rp. 272,817.00

3 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 4 PS Rp. 265,325.00

4 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 5 PS Rp. 261,440.00

Page 48: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIAN PEKERJAAN HARGA

1 2 3

5 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 6 PS Rp. 260,086.00

6 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 2 PS Rp. 138,243.00

7 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 3 PS Rp. 132,971.40

8 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 4 PS Rp. 129,944.00

9 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 5 PS Rp. 128,039.60

10 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 6 PS Rp. 127,012.40

11 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 8 PS Rp. 124,950.00

12 1 M2 PASAANGAN BATU ALAM 30 X 30 CAMP 1PC : 2PS Rp. 150,081.38

13 1 M2 PASANGAN DINDING HOLLOWBLOCK (HB. 10) Rp. 76,268.65

14 1 M2 PASANGAN DINDING HOLLOWBLOCK (HB. 10) TANPA BESI Rp. 59,836.00

15 1 M2 PASANGAN DINDING Terawang/Roster (12 x 11 x 24) CM Rp. 1,537,070.00

16 1 M2 PASANGAN DINDING BEDEG, RANGKA KAYU Rp. 147,842.00

V PEKERJAAN PLESTERAN (SNI 2837 : 2008)

1 1 M2 PLESTERAN CAMP. 1 PC : 1 PS TEBAL 15 MM Rp. 42,112.88

2 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 15 MM Rp. 36,303.28

3 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 15 MM Rp. 33,790.72

4 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 15 MM Rp. 32,074.80

5 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 15 MM Rp. 31,102.48

6 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 15 MM Rp. 30,323.52

7 1 M2 PLESTERAN CAMP. 1 PC : 8 PS TEBAL 15 MM Rp. 29,468.32

8 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 20 MM Rp. 48,593.04

9 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 20 MM Rp. 45,242.96

10 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 20 MM Rp. 42,902.40

11 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 20 MM Rp. 41,658.64

12 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 20 MM Rp. 40,567.36

13 1 M2 PLESTERAN SKONING 1 PC : 2 PS, TEBAL 10 MM Rp. 26,536.00

14 1 M2 PLESTERAN CIPRAT 1 PC : 2 PS Rp. 24,338.40

15 1 M2 FINISHING SIAR PASANGAN DINDING BATA MERAH (=20 M') Rp. 14,190.76

16 1 M2 FINISHING SIAR PASANGAN DINDING CONBLOCK EKSPOSE (= 8 M') Rp. 6,839.00

17 1 M2 FINISHING SIAR PASANGAN BATU KALI ADUKAN 1PC : 2 PS Rp. 30,300.80

18 1 M2 PEKERJAAN ACIAN Rp. 9,245.00

VI PEKERJAAN KAYU (SNI 3434 : 2008)

1 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS I Rp. 10,744,800.00

2 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS II/III Rp. 7,388,400.00

3 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP STANDAR KAYU KELAS II Rp. 439,974.00

4 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP SEDERHANA KAYU KELAS III Rp. 319,974.00

5 MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL KAYU KELAS I/II Rp. 592,650.00

6 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA, KAYU KELAS I/II Rp. 400,870.00

7 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA JALUSI, KAYU KELAS I/II Rp. 808,650.00 8

Rp. 505,070.00 9

Rp. 465,190.00 10 MEMASANG 1 M2 JALUSI KUSEN, KAYU KELAS I/II Rp. 713,680.00 11 MEMBUAT 1 M2 TEAKWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS I Rp. 474,190.00 12

Rp. 512,540.00

MEMBUAT 1 M2 DAUN PINTU PLYWOOD RANGKAP RANGKA TERTUTUP, KAYU KELAS II (Lebar Sampai 90 Cm)

MEMBUAT 1 M2 DAUN PINTU PLYWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS I/II

MEMBUAT 1 M2 TEAKWOOD RANGKAP LAPIS FORMIKA RANGKA EXPOSE, KAYU KELAS II

Page 49: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIAN PEKERJAAN HARGA

1 2 3

13

Rp. 10,234,000.00

14 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA EXPOSE, KAYU KELAS I Rp. 11,675,280.00

15 MEMASANG 1 M3 KONSTRUKSI GORDENG, KAYU KELAS II Rp. 9,835,360.00

16 MEMASANG 1 M2 RANGKA ATAP GENTENG KERAMIK, KAYU KELAS II Rp. 79,340.00

17 MEMASANG 1 M2 RANGKA ATAP GENTENG BETON, KAYU KELAS II Rp. 102,740.00

18 MEMASANG 1 M2 RANGKA ATAP SIRAP, KAYU KELAS II Rp. 1,384,828.00

19 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (50 X 100), KAYU KELAS II/III Rp. 78,400.00

