103.211.51.154103.211.51.154/storage/data/c2_implementation... · ,., ....... .....
TRANSCRIPT
,., .......
.. "·'"
I
PT. PERENTJANA DJAJA in subtonsultancy with ~ Yongma Engineering Co. Ltd and e'PT. Epadaston Pennata Engineering Consultant CTC Office: Jl. Ciniru VII No. 25, Kebayoran Baru,Jakarta Selatan, 12180
Phone /Fax: {021) 7229823
Cc: 1. Direktur Jenderal Bina Marga 2. lnspektorat Jenderal, Kementerian PU-PERA 3. Direktur Transportasi - Bappenas 4. Dir-ektur Pengelolaan Kas Negara (PKN), Kementerian Keuangan 5. Direktur Pengembangan Jaringan Jalan, Dit.Jen Bina Marga 6. Direktur Preservasi Jalan, Dit.Jen Bina Marga 7. Biro Perencanaan & KLN, Kementrian PU-PERA 8. Kepala Balai Besar Pelaksanaan Jalan Nasional 11 Medan 9. Kepala Balai Pelaksanaan Jalan Nasional Ill Padang 10. Kepala Balai Pelaksanaan Jalan Nasiona~ XIX Lampung 11. Kepala Balai Pelaksanaan Jalan Nasional XIV Palu 12. Kasubdit Keterpaduan Perencanaan & Sistem Jaringan, DPJJ - DJBM 13. Ketua Pelaksana Harian PIU WINRIP 14. Kepala Satker Pembinaan Administrasi dan Pelaksanaan Pengendalian PHLN 15. PT. Perentjana Djaja 16. Yonqrna Engineering Co, Ltd 17. PT. Epadascon Permata Engineering Consultant 18. File
I I.
Should you have any comment or additional information that need to be incorporated in the Report, please feel free to get in touch with us.
This Report is reproduced in nineteen (18) copies for distribution to all concerned authorities.
In compliance with the Tenns of Reference of our Consultancy Contract, we submit herewith the Monthly Progress Report No.85 covering the month of January 2020.
Dear Sir,
Subject : Submission of January 2020 Monthly Progress Report No.85; WINRIP Loan IBRD No.8043-ID
Attention: Hengki Hemawan, ST, MT Officer In Charge PMU WINRIP
Directorate General of Highways, MPWH Jl. Patimura 20 Kebayoran Baru Jakarta Selatan Indonesia
Jakarta, February 14, 2020 : 03_02/LHW/O/M-01.2020 Our Ref.No.
Perentjana Djaja
MINISTRY OF PUBUC WORKS & HOUSING .DIRECTORATE GENERAL OF HIGHWAYS
DIRECTORATE OF ROAD NETWORK DEVELOPMENT Core Team Consultant for
Western Indonesia National Roads Improvement Project (WINRIP) IBRD Loan No. 8043-ID
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Table of Contents
1 EXECUTIVE SUMMARY............................................................................................................ 1-1
1.1 Current Implementation Situation.......................................................................................................1-1
1.2 Disbursement..........................................................................................................................................1-5
1.3 World Bank Implementation Review Mission and Site Visit...............................................................1-5
1.4 Procurement of Civil Works Contract Under Category 1 of the Loan Agreement...........................1-6
2 PROJECT DESCRIPTION ........................................................................................................... 2-1
2.1 Background.............................................................................................................................................2-1
2.2 Project Development.............................................................................................................................2-1
2.3 Project Objective ......................................................................................................................................2-8
3 CONSULTANCY SERVICES ........................................................................................................... 3-1
3.1 CTC Consultants ......................................................................................................................................3-1
3.1.1 Scope of Services ........................................................................................................... 3-1
3.1.2 CTC Manning ................................................................................................................. 3-2
3.1.3 CTC Contract.................................................................................................................. 3-43.3 Technical Assistance for Development of Slope Stabilization, Design and Management............3-8
4 CIVIL WORKS............................................................................................................................ 4-1
4.1 Detailed Design Preparation...................................................................................................................4-1
4.2 Procurements ............................................................................................................................................4-1
4.3 Civil Works Implementation ...................................................................................................................4-1
4.4 Civil Works Progress.................................................................................................................................4-3
4.5 Quality Assurance.....................................................................................................................................4-7
4.6 Environmental and Social Considerations...........................................................................................4-10
4.6.1 Current Overall Situation............................................................................................ 4-10
4.6.2 Environmental and Social Issues................................................................................ 4-124.7 Anti Corruption Issues..........................................................................................................................4-18
4.7.1 Anti‐Corruption Action Plan (ACAP) ............................................................................ 4-28
4.7.2 Community Representative Observers (CRO)............................................................ 4-28
4.7.3 Publication / Disclosure ............................................................................................... 4-29
4.7.4 Complaints Handling Mechanism (CHS) ..................................................................... 4-30
4.7.5 Third Party Monitoring (TPM)...................................................................................... 4-315 FINANCIAL & MANAGEMENT INFORMATION SYSTEMS.......................................................... 5-1
5.1 Draw‐Downs and Future Costs..............................................................................................................5-1
5.2 Disbursement..........................................................................................................................................5-1
5.3. Management Information System ......................................................................................................5-1
6 PROJECT PERFORMANCE ........................................................................................................ 6-1
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
6.1 World Bank and GOI Compliance........................................................................................................6-1
6.1.1 World Bank Missions .................................................................................................... 6-1
6.1.2 Agreed Key Actions and during the Coordination Meeting ...................................... 6-16.2 Implementation Support Components...............................................................................................6-3
6.2.1 Core Team Consultant (CTC)........................................................................................ 6-3
6.2.2 Design and Supervision Consultant (DSC)................................................................... 6-3
6.2.3 Study on Development of Slope Stabilization Design and Management................ 6-46.3 Anti‐Corruption Issues .............................................................................................................................6-5
6.3.1 Anti-Corruption Action Plan (ACAP) ............................................................................ 6-5
6.3.2 Community Representative Observers (CRO)............................................................ 6-6
6.3.3 Third Party Monitoring (TPM)...................................................................................... 6-6
6.3.4 Complaint Handling System (CHS)............................................................................... 6-6
6.3.5. Public Disclosures / Publication.................................................................................... 6-76.4 Road Safety Audit ..................................................................................................................................6-8
6.4.1 Activities during This Month (March 2019) ................................................................ 6-86.5 Management Information System ......................................................................................................6-8
6.6 Quality Assurance................................................................................................................................6-11
6.7 Project Risks and Mitigation Measures............................................................................................6-11
6.7.1 Risks Related to Delays ............................................................................................... 6-11
6.7.2 Financial Risks.............................................................................................................. 6-11
6.7.3 Risks Related to Quality .............................................................................................. 6-116.8 Training to Support Project Implementation......................................................................................6-11
7 CURRENT ISSUES AND FOLLOW-UP ACTIONS ......................................................................... 7-1
8 CORRESPONDENCES ............................................................................................................... 8-1
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
ABBREVIATIONS AND ACRONYMS
ACAP : Anti Corruption Action PlanAER : Application Evaluation ReportAIP : Australian Indonesia PartnershipAMDAL : Environmental Management (Analisis Mengenai Dampak
Lingkungan)ANDAS : Analisis Dampak SosialAWPs : Annual Work ProgramsBalai : Regional Office for National Roads ImplementationBAPPENAS : Badan Perencanaan Pembangunan Nasional (National
Development Planning Agency of GOI)Bappedalda : Regional Environmental Impact AgenciesBBPJN : Balai Besar Pelaksanaan Jalan Nasional (Regional Office for
National Roads Implementation)BER : Bid Evaluation Report
BLH : Badan Lingkungan Hidup
BPK : Badan Pemeriksaan Keuangan (Audit Board of the Government
of Indonesia)
CAD : Computer Aided Design
CHS : Complaint Handling System
CTC : Core Team Consultant
CHU : Complaint Handling Unit
CRO : Community Representative Observer ( = WPM)
DIA : Directorate of Implementing Affairs
DRND : Directorate of Road Network Development
DGH : Directorate General of Highways
DMS : Document Management System
DRP : Directorate of Road Preservation
DMS : Document Management System
DSC : Design and Supervision Consultants
EA : Executing Agency
EINRIP : Eastern Indonesian National Roads Improvement Project
EIRTP-1 : Eastern Indonesia Regional Transport Project First Project
ESAMP : Environmental and Social Assessment Plan
ESS : Environmental and Social Safeguards
FMIS : Financial Management Information System
FIDIC : Federation Internationale des Ingenieur Conseils
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
FMIS : Financial Management Information System
GIS : Geographic Information System
GOI : Government of Indonesia
IA : Implementation Agency
IBRD : International Bank for Reconstruction and Development
IFR : Interim Financial Report
IRMS : Integrated Road Management System
Kabupaten : Regency
KPIs : Key Performance Indicators
KPPN : Kantor Pelayanan Perbendaharaan Negara (Indonesian: State
Treasury Service Office)
LAN : Local Area Network
LARAP : Land Acquisition and Resettlement Plan (Rencana Tindak
Pengadaan Tanah dan Pemukiman Kembali)
MIS : Management Information System
MOF : Ministry of Finance
MPW H : Ministry of Public Work & Housing
MPRs : Monthly Progress Reports
P2JN : Perencanaan Pengawasan Jalan dan Jembatan Nasional
PDF : Portable Document Format
PIU : Project Implementation Unit
PAPs : Project Affected Peoples
PMM : Project Management Manual
PMU : Project Management Unit (WINRIP)
POKJA : Procurement Committes
PPC : Project Preparation Consultants
PP3 : Pemantau Pihak ke 3
PPK : Sub Project Manager
PPR : Project Progress Report
QPRs : Quarterly Progress Reports
RKL/RPL : Rencana Pengelolaan/Pemantauan Lingkungan
RS : Road Safety
Satker : Satuan Kerja (Work Unit for Road Project Implementation)
SPPL : Surat Pernyataan Pengelolaan Lingkungan
SRIP : Strategic Road Infrastructure Project
TA : Technical Assistance
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
TOR : Terms of Reference
UKL/UPL : Upaya Pengelolaan Lingkungan / Upaya Pemantauan Lingkungan
(Site Specific Environmental and Monitoring Plan)
WINRIP : Western Indonesia Roads Improvement Project
WB : World Bank
WP : Work Program
WPs : Works Programs
WPM : Wakil Pengamat dari Masyarakat (or Community Representative
Observer / CRO)
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
APPENDICES
Appendix A : Overall Loan Progress
Appendix B : Road Safety Audit Progress
Appendix C : Financial Progress
Appendix D : Quality Assurance Progress
Appendix E : Environmental and Social Progress
Appendix F : Procurement Plan and Progress
Appendix G : WINRIP Website Progress
Appendix H : ACAP Training/Dissemination Progress
Appendix I : Performance Indicator
Appendix J : Correspondences
ANNEXESAnnex P-5A : Package No. 5A
Annex RR-01 : Package No. RR01 Tompe-Palu-Surumana
Annex RR-02 : Package No. RR02 Birobuli-Palolo; Palupi-Simoro & Akses Huntap
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
1 - 1
1 EXECUTIVE SUMMARY
1.1 Current Implementation SituationCivil Works
Implementation of the WINRIP Project is scheduled to be implemented into three (3) Annual WorkPrograms (AWP’s). The implementation starts with the preparation of tender documents (detaileddesign drawings including associated bidding documents), tendering stage (procurement of works)and the actual civil works construction implementation.
The original implementation schedules of the three (3) Annual Work Programs (AWPs) arescheduled in three (3) phases namely; AWP-1 to start in mid-2011 and to be completed on the lastquarter of 2014, AWP-2 is expected to begin in mid 2012 with target date of completion by mid-2016 and AWP-3 is expected to start during the early part of 2013 and to be completed during themiddle part of 2017.
However, due to some unavoidable circumstances the original implementation schedules did notmaterialize.
All procurement processes for the sub-projects in WINRIP have been completed, including for 2additional civil works sub-projects in Central Sulawesi.
In December 2018, the WINRIP was restructured to complete the works under packages 5A and21A and to activate the disaster risk response component. This will enable the rehabilitation andreconstruction of selected sections of national and sub-national roads in Central Sulawesi damagedby devastating earthquakes and tsunami in September 2018. The sub-projects in Central Sulawesiconsist of 3 (three) packages namely RR1, RR2 and Construction Supervision Consultant (CSC) whichcommenced in October and December 2019 respectively.
Based on the present status of the program implementation progress, a revised implementationschedule, the “Project Implementation Timeline” (as shown on Page 1-3) is to be implemented inorder to accommodate the originally delayed schedule into the remaining time frame of theWINRIP Program until the expiry date of the loan agreement by the end of February 2021. Shownon Page 1-4 is the current actual status of the implementation relative to the “ProjectImplementation Timeline”.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
1 - 2
Implementation Status as of January 31, 2020
PackPackage Name
Contract Under Termination Under DefectLiability Period
FHONo. Sign Construct
1 Krui - Biha √ Completed √
2 Padang Sawah - Sp.Empat √ Completed √
3 Manggopoh - Padang Sawah √ Completed √
4 Ipuh - Bantal √ Completed √
5 Sp. Rampa - Poriaha √ Completed √6 Ps. Pedati - Kerkap √ Completed √
7 Indrapura - Tapan √ Completed √8 Bts.Pariaman - Manggopoh √ Completed √
11 Bantal - Mukomuko √ Completed √
12 Kambang - Indrapura √ Completed √13 Sp. Rukis - Tj.Kemuning √ Completed √14 Painan - Kambang √ Completed √15 Sibolga - Bts.Tap Sel √ Completed √16 Seblat - Ipuh √ Completed √17 Sp.Gn.Kemala - Pg.Tampak √ Completed √
19 Lais - Bintunan √ Completed √
20 Lubuk Alung - Sicincin √ Completed √21 Lubuk Alung - Kuraitaji √ √
21A Lubuk Alung - Kuraitaji √ Completed √
5A Penanganan Lereng Ruas Rampa -Poriaha √ √
RR-01 Rehabilitation and ReconstructionTompe – Dalam Kota Palu - Surumana √ √
RR-02Rehabilitation and ReconstructionPalupi-Simoro, Kalubula-Kalawara,Biromaru-Palolo, dan Akses Huntap.
√ √
T O T A L : 22 3 1 9 9Note: Package No.9 (Rantau Tijang – Kota Agung), Package No.10 Sp.Empat-Sp.Air Balam and Package No.18 (Mukomuko – Bts. Sumbar) are cancelled
from the program.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
1 - 3
Length C'tion
Km Period J N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
CTC Core Team Consultant (CTC) 40 mth IMPLEMENTATION Time extension for sevices
DSC Design & Supervision Cslt (DSC) 42 mth IMPLEMENTATION Time extension for sevices
TAS TA for Dev.of Slope Stabilization, Design & M anagement PROCUREMENT
CSC Construction Supervision Cslt (CSC) PROCUREMENT
1 Krui - Biha 25.00 21 mth 8 Jan'14 9 Okt'15
2 Padang Sawah - Sp.Empat 40.90 24 mth 6 Jan'14 5 Jan'15
3 Manggopoh - Padang Sawah 32.00 24 mth 6 Jan'14 5 Jan'15
4 Ipuh - Bantal 42.40 24 mth 10 Jan'14 9 Jan'15
5 SIMPANG RAMPA - PORIAHA 11.10 18 mth 18 Jun'15 11 Feb'17
11 BANTAL - MUKOMUKO 50.10 24 mth 23 Feb'15 11 Feb'17
13 SP RUKIS - TJ KEMUNING 56.30 24 mth 11 Feb'17
17 Sp.Gn.KEMALA - Pg. TAMPAK 36.80 24 mth 04 Sep'15 23 Agt'17
6 PS. PEDATI - KERKAP 25.00 15 mth 11 Mar'15 02 Jun'16
19 LAIS - BINTUNAN 11.60 10 mth 11 Mar'15 08 May'16
15 SIBOLGA - BATAS TAPSEL 36.00 27 mth 20 Nov'15 06 Feb'18
7 INDRAPURA - TAPAN 19.50 21 mth PROC
8 BTS.Kt PARIAMAN-MANGGOPOH 46.80 24 mth
10 SIMPANG EMPAT - SP.AIR BALAM 61.70 The Road has been constructed by MPW within 2011-2013. Road condition is good. Proposed to be deleted from the list of WINRIP's work program
12 KAMBANG - INDRAPURA 55.20 24 mth
14 PAINAN – KAMBANG 31.50 21 mth
16 SEBLAT – IPUH 34.50 21 mth
20 LUBUK ALUNG – SICINCIN 14.60 18 mth
21 LUBUK ALUNG – KURAITAJI 16.80 18 mth
9 RANTAU TIJANG-KOTA AGUNG 42.00 The Road has been constructed by MPW within 2011-2013. Road condition is good. Proposed to be deleted from the list of WINRIP's work program
18 MUKOMUKO-BTS SUMBAR 25.80 The Road has been constructed by MPW within 2011-2013. Road condition is good. Proposed to be deleted from the list of WINRIP's work program
21A LUBUK ALUNG – KURAITAJI 5 mth PROC CONST 150 days
5A SIMPANG RAMPA - PORIAHA 10 mth PROC CONSTRUCTION 300
RR-01 Rehab & Recon Tompe-Dlm Kota Palu-Surumana PROC
RR-02 Rehab & Recon Palupi-Simoro, Kalukubula-Kalawara, Birobuli-Palolo, Akses Huntap PROC
Original target : 715.60 km ENVIRONMENT & SOCIAL SAFEGUARD
Revised target : 586.10 km Prequalification Detail Eng Design LARAP Study
Road Safety Owner's Estimate Appraisal & Public Consultation
Procurement & Sign Contr Bid Document LARAP Implementation
Preparation for Commencement of Work
Standard Biding Document
NCB CONSTRUCTION
20212019 2020
CONSTRUCTION 540 days
CONSTRUCTION 540 days
19-Feb-16
Time for sevices
6-Nov-12
19-Jun-13 30-Nov-16
IMPLEMENTATION
PROC COW CONSTRUCTION
Rev-DED RS
Rev-DED RS
Rev-DED RS
ICB
ICB
NCB
NCB
ICB
ICB
ICB
ICB
NCB
NCB
NCB
Review DED & RS
Review DED & RS
Review DED & RS
PROC
PROCReview DED & RS PQ
PQ
Rev-DED RS
PROC
CONSTRUCTION 720 days
SBD & OE + BD CONSTRUCTION 300 + 125 days
CONSTRUCTION 810 days
CONSTRUCTION
PROC
PROC
CONSTRUCTION
CONSTRUCTION
SBD & OE + BD
CONSTRUCTION 720 days
CONSTRUCTION 720 days
PQ
RS
Proc
COW
SBD
DED RSA & REVISED DED OE & BD
DED
OE
BD
COW
NCB
COW
PROC COW
PROCDED CONSTRUCTION
Pack # PACKAGE NAME2012 2013
Review DED & RS PQ PROC
Review DED & RS PQ
DED
SBD & OE + BD
DED
DED RSA & REVISED DED OE & BD
DED RSA & REVISED DED OE & BD
DED
Review DED & RS
CONSTRUCTIONPROC
CONSTRUCTION 450 days
2014 2015 2016 2017 2018
CONSTRUCTION 640 + 93 days
CONSTRUCTION 540 days
ICB
ICB
ICB
ICB
ICB
ICB
CONSTRUCTION 730 days
CONSTRUCTION 730 days
CONSTRUCTION 730 days
Project Timeline Schedule
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
1 - 4
Actual Implementation Timeline of WINRIP
Length C'tion
Km Period J N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
CTC Core Team Consultant (CTC) 40 mth IMPLEMENTATION Time extension for sevices
DSC Design & Supervision Cslt (DSC) 42 mth IMPLEMENTATION Time extension for sevices
TAS TA for Dev.of Slope Stabilization, Design & M anagement PROCUREMENT
CSC Construction Supervision Cslt (CSC) PROCUREMENT
1 Krui - Biha 25.06 21 mth 8 Jan'14
2 Padang Sawah - Sp.Empat 40.70 24 mth 6 Jan'14
3 Manggopoh - Padang Sawah 32.00 24 mth 6 Jan'14
4 Ipuh - Bantal 42.45 24 mth 10 Jan'14
5 SIMPANG RAMPA - PORIAHA 9.70 18 mth 18 Jun'15
11 BANTAL - MUKOMUKO 50.65 24 mth 23 Feb'15 19 May'17
13 SP RUKIS - TJ KEMUNING 56.27 24 mth
17 Sp.Gn.KEMALA - Pg. TAMPAK 36.15 24 mth 04 Sep'15
6 PS. PEDATI - KERKAP 20.88 15 mth 11 Mar'15
19 LAIS - BINTUNAN 10.80 10 mth 11 Mar'15 CONSTRUCTION 300+125+53 days 30 Jun '16
15 SIBOLGA - BATAS TAPSEL 36.00 27 mth 20 Nov'15
7 INDRAPURA - TAPAN 19.50 21 mth 10 Dec'15
8 BTS.Kt PARIAMAN-MANGGOPOH 46.80 24 mth PROC 23 Mar'16
12 KAMBANG - INDRAPURA 55.20 24 mth
14 PAINAN – KAMBANG 31.50 21 mth PROC 13 Aug'16
16 SEBLAT – IPUH 34.50 21 mth 08 Nov'16
20 LUBUK ALUNG – SICINCIN 14.60 18 mth 1 Sep'16
21 LUBUK ALUNG – KURAITAJI 16.23 18 mth 1 Sep'16
21A LUBUK ALUNG – KURAITAJI 5 mth PROC CONST 150
5A SIMPANG RAMPA - PORIAHA 10 mth PROCCONSTRUCTION 300
RR-01 Rehab & Recon Tompe-Dlm Kota Palu-Surumana PROC
RR-02 Rehab & Recon Palupi-Simoro, Kalukubula-Kalawara, Birobuli-Palolo, Akses Huntap PROC
Original target : 715.60 km ENVIRONMENT & SOCIAL SAFEGUARD1st Revised target : 640.00 km Prequalification Detail Eng Design LARAP Study
2nd Revised target : 578.99 km Road Safety Owner's Estimate Appraisal & Public Consultation
Procurement & Sign Contr Bid Document LARAP Implementation
Preparation for Commencement of Work
Standard Biding Document
2019 2020 2021
19-Feb-16
IMPLEMENTATION
Time for sevices
CONSTRUCTION 540 days
CONSTRUCTION 540 days
31-Jan-21
31-Dec-19
20-Dec-18
15-May-18
27-Dec-17
29-Dec-17
27-Jul-18
1-Jun-19
30-Jul-18
2013 2014 2015 2016
6-Nov-12
19-Jun-13
Review DED & RS PQ
Review DED & RS PQ
PQ
Review DED & RS
Review DED & RS
PROC
CONSTRUCTION 720 + 127 days
CONSTRUCTION 720 + 212 days22-Jul-15
PQ PROC
ICB
ICB
ICB
ICB
ICB
#########CONSTRUCTION 640 + 93 days
Pack # PACKAGE NAME2012 2017 2018
SBD & OE + BD
PQ
RS
Proc
COW
SBD
DED
OE
BD
DED
NCB
NCB
DED
DED
CONSTRUCTION 630 + 151 days
23-May-16 CONSTRUCTION 720 - 132 + 209 days
NCB
NCB
ICB
NCB
NCB
DED
PROC
CONSTRUCTION 720 +104 daysICB
ICB
ICB
Review DED & RS
Review DED & RS SBD & OE + BD
RSA & REVISED DED OE & BD
28-Jan-17
CONSTRUCTION 630 - 114 + 168 days
PROC
PROC
PROC
17-Mar-16
CONSTRUCTION 540 + 445 days
CONSTRUCTION 730 + 105 days
CONSTRUCTION 730 + 75 days
ICB RSA & REVISED DED OE & BD
Review DED & RS SBD & OE + BD
DED RSA & REVISED DED OE & BD
DED
ICB CONSTRUCTION 810 - 37 + 181 days
14-Apr-16
NCB
Terminate
30-Nov-16
DED
Rev-DED RS
PROC
PROC
Rev-DED RS
Rev-DED RS
Rev-DED RS
CONSTRUCTION 450+240 days
CONSTRUCTION 540 - 53 + 179 days
CONSTRUCTION 540 - 53 + 59 days
CONSTRUCTION 730 + 90 days 31-May-16
2-Mar-18
28-Jul-18
CONSTRUCTION 720 - 71 days
CONSTRUCTION 630 days
18-Mar-18
#########
#########
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
1 - 5
1.2 Disbursement
Loan Allocation and Percent (%) Disbursement To Date
The total disbursement summary from the loan by The World Bank to the end of January2020 was USD 206,618,392.21 equivalent to approximately 82.7 % of the loan funds. Thefollowing table summarizes the individual disbursements as calculated by CTC but retainingthe total disbursement from Client Connection at the end of January 2020.
Appendix A shows the Overall Loan Progress Status.
Category DescriptionLoan
RestructuringAmount US$
DisbursementThis Period
PreviousDisbursement
Totals Disbursed toEnd of January
2020 in US$
%Disburse
d
1Part 1 Betterment andCapacity Expansion of
National Roads.205,000,000.00 2,526,786.75 186,371,999.89 188,898,786.64 92.2
2Part 2
Implementation Support20,000,000.00 528,959.06 10,633,759.54 11,162,718.60 55.8
3Part 3
Road Sector InstitutionalDevelopment
0.00 0.00 0.00 0.00 0.0
4Part 4
Contingency for DisasterRisk Response
25,000,000.00 2,612,683.88 0.00 2,612,683.88 10.5
5 Unallocated 0.00 0.00 0.00 0.00 0.0
DA-A Designated Account 3,944,203.09 *)GRAND TOTAL 250,000,000.00 5,668,429.69 197,005,759.43 206,618,392.21 82.7
*) The Ending balane of DA-A USD 4,433,730.69
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
1 - 6
1.3 World Bank Implementation Review Mission and Site Visit
No World Bank Review Mission in this period.
1.4 Procurement of Civil Works Contract Under Category 1 and Category 4 of the LoanAgreement
As of end this reporting month, twenty-one (21) Civil Works packages under Category 1 andtwo (2) under Category 4 are already procured. Eighteen (18) packages had been completedthen taken over to the employer, one (1) package terminated and the remaining three (3)packages are cancelled. One (1) civil works under Category 1 and two (2) civil works packagesunder Category 4 are currently under construction.
The new civil work sub-project named Package No. 5A: Penanganan Lereng Ruas SimpangRampa – Poriaha has been approved by the World Bank to be funded within the WINRIPProject. This package is needed to handle extreme slope conditions in package 05 at somespots, requiring treatment for slope stability and protection against road users. Procurementof this package has been completed. The construction of this package had been started onApril 22, 2019 for 300 calendar days to complete the works.
Package 21: Lubuk Alung – Kuraitaji was terminated and to complete the remaining works, itis needed to carry out a new bidding called Package 21A : Lubuk Alung – Kuraitaji (CompletionStage). The World Bank has issued No-Objection Letter (NOL) on July 9, 2018 for carrying out anew bidding process for Package 21A. The procurement of this package completed onDecember 2018. The construction of this package had been started on January 3, 2019 andhas been completed on July 1, 2019.
In accordance with Amendment of Loan Agreement, the WINRIP program will also fund 2 civilworks packages under Category 4 in Central Sulawesi in order to rehabilitation andreconstruction some roads affected by the earthquake and tsunami disaster. The civil workssub-projects will be fund are as follows:
1. Package No. RR-01: Tompe – Dalam Kota Palu – Surumana; the bidding for thispackage has been announced on May 31, 2019. Announcement of award bidder hasbeen issued on September 27, 2019 after determination of contract award byMinistry PUPR issued on September 23, 2019. Contract signature on October 25, 2019Commencement of work on October 28, 2019.
2. Package No. RR-02: Palupi-Simoro, Kalukubula-Kalawara, Birobili-Palolo and AksesHuntap; final design for this package formally has been submitted to the Bank on June18, 2019 and NOL has been issued by Bank on August 13, 2019. The bidding for thispackage has been announced on August 15, 2019. Announcement of award bidderhas been issued on October 16, 2019. Contract signature on November 1, 2019 andCommencement of work November 4, 2019.
1.5 Procurement of Consultancy Package under Category 2 of the Revised LoanAgreement Reallocation.
As of end this reporting month, four (4) consulting services are completely selected and 2(two) of services are still running. Regarding to the last amendment of the Loan Agreement,there is additional 1 (one) consulting service has been selected for supervised the new civilworks packages on Central Sulawesi. Consulting services under this category are following:
a. Technical Assistance for Core Team Consultant (CTC) to Support the ProjectManagement Unit of Western Indonesia National Roads Improvement Project(WINRIP);
b. Design and Supervision Consultant (DSC) of Western Indonesia National Roads
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
1 - 7
Improvement Project (WINRIP);
c. Technical Assistance for Development of Slope Stabilization, Design and Managementof Western Indonesia Roads.
d. Construction Supervision Consultant (CSC) for Rehabilitation and ReconstructionWorks in Central Sulawesi under WINRIP; Selection for this consultancy service hasbeen started on May 17, 2017 by announced it at LPSE Ministry of Public Works andHousing using SPSE ICB application and UNDB Online. Determination of MinistryPUPR for contract award issued with a letter ref. No. PB.03.01-Mn/2244 date onNovember 28, 2019. Contract signature for this service was done on December 9,2019. The commencement date for this service on December 17, 2019.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
2 - 1
2 PROJECT DESCRIPTION
2.1 Background
The Government of Indonesia wishes to continue strengthening of the National Road system inIndonesia while the Eastern Indonesia National Roads Improvement Project (EINRIP which isassisted by AusAID through the Australian Indonesia Partnership or AIP), is providing supportprogram of National road and bridge improvement works in Eastern Indonesia. The WesternIndonesia National Road Improvement Project (WINRIP) will provide similar support for Nationalroad and bridge in the Sumatera region of Indonesia. The focus of WINRIP will be roadsadministered directly by the National Government, including those currently classified asProvincial, Kabupaten (District) or non-status roads which are in process of being reclassified asNational roads. In addition, provision will be made for major bridge repair works, rehabilitation,duplication and replacement as necessary to complement road betterment works.
2.2 Project Development
The loan effectiveness date for the WINRIP is 12 March 2012 and key project data is shown in thefollowing detail.
Key Project Data WINRIP Loan No. 8043-ID
Project Cost US$350 million
Original Loan Amount US$250 million
Revised Loan Amount N/A
Board Approval Date 26 May 2011
Loan Signing Date 14 December 2011
Effectiveness Date 12 March 2012
Disbursement (as of January 2020) US$ 206,618,392.21 (82.7%)
Original Closing Date 31 December 2018
Closing Date (revised) 28 February 2021
Environmental Category B-Partial Assessment
The IBRD loan amount is US$250 million. The Project is intended to finance a part of the DGHinvestment program for national roads with a particular focus on the Western corridor ofSumatera. The corridor is one of the three main corridors in Sumatera and connects the city ofPadang (with a population of around one million) to major towns along the west coast (Bukittinggi, Sibolga and Bengkulu). It also connects through connector roads on the West coast toMedan in the northeast and to Pekanbaru in the center of the island. The project has fourcomponents:
Project Component 1: Betterment and Capacity Expansion of National Roads
According to the Amendment No.4 Loan Agreement, this component will cover three workprograms of betterment and capacity expansion of approximately 579 km including replacement of160 meters of bridges. This civil works program will be executed in three Annual WorkPrograms(AWP), as summarized in Table 2.1. The table shows the IBRD assisted scope and costs ofcivil works at estimated current (year of implementation) prices, excluding taxes.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
2 - 2
Table 2.1 Proposed Physical Works by DGH Program
Type of WorksAWP-1 AWP-2 AWP-3
Km USDMillion
Km USDMillion
Km USDMillion
Road Betterment - - 53.10 22.77 - -
Capacity Expansion 137.10 79.70 314.60 127.67 207.60 74.58
Bridge works 0.100 1.94 - - 0.08 2.06
TOTAL(excluding tax @ current prices)
137.20 81.64 367.70 150.45 207.68 76.65
The batches of projects are termed Annual Work Programs (AWPs) in line with terminology used inother Bina Marga projects. They are not in fact “annual” programs as such but rather a series ofmulti-year programs, each commencing in consecutive years. Hence, hereinafter it will call as justWork Programs (WPs). It is expected that implementation of the first Works Program (WP-1) willcommence in the third quarter of 2013 and be completed by third quarter or late 2015. Thesecond Work Program (WP-2) is expected to commence in early 2014 and be completed by late2015 or middle 2016. The third Work Program (WP-3) is expected to commence in early 2015 andbe completed by mid-2017. The loan will be closed on February 2021.
Table 2.2 presents details of the First Works Program (WP-1). The four packages in this groupshould have been free from any land acquisition issues, but in fact two packages (Krui – Biha andManggopoh – Padang Sawah) had land issues which were solved by the DGH properly. Thus, thereare no foreseeable impediments to implementation.
Table2.2 IBRD Assisted WINRIP Civil Work WP-1
No Province LinkNo.
LinkName
Clas
s
Road
Typ
e
Road Works Bridge Works Total Cost
From
To Leng
th
Trea
tmen
t
Cost
(201
0)
No
Leng
th
Cost
(201
0)
2010
Pric
es
Equi
vale
nt
Km Km Km Rp mill m Rp mill Rp mill US$ mill
1 Lampung 053.0 Krui –Biha K1 IU 225.91 246.97 25.06 Bett’nt
to 7 m. 148,668 148,668 16.52
2 WestSumatera 047.2
PadangSawa –SimpangEmpat
K1 IU 0.0 40.70 40.70 Bett’ntto 7 m. 189,810 189,810 21.09
2a WestSumatera 34.1 AirGadan
gBridge K1 IU NewBridge 1 100 17.580 17,580 1.95
3 WestSumatera 047.1
Manggopoh –PadangSawah
K1 IU 102.2 134.2 32.0 Bett’ntto 7 m. 152,435 152,435 16.94
4 Bengkulu 015.3 Ipuh -Bantal K1 IU 0.0 42.45 42.45 Bett’nt
to 7 m. 226,275 226,275 25.14
It should be noted that all road sub-projects have been subject to economic appraisal and haveestimated Economic Internal Rates of Return (EIRR) in excess of 15%. These were selected for
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
2 - 3
inclusion and are subject to completion of environmental and social screening, to confirm thatthere is no land acquisition or resettlement requirements remain outstanding.
Final Engineering Designs, Engineer’s Estimates and bidding documents have been completed forall projects proposed for WP-1.
Sub-projects to be included in WP-2 and WP-3 have also been determined as listed in Table 2.3.Final Engineering Designs and Engineer’s Estimates for all WP-2 and WP-3 proposed works requirepreparation or finalization. In the cases of some projects, preliminary Engineering Designs wereprepared during Project preparation which will require review and possible amendment by theDesign and Supervision Consultant prior to procurement.
The revised costs presented in Table 2.3 are planning estimates only, and the revisedimplementation plan is based on the “Revised Implementation Timeline Schedule” of the civilworks.
Table2.3: IBRD Loan WINRIP Civil Work WP-2 and WP-3
NO. SUBPROJECT LINK NO. AND NAME LENGTH(KM)
ENGINEER’SESTIMATE(RP. MILL)
WIDTH(M)
REVISED IMPLEMENTATION PLAN
START DURATION(MONTHS)
WP-2
5. Sumut : Link No. 015.xx,Sp. Rampa – Poriaha 9.70 152,870 6.0 Mar 2015 18
6. Bengkulu : Link No. 010.0,Ps. Pedati – Kerkap 20.89 92,127 7.0 Mar 2015 15
7. Sumbar : Link No. 019.0,Indrapura – Tapan 19.50 178,600 7.0 Jan 2016 21
8. Sumbar : Link No. 024.0,Bts. Pariaman – Manggopoh 46.80 379,034 7.0 Jan 2016 24
9. Lampung : Link No. 026.1,Rantau Tijang - Kota Agung - - - - Cancelled
10. Sumbar : Link No. 034.1,Sp. Empat - Sp. Air Balam 61.70 515,842 7.0 - Cancelled
11. Bengkulu : Link No. 015.2,Bantal – Mukomuko 50.65 246,500 6.0 Feb 2015 24
12. Sumbar : Link No. 017.2,Kambang – Indrapura 55.20 451,810 7.0 Jan 2016 24
13. Bengkulu : Link No. 006.1,Simpang Rukis - Tanjung Kemuning 56.27 316,305 7.0 Jun 2015 24
WP-3
14.Sumbar : Link No. 017.1,Painan – Kambang 31.50 252,000 7.0 May 2016 21
15. Sumut : Link No. 016.0,Sibolga - Bts. TapSel 36.00 376,479 7.0 Oct 2015 27
16. Bengkulu : Link No. 009.4,Seblat – Ipuh, including Air Galang and
34.500.052 241,500 6.0 May 2016 21
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
2 - 4
NO. SUBPROJECT LINK NO. AND NAME LENGTH(KM)
ENGINEER’SESTIMATE(RP. MILL)
WIDTH(M)
REVISED IMPLEMENTATION PLAN
START DURATION(MONTHS)
Air Guntung Bridges
17. Lampung : Link No. 061.1,Sp. Gunung Kemala - Pugung Tampak
35.91 255,269 6.0 May 2015 24
18. Bengkulu : Link No. 015.3,Mukomuko - Bts. Sumbar - - - - Cancelled
19. Bengkulu : Link No. 009.1,Lais – Bintuan 10.81 35,886 7.0 Feb 2015 10
20. Sumbar : Link No. 002.0,Lubuk Alung – Sicincin 14.60 116.800 7.0 May 2016 18
21. Sumbar : Link No. 027.0Lubuk Alung – Kuraitaji 16.23 65,788 7.0 May 2016 18
21A Sumbar : Link No. 027.0Lubuk Alung – Kuraitaji 16.23 99,019 7.0 Jan 2019 5
5ASumut : Link No. 015.xx,Penanganan Lereng Ruas Sp. Rampa –Poriaha
0.69 78,933 - April 2019 10
Project Component 2: Implementation Support
This component provides consulting services to support project management and implementationso as to ensure implementation efficiency and overall quality of the works. It also includes fundsfor a small amount of training of DGH staff and for incremental operating costs for the project. Thiswill provide support to the MPWH for the implementation of the civil works, including: (a)provision of Core Team Consultants (CTC), Design and Supervision Consultants (DSC) and roadsafety audits; (b) Project management support and technical audits. This is directly related to theimplementation of the civil works and covers consulting services for design and supervision of thecivil works in Component 1; management support and technical audits to help improve the qualityof construction and support to governance improvements during procurement andimplementation; and a series of systematic road safety audits of road designs for all project roadsin Component 1. This is to ensure compliance with road safety standards and regulations, identifyroad hazards and undertake remedial treatments for safety improvements, (c) slope protectiondesign and management. This is related to Technical Assistance and Support to StrengthenDisaster Risk Mitigation in the Road Sector mainly to deal with stabilizing and strengthening, inparticular roadway side cut and high embankment slopes by providing appropriate slopeprotection structures. These activities initially is part of Component-3: Road Sector InstitutionalDevelopment, however, due to reallocation or realignment of funds, the propose work, “TechnicalAssistance for Development of Slope Stabilization, Design and Management” implementation hasbeen realigned to Component-2 : Implementation Support. This activity covers consulting servicefor design and management of slope protection. The revised Loan Category restructuring ispresented in Table 2.4 and revised implementation is based on the approval of GOI and WorldBank.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
2 - 5
Tabel 2.4
Project Management Core Team Consultants (CTC)
The CTC will provide support to the PMU and DGH in the management of the Project, based inJakarta. Their tasks include financial and progress monitoring and reporting, informationmanagement and dissemination, quality assurance and performance review for the Design andSupervision Consultants, implementation and monitoring of the anti-corruption action plan,support for project monitoring and evaluation, and support for implementation of a trainingprogram to support project management and implementation. The CTC contract No. 06-20/CTC/TA/LN/8043/1112 was signed on 5 November 2012 by both DGH and a Joint Venture ofPT. Perentjana Djaja, Yongma Engineering Co, Ltd, and PT. Epadascon Permata EngineeringConsultant.
Design and Supervision Consultants (DSC)
A Design and Supervision Consultant (DSC) will be responsible for design of WP-2 and WP-3 civilworks and supervision of all civil works. They will have the role of ‘Engineer’ under a FIDIC-typecontract. The tasks include the preparation and maintenance of a quality assurance plan,validation and updating of designs, supervision of all civil works, environmental and socialmonitoring and management, and support for financial and progress monitoring and reporting.The DSC will also be responsible for quality assurance of materials and workmanship, certifyingwhether or not contractors have achieved the required results, as well as documentation andreporting based on the financial management plan. They will prepare a Quality Assurance systemcovering all subprojects, and continuously monitor the effectiveness of their supervisionprocedures. The team will be contracted and managed by DGH through the Bina Marga RegionalOffice (Balai II), and will be based in Padang, West Sumatera.
CategoryOriginal Amount ofthe Loan Allocated
(expressed in USD)
Revised Amountof the Loan
Allocated(expressed in
USD)
Percentage ofExpenditures to be
financed (inclusive ofTaxes)
(1) Civil Works under Part 1 of theProject WP-l 220,400,000 205,000,000 70%
(2) Goods, Non-consulting Services,Consultants Services andIncremental Operating Costs* underPart 2 of the Project
16,000,000 20,000,000 100%
(3) Goods, Non-consulting services andConsultants' Services under Part 3of the Project
1,000,000 Cancelled Cancelled
(4) Works, Goods, Non-ConsultingServices, Consultants' Services andIncremental Operating Costs* underPart 4 of the Project
0 25,000,000 100%
(5) Unallocated 12,600,000 0T O T A L : 250,000,000 250,000,000
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
2 - 6
Technical Assistance for Development of Slope Stabilization, Design and Management WesternIndonesia Road
The Technical Assistance’s objective is to provide technical support to DGH in improving theircapacity for road slope/embankment protection and management. It will include identification andinventory of the existing slope and embankment conditions, assessment of future potential landslide/road erosion problems, development of risk maps, prioritization of high problem/high riskareas, and development of the Detail Engineering Designs for a limited amount of areas in theWestern Corridor of Sumatra6. It will also include the review (and revision) and preparing the newNational Standard and Manual (NSPM) related to the slope protection and capacity building. TheTA’s contract was signed on July 7, 2017 between DGH trough the Sub-Directorate of Geotechnicaland Slope Management of Directorate of Road Construction and PT. Egis International Indonesia inJV with PT. Disiplan Consult and PT. Widya Graha Asana.
Construction Supervision Consultant (CSC)
A Construction Supervision Consultant (CSC) will be responsible for supervision of all civil worksunder Category 4 in Central Sulawesi Province. They will have the role of ‘Engineer’ under a FIDIC-type contract. The tasks include the preparation and maintenance of a quality assurance plan,validation and updating of designs, supervision of all civil works, environmental and socialmonitoring and management, and support for financial and progress monitoring and reporting.The CSC will also be responsible for quality assurance of materials and workmanship, certifyingwhether or not contractors have achieved the required results, as well as documentation andreporting based on the financial management plan. They will prepare a Quality Assurance systemcovering all subprojects, and continuously monitor the effectiveness of their supervisionprocedures. The team will be contracted and managed by DGH through the Bina Marga RegionalOffice (Balai XIV), and will be based in Palu, Central Sulawesi.
Project Component 3: Road Sector Institutional Development
This component which is originally intended to provide technical assistance and support tostrengthen disaster risk mitigation in the road sector, including capacity building support for thenew environment/risk mitigation and road safety unit of DGH has been cancelled due to revisionof the loan allocation. In the meeting, DGH and World Bank agreed upon that DGH will conductanalytical work of an alternative design for road segment that pass through critical environmentalassets and vulnerable areas especially on slope protection design and management. Due todeletion of the allocated funds for Category 3 of the loan agreement and reallocated to Category 2to accommodate the implementation of Technical Assistance for Development of SlopeStabilization, Design and Management, into Component-2. The Loan Category restructuring can beseen in Table 2.4 page 2-5.
Project Component 4: Contingency for Disaster Risk Response
This special component will provide preparedness and rapid response to disaster, emergencyand/or catastrophic events as needed. In accordance with the last amendment of Loan Agreement,there is budget allocation in amount of USD 25,000,000 to civil works in response to rehabilitation
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
2 - 7
and reconstruction programs after disaster in Central Sulawesi Province.
Given the revised PDO, the activities to be financed under Component 4 are circumscribed to road-related activities along the Western Sumatera Corridor and Central Sulawesi Province. In general,these activities include emergency road works to restore the functionality of selected sections ofnational and sub-national roads in disaster-affected areas in Central Sulawesi. Specifically, theactivities proposed include:
(i) Rehabilitation and reconstruction of approximately 70.14 kilometers of roads, includingdrainage systems, some works in minor bridges and the construction of retaining/sea walls(hazards-proofing structure), in Palu City and Donggala and Sigi Districts in CentralSulawesi as well as Routine Maintenance for 31.67 kilometers of road and 899.45 metersof bridges (see Table 1 and Figure 2 for further details); and
(ii) Provision of Construction Supervision Consultants to assist to the DGH in supervision ofthe civil works in Central Sulawesi. They will have the ‘Engineer’ role under the FIDIC stylecontract. They shall establish and maintain representatives in Palu until completion ofeach Sub-Projects.
