URAIAN ANALISA ALAT No. U R A I A N A. URAIAN PERALATAN 1. Jenis Peralatan 2. Tenaga 3. Kapasitas 4. Alat Baru : a. Umur Ekonomis b. Jam Kerja Dalam 1 Tahu c. Harga Alat B. BIAYA PASTI PER JAM KERJA 1. Nilai Sisa Alat = 10 % x B 2. Faktor Angsuran Modal = i x (1 + i)^A (1 + i)^A - 1 3. Biaya Pasti per Jam : a. Biaya Pengembalian Modal = ( B - C ) x D W b. Asuransi, dll = 0.002 x B W Biaya Pasti per Jam = ( E + F ) C. BIAYA OPERASI PER JAM KERJA 1. Bahan Bakar = (12%-15%) x Pw x Ms 2. Pelumas = (2.5%-3%) x Pw x Mp Biaya bengkel (6.25% dan 8.75%) x B W 3. Perawatan dan 2,5 % - 17,5 %) x perbaikan = W 4. Operator = ( 1 Orang / Jam ) x U 5. Pembantu Operator = ( 1 Orang / Jam ) x U

Upload: pipin-excellente

Post on 11-Nov-2015

11 views

Category:

Documents


0 download

DESCRIPTION

Analisa harga satuan alat berat

TRANSCRIPT

dozerURAIAN ANALISA ALAT

No.U R A I A NKODEKOEF.SATUANKET.

A.URAIAN PERALATAN 1.Jenis PeralatanBULLDOZER 100-150 HP 2.TenagaPw155.0HP 3.KapasitasCp- - 4.Alat Baru : a. Umur EkonomisA5.0Tahun b. Jam Kerja Dalam 1 TahunW2,000.0Jam c. Harga AlatB600,000,000Rupiah

B.BIAYA PASTI PER JAM KERJA 1.Nilai Sisa Alat= 10 % x BC60,000,000Rupiah

2.Faktor Angsuran Modal =i x (1 + i)^AD0.26380-(1 + i)^A - 1 3.Biaya Pasti per Jam :a. Biaya Pengembalian Modal =( B - C ) x DE71,225.32RupiahW

b. Asuransi, dll =0.002 x BF0.00RupiahW

Biaya Pasti per Jam =( E + F )G71,225.32Rupiah

C.BIAYA OPERASI PER JAM KERJA

1.Bahan Bakar = (12%-15%) x Pw x Ms H223,200.00Rupiah

2.Pelumas = (2.5%-3%) x Pw x MpI93,000.00Rupiah

Biaya bengkel(6.25% dan 8.75%) x BJ26,250 W

3.Perawatan dan(12,5 % - 17,5 %) x BK37,500.00Rupiah perbaikan =W

4.Operator= ( 1 Orang / Jam ) x U1L15,000.00Rupiah 5.Pembantu Operator= ( 1 Orang / Jam ) x U2M10,000.00Rupiah

Biaya Operasi per Jam =(H+I+K+L+M)P404,950.00Rupiah

D.TOTAL BIAYA SEWA ALAT / JAM = ( G + P )S476,175.32Rupiah

E.LAIN - LAIN 1.Tingkat Suku Bungai10.00% / Tahun 2.Upah Operator / SopirU115,000.00Rp./Jam 3.Upah Pembantu Operator / Pmb.SopirU210,000.00Rp./Jam 4.Bahan Bakar BensinMb11,000.00Rp/Liter 5.Bahan Bakar SolarMs12,000.00Rp/Liter 6.Minyak PelumasMp24,000.00Rp/Liter 7.PPN diperhitungkan pada lembar RekapitulasiBiaya Pekerjaan

URAIAN ANALISA ALAT

No.U R A I A NKODEKOEF.SATUANKET.