20 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (60 X 60) CM, KAYU KELAS II/III Rp. 79,380.00

21 MEMASANG 1 M' LISPLANK UKURAN (3 X 20) CM, KAYU KELAS I/II Rp. 115,140.00

22 MEMASANG 1 M' LISPLANK UKURAN (3 X 30) CM, KAYU KELAS I/II Rp. 116,240.00

23 MEMASANG 1 M2 RANGKA DINDING PEMISAH (60 X 120) CM, KAYU KELAS II/III Rp. 268,494.00

24 Rp. 323,654.00

25 Rp. 327,200.00

26 MEMASANG 1 M2 LAMBRIZIRING DARI PAPAN KAYU KELAS I Rp. 202,940.00

27 MEMASANG 1 M2 LAMBRIZIRING DARI PLYWOOD UKURAN (120 X 240) CM Rp. 25,173.00

VII PEKERJAAN BETON ( SNI 7394:2008)

1 MEMBUAT 1 M³ BETON MUTU f'C= 7,4 Mpa (K100), Slump (12 ± 2)cm, w/c = 0,87 Rp. 572,428.40

2 MEMBUAT 1 M³ BETON MUTU f'C= 9,8 Mpa (K125), Slump (12 ± 2)cm, w/c = 0,78 Rp. 604,882.96

3 MEMBUAT 1 M³ BETON MUTU f'C= 12,2 Mpa (K150), Slump (12 ± 2)cm, w/c = 0,72 Rp. 630,485.32

4 MEMBUAT 1 M³ BETON MUTU f'C= 14,5 Mpa (K175), Slump (12 ± 2)cm, w/c = 0,66 Rp. 660,608.71

5 MEMBUAT 1 M³ BETON MUTU f'C= 16,9 Mpa (K200), Slump (12 ± 2)cm, w/c = 0,61 Rp. 689,593.30

6 MEMBUAT 1 M³ BETON MUTU f'C= 19,3 Mpa (K225), Slump (12 ± 2)cm, w/c = 0,58 Rp. 710,931.31

7 MEMBUAT 1 M³ BETON MUTU f'C= 21,7 Mpa (K250), Slump (12 ± 2)cm, w/c =0,56 Rp. 725,446.33

8 MEMBUAT 1 M³ BETON MUTU f'C= 24,0 Mpa (K275), Slump (12 ± 2)cm, w/c =0,53 Rp. 750,276.98

9 MEMBUAT 1 M³ BETON MUTU f'C= 26,4 Mpa (K300), Slump (12 ± 2)cm, w/c =0,52 Rp. 758,051.90

10 MEMBUAT 1 M³ BETON MUTU f'C= 28,8 Mpa (K325), Slump (12 ± 2)cm, w/c =0,49 Rp. 787,275.24

11 MEMBUAT 1 M³ BETON MUTU f'C= 31,2 Mpa (K350), Slump (12 ± 2)cm, w/c =0,48 Rp. 797,397.57

12 PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR Rp. 97,875.50

13 1 M2 PASANG BEKISTING UNTUK PONDASI Rp. 143,828.00

14 1 M2 PASANG BEKISTING UNTUK SLOOF Rp. 143,828.00

15 1 M2 PASANG BEKISTING UNTUK KOLOM Rp. 463,899.00

16 1 M2 PASANG BEKISTING UNTUK BALOK Rp. 481,899.00

17 1 M2 PASANG BEKISTING UNTUK LANTAI Rp. 823,899.00

18 1 M2 PASANG BEKISTING UNTUK DINDING Rp. 566,899.00

19 1 M2 PASANG BEKISTING UNTUK TANGGA Rp. 438,149.00

20 1 M2 PASANG JEMBATAN UNTUK PENGECORAN BETON Rp. 128,394.00

21 1 M3 MEMBUAT PONDASI BETON BERTULANG (150 KG BESI + BEKISTING) Rp. 2,890,414.00

22 1 M3 MEMBUAT SLOOF BETON BERTULANG (200 KG + BEKISTING) Rp. 3,584,229.00

23 1 M3 MEMBUAT KOLOM BETON BERTULANG (300 KG BESI + BEKISTING) Rp. 7,889,824.00

24 1 M3 MEMBUAT BALOK BETON BERTULANG (200 KG BESI + BEKISTING) Rp. 6,211,159.00

25 1 M3 MEMBUAT PLAT BETON BERTULANG (150 KG BESI + BEKISTING Rp. 7,010,307.50

26 1 M3 MEMBUAT DINDING BETON BERTULANG (150 KG BESI + BEKISTING) Rp. 6,285,914.00

27 1 M3 MEMBUAT DINDING BETON BERTULANG (200 KG BESI + BEKISTING) Rp. 5,604,979.00

28 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (11 X 11 CM) Rp. 49,559.00

