  • HARGA UPAH HARGA

    SNI KODE SATUAN PEKERJA BAHAN

    (Rp.) (Rp.) (Rp.) (Rp.)

    A. PEKERJAAN TANAH

    1 03-2835-2008 6.1 1 M3 Galian tanah biasa sedalam 1 m

    0.7500 oh Pekerja

    0.0250 oh Mandor

    Jml Total

    2 03-2835-2008 6.2 1 M3 Galian tanah biasa sedalam 2 m

    0.9000 oh Pekerja

    0.0450 oh Mandor

    Jml Total

    3 03-2835-2008 6.9 1 M3 Mengurug tanah kembali ( 1/3 dari indek pek galian )

    0.3000 oh Pekerja

    0.0150 oh Mandor

    Jml Total

    4 03-2835-2008 6.11 1 M3 Urugan pasir

    1.2000 m3 Pasir urug

    0.3000 oh Pekerja

    0.0100 oh Mandor

    Jml Total

    5 03-2835-2008 6.15 1 M3 Urugan tanah + pemadatan

    0.2500 oh Pekerja

    0.0250 oh Mandor

    1.0000 ls Pemadatan

    Jml Total

    6 03-2835-2008 6.15 1 M3 Urugan fill + pemadatan

    0.2500 oh Pekerja

    0.0250 oh Mandor

    1.0000 ls Pemadatan

    Jml Total

    7 03-2835-2008 6.15 1 M3 Pembuangan tanah sejauh 150 m

    0.5160 oh Pekerja

    0.0500 oh Mandor

    Jml Total

    B. PEKERJAAN PONDASI

    1 03-2836-2008 6.9 1 M3 Pasang batu kosong / anstamping

    1.2000 m3 Batu belah

    0.4330 m3 Pasir urug

    0.7800 oh Pekerja

    0.3900 oh Tukang batu

    0.0390 oh Kepala tukang

    0.0390 oh Mandor

    2 03-2836-2008 6.3 1 M3 Pasang batu belah 1 Pc : 5 Ps

    1.2000 m3 Batu belah

    136.0000 kg Portland Cemen ( PC )

    0.5440 m3 Pasir pasang

    1.5000 oh Pekerja

    0.6000 oh Tukang batu

    0.0600 oh Kepala tukang

    0.0750 oh Mandor

    C. PEKERJAAN DINDING & PLESTERAN

    1 03-6897-2008 6,10 1 M2 Pasang batu bata merah (5x11x22) cm tbl 1/2 bata camp 1 Pc : 5 Ps

    70.0000 m3 Batu bata

    9.6800 kg Portland Cemen ( PC )

    0.0450 m3 Pasir pasang

    0.3000 oh Pekerja

    0.1000 oh Tukang batu

    0.0100 oh Kepala tukang

    0.0150 oh Mandor

    ANALISA HARGA SATUAN PEKERJAAN

    NO JUMLAHANALISA PEKERJAAN

  • 2 03-2837-2008 6.16 1 M2 Plesteran 1 Pc : 5 Ps- tbl 20 mm

    6.9120 kg Portland Cemen ( PC )

    0.0350 m3 Pasir pasang

    0.2600 oh Pekerja

    0.2000 oh Tukang batu

    0.0200 oh Kepala tukang

    0.0130 oh Mandor

    3 03-2837-2008 6.15 1 M2 Plesteran 1 Pc : 4 Ps- tbl 20 mm

    8.3200 kg Portland Cemen ( PC )

    0.0320 m3 Pasir pasang

    0.2600 oh Pekerja

    0.2000 oh Tukang batu

    0.0200 oh Kepala tukang

    0.0130 oh Mandor

    4 03-2837-2008 6.19 1 M2 Plesteran braben 1 Pc : 5 Ps- tbl 15 mm

    5.1840 kg Portland Cemen ( PC )

    0.0260 m3 Pasir pasang

    0.1500 oh Pekerja

    0.0700 oh Tukang batu

    0.0070 oh Kepala tukang

    0.0080 oh Mandor

    5 03-2837-2008 6,20 1 M' Plesteran skoning 1 : 2 lebar 10 mm

    0.5000 kg Portland Cemen ( PC )

    0.0130 m3 Pasir pasang

    0.0570 oh Pekerja

    0.0380 oh Tukang batu

    0.0380 oh Kepala tukang

    0.0030 oh Mandor

    6 03-2837-2008 6,26 1 M' Memasang finishing siar batu kali 1Pc : 2Ps

    6.3400 kg Portland Cemen ( PC )

    0.1200 m3 Pasir pasang

    0.3000 oh Pekerja

    0.1400 oh Tukang batu

    0.0140 oh Kepala tukang

    0.0150 oh Mandor

    7 03-2837-2008 6,27 1 M2 Memasang acian

    3.2500 kg Portland Cemen ( PC )

    0.1500 oh Pekerja

    0.1000 oh Tukang batu

    0.0100 oh Kepala tukang

    0.0080 oh Mandor

    D. PEKERJAAN LANTAI

    1 03-7395-2008 6.9 1 M2 Lantai keramik polish 60/60 ( Aula ) :

    3.0000 bh keramik polish 60x60

    14.7000 kg Portland Cemen ( PC )

    1.9500 kg PC warna

    0.0675 m3 Pasir pasang

    0.3750 oh Pekerja

    0.1800 oh Tukang batu

    0.0180 oh Kepala tukang

    0.0195 oh Mandor

    2 03-7395-2008 6.9 1 M2 Lantai keramik unpolish 60/60 ( Aula ) :

    3.0000 bh keramik polish 60x60

    14.7000 kg Portland Cemen ( PC )

    1.9500 kg PC warna

    0.0675 m3 Pasir pasang

    0.3750 oh Pekerja

    0.1800 oh Tukang batu

    0.0180 oh Kepala tukang

    0.0195 oh Mandor

  • 3 03-7395-2008 6.9 1 M2 Lantai granito 60/60 ( Aula ) :

    3.0000 bh granito 60x60

    14.7000 kg Portland Cemen ( PC )

    1.9500 kg PC warna

    0.0675 m3 Pasir pasang

    0.3750 oh Pekerja

    0.1800 oh Tukang batu

    0.0180 oh Kepala tukang

    0.0195 oh Mandor

    4 03-7395-2008 6.9 1 M2 Lantai keramik 40/40 (Polish) :