Table 1. Proposed Road Rehabilitation and Reconstruction Sub-Projects in Central Sulawesi.
No. Sub-project Administrative Status Km
Total Cost,excl. Tax
(IDRmillion)
RR-01 Rehabilitation and Reconstruction of Jalan Tompe -Dalam Kota Palu – Surumanaa.Rehabilitation and Reconstruction of Roadb. Routine Maintenance of Roadc. Routine Maintenance of Bridge (m)
National
48.396.72
634.4
207,050
RR-02 Rehabilitation and Reconstruction of Jalan Palupi -Simoro, Kalukubula - Kalawara, Birobuli - Palolo,Jalan Akses Huntap
a. Rehabilitation and Reconstruction of Roadb. Replacement of Bridge (m)c. Construction of Bridge (m)d. Routine Maintenance of Roade. Routine Maintenance of Bridge (m)
Sub-national(City/District)
21.6710.070.0
24.95265.05
142,000
TOTAL 349,050
US$ 17.40 million and US$ 7.60 million reallocated from the Disbursement Categories 1(“Betterment and Capacity Expansion of National Roads”) and 5 (“Unallocated”) respectively to theDisbursement Category 4, related to disaster risk response, resulting in USD 25.00 million allocatedunder the Disbursement Category 4 (as mentioned on the Section 2.6). The funds of Component 4will be used to finance 100% of the related reconstruction activity, using the existing standard unitcosts for construction approved by a competent agency. Cost estimate includes the GoI taxations.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
2 - 8
2.3 Project Objective
The main objective of the program will be to increase the effective use of selected sections ofNational roads along the Western Sumatera Corridor by reducing road user costs, throughimproving the National road network especially in 4 (four) Provinces of Sumatera (North Sumatera,West Sumatera, Bengkulu and Lampung) and, where desirable, raise the road standard to that setby the Directorate General of Highways. This will contribute significantly to ensuring that thenational road network in the region provides acceptable standards of service and accessibility, andis capable of supporting local and regional economic development; and to restore the functionalityof selected sections of national and sub-national roads in disaster-affected areas in CentralSulawesi.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
3 - 1
3 CONSULTANCY SERVICES
3.1 CTC Consultants
3.1.1 Scope of Services
The CTC contract services originally were structured in its different project management elements.
* Inception Phase
A key activity during the inception phase will be to establish lines of communication with PMU-WINRIP and DSC’s Team Leader as well as with all Provincial Project Managers (Satker) wherethe first works are to be constructed under WP-1.
* Project Management and Support to PMU, including acting DSC until the DSC is established
The Terms of Reference (TOR) identify a number of sub-items to be performed by CTC. The keyfactor that will ensure success is that the CTC must work pro-actively and alongside PMUcounterparts and with DSC team in a professional manner based on mutual respect and trust.
* Preparation of Work Programs
The tendering process for WP 1 sub-projects began as soon as procurement committees havebeen formed and received appropriate training in the procurement procedures required. Theindicative work programs and cost estimates identified for WP-2 and WP-3 are subject toverification, and are likely to change following more detailed investigations. Furtherpreparation for WP-2 and WP-3 will be managed by the PMU supported by the CTC.
* Financial Monitoring
It will be the role of the CTC to first assess the level of understanding of the financialmanagement, monitoring and reporting procedures by the finance staff at the provincial andcentral level and subsequently devise an appropriate training program and assist the PMU intraining delivery.
* Project Progress and Performance Monitoring
CTC will monitor the loan project progress and prepare the report in monthly basis. In themeantime, GOI and the World Bank have agreed on a set of Key Performance Indicators (KPIs)to measure the project’s performance in achieving its stated development objectives. CTC willtherefore first concentrate on the establishment of precise definitions, calculation methodsand data collection procedures to monitor the KPIs.
* Support for the Implementation of the ACAP
The CTC will assist PMU and be responsible for ensuring the ACAP is properly implemented.And for revising the Project Management Manual on an annual basis is to incorporatenecessary improvements of process and procedure.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
3 - 2
* ESAMP and LARAP Implementation Monitoring
CTC will closely work with BLH and DSC and will monitor and report the action of theEnvironmental Management Plan on a periodical basis and/or as required.
* Training to Support Project Implementation
CTC is responsible for preparation and management of all training program required underWINRIP.
* Reporting
CTC is responsible for all reports required under the contract agreement with standardizeforms, charts and tables.
3.1.2 CTC Manning
CTC professional staffs involved in the project as of end of January 2020 are listed in Table 3.1.
The International Staff (Senior Highway Engineer, Senior Road Safety Audit Engineer and SeniorProcurement Specialist) have completed their respective engagements and man-months havedemobilized on March 31, 2014 and May 31, 2015, respectively.
The task of conducting final Road Safety Audit during post-construction phase which is supposedto be conducted by the Senior Road Safety Audit Engineer will be performed by the local RoadSafety Audit Engineer with man-months for the task to be covered by Amendment No.4 of theConsultancy Contract.
The Training Specialist has been demobilized since the end of August 2016 due to completion ofhis allocated man-month under Amendment No.4 of the Consultancy Contract.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
3 - 3
Table 3.1
40.00 - - - - - Mahbub ur Rahman - - - - A
- 35.25 12.25 12.25 9.90 - Per Weiss Pedersen Apr-2013 Mar-2014 12.25 0.00 B
- - 23.00 30.13 24.17 - C.T. Arenas Apr-2014 Oct-2016 30.13 0.00 B
- - - - 23.60 49.60 Lee Hee Won Dec-2016 - 37.60 12.00 -
Senior Highway Engineer 8.00 12.50 14.00 14,00 14.30 - Moon, Sung Hyung Mar-2013 Mar-2014 14.00 0.00 C
Senior Road Safety Audit 6.00 11.00 13.00 11,00 8.97 - Cho, Woo Sung Jun-2013 Mar-2014 11.00 0.00 C
18.00 - - - - - Wasim ur Rahman - - - - A
- 16.00 16.00 16,00 14.03 - Sanjeev Kumar Agarwal Jan-2014 May-2015 16.00 0.00 C
40.00 9.67 9.67 9,67 9.67 - Besar Awiat Bowo Nov-2012 Sep-2013 9.67 0.00 B
- 30.33 6,66 6,66 6.63 - Agus Setiawan Sep-2013 Mar-2014 6.66 0.00 B
- - 23.67 45,50 55.43 81.43 Julius J. Sohilait Apr-2014 - 68.43 13.00
36.00 7.37 7.37 7,37 7.37 - Whiliyanto Nov-2012 Jun-2013 7.37 0.00 B
- 28.40 28.63 38,96 61.60 - Lebiyartono Jul-2013 Nov-2018 66.00 0.00
Quality Assurance Specialist-1 30.00 30.00 30.00 53,83 63.87 88.87 Uray Abdul Manaf Jul-2013 - 77.87 11.00 -
Quality Assurance Specialist-2 - - - - 11.00 - Hafifuddin Jan-2018 Nov-2018 21.00 0.00 -
36.00 10.37 10.37 10,37 10.37 - Uus Martawijaya Nov-2012 Oct-2013 10.37 0.00 B
- 25.63 25.63 50,96 60.73 - YD Tarwanto Oct-2013 Nov-2018 62.00 0.00
- - - - - 25.00 Ishak Rangkuti Jan-2019 - 11.00 14.00
Environmental Specialist 30.00 30.00 30.00 60,33 67.57 94.57 Leti Hermawati Dec-2012 - 82.57 12.00
36.00 9.37 9.37 9,37 9.37 - M. Sutopo Nov-2012 Oct-2013 9.37 0.00 B
- 26.63 26.63 39,96 60.33 75.33 Witono Sep-2013 - 75.33 0.00
12.00 - - - Darmansiri - - - - A
- 12.00 12.00 - Muhdi - - - - A
- - 12.00 7,00 7.00 - Mardiansyah Jul-2014 Mar-2015 7.00 0.00 B
12.00 - 4.10 4,10 4.10 - Rudi Rungkat Nov-2012 Mar-2015 4.10 0.00 B
- 24.00 24.00 40,23 42.70 - M. Edhi Fachri Mar-2013 - 43.20 0.00 C
30 - - - - - Agung Lukito - - - - A
- 25.00 25.00 55,83 66.47 69.47 Sony Thamrin May-2013 Feb-2019 69.47 0.00 -
Community DevelopmentOfficer 36.00 36.00 36.00 59,83 67.33 93.33 Yakobus Jan-2013 Jun-2019 - - -
Road Safety Audit Engineer 25.00 25.00 19.00 42,83 50.80 66.03 Aditya Moraza Alwi Jun-2014 - 65.03 1.00 -
Bridge Engineer 5.00 5.00 5.00 5,00 4.93 4.93 Harimurti Suprihantoro Apr-2013 Aug-2013 5.00 0.00 C
Training Specialist - 12.00 12.00 30,83 31.07 - Roedjitarjo Jan-2014 Aug-2016 31.23 0.00 C
Traffic Engineer - - - 7,00 7.00 10.00 Harianto Parman Mar-2015 - 1.00 7.00 D
Contract Doc. Specialist - - - - 25.00 51.00 M Edhi Fachri Nov-2016 - 39.00 12.00 -
Geotechnical Engineer - - - - - 13.00 Galuh Dewanto Jan-2019 - 12.00 1.00
Geologist - - - - - 13.00 Damai Putra - - - 13.00
RemarksA - Not able to mobilizied due to poor health or personal reasonsB - Resigned due to personal reasons or poor healthC - Task assigment completedD - Intermittent assignment to update AADTE - Man-months untilNovember 30, 2018 to be covered Amendment No.6
Highway Engineer
Man -Month
RemainingName Mobilized Demob-
ilized
Man - MonthUsed as of endof January 2020
AmendNo.4
Man - Months Duration
AmendNo.9
Financial ManagementSpecialist
Social Impact Specialist
Procurement Specialist-1
Procurement Specialist-2
Management InformationSpecialist
RemarksAmendNo.6
Team Leader
Senior ProcurementSpecialist
Assistant Team Leader
OriginalContract
AmendNo.1
AmendNo.2
POSITION
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
3 - 4
3.1.3 CTC Contract
The CTC contract for “Western Indonesia National Roads Improvement Project” (Contract No.06-20/CTC/TA/LN/8043/1112) was signed on 05 November 2012. The contract is between theGovernment of Indonesia represented by Directorate General of Highways in the Ministry of PublicWorks and PT. Perentjana Djaja in joint venture with Yongma Engineering Co.Ltd. and PT.Epadascon Permata Engineering Consultant.
The Notice To Proceed was issued by letter dated 6 November 2012 from the PPK, and the officialstarting date of the contract was set at 6 November 2012.
Likewise, Amendment No. 1 to the original contract was signed on 25 October 2013 to coverall requirements of the CTC are summarized below.
* Replacement of the Senior Procurement Specialist* Extending the assignment of the Senior Highway Engineer.* Extending the assignment of the Senior Road Safety Audit Engineer.* Extending the assignment of the Procurement Specialist 2 and replacement of the
Procurement Specialist 1.* Adding the new position of Bridge Engineer.* Adding the new position of Training Specialist, and* Adding the new position of Road Safety Engineer.
Amendment No. 2 to the Original Contract and Amendment No. 1 was signed on September 3,2014 to cover requirements of CTC are enumerated as follows :
* Additional / Modification to Terms of Reference (TOR)* Amendment to the Team Composition and Staffing Schedule* Replacement of Foreign and Local Consultants* Adjustments of Remuneration paid in foreign currency and local currency* Adjustment inputs of personnel* Modification to various reimbursable and provisional sum to match the actual requirement
Amendment No.3 to the current CTC Contract (Original Contract and Amendments 1 and 2 wassigned on November 30, 2015 which is in line with the Updated Timeline Bar Schedule takinginto consideration the current and look ahead situations of the WINRIP program.
Based on the current progress of the Project, the services of several local professional and sub-professional staff have been extended beyond the end of the respective dates of completionassignments under Amendment No. 2.
In addition, new position of Traffic Engineer for local professional staff have been added toconduct traffic surveys on six (6) selected road links within the WINRIP Program in order toupdate the AADTs and to prepare a “Technical Analysis of the Annual Average Daily Traffic”.
Amendment No.3 covers the requirements of CTC are as follows:
* Amendment to the team composition and staffing schedule* Adjustment of inputs of personnel* Adjustment of remuneration paid in local currency
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
3 - 5
* Adding the new position of Traffic Engineer* Modification to various reimbursable to match the actual requirements.
Amendment No. 4 to the current CTC Contract (Original Contract and Amendments 1, 2 and 3)was signed on March 4, 2016 and to expire or completed on December 31, 2017, the same dateas the expiry/closing date of the loan agreement.
Based on the current progress of the Project, services of professional international and local staffas well as local sub-professional staff have been extended beyond their respective dates ofassignment engagement covered by Amendment No. 3.
Amendment No.4 covers the requirements of CTC are as follows:
* Consultancy services time extension* Additional/Modification to TOR/Terms of Reference* Adjustment of input schedule for Professional Staff, Sub Professional and Supporting Staff* Amendment to the Team Composition* Amendment of the Staffing Schedule* Modification to the Provisional Sums* Adjustment of Remuneration paid in foreign currency and local currency* Adjustment to the reimbursable expenses* Amendment to Clause 6.1(b) of the Special Condition of Contract
Proposed Amendment No.5 to the current CTC Contract will cover the following requirementsof CTC :
* Adjustment of input schedule for professional staff, sub-professional and supporting staff.* Amendment of Staffing schedule.* Adjustment of remuneration covered by Special Conditions of the Contract, Clause 6.2 (a).* Adjustment of cost estimates for foreign and local currencies.
Amendment No.6 to the current CTC Contract cover the following requirements of CTC :* Additional/Modification to Terms of Reference (TOR);* Additional Professional Staff (Key Personnel);* Adjustment of input schedule for Professional Staff* Adjustment to the Reimbursable Expenses* Adjustment of Cost Estimate in Foreign and Local Currency
Amendment No.7 to the current CTC Contract cover the following requirements of CTC :* Adjustment of Price
Amendment No.8 to the current CTC Contract cover the following requirements of CTC :* Extension of the time period of Consultancy Services.* Additional/Modification Term of Reference (TOR).* Replacement for Sub Professional Staff and Supporting Staff.* Revision of input schedule for Professional, Sub-Professional and Supporting Staff.* Revision of the Remuneration and Reimburse Expenses in Foreign and Local Currency.* Modification the Provisional Sums (Local Currency).
Amendment No.9 to the current CTC Contract cover the following requirements of CTC :* Extension of the time period of Consultancy Service* Modification of Terms of Reference (TOR);* Additional Professional Staff;
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
3 - 6
* Re-mobilization and Additional Sub Professional Staff;* Revision of input schedule for Professional, Sub-Professional and Supporting Staff;* New billing rate for the new professional staffs;* Revision of the Remuneration and Reimburse Expenses in Foreign and Local Currency;* Modification of the Provisional Sums (local currency).
Amendment No.10 to the current CTC Contract cover the following requirements of CTC :* Replacement of Authorized Representative of Client (PPK in charge)
Presented in Table 3.2 is the current status of CTC contract.
Table 3.2
Description USD IDR
Original Contract including 10% VAT 1,404,370 23,556,940,000
Amendment No.1 including 10% VAT 1,447,517 24,668,792,500
Variance Against Original Contract +3,07% +4,72%
Combine Variance Against Original Contract +4.12%
Amendment No. 2 including 10% VAT 1,509,117 24,704,544,150
Variance Against Original Contract +7,46% +4,87%
Combine Variance Against Original Contract +5.81%
Amendment No.3 including 10% VAT 1,473,917 26,328,054,500
Variance Against Original Contract +4.95% +11.76%
Combine Variance Against Original Contract +9.29%
Amendment No. 4 including 10% VAT 1,918,158 40,878,169,529
Variance Against Original Contract +36.58% +73.53%
Combine Variance Against Original Contract +60.12%
Amendment No. 5 including 10% VAT 1,595,403.33 41,545,386,446
Variance Against Original Contract 13.69% 76.36%
Combine Variance Against Original Contract 53.58%
Amendment No. 6 including 10% VAT 1,819,253.33 48,653,875,746
Variance Against Original Contract 29.54% 106.54%
Combine Variance Against Original Contract 68.04%
Amendment No. 7 including 10% VAT 1,847,388.04 50,707,302,309
Variance Against Original Contract 31.55% 115.25%
Combine Variance Against Original Contract 73.40%
Amendment No. 8 including 10% VAT 1,867,738.03 51,239,410,810
Variance Against Original Contract 32.99% 117.51%
Combine Variance Against Original Contract 75.25%
Amendment No. 9 including 10% VAT 2,376,488.03 61,522,513,310
Variance Against Original Contract 69.22% 161.17%
Combine Variance Against Original Contract 115.19%
Amendment No. 10 including 10% VAT 2,376,488.03 61,522,513,310
Variance Against Original Contract 69.22% 161.17%
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
3 - 7
Description USD IDR
Combine Variance Against Original Contract 115.19%Note : Combine variance (USD+IDR) is based on 1 USD = Rp. 9,558 exchange rate used during the
time of signing the original Contract Agreement.
3.2 DSC Consultants
The Design and Supervision Consultant (DSC) is responsible to design of WP-2 and WP-3 civil worksand supervision of all civil works. They will assume the role of ‘Engineer’ under a FIDIC-typecontract. The tasks include the preparation and maintenance of a quality assurance plan,validation and updating of designs, supervision of all civil works, environmental and socialmonitoring and management, and support for financial and progress monitoring and reporting.The DSC is also be responsible for quality assurance of materials and workmanship, certifyingwhether or not contractors have achieved the required results, as well as documentation andreporting based on the financial management plan. They will prepare a Quality Assurance systemcovering all subprojects, and continuously monitor the effectiveness of their supervisionprocedures. The team is being contracted and managed by DGH through the Bina Marga RegionalOffice (Balai III), and is being based in Padang, West Sumatera.
DSC has been established in Balai II Padang following the contract signing on 11 June 2013between Balai II and Renardet SA in joint venture with PT. Cipta Strada, PT. Daya Creasi Mitrayasa,PT. Seecons and PT. Yodya Karya. The Notice To Proceed was issued by the Balai II on 19 June2013.
Shown in Table 3.3 is the present status of the Design Supervision Consultant (DSC) contract.
Table 3.3
Description USD IDR
Original Contract plus 10% VAT 902.660 57,000,575,500
Addendum No.1 plus 10% VAT 1,147,190 60,541,139,347
Variance Against Original Contract +27.09% +6.21%
Addendum No.2 plus 10% VAT 848,034 59,973,161,962
Variance Against Original Contract -6.05% +5.22%
Addendum No.3 plus 10% VAT 1,062,534 70,781,353,406
Variance Against Original Contract +17.71% +24.18%
Addendum No.4 plus 10% VAT 1,108,954 78,073,705,751
Variance Against Original Contract +22.85% +36.97%
Addendum No.5 plus 10% VAT 1,394,844 81,686,286,530
Variance Against Original Contract +54.53% 43.31%
Addendum No.6 plus 10% VAT 1,413,729 86,026,909,264
Variance Against Original Contract +56.62% +50.88%Note:
1) Addendum No.5 was approved by DGH on January 14, 2019 with World Bank concurrence andissuance of No Objection Letter (NOL)
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
3 - 8
3.3 Technical Assistance for Development of Slope Stabilization, Design andManagement
The TA’s objective is to provide technical support to DGH in improving their capacity for roadslope/embankment protection and management. It will include identification and inventory of theexisting slope and embankment conditions, assessment of future potential land slide /road erosionproblems, development of risk maps, prioritization of high problem/high risk areas, anddevelopment of the Detail Engineering Design for a limited amount of areas in the Westerncorridor of Sumatra. It will also include the review (and revision) of the National Standard andManual (NSPM) related to the slope protection, and capacity building.
Following the problem that arise in Civil Works of WINRIP especially in related to slope stability,the Consultant is assigned to design the slope stability in Package No. 5 : Sp. Rampa – Poriaha asone of the 5 (five) priority locations. The expected final outputs are design structure of slopestability and structure of road user safety against landslide include design drawing, bill ofquantities and material specification to be additional contract for Package No. 05 above. Until thismonth the consultant had been completed the evaluation for priotity location with highest riskbased on Pusjatan Guideline. There are 5 location with highest risk as follows: 1 location in NorthSumatera (Ruas Rampa – Poriaha), 1 location in Lampung (Ruas Sp. Gunung Kemala – Pg Tampak),1 Location in West Sumatera (Ruas Bukit Putus – Teluk Bayur) and 2 location in Aceh (both on RuasBatas Kota Banda Aceh – Batas Aceh Barat). DED for slope treatment at Sp. Rampa – Poriahaand 4 (four) other design works have been complete.
For other assignment of TA, the consultant had been conducted desk study to identify, review andconduct a preliminary inventory of the road sections/areas that have already slope andembankment problems and those that are prone to the erosions/landslides. Furthermore, fieldsurveys have been conducted along west coast of Sumatera Island on 526 spots identified by deskstudy, resulting from this survey and desk study was presented as the Risk Map of slope stabilityalong West Coast of Sumatera Island. Review of some NSPMs related to slope treatment on roadproject had done.
The NSPM Product for Guidelines and Specifications have been presented in the workshop on Jktdate, 28-May-2018 input from participants have been accommodated in the final product.Capacity building - the final workshop that is planned to be held early June is canceled and deletefrom the contract.
Shown in the Table 3.4 is the present status of the Technical Assistance for Development osSlope Stabilization, Design and Management contract.
Table 3.4Description USD IDR
Original Contract plus 10% VAT 170,830 7,234,700,000
Addendum No.1 plus 10% VAT 170,830 7,234,700,000
Variance Against Original Contract - -
Addendum No.2 plus 10% VAT 91,465 5,967,912,500
Variance Against Original Contract - 46.46% - 17.51%
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
3 - 9
3.4 CSC ConsultantsConstruction Supervision Consultant (CSC) for Rehabilitation and Reconstruction Works inCentral Sulawesi under WINRIP; Selection for this consultancy service has been started onMay 17, 2017 by announced it at LPSE Ministry of Public Works and Housing and UNDBOnline. Contract signature was done on December 9, 2019 and commencement of service onDecember 17, 2019. The interim CSC is acted to supervise the civil work which have begun onend-October 2019 until taking over to definitive CSC scheduled on early January 2020.
Shown in the Table 3.5 is the present status of the Construction Supervision ConsultantContract.
Table 3.5Description USD IDR
Original Contract plus 10% VAT 357,170 10,080,823,500
3.5 Others
Under Category 3 of Loan Agreement the three (3) consultancy packages (capacity building for disasterrisk reduction, environmental management and road safety) has been cancelled. As a result of thecancellation of the three (3) Technical Assistances, the “Technical Assistance for Development of SlopeStabilization, Design and Management” has been included as replacement, but to be part of the LoanCategory-2;
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 1
4 CIVIL WORKS
4.1 Detailed Design Preparation
Final Engineering Designs, Engineer’s Estimates and bidding documents have been completed for allprojects proposed for WP-1, WP-2, and WP-3.
A brief status of the eighteen (18) sub-projects relative to the procurement of Civil works contractsand implementation can be found in “Implementation Status” table on Page 1-2 of this Report.The progresses of road safety audit are shown in Appendix B.
4.2 Procurements
Procurement shall be conducted under the Bank’s Procurement Procedures as mentioned in the LoanAgreement. The International Competitive Bidding (ICB) based on the Bank letter Ref. WINRIP/136 willapply to the packages with the construction estimated cost of more than US$ 25 Million to comply withthe new Bank’s threshold for ICB. According to the GOI regulation, a prequalification shall be applied forthe packages with the construction estimated cost more than IDR 10 Billion. Review from previousprocurement process, the World Bank in the Aide Memoire requested to GOI, for next 4 ICB subprojectsqualification still used Pre-Qualification and for remaining sub-project must be process with PostQualification. As well as for all NCB the World Bank also requested to follow Post Qualification inprocurement process.
As of this reporting month, a more detailed current updates are fully indicated in Sub-Chapter 1.4Procurement of Civil Works Contract Under Category 1 on Page 1-6 of this Report.
Under Category 3 of Loan Agreement the three (3) consultancy packages (capacity building for disasterrisk reduction, environmental management and road safety) has been cancelled. As a result of thecancellation of the three (3) Technical Assistances, the “Technical Assistance for Development of SlopeStabilization, Design and Management” has been included as replacement, but to be part of the LoanCategory-2;
As of this reporting month, a more detailed current updates are fully indicated in Sub-Chapter 1.4Procurement of Civil Works Contract Under Category 1 on Page 1-6 of this Report.
The WINRIP updated Procurement Plan and Progress is shown in Appendix F.
4.3 Civil Works Implementation
As of end of this reporting month, eighteen (18) of contract packages were previously completedand currently under defects liability period for twenty-four (24) months effective on the day theTOCs were issued and three (3) packages are currently under construction and 1 (one) Packagewas terminated
Details of each contract package are shown in Table 4.1.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project4 - 2
Table 4.1
ProgramContractPackage
#Contractor Name of Road Province Contract Signed Commence-
ment of Work
Original TimeExtension/Contraction
Revised
Contract Amount ContractTime
CompletionDate Contract Amount Contract Time Completion Date
AWP-1
1 PT. Jaya Konstruksi MP Tbk Biha - Krui Lampung Nov 25, 2013 Jan 8, 2014 134,909,211,000 640 CD Oct 9, 2015 93 CD 149,193,782,000 733 CD Jan 20, 2016
2 PT. Jaya Konstruksi MP Tbk Pdg. Sawah – Sp. Empatincluding Air Gadang W Sumatera Dec 6, 2013 Jan 6, 2014 197,936,699,000 730 CD Jan 5, 2016 105 CD 247,572,130,000 835 CD
Apr 14, 2016
3 PT. Jaya Konstruksi MP Tbk Manggopoh – Pdg.Sawah W Sumatera Dec 6, 2013 Jan 6, 2014 143,688,963,000 730 CD Jan 5, 2016 75 CD 183,452,130,000 805 CD Mar 17, 2016
4PT. WK - PT. Mulya Turangga(JO)
Ipuh - Bantal Bengkulu Nov 14, 2013 Jan 13, 2014 186,936,750,000 730 CD Jan 12, 2016 90 CD 212,290,705,872 820 CDMay 31, 2016
AWP-2
5PT. Nusa Konstruksi EnjiniringTbk. Sp. Rampa - Poriaha N Sumatera March 17, 2015 June 18, 2015 107,321,260,310 540 CD Dec 8, 2016 455 CD 123,132,763,368 995 CD
Jul 26, 2018
6 PT. Waskita Karya (Persero) Tbk. Ps. Pedati - Kerkap Bengkulu Feb 27, 2015 Mar 11, 2015 86,517,470,000 450 CD Jun 2, 2016 240 CD 118,444,156,000 690 CD Jan 27, 2017
7 PT. Adhi Karya Indrapura – Tapan W Sumatera Nov 26, 2015 Dec 10, 2015 129,699,900,000 630 CD Aug 30, 2017 151 CD 129,699,900,000 778 CD Jan 26, 2018
8PT. PP/PT. Statika Mitra SaranaJ.O
Bts. Kota Pariaman -Manggopoh W Sumatera Jan 28, 2016 Mar 23, 2016 355,500,000,000 720 CD Mar 12, 2018 -71 CD 378.042.000.000 649 CD
Dec 29, 2017
11 PT. HK - PT. Daya Mulya J.O. Bantal – Mukomuko Bengkulu Dec 18, 2014 Feb 23, 2015 228,899,717,000 720 CD Feb 11, 2017 104 CD 263,656,603,000 816 CD May 19, 2017
12 PT. LMA - PT. Cahaya T.A. J.O Kambang – Indrapura W Sumatera Jan 28, 2016 May 23, 2016 350,643,730,000 720 CD May 12, 2018 232 CD 354,144,630,000 952 CDFeb 2, 2019
13 PT. Waskita Karya (Persero) Tbk. Sp. Rukis – TJ. Kemuning Bengkulu Dec 18, 2014 July 22, 2015 292,700,000,000 720 CD July 10, 2017 309 CD 305,886,100,000 1029 CD May 15, 2018
AWP-3
14PT. Yasa Patria Perkasa/Conbloc,JO Painan – Kambang W Sumatera Jun 1, 2016 Aug 3, 2016 214,327,429,680 630 CD Apr 12, 2018 415 CD 209,465,972,800 1045 CD
Nov 8, 2019
15 PT. PP (Persero) Sibolga – Bts. Tapsel N Sumatera July 13, 2015 Nov 20, 2015 260,100,000,000 810 CD Feb 6, 2018 144 CD 205,270,428,803 954 CDJul 3, 2018
16 KSO PT Yasa PP-Multi Structure Ipuh - seblat Bengkulu Oct 28, 2016 Nov 8, 2016 211,374,500,000 630 CD July 30, 2018 62 D 211,374,500,000 692 CD Dec 31, 2018
17 PT. Jaya Konstruksi MP Tbk Sp. Gunung Kemala –Pugung Tampak Lampung Nov 17, 2014 Sept 4, 2015 199,551,000,000 720 CD Aug 23, 2017 126 CD 211,712,283,000 846 CD Dec 26, 2017
19 PT. Roda Tekindo Purajaya Bintunan - Lais Bengkulu Feb 27, 2015 Mar 11, 2015 33,689,452,000 300 CD Jan 4, 2016 178 CD 44,419,760.000 478 CD Jun 30, 2016
20 PT. Nindya Karya Lubuk Alung – Sicincin W Sumatera Jun 1, 2016 Sept 1, 2016 113,818,300,000 540 CD Feb 22, 2018 8 CD 113,818,300,000 548 CD Mar 2, 2018
21 PT. Multi Structure Lubuk Alung – Kuraitaji W Sumatera Jun 1, 2016 Sept 1, 2016 126,301,900,000 540 CD Feb 22, 2018 126 CD 126,301,900,000 666 CDTerminated
Continuation Works
21A PT. NKE – MJP, KSO Kurai Taji – Lubuk Alung W Sumatera Dec 21, 2018 Jan 3, 2019 83,264,709,000 150 CD Jul 1, 2019 30 CD 83,264,709,000 180 CDJul 1, 2019
5APT. Girder Indonesia Sp. Rampa – Poriaha W Sumatera Mar 21, 2019 Apr 22, 2019 77,749,292,000 300 D Feb 15, 2020 - - - -
DisasterRecovery
Works
RR-01 PT NK – Passokorang, KSO Tompe-Palu-Surumana C Sulawesi Oct 25, 2019 Oct 28, 2019 165,640,735,000 450 D Jan 19, 2021 - - - -
RR-02 PT WASKO – Sarana, KSO Birobuli-Palolo; Palupi-Simoro & Akses Huntap C Sulawesi Nov 1, 2019 Nov 4, 2019 73,335,407,795 390 D Nov 27, 2020 - - - -
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 3
4.4 Civil Works ProgressThe nine (9) contract packages under implementation program AWP-1, AWP-2, AWP-3 were alreadycompleted, and the Final Handing Over (FHO) to the client had been done.
Under the implementation program AWP-2 and AWP-3, the nine (9) packages were already completed andnow under defects liability period for two (2) years and the one (1) package was terminated by theemployer (Package #21). There is currently one (1) contract package (#5A) that is on-going construction.Physical progress of this package (Sch: 97.67%, Act: 10.86%) is lagging far behind schedule with negativeslippages, -86.81%.
In accordance with Amendment No.5 of Loan Agreement, The Rehabilitation and Reconstruction of Paludisaster recovery works, two (2) sub-projects (RR-01 ; Tompe-Palu-Surumana, RR-02 ; Palupi-Simoro,Biromaro-Palolo, Akses Huntap Pombawe) commenced from this reporting month (November 2019). Detailsof sub-project will be shown in the respective package.
Progress status of the on-going civil works contracts as of this reporting period are shown in Table 4.2.
Following are brief status of the on-going construction contract packages:
Package No. 1 : Biha – KruiThe contract package was completed on January 20, 2016 and provisionally handed over to the Employerand “Defects Notification Period” of two (2) years was completed on January 20, 2018 and finally handedover to the Employer.
ANNEX P-1 “Executive Summary Report” shows the Complete details of this package.
Package No. 2 : Padang Sawah – Sp. Empat (Including Air Gadang Bridge)The contract package was completed on April 14, 2016 and provisionally handed over to the Employer and“Defects Notification Period” of two (2) years was completed on April 14, 2018 and finally handed over tothe Employer.
ANNEX P-2 “Executive Summary Report” shows the Complete details of this package.
Package No. 3 : Manggopoh – Padang SawahThe contract package was completed on March 17, 2016 and provisionally handed over to the Employer and“Defects Notification Period” of two (2) years was completed on March 17, 2018 and finally handed over tothe Employer.
ANNEX P-3 “Executive Summary Report” shows the Complete details of this package.
Package No. 4 : Ipuh – BantalThe contract package was completed on May 31, 2016 and provisionally handed over to the Employer and“Defects Notification Period” of two (2) years was completed on May 31, 2018 and finally handed over to theEmployer.
ANNEX P-4 “Executive Summary Report” shows the Complete details of this package.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project4 - 4
Table 4.2
ProgramContractPackage
#Contractor Name of Road
Target ProgressSchedule Ending
January 2020
ActualAccomplished Slippage Time Elapsed Remaining
Time PHO Remarks
AWP-1
1 PT. Jaya Konstruksi MP Tbk Biha - Krui Completed - - - - Jan 20, 2016
2 PT. Jaya Konstruksi MP Tbk Pdg. Sawah – Sp. Empat includingAir Gadang Completed - -- - -
Apr 14, 2016
3 PT. Jaya Konstruksi MP Tbk Manggopoh – Pdg.Sawah Completed - - - - Mar 17, 2016
4 PT. WK - PT. Mulya Turangga (JO) Ipuh - Bantal Completed - - - - May 31, 2016
AWP-2
5 PT. Nusa Konstruksi Enjiniring Tbk. Sp. Rampa - Poriaha Completed 94.61% - Contract amount reduced 5.39%(Revised BOQ) Jul 26, 2018
6 PT. Waskita Karya (Persero) Tbk. Ps. Pedati - Kerkap Completed - - - - Jan 27, 2017
7 PT. Adhi Karya Indrapura – Tapan Completed - - - - Jan 26, 2018
8 PT. PP/PT. Statika Mitra Sarana J.O Bts. Kota Pariaman - Manggopoh Completed - - - - Dec 29, 2017
11 PT. HK - PT. Daya Mulya J.O. Bantal – Mukomuko Completed - - - - May 19, 2017
12 PT. LMA - PT. Cahaya T.A. J.O Kambang – Indrapura Completed 97.77% - Contract amount reduced 2.23%(Revised BOQ)
Feb 2, 2019
13 PT. Waskita Karya (Persero) Tbk. Sp. Rukis – TJ. Kemuning Completed - - - - May 15, 2018
AWP-3
14 PT. Yasa PP - Conbloc, JO Painan – Kambang Completed 98.80% - Contract amount reduced 2.3%(Revised BOQ)
Nov 8, 2019
15 PT. PP (Persero) Sibolga – Bts. Tapsel Completed 78.92% - Contract amount reduced21.08% (Revised BOQ)
Jul 3, 2018
16 PT Yasa PP-Multi Structure, KSO Ipuh - seblat Completed - - - - Dec 31, 2018
17 PT. Jaya Konstruksi MP Tbk Sp. G Kemala – Pugung Tampak Completed - - - - Dec 26, 2017
19 PT. Roda Tekindo Purajaya Bintunan - Lais Completed - - - - Jun 30, 2016
20 PT. Nindya Karya Lubuk Alung – Sicincin Completed - - - - Mar 2, 2018
21 PT. Multi Structure Lubuk Alung – Kuraitaji Completed 54.42% - - - Contract Terminated
ContinuationWorks
21A PT. NKE – MJP, KSO Kurai Taji – Lubuk Alung Completed - - - -Jul 1, 2019
5A PT. Girder Indonesia Sp. Rampa – Poriaha 97.67 % 10.86 % -86.81 % 92.98 % 21 D Critical Contract
DisasterRecovery
Works
RR-01 PT NK – Passokorang, KSO Tompe-Palu-Surumana 3.74 % 2.18 % -1.57 % 19.82 % 360 D
RR-02 PT WASKO – Sarana, KSO Birobuli-Palolo; Palupi-Simoro &Akses Huntap 3.82 % 3.61 % 0.21 % 21.08 % 307 D
* Under defects liability period for 720 calendar days.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 5
Package No. 5 : Sp. Rampa – Poriaha
The contract package is completed on July 26, 2018 and provisionally handed over to the Employer andcurrently under “Defect Notification Period” until after two years reckoned from the issuance of TOC.
ANNEX P-5 “Executive Summary Report” shows the Complete details of this package.
Package No. 5A : Sp. Rampa – Poriaha
The work progress as of this reporting month, January 2020 has been achieved of only 10.86% against thescheduled, 97.67%.
The main reasons of delayed progress are the contractor’s lacks of drilling machines and associatedequipments, like cranes, grouting machines, etc for which feasibly are met with the site conditions and theconstruction period and due to their lack of work experience same as the previously described.
The extension of time for the completion is proposed by the contractor and under review of the Engineerand Balai Office.
ANNEX P-5A “Executive Summary Report” shows the Complete details of this package.
Package No. 6 : Kerkap – Ps. Pedati
The contract package was completed on January 27, 2017 and provisionally handed over to the Employerand “Defects Notification Period” of two (2) years was completed on January 27, 2019 and finally handedover to the Employer.
ANNEX P-6 “Executive Summary Report” shows the Complete details of this package.
Package No. 7: Indrapura – TapanThe contract package was completed on January 26, 2018 and provisionally handed over to the Employerand currently under “Defects Notification Period” until after two (2) years reckoned from the issuance of theTOC.
ANNEX P-7 “Executive Summary Report” shows the Complete details of this package.
Package No. 8 : Bts. Kota Pariaman - ManggopohThe contract package was completed on December 29, 2017 and provisionally handed over to the Employerand “Defects Notification Period” of two (2) years was completed on December 29, 2019 and finally handedover to the Employer.ANNEX P-8 “Executive Summary Report” shows the Complete details of this package.
Package No. 11 : Bantal - MukomukoThe contract package was completed on May 19, 2017 and provisionally handed over to the Employer and“Defects Notification Period” of two (2) years was completed on May 19, 2019 and finally handed over tothe Employer.
ANNEX P-11 “Executive Summary Report” shows the Complete details of this package.
Package No. 12 : Kambang - IndrapuraThe contract package was substantially completed on December 31, 2018 and provisionally handed over tothe Employer on February 2, 2019 and currently under “Defects Notification Period” until after two (2)years reckoned from the issuance of the TOC.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 6
ANNEX P-12 “Executive Summary Report” shows the Complete details of this package.
Package No. 13 : Sp. Rukis – Tj. KemuningThe contract package was completed on May 15, 2018 and provisionally handed over to the Employer andcurrently under “Defects Notification Period” until after two (2) years reckoned from the issuance of theTOC.ANNEX P-13 “Executive Summary Report” shows the Complete details of this package.
Package No. 14: Painan - KambangThe contract package was completed on November 8, 2019 and provisionally handed over to the Employerand currently under “Defects Notification Period” until after two (2) years reckoned from the issuance ofthe TOC.
ANNEX P-14 “Executive Summary Report” shows the Complete details of this package.
Package No. 15: Sibolga – Bts. TapselThe contract package was completed on July 3, 2018 and provisionally handed over to the Employer andcurrently under “Defects Notification Period” until after two (2) years reckoned from the issuance of TOC.
ANNEX P-15 “Executive Summary Report” shows the Complete details of this package.
Package No. 16: Seblat – IpuhThe contract package was completed on December 31, 2018 and provisionally handed over to theEmployer and currently under “Defects Notification Period” until after two (2) years reckoned from theissuance of the TOC.
ANNEX P-16 “Executive Summary Report” shows the Complete details of this package.
Package No. 17 : Sp. Gunung Kemala – Pg. TampakThe contract package was completed on December 26, 2017 and provisionally handed over to the Employerand “Defects Notification Period” of two (2) years was completed on December 27, 2019 and finally handedover to the Employer.
ANNEX P-17 “Executive Summary Report” shows the Complete details of this package.
Package No. 19 : Lais – BintunanThe contract package was completed on June 30, 2016 and provisionally handed over to the employer and“Defects Notification Period” of two (2) years was completed on June 30, 2018 and finally handed over tothe Employer.ANNEX P-19 “Executive Summary Report” shows the Complete details of this package.
Package No. 20 : Lubuk Alung - SicincinThe contract package was completed on March 2, 2018 and provisionally handed over to the Employer andcurrently under “Defects Notification Period” until after two (2) years reckoned from the issuance of theTOC.
ANNEX P-20 “Executive Summary Report” shows the Complete details of this package.
Package No. 21 : Lubuk Alung - KuraitajiThis Package was terminated by the client on 11, July 2018.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 7
ANNEX P-21 “Executive Summary Report” shows the Complete details of this package.
Package No. 21A : Lubuk Alung – KuraitajiThe contract package was completed on July 1, 2021 and provisionally handed over to the Employer andcurrently under “Defects Notification Period” until after two (2) years reckoned from the issuance of theTOC.
ANNEX P-21A “Executive Summary Report” shows the Complete details of this package.
Package No. RR-01 : Tompe - Palu - SurumanaThe work progress as of this reporting month, has been achieved 2.18% against the scheduled, 3.74%.
Mostly the delayed progress was from Asphalt Paving Works and Drainage Works.
Asphalt Mixing Plant (AMP) is still erecting at sta 9+800 to surumana direction and to be operated on theearly March 2020.
The physical progress improvement is to be started at the time of full-scaled production of Asphalt concretefor a asphalt paving works.
Package No. RR-02 : Palupi – Simoro, Biromo – Palolo, Akses Huntap PombaweThe work progress as of this reporting month has been achieved 3.61% against the scheduled, 3.82%.
The contractor’s works forces are concentrated in the section, Akses Huntap Pombawe rather than thesection, Palupi-Simoro which is more critical area for work execution owing to 10 segment of the workingsite (Total Length: 11.275m) scatted in 33.4 km and narrow right of way (7-8m width, in Average).
The contractor was adviced for earlier start of the section, Palupi-Simoro as soonn as finishing survey worksand shop drawing due to the above mentioned reasons and remain construction period (10 months).
4.5 Quality AssuranceThe DSC will be responsible for quality assurance of materials and workmanship, certifying whether or notcontractors have achieved the required results, as well as documentation and reporting based on thefinancial management plan. They will prepare a Quality Assurance system covering all subprojects, andcontinuously monitor the effectiveness of their supervision procedures.
The following is the current status of remedial action reports on TFAC findings:
Package №.1: Krui – Bihaa) Completed.b) The package FHO was completed on January 19, 2018.c) TFAC findings formal reports from the 3rd site visit have been submitted to the WB by Dir. PJJ on 23
September, 2019
Package №.2: Padang Sawah – Sp. Empata) Completed.b) The FHO was on 19 April, 2018.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 8
Package №.3: Manggopoh – Padang Sawaha) Completed.b) The package FHO was completed on March 20, 2018.
Package №.4: Ipuh - Bantala) Completedb) The package FHO was completed on April 11, 2018.c) TFAC.WB 3rd ( as TFAC audit during defect liability period) site visit to package 04 was held on
November 7, 2017.d) Formal report was approved by the World Bank on 19 January, 2020.
Package №.5: Sp. Rampa – Poriahaa) Completedb) The package PHO was on July 26, 2018.c) TFAC findings formal reports from the 4th site visit was submitted to the WB by Dir. PJJ on 27
August 2019.
Package №.6: Ps. Pedati - Kerkapa) Completedb) The package PHO was on January 30, 2017c) CTC site visit assessing pavement work quality of package 06 on December 27 to 29, 2017.d) CTC WINRIP participated during TFAC mission site visit to package 06 on October 30 to 31, 2018.e) TFAC findings formal report from the3rd visit was submitted by PJJ to WB on 20 October, 2019.
Package №.11: Bantal - Mukomukoa) Package PHO on May 19, 2017.b) The maintenance period is two years and will end on 09 may 2019.c) TFAC findings report from the 3rd site visit dated July 11, 2018 in progress.d) TFAC findings formal report from the3rd visit was submitted by PJJ to WB on December 03, 2019.
Package №.13: Sp. Rukis – Tj. Kemuninga) Completedb) Package PHO on May 15, 2018c) Special visit of TFAC to package 13 was held on the October 31, 2018, CTC participated in the visit
the report had not taken place yet.d) TFAC.WB 3rd (as TFAC audit during defect liability period) site visit to package 13 was held on
August 27, 2019, CTC participated this visite) Both Informal report have not been approved by the World Bank.