A.URAIAN PERALATAN 1.Jenis PeralatanDUMP TRUCK 10 TON 2.TenagaPw190.0HP 3.KapasitasCp10.0Ton 4.Alat Baru : a. Umur EkonomisA5.0Tahun b. Jam Kerja Dalam 1 TahunW2,000.0Jam c. Harga AlatB380,000,000Rupiah

B.BIAYA PASTI PER JAM KERJA 1.Nilai Sisa Alat= 10 % x BC38,000,000Rupiah

2.Faktor Angsuran Modal =i x (1 + i)^AD0.26380-(1 + i)^A - 1 3.Biaya Pasti per Jam :a. Biaya Pengembalian Modal =( B - C ) x DE45,109.37RupiahW

b. Asuransi, dll =0.002 x BF0.00RupiahW

Biaya Pasti per Jam =( E + F )G45,109.37Rupiah

C.BIAYA OPERASI PER JAM KERJA

1.Bahan Bakar = (12%-15%) x Pw x Ms H273,600.00Rupiah

2.Pelumas = (2.5%-3%) x Pw x MpI114,000.00Rupiah

Biaya bengkel(6.25% dan 8.75%) x BJ16,625Rupiah W

3.Perawatan dan(12,5 % - 17,5 %) x BK23,750.00Rupiah perbaikan =W

4.Operator= ( 1 Orang / Jam ) x U1L15,000.00Rupiah 5.Pembantu Operator= ( 1 Orang / Jam ) x U2M10,000.00Rupiah

Biaya Operasi per Jam =(H+I+K+L+M)P452,975.00Rupiah

D.TOTAL BIAYA SEWA ALAT / JAM = ( G + P )S498,084.37Rupiah

E.LAIN - LAIN 1.Tingkat Suku Bungai10.00% / Tahun 2.Upah Operator / Sopir / MekanikU115,000.00Rp./Jam 3.Upah Pembantu Operator / Pmb.Sopir / Pmb.MekanikU210,000.00Rp./Jam 4.Bahan Bakar BensinMb11,000.00Rp / Liter 5.Bahan Bakar SolarMs12,000.00Rp / Liter 6.Minyak PelumasMp24,000.00Rp / Liter 7.PPN diperhitungkan pada lembar RekapitulasiBiaya Pekerjaan

URAIAN ANALISA ALAT

No.U R A I A NKODEKOEF.SATUANKET.

A.URAIAN PERALATAN 1.Jenis PeralatanEXCAVATOR 80-140 HP 2.TenagaPw133.0HP 3.KapasitasCp0.93M3 4.Alat Baru : a. Umur EkonomisA5.0Tahun b. Jam Kerja Dalam 1 TahunW2,000.0Jam c. Harga AlatB2,000,000,000Rupiah

B.BIAYA PASTI PER JAM KERJA 1.Nilai Sisa Alat= 10 % x BC200,000,000Rupiah

2.Faktor Angsuran Modal =i x (1 + i)^AD0.26380-(1 + i)^A - 1 3.Biaya Pasti per Jam :a. Biaya Pengembalian Modal =( B - C ) x DE237,417.73RupiahW

b. Asuransi, dll =0.002 x BF0.00RupiahW

Biaya Pasti per Jam =( E + F )G237,417.73Rupiah

C.BIAYA OPERASI PER JAM KERJA

1.Bahan Bakar = (12%-15%) x Pw x Ms H191,520.00Rupiah

2.Pelumas = (2.5%-3%) x Pw x MpI79,800.00Rupiah

Biaya bengkel(6.25% dan 8.75%) x BJ87,500Rupiah W

3.Perawatan dan(12,5 % - 17,5 %) x BK125,000.00Rupiah perbaikan =W

4.Operator= ( 1 Orang / Jam ) x U1L15,000.00Rupiah 5.Pembantu Operator= ( 1 Orang / Jam ) x U2M10,000.00Rupiah

Biaya Operasi per Jam =(H+I+K+L+M)P508,820.00Rupiah

D.TOTAL BIAYA SEWA ALAT / JAM = ( G + P )S746,237.73Rupiah

E.LAIN - LAIN 1.Tingkat Suku Bungai10.00% / Tahun 2.Upah Operator / SopirU115,000.00Rp./Jam 3.Upah Pembantu Operator / Pmb.SopirU210,000.00Rp./Jam 4.Bahan Bakar BensinMb11,000.00Rp / Liter 5.Bahan Bakar SolarMs12,000.00Rp / Liter 6.Minyak PelumasMp24,000.00Rp / Liter 7.PPN diperhitungkan pada lembar RekapitulasiBiaya Pekerjaan

URAIAN ANALISA ALAT

No.U R A I A NKODEKOEF.SATUANKET.