    6.6300 bh keramik 40x40

    9.8000 kg Portland Cemen ( PC )

    1.3000 kg PC warna

    0.0450 m3 Pasir pasang

    0.2500 oh Pekerja

    0.1200 oh Tukang batu

    0.0120 oh Kepala tukang

    0.0130 oh Mandor

    5 03-7395-2008 6.9 1 M2 Lantai keramik 40/40 (Un polish) :

    6.6300 bh keramik 40x40

    9.8000 kg Portland Cemen ( PC )

    1.3000 kg PC warna

    0.0450 m3 Pasir pasang

    0.2500 oh Pekerja

    0.1200 oh Tukang batu

    0.0120 oh Kepala tukang

    0.0130 oh Mandor

    6 03-7395-2008 6.35 1 M2 Lantai keramik unpolish 30/30 :

    11.8700 bh Keramik 30x30

    10.0000 kg Portland Cemen ( PC )

    1.5000 kg PC warna

    0.0450 m3 Pasir pasang

    0.6200 oh Pekerja

    0.3500 oh Tukang batu

    0.0350 oh Kepala tukang

    0.0300 oh Mandor

    7 03-7395-2008 6.35 1 M2 Lantai keramik 30/30 :

    11.8700 bh Keramik 30x30

    10.0000 kg Portland Cemen ( PC )

    1.5000 kg PC warna

    0.0450 m3 Pasir pasang

    0.6200 oh Pekerja

    0.3500 oh Tukang batu

    0.0350 oh Kepala tukang

    0.0300 oh Mandor

    8 03-7395-2008 6.54 1 M2 Pasang keramik dinding 20x25 :

    21.5000 bh Keramik 20x25

    10.4000 kg Portland Cemen ( PC )

    1.6200 kg PC warna

    0.0450 m3 Pasir pasang

    0.6200 oh Pekerja

    0.3500 oh Tukang batu

    0.0350 oh Kepala tukang

    0.0300 oh Mandor

    9 03-7395-2008 6.36 1 M2 Pasang keramik lantai 20x20 :

    26.5000 bh Keramik 20x20

    10.4000 kg Portland Cemen ( PC )

    1.6200 kg PC warna

    0.0450 m3 Pasir pasang

  • 0.6200 oh Pekerja

    0.3500 oh Tukang batu

    0.0350 oh Kepala tukang

    0.0300 oh Mandor

    10 03-7395-2008 1 M' Pasang nozing tangga 5x20 :

    5.000 bh Nozing 5x20

    2.600 kg Portland Cemen ( PC )

    0.405 kg PC warna

    0.011 m3 Pasir pasang

    0.088 oh Tukang

    0.009 oh Kepala tukang

    0.155 oh Pekerja

    0.008 oh Mandor

    11 03-7395-2008 1 M' Pasang keramik border dinidng km/wc 5x30 :

    4.000 bh Keramik border 5x30

    1.140 kg Portland Cemen ( PC )

    0.025 kg PC warna

    0.003 m3 Pasir pasang

    0.090 oh Tukang

    0.009 oh Kepala tukang

    0.090 oh Pekerja

    0.005 oh Mandor

    12 1 M' Pasang plint kaca rayband 5 mm L = 10 cm

    0.1000 m2 Plint kaca rayband 5 mm L = 10 cm

    1.1400 kg Portland Cemen ( PC )

    0.090 oh Pekerja

    0.090 oh Tukang

    0.009 oh Kepala tukang

    0.005 oh Mandor

    13 03-7395-2008 1 M' Pasang kuku macan 2,5x10 :

    10.000 bh Kuku macan 2,5x10

    0.945 kg Portland Cemen ( PC )

    0.147 kg PC warna

    0.004 m3 Pasir pasang

    0.032 oh Tukang

    0.003 oh Kepala tukang

    0.056 oh Pekerja

    0.003 oh Mandor

    14 03-7395-2008 6.57 1 M2 Pasang batu serit / mortar

    1.1000 m2 Batu serit

    11.7500 kg Portland Cemen ( PC )

    0.0350 m3 Pasir pasang

    0.6200 oh Pekerja

    0.3500 oh Tukang batu

    0.0350 oh Kepala tukang

    0.0300 oh Mandor

    E. PEKERJAAN BETON

    1 03-7394-2008 6.4 1 M3 Beton lantai kerja mutu fc = 7,4 Mpa ( K100) slum (3-6) cm w/c = 0,87

    230.0000 kg Portland Cemen ( PC )

    893.0000 kg Pasir beton

    1,024.0000 kg Kerikil (maksimum 30 mm)

    200.0000 ltr air

    1.2000 oh Pekerja

    0.2000 oh Tukang batu

    0.0200 oh Kepala tukang

    0.0060 oh Mandor

    2 03-7394-2008 6.5 1 M3 Beton mutu fc = 9,8 Mpa ( K175) slum (122) cm w/c = 0,66

    326.0000 kg Portland Cemen ( PC )

    760.0000 kg Pasir beton

    1,029.0000 kg Kerikil (maksimum 30 mm)

  • 215.0000 ltr air

    1.6500 oh Pekerja

    0.2500 oh Tukang batu

    0.0250 oh Kepala tukang

    0.0800 oh Mandor

    3 03-7394-2008 6.7 1 M3 Beton mutu fc = 19,3 Mpa ( K225) slum (122) cm w/c = 0,58

    371.0000 kg Portland Cemen ( PC )

    698.0000 kg Pasir beton

    1,047.0000 kg Kerikil (maksimum 30 mm)

    215.0000 ltr air

    1.6500 oh Pekerja

    0.2500 oh Tukang batu

    0.0250 oh Kepala tukang

    0.0800 oh Mandor

    4 03-7394-2008 6.9 1 M3 Beton mutu fc = 24 Mpa ( K275) slum (122) cm w/c = 0,53

    406.0000 kg Portland Cemen ( PC )

    684.0000 kg Pasir beton

    1,026.0000 kg Kerikil (maksimum 30 mm)