Package №.15: Sibolga – Bts. Tapsela) Completedb) Package PHO on July 3, 2018c) CTC WINRIP visit before Tfac WB audit had been held on September 16, 2019.d) TFAC WB visit after PHO had been held on October 30, 2019.e) TFAC findings informal reports of the 3rd (after PHO) not yet submitted to the CTC by Contractor.
Package №.17: Sp. Gn. Kemala – Pugung Tampaka) Completedb) Package PHO on December 26, 2017c) TFAC WB visit after PHO had been held on April 26, 2019d) TFAC findings formal report from the3rd visit was submitted by PJJ to WB on 20 January, 2020.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 9
Package №.20: Lb. Alung - Sicincina) Completedb) Package PHO on March 2, 2018c) TFAC WB visit after PHO had been held on July 15, 2019d) Informal report was approved by the World Bank on January 19, 2020.
Package №. 21: Kuraitaji – Lb. Alunga) Package had been terminated by owner.
Package №. 07: Indrapura – Tapana) Completedb) Package PHO on January 26, 2018c) TFAC visit after PHO had been held on February 15, 2019.d) TFAC findings informal reports of the 3rd (after PHO) not yet submitted to the CTC by Contractor.
Package №. 08: Bts. Pariaman – Manggopoha) Completedb) Package PHO on December 29, 2017.c) TFAC findings formal reports of the 3rd visit from PJJ was submitted to the WB on 16 April 2019
Package №. 14: Painan – Kambanga) On going works based on contract signed on June, 2016b) PHO was on November 8, 2019.c) TFAC finding formal reports of the 3rd visit from the Director of PJJ to World Bank was submitted
on January 17, 2018.
Package №. 19: Bintunan – Laisa) Completed.b) TOC/PHO on June 30, 2016.c) CTC 3rd site visit with TFAC WB on 08 November 2017 formal report submission to WB at the latest
on February 05, 2018 had №t taken place yet.d) Informal report was approved by the World Bank on 10 January, 2020.
Package №. 12: Kambang – Indrapuraa) On going works.b) PHO on February 2, 2019c) TFAC findings formal reports of the 2nd visit from the PJJ was submitted to the WB on January 17,
2019.
Package №. 16: Seblat – Ipuha) On Going works.b) TFAC findings formal reports from site the 2nd visit had been submitted to the WB by Dir.PJJ on
April 16, 2019.c) PHO was on December 31, 2018.
Package №.: 21 A (Kuraitaji – Lubuk Alung)a) №. of Contract: 31/21A-WINRIP-AWP III/CE/A/8043/12-18b) Date of contract: on January 3, 2019.c) Contractor: NKE–MJP, JO.d) TFAC 1st visit had been held on April 22, 2019.e) TFAC 2nd visit had been held on July 15, 2019
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 10
f) Both TFAC findings formal reports of 1st and 2nd visit from the PJJ was submitted to the WB onNovember 12, 2019.
Package №.: 5 A (Slope Protection of Rampa – Poriaha)a) №. of Contract: 03-03/05 A-WINRIP-WP3/CE/A/8043/04-19b) Date of contract on April 22, 2019c) Commencement of work: №. SPMK: BM.03.04/Bb2-Wil3.S1/203d) Notice to proceed on April 22, 2019e) Contractor: PT. Girder Indonesia.f) PCM had been held on May 07 to 08, 2019g) SCM 1st had been held on August, 2019.h) SCM 2nd and SCM 3rd had been held on September, 2019.
4.6 Environmental and Social Considerations
4.6.1 Current Overall Situation
A project category is assigned to each package as either Category A, B or C depending on the likely degreeof influence on environmental issues with a brief explanation as follows:
Category A project is one which will have a significant negative impact on the environment and may havean influence on areas outside the actual project area. A project classified as such requires an Amdal (Andal,RKL&RPL) study.
Category B project is one which affects the people or the environment to some extent but with a smallerimpact than a Category A. The required environmental analysis is a UKL/UPL study only.
Category C project has minimal effect on the people or environment and an environmental analysis is notrequired. SPPL are used to handle any minor problem which may arise.
Details of packages that require environmental and social safeguard are given in Appendix E and thefollowing Table 4.3 & 4.4 provides a summary of the work involved in the 18 WINRIP packages.
Table 4.3 Environmental SafeguardWorks
ProgramNo of
PackagesNo of Investigations Approval by Remarks
DLH World Bank
AWP-1 4 6
1 - Amdal2 – UKL-UPL& 1DELH2 - SPPL
1 - Amdal2 – UKL-UPL2 - SPPL
1– EIA /WBNOLNo NeedNo Need
Coverage of SingleAmdal/EIA study arethe following Packages :
a) Packages 1 and 17b) Package 7,12 and
14c) Package 11 and 16d) Package No.08
One package have twostudies (UKL-UPL &DELH) is package No.05
AWP-2 7 7
2–Amdal +1 Amdal4 – UKL-UPL
2–Amdal +1 Amdal4 – UKL-UPL
2 EIA/WBNOLNo Need
AWP-3 7 61 - Amdal5 – UKL-UPL
1 – Amdal;5 – UKL-UPL
1 - EIANo Need
Total 18 19 Env=19 19 Env= 4,
Note: 1) UKL & UPL do not need a NOL from WB, and SPPL not necessary to submit to the WB.2) Packages 9 and 18 to be deleted & package No.21 Terminated & continue with new package No.21 A
and No 05A (but the safeguard still use old safeguard)3) single study in the same color
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 11
Table 4.4 Roads Rehabilitation & Reconstruction Of Palu Recovery WorksWorks Program No of Packages No of
InvestigationsApproval by Remarks
DLH World BankRoadsRehabilitation &ReconstructionOf PaluRecovery Works
RR – 01
Pantoloan-Tawaeli
Kebonsari-Tawaeli
Kebonsari-Tn.Runtuh
Jl.Yos Sudarso
Jl.Basuki Rahmat
Jl.Abdul Rahman Saleh
Watusampu - Ampera
Jl.Diponegoro
Jl.Malonda (Palu)
Ampera-Surumana
1 DELH Completed UnderReview CTC
complements, afterthe earthquake.
RR-02Palupi-Bangga 1 UKL-UPL Completed Under
Review CTCcomplements, afterthe earthquake
Bangga-Simoro 1 UKL-UPL Completed UnderReview CTC
complements, afterthe earthquake
Biromaru – Palolo 1 UKL-UPL Completed UnderReview CTC
complements, afterThe earthquake.The process of makingthe environmentalmanagement reportfor the January 2020semester-1 period.
Acces Huntap Pombewe 1 UKL-UPL Completed UnderReview CTC
complements, afterthe earthquake.The environmentalpermit process is in thedistrict of Sigi, and theUKL and UPL draftreports have beencompleted.
Total 5 5 = in progress 5 Completed 5 = UnderReview CTC
Note: Based on ESMF Addendum the UKL & UPL & DPLH need a NOL from WB
Palu Disaster Recovery Works
The package RR- No.01 package has been completed with the Environment Evaluation Document (DELH)and has been established through the Decision of the Governor of Central Sulawesi Number:660/773/KTHD-G.ST/ 2015 dated December 17, 2015.
In the RR-02 package for the Palupi - Bangga, Bangga - Simoro sections, an environmental permit has beenissued, for the Access Huntap segment for an environmental permit in the process at DLH Sigi Regency.Meanwhile, for the Biromaru-Palolo section it is in the mid-1 environmental monitoring report in January2020.
There are 2 design proposals at link of Biromaru - Palolo (Sta.0 + 000 - Sta.1 + 500) are as follows:1) Design following the existing road.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 12
2) Design refer to road link after earthquake which a relatively winding to avoid the impact of ProjectAffected People building.
The implication is: if the design is chosen according to the existing road, the environment safeguard alreadyexists (UKL-UPL), but if the design is chosen refer to current path (after the earthquake) there will be arevision of the UKL-UPL existing or the preparation of new UKL-UPL .
And selected design follow the original link roads and the loco government has been carried out publicsozialitation and compensation to PAPs assets (building, fence etc).
ESMF Addendum Consultation for RR-01 & RR-02 on Rehabilitation dan Reconstruction Roads postDissaster & Tsunami palu – West Sumatera Province has been implemented on 28 – 29 January 2019 atBPJN XIV office(Consultation with Stakeholeders, BPJN XIV, Satker P2JN,PU,Bappeda,Sekda, DLH at locogovernment). and SMK N 1 Sigi (project location/consultation with communities & informal leader).
Appendix E shows the Progress of Environmental Safeguard Studies.
4.6.2 Environmental and Social Issues
This section outlines the activities of the Social Impact Specialist and the Environmental Specialist duringJanuary 2020.
4.6.2.1 Environmental Issues
Generally, for safeguard all packages on WINRIP complete and on going submit to BLH for implementing,nevertheless the main environmental issues, specifically on the packages under construction are the spilledoil & diesel fuel contamination, air, noise, waste hazardous pollution also poor housekeeping beingoccurred at base camp, Air and dust pollution along stretches of thickly populated areas are not properlyaddressed by the Contractors. Water spraying is not continuously implemented. Dump trucks transportingconstruction material are not fully covered and traffic management plan is not fully implemented, generallyworkers on all packages partially not use PPT, only contractor staff has been used the PPT. Follow-up to theimplementation of the Bank's supervision mission related to the finding of base camp pollution on the allpackages under construction, The Director of Road Network Development requested that all base camppackages under construction be completed with temporary storage (TPS).
Status as 31 August 2019 CTC join surveys with Subdit LKJ and DSC to Monitoring and evaluation ofDemobilization and Return or Land Use for the Base Camp PHO on Packages No.16 (Seblat-Ipuh) and No.12(Kambang-Indrapura) of WINRIP and CTC has been submit the Report of Progress Demobilization andReturn or Land Use for the Base Camp PHO to PMU and the World Bank at 26 August 2019.
Then 2 (two) packages No. 04 & 19, the base camp used by APBN projects partially Done. & needimprovement for solar, asphalt spilled.
The packages available of hazardous waste storage (TPS) are No.05,15,08,21,14,12,13,16, 17 & 21A.
Environmental issues on each of the individual sub-projects (Packages) are shown in Appendix E of thisReport.
Monitoring of Environmental Aspects During Construction
CTC provided revised monitoring forms to DSC/CSC and Contractor for use in monitoring of environmental
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 13
and social impacts. These forms are to be used every month by the DSC/CSC Environmental Specialist.
CTC’s environmental staffs actively advises DSC/CSC on environmental monitoring, DSC/CSC have directlycarried out monitoring or to implement the Environmental and Social Safeguard and Road Safety (ESSR) forWINRIP.
CTC’s Environment Specialist monitored the implementation of environmental mitigations duringconstruction phase until the month of 30 November 2019 and the following were observed :
Package No.12 : Kambang - Indrapura
a. The project has been PHO at 25 january 2019b. The AMP, Stone crusher, genset, BC plan, heavy vehicle & material still exist at base camp 2, No
contaminated soil, the rent of base camp land still valid until Nov 2019 (CTC monitoring at 6 August2019)
Package No.14 : Painan - Kambang
The project PHO process, generally base camp condition clean, No contaminated soil around generator andfuel house, the contractor has been improved, the contractor has been submit draft schedule ofmobilization (Join Monitoring PPK, Subdit LKJ, WB & CTC at 22 October 2019)
Package.No. 16: Seblat - Ipuh
a) The project has been PHO at 12 Febraury 2019
b) There solid waste (plastic around site office) and prime coat spilled at TPS and house keeping needimprovement
c) Heavy equipment (AMP, Stone Crusher and dump trucks and other heavy equipment) owned by PT.Multi Means by Curator, (Join surveys CTC, Subdit LKJ and DSC)
Package No.05 A : Slope Protection on link of Sp.Rampa-Poriaha
The base camp selected Exist and the current status contract process with landowners (under landmeasurement process) PCM at 7-8 May 2019 completed, on going construction.Base camp improvement progress report for on going package No.14 and 21 A has been submit to PMU &World Bank on 13 June 2019.
1. Review Design Integration, Road Safety Aspects and Monitoring of Environmental Studies
Task 5.8.0 of CTC-2 TOR (Implement the Environmental and Social Analysis Management Plan/ESAMP) andparagraph 10.9 of the PMM requires ensuring that environmental management aspects of contracts havebeen implemented in accordance with AMDAL, UKL&UPL, SPPL studies and Environmental issues will beintegrated in the design and to prepare environmental mitigation on construction stage for contractor(Contractor Program for Executing Environmental Management Plan CPEMP/RKPPL). CTC has submitted toPMU all of reports of Review Integration Amdal/UKL-UPL/SPPL for original WINRIP packages at westSumatera.
2. External Monitoring Report (Satker/PPK to BLH) for Implementation of Amdal/UKL-UPL/SPPL on PreConstruction Phase, Construction Phase and Post Construction Phase.
The 3rd external monitoring reports of Amdal, UKL-UPL implementation for BLH are preparation by CTC hasbeen submit to PMU & the WB see Appendix
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 14
3. The Contractor Action Plan on Environmental Management and Monitoring (RKPPL)
The RKPPL provided by the Contractors for the packages (Packages 1,2,3,4,5,6,8,11,12,13,14,15,16,17,19,20 and 21) were completed and No Objection Letter (NOL) have been already issued by the World Bank.
4. Environmental Quarterly Report
The CTC has finalized the environmental quarterly report regularly, Period October to December 2018 hasbeen submit to PMU at January 2019 and period January to March submit to PMU at 23 May 2019).
Socialization of HIV-AIDs Campaign
The socialization of HIV-AIDs activities on 18 (eight ten) packages has been Complete, are packages No.1(Krui-Biha = 10 Nov 2015) , No.2 : Padang sawah-Sp.Empat, incl.Air Gadang bridge and No.3 manggopoh-Padang Sawah = 17 Nov 2015 and No.4 : Ipuh-Bantal = 4 Dec 2015. Package No.11 : Bantal – Muko Muko =5 Dec 2015. Package No.6 : Psr Pedati-Kerkap= 12 Jan 2016. Package No.19: Lais-Bintunan: 13 Jan 2016 thenpackage No.13 :Sp.Rukis-Tj.Kemning = 19 January 2016. Package No.5: Sp.Rampa-Poriaha = 27 Jan 2016.Package No.15: Sibolga-Bts Tapsel = 28 Jan 2016, Package No.7 (Indrapura-Tapan) & No.12 (Kambang –Indrapura) = 6 September 2016, Package No.8 (Bts.Pariaman – Manggopoh) = 4 October 2016 & PackageNo.14: Painan-Kambang was complete and all of reports has been submit to PMU/Balai and the WB, Theschedule to carried out the workshop on HIV/AIDS for new packages ongoing construction No.8 :Manggopoh-Bts.Pariaman Done 7 March 2017, No.20: Lubuk Alung-Sicincin, No.21 Lubuk Alung-KuratajiDone 8 March 2017, No.16: Seblat-Ipuh Done 15 May 2017 and No. 21 A. Done 26 March 2019 for pack ongoing No.05 A socialization of HIV-AIDS not yet Done
Quarries Management.
In most packages under construction, the project contractor purchase material from suppiers that havevalid licenses, but the supplier not implement the environmental management and monitoring plans onquarry site refer to license.
As the World Bank Safeguard Policy considers a quarry as project area of influence, we therefore urgentCTC environmental specialist to discuss this issues with the respective BLHs and check the owner of thequarry complies with the provisions in its environmental license.
The generally permission of quarry, AMP & Stone Crusher on packages WINRIP under construction thepermits from Bupati or Governor have been complete.
Package No.05 A (Slope Protection) no need quarry, because construction material will be pre cashPCM conduct at 7-8 May 2019 completed
Package No. RR-No.01 and No.RR-02 (Reconstruction & Rehabilitation Roads Post Dissaster & Tsunami Paluof Central Sulawesi Provinces.
Still Processing for quarry RR-01 and RR-02.
Health Safety IssuesHas occurred a fatal accident on July 27, 2019 in which Site Engineer – DSC pack No.21 A and the worldbank has established a process for reporting and investigating the chronology of accident.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 15
Join Site Visit between Subdit LKJ, CTC and DSC to Monitoring and Evaluation Demobilization and Returnor Land Use for the Base Camp PHO on Packages No.16 (Seblat-Ipuh) and No.12 (Kambang-Indrapura) ofWINRIP at 5 to 7 August 2019.
1. Pack No.16 : Seblat – Ipuh
PHO Schedule 21 November 2018 and actual PHO 15 February 2019 Current status in theMaintenance Period.
The package 16 contractor is PT. Yasa Patria Perkasa - PT. Multi Structure, KSOProgress of physical work (civil work) by PT. Yasa Patria Perkasa - PT. Multi Structure, KSO TheContractor for the road works along + 36 km has been completed, actual progress is 100%, whenthis includes maintenance.
The status of the base camp land is still valid until 13 November 2019. Contractors are currently preparing the documents for the Demobilization Plan and the Return of
Environmental Conditions in the Post-PHO Base Camp including the demobilization schedule forheavy equipment and materials as well as hazardous waste management.
Most of the heavy equipment of the project had not been demobilized, so were the project offices,K3 buildings, workshops, bathrooms and poses before they were unloaded and the Muslims were anumber of contract contractors and heavy equipment operators who were still on duty at the basecamp and while completing the demobilization administration while waiting for the caradministration schedule.
There are internal problems from PT. Multi Sarana as partner of PT. Yasa Patria Perkasa with otherparties outside the project, in the form of debt liability signed by sealed all heavy equipment (AMP,Stone Crusher and dump trucks and other heavy equipment) owned by PT. Multi Means by Curator,this has the implication of the company's demobilization of the company's original assets.
Aspect of environmental management, it is known that the general condition of the base camp isrelatively clean, but so do the findings of the environment that must be improved, as follows:
a) There are still a few scattered diesel fuel and a heap at the location around AMPThe AMP pool is currently not used with conditions around 2/3 of the pond is covered in silt, so
that contractors are immediately closed / added and declared AMP ponds and the batching planpool to prevent work accidents.
b) Rainwater mixed with diesel fuel in the solar house infrastructure, so that the contractor alwaysbreaks the flood and closes the oil trap to prevent the overflow of hazardous waste from thesolar house infiltration into the ground around it and routinely dredges the diesel that collects inthe oil trap.
c) Small of fuel scattered in the infrastructure of the prime coat scattered in front of the TPS sothat the contractor immediately shakes the B3 waste scattered and is incorporated into thesteering drum and stored in the TPS in the still gazing part, because the condition is halfwaythrough the TPS building when it is not gazing.
d) Ex Tires and Ex drums in front of the TPS building are placed on ground notcontainer/infrastructures.
e) A few scattered plastic and paper waste around site office so that they are collected and storedat the TPS not to be able to do solid waste burning at the base camp location
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 16
2. Pack No.12 : Kambang – Indrapura
PHO Schedule 29 July 2018 / TOC Feb 2019 - Current status in PHO administration process. Link corridor of Kambang – Indrapura along +50 km, physical progress has been completed
100%. The status of the base camp 2 land is Rent, contract, period 1 for 2 (two) years from 17
September 2016 to 18 September 2018 and then extend for 1 (one) year until 18 September2019.
based on information from the contractor that the owner of the base camp requested thatbuildings in the base camp be used (offices, mess for worker, bath rooms, kitchens, mosques,warehouses, workshop buildings and post-fire pavers around the base camp) were notdemolished by the contractor camps being given to the camp owners.
Documents for the Demobilization Plan and the Return of Environmental Conditions in thePost-PHO Base Camp including the demobilization schedule for heavy equipment and materialsunder preparing by the contractor.
Generally condition base camp 2 package No. 12 looks clean, original wanted because in thebase camp area there are tree trees as well as trees and ornamental plants in terraces andMess.
Most of the heavy equipment has not been demobilized because we are still waiting forinstructions from the center to reach the destination / new base camp. But such heavyequipment (AMP, Stone Crusher, generator set, heavy vehicles from base camp 1 have beenremoved and moved to base camp location 2.
The contractor staff and heavy equipment operators still work at base camp 2 to completeadministration and perform scheduled conditions & packing equipment as well as mobilizingnew location equipment.
However, there can be a few prime coat and diesel spills in the location around the vehiclepark, so that the contractor is always proof that it is contaminated with diesel and prime coatand incorporated into the steering drum and placed in a roofed warehouse
The conclusion as follows:
Package No 15 Sibolga – Bts.TapselA. Base Camp Pack No 15 Sibolga – Bts.Tapsel at Pinangsori
a) The package is PHO, actual PHO 30 June 2018, the current status in the maintenance period.b) The contractor pack No.15 is PT. Pembangunan Perumahan (PT.PP)c) Progress of physical work (civil work) the civil worl along 36 km completed (100%)d) The current status of the base camp being rented by CV Roganda, PT PP has been hand over
the base camp to owner at 31 December 2018.e) Demobilization of heavy equipment (Stone crusher, AMP 1, all heavy vehicles owned by PT.
PP) has been demobilized on 31 December 2018. The remaining 1 AMP belongs to PT. PP hasbeen sold to CV Roganda (land owner).
f) Declaration letter for handling base camp to land owner under process and will is being besent to the CTC immediately.
g) The current base camp has already been used by CV Roganda.h) Generally base camp area is relatively clean, however there are some findings of
environmental issues that must be corrected, as follows: There is still a little bit of asphalt scattering in locations around AMP
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 17
The AMP pool is no longer visible (covered in soil) and heavy equipment is no longeravailable.
There are puddles of rainwater at AMP locations and ex cool been. Ex concrete corn and ex zinc & iron are still left in locations around the K3 building.
B. Base Camp / Directors Kit (Pandan) All base camp buildings at Pandan (Kit Directors / Offices, Mess employees, laboratories,
consultant offices, kitchens, mosques etc.) have been demolished, the Ex base campbuildings were partially demobilized to the office of PT. PP in the city of Medan and partly(especially office supplies electronics such as refrigerators, air conditioners, motorcycles,sleeping equipment, zinc roofs, zinc fences, and building walls and ceramics were given toex PT, PP employees who lived in Sibolga.
The remaining material is ceramic, toilet and ex wood are still in the Ex base camp locationin Pandan.
Simpang Rampa - Poriaha (Package No. 05):a) The package is PHO, actual PHO 18 March 2018, the current status in the maintenance
period.b) Roads along + 9.7 km, physical progress is completed (100%), but in some road segments
there have been landslides.c) Handling base camp to land owner has been completed and the current status of base camp
being rented by PT. WIS (APBN contractor)d) Existing buildings (offices, solar houses, workshops, mess operators are not demolished /
demobilized.e) At present the base camp land is used for the operations of contractor PT. WISf) Based on information from worker that PT. NKE have sold the equipment are: 1 AMP unit,
generators of several heavy vehicles to the contractor PT. WISg) In general, the condition of base camp pack No. 05 is relatively clean and there are no spills of
B3 waste (diesel, asphalt, etc.) this is likely because AMP activities have not yet operate.
Package on Going No. 05.A (Slope Protection)a) COW Package No. 05.A on April 22 2019, PCM was held on May 7, 2019b) Schedule PHO on February 15, 2020c) A base camp lease agreement is available but not yet standard refer to spec. The base camp
is only used to temporarily store material before a landslide protection site is installed . Whileheavy equipment is directly placed in the locations of landslide protection activities.
d) Progress of construction activities is currently being carried out clearing and preparationactivities for the installation of drill points, etc.
e) The contractor uses local labor for masonry work to make drains and foremen and cooks.
Join Site Visit between Subdit LKJ, CTC and DSC to Monitoring of Demobilization and Return orLand Use for the Base Camp PHO on Packages No.21.A (Lubuk Alung - Kuraitaji) and No.14(Painan - Kambang) of WINRIP at 22 to 24 October 2019
I. Package No.21.A (Lubuk Alung – Kuraitaji)The package has been PHO no remaining civil work was found. the contractor (PT.NKE) for packageWINRIP has been returning the base camp in good condition to PT. MJP as the owner of the base
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 18
camp (PT.MJP) date 1 July 2019. (declaration in attach). Current the base camp already used forAPBN packages. basecamp condition now there are soil contaminations around AMP areas andpudle at AMP pond and and dust of pond is not managed properly. we suggest that the contractorMJP can be manage the basecamp such for package of WINRIP. The contractor has been submit thedoc return of base camp to DSC & declaration letter from base camp owner in attachment, statuscomplete.
II. Package No.14 (Painan – Kambang)the project in administration process PHO, the implementation of the basecamp managementaction plans have led to improvements. Most fuel drums, tanks and containers have been placed inthe secondary containment. Stone Crusher & weight vehicles also office, Mess, workshop, musholaetc still exist. generally base camp condition clean enough. the AMP pool & asphalt tank and solarexist not yet demobilized. Base camp leases are still valid until November 2019 the handover letterof base camp & declaration letter from land owner not yet needed. the doc of return base camp inpreparing by contractor. and there are 9 (nine) points of landslides causing blockage of drainagechannels but did not cause the broken / damaged embankment and cow crossing signs installed atmany points at link Painan - Kambang.
4.6.2.2 Social Issues
1. Monitoring Report of the LARAPPackage No. 1 : Krui – BihaProvince : Lampung
A. Previous Status:
LARAP implementation documents approved by World Bank on January 4, 2013
Monitoring Report No.1 (revised) approved by World Bank on June 26, 2013
Monitoring Report No.2 approved by World Bank on October 20, 2015.
Construction completed in January 20, 2016.
B. Pending Issues, Concern and Actions
Land certification for 150 APs is not resolved yet by Satker PJN II Lampung.
C. Update during this reporting month of January 2020
For certification 200 from 350 Aps already resolved, and the remaining of certification willconduct April 2020 by Satker II Lampung. The certification progress result being prepared bySatker.
Total PAP = 2,815; Compensated = 2,815; Percent complete = 100%.
2. Monitoring Report of the LARAPPackage No. 2 : Padang Sawah – Sp. EmpatProvince : Sumatera Barat
A. Previous Status:
LARAP documents approved by World Bank on January 13, 2013
Monitoring Report No.1 (revised) approved by World Bank on July 19, 2013
Additional LARAP Implementation documents approved by World Bank on July 21, 2014
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 19
Monitoring Report No.2 approved by World Bank on Feb. 12, 2015
Construction completed in April 19, 2016.
B. Pending Issues, Concern and Actions
a) No more issue, LARAP fully completed
C. Update during this reporting month of January 2020
a) Total PAP = 442; Compensated = 442; Percent complete = 100.00%.
3. Monitoring Report of the LARAPPackage No. 3 : Manggopoh – Padang SawahProvince : Sumatera Barat
A. Previous Status:
LARAP documents approved by World Bank on January 4, 2013
Monitoring Reports No.1, 2, 3, 4 and 5 already approved and World Bank issued No ObjectionLetter (NOL).
Final Monitoring Report approval from WB on 20 Oct 2015
Construction completed on March 17, 2016.
B. Pending Issues, Concerns and Actions
No more issue, LARAP fully completed.
C. Update during this reporting month of January 2020
a) Total PAP = 1,338; Compensated = 1,338; Percent complete = 100%.
4. Monitoring Report of the LARAPPackage No. 4 : Ipuh – BantalProvince : Bengkulu
A. Previous Status:
LARAP documents approved by World Bank on December 10, 2012
Final Monitoring Report approval from World Bank on 12 Feb 2015
Construction completed in April 11, 2016.
B. Pending Issues, Concern and Actions
No more issue, LARAP fully completed.
C. Update during this reporting month of January 2020
a) Total PAP = 257; Compensated = 257; Percent complete = 100%.
5. Monitoring Report of the LARAPPackage No. 5 : Sp. Rampa – PoriahaProvince : Sumatera Utara
A. Previous Status:
Revision of the Additional LARAP documents signed by Satker II North Sumatera Province
6 APs already be relocated to the permanent houses
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 20
Compensation for 92 from total 92 APs has been paid by Satker.
Final Monitoring report appproval from WB on 23 Oct 2018
B. Pending Issues, Concern and Actions
No more issue, LARAP fully completed.
C. Update during this reporting month of January 2020
a) Total PAP = 92; Compensated = 92; Percent complete = 100%
5A. Monitoring Report of the Labor Influx, GBV, VACPackage No. 5A : Sp. Rampa – Poriaha (Sloop Protection)Province : Sumatera Utara
A. Previous Status:
No more one illegally mining rock material in the project area, which can interfere with civilworks.
B. Pending Issues, Concern and Actions
Social Issues (Labor Influx, GBV, VAC) already be included to the Contactor’ ESMP. ESMP is underimplementation.
C. Update during this reporting month of January 2020
a) No update.
6. Monitoring Report of the LARAPPackage No. 6 : Pasar Pedati - KerkapProvince : Bengkulu
A. Previous Status:
World Bank issued on May 30, 2015 a No Objection Letter on the revised LARAP documents forimplementation.
Monitoring Report concerning the compensation payment for 546 out of 637 PAPs was given NoObjection Letter (NOL) on March 23, 2015.
Monitoring Report regarding compensation payment for the remaining 91 PAPs out of 637 PAPshas been given No Objection Letter (NOL) on January 5, 2016.
B. Pending Issues, Concern and Actions
Land certification for 72 APs is not resolved yet by Satker PJN I Bengkulu.
C. Update during this reporting month of January 2020
a) Total PAP = 637; Compensated = 637; Percent complete = 100%.
b) For certification 11 from 72 Aps already resolved, and the remaining of certification willconduct April 2020 by Satker I Bengkulu. The certification progress result being prepared bySatker.
7. Monitoring Report of the LARAPPackage No. 7 : Indrapura - TapanProvince : Sumatera Barat
A. Previous Status:
LARAP documents approved by World Bank on October 14, 2014.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 21
Implementation action plan of the LARAP was issued No Objection Letter (NOL) on March 17,2015 by the World Bank.
A report of the compensation payment for 276 from total 861 PAPs already submitted to WorldBank on February 9, 2016 and no objection letter (NOL) was issued on March 16, 2016.
Monitoring Report No. 2 for the compensation payments of 207 PAPs submitted to WB on July 21,2016 and no objection letter (NOL) was issued on August 18, 2016.
A monitoring report of the payment progress for 89 PAPs has submitted to WB and no objectionletter (NOL) was issued on November 12, 2016
A monitoring report of the payment progress for 61 PAPs has submitted to WB and no objectionletter (NOL) was issued on January 16, 2017.
A monitoring report of the payment progress for 20 PAPs has submitted to WB and no objectionletter (NOL) was issued on 22 June, 2017.
PHO of the package is 28 January 2018
Final MR for 160 APs had issued from WB on 14 Dec 2018
B. Pending Issues, Concern and Actions
No more issue, LARAP fully completed.
C. Update during this reporting month of January 2020
a) Total PAP = 813; Compensated = 813, Percent Complete = 100%.
8. Monitoring Report of the LARAPPackage No. 8 : Bts. Pariaman - ManggopohProvince : Sumatera Barat
A. Previous Status :
LARAP documents submitted to World Bank on August 7, 2014.
LARAP documents approved by World Bank on August 12, 2014.
Monitoring Report for the payment of 840 PAPs has been submitted to World Bank on January 14,2016 and issued on March 8, 2016.
Monitoring Report for compensation payment of 926 PAPs submitted to WB on May 9, 2016 andno objection letter (NOL) was issued on May 12, 2016
A monitoring report of the payment progress for 440 PAPs has submitted to WB and no objectionletter (NOL) was issued on January 9, 2017
B. Pending Issues, Concern and Actions
No more issue, LARAP fully completed.
C. Update during this reporting month of January 2020
a) Total PAP = 2,206; Compensated = 2,206; Percent complete = 100%.
9. Monitoring Report of the LARAPPackage No. 9 : Rantau Tijang – Kota AgungProvince : Lampung
Cancelled from the WINRIP Program.
10. Monitoring Report of the LARAPPackage No. 10 : Sp. Empat – Sp. Air Balam
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 22
Province : Sumatera Barat
A. Previous Status :
LARAP documents submitted to World Bank on August 7, 2014.
LARAP documents approved by World Bank on August 12, 2014.
Monitoring Report for payment of 1,421 PAPs has been submitted to World Bank on January 14,2016 and Bank issued No Objection Letter (NOL) on March 8, 2016.
B. Pending Issues, Concern and Actions
Payments for the remaining 1,190 PAPs not yet paid by Satker PJN I West Sumatera and LocalGovernment.
C. Update during this reporting month of March 2019
a) Monitoring Report for payment of 138 PAPs on-going preparation by Satker PJN I SumateraBarat.
b) PPK/Satker PJN I West Sumatera and Local Government continue the appraisal andpayment processing of the remaining PAP.
c) Total PAP = 2,915; Compensated = 1,725; Percent complete = 59.18%.
Cancelled from the WINRIP Program
11. Monitoring Report of the LARAPPackage No. 11 : Bantal - MukomukoProvince : Bengkulu
A. Previous Status :
World Bank issued on May 30, 2014 a No Objection Letter (NOL) on the revised LARAP documentsfor implementation.
Monitoring Report No.1 and No.2 were issued No Objection Letters (NOL) from the World Bank.
Monitoring Report No. 3 regarding the payment for 15 of the remaining 123 PAPs was given NoObjection Letter (NOL) on November 26, 2015
A monitoring report of the payment progress for the remaining 89 PAPs already submitted to WBand no objection letter (NOL) was issued on October 28, 2016
B. Pending Issues, Concern and Actions
No more issue, LARAP fully completed.
C. Update during this reporting month of January 2020
a) Total PAP = 243; Compensated = 243; Percent complete =100%.
12. Monitoring Report of the LARAPPackage No. 12 : Kambang - IndrapuraProvince : Sumatera Barat
A. Previous Status :
LARAP documents approved by World Bank on October 14, 2014.
Signed Action Plan of LARAP was given No Objection Letter (NOL) by the World Bank.
Monitoring Report for compensation payment of 216 PAPs submitted to WB on May 26, 2016.
A Monitoring Report of the compensation payment progress for 60 PAPs has submitted to WB
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 23
and no objection letter (NOL) was issued on November 14, 2016
A Monitoring Report of the compensation payment progress for 88 PAPs has submitted to WBand no objection letter (NOL) was issued on Feb 13, 2017
A Monitoring Report of the compensation payment progress for 265 PAPs has submitted to WBand no objection letter (NOL) was issued on June, 2017
Final MR for 1.954 APs had issued from WB on 14 Dec 2018
B. Pending Issues, Concern and Actions
No more issue, LARAP fully completed.
C. Update during this reporting month of January 2020
a) Total PAP = 2,873; Compensated = 2.873; Percent complete = 100%.
13. Monitoring Report of the LARAPPackage No. 13 : Sp. Rukis – Tj. KemuningProvince : Bengkulu
A. Previous Status :
World Bank issued on May 30, 2014 a No Objection Letter (NOL) on the revised LARAP documentsfor implementation.
Signed Action Plan of LARAP was given No Objection Letter (NOL) by the World Bank.
World Bank issued on August 18, 2015 No Objection Letter (NOL) on the monitoring Report No.1.
World Bank issued on October 13, 2015 No Objection Letter (NOL) on the monitoring Report No.2.
Monitoring Report No.3 for compensation payments of 193 PAPs in Kab. Kaur submitted to WBwhich was submitted on February 23, 2016 has been issued by the Bank the NOL on March 8,2016.
Monitoring Report No.4 for compensation payments of 188 PAPs in Kab. Kaur submitted to WBwhich was submitted on October 6, 2016 has been issued by the Bank the NOL on October 12,2016.
Monitoring Report of the payments progress for 333 PAPs has submitted to WB has been issuedby the Bank the NOL on November 18, 2016.
Monitoring Report of the payments progress for 1.090 PAPs has submitted to WB has been issuedby the Bank the NOL on March 20, 2017.
Monitoring Report of the payments progress for 186 PAPs has submitted to WB has been issuedby the Bank the NOL on May 23, 2017
B. Pending Issues, Concern and Actions
Land certification for 382 APs is not resolved yet by Satker PJN II Bengkulu.
C. Update during this reporting month of January 2020
a) NOL of Final MR for 606 APs on 04 April 2019
b) For certification 15 from 382 Aps already resolved, and the remaining of certification willconduct April 2020 by Satker II Bengkulu. The certification progress result being prepared bySatker.
c) Total PAP = 2.785; Compensated = 2.785, Percent complete = 100%
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 24
14. Monitoring Report of the LARAPPackage No. 14 : Painan - KambangProvince : Sumatera Barat
A. Previous Status :
World Bank issued on December 19, 2014 the No Objection Letter to the LARAP documents.
LARAP’s signed action plan was given No Objection Letter (NOL) by World Bank.
Monitoring Report No.1 for compensation payments of 126 PAPs submitted to WB which wassubmitted on July 20, 2016 has been issued by the Bank the NOL on August 1, 2016.
Monitoring Report of the payments progress for 62 PAPs has submitted to WB on Nov 11, 2016
Monitoring Report of the payments for 220 PAPs has been issued by the Bank the NOL on March20, 2017
Monitoring Report of the payments for 59 PAPs has been issued by the Bank the NOL on May,2017
Monitoring Report of the payments for 402 PAPs has been issued by the Bank the NOL on July 14,2017
Final Monitoring Report for 386 APs had issued from WB on 8 Jan 2019.
B. Pending Issues, Concern and Actions
No more issue, LARAP fully completed.
C. Update during this reporting month of January 2020
a) Total PAP = 2,137; Compensated = 2,137; Percent complete = 100%.
15. Monitoring Report of the LARAPPackage No. 15 : Sibolga – Bts. TapselProvince : Sumatera Utara
A. Previous Status :
World Bank approved the LARAP documents on February 6, 2014 for implementation in acquiringRoad Right of Ways and removal of obstruction.
Monitoring report No.1 for 40 of the remaining 1.554 PAPs was given No Objection Letter (NOL)on November 16, 2015.
Monitoring Report No.2 for payment of remaining 72 PAPs already submitted to World Bank.
Monitoring Report-3 for the compensation payment for 237 from the remaining 1.439 PAPsalready be submitted to WB on February 19, 2016 and Bank issued no objection letter (NOL) onMarch 16, 2016.
Monitoring Report No.4 for compensation payment of 55 PAPs submitted to WB on April 13,2016 and Bank issued no objection letter (NOL) on May 19, 2016.
Monitoring Report No.5 for compensation payment of 34 PAPs submitted to WB on August 8,2016 and Bank issued no objection letter (NOL) on August 18, 2016.
Monitoring Report No.6 for compensation payment of 127 PAPs is under submission to WB andBank issued no objection letter (NOL) on January 26, 2017.
Monitoring Report No.7 for compensation payment of 134 PAPs is under submission to WB andBank issued no objection letter (NOL) on July 14, 2017.
Monitoring Report No 8 for compensation payment progress for 815 PAPs has submitted to WBand Bank issued no objection letter (NOL) on May 9, 2018
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 25
Monitoring report for the remaining of 335 from 1852 Aps approval WB on 23 Oct 2018
B. Pending Issues, Concern and Actions
Land certification for 321 APs is not resolved yet by Satker PJN II North Sumatera.
C. Update during this reporting month of January 2020
a) For certification process of 321 Aps will conducted by Satker III North Sumatera on April2020.
b) Total PAP = 1.852; Compensated = 1.852; Percent complete = 100%.
16. Monitoring Report of the LARAPPackage No.16 : Seblat - IpuhProvince : Bengkulu
A. Previous Status :
World Bank issued on May 30, 2014 a No Objection Letter (NOL) on the revised LARAP documentsfor implementation.
World Bank issued No Objection Letter (NOL) on Monitoring Report No.1 and 2 for LARAPimplementation.
Monitoring report for 102 of the remaining 120 PAPs was given No Objection Letter (NOL) onNovember 26, 2015.
Updated LARAP documents submitted on February 22, 2016 to World Bank with NOL issued byBank on March 8, 2016.
Monitoring Report No.3 for compensation payment of 33 PAPs submitted to WB on October 24,2016 and NOL issued by Bank on November 11, 2016
B. Pending Issues, Concern and Actions
No more issue, LARAP fully completed.
C. Update during this reporting month of January 2020
a) Total PAP = 259; Compensated = 259; Percent complete = 100.00%.
17. Monitoring Report of the LARAPPackage No.17 : Sp. Gunung Kemala – Pg. TampakProvince : Lampung
A. Previous Status :
World Bank approved the corrected LARAP documents on November 12, 2013
Monitoring Report for 154 of the total 2,014 PAPs was given No Objection Letter (NOL) onOctober 13, 2015.
Monitoring Report for 735 of the remaining 1.860 PAPs was given No Objection Letter (NOL) onNovember 26, 2015.
A Monitoring Report for the compensation payments progress for 1,156 APs was given NoObjection Letter (NOL) on November 18, 2016.
Monitoring Report No.4 for compensation payment of 462 PAPs was given No Objection Letter(NOL) on April 17, 2017.
This package was PHO during Dec 2017
Monitoring report for the remaining of 61 from 2.568 Aps approval WB on 23 Oct 2018
B. Pending Issues, Concern and Actions
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 26
Land certification for 1.806 APs is not resolved yet by Satker PJN II Lampung
C. Update during this reporting month of January 2020
a) For certification 700 from 1806 Aps already resolved, and the remaining of certification willconduct April 2020 by Satker II Lampung. The certification progress result being preparedby Satker.
b) Total PAP = 2,568; Compensated = 2,568; Percent complete = 100%.
18. Monitoring Report of the LARAPPackage No.18 : Mukomuko – Bts. SumbarProvince : Bengkulu
Cancelled from the WINRIP Program.
19. Monitoring Report of the LARAPPackage No.19 : Lais - BintunanProvince : Bengkulu
A. Previous Status :
World Bank issued on May 30, 2014 No Objection Letter (NOL) on the revised LARAP documentsfor implementation
World Bank issued No Objection Letter (NOL) on Monitoring Report No.1 for the LARAPimplementation.
Monitoring Report for 208 of the remaining 272 PAPs was given No Objection Letter (NOL) onNovember 26, 2015.
A Monitoring Report for the compensation payments progress for the remaining of 64 APs hassubmitted to WB and NOL issued by Bank on November 11, 2016.
B. Pending Issues, Concern and Actions
Land certification for 193 APs is not resolved yet by Satker PJN I Bengkulu.
C. Update during this reporting month of January 2020
a) For certification 5 from 193 Aps already resolved, and the remaining of certification willconduct April 2020 by Satker II Bengkulu. The certification progress result being preparedby Satker.
b) Total PAP = 538; Compensated = 538; Percent complete = 100%.
20. Monitoring Report of the LARAPPackage No. 20 : Lubuk Alung - SicincinProvince : Sumatera Barat
A. Previous Status :
World Bank issued NOL to LARAP documents on December 19, 2014.
NOL WB of the Monitoring Report of the payments progress for 670 PAP on Sep 26, 2016.
A monitoring report of the payment progress for 280 Aps already submitted to WB and approvedby WB on April 17, 2017.
B. Pending Issues, Concern and Actions
No more issue LARAP fully completed.
C. Update during this reporting month of January 2020
a) Total PAP =950; Compensated =950; Percent complete =100%.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 27
21. Monitoring Report of the LARAPPackage No. 21 : Lubuk Alung - KuraitajiProvince : Sumatera Barat
A. Previous Status :
World Bank issued NOL to LARAP documents on December 19, 2014.
NOL WB of the Monitoring Report-1 for compensation payment of 515 out of the total 869 PAPson August 23, 2016
A Monitoring Report of the compensation payments progress for 236 Aps has submitted to WBand NOL issued by Bank on January 24, 2017
LARAP monitoring report has complete and no more further comment from WB on 6 March 2019.
B. Pending Issues, Concern and Actions
No more issue LARAP fully completed
C. Update during this reporting month of January 2020
a) Complete
b) Total PAP = 827 (updated); Compensated = 827; Percent complete = 100%.
21A.Monitoring Report of the LARAPPackage No. 21A : Lubuk Alung – Kuraitaji (Re-Tendering)Province : Sumatera Barat
A. Previous Status:
Social Issues (Labor Influx, GBV, VAC) has be included to ESMP’contractor
B. Pending Issues, Concern and Actions
No more social issues.
C. Update during this reporting month of January 2020
a) Complete.
Monitoring Report of Social Issues (the Labor Influx, GBV, VAC)
Package No. RR-1 :Province : Sulawesi Tengah
A. Previous Status:
The bidding winner already determined.
B. Pending Issues, Concern and Actions
Assessment and Action LARAP Tanahruntuh – Kebonsari and Kebonsari – Taweli will preparedmidle Feb 2020 by Satker .
Social Issues (Labor Influx, GBV, VAC) has be introduced to the Contactor and under preparation.
C. Update during this reporting month of January 2019
a) Hotline number of the GRM included the GBV – VAC issue is being provided and publishedby PPK and Contractor. HSE – Contractor is as a Focal Point - GRM
b) Prevention of GBV and VAC is being prepared by the contractor, like to include in theCompany Code of Conduct, Manajaer Code of Conduct and Individual Code of Conduct, aswell as GBV and VAC socialization plans
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 28
Monitoring Report of Social Issues (the Labor Influx, GBV, VAC)
Package No. RR-2 :Province : Sulawesi Tengah
A. Previous Status:
Bidding is under process.
B. Pending Issues, Concern and Actions
Social Issues (Labor Influx, GBV, VAC) has be introduced to the Contactor and under preparation.