29 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (10 X 15 CM) Rp. 67,876.20

MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KELAS I,II,III Bentang 6 M'

MEMASANG 1 M2 RANGKA DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA KAYU KELAS II

MEMASANG 1 M2 RANGKA DINDING PEMISAH PLYWOOD RANGKAP, RANGKA KAYU KELAS II

Page 50: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIAN PEKERJAAN HARGA

1 2 3

30 1 M3 PASANGAN PONDASI SIKLOP, 40% BATU KALI Rp. 1,728,144.00

31 1 M3 PASANGAN PONDASI SUMURAN DIAMETER 1 M Rp. 586,124.00

32 1 M3 PASANGAN BATU KOSONG Rp. 325,902.00

33 1 M1 Pembuatan Tiang Pancang 35 cm x 35 cm Beton Bertulang Rp. 526,201.50

34 1 M1 Pembuatan Tiang Pancang 40 cm x 40 cm Beton Bertulang Rp. 668,329.00

VIII PEKERJAAN PENUTUP ATAP (SNI 03-3436-2002)

1 1 M2 PEKERJAAN ATAP GENTENG PLENTONG Rp. 42,704.00

2 1 M2 PEKERJAAN ATAP GENTENG PLENTONG DI CAT Rp. 45,204.00

3 1 M1 PASANG BUBUNGAN GENTENG PLENTONG Rp. 73,152.00

4 1 M2 PASANG ATAP GENTENG ASBES GELOMBANG 1.8 M X 0.92 M X 5 MM Rp. 34,496.00

5 1 M1 PASANG BUBUNGAN STEL GELOMBANG 0.92 M Rp. 227,887.00

6 1 M2 PEKERJAAN ATAP SIRAP Rp. 535,234.00

7 1 M2 PEKERJAAN ATAP NOK SIRAP Rp. 76,884.00

8 1 M2 PASANG ATAP ALANG-ALANG 3 M1 Rp. 94,680.00

9 1 M2 PEKERJAAN ATAP SENG GELOMBANG Rp. 38,898.00

10 1 M2 PASANGAN LAPISANG ALUMINIUM FOIL Rp. 40,044.00

11 1 M1 PASANG NOK SENG GELOMBANG Rp. 25,248.00

IX PEKERJAAN LANGIT - LANGIT (SNI 2839-2008)

1 MEMASANG 1 M2 LANGIT-LANGIT ASBES SEMEN, TEBAL 4 MM, 5 MM DAN 6 MM Rp. 57,582.00

2 1 M2 PASANG LANGIT-LANGIT TRIPLEKS 120X240 CM/6MM Rp. 28,485.00

3 1 M2 PASANG LANGIT-LANGIT LAMBRIZIRING Rp. 218,660.00

4 1 M1 PASANG LIST LANGIT-LANGIT KAYU PROFIL Rp. 19,700.50

5 1 M2 PASANG LANGIT-LANGIT ASBES + RANGKA Rp. 187,982.40

6 1 M2 PASANG LANGIT-LANGIT GYPSUM BOARD UKURAN (1200X2400X9) MM Rp. 32,484.00

7 1 M2 PASANG LANGIT-LANGIT KALSIBOARD 4.5 MM Rp. 35,578.00

X PEKERJAAN SANITASI ( SNI 2002 )

1 MEMASANG 1 BUAH KLOSET DUDUK/MONOBLOK Rp. 1,639,340.00

2 MEMASANG 1 BUAH KLOSET JONGKOK PORSELIN Rp. 352,280.00

3 MEMASANG 1 BUAH URINOIR Rp. 1,221,820.00

4 MEMASANG 1 BUAH WASHTAFEL KIA Rp. 345,150.00

5 MEMASANG 1 BUAH BAK MANDI FIBREGLASS, VOLUME 0,30 M3 Rp. 504,780.00

6 MEMASANG 1 M1 PIPA GALVANIS f 0,5" - 1 " Rp. 67,936.00

7 MEMASANG 1 M1 PIPA GALVANIS f 1,5" - 3" Rp. 286,017.20

8 MEMASANG 1 M1 PIPA PVC TYPE AW f 0,5" - 1,5" Rp. 27,970.90

9 MEMASANG 1 M1 PIPA PVC TYPE AW f 2" Rp. 41,871.10

10 MEMASANG 1 M1 PIPA PVC TYPE AW f 3" - 4" Rp. 98,266.30

11 MEMASANG 1 BUAH KRAN f 0,75" ATAU 0,5" Rp. 24,405.00

XI PEKERJAAN BESI DAN ALUMINIUM (SNI 7393:2008)