    215.0000 ltr air

    1.6500 oh Pekerja

    0.2500 oh Tukang batu

    0.0250 oh Kepala tukang

    0.0800 oh Mandor

    5 03-7394-2008 6.9 1 M3 Beton mutu fc = 26.4 Mpa ( K300) slum (122) cm w/c = 0,52

    413.0000 kg Portland Cemen ( PC )

    681.0000 kg Pasir beton

    1,021.0000 kg Kerikil (maksimum 30 mm)

    215.0000 ltr air

    1.6500 oh Pekerja

    0.2750 oh Tukang batu

    0.0280 oh Kepala tukang

    0.0830 oh Mandor

    6 03-7394-2008 6.17 10 kg Pembesian dengan besi polos / ulir

    10.5000 kg Besi polos / ulir

    0.1500 kg Kawat beton

    0.0700 oh Pekerja

    0.0700 oh Tukang batu

    0.0070 oh Kepala tukang

    0.0040 oh Mandor

    1 kg Pembesian dengan besi polos / ulir

    7 03-7394-2008 6.21 1 M2 Memasang Bekisting untuk sloof

    0.0450 m3 Kayu kelas III (terentang)

    0.3000 kg Paku biasa 2"-5"

    0.1000 ltr Minyak bekisting

    0.5200 oh Pekerja

    0.2600 oh Tukang batu

    0.0260 oh Kepala tukang

    0.0260 oh Mandor

    8 03-7394-2008 6.22 1 M2 Memasang Bekisting untuk kolom

    0.0400 m3 Kayu kelas III (terentang)

    0.4000 kg Paku biasa 2"-5"

    0.2000 ltr Minyak bekisting

    0.0150 m3 Balok kayu kelas II

    0.3500 lbr Multiplex 6 mm

    2.0000 btg Dolken kayu dia 8-10 cm / 4 m

    0.6600 oh Pekerja

    0.3300 oh Tukang batu

    0.0330 oh Kepala tukang

    0.0330 oh Mandor

    9 03-7394-2008 6.23 1 M2 Memasang Bekisting untuk balok

  • 0.0400 m3 Kayu kelas III (terentang)

    0.4000 kg Paku biasa 2"-5"

    0.2000 ltr Minyak bekisting

    0.0180 m3 Balok kayu kelas II

    0.3500 lbr Multiplex 6 mm

    2.0000 btg Dolken kayu dia 8-10 cm / 4 m

    0.6600 oh Pekerja

    0.3300 oh Tukang batu

    0.0330 oh Kepala tukang

    0.0330 oh Mandor

    10 03-7394-2008 6.24 1 M2 Memasang Bekisting untuk lantai

    0.0400 m3 Kayu kelas III (terentang)

    0.4000 kg Paku biasa 2"-5"

    0.2000 ltr Minyak bekisting

    0.0150 m3 Balok kayu kelas II

    0.3500 lbr Multiplex 6 mm

    2.0000 btg Dolken kayu dia 8-10 cm / 4 m

    0.6600 oh Pekerja

    0.3300 oh Tukang batu

    0.0330 oh Kepala tukang

    0.0330 oh Mandor

    11 03-7394-2008 6.26 1 M2 Memasang Bekisting untuk tangga

    0.0300 m3 Kayu kelas III (terentang)

    0.4000 kg Paku biasa 2"-5"