Action Plan for emptying ROW area on the Biromaru – Palolo, and Akses Huntap Pombewe havenot been provided.
C. Update during this reporting month of January 2020
a) Larap implementation is going on.
b) Hotline number of the GRM included the GBV – VAC issue is being provided and publishedby PPK and Contractor. HSE – Contractor is as a Focal Point - GRM
c) Prevention of GBV and VAC is being prepared by the contractor, like to include in theCompany Code of Conduct, Manajaer Code of Conduct and Individual Code of Conduct, aswell as GBV and VAC socialization plans
4.7 Anti Corruption Issues
4.7.1 Anti‐Corruption Action Plan (ACAP)
ACAP for WINRIP was developed from the previous SRIP experiences. Basically, it has the same maincomponents of involving the Community Representative Observers (CRO) in the bid opening and ThirdParty Monitoring (TPM) during the construction supervision although modification was made on theselection process of the CROs for SRIP. Within this plan there are four main pillars as indicated separatelybelow
a) Community Representative Observers (CRO)b) Publication / Disclosurec) Complaints Handling System (CHS)d) Third Party Monitoring (TPM)
4.7.2 Community Representative Observers (CRO)
The Community Representative Observers, who are required to observe the actual bidding activities, wereappointed for WP-1 group. All of the CROs were university staff, selected in accordance with the WorldBank suggestion to request assistance from local universities.
CRO is the independent observer who is not related directly or indirectly to the Contractors, Consultants,and Suppliers or not be part of the WINRIP’s management, and not a member of any political party.
CROs selection procedures:
a. Review the criteria and qualifications of candidates for the CRO.b. Director of Planning, DGH/ as Chairman of the Project Management Unit, delegated the authority to
the selection of the CRO to the Head of National Roads Implementation Agency
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 29
(BBPJN) / Head of Procurement Services Unit (Unit Layanan Pengadaan - ULP), hereinafter referred to asHead of Balai.
c. Head of Balai to invite CRO candidates from the local universities or colleges.d. Selection of CRO to be facilitated by Balai (BBPJN) / Procurement Services Unit (Unit Layanan
Pengadaan - ULP).e. Elected CRO and substitute CRO must attend one day training to be conducted by the PMU / CTC
WINRIP.f. Head of Balai to report the result of CRO selection by attaching the Minutes of Election Meeting and
send an approval application letter of the CRO to Director of Planning DGH as the Chairman of PMU.g. Based on the report and a written request from the Head of Balai, the Director of Planning DGH as the
Chairman of PMU must sign a Letter of Agreement and the Decree of the Establishment of CROs.
The duties and obligations of CRO are:
a. CRO must be present in any procurement activity (Pre-Bid Meeting, Site Visit, Bids Submission andOpening of Bids, and Announcement of Bids Winner) by invitation of the Procurement Committee, andare required to sign the attendance list
b. If the elected CRO is unable to attend on procurement activities, a Substitute CRO shall be appointed toattend these activities.
c. In discharging of duties the Substitute CRO have the same responsibilities as elected CRO.d. The CRO / Substitute CRO, after attending the Procurement activities, required to make a report of
his/her activities and submit them to the PMU and copy furnished to the related Head of Balai.
CRO as the representative of the community is to be independent observers and in performing their dutiesvoluntarily and not demanding benefits of their works.
In the performance of its duties, the CROs receive transportation cost from their home / office to thelocation of procurement meeting, and also he / she also receives per diem or Out Station Allowance (OSA)and hotel accommodation if necessary to stay. CROs also get additional charged for their reporting costs.The financing standards adjusted to the General Cost Standard (Standar Biaya Umum) issued by theMinistry of Finance.
The CRO’s financing charged to the Contract for Consulting Services for Technical Assistance for Core TeamConsultants (CTC) No: 06-20/CTC/TA/LN/8043/1112, dated 5 November 2012.
4.7.3 Publication / Disclosure
The second task under ACAP is publication of related ACAP documents for public disclosure with easyaccess to the general public and this is mainly manifested in the ACAP segment of the WINRIP website. ThisACAP section has been being designed to attain the best possible transparency of the project.
Ministry of Public Work (MPW) will provide necessary information in the Project Implementation Plan (PIP),Project Management Manual (PMM) on its website, and in the bidding documents, such as contact pointfor complaint (mail and e-mail address, phone, fax, text message). The contact will also include the Bank’sFraud and Corruption Hotline. MPW will hold Annual Accountability Meetings to enhance accountabilityand project information sharing with civil society. The PMM will provide guidelines on disclosure of
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 30
information related to the project. MPW official website will display critical information on WINRIP toenhance both internal and external monitoring of the project:
Work Plan and Procurement Plan.
Quarterly newsletter containing information on the list of contracts, implementation progress, projectsrelated activities, number, types and status of complaints in each location. The newsletter will also bemade available to civil society in hard copy and through electronic mailing system.
Mid-Term Review Report, promptly after completion of the mid-term review implementation support iscarried out in accordance with the loan agreement;
All final audit reports (financial or otherwise, including qualified audit reports) prepared in accordancewith the loan agreement and all formal responses of the government in relation to such reports. Thepublication should be done within one month after the report is accepted as final.
Contracts awarded with information on general scope of work (with location), value, and summaryinformation of the awarded firms/ contractors. The practice in other projects demonstrates thatdisclosure of contracts awarded will help in reducing fraudulent practices
Ministry of Public Works (MPW) maintains a website: http://www.pu.go.id/, with a link to 'eproc.pu.go.id'for information on semi e-procurement or e-procurement. PMU WINRIP supported by CTC will developtheir own website: http://www.winrip-ibrd.com, and with it all the information and data about WINRIP beinputted or uploaded on this site.
In the application of one of the components of ACAP, the public disclosure and transparency, it is necessaryto spread information and increase the capacity of all stakeholders involved in the implementation of thisWINRIP project, through a variety of relevant training. The trainings have been expressed in the TOR of CTCWINRIP and described in the Project Implementation Plan (PIP).
One of the major risks to effective project implementation and management derives from the likelihoodthat project management staff does not have adequate training in or experience of the management oflarge-scale projects.
4.7.4 Complaints Handling Mechanism (CHS)
The ACAP as adopted by the Ministry of Public Works for WINRIP states on the subject of “ComplaintsHandling System”. The Community Development Specialist and the Management Information Specialist willplay a crucial role in the set-up of the Complaints Handling System (CHS) within PMU, in cooperation withthe PMU officer(s) in charge of the Complaints Handling Unit (CHU).
CHS essentially has four main components as follows:
Data Entry.
All complaints are expected to be submitted through the WINRIP website but in fact, to date, mostcomplaints have been received by letter, either directly or indirectly, although a few were sent by faxor email. However, to attain the best possible transparency of the project, complaints submittedmanually through letter, facsimile, telephone, e‐ mail or visit to the Public Works regional offices willbe entered in the WINRIP website by the CHS team of CTC. The possibility of using the ‘short messageservice’ (SMS) from a cell phone for complaints was considered and it was decided that all SMS
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
4 - 31
messages, although not treated as formal complaints, will be recorded as additional information.
Complaint Registration.
Every submitted complaint is registered and stored into the CHS database, categorized, and sent tothe correlated expert for future consultation in order to formulate a response.
Complaint Assessment.
The CHS Team assesses the urgency and complexity of all complaints. Simple complaints are followedby the formulation of a response for PMU’s approval before uploading the formal response into theWINRIP website. Complex complaints are followed by a thorough investigation.
Field Investigation and Analysis.
In the case of an investigation being required, the CHS team will make field visits and take necessaryaction such as discussion with related institutions (Satker, Dinas, Supervision Consultant, etc); invitethe complainer; interview the contractor; etc. Findings will be used for analysis to formulate aconclusion, solution, next action and any further decision.
4.7.5 Third Party Monitoring (TPM)
All WINRIP packages are designed to have external parties involved in conducting an independentassessment of the project throughout construction. Project information is accessible through the WINRIPwebsite (under construction), project information booth which is normally maintained in thePPK/Satker/Dinas office or, project announcement (billboard) at each site. ACAP requires a third party, fromoutside the project, to independently monitor the progress of construction work of each link and thesepersonnel are provided by universities nearby each package.
It was decided that the best method of recruitment for TPM was through the universities closest to eachpackage and PMU mailed invitations asking them to express their interest in forming independentmonitoring teams of Third Party Monitors. This concept is based on the fact that Universities/TechnicalFaculties have the engineers available for recruitment and Universities could use this opportunity to beinvolved in public service. It is hoped that this concept will be more effective and more efficient in gettinglegitimate, competent, independent Third Party Monitoring (TPM).
The duties of a TPM included:
a) Report to the PPK for his intended package and obtain copies of all drawings and contractdocumentation.
b) Make at least three (3) separate visits to site, with each visit up to four (4) days long, and ascertain thatthe works are being carried out in compliance with the drawings and documentation.
c) Prepare and submit a report for the PMU following each visit with their last report post PHO.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
5 - 1
5 FINANCIAL & MANAGEMENT INFORMATION SYSTEMS
5.1 Draw‐Downs and Future Costs
Details of the disbursements already made from the loan are listed in the followingsub‐section.
5.2 Disbursement
The total disbursement by World Bank from the loan to the end of January 2020 was USD206,618,392.21 equivalent to approximately 82.7 % of the loan funds.
The total expenditure to date measured in the term of the World Bank commitment isshown in Appendix C. The following table summarizes the individual disbursements ascalculated by CTC but retaining the total disbursement from Client Connection at the end ofJanuary 2020.
Category DescriptionLoan Restructuring
Amount USDTotals Disbursed toEnd of January 2020
in USD
%Disbursed
1Part 1 Betterment andCapacity Expansion of
National Roads.205,000,000.00 188,898,786.64 92.2
2Part 2
Implementation Support20,000,000.00 11,162,718.60 55.8
3Part 3
Road Sector InstitutionalDevelopment
0.00 0.00 0.0
4Part 4
Contingency for DisasterRisk Response
25,000,000.00 2,612,683.88 10.5
5 Unallocated 0.00 0.00 0.0
DA-A Designated Account 3,944,203.09
GRAND TOTAL 250,000,000.00 206,618,392.21 82.7
5.3. Management Information System
5.3.1. General OverviewThe Management Information System tasks are as follows below:
1) Information Systema. Develop and manage the File Storage as database system to store soft copy
documents into the server.b. Establish the Document Management System (DMS) to provide:
Letter Database System, used to record all information of incoming andoutgoing letter.
Document Library System, used to record all information of hard copydocuments then store it into library shelves.
c. Create and updated content of the WINRIP official website.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
5 - 2
d. Develop and updated content of the Website Geographic Information System(WebGIS) of spatial and roads information that overlay into Google Maps.
e. Develop, manage and updated content of the Financial ManagementInformation System (FMIS), the web based application to monitoring thefinancial report and the physical progress report.
f. Provide and manage of the Complaint Handling System (CHS), used andsupport the ACAP activities to accommodate complaints from the public.
2) Data Collection and Document Uploada. Collecting data and updating list of data catalog every month.b. Uploading documents into a file storage server.
3) Technical and Computer Troubleshootinga. Setting up and manage cable network of local area network and internet
connection.b. Setting up and manage hardware problem of the computer, printer, copier
and phone.c. Software installation and cleaning up of computer virus.
5.3.2. Database
A typical workflow in management of incoming and outgoing data is divided into 3types of data handling, below:
1. Hardcopy, the document is stored in a rack.2. Soft files, saved in the File Storage Server.3. Data information, inputted in database applications.
For further handling that needs to be made an integrated database managementsystem so that all data can be stored properly. The database system has beenprepared to store all of WINRIP project information in a systematic, easilytraceable, maintainable, and manageable format as outlined below with the followingsystems:
Incoming andOutgoing Data Administrator Saved
Stored
Inputted
File StorageServer
Shelves
DatabaseApplication
Soft File
Hard Copy
DataInformation
Typical Workflow ofDatabase Management
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
5 - 3
a. File Storage Server, used to stored all files of report and other document. Pleasecheck the URL address http://storage.winrip-ibrd.com.
b. Document Management System (DMS), used to record all information of letter anddocument files. The URL address of the DMS application will be athttp://dms.winrip-ibrd.com. The DMS have 2 main modules below:
1. Letter Database System, used to record all information of incoming andoutgoing letter.
2. Document Library System, used to record all information of document andreport files.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project1
6 - 1
6 PROJECT PERFORMANCE
6.1 World Bank and GOI Compliance
6.1.1 World Bank Missions
A World Bank supervision mission for implementation review took place on April 24, 2019 withMission End Date 10-May-19.
6.1.2 Agreed Key Actions and during the Coordination Meeting
Lists of the key actions monitored during the period are listed below.No. Outstanding Action By Whom Deadline Action
1 Expedite budget revision and allocation. PMU URGENT done2 Package 14 – Amend the contract in order to extend the closing
date and the performance bond. Carry out the outstandingpayments for the completed works.
PMU/DSC/Balai III
Mid-May 2019 PHO:November 8,
20193 Package 21A – Submit to the Bank the closing date extension
request.PMU/PIU/
BalaiIII/DSC
May 17, 2019 done
4 Road safety – Implement the proposed remedial measures onthe ongoing packages through variation orders.
PMU/BalaiIII/DSC
May 2019 done
5 Road safety – Prepare the TOR for the consultancy services tocarry out audits along all project corridors to identify roadsafety hazards and propose remedial actions and safetyimprovements and submit to the Bank for review.
PMU June 2019 done
6 Package 5A – Perform a pre-construction workshop. PMU/CTC/WB
May 6 – 10,2019
done
7 Procurement – Publish invitation for bids and request forexpression of interest respectively for packages RR1 and CSC.
PMU/PokjaUKPBJ
May 10, 2019 done
8 Procurement – Publish invitation for bids for package RR2. PMU/PokjaUKPBJ
June 14, 2019 done
9 Procurement – Submit to the Bank the revised procurementplan for prior review.
PMU May 10, 2019 done
10 Price escalation – Work closely with BPKP to get the approval. PMU/PIU/Balai
May 2019 done
11 Submit to the WB the confirmation letter reflecting thatsufficient budget will be allocated to conduct the splitzingprocess.
PMU/PIU Mid-June 2019 Bengkulu ProvDone
Lampung wasImplemented
North SumateraIn progress
12 Package 14 – Pay particular attention to the quality of the civilworks and reject them if the technical specification is not fullymet.
BalaiIII/DSC
Continuously PHO:November 8,
201913 Package RR2 – Send to the WB the investigation report with the
proposed remedial treatments on the liquefied areas.PMU/CTC Mid-June 2019 done
14 Packages RR1 and RR2 – Carry out a field mission to revise RR2designs.
WB Mid-July 2019 done
15 Pavement investigation – Send to the WB the pavementinvestigation reports for packages 2, 3, 4, 6, and 19.
BalaiIII/DSC
May 2019 done
16 Maintenance/Safety – Monitor that vegetation is properlytrimmed on the shoulders for all the packages, especially on thecurves, to avoid endangering road users. Drainage maintenanceand ditch cleaning to be done regularly by contractors.
Balai/DSC Regularly done
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project2
6 - 2
No. Outstanding Action By Whom Deadline Action
17 Environmental safeguards – Send to the WB the environmentalmanagement and monitoring plan of RKPPLs and UKL-UPLimplementation quarterly and every semester respectively for allpackages.
PMU/CTC Quarterly andeach semester
done
18 Environmental safeguards – Update the WINRIP’s website withall environmental documents including RKPPLs, RKPPL, DELH forpackage RR1, UKL/UPL and DPHL for package RR2 and othermonitoring reports, etc.
PMU/CTC May 15, 2019 done
19 Social safeguards – Carry out the splitzing process for packages6, 13, 15, 17 and 19.
PMU/CTC June 2018 In progress
20 Complaint Handling Unit (CHU) – Update the WINRIP’s websitewith all the received complaints through the CHU to make it fullyconsistent with the complaints list handled by the CHU of thePMU.
PMU/CTC Regularly done
21 TFAC – Send to the WB all the outstanding responses forpackages 4, 7, 13, 15 and 20.
PMU/DSC/CTC
Mid-May 2019 In progress
22 Financial Management – Submit to the WB the quarterly IFR forthe period January - March 2019.
PMU May 15, 2019 done
23 Financial Management – Submit to the WB the FY 2018 financialaudit report.
PMU June 30, 2019 done
24 Traffic data – Send to the Bank the results of the surveysconducted by Balai along the eighteen road sections.
PMU/CTC September2019
UnderInspection by
CTC25 Submit regularly to the WB the quarterly progress reports. PMU Quarterly done26 Update the newsletter quarterly, including the list of contracts,
implementation progress, project related workshops, andnumber, typology and status of complaints; and send thisnewsletter to the WB.
PMU Regularly done
27 Send the quarterly newsletter to the civil society forum in eachproject province in hard copy or through an electronic mailingsystem.
PMU This activitymust be
carried outevery calendar
quarter
done
6.1.3 The Next Supervision MissionNo Supervision Mission during this period.
6.1.4 Performance IndicatorsKey Performance Indicators are developed and agreed between the World Bank and GOI,and will be monitored over the whole project period the changes in variables will becalculated annually. The set indicators are describing in the project Appraisal Document(PAD) and the Loan Agreement between the GOI and the World Bank.
The overall progress towards achieving the PDO of increasing the effective use of selectedsections of national roads along the Western Sumatra Corridor by reducing road user costsis considered moderately satisfactory. Progress in implementation has picked up, andthere has been an advance with respect to several project indicators. In addition, a projectrestructuring is being processed which should bring the project largely back on track.
The PMU provided an update on the achievement of the indicator targets. There has been
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project3
6 - 3
relatively good progress on three of the five intermediate indicators. For one of theremaining intermediate indicators on bridge improvement, progress is expected within thenext semester. The last intermediate indicator related to institutional strengthening will becancelled in the framework of project restructuring. For the PDO indicator on AADT, CTCcarried out static traffic counts in March 2015 and confirmed that the original indicatortargets are adequate. The mission refined a few indicators definitions/baselines andupdated some indicator targets to take into account the project implementation delays.These changes will be reflected in the upcoming project restructuring.
From the “baseline 2010 AADT and estimated AADT for the year 2014/2015, theextrapolated AADT for the year 2013 resulted to 11,254 vehicles per day or 8.8% above thetargeted 10,347 vehicles per day in 2013. Shown in Table 6.1 is the comparison betweentarget and actual estimated AADT.
Table 6.1Year Targeted AADT EstimatedBaseline (2010) 7,837
FY1 (2013) target 10,347FY1 (2013) actual 11,254FY2 (2014) target 11,351FY2 (2014) actual 12,696FY3 (2015) target 12,453FY4 (2016) target 13,304
FY5 (2017) end target 14,214
Appendix I shows the updated WINRIP Performance Indicators.
6.2 Implementation Support Components
6.2.1 Core Team Consultant (CTC)
The CTC is responsible to provide support to the PMU and DGH in the management of the Project,based in Jakarta. The CTC tasks include financial and progress monitoring and reporting, informationmanagement and dissemination, quality assurance and performance review for the Design andSupervision Consultants (DSC), implementation and monitoring of the anti-corruption action plan,support for project monitoring and evaluation, and support for implementation of a trainingprogram to support project management and implementation.
The CTC contract No. 06-20/CTC/TA/LN/8043/1112 was signed on 5 November 2012 by both DGHand a Joint Venture of PT. Perentjana Djaja, Yongma Engineering Co.Ltd., and PT. EpadasconPermata Engineering Consultant.
The main CTC activities during January 2020 are as follows:
Preparation of Monthly Progress Reports. Monitoring the implementations of the ESAMP, anti-corruption action plans, complains from project
site, progress of LARAP and financial progress.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project4
6 - 4
Prepared and issued various letters to PMU and DSC. Preparing the draft of outgoing letter for PMU and PIU. Submitted various Reports to PMU concerning environmental, and Site Visit Reports of each
Specialist who conducted site inspection. Monitored the actual construction progresses of the on-going contract packages and advised PMU
of the current situations of the sub-projects. Submitted various documents to PMU concerning preparation of Palu Disaster Recovery Works. Road Safety Improvement discussion at P2JN Padang on January 8-9, 2020. Review TFAC Finding remedial action P#19 & P#13 Bengkulu on January 9-10, 2020. IQA inspection for P#07, P#12 & P#14 on January 14-18, 2020. DGH Consolidation gathering of financial report at Jogya, Banjarmasin, Denpasar, & Bekasi on
January 14-18, 22-25, 27-28, 2019 Design review of Road Safety Improvement at P2JN Padang on January 14-18, 2020 Design review of Road Safety Improvement ex P#08 on January 22, 2020 Procurement Evaluation Presentation of Palu Disaster Recovery Works at Inspectorate General-
MPWH on January 22, 2020 Implementation monitoring of Contractor & Supervision Team of Palu Disaster Recovery Works on
January 23-25, 2020 Review Road Safety Improvement of P#RR-01 & RR-02 at Palu on Jan 28-31, 2020
6.2.2 Design and Supervision Consultant (DSC)
The Design and Supervision Consultant (DSC) will be responsible for design of WP 2 and WP 3 civilworks and supervision of all civil works. They will have the role of ‘Engineer’ under a FIDIC-typecontract. The tasks include the preparation and maintenance of a quality assurance plan, validationand updating of designs, supervision of all civil works, environmental and social monitoring andmanagement, and support for financial and progress monitoring and reporting.
The DSC will also be responsible for quality assurance of materials and workmanship, certifyingwhether or not contractors have achieved the required results, as well as documentation andreporting based on the financial management plan. They will prepare a Quality Assurance systemcovering all subprojects, and continuously monitor the effectiveness of their supervision procedures.The team will be contracted and managed by DGH through the Bina Marga Regional Office (Balai II),and will be based in Padang, West Sumatera.
DSC contract was negotiated in Balai Besar Pelaksanaan Jalan Nasional II (Balai-II) of DGH. Thenegotiation result and draft contract have been sent to WB on 25 March 2013 for review andapproval. The Bank issued no objection letter on the negotiation results and draft contract withletter dated 19 April 2013.
6.2.3 Study on Development of Slope Stabilization Design and Management
This component consists of technical assistance for analytical work of an alternative design for roadsegment that pass through critical environmental assets and vulnerable areas especially on slopeprotection design and management. This activity was completed on December 20, 2018.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project5
6 - 5
6.2.4 Interim Construction Supervision Consultant (Interim CSC)
The Construction Supervision Consultant (CSC) will be responsible for supervision of all civil works,environmental and social monitoring and management, and support for financial and progressmonitoring and reporting of Palu Disaster Recovery Works.
The CSC will also be responsible for quality assurance of materials and workmanship, certifyingwhether or not contractors have achieved the required results, as well as documentation andreporting based on the financial management plan. They will prepare a Quality Assurance Plancovering all subprojects, and continuously monitor the effectiveness of their supervision procedures.The team will be contracted and managed by DGH through the Bina Marga Regional Office (BalaiXIV), and will be based in Palu, Central Sulawesi.
The CSC was selected in Balai Pengadaan Barang dan Jasa Central Sulawesi Province of DG of BinaKonstruksi MPWH. The selection result and the contract have been signed on Dec 9, 2010 and startservices on Dec 17, 2019.
6.3 Anti‐Corruption Issues
6.3.1 Anti-Corruption Action Plan (ACAP)
The main duties of the Community Development Officer are implemented of Anti-CorruptionMeasures, and Monitoring their Effectiveness. Provide assistance as required with the establishmentof anti-corruption measures necessary to support the project, and monitor and report theireffectiveness based on the Anti-Corruption Action Plan (ACAP) agreed between the World Bank andthe DGH.
The following tasks particularly need to establish procedures to be undertaken:
Selection of Community Representative Observers (CROs) of civil society groups to attend theProcurements process on key procurement steps including Pre-Bid meeting and site visit, bidssubmission and bids opening, and the announcement of the bid winner. These CROs will beinvited from local universities or other selected independent institutions, and will sign theattendance list for the procurement/selection process.
Establishment of a Third Party Monitoring (TPM) mechanism, whereby the media and civilsociety groups can become involved in monitoring the progress of the project. This Mechanismwill include regular sharing of information with the media.
Establishment and Management of a Complaints Handling Mechanism System (CHS), whichincludes maintaining project complaint log and filing to monitor status of follow-up of eachcomplaint. This mechanism will include provision for follow up investigations of substantialcomplaints by the Inspectorate General of Ministry of Public Works or third party audit to ensureindependence and reliability of the system. The CTC assignment concerns the monitoring of theaspects of Anti-Corruption Action Plan (ACAP) implementation and where required act pro-active in resolving issues when such a matter arises. The Community Development Officer has a
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project6
6 - 6
major role in monitoring performance and assists PMU in the set-up and follow-through of theComplaints Handling Unit (CHU) for the ACAP related incidents
Enhanced Disclosure Provisions and Transparency, Ministry of Public Work (MPW) have beenprovided necessary information in the Project Implementation Plan (PIP), Project ManagementManual (PMM) on their website, and in the bidding documents, such as contract point forcomplaint (mail and e-mail address, phone, fax, text message). The contact will also include theBank’s Fraud and Corruption Hotlines. MPW will hold Annual Accountability Meetings toenhance accountability and project information sharing with civil society. The PMM will provideguidelines on disclosure of information related to the project. MPW official website will displaycritical information on WINRIP to enhance both internal and external monitoring of the project
6.3.2 Community Representative Observers (CRO)
The Anti-Corruption Action Plan (ACAP) on Community Representative Observers (CROs) aspectduring January, 2020 was held relative minor activities.
The activities progress of Community Representative Observers (CROs) from January 2013 untilJanuary 2020, as shown in Appendix H1.
6.3.3 Third Party Monitoring (TPM)
The Third Party Monitoring (TPM) activity during January 2013 – January 2020 as is below:
On 20 – 22 February 2019 the Community Development Officer of CTC WINRIP was selected ofThird Party Monitoring (TPM) of packages 21A (Lubuk Alung – Kuraitaji) in West SumateraProvince.
On 18 – 19 December 2019 the Community Development Officer of CTC WINRIP was selectedand appointed of Third Party Monitoring (TPM) of Package RR-01 and RR-02 in Palu CentralSulawesi Province.
The activities progress of the Third Party Monitoring (TPM) from January 2013 until January 2020, asshown in Appendix H2.
6.3.4 Complaint Handling System (CHS)
The Community Development Officer with collaboration with MIS Specialist has developed asoftware application of Complaint Handling System (CHS) in integrated to website of WINRIPhttp://www.winrip-ibrd.com.
In the implementation of Complaint Handling System (CHS) essentially there are four maincomponents as follows:
Data Entry. Complaint Registration. Complaint Assessment. Field Clarification and Analysis.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project7
6 - 7
Problem Solving and taking the Decision
The final draft of Complaint Handling System (the framework of the complaint procedures on theweb site of WINRIP and provided ACAP inputting data in the web site) has ready to be operated.
However these applications still continuously to be refined by considering input from various parties.The CHS team has been monitored and noted the public complaints via website of Sytem InformasiPemantauan Proyek “SiPP” / Project Monitoring Information System and WINRIP website.
On January – January 2020 the Complaint Handling Unit was Not reviewed a complaint from anyparties.
The Complaints Handling Mechanism System (CHS) Activities is shown in Appendix H3.
6.3.5. Public Disclosures / Publication
Publication and disclosure is an attempt to increase transparency of information to the public, sothe public can easily to access information about the project WINRIP. Some components ofpublication and disclosures are as follows: a) announcing the information about the project throughdissemination activities and provision the leaflets, b) installation of the project information boards,c) the provision of space / project information booth, d) providing important information that canonly be accessed by public with submitted an officially applications to the authorities, and e) theprovision of information in the website which can be accessed via the internet.
The Community Development Team has sent the CRO’s activities and Third Party Monitoring (TPM)activities and has been up load to the website of WINRIP.
Data and report documents of the Community Development activities on CommunityRepresentative Observers (CROs) for 20 packages (# 01, 02, 03, 04, 05, 06, 07, 08, 10, 11, 12, 13,14, 15, 16, 17, 19, 20, 21 and 05A#) has been uploaded on the website of WINRIP, and data CROsfor Package 21A, RR-01, RR-02 and CSC is under process to upload in website.
The Third Party Monitoring (TPM) for all of 19 packages was completed selected / appointed andall of the TPM’s data has been entry /uploaded to the website of WINRIP (# 01, 02, 03, 04, 05,06, 07, 08, 10, 11, 12, 13, 14, 15, 16, 17, 19, 20 and 21).
Review and being updating of the Project Management Manual (PMM).
During January – January 2020, the Community Development team relatively minor activity on publicdisclosure / publication. The Newsletter period of January to December is under develop.
The Works Activities for Publication / Disclosure is shown in Appendix H4.
6.3.6. Action Plan for Next Month (February 2020)
The Activities plan for future months, in order of priority are as follows:
Prepare and finishing the contrac agreemen for TPM package RR-01 and RR-02 between PTPerentjana Djaja / CTC WINRIP and Tadulako University in Palu Central Sulawesi Province
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project8
6 - 8
Prepare the document TPM report for package RR-01 and RR-02 and practice its TPM reportin Palu Central Sulawesi Province.
Prepare and finishing the contrac agreement for TPM package 21A between PT PerentjanaDjaja/CTC WINRIP and Bung Hatta University in Padang West Sumatera Provice andmonitoring the TPM Report.
Prepare and finishing the Berita Acara Appointment TPM and others document for package05A and consolidation with TPM Team in Sibolga North Sumatera
Prepare and finishing the TPM Appointment Letter ( SK ) for package 05A in PMU Jakarta.
Prepare the contrac agreement for TPM package 05A between PT Perentjana Djaja/CTCWINRIP and GRaha Nusantara University in Sibolga North Sumatera Provice
6.4 Road Safety Audit
6.4.1 Activities during This Month (January 2020)Road Safety Engineer activities of this month are :
1. Discussion with P2JN Padang to review the Engineering Design of four (4) packages Road SafetyImprovement Program in West Sumatera, Padang, 8 – 9 January 2020.
2. Site survey detailed of four (4) packages Road Safety Improvement Program in West Sumatera,14 – 18 January 2020.
3. Discussion with PPK RR-01, PPK RR-02, Contractors and CSC to finalize the Road Safety featuresestimation cost with reference to the recommendations of International Road Safety Expert, 28– 31 January 2020.
6.4.2 Current status of the project for technical field as of January 2020
The Details of Program of Road Safety Audit as of the end of January 2020 are shown in the table onAppendix B.
6.5 Management Information SystemWe continue to archive all WINRIP project documents in the soft files and hard copies. Forthe soft file archive, it has been arranged neatly on the Pusdatin server at the Ministry ofPublic Works with the URL address http://103.211.51.154/storage. Whereas the hard copyarchive is still not arranged neatly in the box at the CTC-WINRIP office. For this reason, it isnecessary to work harder to tidy up the hard copy document file.
Furthermore, in addition with the collection of the as built documents and reports, in theAppendix G is documents list of completed WINRIP packages that already be collected.Other Packages send documents in hard copy. Then we need to scan it, and save as the PDFfiles. And we use the Cano pile to scanning all of them.
Regarding to document update, the DMS application is still online well. And upload activitiesinto the DMS database continues as usual. Then number of files that have been uploaded toincrease rapidly. The data that has been uploaded to the DMS database until the end of June
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project9
6 - 9
2019 are: 802 records of letters and 561 records of documents.6.5.1 Migration of WINRIP Server
1) WINRIP WebsiteWe have migrated the WINRIP website to the new server owned by the Pusdatin, Ministry ofPublic Works. The new website address is at http://binamarga.pu.go.id/winrip. And nowthe website is running online.
2) WINRIP File StorageAnd we have also migrated the WINRIP document archive to the new server owned by thePusdatin, Ministry of Public Works. The new address of WINRIP File Storage ishttp://103.211.51.154/storage.
We use the Explorer platform as a file manager to display data files. Explorer interface isvery similar to Windows Explorer on the Windows operating system, then users are familiarand easy to use this application.
6.5.2 DMS StatisticToday the DMS application already stored many file of Letters and Documents. And the nextdays will be more files are stored in the DMS database. At the end, it is expected to store allof files that related with WINRIP project.
Below is the number of Letter files that have been stored in DMS database, updates until theend of January 2020. This Letter statistics have sorted by "Package".
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project10
6 - 10
0
10
20
30
40
50
60
70
P1 K
rui -
Bih
a
P2 P
adan
g Sa
wah
- Sp
Em
pat
P3 M
angg
opoh
- Pa
dang
Saw
ah
P4 Ip
uh -
Bant
al
P5 S
p Ra
mpa
- Po
riaha
P6 P
asar
Ped
ati -
Ker
kap
P7 In
drap
ura
- Tap
an
P8 B
ts K
ota
Paria
man
- M
angg
opoh
P9 R
anta
u Ti
jang
- Ko
ta A
gung
P10
Sp E
mpa
t - S
p Ai
r Bal
am
P11
Bant
al -
Muk
omuk
o
P12
Kam
bang
- In
drap
ura
P13
Sp R
ukis
- Tj K
emun
ing
P14
Pain
an -
Kam
bang
P15
Sibo
lga
- Bat
as T
apse
l
P16
Sebl
at -
Ipuh
P17
Sp G
n Ke
mal
a - P
g Ta
mpa
k
P18
Muk
omuk
o - B
ts S
umba
r
P19
Lais
- Bin
tuna
n
P20
Lubu
k Al
ung
- Sici
ncin
P21
Lubu
k Al
ung
- Kur
aita
ji
WIN
RIP
36
28
61
25
15 1711
70
6
1612 12
6 8 5 40
14
2 2
66
Package
Letter StatisticSorted by Package
And here are the number of Document files that have been stored in DMS database, updatesuntil the end of January 2020. This Document statistics have sorted by "Document Type".
0
10
20
30
40
50
60
70
7
38
0
66
33
15 13
6 8
18
10
28
0
8
Document StatisticSorted by Document Type
Document Type
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project11
6 - 11
6.6 Quality AssuranceThe status of follow up of findings, that is finished and unfinished repair works by eachpackage is listed in appendix D of this report.
6.7 Project Risks and Mitigation Measures
6.7.1 Risks Related to Delays
Since the detailed engineering design (DED) is under responsibility of the Design andSupervision Consultant (DSC), delay on DSC establishment affected the procurement ofAWP-2 and AWP-3 sub-projects. The DED of several subprojects of WP-2 and WP-3 wereprepared and completed by respective P2JN. The CTC has then been instructed by DGH toreview the DEDs of seven packages completed by the P2JNs (package 5, 6, 11, 13, 15, 17 and19).
6.7.2 Financial Risks
The following factors will be monitored during implementation of the loan project. Loan Amount Actual Tender Prices Price Adjustments Contract Amendments (Additive or Deductive Variations) Currency Fluctuation Current Estimated Situation
No risk was detected until preparation of this report, however CTC prepared revised costestimates in anticipation of future cost claims to cover contract price escalations andvariation orders. A revised factor from 10% has been reduced to 5% for both additional costcomponents is applied on the original cost.
6.7.3 Risks Related to Quality
The quality of work is inherently tied to the competence of the Contractors and the diligenceof the Supervision Teams. The competence of contractors shall be considered at the time ofbid evaluation and prior to the award of any contract.
The quality of supervision however is influenced by the following factors:
Ensuring that supervision staff levels are fully manned with competent, honest,qualified and experienced personnel.
The provision of properly equipped laboratories with properly trained operators foreach package.
Package supervision comes under the responsibilities of the immediate supervision teamsand the relevant DSC and the Quality Assurance Engineer from CTC.
6.8 Training to Support Project ImplementationNot performed for this month.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project7 - 17 - 1
7 CURRENT ISSUES AND FOLLOW-UP ACTIONS
PACKAGE CURRENT ISSUES FOLLOW-UP Actions
# 05A Simpang Rampa - Poriaha Delayed Progress
Test Case No.2 (October 27 – November 15, 2019) results are notsatisfactory because lower point of anchoring works arerelatively well done but middle and higher points of the worksare not started owing to lack of establishing appropriate workingmethods.
Approved working methods and related mobilization ofequipments for such points are crucial to advance in progressand catch up the delayed progress.
The proposed extension of time for the completion is underreview by the Engineer.
# 06 Ps. Pedati - KerkapSplitzing program for land acquisition in province ofBengkulu is still not budgeted.
The PPK is trying to allocate the fund for splitzing program (FY 2019).
# 13 Sp Rukis - Tj KemuningSplitzing program for land acquisition in province ofBengkulu is still not budgeted.
The PPK is trying to allocate the fund for splitzing program (FY 2019).
# 14 Painan - Kambang PHO inspectionAlready completed.
# 15 Sibolga - Batas Tapsel Splitzing program for land acquisition in the provinceof North Sumatra is still not budgeted.
The PPK is trying to allocate the fund for splitzing programs(FY 2019).
# 17 Sp.Gn. Kemala - Pg.Tampak
Splitzing program for land acquisition in the provinceof Lampung is still not budgeted.
The PPK is trying to allocate the fund for splitzing programs(FY 2019).
# 19 Bintunan - LaisSplitzing program for land acquisition in province ofBengkulu is still not budgeted.
The PPK is trying to allocate the fund for splitzing program (FY 2019).
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project1
8 - 1
8 CORRESPONDENCESDuring the period the CTC received and issued letters. Lists of letters received and issued areshown in Appendix J.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
ANNEXES
Annex P-5A: Package No.5A
Annex P-RR-01: Package No.RR-01
Annex P-RR-02: Package No.RR-02
5-Jul-15 Status : 25-Jan-20Contract
BALAI Amount Time ellaps RemainingPlan (incl VAT) days days Target Highest Avg The latest
Actual IDR million % % % % % % SIMPANG RAMPA - PORIAHA II 17-Mar-15 540 8-Mar-18 130,143 100.00 94.61 (5.39) Contract amount reduced 5.39 %PT. NUSA KONSTRUKSI ENJ Tbk. Medan 18-Jun-15 455 26-Jul-18 123,133 100 100 - Revised BOQSIBOLGA - Batas TAPSEL II 13-Jul-15 810 30-Jun-18 260,100 100.00 78.92 (21.08) Contract amount reduced 21.08 %
PT. PEMBANGUNAN PERUMAHAN Medan 20-Nov-15 144 3-Jul-18 205,270 100 100 - Revised BOQ
PADANG SAWAH-SIMPANG EMPAT III 6-Dec-13 730 19-Apr-16 247,572 100 100 -PT Jaya Konstruksi MP, Tbk Padang 6-Jan-14 105 14-Apr-16MANGGOPOH - PADANG SAWAH III 6-Dec-13 730 20-Mar-16 183,542 100 100 -PT Jaya Konstruksi MP, Tbk Padang 6-Jan-14 75 17-Mar-16BATAS KOTA PARIAMAN-MANGGOPOH III 28-Jan-16 720 31-Dec-17 378,042 100 100 -PT PP - STATIKA JO Padang 23-Mar-16 -71 29-Dec-17LUBUK ALUNG - SICINCIN III 1-Jun-16 540 2-Mar-18 113,818 100 100 -PT NINDYA KARYA Padang 1-Sep-16 8 2-Mar-18KURAI TAJI - LUBUK ALUNG III 1-Jun-16 540 28-Jun-18 68,733 100.00 54.42 (45.58) Contract is terminatedPT MULTI STRUCTURE Padang 1-Sep-16 126INDRAPURA-TAPAN III 26-Nov-15 630 28-Jan-18 129,700 100 100 -PT. ADHI KARYA Padang 10-Dec-15 151 26-Jan-18KAMBANG-INDERAPURA III 28-Jan-16 720 28-Jul-18 358,650 100.00 97.77 (2.23) Contract amount reduced 2.23 %PT LANCARJAYA MA-CAHAYA TA,JO Padang 23-May-16 77 2-Feb-19 354,144 100.00 100.00 - Revised BOQPAINAN - KAMBANG III 1-Jun-16 630 27-Jul-18 214,327 100.00 98.80 (1.20) Contract amount reduced 1.2 %KSO YASA - CONBLOC Padang 3-Aug-16 94 8-Nov-19 209,465 100.00 100.00 - Revised BOQ
IPUH - BANTAL III 14-Nov-13 730 11-Apr-16 212,290 100 100 -PT WASKITA KARYA - PT DMT, JO Padang 13-Jan-14 90 31-May-16KERKAP - PASAR PEDATI III 27-Feb-15 450 28-Jan-17 118,444 100 100 -PT. WASKITA KARYA Tbk Padang 11-Mar-15 240 30-Jan-17BANTAL - MUKOMUKO III 18-Dec-14 720 26-May-17 263,656 100 100 -PT. HUTAMA KARYA - PT. DMT, JO Padang 23-Feb-15 104 19-May-17 BINTUNAN-LAIS III 27-Feb-15 300 30-Jun-16 44,419 100 100 -PT RODATEKNINDO PURAJAYA Padang 11-Mar-15 178 30-Jun-16SEBLAT - IPUH III 28-Oct-16 630 30-Sep-18 211,375 100 100PT YASA - MULTI STRUCTURE, JO Padang 8-Nov-16 62 31-Dec-18SIMPANG RUKIS-TANJUNG KEMUNING III 18-Dec-14 720 15-May-18 305,886 100 100 -PT. WASKITA KARYA Padang 22-Jul-15 309 15-May-18
BIHA - KRUI XIX 25-Nov-13 640 10-Jan-16 149,193 100 100 -PT Jaya Konstruksi MP, Tbk Lampung 8-Jan-14 93 20-Jan-16Sp.Gn KEMALA-PUGUNG TAMPAK XIX 17-Nov-14 720 27-Dec-17 211,712 100 100 -PT Jaya Konstruksi MP, Tbk Lampung 4-Sep-15 126 26-Dec-17
KURAI TAJI - LUBUK ALUNG (Lanjutan) III 21-Dec-18 150 1-Jul-19 83,625 100.00 100.00 -PT. NKE - MJP, KSO Padang 3-Jan-19 30 1-Jul-19 SIMPANG RAMPA - PORIAHA II 21-Mar-19 300 15-Feb-20 77,749 97.67 10.86 (86.81) 279 21 89.14 5.05 1.55 0.42PT. Girder Indonesia Medan 22-Apr-19 92.98% 7.02%
TOMPE-PALU-SURUMANA XIV 25-Oct-19 450 19-Jan-21 165,640 3.74 2.18 (1.57) 90 360 8.89 1.11 1.09 1.11PT. NK - Passokorang, KSO Palu 28-Oct-19 19.82% 80.18%
BIROMARU-PALOLO; PALUPI-SIMORO;AKSES HUNTAP POMBEWE XIV 1-Nov-19
39027-Nov-20 73,335 3.82 3.61 (0.21)
83 3079.64 1.60 1.20 1.60
PT Wasko - Sarana, KSO Palu 4-Nov-19 21.08% 78.92%
RR-01
RR-02
12
14
01
13
04
06
19
05A
21A
17
11
Actual Dev
Physical Progress (%)
SchTime extension
CIVIL WORKS PROGRESSWESTERN INDONESIA ROAD IMPROVEMENT PROJECT (WINRIP)
Package No. & Name PROGRESS ACHIEVEMENTTime for
CompletionTOC/ PHO
Time for CompletionCONTRACTSIGN DATE
COW
03
08
05
15
07
16
Contractor
21
02
20
1 ESR CTC 25 Jan 2020_102899E.xlsx
Plan 2020Actual Jan Feb Mar Apr Mei Jun Jul Aug Sept Oct Nov Dec Jan
Slope Protection Sp Rampa-Poriaha II 21-Mar-19 300 15-Feb-20 0.18 0.18 0.24 1.25 0.04 0.90 5.05 2.61 0.42PT Girder Indonesia Medan 22-Apr-19 Decline Decline
TOMPE-PALU-SURUMANA XIV 25-Oct-19 450 19-Jan-21 0.77 0.30 1.11PT. NK - Passokorang, KSO Palu 28-Oct-19 Decline Improved
BIROMARU-PALOLO; PALUPI-SIMORO;AKSES HUNTAP POMBEWE XIV 1-Nov-19
390
27-Nov-200.92 1.09 1.60
PT Wasko - Sarana, KSO Palu 4-Nov-19 Improved Improved
CIVIL WORKS PROGRESS per MONTH(Ongoing Construction only)
WESTERN INDONESIA ROAD IMPROVEMENT PROJECT (WINRIP)
2019
TOC/ PHO
Extension
Time forCompletion PROGRESS per MONTH (%)
RR-02
RR-01
COWBALAI
CONTRACTSIGN DATEPackage No. & Name
Contractor
05A
C:\Users\Tediero\AppData\Local\Temp\1 ESR CTC 25 Jan 2020_102899E.xlsx % Per MONTH
5-Jul-15 Status tanggal : 25-Jan-20Re Target Time for 25-Jan-20
BALAI Time ellaps Remaining maining Progress completion Est
Plan days days Target Highest Avg The latest progress per required Completion
Actual % % % % % % month month date
Slope Protection Sp Rampa-Poriaha II 21-Mar-19 300 15-Feb-20 97.67 10.86 (86.81) 279 21 89.14 5.05 1.55 0.42 89.14% 89.14%PT Girder Indonesia Medan 22-Apr-19 - - - 92.98% 7.02%
TOMPE-PALU-SURUMANA XIV 25-Oct-19450
19-Jan-21 3.74 2.18 (1.57) 90 360 8.89 1.11 1.09 1.11 97.82% 8.89% 19-Jan-21PT. NK - Passokorang, KSO Palu
28-Oct-19- - - 19.82% 80.18%
BIROMARU-PALOLO; PALUPI-SIMORO;AKSES HUNTAP POMBEWE XIV 1-Nov-19
39027-Nov-20 3.82 3.61 (0.21) 83 307 9.64 1.60 1.20 1.60 96.39% 10.71% 27-Nov-20
PT Wasko - Sarana, KSO Palu 4-Nov-19 - - - 21.08% 78.92%
ESTIMATED COMPLETION DATES OF ONGOING PAKAGESWESTERN INDONESIA ROAD IMPROVEMENT PROJECT (WINRIP)
Package No. & Name CONTRACTSIGN DATE
Time forCompletion TOC/ PHO Physical Progress (%) Time for Complation PROGRESS ACHIEVEMENT
DevContractor COW
05A
RR-01
Timeextension Sch
RR-02
Actual
Required EoT
ANNEX-P05A
MONTH :
Package No. Time Elapsed (Days) 278
Name Time Elapsed (%) 92.67
Project Manager / Satker Scheduled Progress (%) 97.670 • Late mobilization • Catch up schedule Sub Project Manager / PPK Actual Overall Progress (%) 10.860
Contractor PT. Girder Indonesia Balance (%) (86.81) • Test case of SCM-2 was FAILED • Performe SCM-3 Supervision Consultant Progress This Month (%) 0.416 GS Contractor Ekwan Yulianto • Time for completion ended Feb 15, 2020 • EoT under process SSE Consultant
Contract Sign Status date • Lack of contruction equipment • one crane has been added Commencement Date Accumulative Rp. 15.00%
Time for Complation (Days) 300 Days *) Include advance payment
Add Time for Complation (Days) Days
Take Over Date
Contract Amount Rp.