1 1 KG PASANG RANGKA ATAP BAJA Rp. 20,870.40

2 1 M2 PASANG JENDELA NAKO Rp. 383,968.00

3 1 M1 PASANG TALANG DATAR, SENG BJLS 28 Rp. 247,683.40

XII PEKERJAAN KUNCI DAN KACA (SNI 2002)

1 1 BH PASANG KUNCI TANAM BIASA Rp. 131,340.00

2 1 PS PASANG ENGSEL PINTU Rp. 36,054.40

Page 51: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIAN PEKERJAAN HARGA

1 2 3

3 1 PS PASANG ENGSEL JENDELA KUPU-KUPU Rp. 55,034.00

4 1 BH PASANG KAIT ANGIN Rp. 31,054.40

5 1 BH PASANG KUNCI SLOT Rp. 112,068.00

6 1 M2 PASANG KACA, TEBAL 3 - 5 MM Rp. 121,254.40

XIII PEK. PENUTUP LANTAI DAN DINDING (SNI 7395:2008)

1 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM Rp. 134,849.09

2 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM Rp. 316,178.00

3 1 M1 PASANG PLIN KERAMIK 10 X 30 CM Rp. 25,267.53

4 1 M2 PASANG DINDING KERAMIK 20 X 20 CM Rp. 328,350.00

5 1 M1 PASANG PLIN KAYU 2 X 10 CM Rp. 40,853.00

XIV PEKERJAAN PENGECATAN (SNI 2002)

1 1 M2 PENGECATAN BIDANG KAYU BARU (1 LAPIS PLAMIR, Rp. 34,152.00

1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)

2 1 M2 PENGECATAN BIDANG KAYU DENGAN VERNIS Rp. 24,808.00

3 1 M2 PENGECATAN TEMBOK BARU (1 LAPIS PLAMIR, Rp. 16,584.00

1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)

4 1 M2 PENGECATAN TEMBOK LAMA (1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP Rp. 12,162.00