    0.1500 ltr Minyak bekisting

    0.0150 m3 Balok kayu kelas II

    0.3500 lbr Multiplex 6 mm

    2.0000 btg Dolken kayu dia 8-10 cm / 4 m

    0.6600 oh Pekerja

    0.3300 oh Tukang batu

    0.0330 oh Kepala tukang

    0.0330 oh Mandor

    12 Dihitung 1 M3 Beton bertulang praktis 15 x 15 :

    1.0000 m3 Beton K 225

    149.5207 kg Besi

    13.3332 m2 Bekisting

    Jml Total

    13 Dihitung 1 M3 Beton bertulang sloof 15 x 20 :

    1.0000 m3 Beton K 225

    173.2849 kg Besi

    13.3320 m2 Bekisting

    Jml Total

    14 Dihitung 1 M3 Beton bertulang sloof 15 x 25 ( Asrama ) :

    1.0000 m3 Beton K 225

    144.9191 kg Besi

    13.3335 m2 Bekisting

    Jml Total

    15 Dihitung 1 M3 Beton bertulang sloof 20 x 40 ( Asrama ) :

    1.0000 m3 Beton K 225

    153.8700 kg Besi

    10.0000 m2 Bekisting

    Jml Total

    16 Dihitung 1 M3 Beton bertulang sloof 20 x 30 ( Aula ) :

    1.0000 m3 Beton K 225

    197.3039 kg Besi

    10.0002 m2 Bekisting

    Jml Total

    17 Dihitung 1 M3 Beton bertulang balok 20 x 40 B1 ( Aula ) :

    1.0000 m3 Beton K 225

    144.1000 kg Besi

    12.5000 m2 Bekisting

    Jml Total

    18 Dihitung 1 M3 Beton bertulang balok 20 x 30 B2 ( Aula ) :

    1.0000 m3 Beton K 225

  • 177.6702 kg Besi

    13.3336 m2 Bekisting

    Jml Total

    19 Dihitung 1 M3 Beton bertulang balok 15 x 25 B3 ( Aula ) :

    1.0000 m3 Beton K 225

    187.2023 kg Besi

    17.3336 m2 Bekisting

    Jml Total

    20 Dihitung 1 M3 Beton bertulang balok 15 x 20 B4 ( Aula ) :

    1.0000 m3 Beton K 225

    219.5311 kg Besi

    18.3332 m2 Bekisting

    Jml Total

    21 Dihitung 1 M3 Beton bertulang balok 30 x 70 B1 (Asrama ) :

    1.0000 m3 Beton K 225

    153.5364 kg Besi

    5.2382 m2 Bekisting

    Jml Total

    21 Dihitung 1 M3 Beton bertulang balok 25 x 50 B2 ( Asrama ) :

    1.0000 m3 Beton K 225

    198.1280 kg Besi

    10.0000 m2 Bekisting

    Jml Total

    22 Dihitung 1 M3 Beton bertulang balok 20 x 30 B3 ( Asrama ) :

    1.0000 m3 Beton K 225

    184.0703 kg Besi

    13.3336 m2 Bekisting

    Jml Total

    23 Dihitung 1 M3 Beton bertulang balok 15 x 25 B3 (Asrama) :

    1.0000 m3 Beton K 225

    153.3032 kg Besi

    17.3336 m2 Bekisting

    Jml Total

    24 Dihitung 1 M3 Beton bertulang balok 15 x 25 B4 (Asrama) :

    1.0000 m3 Beton K 225

    156.4393 kg Besi

    17.3336 m2 Bekisting

    Jml Total

    25 Dihitung 1 M3 Beton bertulang plat konsol penyangga talang t = 15 cm :

    1.0000 m3 Beton K 225

    21.068 kg Besi

    6.667 m2 Bekisting

    Jml Total

    26 Dihitung 1 M3 Beton bertulang ring balok 15 x 25 RB1 ( Asrama / Aula ) :

    1.0000 m3 Beton K 225

    144.9191 kg Besi

    13.3335 m2 Bekisting

    Jml Total

    27 Dihitung 1 M3 Beton bertulang ring balok 15 x 20 RB 2 ( Asrma ) :

    1.0000 m3 Beton K 225

    173.2849 kg Besi

    13.3332 m2 Bekisting

    Jml Total

    28 Dihitung 1 M3 Beton bertulang ring balok 15 x 25 RB3 ( Aula ) :

    1.0000 m3 Beton K 225

    144.9191 kg Besi

    13.3335 m2 Bekisting

    Jml Total

    29 Dihitung 1 M3 Beton bertulang kolom 30 x 50 K1 ( Asrama ) :

    1.0000 m3 Beton K 225

    149.3515 kg Besi

    10.6672 m2 Bekisting

    Jml Total

    30 Dihitung 1 M3 Beton bertulang kolom 30 x 30 K2 ( Asrama ) :

    1.0000 m3 Beton K 225

    106.9012 kg Besi

    13.3332 m2 Bekisting

  • Jml Total

    31 Dihitung 1 M3 Beton bertulang kolom 20 x 20 ( Asrama / Aula ) :

    1.0000 m3 Beton K 225

    135.8600 kg Besi

    20.0000 m2 Bekisting

    Jml Total

    32 Dihitung 1 M3 Beton bertulang kolom atas talang 15 x 30 ( Asrama ) :

    1.0000 m3 Beton K 225

    126.0032 kg Besi

    19.9998 m2 Bekisting

    Jml Total

    33 Dihitung 1 M3 Beton bertulang kolom 15 x 50 ( Asrama ) :

    1.0000 m3 Beton K 225

    79.2687 kg Besi

    17.3329 m2 Bekisting

    Jml Total

    33 Dihitung 1 M3 Beton bertulang kolom 30 x 70 K1 ( Aula ) :

    1.0000 m3 Beton K 225

    169.9082 kg Besi

    9.5240 m2 Bekisting

    Jml Total

    34 Dihitung 1 M3 Beton bertulang kolom 30 x 30 K2 ( Aula ) :

    1.0000 m3 Beton K 225

    157.8651 kg Besi

    13.3332 m2 Bekisting

    Jml Total

    35 Dihitung 1 M3 Beton bertulang balok tangga 15 x 25 ( Asrama ) :

    1.0000 m3 Beton K 225

    192.2264 kg Besi

    17.3336 m2 Bekisting

    Jml Total

    36 Dihitung 1 M3 Beton bertulang kolom 15 x 20 (Pos jaga ) :

    1.0000 m3 Beton K 225

    169.3550 kg Besi

    23.3331 m2 Bekisting

    Jml Total

    37 Dihitung 1 M3 Beton bertulang kuda-kuda 15 x 25 B3 ( Mushola ) :

    1.0000 m3 Beton K 225

    187.2023 kg Besi

    17.3336 m2 Bekisting

    Jml Total

    38 Dihitung 1 M3 Beton bertulang kolom 30 x 30 (Doorlupe ) :

    1.0000 m3 Beton K 225

    70.8615 kg Besi

    13.3332 m2 Bekisting

    Jml Total

    39 Dihitung 1 M3 Beton bertulang pedestal 30x40 ( Aula ) :

    1.0000 m3 Beton K 225

    52.4896 kg Besi

    5.8331 m2 Bekisting

    Jml Total

    40 Dihitung 1 M3 Beton bertulang pedestal 25x30 ( Asrama ) :

    1.0000 m3 Beton K 225

    76.1248 kg Besi

    7.3332 m2 Bekisting

    Jml Total

    41 Dihitung 1 Bh Pondasi foot plat 175x175 F1 ( Asrama ) :

    4.5938 m3 Galian tanah

    1.8375 m3 Urugan kembali

    0.3063 m3 Urugan pasir

    0.1531 m3 Beton K 100

    0.7656 m3 Beton K 225

    81.7020 kg Besi

    1.4000 m2 Bekisting

    Jml Total