Contract Amount (+ PPN) Rp.
Comp Accum Actual Accum AccumTotal Last this to this Sch to this% Month Month Month Month
I G e n e r a l 2.11 1.81 - 1.81 1.48II D r a i n a g e 0.70 0.01 - 0.01 0.03III Earthworks 96.44 8.14 0.416 8.56 88.53IV Pavement Widening &Shoulders - -V Granular Pavement - -VI Asphalt Pavement - -VII S t r u c t u r e s 0.74 0.48 - 0.48 0.74VIII Reinstatement & MinorWorks 0.01 - -IX Day Work -X Routine MaintenanceWorks -
TOTAL 100.00 10.44 0.42 10.86 90.78Note :
Year Month May June July August Sep Oct Nop Dec Jan Feb Mar Apr May June July August Sep Oct The month of time for complation 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 Sch Original (%) - 0.56 1.12 7.80 14.48 19.49 33.70 64.78 90.78 97.67 100 Actual Progress Original (%) - 0.18 0.36 0.60 1.85 1.89 2.79 7.84 10.44 10.86 Balance (%) (0.38) (0.76) (7.20) (12.63) (17.60) (30.91) (56.94) (80.34) (86.81)Progress per month 0.18 0.18 0.24 1.25 0.04 0.90 5.05 2.61 0.42
0.24 1.25 0.04 0.90 5.05 2.61 0.42 (10.86) - - - -
PHYSICAL PROGRESS MONITORING TABLE2020
11,662,393,800
PHYSICAL WORK PROGRESS BY CATEGORY
AMO
UN
T
2019
Ir. Humisar Sitorus DISBURSEMENT *)21-Mar-19 January 25, 2020
Div Description
15-Feb-20
70,681,174,545.45
77,749,292,000.00
Khairunnisa Lubis, ST. MSc
RENARDET S.A JV PT Seecons
22-Apr-19
EXECUTIVE SUMMARY REPORT
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS05 A
TIM
E January 25, 2020Sp Rampa - Poriaha MAJOR PROBLEMS ACTION TO BE TAKEN
Jan-20
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10
PHYS
ICAL
PRO
GRES
(%)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # 05A
ORIGINAL SCH
ACTUAL
C:\Users\Tediero\AppData\Local\Temp\1 ESR CTC 25 Jan 2020_102899E.xlsx P-05A
ANNEX - P RR01
MONTH :
Package No. Time Elapsed (Days) 89 Name Time Elapsed (%) 19.78%
Scheduled Progress (%) 3.74
Project Manager / Satker Tri Bhakti Mulianto, ST,MT Actual Overall Progress (%) 2.18
Sub Project Manager / PPK Rhismono ST Balance (%) (1.57) Contractor PT Nindya Karya - Passokorang, KSO Progress This Month (%) 1.11 Supervision Consultant Interim CSC Contract Sign Commencement Date Status date Take Over Date Accumulative Rp. 15.00% Time for Complation (Days) 450 Calendar Days *) Include advance payment
Contract Amount Rp.
Comp Actual AccumTotal this
% % MonthI G e n e r a l 1.75 0.72 0.28 1.00 0.94II D r a i n a g e 19.66 0.06 0.24 0.30 1.68III Earthworks 4.59 - 0.39 0.39 0.11
IV Pavement Widening &Shoulders
- - - - -
V Granular Pavement 5.21 - - - -VI Asphalt Pavement 34.08 - - - -VII S t r u c t u r e s 20.99 0.09 0.13 0.22 0.63
VIII Reinstatement & MinorWorks
- - - - -
IX Day Work 8.67 - - - 0.02
X Routine MaintenanceWorks
5.05 0.20 0.06 0.26 0.37
TOTAL 100.00 1.07 1.11 2.18 3.74Note :●
Year Month Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Schedule Progress Original (%) 0.12 0.71 2.27 3.74 10.39 18.24 24.92 29.73 41.81 59.45 71.44 80.06 90.31 97.30 100.00 Actual Progress (%) - 0.77 1.07 2.18 Balance (%) (0.12) 0.06 (1.20) (1.57)Progress per month - 0.77 0.30 1.11
20-Jan-21 24,846,110,250.00
165,640,735,000.00
PHYSICAL WORK PROGRESS BY CATEGORY
28-Oct-19 25-Jan-20
PHYSICAL PROGRESS MONITORING TABLE
2019 2020
Div Description Accum
Last MonthAccum to
thisMonth
Sch tothis
Month
9 units have been added and now the totalexcavation equipment in the ite is 11 units
RR-01
TIM
E January 25, 2020Rekonstruksi & Rhabilitasi Ruas JalanTompe - DalamKota Palu- Surumana
MAJOR PROBLEMS ACTION TO BE TAKEN
EXECUTIVE SUMMARY REPORT25-Jan-20
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
AMO
UN
T
25-Oct-19 DISBURSEMENT *)
Lack of excavation equipmentin the site only 2 unit
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
PHYS
ICAL
PRO
GRES
(%)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # RR-01
Original Sch
Actual Progress
C:\Users\Tediero\AppData\Local\Temp\1 ESR CTC 25 Jan 2020_102899E.xlsx RR-01
ANNEX - P RR02
MONTH :
Package No. Time Elapsed (Days) 82
Name Time Elapsed (%) 21.03%
Scheduled Progress (%) 3.82 Project Manager / Satker Dr. Andri Irfan Rifai, ST,ME Actual Overall Progress (%) 3.61
Sub Project Manager / PPK Eko Prasetyo Galih,ST. Balance (%) (0.21)
Contractor PT Wasko - Sarana, KSO Progress This Month (%) 1.60
Supervision Consultant Interim CSC
Contract Sign 1-Nov-19 Commencement Date 4-Nov-19 Status date
Take Over Date Accumulative Rp. 15.00%
Time for Complation (Days) 390 Calendar Days *) Include advance payment Contract Amount Rp.
Comp Actual Accum
Total this
% % MonthI G e n e r a l 2.55 0.96 0.134 1.09 1.35II D r a i n a g e 21.06 0.26 0.480 0.74 1.29III Earthworks 4.66 0.10 0.511 0.61 0.20
IV Pavement Widening &Shoulders
- - - -
V Granular Pavement 7.37 0.54 0.445 0.98 -VI Asphalt Pavement 32.14 - - -VII S t r u c t u r e s 23.54 - - 0.06
VIII Rehabilitasi Jembatan - - - -
IX Pekerjaan Harian DanPekerjaan Lain
5.34 - 0.033 0.03 0.22
X Pekerjaan PemeliharaanKinerja
3.35 0.16 - 0.16 0.71
TOTAL 100.00 2.01 1.60 3.61 3.82
Note :●
Year
Month Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 Schedule Progress Original (%) 0.83 1.68 3.82 9.83 19.36 32.02 46.59 61.74 73.93 82.85 90.92 96.48 100.0 Actual Progress (%) 0.92 2.01 3.61 Balance (%) 0.09 0.33 (0.21)Progress per month 0.92 1.09 1.60
1.09
PHYSICAL PROGRESS MONITORING TABLE
2019
Palupi -Simoro, Biromaru- Palolo, danAkses Huntap Pombewe
73,335,407,795.00
PHYSICAL WORK PROGRESS BY CATEGORY
Div Description Accum
Last MonthAccum to
thisMonth
Sch tothis
Month
25-Jan-20
28-Nov-20 11,000,311,050.00
ACTION TO BE TAKEN
AMO
UN
T Lack of surveyors to staking out on the Palupi-Simororoad section that is hampering field engineering andstarting work on this section
The surveyor team has been updated andcurrently the progress of staking out and fieldengineering has reached 8 out of 10 plannedsegments
DISBURSEMENT *)
RR - 02
TIM
E January 25, 2020
MAJOR PROBLEMS
EXECUTIVE SUMMARY REPORT25-Jan-20
PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13
PHYS
ICAL
PRO
GRES
(%)
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULEPACKAGE # RR-02
Schedule
Actual
C:\Users\Tediero\AppData\Local\Temp\1 ESR CTC 25 Jan 2020_102899E.xlsx RR-02
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Appendix A
Overall Loan Progress
Estimated Contractor(s) or Total Est. Budget
Starting Completion Consultant(s) Man-Month WB + GOI Remarks
Date Date Name (Excl. the (PIP) Original Physical Man-Month Physical Man-Month Physical Man-Month
Supp. Staff) (USD, Excl.VAT) In IDR In USD 1st Revised 2nd Revised 3rd Revised 4th Revised 5th Revised 10th Revised ( % ) ( MM ) ( % ) ( MM ) ( % ) ( MM )
1 Betterment and Capacity 205,000,000.00 $222,678,368.65Expansion of NationalRoads
AWP-1 ICB DGH $57,821,551.951. Krui-Biha 8-Jan-14 20-Jan-16 PT. Jaya Konstruksi 134,909,211,000.00Rp $11,757,337.74 154,073,015,000Rp 140,255,020,000Rp 149,193,782,000Rp 100% 100% 0.00% FHO2. Pd. Sawah-Sp. Empat 6-Jan-14 14-Apr-16 PT.Jaya Konstruksi 197,936,699,896.00Rp $17,250,183.32 226,713,217,000Rp 249,348,931,000Rp 247,572,130,000Rp 100% 100% 0.00% FHO3. Manggopoh-Pd. Sawah 6-Jan-14 17-Mar-16 PT. Jaya Konstruksi 143,688,963,435.00Rp $12,522,493.13 165,157,772,000Rp 183,940,872,000Rp 183,452,685,000Rp 100% 100% 0.00% FHO4. Ipuh-Bantal 10-Jan-14 31-May-16 PT. Waskita Karya 186,936,750,000.00Rp $16,291,537.76 196,438,084,000Rp 194,902,179,000Rp 212,290,705,872Rp 100% 100% 0.00% Completed
AWP-2 and AWP-3 ICB &NCB DGH $164,856,816.70
5. Sp. Rampa - Poriaha 18-Jun-15 18-Mar-18 PT. Nusa Konstruksi Enjiniring Tbk 107,321,260,000.00Rp $8,084,464.03 130,143,384,830Rp 120,893,687,000Rp 123,132,763,000Rp 100% 95% -5.39% Revised BOQ
6. Ps Pedati - Kerkap 11-Mar-15 28-Jan-17 PT. Waskita Karya Tbk 86,517,470,000.00Rp $6,641,396.33 118,444,156,000Rp 100% 100% 0.00% FHO7. Indrapura - Tapan 10-Dec-15 28-Jan-18 PT. Adhi Karya 129,699,900,000.00Rp $9,350,065.79 100% 100% 0.00% Completed8. Bts. Kt Pariaman - Manggopoh 23-Mar-16 29-Dec-17 PT. PP/PT. Statika 355,500,000,000.00Rp $25,627,995.00 381,795,000,000Rp 378,042,000,000Rp 100% 100% 0.00% FHO9. R. Tijang - Kt. Agung Cancelled10. Sp Empat - Sp Air Balam Cancelled
11. Bantal - Mukomuko 23-Feb-15 26-May-17 PT. Hutama Karya - PT. DMT, JO 228,899,717,000.00Rp $18,765,198.80 262,611,303,000Rp 263,656,603,000Rp 100% 100% 0.00% FHO
12. Kambang - Indrapura 23-May-16 28-Jul-18 PT. Lancarjaya/PT. Cahaya T.A 358,650,400,000.00Rp $25,855,107.34 350,643,730,000Rp 354,144,630,000Rp 100% 97.77% -2.23% Revised BOQ
13. Sp. Rukis - Tj. Kemuning 22-Jul-15 15-May-18 PT. Waskita Karya 292,700,000,000.00Rp $23,454,051.00 305,886,100,000Rp 100% 100% 0.00% Completed14. Painan -Kambang 3-Aug-16 27-Jul-18 KSO Yasa - Conbloc 214,327,429,680.00Rp $16,286,741.38 211,755,000,000Rp 209,465,972,800Rp 100% 98.80% -1.20% Substantially Complete15. Sibolga - Bts Tap Sel 20-Nov-15 31-Dec-17 PT. PP 260,100,000,000.00Rp $19,954,872.00 205,270,429,680Rp 100% 78.92% -21.08% Revised BOQ16. Seblat - Ipuh 8-Nov-16 30-Jul-18 KSO Yasa - Conbloc 211,374,500,000.00Rp 100% 100% 0.00% Completed
17. Sp. Gunung Kemala - Pg. Tampak 4-Sep-15 26-Dec-17 PT. Jaya Konstruksi 199,551,233,000.00Rp $16,335,263.93 223,922,283,000Rp 211,712,283,000Rp 100% 100% 0.00% FHO
18. Mukomuko - Bts. Sumbar Cancelled19. Lais- Bintunan 11-Mar-15 30-Jun-16 PT. Rodatekindo Purajaya Rp 33,689,452,000.00 $2,586,125.12 Rp 44,419,760,000 100% 100% 0.00% FHO20. Lubuk Alung - Sicincin 1-Sep-16 2-Mar-18 PT. Nindya Karya Rp 113,818,300,000.00 $8,578,485.27 100% 100% 0.00% Completed21. Lubuk Alung -Kuraitaji 1-Sep-16 PT. Multi Structure Rp 126,301,900,000.00 $9,519,374.20 100% 54.42% -45.58% Contract Terminated
3-Jan-19 1-Jun-19 KSO Nusa Konstruksi Enjiniring -PT. Multikon Jagad Perkasa Rp 83,624,709,000.00 $5,750,467.38 100% 100% 0.00% Completed
5A. Sp. Rampa - Poriaha (Penanganan Lereng) 22-Apr-19 15-Feb-20 PT. Gerder Indonesia Rp 77,749,292,000.00 $5,553,520.86 97.67% 10.86% -86.81% Ongoing Construction Contingency - DGH -
2 Implementation Support 20,000,000.00
Core Team Consultants (CTC) QCBS DGH 6-Nov-12 31-Dec-17 PT. Perentjana Djaja 556 $1,276,700.00 $1,315,925.00 $1,371,925.00 $1,339,925.00 $1,450,367.33 $2,160,444.33 74.02 64.92 -9.09 Supporting PMU. Joint Venture with Rp21,415,400,000.00 Rp22,426,175,000 Rp22,458,676,500 Rp23,934,595,000 Rp37,768,533,132 Rp55,929,557,554 Yongma Engineering Co.Ltd. Or US$ equivalent total : 25-Oct-13 3-Sep-14 30-Nov-15 10-Apr-17 9-Jan-19 PT. Epadascon Permata $3,512,681.91 $3,641,077.48 $3,651,993.68 $3,757,560.86 $4,471,849.32 $6,397,531.36
Design & Superv. Consultants QCBS DGH 19-Jun-13 31-Dec-17 Renardet S.A. 1,068 $820,600.00 $1,042,900.00 $770,940.00 $965,940.00 $1,008,140.00 $1,268,040.00 62.94 49.04 -13.90 Construction Supervision.
Joint Venture with Rp51,818,705,000.00 Rp55,037,399,000 Rp54,521,056,000 Rp64,346,684,915 Rp71,957,924,596.00 Rp74,260,260,482.00 PT Cipta Strada Or US$ equivalent total : PT. Daya Creasi Mitrayasa $6,465,729.72 $6,836,310.42 $6,306,072.59 $7,465,605.14 $8,203,932.46 $8,340,445.76 PT. Seecons PT. Yodya Karya
QCBS DGH 13-Jul-17 8-Jan-18 PT. Egis International Indonesia 96 $155,300.00 $83,150.00 100 100 0 CompletedPT. Disiplan Consultant Rp6,577,000,000.00 Rp5,425,575,000.00PT. Widya Karya Or US$ equivalent total : Or US$ equivalent total :
$643,787.00 $458,556.00
QCBS DGH 17-Dec-19 31-Jan-21 287 $324,700.00Rp916,438,500,000.00
Or US$ equivalent total :$975,066.00
Incremental Operating Cost Varies PMU Rp 4,901,450,421.00 $375,418.00Including Technical Audits
3 -
4 Contingency for Disaster DGH 25,000,000.00Risk ResponseRR-01. Tompe-Palu-Surumana 25-Oct-19 19-Jan-21 PT. NK - Passongkorang, KSO Rp 165,640,735,000.00 3.74% 2.18% -1.56% Ongoing Construction
1-Nov-19 27-Nov-20 PT. WASKO - Sarana, KSO Rp 73,335,407,795.00 3.82% 3.61% -0.21% Ongoing Construction
5 Unallocated DGH -
Total 250,000,000.00 237,874,901.77
Planned Actual
21A. Lubuk Alung -Kuraitaji(Lanjutan
Development of Slope Stabilization,Design and Management
Balance
RR-02. Biromaru-Palopo; Palupi-Simoro; Akses Huntap Pombewe
Construction Supervison Consultant BOTEK Bosphorus TechnicalConsulting Corporation
Road Sector InstitutionalDevelopment
Respon-sibility
Total ( WB + GOI )
Contract Value
Appendix - AOVERALL PROGRESS STATUS
Description
WESTERN INDONESIA NATIONAL ROADS IMPROVEMENT PROJECT (WINRIP)IBRD LOAN No. 8043-ID
Proc.Metho
d
31 January 2020
PROGRESS
RevisedCategory
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Appendix B
Road Safety Audit Progress
Appendix B. Road Safety Audit Progresss January 2020)
Site VisitSubmission of
ReportSite Visit
Submission ofReport
Site VisitSubmission of
Report1. No Road Safety Audit at Design Stage.
2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Dec, 2014
3. RSA at PHO stage by CTC, February, 2016
Date 13-Nov-14 29-Dec-14 13-Nov-14 29-Dec-14 11-Feb-16 22-Feb-16 4. RSA at Operational Stage by Balai III Padang
1. No Road Safety Audit at Design Stage.
2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Dec, 2014
3. RSA at PHO stage by CTC, April, 2016
Date 9-Oct-14 5-Nov-14 9-Oct-14 5-Nov-14 6-Apr-16 12-Apr-16 4. RSA at Operational Stage by Balai III Padang
1. No Road Safety Audit at Design Stage.
2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Dec, 2014
3. RSA at PHO stage by CTC, March, 2016
Date 9-Oct-14 5-Nov-14 9-Oct-14 5-Nov-14 17-Mar-16 23-Mar-16 4. RSA at Operational Stage by Balai III Padang
1. No Road Safety Audit at Design Stage.
2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Dec, 2014
3. RSA at PHO stage by CTC, April, 2016
Date 13-Nov-14 29-Dec-14 13-Nov-14 29-Dec-14 14-Apr-16 26-Apr-161. Technical Advisory Report by International RSA CTC, Sept 2013
2. RSA at PHO stage by CTC, March, 2018
Date 08-May-13 17-Sep-13 28-Feb-18 26-Mar-181. Technical Review & RSA at Design Stage done by International RSA CTC
2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Sep, 2015
3. RSA at PHO stage by CTC, November, 2016
Date 18-Jul-13 17-Sep-13 25-Aug-15 8-Sep-15 18-Nov-16 19-Dec-161. Technical Advisory Report by International RSA CTC, Sept 2013
27-Sep-13 2. Road Safety Audit by Dit. EA & RS, May 2014
3. RSA at Construction stage by CTC, December, 2016
Date Apr-14 May-14 8-Dec-16 22-Dec-16 27-Dec-17 5-Jan-18 4. RSA at PHO stage by CTC, January, 2018
1. Technical Advisory Report by CTC, Sept 2013
27-Sep-13 2. Road Safety Audit by Dit. EA & RS, May 2014
3. RSA at Construction stage by CTC, August 2017
Date Apr-14 May-14 26-Jul-17 25-Aug-17 7-Dec-17 11-Dec-17 4. RSA at PHO stage by CTC, December 2017
1. Technical Review & RSA at Design Stage by International RSA CTC , Jul, 2013
2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Dec, 2015
3. RSA at PHO stage by CTC, April 2017
Date 18-Jul-13 18-Jul-13 17-Dec-15 29-Dec-15 11-Apr-17 24-Apr-071. Technical Advisory Report by International RSA CTC, Sept 2013
27-Sep-13 2. Road Safety Audit by Dit. EA & RS, May 2014
3. RSA at Construction stage by CTC, January 2018
Date Apr-14 May-14 17-Jan-18 6-Feb-18 28-Aug-18 10-Sep-181. Technical Advisory Report by International RSA CTC, Sept 2013
2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Mar, 2017
3. RSA at PHO stage by CTC, April, 2018
Date 18-Jul-13 18-Jul-13 23-Mar-17 3-Apr-17 5-Apr-18 20-Apr-181. RSA DED Report by CTC, June, 2015
2. RSA at Construction stage by CTC, January 2018
3. RSA at PHO stage by CTC, September, 2018
Date 15-Apr-15 15-Jun-15 16-Jan-18 30-Jan-18 30-Aug-18 12-Sep-181. Technical Advisory Report by International RSA CTC, Sept 2013
2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Aug, 2017
3. RSA at PHO stage by CTC, August, 2018
Date08-May-1321-Aug-13
23-Sep-13 28-Aug-17 25-Sep-17 24-Jul-18 6-Aug-18
1. RSA DED Report by CTC, Sept, 2014
2. RSA at Construction stage by CTC, January 2018
3. RSA at PHO stage by CTC, August, 2018
Date 14-Aug-14 1-Sep-14 29-Jan-18 15-Feb-18 26-Jul-18 8-Aug-18
110,237Process
100%
Process100%
118,993Process
100%
14 #16 Seblat – Ipuh
13 #15 Sibolga – Bts TapSel
316,304.8Process
100%
12 #14 Painan – Kambang
11 #13 SP.Rukis - TJ.Kemuning
376,479
438,675Process
100%
262,611Process
100%
10 #12 Kambang – Indrapura
9 #11 Bantal - Mukomuko
175,812Process
100%
8 #8 Bts.Pariaman – Manggopoh
7 #7 Indrapura – Tapan
374,647Process
100%
92,127Process
100%
152,870Process
100%
No RSA at Const. Stage
6 #6 PS.Pedati - Kerkap
5 #5 Sp.Rampa – Poriaha
247,105Process
100%
167,678Process
100%
4 #4 Ipuh - Bantal
3 #3 Manggopoh -Padangsawah
228,772Process
100%
163,535Process
100%
2 #2 Padangsawah - Simpangempat
1 #1 Biha - Krui
EstimatedCost /
Excl.VAT(mil. RP)
Road Safety AuditTotal Process
(%)Remarks
StatusDesign Stage Construction Stage PHO StageNo
PkgNo.
Name of Sub-project
Site VisitSubmission of
ReportSite Visit
Submission ofReport
Site VisitSubmission of
Report
EstimatedCost /
Excl.VAT(mil. RP)
Road Safety AuditTotal Process
(%)Remarks
StatusDesign Stage Construction Stage PHO StageNo
PkgNo.
Name of Sub-project
1. No Road Safety Audit at Design Stage.
2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, May, 2017
3. RSA at PHO stage by CTC, October, 2017
Date 17-18 May 2017 18-Jul-17 3-Oct-17 30-Nov-17 4. RSA at Operational Stage by Balai IV Palembang
1. Technical Advisory Report by International RSA CTC, Sept 2013
2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Sep, 2015
3. RSA at PHO stage by CTC, May, 2016
Date 18-Jul-13 17-Sep-13 25-Aug-15 8-Sep-15 19-May-16 24-May-161. RSA DED Report by CTC, June, 2015
2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Jul, 2017
3. RSA at PHO stage by CTC, January, 2018
Date 15-Apr-15 15-Jun-15 27-Jul-15 25-Aug-15 15-Jan-18 24-Jan-181. RSA DED Report by CTC, June, 2015
2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Jul, 2017
Date 15-Apr-15 15-Jun-15 25-Jul-15 25-Aug-151. RSA DED Report by CTC, June, 2015
2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Apr, 2019
3. RSA at PHO stage by CTC, July, 2019
Date 23-Apr-19 3-May-19 9-Jul-19 28-Jul-19
Date
PALU DISASTER1. RSA DED Report by CTC, March, 2019
Date 19-Feb-19 22-Mar-191. RSA DED Report by CTC, March, 2019
Date 20-Feb-19 22-Mar-19
Notes :
Road Safety Audit by International RSA CTC
Road Safety Audit by Dit. EA & RS DGH
Road Safety Audit by CTC
Road Safety Audit at Operational Stage by Balai III Padang & Balai IV Palembang
No Road Safety Audit
P#21 RSA DED Report 100%
No RSA at PHO Stage
19 #21A Lubuk Alung - Kuraitaji 65,788Process
0%No RSA at DED Stage
65,788Process
100%
54,557Process
100%
TERMINATION by DGH
No RSA at DED. Stage
18 #21 Lubuk Alung - Kuraitaji
35,886Process
100%
17 #20 Lubuk Alung – Sicincin
16 #19 Lais - Bintuan
15 #17 Sp.Gng Kemala–Pg.Tampak 255,269Process
100%
33%
20 #5ASlope Protection Works : Sp. Rampa -
Poriaha-
Process
1 RR-01 National Road 48,440Process
33%2 RR-02 Provincial Road 32,575Process
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Appendix C
Financial Progress
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Appendix C Financial Progress
The table below shows total expenditure to date measured in the terms of World BankCommitment.
DatePercentage
Completion oftime
WBExpenditureCommitment
Percentage ofAvailable
ExpenditureSource
31/03/2012 1.45% - - -30/04/2012 2.90% - - -31/05/2012 4.35% - - -30/06/2012 5.80% - - -31/07/2012 7.25% - - -30/08/2012 8.70% - - -30/09/2012 10.15% - - -31/10/2012 11.60% - - -30/11/2012 13.05% - - -31/12/2012 14.50% 800,000 0.32% Actual31/01/2013 15.95% 800,000 0.32% Actual28/02/2013 17.40% 800,000 0.32% Actual31/03/2013 18.85% 2,207,915 0.88% Actual30/04/2013 20.30% 2,207,915 0.88% Actual31/05/2013 21.75% 2,207,915 0.88% Actual30/06/2013 23.20% 2,207,915 0.88% Actual31/07/2013 24.65% 2,207,915 0.88% Actual31/08/2013 26.10% 2,207,915 0.88% Actual30/09/2013 27.55% 2,207,915 0.88% Actual31/10/2013 29.00% 2,207,915 0.88% Actual30/11/2013 30.45% 2,207,915 0.88% Actual31/12/2013 31.90% 2,207,915 0.88% Actual31/01/2014 33.35% 4,940,115 1.98% Actual28/02/2014 34.80% 4,940,115 1.98% Actual31/03/2014 36.25% 4,966,535 1.99% Actual30/04/2014 37.70% 4,966,535 1.99% Actual31/05/2014 39.15% 6,109,480 2.44% Actual30/06/2014 40.60% 6,263,610 2.51% Actual31/07/2014 42.05% 6,470,288 2.59% Actual31/08/2014 43.50% 6,470,288 2.59% Actual30/09/2014 44.95% 6,681,304 2.67% Actual31/10/2014 46.40% 6,991,757 2.80% Actual30/11/2014 47.85% 7,323,303 2.93% Actual31/12/2014 49.30% 11,533,045 4.61% Actual31/01/2015 50.75% 11,533,045 4.61% Actual28/02/2015 52.20% 12,794,201
4.61%Actual4.61%Actual
5.12% Actual31/03/2015 53.65% 14,918,776 5.97% Actual30/04/2015 55.10% 18,424,843 7.37% Actual
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
DatePercentage
Completion oftime
WBExpenditureCommitment
Percentage ofAvailable
ExpenditureSource
31/05/2015 56.55% 21,646,890 8.66% Actual30/06/2015 58.00% 23,691,573 9.48% Actual31/07/2015 59.45% 27,426,670
9.48%10.97% Actual
31/08/2015 60.90% 27,861,670 11.14% Actual30/09/2015 62.35% 31,214,254 12.49% Actual31/10/2015 63.80% 33,538,544 13.42% Actual30/11/2015 65.25% 37,740,899 15.10% Actual31/12/2015 66.70% 48,269,952 19.31% Actual31/01/2016 68.15% 48,845,535 19.54% Actual28/02/2016 69.60% 50,144,535 20.06% Actual31/03/2016 71.05% 52,938,748 21.18% Actual30/04/2016 72.50% 58,007,328 23.20% Actual31/05/2016 73.95% 61,427,937 24.57% Actual30/06/2016 75.40% 65,009,653 26.00% Actual31/07/2016 76.85% 70,619,401 28.25% Actual31/08/2016 78.30% 70,846,499 28.34% Actual30/09/2016 79.75% 74,387,379 29.75% Actual31/10/2016 81.20% 78,314,016 31.33% Actual30/11/2016 82.65% 81,725,868 32.69% Actual31/12/2016 84.10% 101,180,236 40.47% Actual31/01/2017 85.55% 102,340,497 40.94% Actual28/02/2017 87.00% 102,921,579 41.17% Actual31/03/2017 88.45% 105,584,628 42.23% Actual30/04/2017 89.90% 109,100,923 43.64% Actual31/05/2017 91.35% 112,475,095 44.99% Actual30/06/2017 92.80% 119.094.262 47.64% Actual31/07/2017 94.25% 124,057,518 49.62% Actual31/08/2017 95.70% 128.416.537 51.37% Actual30/09/2017 97.15% 132,776,084 53.11% Actual31/10/2017 98.60% 136.337.674 54.54% Actual30/11/2017 99.05% 142,023,219 56.81% Actual31/12/2017 100.00% 156,090,198 62.44% Actual
LOAN EXTENSION TIME UP TO DECEMBER 201831/01/2018 86.56% 157,742,185 63.10% Actual28/02/2018 87.69% 158,678,166 63.47% Actual31/03/2018 88.93% 160,428,518 64.17% Actual30/04/2018 90.14% 161,174,355 64.47% Actual31/05/2018 91.39% 163,525,763 65.41% Actual30/06/2018 92.60% 163,525,763 65.41% Actual31/07/2018 93.84% 174.283.884 69.71% Actual31/08/2018 95.09% 175,701,077 70.28% Actual30/09/2018 96.30% 176,481,530 70.59% Actual31/10/2018 97.55% 178.723.808 71.49% Actual30/11/2018 98.75% 179,410,372 71.76% Actual31/12/2018 100.00% 192.609.180 77.04% Actual
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
DatePercentage
Completion oftime
WBExpenditureCommitment
Percentage ofAvailable
ExpenditureSource
LOAN EXTENSION TIME UP TO FEBRUARY 202131/01/2019 76.62% 192,609,180 77.04% Actual28/02/2019 77.54% 192,609,180 77.04% Actual31/03/2019 78.46% 200,178,180 80.07% Actual30/04/2019 79.54% 200,178,180 80.07% Actual31/05/2019 80.49% 201,634,173 80.65% Actual30/06/2019 81.40% 201,634,173 80.65% Actual31/07/2019 82.35% 201,636,795 80.65% Actual31/08/2019 83.30% 201,636,795 80.65% Actual30/09/2019 84.21%
%
204,091,605 81.64% Actual31/10/2019 85.16% 204,879,591 81.95% Actual30/11/2019 86.08% 204,879,591 81.95% Actual31/12/2019 87.02% 206,618,392 82.65% Actual31/01/2020 87.97% 206,618,392 82.65% Actual
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Appendix D
Quality Assurance Progress
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Appendix D: Quality Assurance Progress
Package
# DateFollow-
UpDate
Follow-Up
DateFollow-
UpDate
FollowUp
DateFollow-
Up1 BIHA - KRUI 1-Feb-15 √ 27-Nov-15 √ 22-Nov-17 √2 PADANG SAWAH-SIMPANG EMPAT 12-Feb-15 √ 28-Oct-15 √ 17-Jan-17 √3 MANGGOPOH - PADANG SAWAH 11-Feb-15 √ 27-Oct-15 √ 17-Jan-17 √4 IPUH - BANTAL 27-May-15 √ 4-Nov-15 √ 7-Nov-17 √ Pavement crack investigation5 SIMPANG RAMPA - PORIAHA 22-Aug-16 √ 11-May-17 √ 20-Nov-17 √ 6-Aug-18 √
5 A SIMPANG RAMPA - PORIAHA6 KERKAP - PASAR PEDATI 30-Nov-15 √ 25-Aug-16 √ 9-Nov-17 √7 INDRAPURA-TAPAN 21-Nov-16 √ 17-May-17 √ 14-Feb-19 ? Finalizing follow-up report8 BATAS KOTA PARIAMAN-MANGGOPOH 17-Jan-17 √ 15-May-17 √ 1-Oct-18 √
11 BANTAL - MUKOMUKO 1-Mar-16 √ 25-Aug-16 √ 11-Jul-18 √12 KAMBANG-INDRAPURA 18-May-17 √ 3-Sep-18 √13 SIMPANG RUKIS-TANJUNG KEMUNING 28-Aug-16 √ 22-May-17 √ 31-Oct-18 ? 27-Aug-19 ? Finalizing follow-up report14 PAINAN - KAMBANG 22-Mar-17 √ 31-Oct-17 √ 3-Sep-18 √15 SIBOLGA - Batas TAPSEL 22-Aug-16 √ 11-May-17 √ 7-Aug-18 √ ?16 SEBLAT - IPUH 8-Sep-17 √ 10-Jul-18 √ 4-Oct-18 √17 Sp.Gn KEMALA-PUGUNG TAMPAK 4-Oct-16 √ 23-May-17 √ 23-Nov-17 √ 24-Apr-19 √19 BINTUNAN-LAIS 2-Nov-15 √ 3-Mar-16 √ 8-Nov-17 √ Rising existing guardrail20 LUBUK ALUNG - SICINCIN 20-Mar-17 √ 1-Nov-17 √ 16-Juli-19 √ Finalizing follow-up report21 KURAI TAJI - LUBUK ALUNG 21-Mar-17 √ 2-Nov-17 √ 3-Sep-18 Non audit
21 A KURAI TAJI - LUBUK ALUNG (A) 22-Apr-19 √ 15-juli-19 √Remarks :
1st : First inspection, physical progress > 20% √ : Complete follow-up report2nd : Second inspection, physical progress > 60%3rd : Third inspection, 6 months warranty period ? : Unfinished follow-up report4th : Optional
PACKAGE TITLE3rd OPTIONAL
Unsettled Issues1st 2nd 4th
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Appendix E
Environmental Progress and Social Progress
Status, 31 January 2020
Length Width Safeguard RKPPLDoc
Integration ofAmdal/UKL-UPL/SPPLin Design
HIV-AIDsSocialization Quarry Owner
(Km) (m) DocRequirement Status Status Status Status Remarks Status Remarks License Base camp Polution &
Return Conditions Owner/Env License
1 Krui - Biha (FHO) 25 7 CompleteAmdal Complete Complete Complete 10 Nov
2015 OK period 3 on21 Feb 2019 OK Regularly Complete
Base camp has beendemobilization/no contaminatedsoil (24 Jan 2018),
TP/Complete
2Pdg.Sawah-Sp.Empat,incl.Air Gadang Bridge (100m) (FHO/process)
40.9 7 CompleteUKL-UPL Complete Complete Complete 17
Nov 2015 OK period 3 on17 Jan 2019 OK Regularly Complete
Base camp has beendemobilization/no contaminatedsoil (16 Jan 2019)
TP/Complete
3 Manggopoh-Pdg.Sawah(FHO/process) 32 7 Complete
UKL-UPL Complete Complete Complete 17Nov 2015 OK period 3 on
17 Jan 2019 OK Regularly CompleteBase camp has beendemobilization/no contaminatedsoil (5 May 2018)
TP/Complete
4 Ipuh - Bantal (FHO process) 42.4 7 CompleteUKL-UPL Complete Complete Complete 4
Dec 2015 OK period 3 on29 Dec 2018 OK Regularly Complete
Used for APBN project /PartiallyDone, contaminated soil (8 Feb2018). return condition doc.Process
TP/Complete
5 Sp. Rampa - Poriaha (PHO) 11.1 6 CompleteUKL-UPL Complete Complete Complete
28 Jan 2016 OK Period 3 March2018 OK Regularly Complete
Base camp has beendemobilization, no contaminatedsoil (16 Sep 2019). The currentbase camp used by PT.WIS
TP/Complete
6 Pasar Pedati Kerkap (PHO) 25 7 CompleteUKL-UPL Complete Complete Complete 11
Jan 2016 OK period 3 on 29Dec 2018 OK Regularly Complete
Base camp has beendemobilization /no contaminatedsoil (11 April 2018)
TP/Complete
7 Indrapura - Tapan (PHO 28January 2018) 19.5 7 Complete
Amdal Complete Complete Complete6 Sep 2016 OK
RKL-RPLimplementationon PHO receivedby DLH 26 Nov2018
OK Regularly Complete
Base camp has beendemobilization (was used by landowner) /no contaminated soil (17July 2018)
TP/Complete
8Bts. Kota Pariaman -Manggopoh (PHO 31 Dec2017)
46.8 7 CompleteAmdal Complete, Complete Complete
4 Oct 2016 OK
RKL-RPLimplementationon PHO receivedby DLH 26 Nov2018
OK Regularly Complete
Done (Infrastructure,housekeeping & B3 Storage.improved/ Suitable as SOP /good(27 July 2018), return conditiondoc. Complete
TP/Complete
11 Bantal - Muko Muko (PHO) 50.1 6 CompleteAmdal Complete, Complete, Complete, 5
Dec 2015 OK period 3 on 29Jan 2019 (PHO) OK Regularly Complete
Base camp has beendemobilization /no contaminatedsoil (1 Aug 2018)
TP/Complete
12 Kambang - Indrapura (PHO) 25 January 2019 55.2 6 Complete
Amdal Complete Complete Complete6 Sep 2016 OK
RKL-RPLimplementationon PHO receivedby DLH 26 Nov2018
OK Regularly Complete
Done (Infrastructure,housekeeping & B3 storage TPSimproved. AMP, ST & Weightvehicle not yet moved from BaseCamp 2. the contractor has beensubmit the draft return conditionsat (6 Agt 2019)
TP/Complete
13 Sp. Rukis - Tj.Kemuning(PHO) 56.3 7 Complete UKL-
UPL Complete Complete Complete14 Jan 2016 OK
UKL - UPLimplementationon PHO submitto PMU on 29Nov 2018
OK Regularly CompleteDone (Infrastructure,housekeeping & B3 storageimproved (25 Sep 2017)
TP/Complete
14 Painan - Kambang (PHO) 31.5 7 CompleteAmdal Complete Complete
Complete29 November
2016OK
RKL-RPLimplementation,received by DLH26 Nov 2018
OK
Regularly,submit to
PMU 0n 23May 2019
Complete
Done, (Infrastructure,housekeeping has been improved,the contractor has been submitdraft schedule of mobilization toCTC. (22 Oct 2019),
TP/Complete
15 Sibolga - Bts.Tap Sel (PHO) 36 7 UKL-UPL Complete, Complete Complete27 Jan 2016 OK Period 3 March
2018 OK Regularly Complete
Done housekeeping improved.AMP,ST & weight vehicle etc.hasben moved at Dec 2018.Thecurrent base camp used by CVRoganda & Office & Mess PT.PPat Pandan has beendemolished.(16 Sep 2019)
TP/Complete
Pack.No. Loan Package Name
Amdal/UKL-UPL/DELH/DPLHimplementation
for BLH, WB
RKPPLimplementation
(Quarterly report)
Status & Progress of Environmental Safeguard on WINRIP
Base Camp Management
Status, 31 January 2020
Length Width Safeguard RKPPLDoc
Integration ofAmdal/UKL-UPL/SPPLin Design
HIV-AIDsSocialization Quarry Owner
(Km) (m) DocRequirement Status Status Status Status Remarks Status Remarks License Base camp Polution &
Return Conditions Owner/Env License
Pack.No. Loan Package Name
Amdal/UKL-UPL/DELH/DPLHimplementation
for BLH, WB
RKPPLimplementation
(Quarterly report)
Status & Progress of Environmental Safeguard on WINRIP
Base Camp Management
Seblat - Ipuh including 34.5 6
Air Lalang & Air GuntungBridge(PHO 12 February 2019)
64 m 6
19 Lais - Bintunan (PHO) 11.6 7 Complete UKL-UPL Complete Complete Complete 12
Jan 2016 OK period 3 on 29Dec 2019 (PHO) OK Regularly P (APBN)
Used for APBN project /PartiallyDone, contaminated soil(11 April 2018)
TP/Complete
20 Lubuk Alung - Sicincin(PHO) 14.6 7 Complete UKL-
UPL Complete Complete Complete8 March 2017 OK
period 3 on17 Jan 2019(PHO)
OK Regularly CompleteBase camp has beendemobilization /no contaminatedsoil (10 May 2018)
TP/Complete
21 Lubuk Alung - Kuraijati(TERMINATED) 16.8 7 Complete UKL-
UPL Complete, Complete Complete8 March 2017 OK
period 3 on17 Jan 2019(PHO)
OK Regularly Complete Done (Infrastructure &Housekeeping improved)
TP/Complete
21 A Lubuk Alung - Kuraijati (NewContractor/PHO) 16.8 7 Complete UKL-
UPL Complete Complete Complete26 March 2019 OK period 3 on
17 Jan 2019 OK Regularly Complete
Done: AMP pond water overflowshas been given a separation,nocontaminated soil (13 May 2019)return condition doc. Complete
TP/Complete
05A Slope Protection /On Going 11.1 600 m Complete UKL-UPL & DELH to be revised Complete P OK Period 1 on 26
July 2019 OK Regularly Complete(land lease)
for a while the house in the basecamp area is used for storingmaterial also for Mess employeesand heavy equipment is directlyplaced at the construction site
No needs
Palu Disaster Recovery WorksRR-01 Jl. Abdurahman Saleh 1,25 Process Complete NY P
to be update,DELH report into
oneP Regularly Available
The base camp being built is still incomplementary to the complementarybuildings There is a quarry supplier
Jl. Basuki Rahmat 1,70Kebonsari-Tn.Runtuh 10.82Jl.Yos Sudarso 1.50Jl.Basuki Rahmat 1.80Jl. Yos Sudarso 1,50Kenonsari-Tanah Runtuh 6,835Kebonsari - Tawaeli 8,979Jl. Diponogoro 2,680Malonda-Watusampu 10,055Watusampu-Ampera 14,756Ampera-Surumana 1,125
RR-02 Palupi-Bangga-Simoro 18.88UKL-UPL
(Process inDLHK Prov)
Process Complete NY P to be revised P Regularly Complete The base camp being built is still incomplementary to the complementarybuildings There is a quarry supplier
Biromaru-Palolo 5.48 UKL-UPL Complete NY P to be updateUtilization of Base Camp to be one forthe Biromaru-Palolo and Access Huntaproads
Acces Huntap-Pombewe,incl.bridge acces Huntap 4.09
UKL-UPL(Process in
DLHK Kab Sigi)P to be revised
P NY = Not YetProcess: Project PHO
Regularly
OK
OKComplete, Complete9 May 2017Complete
Period 4 submitto PMU on 9 Nov2018
OK
Project Terminated
Period 4 submitDLH on 21 Feb2019
TP/Complete
17Sp.Gunung Kemala -Pg.Tampak (PHO 27 Dec2017)
CompleteAmdal Complete , Complete
10 Nov 2015
CompleteAmdal
Complete36.8 6
Note :
OK Regularly
16
DELH
Contractor/Complete
Base camp has beendemobilization/no contaminatedsoil (19 Feb 2019)
Complete
Partially Done: Stone crusher 1has been removed (PT. YASA).AMP & ST 2, office, workshop,TPS etc Still Exist.generally basecamp location clean but littlehazardous waste at TPS. Heavyequipment & vehicles owned byPT. Multi Structure in confiscationstatus, Base camp leases are stillvalid until Nov 19. (5 Aug2019).return condition doc.process
Complete
Length Width
(Km) (m) Result Comments Budget Alocated,Year StatusTHE WB Approval (A=Studi
LARAP ;B=Implementation LARAP
AWP - 1A. NOL LARAP 04 Jan2013 ;
ICB/Prior B. NOL Final Mon Report(MR) 20 Oct 2015.