A.URAIAN PERALATAN 1.Jenis PeralatanWHEEL LOADER 1.0-1.6 M3 2.TenagaPw96.0HP 3.KapasitasCp1.5M3 4.Alat Baru : a. Umur EkonomisA5.0Tahun b. Jam Kerja Dalam 1 TahunW2,000.0Jam c. Harga AlatB600,000,000Rupiah

B.BIAYA PASTI PER JAM KERJA 1.Nilai Sisa Alat= 10 % x BC60,000,000Rupiah

2.Faktor Angsuran Modal =i x (1 + i)^AD0.26380-(1 + i)^A - 1 3.Biaya Pasti per Jam :a. Biaya Pengembalian Modal =( B - C ) x DE71,225.32RupiahW

b. Asuransi, dll =0.002 x BF0.00RupiahW

Biaya Pasti per Jam =( E + F )G71,225.32Rupiah

C.BIAYA OPERASI PER JAM KERJA

1.Bahan Bakar = (12%-15%) x Pw x Ms H138,240.00Rupiah

2.Pelumas = (2.5%-3%) x Pw x MpI57,600.00Rupiah

Biaya bengkel(6.25% dan 8.75%) x BJ26,250Rupiah W

3.Perawatan dan(12,5 % - 17,5 %) x BK37,500.00Rupiah perbaikan =W

4.Operator= ( 1 Orang / Jam ) x U1L15,000.00Rupiah 5.Pembantu Operator= ( 1 Orang / Jam ) x U2M10,000.00Rupiah

Biaya Operasi per Jam =(H+I+K+L+M)P284,590.00Rupiah

D.TOTAL BIAYA SEWA ALAT / JAM = ( G + P )S355,815.32Rupiah

E.LAIN - LAIN 1.Tingkat Suku Bungai10.00% / Tahun 2.Upah Operator / SopirU115,000.00Rp./Jam 3.Upah Pembantu Operator / Pmb.SopirU210,000.00Rp./Jam 4.Bahan Bakar BensinMb11,000.00Rp / Liter 5.Bahan Bakar SolarMs12,000.00Rp / Liter 6.Minyak PelumasMp24,000.00Rp / Liter 7.PPN diperhitungkan pada lembar RekapitulasiBiaya Pekerjaan

URAIAN ANALISA ALAT

No.U R A I A NKODEKOEF.SATUANKET.

A.URAIAN PERALATAN 1.Jenis PeralatanGENERATOR SET 2.TenagaPw180.0HP 3.KapasitasCp150.0KVA 4.Alat Baru : a. Umur EkonomisA5.0Tahun b. Jam Kerja Dalam 1 TahunW2,000.0Jam c. Harga AlatB120,000,000Rupiah

B.BIAYA PASTI PER JAM KERJA 1.Nilai Sisa Alat= 10 % x BC12,000,000Rupiah

2.Faktor Angsuran Modal =i x (1 + i)^AD0.26380-(1 + i)^A - 1 3.Biaya Pasti per Jam :a. Biaya Pengembalian Modal =( B - C ) x DE14,245.06RupiahW

b. Asuransi, dll =0.002 x BF0.00RupiahW

Biaya Pasti per Jam =( E + F )G14,245.06Rupiah

C.BIAYA OPERASI PER JAM KERJA

1.Bahan Bakar = (12%-15%) x Pw x Ms H259,200.00Rupiah

2.Pelumas = (2.5%-3%) x Pw x MpI108,000.00Rupiah

Biaya bengkel(6.25% dan 8.75%) x BJ5,250Rupiah W

3.Perawatan dan(12,5 % - 17,5 %) x BK7,500.00Rupiah perbaikan =W

4.Operator= ( 1 Orang / Jam ) x U1L15,000.00Rupiah 5.Pembantu Operator= ( 1 Orang / Jam ) x U2M10,000.00Rupiah

Biaya Operasi per Jam =(H+I+K+L+M)P404,950.00Rupiah

D.TOTAL BIAYA SEWA ALAT / JAM = ( G + P )S419,195.06Rupiah

E.LAIN - LAIN 1.Tingkat Suku Bungai10.00% / Tahun 2.Upah Operator / SopirU115,000.00Rp./Jam 3.Upah Pembantu Operator / Pmb.SopirU210,000.00Rp./Jam 4.Bahan Bakar BensinMb11,000.00Rp / Liter 5.Bahan Bakar SolarMs12,000.00Rp / Liter 6.Minyak PelumasMp24,000.00Rp / Liter 7.PPN diperhitungkan pada lembar RekapitulasiBiaya Pekerjaan

DT10URAIAN ANALISA ALAT

No.U R A I A NKODEKOEF.SATUANKET.