    42 Dihitung 1 Bh Pondasi foot plat 100x100 F2 ( Asrama ) :

  • 1.0000 m3 Galian tanah

    0.4000 m3 Urugan kembali

    0.1000 m3 Urugan pasir

    0.0500 m3 Beton K 100

    0.2500 m3 Beton K 225

    32.7972 kg Besi

    0.8000 m2 Bekisting

    Jml Total

    43 Dihitung 1 Bh Pondasi foot plat 80x80 F2 ( Asrama ) :

    0.6400 m3 Galian tanah

    0.2560 m3 Urugan kembali

    0.0640 m3 Urugan pasir

    0.0320 m3 Beton K 100

    0.1600 m3 Beton K 225

    21.5100 kg Besi

    0.6400 m2 Bekisting

    Jml Total

    44 Dihitung 1 Bh Pondasi foot plat 120x120 F1 ( Aula ) :

    1.5840 m3 Galian tanah

    0.6336 m3 Urugan kembali

    0.0720 m3 Urugan pasir

    0.0720 m3 Beton K 100

    0.3600 m3 Beton K 225

    50.2048 kg Besi

    0.9600 m2 Bekisting

    Jml Total

    45 Dihitung 1 Bh Pondasi foot plat tangga 60x150 F3 ( Asrama ) :

    0.9750 m3 Galian tanah

    0.3900 m3 Urugan kembali

    0.0488 m3 Urugan pasir

    0.0488 m3 Beton K 100

    0.2438 m3 Beton K 225

    26.1280 kg Besi

    0.8600 m2 Bekisting

    Jml Total

    46 Dihitung 1 M3 Beton bertulang plat T = 10 cm

    1.0000 m3 Beton K 225

    62.000 kg Besi

    10.000 m2 Bekisting

    Jml Total

    47 Dihitung 1 M3 Beton bertulang plat lantai T = 12 cm

    1.0000 m3 Beton K 225

    92.996 kg Besi

    8.333 m2 Bekisting

    Jml Total

    48 Dihitung 1 M3 Beton bertulang plat tangga T = 12 cm

    1.000 m3 Beton K 225

    189.137 kg Besi

    8.333 m2 Bekisting

    Jml Total

    49 Dihitung 1 M3 Beton bertulang plat T = 8 cm

    1.0000 m3 Beton K 225

    49.1250 kg Besi

    12.500 m2 Bekisting

    Jml Total

    50 Dihitung 1 M3 Beton bertulang plat T = 6 cm

    1.0000 m3 Beton K 225

    65.2380 kg Besi

    16.667 m2 Bekisting

    Jml Total

    51 Dihitung 1 Bh Beton bertulang poor mini pail 60x120 t= 40 cm (Aula)

    0.288 m3 Beton K 300

    48.980 kg Besi

    1.440 m2 Bekisting

    Jml Total

    F. PEKERJAAN KAYU ATAP

    1 03-3434-2008 6.15 1 M3 Memasang konstruksi gording kayu kelas II

  • 1.1000 m3 Kayu kruing balok

    15.0000 kg Besi strip

    3.0000 kg Paku biasa 2"-5"

    2.4000 oh Pekerja

    7.2000 oh Tukang kayu

    0.7200 oh Kepala tukang

    0.1200 oh Mandor

    2 03-3434-2008 6,15a 1 M3 Memasang konstruksi nok / jurai kayu kelas II

    1.1000 m3 Kayu kruing balok

    15.0000 kg Besi strip

    3.0000 kg Paku biasa 2"-5"

    2.4000 oh Pekerja

    7.2000 oh Tukang kayu

    0.7200 oh Kepala tukang

    0.1200 oh Mandor

    3 03-3434-2008 6.16 1 M2 Memasang rangka atap genteng glazur, kayu kelas II

    0.0140 m3 Kayu kelas II kruing (5x7) cm

    0.0080 m3 Reng bengkirai (3x5) cm

    0.2500 kg Paku biasa 2"-5"

    0.1000 oh Pekerja

    0.1000 oh Tukang kayu

    0.0100 oh Kepala tukang

    0.0050 oh Mandor

    4 03-3434-2008 6.22 1 M' Memasang listplank Uk ( 3x30 ) cm kayu kelas II

    0.0110 m3 Kayu kelas II bengkirai papan

    0.0500 kg Paku biasa 2"-5"

    0.1000 oh Pekerja

    0.2000 oh Tukang kayu

    0.0200 oh Kepala tukang

    0.0050 oh Mandor

    5 3434-2008 1 M' Memasang reiter kayu kruing ( 2x20 ) cm

    0.004 m3 Kayu kruing

    0.040 kg Paku biasa 2"-5"

    0.175 oh Pekerja

    0.175 oh Tukang kayu

    0.010 oh Kepala tukang

    0.004 oh Mandor

    G. PEKERJAAN PENUTUP ATAP

    1 03-3436-2002 6.3 1 M2 Pasang atap genteng glazur

    18.0000 bh Genteng glazur

    0.1500 oh Pekerja

    0.0600 oh Tukang kayu

    0.0060 oh Kepala tukang

    0.0080 oh Mandor

    2 03-3436-2002 6.5 1 M' Pasang bubungan genteng glazur

    4.0000 bh Bubungan genteng glazur

    8.0000 kg Portland Cemen ( PC )

    0.0320 m3 Pasir pasang

    0.4000 oh Pekerja

    0.2000 oh Tukang kayu

    0.0200 oh Kepala tukang

    0.0020 oh Mandor

    3 03-3436-2002 6.42 1 M2 Pasang alluminium foil / sisalation

    1.0500 m2 Alluminium foil

    0.1500 oh Pekerja

    0.0500 oh Tukang kayu

    0.0050 oh Kepala tukang

    0.1200 oh Mandor

    4 03-7393-2008 6.18 1 M' Pasang talang jurai seng BJLS 28 lebat 90 cm

  • 1.0500 lbr Seng plat

    0.0150 kg Paku biasa 1"-2,5"

    0.0190 m3 Papan kelas II

    0.2000 oh Pekerja

    0.4000 oh Tukang kayu

    0.0250 oh Kepala tukang

    0.0100 oh Mandor

    H. PEKERJAAN LANGIT-LANGIT

    1 03-2839-2008 6.7 1 M2 Plafond gypsum board (120x240) tebal 9 mm:

    0.3640 lbr Gypsum Board 9 mm

    1.0250 btg Rangka hollow 2x4 cm t = 0,35 mm

    3.0000 bh Stifenner

    0.1100 kg Paku keling/sekrup

    4.0000 bh Penggantung dan Ramzet

    0.1000 oh Pekerja

    0.0500 oh Tukang kayu

    0.0050 oh Kepala tukang

    0.0050 oh Mandor

    2 03-2839-2008 6.7 1 M2 Plafond kalsiboard (120x240) tebal 4 mm:

    0.3640 lbr Kalsiboar 4 mm

    1.0250 btg Rangka hollow 2x4 cm

    3.0000 bh Stifenner

    0.1100 kg Paku keling/sekrup

    4.0000 bh Penggantung dan Ramzet

    0.1000 oh Pekerja

    0.0500 oh Tukang kayu

    0.0050 oh Kepala tukang

    0.0050 oh Mandor

    3 Hitung 1 M2 Kompon plat

    0.0784 zak Semen gypsum

    0.1500 lbr Amplas

    0.1600 oh Pekerja

    0.0800 oh Tukang batu

    0.0080 oh Kepala tukang

    0.0080 oh Mandor

    4 03-2839-2008 6.9 1m' Pasang list plafond gypsum

    1.0000 m' m' List Profil Gypsum

    0.6500 kg kg Compon

    1.0000 ls Upah

    I. PEKERJAAN KAYU KUSEN

    1 03-3434-2008 6.8 1 M2 Daun pintu dobel teakwood 9mm lapis HPL rangka ky bengkirai :