2 Padang Sawah - Sp Empat Sumatera Barat 40.9 7 Total PAP 430 . No Land affected . Aset affected:building 149 unit = 2.110 M2 ; Fence 2 unit = 341.8 M ;Kiosks BBM: 25 unit; Trees: 873 rod ; Mosque: 2 unit
A. NOL LARAP 13 Jan 2013 ;
2a Including Air Gadang Bridge Sumatera Barat 100 m 7 Total PAP 12. Land affected 2,110 M2 ; Aset affected:building 6 unit = 410 M2 ; Trees 72 rod.
B. NOL Final MR: 12 Feb2015
ICB/Prior A. NOL LARAP 04 Jan 2013
B. NOL Final MR: 20 Oct2015.
A. NOL LARAP 10 Dec 2012
ICB/Prior B.NOL Final MR: 12 Feb2015
AWP - 2NCB/Post A. NOL LARAP 20 March
2017;
B.NOL Final MR: 23 Oct2018
NCB/Post
A. NOL LARAP 20November 2013;
NCB/Post B: NOL Final MR: 5 Jan2016
ICB/Prior NOL Larap: Oct 14, 2014
B: NOL WB MonitoringReport No 6: 14 Dec 2018
A. NOL LARAP 12 Sep 2014;
Remedial Action
Approval Status by The World BankSocial ScreeningProcure
ProvincesLoan Package Name
LARAP For the remaining ofAPs: Rp 0,5 Billion.APBN 2017
Total PAP 817 change original 1,193. Partilly affectedbuilding ( houses an kiosks) = 4,013 M2 : Affected fence= 19,206 m : Partially affected other building (terrace,decker and floors) = 9,401 M2, and trees = 3,290.
B: NOL WB for the FinalMonitoring Report: on Jan9, 2017.
Complete
Complete(1) Revision of the Additional LARAP documents (consist92 Aps) signed by Satker II North Sumatera Province(2) 6 APs has to relocated.
Land certification process for 200 from 350 APs iscomplete, and the remaining will conducted by SatkerApril 2020. The certification progress result beingprepared by Satker.
Rp. 5.172.349.955APBN, Satker PJN IILampung, 2011 - 2012
7 LARAP Total PAP: 2,206 change from original 1,282. Partillyaffected building ( houses an kiosks) = 8,352 M2 :Affected fence = 3,673 m : Partially affected otherbuilding (terrace, decker and floors) = 8,771 M2 andtrees = 7,863.
For the remaining ofAPS: Rp 1.5 Billion onFY 2017
Complete
7 Indrapura - Tapan (1 Doc Amdal) Sumatera Barat 19.5 7
CompleteICB/Pr
Rp.2.700.000.000APBN, Satker PJN II,
Sumut, 2017
Complete
5A Sp. Rampa - Poriaha (Sloop Protection) Sumatera Utara 11.1 6 Social Risks No more one illegally mining rock material in the projectarea, which can interfere with civil works
Social Issues (Labor Influx, GBV, VAC) already beincluded to the Contactor’ ESMP. ESMP is underimplementation
Complete
8 Bts. Kota Pariaman - Manggopoh Sumatera Barat 46.8
Rp. 1.147.700.000APBD Prov Sumbar,Dinas PU, 2012/2013;4.9 M from APBD 2014
Complete Complete
LARAP Total PAP 2.815 in 21 Pekon. Land affected 28.763,12M2 ; Aset affected : building 882,13 M2; Fence 2.445,41M ; Trees 653 rod ; paddy field 25 plots ; Social & PablicFacilities
CompleteRp.2.340.600.000APBD Prov Sumbar,Dinas PU, 2012
6 Ps Pedati - Kerkap Bengkulu 25 7 LARAP Total PAP = 637. Affected land = 3,625 M2. Terrace =2,925 M2 ; Fence = 4,169 M, pavement = 4399 m2
RP. 8.049.290.000APBN, Satker PJN I,
Bengkulu, 2014
Payment has complete, certification process for 11from 72 plots already complete and the remaining ofcertification will resolved April 2020. The certificationprogress result being prepared by Satker.
LARAPICB/Prior
LARAP
611.1 Sumatera Utara Sp. Rampa - Poriaha5
1 Krui - Bha
Appendix E : Progress of Social Safeguard Studies on WINRIPas Jan 31, 2020
Lampung 25 7
Complete Ipuh- Bantal4 Bengkulu 42.4 7
Complete
Manggopoh - Padang Sawah3 Sumatera Barat 32 7
No
Total PAP 1.338 . No affected land . Aset affected:building 115 unit = 668,33 M2; Culvert 661,05 m;concrete & foundations 1.421,60M3 ; Soil embankment5.564,21 M3; Trees 5.324 rod
SOCIAL STATUS & PROGRESS FOR WINRIP, IBRD LOAN NO.8043-ID
Simple LARAPand Additional
LARAP
Complete
LARAP Total PAP are change from 227 PAP becomes 257 PAP.257 PAP has received compensation from The LocalGovernment as : Affected Assets: house building =307,05 M2; terace = 672,84M2; fence = 503,85M ;foundation = 8,9 m; pavement = 2,632,01M2; Trees = 82rod, tomb = 7 unit
Rp.286.743.000.APBN, Satker PJN I,Bengkulu, 2013
Complete
Length Width
(Km) (m) Result Comments Budget Alocated,Year StatusTHE WB Approval (A=Studi
LARAP ;B=Implementation LARAP
Remedial Action
Approval Status by The World BankSocial ScreeningProcure
ProvincesLoan Package NameNo
A. -
A. NOL LARAP 12 Sep 2014;
B: NOL WB for theMonitoring Report-1 onMarch 8, 2016
ICB/Prior A. NOL LARAP 20November 2013;
B: NOL Final WB: 28 Oct2016
ICB/Prior NOL Larap: Oct 14, 2014
ICB/Prior A. NOL LARAP 20November 2013;B: NOL Final MR: 04 Apr2019
AWP - 3 .ICB/Prior A. NOL LARAP 19
December 2014;
ICB/Prior A. NOL LARAP 28 October2013 and NOL revise 05Feb 2014;B: NOL Final MR 23 Oct2018
Seblat - Ipuh including (1 Amdal) 34.5 6 A. NOL LARAP 20November 2013; NOLUpdate LARAP on Jun 7,2016
Air Lalang & Air Guntung Bridge 64 m 6 B: NOL Final MR on Nov 11,2016A. NOL LARAP 16 Sept 2013
B: NOL Final MonitoringReport on 23 Oct 2018
A. -
NCB/Post A. NOL LARAP 20November 2013;
B: NOL Final MR: 13 Dec2016
ENVIRONMENTAL: Based on CTC survey for environmental screening isconclusion that this packages need completed by UKL&UPL. WILLDELETED
7
Complete
Complete
ENVIRONMENTAL: Link of Bengkunat-Biha already completed by AMDALstudy with environmental permit from the Governor at 2012. DELETED
PPK/Satker PJN I West Sumatera and Local Government are continuingthe process of payments to the remaining of the PAPs
LARAP
19 Lais- Bintunan Bengkulu 11.6 7
18 Mukomuko - Bts. Sumbar / Replace toSorkam - Sibolga
Bengkulu 25.8 6 NCB/
For certification process of 321 Aps will conducted by Satker III NorthSumatera on April 2020
Sp.Gunung Kemala - Pg. Tampak 36.8 6
Complete
LARAP Total PAP 2568 (updated) . Land affected 1.926 plot =194.278 M2. Aset affected : building 440 unit = 4.557M2 ; ; Trees 4.267 rod ;paddy field 48.602 clumps.
For the remaining ofAPs: Rp 825 Million onFY 2017
Simple LARAP
(1). Payment has complete. (2). Land certificationprocess for 700 from 1806 APs is complete, and theremaining will conducted by Satker April 2020. Thecertification progress result being prepared by Satker.
15 Sibolga - Bts Tap Sel Sumatera Utara
13 Sp Rukis - Tj Kemuning Bengkulu 56.3 7 For the remaining ofAPs: FY 2017: 4.5Billion
LARAP
14 Painan -Kambang (1 doc Amdal) Sumatera Barat 31.5 7 Simple LARAP Total PAP 2.137. Partilly affected building ( houses ankiosks) = 10,474 M2 : Affected fence 21,735m : Partiallyaffected other building (terrace, decker and floors) =20,988 M2 and trees = 1044
For the remaining ofAPs: Rp 4.5 Billion on
FY 2017
36
Complete
Payment has complete, certification process for 15from 382 plots already complete and the remaining ofcertification will resolved April 2020. The certificationprogress result being prepared by Satker.
12 Kambang - Indrapura (1 Doc Amdal) Sumatera Barat 55.2 6 LARAP Total PAP 2.873 (update). Partilly affected building (houses an kiosks) = 2,057 M2 : Affected fence =32,741m : Partially affected other building (terrace,decker and floors) = 17,144 M2 and trees = 3,225
on FY 2017 Complete
LARAP Total PAP 2059 change from original 1,514. Partillyaffected building ( houses an kiosks) = 11,523 M2 :Affected fence = 2,613 m : Partially affected otherbuilding (terrace, decker and floors) = 11,538 M2 andtrees = 4,369
Rp 14.02 Billion. APBDProv Sumbar, Dinas PU,
a) Total PAPs 2.915, and already compensated 1.725.b) PPK/Satker PJN I West Sumatera and LocalGovernment is under payment process for theremaining PAP.
11 Bantal - Mukomuko (1 Paket doc AMDAL) Bengkulu 50.1 6 LARAP RP. 8.237.443.000APBN Satker PJN I,Bengkulu, 2014
CompleteTotal PAP 243 (updated) . No affected land. Housebuilding = 261.7 M2; kiosks = 147.7 m2, terrace = 412.9m2, Fence = 249 M ; Trees= 36 rod, foundation = 17.2m2, retaining wall = 35.1 m, pavement = 2,937 m2
ICB/Pri
10 Sp Empat - Sp Air Balam Sumatera Barat 61.7 7
9 Rantau Tijang - Kota Agung / Replace toBengkunat - Biha (already completed byAMDAL)
Lampung 42 7 ICB/
LARAP is under preparation by Balai III Palembang. Thispackage was changed to Bengkunat - Biha
B: NOL MR_7: 9 Jan 2019
B: NOL MR_6: 14 Dec 2018
LARAP Total PAP 538 Affected land = 9,504 M2. Aset affected: floor = 1,381 M2; Terrace: 652 M2; Fence = 3,276 M;Tomb = 18 units; Trees 379 rod; utilities 14 unit
Rp.3.349.829.000APBN, Satker PJN IIBengkulu
Payment has complete. Land certification process for 5from 193 Aps is complete and the remaining willconducted April 2020. The certification progress resultbeing prepared by Satker.
17 Lampung ICB/Prior
16 Bengkulu ICB/Prior Total PAP 259 changed from original 316. No affectedland, Affected assets: building= 658 M2 ; Terrace= 98;Fence= 232 M ; Trees 33 rod
Complete
Complete.
LARAP
LARAP Total PAP: 2.785 update from 2.917. Affected land =88,852 M2. Aset affected : building 111 unit = 2.196 M2
; Fence 127 unit = 1.575 M ; Trees 363 rod ; electricitypole 25 unit
Total PAP 1.852 . Land affected 1.531 plot = 45,831M2.Aset affected : building 340 nit = 3.399 M2 ; Fence 12unit = 1.563 M ; Trees 385 rod, Terrace = 991,607 M2
For the remaining ofAPs: Rp 9 Billion on FY2018
Payment has complete, certification process for 321plots not available
APBN, 2015 LARAP is under preparation by Balai III Palembang.
Length Width
(Km) (m) Result Comments Budget Alocated,Year StatusTHE WB Approval (A=Studi
LARAP ;B=Implementation LARAP
Remedial Action
Approval Status by The World BankSocial ScreeningProcure
ProvincesLoan Package NameNo
NCB/Post A. NOL LARAP on Dec 19,2014
B: NOL Final MonitoringReport on Apr 18, 2017
A. NOL LARAP on Dec 19,2014
NCB/Post B: NOL of Final MonitoringReport 6 March 2019
NCB/Post
Tanah Runtuh - Kebunsari Link 6.9 9
Kebunsari - Tawaeli Link 8.8 9
Social RisksSocial Issues (Labor Influx, GBV, VAC) already beincluded to the Contactor’ ESMP. Project have to theProject GRM including GBV and VAC.
a). ESMP is under preparation, b) Hotline number ofthe GRM included the GBV – VAC issue is beingprovided and published by PPK and Contractor. HSE –Contractor is as a Focal Point - GRMc) Prevention of GBV and VAC is being prepared by thecontractor, like to include in the Company Code ofConduct, Manajaer Code of Conduct and IndividualCode of Conduct, as well as GBV and VAC socializationplans
Monitoring report under prepared by CTC
Biromaru - Palolo 2.16 7There are 21 structure owners occupied ROW that haveto be shifted behind
12 from the total of 21 structure owners have made astatement willing to move their structure out of RoW
Monitoring report under prepared by CTC
Jalan Akses Huntap 3.85 611 affected land owners that be requested to donortheir land to the project
All of land owners have made a statement willing todonor their land to the project
Monitoring report under prepared by CTC
Social RisksSocial Issues (Labor Influx, GBV, VAC) already beincluded to the Contactor’ ESMP. Project have to theProject GRM including GBV and VAC.
a). ESMP is under preparation b) Hotline number of theGRM included the GBV – VAC issue is being providedand published by PPK and Contractor. HSE –Contractor is as a Focal Point - GRMc) Prevention of GBV and VAC is being prepared by thecontractor, like to include in the Company Code ofConduct, Manajaer Code of Conduct and IndividualCode of Conduct, as well as GBV and VAC socializationplans
Monitoring report under prepared by CTC
Under prepared by CTC
RR-01
Sulawesi TengahRR-02
There are street vendors who are above the existingcanal and / or are on the outer border of the shoulder ofthe road that will be affected during the constructionwork period
Assessment and Action LARAP Tanahruntuh –Kebonsari and Kebonsari – Taweli will prepared midleFeb 2020 by Satker
Sulawesi TengahAssessmentand ActionPlan LARAP
Assessmentand ActionPlan LARAP
Simple LARAP Complete
21 Lubuk Alung -Kurataji Sumatera Barat 16.8 7 Simple LARAP Total PAP: 827 (updated), Affected land: 40,612 m2,Partilly affected building (houses and kiosks) = 360.9m2Affected fence = 284m Irrigation channal: 433m
For the remaining ofAPs: Rp 1.5 Billion onFY 2017
Complete
20 Lubuk Alung - Sicincin Sumatera Barat 14.6 7 Total PAP: 950 (updated), Affected land: 46,579 m2, PTKAI Affected land: 682 m2, Partilly affected building(houses and kiosks) = 528m2, Affected fence = 294m,Irrigation channal: 2.600m.
Complete.
21A Lubuk Alung -Kurataji (Re-tendering) Sumatera Barat 16.8 7 Social Risks No social pending issue. Civil works complete complete
For the remaining ofAPs: Rp 2 Billion on FY2017
Complete
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Appendix F
Procurement Plan & Progress
Procurement Plan of Civil WorksWestern Indonesia National Roads Improvement Project (WINRIP)Executing Agency: Directorate General of Highways , Ministry of Public Works and Housing. Updated January 31, 202015000 Edit 250112
Qualification Schedule Submission Notification Contractor
Sub - Project Link No. Length Criteria Actual of of(Km) IDR (x10
⁶) USD million (Pre/Post) Application Qualification IDR
A W P - 1Schedule 12-Jan-11 09-Feb-11 09-May-11 07-Aug-11 15-Dec-11 09-Feb-12 13-Sep-12 28-Feb-13 01-Mar-13 07-Mar-13 18-Apr-13 05-May-13 19-May-13 18-Jun-13Revised 17-May-13 27-May-13 08-Jul-13 10-Sep-13 24-Sep-13 14-Nov-13 06-Dec-13 07-Sep-15Actual 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13 28-Mar-13 17-May-13 27-Jun-12 31-Oct-12 27-May-13 18-Jul-13 10-Sep-13 18-Sep-13 25-Nov-13 08-Jan-14 09-Oct-15
733 10-Jan-16 149,193,782,000Date of Taking Over 20-Jan-16
Schedule 12-Jan-11 09-Feb-11 09-May-11 07-Aug-11 15-Dec-11 09-Feb-12 13-Sep-12 28-Feb-13 01-Mar-13 07-Mar-13 18-Apr-13 05-May-13 19-May-13 18-Jun-13Revised 17-May-13 27-May-13 08-Jul-13 10-Sep-13 24-Sep-13 14-Nov-13 06-Dec-13 06-Dec-15Actual 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13 28-Mar-13 17-May-13 27-Jun-12 31-Oct-12 27-May-13 18-Jul-13 10-Sep-13 18-Sep-13 06-Dec-13 06-Jan-14 05-Jan-16
835 19-Apr-16 247,572,130,000Date of Taking Over 14-Apr-16
Schedule 12-Jan-11 09-Feb-11 09-May-11 07-Aug-11 15-Dec-11 09-Feb-12 13-Sep-12 28-Feb-13 01-Mar-13 07-Mar-13 18-Apr-13 05-May-13 19-May-13 18-Jun-13Revised 17-May-13 27-May-13 08-Jul-13 10-Sep-13 24-Sep-13 14-Nov-13 06-Dec-13 06-Dec-15Actual 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13 28-Mar-13 17-May-13 27-Jun-12 31-Oct-12 27-May-13 18-Jul-13 10-Sep-13 18-Sep-13 06-Dec-13 06-Jan-14 05-Jan-16
805 20-Mar-16 183,452,685,000Date of Taking Over 17-Mar-16
Schedule 12-Jan-11 09-Feb-11 09-May-11 07-Aug-11 15-Dec-11 09-Feb-12 13-Sep-12 28-Feb-13 01-Mar-13 07-Mar-13 18-Apr-13 05-May-13 19-May-13 18-Jun-13Revised 17-May-13 27-May-13 08-Jul-13 10-Sep-13 24-Sep-13 14-Nov-13 06-Dec-13 06-Dec-15Actual 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13 28-Mar-13 17-May-13 27-Jun-12 31-Oct-12 27-May-13 18-Jul-13 10-Sep-13 18-Sep-13 14-Nov-13 13-Jan-14 12-Jan-16
820 11-Apr-16 212,290,705,872Date of Taking Over 31-May-16
Sub Total AWP - 1 807,090.72 53.81 792,509,302,872
A W P - 2 and 3243
Schedule 30-Sep-13 14-Oct-13 30-Sep-13 14-Oct-13 06-Nov-13 18-Dec-13 22-Jan-14 06-Feb-14 10-Feb-14 02-Dec-13 16-Dec-13 17-Feb-14 01-Apr-14 30-Apr-14 14-May-14 7-Jul-14 11-Aug-14 31-Jul-16Revised 19-May-14 2-Jun-14 9-Jun-14 14-Feb-14 28-Feb-14 16-Jun-14 28-Jul-14 1-Sep-14 15-Sep-14 8-Nov-14 13-Dec-14 1-Dec-16Actual 30-Sep-13 10-Oct-13 30-Sep-13 10-Oct-13 11-Nov-13 30-Dec-13 28-Feb-14 13-Jun-14 25-Jun-14 19-Dec-14 7-Jan-14 4-Jul-14 15-Aug-14 10-Oct-14 14-Oct-14 17-Nov-14 4-Sep-15 23-Aug-17
846 27-Dec-17 211,712,283,000Date of Taking Over 26-Dec-17
Schedule 06-Nov-13 20-Nov-13 06-Nov-13 20-Nov-13 22-Nov-13 6-Jan-14 7-Feb-14 21-Feb-14 24-Feb-14 2-Dec-13 16-Dec-13 4-Mar-14 15-Apr-14 19-May-14 2-Jun-14 23-Jul-14 22-Aug-14 12-Feb-16Revised 26-May-14 9-Jun-14 16-Jun-14 2-Jun-14 16-Jun-14 23-Jun-14 4-Aug-14 8-Sep-14 22-Sep-14 15-Nov-14 20-Dec-14 11-Jun-16Actual 07-Nov-13 15-Jul-14 07-Nov-13 18-Nov-13 23-Dec-13 10-Feb-14 9-Jun-14 15-Jul-14 22-Jul-14 18-Jul-14 22-Jul-14 11-Aug-14 22-Sep-14 18-Nov-14 27-Jan-15 17-Mar-15 18-Jun-15 8-Dec-16
1004 17-Mar-18Date of Taking Over 26-Jul-18 123,132,763,000
Schedule 06-Nov-13 20-Nov-13 06-Nov-13 20-Nov-13 22-Nov-13 6-Jan-14 7-Feb-14 21-Feb-14 24-Feb-14 2-Dec-13 16-Dec-13 4-Mar-14 15-Apr-14 19-May-14 2-Jun-14 23-Jul-14 22-Aug-14 11-Aug-16Revised 26-May-14 9-Jun-14 16-Jun-14 2-Jun-14 16-Jun-14 23-Jun-14 4-Aug-14 8-Sep-14 22-Sep-14 15-Nov-14 20-Dec-14 8-Dec-16Actual 07-Nov-13 25-Jun-14 07-Nov-13 18-Nov-13 23-Dec-13 10-Feb-14 16-Jun-14 25-Jun-14 11-Jul-14 21-Jul-14 6-Aug-14 22-Aug-14 3-Oct-14 4-Nov-14 13-Nov-14 18-Dec-14 23-Feb-15 11-Feb-17
816 18-May-17 263,656,603,000Date of Taking Over 19-May-17
Schedule 06-Nov-13 20-Nov-13 06-Nov-13 20-Nov-13 22-Nov-13 6-Jan-14 7-Feb-14 21-Feb-14 24-Feb-14 2-Dec-13 16-Dec-13 4-Mar-14 15-Apr-14 19-May-14 2-Jun-14 23-Jul-14 22-Aug-14 11-Aug-16Revised 26-May-14 9-Jun-14 16-Jun-14 2-Jun-14 16-Jun-14 23-Jun-14 4-Aug-14 8-Sep-14 22-Sep-14 15-Nov-14 20-Dec-14 8-Dec-16Actual 07-Nov-13 25-Jun-14 07-Nov-13 18-Nov-13 23-Dec-13 10-Feb-14 16-Jun-14 25-Jun-14 11-Jul-14 21-Jul-14 6-Aug-14 22-Aug-14 3-Oct-14 4-Nov-14 18-Nov-14 18-Dec-14 22-Jul-15 10-Jul-17
1029 15-May-18 305,886,100,000Date of Taking Over 15-May-18
Schedule 13-Nov-13 27-Nov-13 13-Nov-13 27-Nov-13 04-Dec-13 03-Jan-14 02-Feb-14 16-Feb-14 16-Mar-14 15-Apr-14 9-Jul-15Revised 14-Nov-14 28-Nov-14 5-Dec-14 4-Jan-15 22-Feb-15 8-Mar-15 30-May-16Actual 21-Nov-13 - 19-Nov-14 24-Nov-14 29-Dec-14 - - 3-Mar-15 11-Mar-15 2-Jun-16
690 28-Jan-17 118,444,156,000Date of Taking Over 27-Jan-17
Schedule 13-Nov-13 27-Nov-13 13-Nov-13 27-Nov-13 04-Dec-13 03-Jan-14 02-Feb-14 16-Feb-14 16-Mar-14 15-Apr-14 9-Feb-15Revised 14-Nov-14 28-Nov-14 5-Dec-14 4-Jan-15 22-Feb-15 8-Mar-15 1-Jan-16Actual 21-Nov-13 - 19-Nov-14 24-Nov-14 29-Dec-14 - - 3-Mar-15 11-Mar-15 4-Jan-16
478 30-Jun-16 44,419,760,000Date of Taking Over 30-Jun-16
Schedule 13-Nov-13 27-Nov-13 27-Dec-13 10-Jan-14 17-Jan-14 28-Feb-14 30-Mar-14 13-Apr-14 11-May-14 10-Jun-14 28-Aug-16Revised 16-Dec-13 30-Dec-13 14-Nov-14 28-Nov-14 15-Jan-15 26-Feb-15 31-Mar-15 14-Apr-15 22-Jun-15 10-Aug-15 27-Oct-17Actual 30-Dec-13 28-Feb-14 18-Dec-14 23-Dec-14 12-Jan-15 23-Feb-15 4/24/2015 7-May-15 3-Jul-15 20-Nov-15 6-Feb-18
954 30-Jun-18Date of Taking Over 03-Jul-19 205,270,429,000
Schedule 14-Jul-14 28-Jul-14 04-Aug-14 18-Aug-14 25-Aug-14 06-Oct-14 10-Nov-14 24-Nov-14 17-Jan-15 16-Feb-15 5-Feb-17Revised 01-Dec-14 15-Dec-14 11-Mar-15 25-Mar-15 1-Apr-15 15-May-15 22-Jun-15 6-Jul-15 11-Sep-15 30-Oct-15 18-Oct-17Actual 18-Dec-14 22-Dec-14 12-May-15 26-May-15 28-May-15 13-Aug-15 9-Oct-15 9-Dec-15 28-Jan-16 23-Mar-16 12-Mar-18
649 31-Dec-17 378,042,000,000Date of Taking Over 29-Dec-17
Schedule 14-Jul-14 28-Jul-14 04-Aug-14 18-Aug-14 25-Aug-14 06-Oct-14 10-Nov-14 24-Nov-14 17-Jan-15 16-Feb-15 5-Feb-17Revised 01-Dec-14 15-Dec-14 11-Mar-15 25-Mar-15 1-Apr-15 15-May-15 22-Jun-15 6-Jul-15 11-Sep-15 30-Oct-15 18-Oct-17Actual 18-Dec-14 22-Dec-14 12-May-15 26-May-15 28-May-15 13-Aug-15 9-Oct-15 22-Feb-16
Schedule 14-Jul-14 28-Jul-14 04-Aug-14 18-Aug-14 25-Aug-14 29-Sep-14 3-Nov-14 17-Nov-14 29-Dec-14 28-Jan-15 19-Oct-16Revised 01-Dec-14 15-Dec-14 11-Mar-15 25-Mar-15 1-Apr-15 6-May-15 11-Jun-15 25-Jun-15 21-Aug-15 4-Sep-15 25-May-17Actual 18-Dec-14 22-Dec-14 12-May-15 26-May-15 28-May-15 13-Aug-15 9-Oct-15 12-Oct-15 3-Dec-15 10-Dec-15 30-Aug-17
781 28-Jan-18 129,700,000,000Date of Taking Over 26-Jan-18
Schedule 14-Jul-14 28-Jul-14 04-Aug-14 18-Aug-14 25-Aug-14 06-Oct-14 10-Nov-14 24-Nov-14 17-Jan-15 16-Feb-15 5-Feb-17Revised 01-Dec-14 15-Dec-14 11-Mar-15 25-Mar-15 1-Apr-15 6-May-15 11-Jun-15 25-Jun-15 21-Aug-15 4-Sep-15 23-Aug-17Actual 18-Dec-14 22-Dec-14 12-May-15 26-May-15 28-May-15 13-Aug-15 9-Oct-15 26-Nov-15 28-Jan-16 23-May-16 12-May-18
952 30-Dec-18 354,144,630,000Date of Taking Over 02-Feb-19
Schedule 01-Oct-14 15-Oct-14 01-Oct-14 15-Oct-14 22-Oct-14 26-Nov-14 31-Dec-14 14-Jan-15 25-Feb-15 11-Mar-15 30-Nov-16Revised 10-Jul-15 24-Jul-15 10-Aug-15 24-Aug-15 2-Nov-15 16-Dec-15 13-Jan-16 27-Jan-16 2-Mar-16 16-Mar-16 5-Dec-17Actual 10-Sep-15 22-Oct-15 22-Oct-15 2-Nov-15 5-Jan-16 22-Mar-16 4-Apr-16 1-Jun-16 3-Aug-16 24-Apr-18
1045 13-Jun-19 209,465,972,800Date of Taking Over 08-Nov-19
Amendments
CANCELED
Amendments
Amendments
720
630
Amendments
Prior
Prior
Prior
214,327,429,680
PT. PP (Persero), Tbk.
355,500,000,000PT. PP (Persero), Tbk.- PT.Statika Mitrasarana, J.O.
260,100,000,011
PT. Adhi Karya (Persero),Tbk. 129,699,900,000
PT. Lancarjaya MandiriAbadi - PT. Cahaya TunggalAbadi, J.O.
350,643,730,000
630 KSO YASA - CONBLOC
720
Prior
33,689,452,000
PT. Waskita Karya(Persero), Tbk.
Amendments
Amendments
Amendments
143,688,963,000
186,936,750,000
107,321,260,310
228,899,717,000
199,551,233,000
PT. Rodateknindo Purajaya.
86,517,470,000
PT. Jaya KonstruksiManggala Pratama, Tbk.
PT. Nusa KonstruksiEnjiniring, Tbk.
PT. Waskita Karya(Persero), Tbk.
Amendments
300
Amendments
Prior
292,700,000,000
PT. Waskita Karya(Persero), Tbk. and PT.
Daya Mulia Turangga, J.O.Prior
640
730
730
730
720
540
720
720
450
810
720
Amendments
10.90Amendments
Amendments
Prior
197,936,699,000
Amendments
PT. Hutama Karya (Persero)and PT. Daya Mulia
Turangga, J.O.
Contract Amount(Incl. VAT10%)Completion
Date
134,909,211,000
PT. Jaya KonstruksiManggala Pratama, Tbk.
CommencementDate
Construction
Period(day)
PT. Jaya KonstruksiManggala Pratama, Tbk.
Bid Evaluation Report ContractSignature
DateWB NOL
Design
Submission Date
Amendments
Amendments
PART 1. BETTERMENT AND CAPACITY EXPANSION OF NATIONAL ROAD
Krui - Biha Lampung 053.0 25.06 163,534.85
PT. Jaya KonstruksiManggala Pratama, Tbk.
Ref. No. Province Procurement Method
Estimated CostEE
(Incl. VAT)
Estimated CostEE
(Incl. VAT)
Invitationfor Bids
Date
BidOpening
DateWB NOLDate
SubmissionDate
WB NOLDate
Submission Date
PQ Document Invitation forPre-
qualification
Evalt.QualificationReport Bidding Document
SubmissionDate NOL Date WB NOL
DateSubmission
Date
WB Prior/Post
Rewiew
ICB Pre Prior1
2 Padang Sawah - Sp.EmpatIncluding Air Gadang Bridge
WestSumatera 047.2
40.7 +100 mbridge
228,772.24 15.25 ICB Pre Prior
3 WestSumatera 047.1 32.00 167,678.40 11.18 ICB Pre PriorManggopoh - Padang Sawah
Prior
Ipuh - Bantal4 Bengkulu 015.1 42.45 247,105.24 16.47 ICB Pre
17 Sp.Gng Kemala - Pugung Tampak Lampung 061.1 36.15 255,269.25 17.02 ICB Pre
5 Simpang Rampa - Poriaha NorthSumatera 015. 9.70 152,870.49 10.19 ICB Pre
Prior
13 Sp Rukis - Tj Kemuning Bengkulu 006.1 56.27 316,304.67 21.09 ICB Pre Prior
11 Bantal - Mukomuko Bengkulu 015.2 50.65 246,499.55 16.43 ICB Pre
Post
19 Lais - Bintunan Bengkulu 009.1 10.80 35,886.28 2.39 NCB Post Post
6 Ps. Pedati - Kerkap Bengkulu 010.0 20.88 92,127.40 6.14 NCB Post
15 Sibolga - Batas Tapsel NorthSumatera 016.1 36.00 376,479.38 25.10 ICB Post
8 Bts.Kota Pariaman - Manggopoh WestSumatera 024.0 46.80 379,034.45 25.27 ICB Post
10 Simpang Empat - Sp.Air Balam WestSumatera 034.1 61.70 515,842.21 34.39 ICB
Post
7 Indrapura - Tapan WestSumatera 019.0 19.50 178,600.23 11.91 NCB Post
Prior
14 Painan - Kambang WestSumatera 017.1 31.50 267,588.30 17.84 NCB Post
12 Kambang - Indrapura WestSumatera 017.2 55.20 451,810.58 30.12 ICB Post
C:\Users\Tediero\AppData\Local\Temp\Appendix F Proc Plan WINRIP CivilWorks 20200131_FDDEEE.xlsx
Qualification Schedule Submission Notification Contractor
Sub - Project Link No. Length Criteria Actual of of(Km) IDR (x10
⁶) USD million (Pre/Post) Application Qualification IDR
Contract Amount(Incl. VAT10%)Completion
Date
CommencementDate
Construction
Period(day)
Bid Evaluation Report ContractSignature
DateWB NOL
Design
Submission Date
Ref. No. Province Procurement Method
Estimated CostEE
(Incl. VAT)
Estimated CostEE
(Incl. VAT)
Invitationfor Bids
Date
BidOpening
DateWB NOLDate
SubmissionDate
WB NOLDate
Submission Date
PQ Document Invitation forPre-
qualification
Evalt.QualificationReport Bidding Document
SubmissionDate NOL Date WB NOL
DateSubmission
Date
WB Prior/Post
Rewiew
Schedule 01-Oct-14 15-Oct-14 01-Oct-14 15-Oct-14 22-Oct-14 26-Nov-14 31-Dec-14 14-Jan-15 25-Feb-15 11-Mar-15 30-Nov-16Revised 10-Jul-15 24-Jul-15 10-Aug-15 24-Aug-15 22-Oct-15 19-Nov-15 17-Dec-15 31-Dec-15 4-Feb-16 18-Feb-16 8-Nov-17Actual 4-Sep-15 22-Oct-15 30-Sep-15 22-Oct-15 22-Oct-15 19-Nov-15 11-Jan-16 24-Aug-16 28-Oct-16 8-Nov-16 30-Jul-18
Amendments 692 30-Sep-18Date of Taking Over 31-Dec-18
Schedule 01-Oct-14 15-Oct-14 01-Oct-14 15-Oct-14 22-Oct-14 26-Nov-14 31-Dec-14 14-Jan-15 11-Feb-15 25-Feb-15 18-Aug-16Revised 10-Jul-15 24-Jul-15 10-Aug-15 24-Aug-15 2-Nov-15 16-Dec-15 13-Jan-16 27-Jan-16 2-Mar-16 16-Mar-16 6-Sep-17Actual 25-Aug-15 22-Oct-15 22-Oct-15 2-Nov-15 5-Jan-16 22-Mar-16 23-Mar-16 1-Jun-16 1-Sep-16 22-Feb-18
548 2-Mar-18Date of Taking Over 02-Mar-18
Schedule 01-Oct-14 15-Oct-14 01-Oct-14 15-Oct-14 22-Oct-14 26-Nov-14 31-Dec-14 14-Jan-15 11-Feb-15 25-Feb-15 18-Aug-16Revised 10-Jul-15 24-Jul-15 10-Aug-15 24-Aug-15 2-Nov-15 16-Dec-15 13-Jan-16 27-Jan-16 2-Mar-16 16-Mar-16 6-Sep-17Actual 25-Aug-15 22-Oct-15 22-Oct-15 02-Nov-15 05-Jan-16 22-Mar-16 23-Mar-16 01-Jun-16 1-Sep-16 22-Feb-18
666 28-Jun-18 TERMINATED 70,423,502,034.00ScheduleRevised
ActualScheduleRevised
Schedule 06-Mar-18 20-Mar-18 19-Mar-18 02-Apr-18 16-Apr-18 16-May-18 - - 27-Jun-18 2-Jul-18 150 29-Nov-18
Actual 13-Mar-18 15-Mar-18 10-Apr-18 18-Apr-18 24-Apr-18 16-May-18RebiddingSchedule 30-Aug-18 20-Sep-18 11-Oct-18 - 1-Nov-18 15-Nov-18 180 13-May-19Rebidding
Actual 30-Aug-18 20-Sep-18 07-Nov-18 09-Jan-192nd
Rebidding 28-Jan-19 18-Feb-19 04-Mar-19 - 28-Mar-19 11-Apr-19 300 4-Feb-20Rebidding
Actual 30-Jan-19 21-Feb-19 05-Mar-19 - 01-Apr-19 22-Apr-19 15-Feb-20Schedule 20-Aug-18 31-Aug-18 21-Sep-18 - 24-Sep-18 15-Oct-18 5-Nov-18 - 26-Nov-18 10-Dec-18 9-May-19
Actual 1-Oct-18 - 11-Oct-18 1-Nov-18 30-Nov-18 21-Dec-18 3-Jan-19 1-Jun-19180 1-Jul-19
Date of Taking Over 01-Jul-19Sub Total AWP - 2 & 3 4,579,869.81 305.32 2,900,864,999,834Total AWP - 1 , 2 & 3 5,386,960.53 359.13 3,693,374,302,706
Schedule 06-May-19 17-May-19 06-May-19 - 27-May-19 17-Jun-19 15-Jul-19 - 23-Aug-19 6-Sep-19 28-Nov-20Actual 17-May-19 31-May-19 02-Jul-19 22-Aug-19 25-Oct-19 28-Oct-19 19-Jan-21
Schedule 10-Jun-19 24-Jun-19 10-Jun-19 - 1-Jul-19 22-Jul-19 13-Aug-19 - 20-Sep-19 4-Oct-19 27-Oct-20Revised - 15-Aug-19 5-Sep-19 26-Sep-19 17-Oct-19 31-Oct-19Actual 18-Jun-19 13-Aug-19 15-Aug-19 05-Sep-19 16-Oct-19 01-Nov-19 4-Nov-19 27-Nov-20
Total Civil Works of Part 4 349,050.00 23.27 238,976,135,795USD 3,932,350,438,501
Note: USD 2,752,645,306,9511 USD = (Exchange rate assumption for RAPBN FY 2019, Ministry of Finance)
Post21A Lubuk Alung - Kuraitaji(Penyelesaian)
WestSumatera 027.0 16.23 99,019.00 6.60 NCB Post
5A
65,726.63 4.38 NCB Post Post
79,780.00 5.32 NCB Post
78,933.34 5.26 NCB Post Post
NorthSumatera 015. 0.69
165,640,728,000
390
WASCO-SARANA, KSO(PT. Widya SaptaContractor, PT.
Saranamukti Puterasejati)
018. 019.020.
73,335,407,795
83,624,709,000
77,749,292,000
PART 4. CONTINGENCY FOR DISASTER RISK RESPONSE
KSO PT. Nusa KonstruksiEnjiniring, Tbk. - PT.
Multikon Jagad Perkasa
PT. GIRDER INDONESIA
Penanganan Lereng Ruas Sp.Rampa - Poriaha Post
RR01
RR02
55.74 207,050.00 13.80 NCB Post Post
no bidders pass the qualification
540
113,818,300,000Amendments
PT. Multi Structure 126,301,900,000
Amendments
PT. Nindya Karya (Persero)540
630 KSO. PT. Yasa PatriaPerkasa - PT. Multi
Structure211,374,500,000
Prior
Rp15,000.00
CANCELED
CANCELED
no bidders pass the qualification
CentralSulawesi
CentralSulawesi
WestSumatera 002.0 14.60 131,302.20 8.75 NCB Post
21 Lubuk Alung - Kuraitaji WestSumatera 027.0 16.23 164,629.30 10.98 NCB Post
Tompe - Dalam Kota Palu -Surumana
Palupi-Simoro, Kalukubula -Kalawara, Birobuli - Palolo and
Akses Huntap
450KSO NINDYA-
PASSOKORANG(PT. Nindya Karya
150
Amendments
Prior
9 Rantau Tijang - Kota Agung Lampung 026.1 42.00 149,831.00 9.99
21.67 142,000.00 9.47 NCB Post Post
Mukomuko - Batas Sumbar
NCB Post Prior
18
16 Seblat - Ipuh, Including Air Lalang& Air Guntung Bridge Bengkulu 009.4
34.5 +60 m
bridges269,559.20 17.97 NCB Post Prior
Bengkulu 015.3 25.80 69,233.00 4.62 NCB Post
Prior
20 Lubuk Alung - Sicincin
C:\Users\Tediero\AppData\Local\Temp\Appendix F Proc Plan WINRIP CivilWorks 20200131_FDDEEE.xlsx
Procurement Plan of Implementation SupportWestern Indonesia National Roads Improvement Project (WINRIP)Executing Agency: Directorate General of Highways , Ministry of Public Works and Housing.
Ref.No. Contract Description Project Cost
(US$)Procurement
Method
Review byBank
(Prior/Post)Schedule
Preparationof Draft
REOI
EOIadvertised in
MPWWebsite
Dateline ofEOI
Submission
SubmissionRFP to WB WB NOL to RFP
Opening ofFinancialProposal
FinalEvaluation
Report
ContractSign
Service Startdate Consultant Remarks
Allocated Original Addendum Actual Submission WB NOL Submission WB NOL Submission Submission WB NOL Original Addendum
2 Part 2: Implementation Support
Schedule 14-Nov-10 05-Dec-10 23-Jan-11 12-Feb-11 12-Mar-11 02-Apr-11 23-Apr-12 04-Jun-12 22-Jul-12 05-Aug-12 12-Aug-12 15-Sep-12 29-Sep-12 22-Oct-12 12-Nov-12
Actual 26-Nov-10 7-Jun-11 7-Jul-11 30-Jan-12 7-Mar-12 9-Dec-11 6-Mar-12 20-Mar-14 30-Apr-12 14-Jun-12 29-Jun-12 27-Aug-12 3-Sep-12 21-Sep-12 12-Oct-12 5-Nov-12 16-Nov-12
Schedule 11-Dec-11 08-Jan-12 27-Feb-12 26-Mar-12 07-May-12 28-May-12 08-Oct-12 22-Oct-12 05-Nov-12 12-Nov-12 19-Nov-12 26-Nov-12 01-Apr-13 18-Apr-13 02-May-13
Actual 26-Nov-10 7-Jun-11 7-Jul-11 4/2/2012 10-Aug-12 20-Jan-12 23-May-12 31-Aug-14 23-Oct-12 20-Dec-12 21-Feb-13 5-Mar-13 13-Mar-13 25-Mar-13 19-Apr-13 11-Jun-13 25-Jun-13
Schedule 15-Dec-15 22-Dec-15 19-Jan-16 29-Jan-16 12-Feb-16 05-Feb-16 19-Feb-16 26-Feb-16 08-Apr-16 06-May-16 20-May-16 03-Jun-16 17-Jun-16 15-Jul-16 29-Jul-16 12-Aug-16 26-Aug-16 12
Revised 24-Jun-16 15-Jul-16 04-Aug-16 01-Aug-16 08-Aug-16 18-Aug-16 26-Aug-16 29-Aug-16 28-Sep-16 21-Oct-16 04-Nov-16 21-Nov-16 25-Nov-16 05-Dec-16 16-Dec-16 13-Jan-17 23-Jan-17 11
2nd Revised 02-Nov-16 05-Dec-16 09-Jan-17 23-Jan-17 18-Apr-17 28-Apr-17 10-May-17 17-May-17 14-Jun-17 19-Jun-17 11
Actual 24-Jun-16 15-Jul-16 4-Aug-16 18-Aug-16 23-Sep-16 2-Sep-16 27-Oct-16 2-Nov-16 5-Dec-16 12-Jan-17 7-Apr-17 20-Apr-17 15-May-17 19-May-17 15-Jun-17 7-Jul-17 13-Jul-17 11 17
Schedule 06-May-19 17-May-19 31-May-19 - - 14-Jun-19 - 24-Jun-19 22-Jul-19 08-Aug-19 - 16-Aug-19 21-Aug-19 25-Aug-19 - 07-Sep-19 14-Sep-19 16
Actual 17-May-19 30-May-19 28-Jun-19 28-Jun-19 26-Jul-19 15-Aug-19 22-Aug-19 29-Aug-19 30-Sep-19 9-Dec-19 17-Dec-19 16 13.4839d Construction Supervision Consultant (CSC) in
Central Sulawesi ProvinceUSD 324,700 +
IDR 9,164,385,000 QCBS2,000,000
Technical Assistance for Development of SlopeStabilization, Design and Management, Western
Indonesia Roadsc
aCore Team Consultant (Project Management,Technical Assistant, Enviromental & Social Aspectand Road safety Audit)
bDesign and Supervision Consultant (Design AWP-2 & 3 and Construction Supervision of Civil WorksProject)
Updated January 31, 2020
PT. Egis InternationalIndonesia, PT.