A.URAIAN PERALATAN 1.Jenis PeralatanDUMP TRUCK 10 TON 2.TenagaPw190.0HP 3.KapasitasCp10.0Ton 4.Alat Baru : a. Umur EkonomisA5.0Tahun b. Jam Kerja Dalam 1 TahunW2,000.0Jam c. Harga AlatB380,000,000Rupiah

B.BIAYA PASTI PER JAM KERJA 1.Nilai Sisa Alat= 10 % x BC38,000,000Rupiah

2.Faktor Angsuran Modal =i x (1 + i)^AD0.26380-(1 + i)^A - 1 3.Biaya Pasti per Jam :a. Biaya Pengembalian Modal =( B - C ) x DE45,109.37RupiahW

b. Asuransi, dll =0.002 x BF0.00RupiahW

Biaya Pasti per Jam =( E + F )G45,109.37Rupiah

C.BIAYA OPERASI PER JAM KERJA

1.Bahan Bakar = (12%-15%) x Pw x Ms H273,600.00Rupiah

2.Pelumas = (2.5%-3%) x Pw x MpI114,000.00Rupiah

Biaya bengkel(6.25% dan 8.75%) x BJ16,625Rupiah W

3.Perawatan dan(12,5 % - 17,5 %) x BK23,750.00Rupiah perbaikan =W

4.Operator= ( 1 Orang / Jam ) x U1L15,000.00Rupiah 5.Pembantu Operator= ( 1 Orang / Jam ) x U2M10,000.00Rupiah

Biaya Operasi per Jam =(H+I+K+L+M)P452,975.00Rupiah

D.TOTAL BIAYA SEWA ALAT / JAM = ( G + P )S498,084.37Rupiah

E.LAIN - LAIN 1.Tingkat Suku Bungai10.00% / Tahun 2.Upah Operator / Sopir / MekanikU115,000.00Rp./Jam 3.Upah Pembantu Operator / Pmb.Sopir / Pmb.MekanikU210,000.00Rp./Jam 4.Bahan Bakar BensinMb11,000.00Rp / Liter 5.Bahan Bakar SolarMs12,000.00Rp / Liter 6.Minyak PelumasMp24,000.00Rp / Liter 7.PPN diperhitungkan pada lembar RekapitulasiBiaya Pekerjaan

URAIAN ANALISA ALAT

No.U R A I A NKODEKOEF.SATUANKET.

A.URAIAN PERALATAN 1.Jenis PeralatanWHEEL LOADER 1.0-1.6 M3 2.TenagaPw96.0HP 3.KapasitasCp1.5M3 4.Alat Baru : a. Umur EkonomisA5.0Tahun b. Jam Kerja Dalam 1 TahunW2,000.0Jam c. Harga AlatB600,000,000Rupiah

B.BIAYA PASTI PER JAM KERJA 1.Nilai Sisa Alat= 10 % x BC60,000,000Rupiah

2.Faktor Angsuran Modal =i x (1 + i)^AD0.26380-(1 + i)^A - 1 3.Biaya Pasti per Jam :a. Biaya Pengembalian Modal =( B - C ) x DE71,225.32RupiahW

b. Asuransi, dll =0.002 x BFERROR:#REF!RupiahW

Biaya Pasti per Jam =( E + F )GERROR:#REF!Rupiah

C.BIAYA OPERASI PER JAM KERJA

1.Bahan Bakar = (12%-15%) x Pw x Ms H138,240.00Rupiah

2.Pelumas = (2.5%-3%) x Pw x MpI57,600.00Rupiah

Biaya bengkel(6.25% dan 8.75%) x BJ26,250Rupiah W

3.Perawatan dan(12,5 % - 17,5 %) x BK37,500.00Rupiah perbaikan =W

4.Operator= ( 1 Orang / Jam ) x U1L15,000.00Rupiah 5.Pembantu Operator= ( 1 Orang / Jam ) x U2M10,000.00Rupiah