    0.0250 m3 Kayu bengkirai

    0.0300 kg kg paku

    0.5000 kg Lem kayu

    2.0000 m2 HPL

    2.0000 m2 Teakwood 9 mm

    0.6000 oh Pekerja

    2.0000 oh Tukang kayu

    0.2000 oh Kepala tukang

    0.0400 oh Mandor

    J. PEKERJAAN BESI

    1 03-7393-2008 6.2 1 Kg Pasang rangka kuda-kuda baja IWF :

    1.1500 kg Besi IWF

    0.0600 oh Pekerja

    0.0600 oh Tukang besi

    0.0060 oh Kepala tukang

    0.0030 oh Mandor

    2 03-7393-2008 6.2 1 m2 Pasang mainan listplank hollow 4x4 ( Aula ) :

    9.1000 m' pipa hollow kotak 4x4 t = 2 mm

    12.0000 tk las

  • 0.0300 oh Pekerja

    0.0300 oh Tukang besi

    0.0030 oh Kepala tukang

    0.0015 oh Mandor

    K. PEKERJAAN KUSEN ALLUMINIUM

    1 03-7393-2008 6.11 1 Unit Kusen alumunium Type J1 ( Asrama )

    125.880 m' Rangka kusen alumunium 4" (brown)

    64.200 m' Frame daun jendela / BV

    131.640 m' Tube sealant

    65.820 m' Silicon gel

    180.000 bh Sekrup fixer

    1.000 unit Upah

    2 03-7393-2008 6.11 1 Unit Kusen alluminium Type J2 ( Asrama )

    83.920 m' Rangka kusen alumunium 4" (brown)

    42.800 m' Frame daun bv

    87.760 m' Tube sealant

    43.880 m' Silicon gel

    120.000 bh Sekrup fixer

    1.000 unit Upah

    3 03-7393-2008 6.11 1 Unit Kusen alluminium Type J3 ( Asrama )

    48.320 m' Rangka kusen alumunium 4" (brown)

    25.120 m' Frame daun jendela

    17.120 m' Frame daun bv

    37.120 m' Tube sealant

    18.560 m' Silicon gel

    112.000 bh Sekrup fixer

    1.000 unit Upah

    4 03-7393-2008 6.11 1 Unit Kusen alluminium Type J4 ( Asrama )

    12.480 m' Rangka kusen alumunium 4" (brown)

    6.480 m' Frame daun jendela

    4.480 m' Frame daun bv

    9.680 m' Tube sealant

    4.840 m' Silicon gel

    28.000 bh Sekrup fixer

    1.000 unit Upah

    5 03-7393-2008 6.11 1 Unit Kusen alluminium Type J5 tampak depan ( Asrama )

    79.400 m' Rangka kusen allumunium 4" (brown)

    184.600 m' Tube sealant

    92.300 m' Silicon gel

    76.000 bh Sekrup fixer

    1.000 unit Upah

    6 03-7393-2008 6.11 1 Unit Kusen alluminium Type BV ( Asrama )

    4.080 m' Rangka kusen allumunium 4" (brown)

    4.000 m' Frame daun bv

    4.280 m' Tube sealant

    2.140 m' Silicon gel

    12.000 bh Sekrup fixer

    1.000 unit Upah

    7 03-7393-2008 6.11 1 Unit Kusen alluminium Type P2 ( Asrama )

    10.600 m' Rangka kusen alumunium 4" (brown)

    12.800 m' Rangka daun pintu

    4.800 m' Frame daun jendela / bv

    15.920 m' Tube sealant

    7.960 m' Silicon gel

    21.000 bh Sekrup fixer

    1.000 unit Upah

    8 03-7393-2008 6.11 1 Unit Kusen alluminium Type P3 ( Asrama )

  • 8.270 m' Rangka kusen alumunium 4" (brown)

    2.540 m' Rangka daun bv

    2.240 m' Tube sealant

    1.120 m' Silicon gel

    14.000 bh Sekrup fixer

    1.000 unit Upah

    9 03-7393-2008 6.11 1 Unit Kusen alluminium Type PJ1 ( Aula )

    21.200 m' Rangka kusen alumunium 4" (brown)

    11.600 m' Rangka daun pintu

    9.520 m' Rangka daun juendela / bv

    48.880 m' Tube sealant

    24.440 m' Silicon gel

    36.000 bh Sekrup fixer

    1.000 unit Upah

    10 03-7393-2008 6.11 1 Unit Kusen alluminium Type PJ2 ( Aula )

    17.250 m' Rangka kusen alumunium 4" (brown)

    14.200 m' Rangka daun juendela / bv

    22.200 m' Tube sealant

    11.100 m' Silicon gel

    33.000 bh Sekrup fixer

    1.000 unit Upah

    11 03-7393-2008 6.11 1 Unit Kusen alluminium Type PBV ( Aula )

    13.300 m' Rangka kusen alumunium 4" (brown)

    7.000 m' Rangka daun juendela / bv

    10.360 m' Tube sealant

    5.180 m' Silicon gel

    22.000 bh Sekrup fixer

    1.000 unit Upah

    12 03-7393-2008 6.11 1 Unit Kusen alluminium Type J1 ( Aula )

    11.140 m' Rangka kusen alumunium 4" (brown)

    11.600 m' Rangka daun juendela / bv

    18.240 m' Tube sealant

    9.120 m' Silicon gel

    24.000 bh Sekrup fixer

    1.000 unit Upah

    13 03-7393-2008 6.11 1 Unit Kusen alluminium Type BV ( Aula )

    4.520 m' Rangka kusen alumunium 4" (brown)

    4.400 m' Rangka daun juendela / bv

    6.320 m' Tube sealant

    3.160 m' Silicon gel

    8.000 bh Sekrup fixer

    1.000 unit Upah

    14 03-7393-2008 6.11 1 Unit Kusen alluminium Type P2 ( Aula )