Disiplan Consult, PT.Widya Graha Asana.
98.83
80
USD 155,300. +IDR
6,577,000,000.
USD 83,150. + IDR5,425,375,000. QCBS Prior
Period (Month)
40
42
Contract(US$)
(excl. VAT)
USD 2,160,443 +IDR
55,929,557,554
USD 1,285,208 +IDR
78,206,281,149
USD 1,276,700 +IDR
21,415,400,000
USD 820,600+
IDR51,818,705,000
the serviceis
completed
QCBS
QCBS
PT. Perentjana Djaja,Yongma Eng. Co. Ltdand PT. Epadascon
Permata EngineeringConsultant
Renardet S.A., PT.Cipta Strada, PT. DayaCreasi Mitrayasa, PT.Seecons, PT. Yodya
Karya (Persero)
Serviceperiod untilJanuary 31,2021
Serviceperiod untilJanuary 31,2020
Post
7,500,000
8,500,000
1,000,000
BOTEK BhosporusTechnical Cons. Corp
JV with AssociatedConsulting Engineers -
ACE (Pvt) Ltd
Date ofReceipt ofProposals
Prior
Evaluation and Short List Technical EvaluationReport Negotiation & Draft Contract
Prior
Theissuance
RFP to theshortlisted
firms
T O T A L
C:\Users\Tediero\AppData\Local\Temp\Appendix F Proc Plan WINRIP Consultants 20200131_FE0B0C.xlsx
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Appendix G
WINRIP Website & Application Progress
APPENDIX GManagement Information System (MIS) Status on January 2020
NO. TASK DESCRIPTION STATUS WORK PLAN1 File Storage
storage.winrip-ibrd.comThe storage server to stored allof soft files of reports anddocuments.
The new version of application has beencompleted on February 2015.
Has finished migrating to thePusdatin server.
2 DMS (DocumentManagement System)dms.winrip-ibrd.com
The application to record allinformation of letter anddocument files.
The DMS applications is already finalsdeveloped with the addition of features suchas parent-child mechanism, letter comments,and direct notification.
Has finished migrating to thePusdatin server.
3 Websitewww.winrip-ibrd.com
The WINRIP official website. The website has been developed on August2013.
Has finished migrating to thePusdatin server.
4 WebGISwebgis.winrip-ibrd.com
The spatial data and roadsinformation that overlay intoGoogle Maps.
The application has been developed onOctober 2013.
Has finished migrating to thePusdatin server.
5 FMIS (FinancialManagementInformation System)fmis.winrip-ibrd.com
The application to monitoring afinancial and physical progressreport.
The programming modules that have beenfinished are as follows: Project Data Financial and Physical Progress Progress Summary History of Financial and Physical Progress User
Has finished migrating to thePusdatin server.
6 CHS (ComplaintHandling System)chs.winrip-ibrd.com
The application to accommodatecomplaints from the public.
The application has been developed onJanuary 2014.
Has finished migrating to thePusdatin server.
7 WINRIP Cloudcloud.winrip-ibrd.com
The WINRIP-Storage server oncloud system.
The cloud system is running online inDecember 2016.
Has finished migrating to thePusdatin server.
8 CTC Daily ActivitiesReportdar.winrip-ibrd.com
Activity of all CTC personnelevery day.
It was completed on January 19, 2018, and isnow used by all CTC personnel.
Has finished migrating to thePusdatin server.
As Built Documents (PHO/FHO) of WINRIP PackagesStatus: January 2020
No. Document Type
WINRIP Package
DescriptionSumatera
Utara Sumatera Barat Bengkulu Lampung
05 15 02 03 07 08 20 21 04 06 11 13 19 01 17
1 Contract Agreement H S H S H S H S H S H S H S S H S H S H S H S H S H S H S
2 Contract Amendment and Support H S H S H S H S H S H S H S S H S H S H S H S H H S H S
3 Site Hand Over (SHO) H S H S H S H S H S
4 Commencement of Works (COW) H S H S H S H S H S H H S
5 Pre-Construction Meeting (PCM) H S H S H S H H S H S H S H H S H H
6 Job Mix Design, Job Mix Formula H S H S H S H S H S H S H S H S H H S H S H H S
7 Final Quantity and Back Up H S H S H S H H S H S H S S H S H H S H H
8Photo Documentation 0%, 50%, 100%Progress H S H S H S H S H S S H H S H S H S H S H H S
P20 only sends JPG andhard copy photo files.
9 As Built Drawing H S H S H S H H S H S H S S H S H S H S H S H H H SP06, 08, 21 send AutocadDWG files, not PDF files.
10 Payment Certificate (MS, IPC) H S H S H S H S H S H S H S S H S H S H S H S H H S H S
11 Taking Over Certificate (TOC) H S H S H S H S N/A S N/A N/A H S N/A H S H S N/A H S H S
12 Provisional Hand Over (PHO) H S H S H S H S H S H S H S H S H H S H S H S H S H S
13 Maintenance Program Plan (MPP) H S S H S H S H S H S H S H S
14 Final Hand Over (FHO)P01, 02, 03, 04 haven't sentFHO documents.
*) InformationH: Hard copyS: Soft fileN/A: Not Available
CHECKLIST OF DOCUMENTS IN THE WINRIP FILE STORAGELast Updated at The End of January 2020
NO PACKAGEACAP ENVIRONMENT FINANCIAL HIGHWAY PROCUREMENT QA RSA SOCIAL TRAINING
PROJECTPMU CTC
CRO CHU TPM AMDAL HIV/AIDS RKPPL SPPL UKL/
UPL IFR AUDIT DED EE RTA BD BEPR CON-TRACT PRAR COW PCM PMER PHO RSTMMR RSA LARAP STUDY
LARAP TIR WIR PMM IR MPR QPR SR PCR
1 Krui - Biha
#01#02#03#04#05#06#07#08#09#10#11#12#13#14#15#16#17#18#19#20#21#22#23#24
#2013#2014#2015#2016
Loan Agr.PIPPADMTR
#01 #56#02 #57#03 #58#04 #59#05 #60#06 #61#07 #62#08 #63#09 #64#10 #65#11 #66#12 #67#13 #68#14 #69#15 #70#16 #71#17 #72#18 #73#19 #74#20 #75#21 #76#22 #77#23 #78#24 #79#25 #80#26#27#28#29#30#31#32#33#34#35#36#37#38#39#40#41#42#43#44#45#46#47#48#49#50#51#52#53#54#55
#01#02#03#04#05#06#07#08#09#10#11#12#13#14#15#16#17#18
#01#02#03#04#05#06#07
2 Pd Sawah - SpEmpat
3 Manggopoh - PdSawah
4 Ipuh - Bantal
5 Sp Rampa - Poriaha
6 Ps Pedati - Kerkap
7 Indrapura - Tapan
8 Bts Kota Pariaman -Manggopoh
9 Rantau Tijang - KotaAgung
10 Sp Empat - Sp AirBalam
11 Bantal - Mukomuko
12 Kambang -Indrapura
13 Sp Rukis - TjKemuning
14 Painan - Kambang
15 Sibolga - Bts Tapsel
16 Seblat - Ipuh
17 Sp Gn Kemala -Pugung Tampak
18 Mukomuko - BtsSumbar
19 Lais - Bintunan
20 Lubuk Alung -Sicincin
21 Lubuk Alung -Kuraitaji
5A Simpang Rampa-Poriaha
RR-01 Tompe-Palu-Surumana
RR-02
Biromaru-Palopo;Palupi-Simoro;AksesHuntap Pombewe
*(Read the list of glossary on the next page).
Glossary of the Document Types in the DMS database.
NO DOCUMENT TYPE ABBREVIATION1 Addendum ADD2 Aide Memoire AM3 Amendment AMD4 Analisis Mengenai Dampak Lingkungan AMDAL5 Audit AUDIT6 Bid Document BD7 Bid Evaluation Procurement Report BEPR8 Commencement of Work COW9 Complaint Report CR
10 Contract CONTRACT11 Detail Engineering Design DED12 Draft Project Completion Report DPCR13 Engineer Estimate EE14 HIV AIDS Report AIDS15 Inception Report IR16 Interim Financial Report IFR17 Invoice INV18 Land Acquisition Resettlement Action Plan LARAP19 Loan Agreement LA20 Mid Term Review MTR21 Minute of Meeting MOM22 Monthly Progress Report MPR23 Photo PHOTO24 Pre-Construction Meeting PCM25 Procurement Plan PP26 Procurement Readiness Assessment Report PRAR27 Project Appraisal Document PAD28 Project Completion Report PCR29 Project Implementation Plan PIP30 Project Management Manual PMM31 Project Monitoring and Evaluation Report PMER32 Provisional Hand Over PHO33 Quarterly Progress Report QPR34 Rencana Kerja Pengelolaan dan Pemantauan Lingkungan RKPPL35 Report RPT36 Road Safety and Traffic Management Monitoring Report RSTMMR37 Road Safety Audit RSA38 Road Technical Analysis RTA39 Surat Pernyataan Pengelolaan Lingkungan SPPL40 Semestral Report SR41 Term of Reference TOR42 Third Party Monitoring TPM43 Training Implementation Report TIR44 Upaya Kelola/Pemantauan Lingkungan UKL-UPL45 Video VIDEO46 Wakil Pengamat Masyarakat WPM47 Workshop Implementation Report WIR
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Appendix H
ACAP Training /Dissemination Progress
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Appendix H ACAP Activity ProgressAppendix H1
Activities Progress of Community Representative Observers (CROs) and the Works PlanJanuary 2013 – January 2020
No Subject Activities of Community Representative Observers (CROs) Date of Finish/completed
1. Orientation and studied of WINRIP documents and Development of Works Plan January 2013
2 Prepared of Workshop of Procurement Document Evaluation. February 2013
3. Conducted Workshop of Procurement Document Evaluation for POKJA, Satker/PPK, BalaiBBPJN and PMU.
Febr. 28, 2013 –March 01, 2013
4. Provided of Term of Reference (TOR) of the CRO's Selection and Guidelines for CRO’sSelection
March 1, 2013
5. Provided the Materials (Slide Presentation/Power-point) of General Explanations aboutWINRIP and the CRO’s selection and
March 8, 2013
6. Provided Training Materials for CROs. March 8, 2013
7. Sending an official letter No. Hm.0603/Bp-11/0175/2013, from the Director of Planning asChairman of PMU to Head of BBPJN II & III, about the Selection of CROs/WPM, + TOR andGuidelines Document
March 11, 2013
8 Preparation of Socialization on CROs selection in BBPJN II Padang for package 02 PadangSawah – Simpang Empat and package 03 Manggopoh - Padang Sawah, and Socialization onCROs selection in BBPJN III Palembang for package 01 Krui – Biha and package 04 Ipuh –Bantal.
March 31, 2013
9. Socialization on CROs selection in BBPJN II Padang for package 02 Padang Sawah – SimpangEmpat and package 03 Manggopoh - Padang Sawah
April 9, 2013
10 Socialization on CROs selection in BBPJN III Palembang for package 01 Krui – Biha andpackage 04 Ipuh – Bantal.
April 11, 2013
11. Sent the Invitation letter from Head of BBPJN III to Rector of Universities /Head of Colleges inPalembang, about selection of the CROs for package 01. Krui – Biha (Prov. Lampung) andpackage 04. Ipuh – Bantal (Prov. Bengkulu).
May 17, 2013
12. Sent the Invitation letter from Head of BBPJN II to Rector of Universities /Head of Colleges inPadang, about selection of the CROs for package 02. Padang Sawah – Simpang Empat andpackage 03. Manggopoh - Padang Sawah (Prov. Sumatera Barat).
May 20, 2013
13. Selection of CROs for Packages Krui – Biha Province Lampung and Ipuh – Bantal ProvinceBengkulu, and training for selected CROs in BBPJN III Palembang
May 23, 2013
14. Selection of WPM/CROs for Packages Manggopoh – Padang Sawah and Padang Sawah –Simpang Empat, and training for selected CROs in BBPJN II Padang
May 27, 2013
15. Sending an official letter No. Hm.0603/Bp-11/0175/2013, from the Director of Planning asChairman of PMU to Head of BBPJN II & III, about the Selection of CROs/WPM, + TOR andGuidelines Document
May 28, 2013
16. Guiding the Balai Besar Pelaksanaan Jalan Nasional (Balai) II Padang to compose theApplication Letter for Approval of selected CROs for Package 03. Manggopoh – PadangSawah, package 02. Padang Sawah – Simpang Empat, and Balai III Palembang for Package 01.Krui – Biha Province Lampung and Package 04. Ipuh – Bantal Province Bengkulu.
May 29, 2013
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
No Subject Activities of Community Representative Observers (CROs) Date of Finish/completed
17. Compiling summary of the results of Selection the Community Representative Observers(CROs)/ Wakil Pengamat dari Masyarakat (WPM) and the Training activities for selectedCROs for four Packages AWP-1
June 1 - 9, 2013
18. Assist PMU to prepare the Approval letter of selected CROs for four AWP-1 Packages, andprepare of the Decree on Establishment the CROs of AWP-1 WINRIP from Director ofPlanning DGH, as the Chairman of PMU.
June 1 - 9, 2013
19. Monitor and observation the Pre-Bid Meeting and Site Visit activities of Procurement Processthat held by the Procurement Committee, in BBPJN II and III, on 10 June 2013 by CROs inimplementing their tasks on the
June 10 - 16,2013
20. Evaluate of the CROs observation on Pre-Bid Meeting and Site Visit activities Jun.17 - 23, 2013
21. Examine the report of CROs on the monitoring and observation of Pre-Bid Meeting and SiteVisit at the packages of Annual Works Program - 1 (AWP-1) WINRIP.
Modify the template of monitoring the report of the CROs, to be more focused and moresystematically
June 24 - 30,2013
22. Monitor /Observe of Bids Submission and Bids Opening for four packages AWP-1 byCommunity Representative Observers (CROs) for Package 01, 02, 03, and 04
July 18, 2013
23. Monitoring and examined of the CRO’s Report on the monitoring and observation of BidSubmission and Bid Opening activities for four packages of Annual Works Program - 1 (AWP-1) WINRIP, which have been carried out on July 18, 2013
August, 2013
24 Preparation on the Socialization of CROs selection to the Procurement Committee (POKJA) ofSumatera Utara province, for package Simpang Rampa – Poriaha and package Sibolga – BatasTapanuli Selatan
October 2013
25 Monitored /Observed of Procurement progress on Commencement of Bid Winners for fourpackages AWP-1 (Package 01, 02, 03, and 04) and informed to related CommunityRepresentative Observers (CROs).
November 2013
26 Carried out the dissemination of CROs selection to the Procurement Committee (POKJA) ofSumatera Utara province, for package Simpang Rampa – Poriaha. in Balai (BBPJN) I Medanand in Project Management (Satker) Office.
November 19 –20, 2013
27 Carried out the CROs selection for package 17: Simpang Gunung Kemala – Pugung Tampak inLampung..
July 17, 2014
28 Carried out the CROs selection for package 05: Simpang Rampa – Poriaha in North Sumateraprovince.
August 20, 2014
29 Carried out the CROs selection for package 11: Bantal – Mukomuko, and package 13:Simpang Rukis – Tanjung Kemuning in Bengkulu province.
Sept. 1, 2014
30 Ms. Hesti Aulia Sari, ST, CRO for Package 11: Bantal - Mukomuko, meet the invitation of theProcurement Committee (Pokja of Procurement Unit/Unit Layanan Pengadaan BBPJN III,PIU/Satker PJN Region I Bengkulu Province).
Oct. 03, 2014
31 Ms. Hot Maria Angelina, ST, CRO for Package 13: Simpang Rukis - Tanjung Kemuning wasattended Bid-Opening meeting meet the invitation by the Procurement Committee (Pokja ofProcurement Unit/Unit Layanan Pengadaan BBPJN III, PIU/Satker PJN Region II BengkuluProvince).
Oct. 03, 2014
32 Carried out the CROs selection for package 06: pasar Pedati –Kerkap and package 19: Lais -Bintunan in Bengkulu province.
Nov. 27, 2014
33 The elected CROs (Ms. Hot Maria Angelina, ST and Ms. Hesti Aulia Sari, ST) attanded Pre-BidMeeting and site visit for package 06 (Pasar Pedati – Kerkap) and package 19 (Lais –Bintunan), Bengkulu Province
Dec. 05, 2014
34 The Community Development team CTC WINRIP has carried out the selection of CROs forPackage 15: Sibolga – Batas Tapanuli Selatan. The Elected CRO is Ernie Shinta Y. Sitanggang,ST, MT, and Ir. M. Koster Silaen, MT as the substitute CRO (both from Politeknik NegeriMedan / State Polytechnic of Medan)
Dec. 16, 2014,
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
No Subject Activities of Community Representative Observers (CROs) Date of Finish/completed
35 The elected CROs for package 06 (Pasar Pedati – Kerkap) and package 19 (Lais – Bintunan)Bengkulu Province was attanded the Bid-Opening Meeting.
Dec. 29, 2014
36 Ir. M. Koster Silaen, MT as the substitute CRO of Package 15: Sibolga – Batas Tapanuli Selatanwas attended the Pre-Bid Meeting.
Jan. 26, 2015
37 Ir. M. Koster Silaen, MT as the substitute CRO of Package 15: Sibolga – Batas Tapanuli Selatanwas attended the Bid Opening Meeting
Feb. 23, 2015
38 The Community Development team CTC WINRIP has carried out the selection of CROs forfour packages WINRIP in West Sumatera province, as follow;6 The appointed CRO for Package 07: Indrapura – Tapan, is Ir. Riswandi, M.Si, and
Apwiddhal, ST, MT as the substitute CRO, both from State Polytechnic of Padang(Politeknik Negeri Padang).
7 The appointed CRO for Package 08: Batas Pariaman – Manggopoh, is M. Nursyaifi Yulius,MT (Mgt), and Ir. Alzahri, MT as the substitute CRO, both from Bung Hatta University ofPadang (Universitas Bung Hatta Padang).
8 The appointed CRO for Package 10: Simpang Empat – Simpang Air Balam, is Ir. Drs. Heldi,M.Si, and Ir. Afrizal Naumar, MT as the substitute CRO, both from Bung Hatta University ofPadang (Universitas Bung Hatta Padang).
9 The appointed CRO for Package 12: Kambang – Indrapura, is Syaiful Amri, SST, MT, and B.Army, ST, MT as the substitute CRO, both from State Polytechnic of Padang (PoliteknikNegeri Padang)
June 12, 2015
39 The appointed CRO Ir. Riswandi, M.Si for Package 07: Indrapura – Tapan, and the appointedCRO Syaiful Amri, SST, MT for Package 12: Kambang – Indrapura were attended the Pre-BidMeeting and Site Visit as invited by the Procurement Committee (Pokja) of PIU/Satker PJNRegion II of West Sumatera ProvinceThe appointed CRO M. Nursyaifi Yulius, MT (Mgt) for Package for Package 08: Batas Pariaman– Manggopoh, , and the appointed CRO Ir. Drs. Heldi, M.Si for Package 10: Simpang Empat –Simpang Air Balam were attended the Pre-Bid Meeting and Site Visit as invited by theProcurement Committee (Pokja) of PIU/Satker PJN Region I of West Sumatera Province.
June. 15-16, 2015
40 The appointed CRO Ir. Riswandi, M.Si for Package 07: Indrapura – Tapan, and the appointedCRO Syaiful Amri, SST, MT for Package 12: Kambang – Indrapura were sent the ObservationReport on Pre-Bid Meeting and Site Visit.
July. 02, 2015
41 The appointed CRO M. Nursyaifi Yulius, MT (Mgt) for Package for Package 08: Batas Pariaman– Manggopoh, , and the appointed CRO Ir. Drs. Heldi, M.Si for Package 10: Simpang Empat –Simpang Air Balam were sent the Observation Report on Pre-Bid Meeting and Site Visit.
July. 10, 2015
42 The CRO for Package 07: Indrapura – Tapan (Ir. Riswandi, M.Si), and the CRO for Package 12:Kambang – Indrapura (Syaiful Amri, SST, MT) were attended the Bid Opening Meeting.
August 13, 2015
43 The CRO for Package for Package 08: Batas Pariaman – Manggopoh (M. Nursyaifi Yulius, MT(Mgt), and the CRO for Package 10: Simpang Empat – Simpang Air Balam (Ir. Drs. Heldi, M.Si)were attended the Bid Opening Meeting.
August 13, 2015
44 Selection of CROs for packages 16 (Sebelat – Ipuh) in Bengkulu province, as follow;10 The appointed CRO for Package 16 is Mr. Besperi, ST, MT, and and Ms. Anggi Nidya Sari,
ST., MT as the substitute CRO. Both of them were from Bengkulu University.
Nov,.4-5, 2015
45 Selection of CROs for packages 14, 20, and 21 in West Sumatera province, as follow;11 The Elected CRO for Package 14 (Painan - Kambang) were Mr. M. Nursyaifi Yulius, MT
(Mgt), and Mr. Ir. Alzahri, MT, as the substitute CRO, both of them were from Bung HattaUniversity.
12 The Elected CRO for Package 20 (Lubuk Alung - Sicincin), were Mr. Ir. Riswandi, M.Si andMr. Syaiful Amri, SST., MT, as the substitute CRO, both of them were from StatePolitechnic of Padang (Politeknik Negeri Padang).
13 The Elected CRO for Package 21 (Lubuk Alung - Kuraitaji) were Mr. Jafril Tanjung, DR. Engand Mr. Ophiyandri, Ph.D as the substitute CRO, both of them were from AndalasUniversity
Nov,.16-17, 2015
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
No Subject Activities of Community Representative Observers (CROs) Date of Finish/completed
46 The substitute CRO for Package 16: Sebelat – Ipuh, Ms. Anggi Nidya Sari, ST., MT wasattended the Pre-Bid Meeting and Site Visit as invited by the Procurement Committee (Pokja)of PIU/Satker PJN Region I of Bengkulu Province.
Nov. 05, 2015
47 The substitute CRO for Package 14: Painan - Kambang, Mr. Ir. Alzahri, MT was attended thePre-Bid Meeting and Site Visit as invited by the Procurement Committee (Pokja) ofPIU/Satker PJN Region II of West Province.
Nov. 18, 2015
48 The Elected CRO for Package 20 (Lubuk Alung - Sicincin), Mr. Ir. Riswandi, M.Si, was attendedthe Pre-Bid Meeting and Site Visit as invited by the Procurement Committee (Pokja) ofPIU/Satker PJN Region I of West Sumatera Province.
Nov. 18, 2015
49 The Elected CRO for Package 21 (Lubuk Alung - Kuraitaji), Mr. Jafril Tanjung, DR. Eng, wasattended the Pre-Bid Meeting and Site Visit as invited by the Procurement Committee (Pokja)of PIU/Satker PJN Region I of West Sumatera Province.
Nov. 18, 2015
50 The substitute CRO for Package 16: Sebelat – Ipuh, Ms. Anggi Nidya Sari, ST., MT wasattended the Bid Opening Meeting, invited by the Procurement Committee (Pokja) ofPIU/Satker PJN Region I of Bengkulu Province.
Nov. 19, 2015
51 The substitute CRO for Package 16: Sebelat – Ipuh, Ms. Anggi Nidya Sari, ST., MT, was sentthe observation report on Pre-Bid Meeting and Site Visit
Nov. 25, 2015
52 The CRO for Package 14: Painan - Kambang, Mr. Ir. Alzahri, MT was attended the Bid OpeningMeeting as invited by the Procurement Committee (Pokja) of PIU/Satker PJN Region II ofWest Province.
Jan. 05, 2016
53 The Elected CRO for Package 20 (Lubuk Alung - Sicincin), Mr. Ir. Riswandi, M.Si, was attendedthe Bid Opening Meeting as invited by the Procurement Committee (Pokja) of PIU/Satker PJNRegion I of West Sumatera Province.
Jan. 05, 2016
54 The Elected CRO for Package 21 (Lubuk Alung - Kuraitaji), Mr. Jafril Tanjung, DR. Eng, wasattended the Bid Opening Meeting as invited by the Procurement Committee (Pokja) ofPIU/Satker PJN Region I of West Sumatera Province.
Jan. 05, 2016
55 The Elected CRO for Package 20 (Lubuk Alung - Sicincin), Mr. Ir. Riswandi, M.Si, was sent theObservation Report on Pre-Bid Meeting and Site Visit.
Jan. 06, 2016
56 The CRO for Package 07: Indrapura – Tapan (Ir. Riswandi, M.Si), was sent the ObservationReport on Bid Opening and Bid Winner Announcement.
Jan. 19, 2016
57 The CRO for Package 12: Kambang – Indrapura (Syaiful Amri, SST, MT) was sent theObservation Report on Bid Opening and Bid Winner Announcement.
Jan. 19, 2016
58 The CRO for Package 14: Painan - Kambang, (Mr. Ir. Alzahri, MT) was sent the observationreport on Pre-Bid Meeting and Site Visit.
Jan. 25, 2016
59 The Elected CRO for Package 21 (Lubuk Alung - Kuraitaji), Mr. Jafril Tanjung, DR. Eng, wassent the Observation on Pre-Bid Meeting and Site Visit.
Jan. 29, 2016
60 The CRO for Package for Package 08: Batas Pariaman – Manggopoh (M. Nursyaifi Yulius, MT(Mgt), was sent the Observation Report on Bid Opening and Bid Winner Announcement.
Feb. 17, 2016
61 The CRO for Package 14: Painan - Kambang, (Mr. Ir. Alzahri, MT), was sent the ObservationReport on Bid Opening and Bid Winner Announcement
May 10, 2016
62 The Elected CRO for Package 20 (Lubuk Alung - Sicincin), Mr. Ir. Riswandi, M.Si, was sent theObservation Report on Bid Opening and Bid Winner Announcement
May 10, 2016
63 The Elected CRO for Package 21 (Lubuk Alung - Kuraitaji), Mr. Jafril Tanjung, DR. Eng, wassent the Observation on Bid Opening and Bid Winner Announcement
May 31, 2016
64 The substitute CRO for Package 16: Sebelat – Ipuh, Ms. Anggi Nidya Sari, ST., MT, was sentthe observation report on Bid Opening Meeting and the Announcement of Bid-Winner forPackage 16 (Seblat – Ipuh) in Bengkulu Province
September 2016
65 Appointment of the CROs for procurement process of package 05A (Slope Protection of RoadSegment of Rampa – Poriaha / Mungkur in North Sumatera Province,. The appointed CRO isMrs. Ernie Shinta Sitanggang, ST, MT., as the main CRO, and Mr. Ir. M. Koster Silaen, MT, asthe reserve / replacement
April 24, 2018
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
No Subject Activities of Community Representative Observers (CROs) Date of Finish/completed
66 Provide Agreement Letter of establishment the CROs for Package 05A that was signed byDirector of Roads Network Development, Directorate of Highway.
April 25, 2018
67 The appointed CRO, Mrs. Ernie Shinta Sitanggang, ST, MT was attended the Pre-Bid meeting,as the step of procurement process of package 05A, in Balai Besar Pelaksanaan JalanNasional (BBPJN) / National Roads Implementation Agency II Medan
April 27, 2018
68 The pointed CRO of package No. 05A ((Slope Stabilization of Roads Link Simpang Rampa -Poriaha/Mungkur) Mr. Ir. Koster Silaen, MT accompanied by Community DevelopmentOfficer of CTC WINRIP (Mr. Yakobus) attended the Pre-Bid Meeting by ProcurementCommittee that was carried out in Satker PJN Wilayah II office of North Sumatera Province inMedan
Sept. 10, 2018,
69 The selection of Community Representative Observers (CROs) for WINRIP Package No. 21A(Lubuk Alung – Kuraitaji) in West Sumatera Province, in the office of Satker PJN Region I ofWest Sumatera Province. The pointed CRO for this package is Ir. M. Syaifi Yulius, M(Mgt),PhD, Lecturer from Pascasarjana of Bung Hatta University of Padang, and as the SubstituteCRO is Ir. Drs. Heldi, MSi, PhD.
Sept. 27, 2018
70 The Substitute CRO of package No. 21A (Lubuk Alung – Kuraitaji) Ir. Drs. Heldi, M.Si, PhDattended the Pre-Bid Meeting by Procurement Committee in Satker PJN Wilayah II office ofWest Sumatera Province in Padang
Oct., 18, 2018,
71 Appointment of the CROs for procurement process of package RR-01 (Tompe – Dalam KotaPalu – Surumana ) in Central Sulawesi . The appointed CRO is Mr. Dr.Ir.H. Jurair Patunrangi,MT., as the main CRO, and Mr. Ir. H.M. Kasan, MT, as the reserve / replacement
May 9, 2019
72 Appointment of the CROs for procurement process of package RR-02 (Palupi-Simoro ,Kalukubula-Kalawara , Birobuli-Palolo dan Akses Huntab) in Central Sulawesi . The appointedCRO is Mr. Dr. Ir.H.Syamsul Arifin MSc. , as the main CRO, and Mr.Dr.Ir. H Jurair Patunrangi ,MT, as the reserve / replacement
May 9, 2019
73 Appointment of the CROs for procurement process of package Construction SupervisionConsultant (CSC) in Central Sulawesi . The appointed CRO is Mr. Ir.H. M. Kasan , MT., as themain CRO, and Mr. Dr. Ir. H.Syamsul Arifin , MSc., as the reserve / replacement
May 9, 2019
74 The appointed CRO, Mr. Dr. Ir. H. Jurair Paturangi, MT was attended the Opening TenderDocument meeting, as the step of procurement process of package RR-01, in Office PJNWilayah I Central Sulawesi Jl. Kijang Raya No. 23 Palu
September 5 ,2019
75 The appointed CRO, Mr. Dr. Ir. H. Syamsul Arifin, MT was attended the Opening TenderDocument meeting, as the step of procurement process of package RR-02, in Office PJNWilayah I Central Sulawesi Jl. Kijang Raya No. 23 Palu
September 5 ,2019
76 The appointed CRO, Mr. Ir. H. M. Kasan , MT was attended the Opening Tender Documentmeeting, as the step of procurement process of package CSC, in Office PJN Wilayah I CentralSulawesi Jl. Kijang Raya No. 23 Palu
September 5 ,2019
77 The appointed CRO, Mr. Dr. Ir. H. Jurair Paturangi, MT was attended the Tender Evaluationmeeting with Tim Peneliti BP2JK, as the step of procurement process of package RR-01, inOffice BP2JK Wilayah I Central Sulawesi Jl. RE. Martadinata Ruko Tranway Avevue No. BB3/58Citra Land Palu.
October 11 , 2019
78 The appointed CRO, Mr. Dr. Ir. H. Syamsul Arifin , MSc. was attended the Tender Evaluationmeeting with Tim Peneliti BP2JK, as the step of procurement process of package RR-02, inOffice BP2JK Wilayah I Central Sulawesi Jl. RE. Martadinata Ruko Tranway Avevue No. BB3/58Citra Land Palu.u
October 11 , 2019
79 The appointed CRO, Mr. Ir. H. M. Kasan , MT was attended the Tender Evaluation meetingwith Tim Peneliti BP2JK, as the step of procurement process of package CSC, in Office BP2JKWilayah I Central Sulawesi Jl. RE. Martadinata Ruko Tranway Avevue No. BB3/58 Citra LandPalu.u
October 11 , 2019
80 The Community Development CTC WINRIP ( Mr. Gunawan Nugroho) has carried out thecoordination meeting with CROs for Package RR-01 , RR-02 and CSC for evaluation the CROsReport on Fakultas Teknik Tadulako University.
Nov. 17, 2019
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Appendix H.2The Progress of Third Party Monitoring (TPM) Activities and Works Plan for Next Steps
January 2013 – January 2020
No Subject Activities of Third Party Monitoring (TPM) Target Completed
1. Preparation the initial draft of ToR of selection the TPM Dec, 2013 Dec, 2013
2. Providing the TPM selection guidelines. Dec, 2013 Dec, 2013
3. Providing the Training Materials for the TPM Dec, 2013 Dec, 2013
4. Preparing the official letter from the Director of Planning as Chairman ofPMU to Head of BBPJN II & III, about the Selection of TPM. Jan, 2014 Jan. 24, 2014
5. Preparing the official letter from the Director of Planning as Chairman ofPMU to Universities, about the Selection of TPM. Jan., 2014 Jan 29, 2014
6. Preparing the official letter from the Official in Charge/Ketua PelaksanaHarian PMU to Satker/PPK, about the Selection of TPM Jan, 2014 Jan 13, 2014
7.Preparing the official letter from the Official in Charge/Ketua PelaksanaHarian PMU to Universities and Satker/PPK, about the Socialization ofTPM Selection for Package 01, 02, & 03
Feb. 2014 Feb. 07, 2014Feb. 13, 2014
8. Socialization of the TPM selection for package 01: Krui - Biha. Feb. 2014 Febr. 14, 2014
9. Socialization of the TPM selection for package 02: Padang Sawah –Simpang Empat and package 03: Manggopoh – Simpang Empat Feb. 2014 Febr. 18, 2014
10.Preparing the official letter from the Director of Planning as Chairman ofPMU to University of Bengkulu, about the Selection of TPM for package04: Ipuh - Bantal.
Jan, 2014 Febr. 19, 2014
11. Help the PMU on formulating the TPM Evaluation Team March 2014 Febr. 25, 2014
12. Implementation of selection of the TPM for four AWP-1 packages by TPMEvaluation Team March 2014 March 10, 2014
13. Delivery of the Preparatory Training for elected TPM for package 01: Krui– Biha in Lampung June 2014 June 5 - 6, 2014
14Delivery of the Preparatory Training for elected TPM for package 02:Padang Sawah – Simpang Empat, and package 03: Mangopoh – PadangSawah in West Sumatera
June 2014 June 17-18, 2014
15 Delivery of the Preparatory Training for elected TPM for package 04: Ipuh– Bantal in Bengkulu July 2014 July 7 – 8, 2014
16 Approval process of elected TPM July 2014 July 7 – 8, 2014
17 Assist PMU to prepare the Decree on Establishment the TPM of AWP-1WINRIP from Director of Planning DGH, as the Chairman of PMU.
August 2014 Sept. 1, 2014
18
Sending the Coordination Letter from Director of Planning, DirectorateGeneral of Highways to the Head of BBPJN Region I Medan, aboutSelection of the Third Party Monitoring (TPM) for package 05 (SimpangRampa – Poriaha, and package 15 (Sibolga – Tapanuli Selatan border) inNorth Sumatera.
October 2014 Oct, 07, 2014
19
Sent the Information Letter about participation of Third Party Monitoring(TPM) on WINRIP, from Director of Planning, Directorate General ofHighways to the University of Lampung (UNILA) for package 17 (SimpangGunung Kemala – Pugung Tampak) in Lampung Province.
October 2014 Oct, 03, 2014
20
Sent the Information Letter about participation of Third Party Monitoring(TPM) on WINRIP, from Director of Planning, Directorate General ofHighways to the University of Sumatera Utara (USU) for package 05(Simpang Rampa – Poriaha) in North Sumatera Province
October 2014 Oct, 03, 2014
21Sent the Information Letter about participation of Third Party Monitoring(TPM) on WINRIP, from Director of Planning, Directorate General ofHighways to the University of Bengkulu (UNIB) for package 11 (Bantal –
October 2014 Oct, 20, 2014
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
No Subject Activities of Third Party Monitoring (TPM) Target Completed
Mukomuko) and package 13 (Simpang Rukis - Tanjung Kemuning) inBengkulu Province.
22Selection of the Third Party Monitoring (TPM) for packages 17 (SimpangGunung Kemala – Pugung Tampak) Lampung Province November 2014 Dec. 4, 2014
23 Selection of the Third Party Monitoring (TPM) for packages 11, and 13,Bengkulu Province
December 2014 Dec. 22, 2014
24 Socialization and Explaination of the Third Party Monitoring (TPM) forpackages 05, and 15 in Universitas Graha Nusantara Padang-sidempuan
January 2015 Jan, 28, 2015
25 Socialization and Explaination of the Third Party Monitoring (TPM) forpackages 05, and 15 in Universitas Sumatera Utara Medan
January 2015 Jan, 30, 2015
26The Employment Agreement or Memorandum of Understanding betweenTPM (packages 01, 02, 03, and 04) with the CTC WINRIP (PT. PlannersDjaja) has been signed.
November 2014 Feb. 26, 2015
27Delivery of the Preparatory Training for elected TPM for package 11:Bantal – Mukomuko and package 13: Simp. Rukis – Tj. Kemuning, inBengkulu
January 2015 March 11-12,2015
28 Selection of the Third Party Monitoring (TPM) for packages 05, and 15,Northern Sumatera Province March 2015 April 9, 2015
29 Selection of the Third Party Monitoring (TPM) for packages 06, and 19, inBengkulu Province May 2015 May 5, 2015
30Delivery of the Preparatory Training for elected TPM for package 06:Pasar Pedati – Kerkap and package 19: Lais – Bintunan, in BengkuluProvince
June 2015 June 4-5, 2015
31 The TPM of package 01 (Krui - Biha) has been doing site observations (fieldvisit) for the first phase July 2015
32 TPM package 02 (Padang Sawah - Simpang Empat) and package 03(Mangopoh - Padang Sawah), had conducted a field visit for first phase July 2015
33 The TPM of package 01 (Krui - Biha) has been done site observations (fieldvisit) for the second phase
3rd week ofAugust 2015
34 The TPM of package 04 (Ipuh - Bantal) has been done site observations(field visit) for the first phase
4th of August2015
35 The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 01 Krui - Biha Agt. 19 -21, 2015
36 The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 04 Ipuh - Bantal Agt. 27 -28, 2015
37The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 02 (Padang Sawah – Simpang Empat)package 03 (Manggopoh Padang Sawah)
Sept. 10 - 11,2015
38The TPM of Package 02 (Padang Sawah – Simpang Empat) an package 03(Manggopoh Padang Sawah) had been done site observations (field visit)for the first phase
Sept, 2015
39Delivery of the Preparatory Training for appointed TPM for package 05:Sp. Rampa – Poriaha and package 15: Sibolga – Batas Tapsel in NorthSumatera Province
October 9, 2015
40 Delivery of the Preparatory Training for appointed TPM for package 17:Sp. Gunung Kemala – Pugung Tampak in Lampung Province Oct. 22, 2015
41 TPM package 04 Ipuh – Bantal has submitted their Field Visit MonitoringReport to PMU WINRIP Oct. 27, 2015
42 TPM package 03 Maggopoh – Padang Sawah has submitted their FieldVisit Monitoring Report to PMU WINRIP Nov. 11, 2015
43 TPM package 01 Krui – Biha has submitted their Field Visit MonitoringReport to PMU WINRIP Nov. 26, 2015
44 The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 11 (Bantal – Mukomuko) package 13 Dec. 03-04, 2015
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
No Subject Activities of Third Party Monitoring (TPM) Target Completed
(Simpang Rukis – Tanjung Kemuning) in Bengkulu Province
45 Selection of the Third Party Monitoring (TPM) for packages 07 and 12 inWest Sumatera Province Dec. 22, 2015
46 Selection of the Third Party Monitoring (TPM) for package 16 in BengkuluProvince Dec. 29, 2015
47 Selection of the Third Party Monitoring (TPM) for packages 08 and 10 inWest Sumatera Province Jan. 14, 2016
48The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 04 (Ipuh – Bantal) and package 11 (Bantal– Mukomuko) in Bengkulu Province
Apr. 6-8, 2016
49The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 02 (Padang Sawah – Simpang Empat) andpackage 03 (Manggopoh – Padang Sawah) in West Sumatra Province
Apr. 20-22, 2016
50The Community Development Team of CTC WINRIP has carry out ofSocialization of the TPM for package 14, 20, 21 to Andalas University ofpadang in BBPJN II Padang.
Apr. 27, 2016
51Community Development team has monitored the TPM activity onpackage 06 (Pasar Pedati – Kerkap) and package 19 (Lais – Bintunan) inBengkulu Province.
May 18–20, 2016
52Community Development team has carry out of TPM selection for package20 (Lubuk Alung - Sicincin) and package 21 (Lubuk Alung – Kuraitaji) inWest Sumatera Province
May 26, 2016
53Community Development team has delivered of the Preparatory Trainingfor appointed TPM for package 07and package 08 in West SumateraProvince
June 9, 2016
54Community Development team has monitored the TPM activity onpackage 05 (Simpang Rampa – Poriaha) and package 15 (Sibolga – BatasTapsel) in North Sumatera Province.
June 20–22, 2016
55 Community Development team has monitored the TPM activity onpackage 17 (Simpang Gn. Kemala – Pugung Tampak) in Lampung Province. July 27–29, 2016
56 Community Development team has carry out of TPM selection for package14 (Painan – Kambang) in West Sumatera Province Agt. 11–13, 2016
57 Community Development team has monitored the TPM activity onpackage 06 (Pasar Pedati – Kerkap) in Bengkulu. Agt. 24–26, 2016
58
Community Development team has delivered of the Preparatory Trainingfor appointed TPM for package 12 and package 14 in West SumateraProvince Sept. 27, 2016
59Community Development team has delivered of the Preparatory Trainingfor appointed TPM for package 20 and package 21 in West SumateraProvince
Oct. 13, 2016
60Community Development team has monitored the TPM activity onpackage 07 (Indrapura – Tapan) and package 12 (Kambang – Indrapura) inWest Sumatera Province.
Nov. 16–19, 2016
61 Community Development team has monitored the TPM activity onpackages 13 (Simpang Rukis – Tanjung Kemuning) in Bengkulu Proince. Nov. 28–30, 2016
62 Community Development team has monitored the TPM activity onpackage 05 (Simpang Rampa – Poriaha) in Nort Sumatera Province. Dec. 15 - 17, 2016
63 Community Development team has monitored the TPM activity onpackage 08 (Bt. Kota Pariaman – Manggopoh) in West Sumatera Province. Dec. 22 - 24, 2016
64 Community Development team has monitored the TPM activity onpackage 06 (Ps. Pedati – Kerkap) in Bengkulu Province. Dec. 29 - 31, 2016
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
No Subject Activities of Third Party Monitoring (TPM) Target Completed
65
Community Development team was facilitation TPM for package 04 (Ipuh- Bantal) and package 11 (Bntal – Mukomuko) of Bengkulu Province,meeting with Management of PT. Perentjana Djaja, on topic ofreimbursement of TPM monitoring cost.
Jan. 16, 2017
66Community Development team has monitored the TPM activity onpackage 20 (Lubuk Alung – Sicincin) and package 21 (Lubuk Alung –Kuraitaji) in West Sumatera Province.
March 2 - 4, 2017
67 Community Development team has monitored the TPM activity onpackage 14 (Painan – Kambang) in West Sumatera Province.
March 15 - 17, 2017
68 Community Development team has monitored the TPM activity onpackage 17 (Simp. Gng Kemala – Pugung Tampak) in Lampung Province.
March 22 - 24, 2017
69 Community Development team has monitored the TPM activity onpackage 12 (Kambang – Indrapura) in West Sumatera Province.
April 10 - 12, 2017
70 Community Development team has delivered of the Preparatory Trainingfor appointed TPM for package 16 in Bengkulu Province
April 27, 2017
71 Develop Report of Preparatory Training for TPM of package 16 (Sebelat -Ipuh) in Bengkulu
May 2, 2017
72 Develop Evaluation Report on Implementation of Third Party Monitoring(TPM) from the project beginning up to May 2017
May 4-8, 2017
73Prepare draft Special Report of the Implementation of Anti-CorruptionAction Plan (ACAP) as a part of draft CTC WINRIP Final Report or ProjectCompleting Report
Begin on May 9,2017
74Prepare the response to Supreme Audit Board / Badan PemeriksaKeuangan (BPK) Republic of Indonesia findings on funding the Third PartyMonitoring from Provisional Sums.
May 29-30, 2017
75Community Development team has monitored the TPM activity onpackage 15 (Sibolga – Batas Tapsel) and package 05 (Simpang Rampa –Poriaha) in North Sumatera Province.
June 13 - 17, 2017
76 Community Development team has monitored the TPM activity onpackage 16 (Seblat – Ipuh) in Bengkulu Province.
July 26 - 28, 2017
77Community Development team has monitored the TPM activity onpackage 08 (Batas Kota Pariaman – Manggopoh) in West SumateraProvince.
Agt. 28 - 30, 2017
78 Community Development team has monitored the TPM activity onpackage 14 (Painan –Kambang) in West Sumatera Province.
Sept. 14 - 16, 2017
79 Community Development team has monitored the TPM Activity forPackage 12 (Kambang – Indrapura) phase 2, in West Sumatera Province. Oct. 04 – 06, 2017
80Community Development team has monitored the TPM Activity forPackage 17 (Simpang Gunung Kemala – Pugung Tampak) phase 3, inLampung Province.