Biaya Operasi per Jam =(H+I+K+L+M)P284,590.00Rupiah

D.TOTAL BIAYA SEWA ALAT / JAM = ( G + P )SERROR:#REF!Rupiah

E.LAIN - LAIN 1.Tingkat Suku Bungai10.00% / Tahun 2.Upah Operator / SopirU115,000.00Rp./Jam 3.Upah Pembantu Operator / Pmb.SopirU210,000.00Rp./Jam 4.Bahan Bakar BensinMb11,000.00Rp / Liter 5.Bahan Bakar SolarMs12,000.00Rp / Liter 6.Minyak PelumasMp24,000.00Rp / Liter 7.PPN diperhitungkan pada lembar RekapitulasiBiaya Pekerjaan

URAIAN ANALISA ALAT

No.U R A I A NKODEKOEF.SATUANKET.

A.URAIAN PERALATAN 1.Jenis PeralatanGENERATOR SET 2.TenagaPw180.0HP 3.KapasitasCp150.0KVA 4.Alat Baru : a. Umur EkonomisA5.0Tahun b. Jam Kerja Dalam 1 TahunW2,000.0Jam c. Harga AlatB120,000,000Rupiah

B.BIAYA PASTI PER JAM KERJA 1.Nilai Sisa Alat= 10 % x BC12,000,000Rupiah

2.Faktor Angsuran Modal =i x (1 + i)^AD0.26380-(1 + i)^A - 1 3.Biaya Pasti per Jam :a. Biaya Pengembalian Modal =( B - C ) x DE14,245.06RupiahW

b. Asuransi, dll =0.002 x BFERROR:#REF!RupiahW

Biaya Pasti per Jam =( E + F )GERROR:#REF!Rupiah

C.BIAYA OPERASI PER JAM KERJA

1.Bahan Bakar = (12%-15%) x Pw x Ms H259,200.00Rupiah

2.Pelumas = (2.5%-3%) x Pw x MpI108,000.00Rupiah

Biaya bengkel(6.25% dan 8.75%) x BJ5,250Rupiah W

3.Perawatan dan(12,5 % - 17,5 %) x BK7,500.00Rupiah perbaikan =W

4.Operator= ( 1 Orang / Jam ) x U1L15,000.00Rupiah 5.Pembantu Operator= ( 1 Orang / Jam ) x U2M10,000.00Rupiah

Biaya Operasi per Jam =(H+I+K+L+M)P404,950.00Rupiah

D.TOTAL BIAYA SEWA ALAT / JAM = ( G + P )SERROR:#REF!Rupiah

E.LAIN - LAIN 1.Tingkat Suku Bungai10.00% / Tahun 2.Upah Operator / SopirU115,000.00Rp./Jam 3.Upah Pembantu Operator / Pmb.SopirU210,000.00Rp./Jam 4.Bahan Bakar BensinMb11,000.00Rp / Liter 5.Bahan Bakar SolarMs12,000.00Rp / Liter 6.Minyak PelumasMp24,000.00Rp / Liter 7.PPN diperhitungkan pada lembar RekapitulasiBiaya Pekerjaan

excavatorURAIAN ANALISA ALAT

No.U R A I A NKODEKOEF.SATUANKET.

A.URAIAN PERALATAN 1.Jenis PeralatanEXCAVATOR 80-140 HP 2.TenagaPw133.0HP 3.KapasitasCp0.93M3 4.Alat Baru : a. Umur EkonomisA5.0Tahun b. Jam Kerja Dalam 1 TahunW2,000.0Jam c. Harga AlatB2,000,000,000Rupiah

B.BIAYA PASTI PER JAM KERJA 1.Nilai Sisa Alat= 10 % x BC200,000,000Rupiah

2.Faktor Angsuran Modal =i x (1 + i)^AD0.26380-(1 + i)^A - 1 3.Biaya Pasti per Jam :a. Biaya Pengembalian Modal =( B - C ) x DE237,417.73RupiahW

b. Asuransi, dll =0.002 x BF0.00RupiahW

Biaya Pasti per Jam =( E + F )G237,417.73Rupiah

C.BIAYA OPERASI PER JAM KERJA

1.Bahan Bakar = (12%-15%) x Pw x Ms H191,520.00Rupiah

2.Pelumas = (2.5%-3%) x Pw x MpI79,800.00Rupiah

Biaya bengkel(6.25% dan 8.75%) x BJ87,500Rupiah W

3.Perawatan dan(12,5 % - 17,5 %) x BK125,000.00Rupiah perbaikan =W

4.Operator= ( 1 Orang / Jam ) x U1L15,000.00Rupiah 5.Pembantu Operator= ( 1 Orang / Jam ) x U2M10,000.00Rupiah