5 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI Rp. 13,048.00

6 1 M2 PENGECATAN PERMUKAAN BAJA, 1 LAPIS DENGAN CAT BESI Rp. 24,918.00

7 1 M2 PELABURAN BIDANG KAYU DENGAN POLITUR Rp. 38,664.00

Page 52: Analisa Sni 2002 & 2008.Dck Januari 2013

NO URAIAN PEKERJAAN HARGA

1 2 3

XV PEKERJAAN TETEMPELAN STYLE BALI

1 1 M2 PASANGAN BATA GOSOK 2 MUKA Rp. 498,048.00

2 1 M2 PASANGAN PARAS KEROBOKAN 1 MUKA Rp. 285,873.00

3 1 M2 PASANGAN BATA GOSOK 1 MUKA Rp. 259,024.00

4 1 M2 PASANGAN PARAS 1 MUKA Rp. 370,124.00

5 1 M2 PASANGAN PARAS + BATA GOSOK 1 MUKA Rp. 314,205.00

6 1 M2 PASANGAN BATA GOSOK DIUKIR Rp. 402,524.00

7 1 M2 PASANGAN PARAS DIUKIR Rp. 513,624.00

8 1 M2 PASANGAN PARAS + BATA GOSOK DIUKIR Rp. 449,205.00

XVI PEKERJAAN LANDSCAPE

1 1 M2 PASANGAN PAVING BETON 10/20 CM TEBAL 6 CM K 225 Rp. 89,450.00

2 Paving 10 x 20 cm tebal 6 cm K350 Rp. 97,450.00

3 Paving 10 x 20 cm tebal 8 cm K225 Rp. 97,450.00

4 Paving 10 x 20 cm tebal 8 cm K350 Rp. 102,450.00

5 Paving 20 x 20 cm tebal 6 cm K225 Rp. 89,450.00

6 Paving 20 x 20 cm tebal 6 cm K350 Rp. 97,450.00

7 Paving 20 x 20 cm tebal 8 cm K225 Rp. 97,450.00

8 Paving 20 x 20 cm tebal 8 cm K350 Rp. 102,450.00

9 Paving 20 x 20 cm tebal 8 cm K425 Rp. 109,950.00

10 Paving 20 x 20 cm tebal 10 cm K225 Rp. 100,950.00

11 Paving 20 x 20 cm tebal 10 cm K350 Rp. 110,450.00

12 Paving 20 x 20 cm tebal 10 cm K425 Rp. 119,450.00

13 Paving Tiga Berlian tebal 6 cm K225 Rp. 87,450.00

14 1 M2 PASANGAN GRASS BLOCK Rp. 132,870.00

15 1 M2 PASANGAN KORAL SIKAT Rp. 123,879.60

16 1 M1 KANSTEIN BULAT (50 x 30 x 10 ) CM K225 Rp. 132,222.40

17 Kanstein Jumbo (P:50,L:15,T:30 cm K225) Rp. 160,231.60

18 Kanstein Segi Lima Jumbo (P:50,L:15, T:40 cm K225) Rp. 174,231.60

19 1 M2 PENGECATAN KANSTEIN Rp. 29,274.00

XVII PEKERJAAN ELEKTRIKAL

1 1 TITIK INSTALASI STOP KONTAK, LAMPU, EXHAUST FAN DAN CEILING FAN Rp. 198,250.00

2 1 TITIK INSTALASI AC Rp. 252,750.00

3 1 TITIK INSTALASI TELEPHONE Rp. 266,750.00

4 1 TITIK INSTALASI MATV Rp. 268,000.00

Kepala Dinas Cipta Karya

Kabupaten Badung

Ir. Ni Luh Putu Dessy Dharmayanty, M.T

Pembina Tk. I

NIP. 196110101994032001

Page 53: Analisa Sni 2002 & 2008.Dck Januari 2013

Harga Barang dan Upah Hal. 53

DAFTAR HARGA SATUAN BAHAN TAMBAHANBULAN Januari TAHUN 2013

A. Harga Satuan Bahan

NO NAMA BARANG SATUAN HARGA SATUAN

1 2 3 4

BATUBatu Candi

1 20x20x2 m2 78,000.00 2 15x30x2 m2 78,000.00 3 20x30x2 m2 78,000.00 4 20x40x2 m2 80,000.00 5 30x30x2 m2 80,000.00 6 40x40x2 m2 105,000.00 7 30x60x2 m2 115,000.00 8 20x40x3 m2 135,000.00 9 30x30x3 m2 135,000.00

10 30x30x5 m2 165,000.00 11 40x40x5 m2 185,000.00

Palimanan putih1 20x20x2 m2 65,000.00 2 20x30x2 m2 67,000.00 3 20x40x2 m2 68,000.00 4 20x40x3 m2 110,000.00 5 30x30x3 m2 110,000.00

Palimanan Serat Kuning1 20x30 m2 75,000.00 2 20x40 m2 75,000.00 3 15x30 m2 75,000.00

Palimanan Cirebon1 15x30x2 m2 72,000.00 2 20x30x2 m2 73,000.00 3 20x40x2 m2 75,000.00 4 30x30x2 m2 80,000.00

Alur Bali Green Lurus1 20x30 m2 105,000.00 2 20x40 m2 105,000.00

Alur Bali Green Cukil1 20x30 m2 105,000.00 2 20x40 m2 105,000.00 3 20x20 m2 105,000.00

Batu Bali Green1 15x30 m2 75,000.00 2 20x30 m2 75,000.00 3 20x40 m2 75,000.00 4 40x40 m2 80,000.00

PARASParas Kerobokan

1 20x40x3 Bj 6,000.00 2 20x40x5 Bj 8,000.00

Paras Kelating1 20x40x3 Bj 6,000.00 2 20x40x5 Bj 8,000.00

Alur Andesit Lurus1 20x40 m3 135,000.00 2 30x60 m3 140,000.00

Alur and cukil1 20x40 m2 135,000.00 2 15x30 m2 135,000.00

Page 54: Analisa Sni 2002 & 2008.Dck Januari 2013

Harga Barang dan Upah Hal. 54

NO NAMA BARANG SATUAN HARGA SATUAN

1 2 3 4

Alur And Gelombang m2 140,000.00 Alur And Gelombang lurus m2 140,000.00

Random Singaraja m2 25,000.00 Random Cirebon m2 65,000.00 Random Jember m2 45,000.00