    11.190 m' Rangka kusen allumunium 4" (brown)

    11.000 m' Rangka daun pintu

    29.800 m' Tube sealant

    14.900 m' Silicon gel

    26.000 bh Sekrup fixer

    1.000 unit Upah

    15 03-7393-2008 6.11 1 Unit Kusen alluminium Type P3 ( Aula )

    11.200 m' Rangka kusen allumunium 4" (brown)

    5.120 m' Rangka daun juendela / bv

    8.080 m' Tube sealant

    4.040 m' Silicon gel

    19.000 bh Sekrup fixer

    1.000 unit Upah

    16 03-7393-2008 6.11 1 Unit Kusen alluminium Type P4 ( Aula )

    7.900 m' Rangka kusen allumunium 4" (brown)

    2.400 m' Rangka daun juendela / bv

  • 3.720 m' Tube sealant

    1.860 m' Silicon gel

    16.000 bh Sekrup fixer

    1.000 unit Upah

    17 03-7393-2008 6.11 1 Unit Kusen alluminium Type BV atas ( Aula )

    3.600 m' Rangka kusen allumunium 4" (brown)

    0.600 m2 Kaca talip bening 5 mm

    3.200 m' Tube sealant

    1.600 m' Silicon gel

    12.000 bh Sekrup fixer

    1.000 unit Upah

    18 03-7393-2008 6.11 1 Unit Kusen alluminium Type P1 ( mushola )

    6.110 m' Rangka kusen allumunium 4" (brown)

    13.860 m' Rangka daun pintu aluminium brown

    21.360 m' Tube sealant

    10.680 m' Silicon gel

    12.000 bh Sekrup fixer

    1.000 unit Upah

    19 03-7393-2008 6.11 1 Unit Kusen alluminium Type J1 ( mushola )

    11.450 m' Rangka kusen allumunium 4" (brown)

    7.920 m' Rangka daun juendela aluminium brown

    24.480 m' Tube sealant

    12.240 m' Silicon gel

    16.000 bh Sekrup fixer

    1.000 unit Upah

    20 03-7393-2008 6.11 1 Unit Kusen alluminium Type J2 ( mushola )

    10.160 m' Rangka kusen allumunium 4" (brown)

    12.930 m' Rangka daun juendela aluminium brown

    26.216 m' Tube sealant

    13.108 m' Silicon gel

    18.000 bh Sekrup fixer

    1.000 unit Upah

    21 03-7393-2008 6.11 1 Unit Kusen alluminium Type BV ( mushola )

    2.680 m' Rangka kusen allumunium 4" (brown)

    2.200 m' Rangka daun juendela aluminium brown

    2.800 m' Tube sealant

    1.400 m' Silicon gel

    8.000 bh Sekrup fixer

    1.000 unit Upah

    22 03-7393-2008 6.11 1 Unit Kusen alluminium Type P1 ( pos jaga )

    5.220 m' Rangka kusen allumunium 4" (brown)

    6.580 m' Rangka daun pintu aluminium brown

    11.600 m' Tube sealant

    5.800 m' Silicon gel

    10.000 bh Sekrup fixer

    1.000 unit Upah

    23 03-7393-2008 6.11 1 Unit Kusen alluminium Type J1 ( pos jaga )

    20.500 m' Rangka kusen allumunium 4" (brown)

    27.700 m' Tube sealant

    13.850 m' Silicon gel

    26.000 bh Sekrup fixer

    1.000 unit Upah

    L. PEKERJAAN CAT

    1 03-24 6.1 1 M2 Mengikis / Mengerok Permukaan Cat Tembok Lama :

    0.0500 kg Soda api

    0.1500 oh Pekerja

    0.0025 oh Mandor

    2 03-24 6.8 1 M2 Pengecatan kayu baru ( 1 lap. Plamir ) 1 lap. Cat dasar & 2 lap cat penutup :

  • 0.2000 kg Cat meni

    0.1500 kg Plamur

    0.1700 kg Cat dasar

    0.2600 kg Cat penutup 2 kali

    0.0700 oh Pekerja

    0.0090 oh Tukang cat

    0.0060 oh Kepala tukang

    0.0025 oh Mandor

    3 03-24 6.14 1 M2 Pengecatan tembok baru ( 1 lap. Plamir ) 1 lap. Cat dasar & 2 lap cat penutup :

    0.1000 kg Plamur

    0.1000 kg Cat dasar

    0.2600 kg Cat penutup 2 kali

    0.2600 lbr Amplas

    0.0200 oh Pekerja

    0.0630 oh Tukang cat

    0.0063 oh Kepala tukang

    0.0025 oh Mandor

    4 03-24 6.15 1 M2 Pengecatan tembok lama ( 1 lap. Plamir ) 1 lap. Cat dasar & 2 lap cat penutup :

    0.1000 kg Cat dasar

    0.1800 kg Cat penutup 2 kali

    0.2600 lbr Amplas

    0.0280 oh Pekerja

    0.0420 oh Tukang cat

    0.0042 oh Kepala tukang

    0.0025 oh Mandor

    M. PEKERJAAN KACA

    1 6.17 1 M2 Memasang kaca bening 5 mm :

    1.1000 m2 Kaca bening 5 mm

    0.0150 oh Pekerja

    0.1500 oh Tukang

    0.0150 oh Kepala tukang

    0.0008 oh Mandor

    2 6,17a 1 M2 Memasang kaca bening 12 mm :

    1.1000 m2 Kaca bening 12 mm

    0.0150 oh Pekerja

    0.1500 oh Tukang

    0.0150 oh Kepala tukang

    0.0008 oh Mandor

    N. PEKERJAAN SANITASI

    1 6.25 1 M' Pasang pipa GIP 1 1/2" :

    1.2000 m' Pipa GIP 1 1/2"

    0.3500 ls Perlengkapan 35 % harga pipa

    0.1080 oh Pekerja

    0.1800 oh Tukang

    0.0180 oh Kepala tukang

    0.0540 oh Mandor

    2 6.25 1 M' Pasang pipa PVC AW 1/2" :