Biaya Operasi per Jam =(H+I+K+L+M)P508,820.00Rupiah

D.TOTAL BIAYA SEWA ALAT / JAM = ( G + P )S746,237.73Rupiah

E.LAIN - LAIN 1.Tingkat Suku Bungai10.00% / Tahun 2.Upah Operator / SopirU115,000.00Rp./Jam 3.Upah Pembantu Operator / Pmb.SopirU210,000.00Rp./Jam 4.Bahan Bakar BensinMb11,000.00Rp / Liter 5.Bahan Bakar SolarMs12,000.00Rp / Liter 6.Minyak PelumasMp24,000.00Rp / Liter 7.PPN diperhitungkan pada lembar RekapitulasiBiaya Pekerjaan

alatDAFTAR BIAYA SEWA PERALATAN PER JAM KERJA (2015)

No.JENIS ALATKODEHPKAP.HARGA ALATBIAYA SEWA ALAT(Jam)(di luar PPN)

1BULLDOZER 100-150 HPE04155.00- - 610,000,000.00459,356.342COMPRESSOR 4000-6500 L\ME0560.005,000.00500065,000,000.00156,658.753CONCRETE MIXER 0.3-0.6 M3E0620.00500.00Liter12,500,000.0081,897.024CRANE 10-15 TONE07138.0015.00Ton2,400,000,000.00831,692.715DUMP TRUCK 3.5 TONE08100.003.50Ton230,000,000.00269,541.976DUMP TRUCK 10 TONE09190.0010.00Ton480,000,000.00496,131.687EXCAVATOR 80-140 HPE10133.000.93M31,550,000,000.00630,177.678GENERATOR SETE12180.00135.00KVA95,000,000.00390,237.529MOTOR GRADER >100 HPE13135.0010,800.00108001,760,000,000.00681,409.0310TRACK LOADER 75-100 HPE1470.000.80M3542,000,000.00283,341.1311WHEEL LOADER 1.0-1.6 M3E1596.001.50M3600,000,000.00345,586.7512VIBRATORY ROLLER 5-8 T.E1982.007.05Ton918,787,500.00391,159.6113CONCRETE VIBRATORE205.5025.00257,500,000.0045,367.1114STONE CRUSHERE21220.0050.00T/Jam1,010,989,671.00684,242.0815WATER PUMP 70-100 mmE226.00- - 3,500,000.0040,920.1316WATER TANKER 3000-4500 L.E23100.004,000.00Liter320,000,000.00289,878.2717PEDESTRIAN ROLLERE248.80835.00Ton150,000,000.0088,433.6818JACK HAMMERE260.01,330.00133015,000,000.0031,960.8119FULVI MIXERE27345.002,005.002005900,000,000.001,306,952.7820TRAILER 20 TONE29175.0020.00Ton600,000,000.00485,665.4221PILE DRIVER + HAMMERE3025.002.50Ton875,000,000.00273,535.4422CRANE ON TRACK 35 TONE31125.0035.00Ton850,000,000.00443,808.7523WELDING SETE3240.00250.00Amp10,000,000.00106,431.0224BORE PILE MACHINEE33150.002,000.00Meter2,250,000,000.00785,861.4025TRONTONE35150.0015.00Ton450,000,000.00525,719.8326ROCK DRILL BREAKERE373.00--900,000,000.00305,031.0827AGGREGAT (CHIP) SPREADERE40115.003.50M395,000,000.00527,280.9428ASPHALT DISTRIBUTORE41115.004,000.00Liter395,000,000.00358,032.3229CONCRETE PAN MIXERE43134.00600.00Liter1,000,000,000.00638,969.1430CONCRETE BREAKERE44290.0020.00m3/jam900,000,000.00802,891.5531CEMENT TANKERE46190.004,000.00liter500,000,000.00492,958.0932VIBRATING RAMMERE484.2080.00KG20,000,000.0048,867.9033BORE PILE MACHINEE50125.0060.00CM1,170,000,000.00641,628.7034CRANE ON TRACK 75-100 TONE51200.0075.00Ton900,000,000.00609,934.41