    1.2000 m' Pipa PVC

    0.3500 ls Perlengkapan 35 % harga pipa

    0.0360 oh Pekerja

    0.0600 oh Tukang

    0.0060 oh Kepala tukang

    0.0018 oh Mandor

    3 1 M' Pasang pipa PVC 3/4" :

    1.2000 m' Pipa PVC

    0.3500 ls Perlengkapan 35 % harga pipa

    0.0360 oh Pekerja

    0.0600 oh Tukang

    0.0060 oh Kepala tukang

    0.0018 oh Mandor

  • 4 1 M' Pasang pipa PVC 1" :

    1.2000 m' Pipa PVC

    0.3500 ls Perlengkapan 35 % harga pipa

    0.0360 oh Pekerja

    0.0600 oh Tukang

    0.0060 oh Kepala tukang

    0.0018 oh Mandor

    5 1 M' Pasang pipa PVC 1 1/2" :

    1.2000 m' Pipa PVC

    0.3500 ls Perlengkapan 35 % harga pipa

    0.0360 oh Pekerja

    0.0600 oh Tukang

    0.0060 oh Kepala tukang

    0.0018 oh Mandor

    6 6.29 1 M' Pasang pipa PVC 2" :

    1.2000 m' Pipa PVC

    0.3500 ls Perlengkapan 35 % harga pipa

    0.0540 oh Pekerja

    0.0900 oh Tukang

    0.0090 oh Kepala tukang

    0.0027 oh Mandor

    7 6.31 1 M' Pasang pipa PVC 3" :

    1.2000 m' Pipa PVC

    0.3500 ls Perlengkapan 35 % harga pipa

    0.0810 oh Pekerja

    0.1350 oh Tukang

    0.0140 oh Kepala tukang

    0.0041 oh Mandor

    8 1 M' Pasang pipa PVC 4" :

    1.2000 m' Pipa PVC

    0.3500 ls Perlengkapan 35 % harga pipa

    0.0810 oh Pekerja

    0.1350 oh Tukang

    0.0140 oh Kepala tukang

    0.0041 oh Mandor

    9 6.1 1 Bh Memasang Klosed duduk monoblok ( TOTO ) :

    1.0000 bh Klosed duduk

    0.0600 ls Perlengkapan 6 % harga pipa

    3.3000 oh Pekerja

    1.1000 oh Tukang

    0.0010 oh Kepala tukang

    0.1600 oh Mandor

    10 6.5 1 Bh Memasang Wastafel :

    1.0000 bh Wastafel meja oval

    0.3000 ls Perlengkapan 30 % harga pipa

    6.0000 kg Portland cement

    0.0100 m3 Pasir pasang

    1.2000 oh Pekerja

    0.1450 oh Tukang

    0.1500 oh Kepala tukang

    0.1000 oh Mandor

    11 6.5 1 Bh Memasang Shower lengkap :

    1.0000 bh Shower

    0.3000 ls Perlengkapan 30 % harga pipa

    6.0000 kg Portland cement

    0.0100 m3 Pasir pasang

    1.2000 oh Pekerja

    0.1450 oh Tukang

    0.1500 oh Kepala tukang

  • 0.1000 oh Mandor

    12 6.36 1 Bh Memasang Floor Drain

    1.0000 bh Floor Drain

    0.0100 oh Pekerja

    0.1000 oh Tukang

    0.0100 oh Kepala tukang

    0.0050 oh Mandor

    13 6.35 1 Bh Memasang Kran dia 3/4" dan 1/2"

    1.0000 bh Kran air

    1.0000 set Seal tape

    0.0100 oh Pekerja

    0.1000 oh Tukang

    0.0100 oh Kepala tukang

    0.0050 oh Mandor

    14 1 M2 Pasang paving blok Holland t = 6 cm : K 300

    45.0000 bh paving holland t = 6 cm

    0.0800 m3 Pasir pasang

    0.4000 oh pekerja

    0.2000 oh tukang batu

    0.0200 oh kepala tukang

    0.0200 oh mandor

    15 1 M' Pasang kansteen beton

    2.0000 bh kansteen 10x20x50

    0.0500 m3 Pasir pasang

    0.1000 oh pekerja

    0.0500 oh kepala tukang

    0.0100 oh mandor

    16 1 M' Saluran U 30 :

    0.4000 m2 pas. batu bata 1:5

    0.2400 m2 plesteran 1:5

    0.0100 m3 pasir urug

    0.0400 m3 galian tanah

    1.0000 m' buis beton U 30

    17 1 BH Bak kontrol U 30 :

    0.3600 m2 m2 pas.batu bata 1:5

    0.0100 m3 m3 pas. koral

    0.0045 m3 m3 pasir urug

    0.5040 m3 m2 plester 1:5

    0.0429 m3 m3 galian tanah

    18 1 M' Saluran O 30 :

    0.4000 m2 pas. batu bata 1:5

    0.0100 m3 pasir urug

    0.0400 m3 galian tanah

    1.0000 m' buis beton 0 30

    19 1 M' Pasang grill penutup saluran

    10.3675 kg besi siku 50.50.5

    6.3200 kg besi dia 16 mm

    15.0000 ttk las

    0.4000 oh pekerja

    0.2000 oh tukang

    0.0200 oh kepala tukang

    0.0200 oh mandor

    20 1 M2 Pasang atap Pollycarbonate datar

    1.2000 m2 m2 pollycarbonat datar

    0.4700 kg kg angkur baut

    0.2300 oh tukang

    0.0230 oh kepala tukang

    0.0230 oh mandor

  • 21 1 Unit Memasang rangka atap doorloop rangka pipa hitam

    11.6 m' kuda-kuda pipa hitam 2"

    75.0000 m' gording pipa hitam 1"

    15.3600 kg plat landas 6 mm

    14.9760 kg angkur baut 16 mm

    1.0000 ls las

    0.0520 oh mandor

    0.1050 oh kep tukang besi

    1.0500 oh tukang besi

    1.0500 oh pekerja

    22 1 Unit Memasang resapan dari bis beton + penutup

    1.500 m' galian tanah

    1.0000 bh Bis beton 80 cm

    0.0500 m3 Penutup dari plat beton t = 5 cm

    1.0000 bh besi pengan tutup