Oct. 16 – 18, 2017
81 Community Development team has monitored the TPM Activity forPackage 20 (Lubuk Alung – Sicincin) phase 2, in West Sumatera Province Oct. 26 – 28, 2017
82 Community Development team has monitored the TPM Activity forPackage 21 (Lubuk Alung – Kuraitaji) phase 2, in West Sumatera Province. Nov. 15 – 17, 2017
83 Community Development team has monitored the TPM Activity forPackage 07 (Indrapura – Tapan) phase 2, in West Sumatera Province Nov. 22 – 24, 2017
84Community Development team has monitored the TPM Activity for thirdphase of Package 08 (Batas Kota Pariaman – Manggopoh), in WestSumatera Province.
Dec. 13 – 15, 2017
85Community Development team has monitored the TPM Activity forsecond phase of Package 13 (Simpang Rukis – Tanjung Kemuning) inBengkulu Province
Dec. 20 - 22, 2017
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
No Subject Activities of Third Party Monitoring (TPM) Target Completed
86 Community Development team has monitored th TPM Activity for thirdphase of Package 07 (Indrapura – Tapan)in West Sumatera Province Jan. 22 – 25, 2018
87 Community Development team has monitored th TPM Activity for thirdphase of Package 20 (Lubuk Alung – Sicincin) in West Sumatera Province Feb. 7 – 9, 2018
88Community Development team has monitored the TPM Activity for thirdphase of Package 05 (Simpang Rampa – Poriaha) in North SumateraProvince
Feb. 21 – 23, 2018
89Community Development team has monitored the TPM Activity forsecond phase of Package 15 (Sibolga – Batas Tapsel) in North SumateraProvince
March 21 – 23,2018
90 Community Development team has monitored the TPM Activity forsecond phase of Package 16 (Seblat – Ipuh), in Bengkulu Province.
March 26 – 28,2018
91Community Development team has monitored TPM Activity for secondphase of package 13 (Simpang Rukis – Tanjung Kemuning) in BengkuluProvince.
April 19 – 22, 2018
92 Community Development team has monitored TPM Activity for thirdphase of package 12 (Kambang – Indrapura) in West Sumatera Province. May 03 – 06 2018
93 Community Development team has monitored TPM Activity for secondphase of package 14 (Painan - Kambang) in West Sumatera Province. May 22 – 24 2018
94 Community Development team has monitored TPM Activity for thirdphase of package 15 (Sibolga – Batas Tapsel) in North Sumatera Province. July 11 – 13, 2018
95 Community Development team has monitored TPM Activity for thirdphase of package 16 (Seblat - Ipuh) in Bengkulu Province. July 25 – 27, 2018
96 Community Development team has monitored TPM Activity observed ofpackage 16 (Seblat - Ipuh) in Bengkulu Province. Oct 18 – 20, 2018
97
Community Development Officer of CTC WINRIP and Third PartyMonitoring (TPM) team from State Polytechnic of Padang was monitoredand observed to the project field Package No. 12 (Kambang – Indrapura)in West Sumatera Province.
Nov. 15 - 17 2018
98
Community Development Officer of CTC WINRIP and Third PartyMonitoring (TPM) team from Bung Hatta University of Padang wasmonitored and observed to the project field Package No. 14 (Painan -Kambang) in West Sumatera Province.
Nov. 23 - 25 2018
99Community Development Officer of CTC WINRIP monitored the activitiesof Third Party Monitoring (TPM) of packages 08, 14, and 20 in WestSumatera Province on developing the TPM Monitoring Reports.
Nov. 28 - 30 2018
100 Selection of the Third Party Monitoring (TPM) for packages 21A in WestSumatera Province Feb. 20 – 22, 2019
101
Community Development Officer CTC WINRIP ( Mr, Gunawan Nugroho )has carried out the TPM Sozialisation on Fakultas Teknik TadulakoUniversity , It was attended by 6 candidates of TPM for packages RR-01and RR-02 Central Sulawesi Province
December 18 ,2019
102Selection and Appointed of the Third Party Monitoring (TPM) for packagesRR-01 and RR-02 in Central Sulawesi Province , on Office Balai PelaksanaJalan Nasional ( BPJN ) XIV Palu , Jalan MT. Haryono No. 10 Palu
December 19 ,2019
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
No Subject Activities of Third Party Monitoring (TPM) Target Completed
Works Plan for Next Step
1 Prepare and finishing the Contract Agreement between PT. PerentjanaDjaja and Tadulako University for Package RR-01 and RR-02 in Palu February , 2020 February , 2020
2 Prepare and practice the document of TPM Repot for Package RR-01 andRR-02 in Palu February , 2020 February , 2020
3Prepare and finishing the TPM Contract between PT. PerentjanaDjaja/CTC WINRIP and Universitas Bung Hatta Padang for Package 21A inPadang
February , 2020 February , 2020
4 Evaluation and finishing the TPM repots for Package 21A in Padang February , 2020 February , 2020
5 Prepare and finishing the Berita Acara Selection and Appointed TPMPackage 05A in Sibolga North Sumatera Provice February , 2020 February , 2020
6 Prepare and Finishing the letter of TPM Appointed for Package 05A inPMU WINRIP. February , 2020 February , 2020
7 Prepare the Contract Agreement between PT. Perentjana Djaja/CTCWINRIP and Universitas Graha Nusantara for package 05A. February , 2020 February , 2020
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Appendix H.3Works Activities on Complaints Handling Mechanism System (CHS)
March 2013 – January 2020
No Subject of Activities / Item of Tasks on Handling CHS Completion Plan/Progress Condition
1 Review of Minister Decree of Public Works No. 323/2005 concerning the procedures ofHandling input from communities on the environment of the Ministry of Public Works April 18, 2013
2 Preparation of Complaints Register and the complaints address (developing of web site ofWINRIP) and provided ACAP to inputting data in the web site.
Completed on themiddle of Feb. 2014.
3 Preparation of Complaint Handling Procedure (already available on the websiteapplication http://www.winrip-ibrd.com) April 2014
4The completion of the Initial investigation of a complaint Procedure, and the procedurefor the investigation of Complaints, as well as the conclusion of investigation (alreadyavailable on the website application http://www.winrip-ibrd.com)
April 2014
5 Monitored and noted the public complaints via SiPP website and WINRIP website, butuntil December 2014 have no complaint about the WINRIP programs December 2014
6
Clarification of Community complaint for package 02 & 03 by Jejak Media Group (JMG) byMr. Buyung on gravel aggregate materials, routine maintenance, and watering work site(dust pollution). It has been followed up by PPK 09 and PPK 10 to hold a clarificationmeeting, followed by the elements PPK, Supervision Consultant (DSC), and Jejak MediaGroup (JMG).
March 23, 2015
7
Clarification of information of work implementation on package 04: Ipuh - Bantal wasunfavorable, by TPM member (Mr. Hardiansyah, ST, MT). The information obtained fromthe local mass media. The problem is that the people around the location of the packageIpuh - Bantal especially road users complained about the excavation of road widening isleft open for an extended period of time without equipped with signs and safety fence,felt very dangerous, especially when driving at night, and according to the informationsome of the riders had been an accident which the vehicle plunged into the hole dug.This information has been followed up by PPK 01 Bengkulu together with the SupervisionConsultant (DSC Field Team) to instruct the Contractor to install traffic signs and safetyfences in places that endanger of road user
March 26, 2015
8
On May 11, 2015, Mr. Dr. M. Fauzi, ST, MT,, the main observer of the Third PartyMonitoring for Package 11 (Bantal - Mukomuko) Bengkulu Province, conveyinginformation from local newspaper clippings (Koran Rakyat Bengkulu) containing news thata 1.5-year-old toddler fell and nearly drowned in the excavation of the road wideningPackage 11 (Bantal - Mukomuko) which flooded about 80 cm deep. That is because theexcavation is situated in the location residential and not immediately undertaken, andwere not given the signs and safety fence.The complaint was submitted to the PMU and forwarded to the related PIU / PPK to beclarified. Until the end of May there has been no follow-up report to the complaint fromthe PIU / PPK 01 linked.
May 11, 2015
9
The CHS team has been received the copy of complaints letter from Tender Participantson package 08 to the Procurement Committee. Disclaimer of submitted by the tenderparticipants of package 08 (Batas Kot Pariaman – Manggopoh) PT. Adhi Karya (Persero)Tbk – PT. Yasa Patria Perkasa, JO by letter No: ADHI-YASA/12/I/2016 dated January 12,2016, to the Procurement Committee concerning to the results of Bid Evaluation Report(BER) section III, clause 4, point 4.2 (b): Specific Construction Experience in Key Activitiesspecifically on the experience of aggregate base production.
Jan. 15, 2016
10
CHS team has been received the other similar complaint to the Procurement Committeewas submitted by the same tender participant of package 12: Painan – Kambang (PT. AdhiKarya (Persero) Tbk – PT. Yasa Patria Perkasa, JO) by letter No: ADHI-YASA/11/I/2016dated January 4, 2016. The content of complaint was the similar subject i.e. the results ofBid Evaluation Report (BER) section III, clause 4, point 4.2 (b): Specific ConstructionExperience in Key Activities specifically on the experience of aggregate base production
Jan. 15, 2016
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
No Subject of Activities / Item of Tasks on Handling CHS Completion Plan/Progress Condition
11
CHS team has been received the complaints from Riki Susanato (Konsorsium Nasional LSMProvinsi Bengkulu) dated February 02, 2016. Riki Susanato and Edy Novriansyah had sent aletter No: 06/Khusus/XII/2015 dated December 11, 2015 on a request for publicinformation related to the documents of WINRIP project in Bengkulu province. But thisrequest was unable to fulfill by Satker PJN Wil. I of Bengkulu Province, especially inrelation to Contract Document / Letter of Agreement between the ProjectImplementation Unit of WINRIP for Bengkulu Province with the Contractors.By not granting of the request of the documents, then Riki Susanto delivered thecomplaint through the Complaint Handling System (CHS) of WINRIP website (www.winrip-ibrd.com). The complaint was submitted to the PMU WINRIP and the relevantstakeholders to immediately follow-up.
Feb. 02, 2016
12
On January 20, 2016, there was a World Bank letter No. 281 on reviewing Bid EvaluationReport (BER) for Package 16: Seblat – Ipuh in Bengkulu Province. World Bank has and havecomments on the Bina Marga proposed rejection of the five lower priced bidders.As a follow up of these comments, on February 10, 2016 has been held DiscussionMeeting to respond to the letter. Meeting followed by elements from the WB, PMU, PokjaPJN Reg. 1 of Bengkulu Province. Clarification should be explained in the revision of BERand sent to World Bank.
January 20, 2016February 10, 2016
13
The Complaint from Civil Society of villages in around the project STA 28+900 (DesaPondok Kandang, Desa Pondok Suguh, dan Desa Karya Mulya) was submitted through aletter of district head (Surat Camat) of Pondok Suguh, No. 620.52/56/K.05/IV/2016 datedApril 11, 2016, sent to the Supervision Consultants (Field Team DSC of Package 04) on therequest of one extra culvert / box culvert again, because the existing culvert in small sizeand its surface less downward, which is predicted when it rains the water could not floweasily or drained from the settlement and the Villages will be flooded.
April 11, 2016
14
Complaint by Buyung Fajri from Jejak Community sent to PMU WINRIP" via [email protected] on subject of performance audit of PT, JAYA KONTRUKSI MP.Tbkthat was Addendum until April 19, 2016 but the work is still ongoing until April 23 2016,how it could happen, we ask for explanation
May 11, 2016,
15
Complaint by Buyung Fajri from Jejak Community sent to PMU WINRIP" via [email protected] on subject evaluation of stone masonry works on bridgeapproach of Air Gadang Bridge in package 02 (Padang Sawah – Simpang Empat) WestSumatera Province. The stone masonry works by contractor PT. JAYA KONTRUKSI MP.Tbkis bed quality, did not match to the specification
May 14, 2016
16
Complaint by Buyung Fajri from Jejak Community sent to PMU WINRIP" via [email protected] and to Menteri PUPERA by e-mail minister of Public Works and onsubject of the National Road in Pasaman Barat - West Sumatra province, many of themwere which seriously damaged.
May 17, 2016
17Complaint by Buyung Fajri from Jejak Community sent to PMU WINRIP" via [email protected] on subject that Air Gadang Bridge until May 31, 2016 is not yet befinished.
May 31, 2016
18
The Community Development Officer and Information Management Specialist wasmeeting with World Bank (Mr. Andri Wibisono) on topic of completeness the WINRIPwebsite included Complaint Handling System (CHS). The main subject is the completenessof the website application program, the completeness data sources, and the applicableand accessible of this website, so everyone can access or find the data that they needs.
August 2, 2016
19
On January 30, 2017 Complaint Unit has received one complaint from someone namedBuyung Fajri from Non-Government Organization “JEJAK Community”. It is complained ofis that, the contract value is not listed on the information board and workers of heavyequipment Operators are not using personal safety (K3) i.e helmet
January 30, 2017
20Complaint Unit has received one complaint from Buyung Fajri from Non-GovernmentOrganization “JEJAK Community” thru email dated February 15, 2017, regarding theimplementation of WINRIP Packages No.21 Lubuk Alung – Kuraitaji
February 15, 2017
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
No Subject of Activities / Item of Tasks on Handling CHS Completion Plan/Progress Condition
21On February 16, 2017, Complaint Unit has received one complaint from Buyung Fajri (Non-Government Organization “JEJAK Community”) thru email, regarding the maintenance ofWINRIP Packages No.03 Manggopoh – Padang Sawah
February 16, 2017
22
Complaint Handling Unit of CTC has received public complaints from Buyung Fajri (Non-Government Organization “JEJAK”), thru email on March 5, 14, and 21, 2017, regardingthe condition of retaining wall on approach road of Air Gadang Bridge in Packages No. 02Padang Sawah – Simpang Empat. This package has been PHO on April 14, 2016 is nowentered the maintenance period.
March 5, 14, and21, 2017
23Complaint Handling Unit of CTC has received public complaints from Buyung Fajri (Non-Government Organization “JEJAK”), thru email on March 21, 2017, regarding theimplementation of WINRIP Packages No.21 Lubuk Alung – Kuraitaji
March 21, 2017
24
On April 6, 2017 was complaint from Berita Harian Sumbar http://sumbar.auditpos.com(Non-Government Organization), thru email to the World Bank’s Highway Engineer Mr.Agus Sjamsudin ([email protected]) regarding the implementation of Package20 Lubuk Alung – Sicincin on concrete reinforcement of drainage structure was not inaccordance with the specification, and the bad quality of mortar for retaining wall
April 6, 2017ClarifiedApril 13, 2017
25
Complaint Handling Unit of CTC has received public complaints from Buyung Fajri (Non-Government Organization “JEJAK”), thru email on April 7, 2017 and April 23, 2017,regarding the implementation of WINRIP Packages No.21 Lubuk Alung – Kuraitaji. TheContractor PT. MULTI STRUCTURE ignores the road user's safety.
April 7, 2017April 23, 2017
26Prepare the Response of the complaints from Mr. Buyung Fajri (Non-GovernmentOrganization “JEJAK”) of April 23, 2017 regarding the implementation of WINRIP PackagesNo.21 Lubuk Alung – Kuraitaji
May 2, 2017
27Complaint Handling Unit of CTC has received public complaints thru [email protected] on July 10, 2017, regarding the implementation of package 12(Kambang - Indrapura) in West Sumatera Province, on subject of Asphalt pavement quality.
July 10, 2017
28
The Complaint Handling Unit of PMU has received one public complaints submitted by Mr.Buyung Fajri (Non-Government Organization "JEJAK") thru email([email protected]), regarding the implementation of WINRIP Package No. 12:Kambang – Indrapura in West Sumatera Province.The Subject of complaint is the Contractor PT. LMA - CTA, performs paving/asphaltingwork at the night and during the rain. This would reduce the quality of work is not inaccordance with specifications
August 20, 2017
29 The Complaint Handling Unit has received one complaint from NGO “Portal Bengkulu”regarding implementation of Package 16 (Sebelat – Ipuh) Dec. 19, 2017
30
The public complaints submitted by Mr. Yudha from “Masyarakat Transportasi Indonesia”(Indonesian Transportation Society) of West Sumatera Province, thru WhatsApp to theMinister of Public Works and Housing, on January 30, 2018 regarding the implementationof WINRIP Package No. 21: Lubuk Alung – Kuraitaji in West Sumatera Province.The subject of the complaint is that package 21 (Lubuk Alung - Kuraitaji) should be finished(Professional Hand Over "PHO") or take over on December 31, 2017. The reality ofimplementation progress is only about 50%, even execution time is extended or anaddendum of time. This is an indication that something is wrong with the implementationof the package.Up to May 2018 the PMU/PIU has not provided information on the answer to thecomplaint.
Jan. 30, 2018
31
The complaints submitted by Mr. Agung Anwari thru email <[email protected]>to the PMU WINRIP ([email protected]) dated October 19, 2018 regarding theimplementation of WINRIP Package No. 12: Kambang - Indrapura in West SumateraProvince,The Subject of complaint is cheating trick of PT. LMA - CTA as Contractor on package 12WINRIP (Kambang – Indrapura), performs cheating trick regarding the implementation ofPackage 12:1. Part of structure especially mortar channel and retaining wall, the dimension not
appropriate with the design and mortar is not appropriate with the techniquespecification.
October 19, 2018
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
No Subject of Activities / Item of Tasks on Handling CHS Completion Plan/Progress Condition
2. Widening excavation depth should be 60 cm (25 cm for selected, 20 cm for aggregatebase B and 15 cm for aggregate base A). But, in implementation there are manylocations did not reach to 60 cm (only 30-45 cm). Thus, contractor has been “steal” tothe excavation nor pile of excavation because it is still billed to the state 60 cm. if itless of depth excavation means less of foundation layer. The examples of “stealexcavation depth” locations as follows:a. Sta. 12 – Sta. 15 (L/R), the executor of the work is Sartono from PPb. Sta. 19 – Sta. 21 (L/R), the executor of the work is Suryadi from LMAc. Sta. 24 – Sta. 27 (L/R), the executor of the work is Jondra from LMAd. Sta. 37+300 (L/R), the executor of the work is Yudi from LMA. At this location only
using aggregate base A.3. Asphalt paving
Asphalt paving should be layer by layer, begin with AC Base leveling, AC Base, ACBinder, AC Wearing. AC Base leveling pavement process should be appropriate withthe existing (as wide as existing and maximum thickness 5 cm), after that, prime coatand take coat process, and last AC Base pavement process with maximum thickness7.5 cm and wideness 7 m. But, at package 12 AC Base leveling and AC Baseimplemented at once not layered. Implemented all process at once means it haseliminated one (1) item that is take coat (which is still billed to the state). If Asphaltpavement implemented at once, can it guarantee the asphalt density?The examples of “steal take coat and asphalt pavement at once” locations (AC Baseleveling + AC Base) as follows:a. Sta. 0+000 – 0+580 (Pasar Kambang)b. Sta. 3+760 – 5+700 (Lakitan Bridge)c. Sta. 5+700 – 6+900 (Lakitan Bridge – Koto Raya Bridge)d. Sta. 6+925 – 8+150 (Koto Raya Bridge – Karang tengah – Lakitan Selatan)e. Sta. 29+480 – 30+100 (SMKN 1 Linggo Sari Baganti – Lagan)f. Sta. 30+500 – 31+050 (in front of SPBU Lagan – Tandikat Bridge)g. Sta. 31+080 – 31+320 (Tandika Pusangga Utara Bridge)
All the cheating above implemented before Idul Fitri 1439 H and still working until now.Policy maker of “steal implementation work” are:1. Immanuel Riberitas (PP)2. Dasril (GS of PT. LMA)3. Refly (chief inspector consultant PT. YASA)Other than that “steal” implementation work, package No. 12 has other broken work asfollows:1. Regarding Health and Safety of Works (Kesehatan dan Keselamatan Kerja “K3”), there
are illegal levies to K3 members by coordinator of K3 that is Rafik and Wulanregarding office hour arrangement (on setting mandatory working hours andovertime hours).
2. The omission by GS of PT. LMA (Dasril) against one of the community relationsofficers named Irwanto (retired Army) who traded (buy-and-sell) materials belongingto the project package No. 12 for personal interest.
3. The daily labor problem since project begin at 2016 has occurred, such as if laborworking at holiday or week end, they not paid and also on Idul Fitri holidayallowances they never get benefits.
Other Activity
1 The establishment of the settlement Commission Handling the Complaint under theInspectorate General of the Ministry of Public Works (Executing Agency) if it necessary
Will establish if there is acase that needs specialhandling
2Preparation of the device for Executing Agency such as: Procedures announcement ofpenalties, procedures for the annual Survey, Procedure Annual Independent Review, theprocess of Auctions
Done by ProcurementSpecialist and theContract ExaminerCommittee
3 The development of a code of conduct and actions for Implementing Institutions/Implementing Agency (Bidders, Suppliers, contractors and Consultants)
Done by PMU of DGH
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
No Subject of Activities / Item of Tasks on Handling CHS Completion Plan/Progress Condition
4 Support the PMU in the Management and Monitoring of the implementation policy inhandling public complaints
Have been carried outthroughout projectimplementation period
Appendix H.4Works Activities on Publication / Disclosure Activities
January 2013 – January 2020
No Subject of Activities / Item of Tasks of Publication / Disclosure Completion Plan/Progress Condition
1 Conducted Workshop of Procurement Document Evaluation for POKJA,Satker/PPK, Balai BBPJN and PMU
February 28, 2013– March 01, 2013
2 Conducted Workshop of World Bank Guidelines of Procurement for WINRIP tothe POKJA, Satker/PPK, Balai BBPJN and PMU
April 24 – 25, 2013
3 Review training materials on Project Management Manual (PMM), especiallyCHAPTER XI of the anti-Corruption Action Plan (ACAP)
First updating April 29, 2013
4 The second Review of training materials on Project Management Manual(PMM), Chapter I - XII
Second updating onDecember 18, 2013
5 The third Review of training materials on Project Management Manual (PMM),Chapter I - XII
third updating onApril, 2014
6. Preparing Method Transparency to the Public, and Improvement the proceduresto the Public Disclosure through information media (website).
Establishment of InformationSystem (MIS) was finish on
March 2014
7. The updating of Project Management Manual (PMM), Chapter 3, 9, 11, and 13,has been held in Bogor June 2014
8 Delivery of the Preparatory Training for elected TPM for AWP-a packages: 01,02, and 03 June 2014
9 Delivery of the Preparatory Training for elected TPM for AWP-a packages: 04 July 2014
10 The implementation of Dissemination/training of the PMM to Stakeholders forPackages 01, 02, 03, and 04
September 10 - 11 2014
11Inputting / upload / update of data/documents/reports of the CommunityRepresentative Observers (CROs) activities for packages 01, 02, 03, 04, 17, 11,13, 05, 06, 19, and 15 into the WINRIP’s website.
From Augt 2013 – April, 2015
12Inputting / upload / update of data/documents/reports of the Third PartyMonitoring (TPM) activities for packages 01, 02, 03, 04, 17, 11, and 13 into theWINRIP’s website.
From Augt 2013 – April, 2015
13Inputting / upload / update of data/documents/reports of Procurement ofContractors for packages 01, 02, 03, 04, 17, 11, 13, 05, 06, and 19 into theWINRIP’s website.
From Augt 2013 – April, 2015
14Inputting / upload / update of data/documents/reports of Environmentalactivities for packages 01, 02, 03, 04, 17, 11, 13, 05, 06, and 19 into the WINRIP’swebsite.
From Augt 2013 – April, 2015
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
No Subject of Activities / Item of Tasks of Publication / Disclosure Completion Plan/Progress Condition
15Inputting / upload / update of data/documents/reports of Social Safeguard /LARAP for packages 01, 02, 03, 04, 17, 11, 13, 05, 06, and 19 into the WINRIP’swebsite.
From Augt 2013 – April, 2015
16Inputting / upload / update of Progress Report/ Actual Status (fisichal worksand financial) of each package that has been contracted (packages 01, 02, 03,and 04) into the WINRIP’s website.
From Augt 2013 – April, 2015
17 Inputting / upload of Monthly Progress Report (MPR December 2012 – December2014) into the WINRIP’s website.
Every Month
18 Inputting / upload of Quarterly Progress Report (QPR December 2012 –December 2014) into the WINRIP’s website.
Every Three Months
19 Delivery the IFM Training for Stakeholders (Official and staff of Satker, Officialand staff of PPK) packages 01, 02, 03, and 04.
26 – 27 November 2014
20 Publish the Quarterly Newsletter on official website of MPW and WINRIP’swebsite
Every three months forQuarterly Newsletter October –
December 2015
21 Delivery the IFM Training for Stakeholders (Official and staff of Satker, Officialand staff of PPK) packages 05, 11, 13, and 17.
Feb. 11 - 12, 2015
22 Report of Technical and Financial Audit Consultants (TFAC) for Packages 02 and03 has been received from TFAC Team
Feb. 27, 2015
23
Delivery of the Preparatory Training for elected TPM for package 11: Bantal –Mukomuko and package 13: Simp. Rukis – Tj. Kemuning, in Bengkulu. Thistraining followed the elements of TPM, Satker/PPK, Contractors, SupervisionConsultants, and Balai BBPJN III Palembang.This training is intended to provide an explanation of the scope of duties of TPMand provide information to all elements involved in the implementation of theproject that the community be involved in monitoring the implementation ofthe project which is represented by the TPM, in accordance with the LoanAgreement.
March 11 – 12, 2015
24 Publish the Quarterly Newsletter on official website of MPW and WINRIP’swebsite
Every three months forQuarterly Newsletter January –
March 2015
25Delivery of PMM Socialization to Stakeholders (Balai BBPJN III, PIU/PPK,contractors and Supervision Consultants ‘DSC’) for four Packages (06, 11, 13,and 19) in Bengkulu Province
May 6 – 7, 2015
26
Delivery of the Preparatory Training for elected TPM and Work Plan for manageand monitor the Environment / Rencana Kerja Pengelolaan dan PemantauanLingkungan (RKPPL) for package 06: Ps. Pedati – Kerkap and package 19: Lais –Bintunan, in Bengkulu. This training followed the elements of TPM, Satker/PPK,Contractors, Supervision Consultants, and Balai BBPJN III Palembang.
June 4 – 5, 2015
27 Publish the Quarterly Newsletter on official website of MPW and WINRIP’swebsite
Every three months forQuarterly Newsletter April –
June 2015
28 The Mid-Term Report of the first semester 2015 has been written by the early ofJuly 2015
July, 2015
29 Delivery of PMM Training for Stakeholders (PPK, contractors and SupervisionConsultants ‘DSC’) for Packages 17, 05, and 15
November 23 – 24, 2015
30Inputting / upload / update of data/documents/reports of the CommunityRepresentative Observers (CROs) activities for packages 07, 08, 10, 12, 14, 16,20 and 21 into the WINRIP’s website.
From May – Dec, 2015
31Inputting / upload / update of data/documents/reports of the Third PartyMonitoring (TPM) activities for packages 05, 06, 07, 12, 15, 19 and 16 into theWINRIP’s website.
December, 2015
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
No Subject of Activities / Item of Tasks of Publication / Disclosure Completion Plan/Progress Condition
32Inputting / upload / update of data/documents/reports of Procurement ofContractors for packages 07, 08, 10, 12, 14, 16, 20 and 21 into the WINRIP’swebsite.
From June – Dec, 2015
33 Inputting / upload / update of data/documents/reports of Environmentalactivities for 07, 08, 10, 12, 14, 16, 20 and 21 into the WINRIP’s website.
From May – Dec, 2015
34Inputting / upload / update of data/documents/reports of Social Safeguard /LARAP for packages for 07, 08, 10, 12, 14, 16, 20 and 21 into the WINRIP’swebsite.
From May – Dec, 2015
35Inputting / upload / update of Progress Report/ Actual Status (physically works,financial and audits) of each package that has been contracted (packages 05, 06,07, 11, 13, 15, 17 and 19) into the WINRIP’s website.
From May – Dec, 2015
36Inputting / upload / update of data/documents/reports of the CommunityRepresentative Observers (CROs) activities for packages 14, 20 and 21 into theWINRIP’s website.
January, 2016
37Inputting / upload / update of data/documents/reports of the Third PartyMonitoring (TPM) activities for packages 14, 20, and 21 into the WINRIP’swebsite.
December, 2015
38 Updated the Project Management Manual (PMM) Chapter III : Planning andProgramming
January, 2016
39 Review and Updated of the Project Management Manual (PMM) Chapter IX :Performance Monitoring and Evaluation,
March, 2016
40 Review and Updated of the Project Management Manual (PMM) Chapter XI:Anti-Corruption Action Plan (ACAP)
April, 2016
41Review and Updated of Power-point presentation of the Project ManagementManual (PMM) Chapter IX : Performance Monitoring and Evaluation, Chapter XI:Anti-Corruption Action Plan (ACAP)
June, 2016
42
The Information Management Specialist and Community Development Officerimmediately follow up the results of the meeting with World Bank to becompleted and perfected. The results of that meeting be used as an ingredientof Kick-off and Wrap-up Meeting, which would then be inserted in the Final AdieMemoire of August 11, 2016
August 11, 2016
43
Delivery of PMM Socialization to Stakeholders (Balai BPJN III, PIU/Satker Region Iand II of West Sumatera, PPK 06 (pack. 20), PPK 10 (Pack. 08 & 21), PPK 14(Pack. 14), PPK 15 (Pack. 07), contractors and Supervision Consultants ‘DSC’) forfour Packages (07, 08, 14, 20, and 21) in West Sumatera Province
Augt. 29 –31, 2016
44 Delivery of TPM Preparatory Training for packages 12 and 14 in Padang, WestSumatera
Sept. 26 – 28, 2016
45The CTC (Community Development Team) has been carried out preparatorytraining for Third Party Monitoring (TPM) of packages 20 and 21 in Padang, WestSumatera.
October 13, 2016
46 Review and identify the changing of Project Management Manual (PMM)Modules from Revision-1 version to Revision-2. Oct. 18 - 24, 2016
47Prepare draft of Agreement Letter of Director of Roads Net WorkingDevelopment on establishment of Working Group /Task Force for updating andimprovement of the PMM.
Oct. 25 - 27, 2016
48 Prepare draft proposal of Price Adjustment /Escalation Workshop for theWINRIP Oct. 28 – Nov. 14, 2016
49 During January 2017 all CTC Professional were prepare the updating the ProjectManagement Manual (PMM) January 2017
50During February 2017 all CTC Professional were updated the ProjectManagement Manual (PMM) for revision 2. The Community DevelopmentOfficer was updated Chapters III, IX, XI, and XIII.3.
February 2017
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
No Subject of Activities / Item of Tasks of Publication / Disclosure Completion Plan/Progress Condition
51Prepare the response to Supreme Audit Board / Badan Pemeriksa Keuangan(BPK) Republic of Indonesia findings on funding the Third Party Monitoring fromProvisional Sums, and meeting with BPK.
May 29-30, 2017
52During January 2018 the Community Development Officer was updated theProject Management Manual (PMM) for last final update of Chapters III, IX, XI,and XIII.3.
Jan. 15 – 19, 2018
53During March 2018 the Community Development Officer in collaboration withInformation Management Specialist was updated the list of Complaint Handlingin website of WINRIP (www.winrip-ibrd.com)
March 2018
54
On April 2018 the Community Development Officer in collaboration withInformation Management Specialist was updated the data of CROs of Package05A Slope Protection of Roads Segment of Rampa – Poriaha in North SumateraProvince in website of WINRIP (www.winrip-ibrd.com)
April 2018
55 During August 2018 the Community Development Officer was updated theProject Management Manual (PMM) Chapters III, IX, XI, and XIII.3. August 2018
56During September 2018, input data CROs for Package No. 05A ((SlopeStabilization of Roads Link Simpang Rampa - Poriaha/Mungkur) in NorthSumatera) and Package 21A (Lubuk Alung – Kuraitaji) in West Sumatera.
September 2018
57 During October 2018, input data CROs for Package No. 21A (Lubuk Alung –Kuraitaji) in West Sumatera October 2018
Activities Plan for Next Step
1 Delivering the other training programs of WINRIP shall inline of projectimplementation progress.
Depend on projectimplementation progress
2 Public Expose on ACAP to the civil society forum in each project location (eachpackage)
Before the construction worksstarted
3 Monitoring of the implementation of disclosure and transparency of informationto each package during contraction period.
Plan for three time monitoringto field for each package during
contraction period
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Appendix H.5Status of WINRIP’s Anti-Corruption Action Plan Activity
Edition: January, 2020
RISKAREA
NoACTIONS STATUS (as of January, 2020)
Enha
nced
Dis
clos
ure
and
Tran
spar
ency
-
1 MPWH will provide the contact information forcomplaints related to WINRIP in the PIP, PMM, andMPWH website and in the bidding documents.
Complaint Handling System has been established, written inPMM (Chapter 11.4), and published on DGH website(http://binamarga.pu.go.id) linked to WINRIP website(http://www.winrip-ibrd.com).Contact information is provided in the Bidding DocumentsChapter 2: Instruction to Bidders (Instruksi Kepada PesertaLelang - IKP 34).
2 Work Programs and Procurement Plan publishedon the official MPWH website and made itavailable to the public.
Work Programs and Procurement Plan available in the MPWHwebsite (http://eproc.pu.go.id) and in the WINRIP website (onhttp://www.winrip-ibrd.com, click Pengadaan to see all thedata on Procurement Plan, Procurement Information, and Listof Contract awarded).- Procurement data for package 05A , 21A , RR-01 and RR-02is
under process uploading in to the website.3 Procurement Plan updated annually. The last version as draft has been updated on October 31,
20184 Quarterly newsletter published on the official
website of MPWH, including informationconcerning the list of contracts, implementationprogress, project-related workshops and thenumber, typology, and status of complaints.
Quarterly newsletter is updated every three months. Threenewsletters were published in 2015 (the first one correspondsto the period between January and March, 2015); and threenewsletters were also published in 2016. The latest newsletter(July – September, 2018) has been published on the WINRIPwebsite (http://www.winrip-ibrd.com) linked to DGH website(http://binamarga.pu.go.id).These newsletters include the summary of the physical worksimplementation progress, the list of the trainings/workshopshold, and other relevant information on contracting aspects.
5 Quarterly newsletter sent by MPWH to the civilsociety forum in each project province in hard copyor through an electric mailing system.
The Quarterly Newsletter is always sent to the civil societyforum: i.e. Indonesian Road Development Association/Himpunan Pengembangan Jalan Indonesia (HPJI) andIndonesian Transportation Society/Masyarakat TransportasiIndonesia (MTI) in central level and to the provincial levelwhere the WINRIP project are developed, by e-mail.The latest newsletter of October – December 2018 has beenpublished and been sent to the civil society forum by e-mail andby mail in early of January 2019.
6 Bidding documents, short-list of consultants andrequests for proposals (this provision does notinclude actual bids and proposals), issued inaccordance with the procurement provisions of theloan agreement, are available to any member ofpublic promptly upon request, subject to paymentof a reasonable fee for producing biddingdocuments and request for proposals. Thedocuments are available until a year aftercompletion of the contract for the goods, works orservices in question.
The Bidding Documents such as: Standard Bidding Document,Bid Invitations, Instruction to Bidders, General Specifications,Detailed Engineering Design/Drawing, General Condition ofContracts, Special Condition, Bill of Quantity, Owner Estimate,etc, are available on MPWH website (http://eproc.pu.go.id)and some of them were also uploaded in WINRIP website(http://www.winrip-ibrd.com). Packages 01, 02, 03, 04, 05, 06, 07, 08, 11, 12, 13, 14, 15, 16,
17, 19, 20, 21, 05A , 21A , RR-01 and RR-02 have beenalready awarded.
Packages 09, 10 and 18 were cancelled from list of WINRIPProgram.
The bidding of Package 05A (Slope Protection of RoadSegment in Rampa – Poriaha / Mungkur in North SumateraProvince, on April 27, 2018 is failed. Re-bid for this packagewas held on September 2018. The bidding was failure and
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
RISKAREA
NoACTIONS STATUS (as of January, 2020)
that was no winner. So that the package should be re-bidding again.
The contract Package 21A was sign on 21 December 2018. Package in Central Sulawesi Province : Paket RR-01 was sign
on October 25 ,2019 and Paket RR-02 was sign November 1 ,2019
7 Information as follows published in UNDB on-line,and on MPWH website within two weeks ofcontract award (after Bank’s no objection): (a)name of each bidder who submitted a bid; (b) bidprices as read out at the bid opening; (c) name andevaluated prices of each bid; (d) name of bidderswhose bids were rejected and the reasons forrejection; and (e) name of the winning bidders andthe prices, as well as the duration and summaryscope of the contract awarded.
ICB Contract Award Notices for packages 01, 02, 03, 04, 05,08, 11, 12, 13, 15, and 17 were published in UNDB on-lineand on the MPWH website (http://www.PU.go.id).
NCB Contract Award Notices for packages 06, 07, 14, 16, 19,20, 21 , 05A , 21A , RR-01 and RR-02 were published on theMPWH website.
8 List of all contracts awarded in the three monthspreceding the date of the request by any person orcompany request are available, including the nameof the contractor/ supplier/ consultant, thecontract amount, the number ofbidders/proposals, the procurement method andthe purpose of the contract.
All this information is available on the WINRIP website.However, no request from any person or company has beenreceived.The physical progress data of the under-construction packageshad been completed including contract changes such asreview design, CCO, technical justification, memorandum,addendum, etc.
9 Final audit reports (financial or otherwise, includingqualified audit reports) and all formal responses ofthe Government in relation to such reports shouldbe publicly available on the MPWH website withinone month after the report is accepted as final.
The Final Audit for the years 2012, 2013, 2014, 2015 , 2016and 2017 have been completed, and the related reportsuploaded on the WINRIP website. Moreover, DGH has sent theaudit results response to the Bank.The Final Audit for 2018 was completed and was send to Bankon December 5 , 2019.
10 Financial, technical, and physical progress of theproject monitored by an IT system (integrated SiPP)as publicly accessible project monitoring system.
These reports are available on the WINRIP website: The financial, technical, and physical progress have been
completed with information of contractors’ names, numberof contract, date of contract, contract volume/amount,duration of contract, etc.
The tutorial guidance has been developed and sent by MISspecialist.
The financial progress report is updated every three monthsas the IFR quarterly report.
The technical and physical progress is updated every monthas the Monthly Progress Report, and every three months asthe Quarterly Progress Report.
Enha
nced
Civ
il So
ciet
y O
vers
ight
11 Representatives of civil society groups invited toattend the public bid openings and other keyprocurement steps. Community RepresentativeObservers (CROs) invited from local universities orother selected independent institutions.Attendance list for the procurement/selectionprocess signed.
The CROs for 19 packages (01, 02, 03, 04, 05, 06, 07, 08, 10,11, 12, 13, 14, 15, 16, 17, 19, 20, 21 have been appointed,and have attended the required meeting (Pre-Bid Meetingand Bid Opening Meeting). Attendances list are available.
The CRO for package 05A has been appointed on April 24,2018, and has been attended the Pre-Bid meeting on April27, 2018.
The Substitute CRO, Mr. Ir. Koster Silaen, MT was attendedthe Pre-Bid Meeting of Re-Bid package No. 05A in SatkerPJN Region II office in Medan, on September 11, 2018.
The CRO for package 21A has been appointed on September27, 2018,
The Substitute CRO (Ir. Drs. Heldi, M.Si, PhD) has beenattended the Pre-Bid meeting on October 18, 2018.
The CRO for ppackage RR-01 , RR-02 and CSC has beenappointed on May 9 , 2019
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
RISKAREA
NoACTIONS STATUS (as of January, 2020)
12 Guidelines on appropriate procedures for theabove provided in the PMM.
The Appropriate procedures are written in PMM Chapter 11.2,and in the TOR of CROs Selection.
13 Third Party Monitoring (TPM) mechanismestablished. This mechanism includes regularsharing of information with the media.
TPM for 19 packages had been selected (packages 01, 02,03, 04, 05, 06, 07, 08, 10, 11, 12, 13, 14, 15, 16, 17, 19, 20,and 21.
TPM Letter of Agreement for the above-mentioned 19packages had been signed.
The Agreement of TPM operational funding between TPMand CTC (PT. Perentjana Djaja) has been signed for theabove-mentioned 18 packages.
Packages 09, 10, 18 were cancelled from the list of WINRIPprogram.
TPM package 05A was appointed on May 2019 but the TPMletter agreement not yet been signed
TPM package 21A was appointed on 21 February 2019 ,TPM letter agreement has been signed and the agreementof TPM operational funding between TPM ang CTC ( PT.Perentjana Djaja0 not yet been signed .
14 Annual Accountability Meetings held. First meetingheld at the province level before procurement ofcontractors or service providers.
The Annual Accountability Meetings were held through thefollowing activities: Coordination meeting at the Regional level (Balai- BBPJN) and
in each province. Public Expose of LARAP to the community around the project
area. Socialization of projects during selection of CROs and TPM at
local universities near project sites and in the same province.(Detail dates of socialization meeting and training of the CROsand TPM can be found in the Monthly or Quarterly Report ofWINRIP on the WINRIP website).
Public expose and dissemination of information to inhabitantsaround the project is delivered through Project InformationBoard.
PMM workshop has been carried out in:o Padang on September 12, 2014 for packages 01, 02, 03,
and 04.o Bengkulu on May 6 – 7, 2015 for packages 06, 11, 13, and
19.o Bogor on November 24 – 25, 2015 for packages 05, 15, and
17.o Padang on August 29 – 30, 2016, for packages 07, 08, 12,
14, 20, and 21.o Bengkulu on April 27, 2017 for package 16.o Palu on November 27 – 29 2019 for package RR-01 and RR-
02
Enha
nced
Com
plai
nts H
andl
ing
Mec
hani
sm
15 Enhanced complaints handling mechanism, whichincludes maintaining project complaint log andfiling to monitor status of follow-up of eachcomplaint, established by the MPWH.
A Complaint Handling System has been established, written inPMM (Chapter 11.4), and published on WINRIP website(http://chs.winrip-ibrd.com).
16 Complaints received acknowledged to thecomplainant by the PIU within seven (7) days ofreceipt with a copy to PMU, DGH and then WorldBank. Bid-related complaints received during bidevaluation period responded after the contractaward. All complaints handling componentincluded in the MPWH website, and updated on amonthly basis.
24 complaints have been followed up to March 2019. Complaints are handled by the Secretariat of CHU under PMU
WINRIP. Dispute resolution of complaints will be handled by different
institutions (PPK, Satker, Inspectorate General, KomisiPenyelesaian Pengaduan), depending on the type ofcomplaints (i.e. general matters, technical matters, or specificmatters).
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
RISKAREA
NoACTIONS STATUS (as of January, 2020)
17 Information concerning the alternative conduits forcomplaints (telephone hotline, dedicated emailaddress and PO Box) widely disseminated.
The information of complaint procedures has beendisseminated to the different institutions related to projectimplementation (PPK, Satker, Contractors, Engineer/Supervision Consultants) during PMM workshops and to theCROs & TPM during introductory training.The PPKs published the complaint procedures through theirProject Information Board.
18 Strict procedures to ensure anonymity ofinformants.
The procedures ensure anonymity of informants.
19 Recording and appropriate referral of all incomingcomplaints undertaken by MPWH with each casegenerating an automatic, standard format report tothe Bank.
It has been established on the WINRIP website(http://chs.winrip-ibrd.com).
Miti
gatin
g Co
llusi
on, F
orge
ry a
nd F
raud
Ris
ks
20 “Semi E-Tendering” on the MPWH official publicwebsite used by MPWH for both, works andconsultant services. Key information (see list)published on the official website (www.pu.go.id):(a) invitation for bids; (b) download of biddingdocuments; (c) bid clarifications; (d) minutes of bidopening; (e) information of contract award.
Semi e-procurement was applied before November 2014 andfull e-procurement was applied afterward.
21 All specifications defined in the bidding documents,and all clarifications sought through writtencorrespondence and replies sent to all bidders.
Done.
22 Key indicators of submitted bids analyzed byMPWH, through CTC. Short technical report foreach group of bidding (the bidding packagessimultaneously invited) prepared and shared withthe Bank.
Short technical reports for each contracted package have beenindividually prepared and shared with the Bank except for thepackages under AWP-1 (packages 01, 02, 03, and 04), where agroup report was prepared.
23 Contracts awarded within original bid validityperiod.
There were nine (9) contracts awarded within the original bidvalidity period (packages 04, 06, 11, 13, 17, 19 , 05A , 21A andRR-02).
Thirteen (13) contracts were awarded after the original bidvalidity period (packages 01, 02, 03, 05, 07, 08, 12, 14, 15, 16,20, 21 and RR-01 ).
24 Guidelines for preparation ofspecifications/selection criteria in the biddingdocuments and request for proposals prepared toensure compliance with the Bank Guidelines.
Done.
25 FIDIC arrangements used by MPWH with theindependent supervision consultant havingresponsibility as the “Engineer” in the workscontracts.
Done.
26 Criteria for nominating procurement committeesestablished by MPWH. Each ProjectImplementation Unit includes a specifiedprocurement officer and financial managementofficer.
Done.
27 Procedures to maintain proper project andprocurement filing established by MPWH, includingfiling of advertisements, biddingdocuments/request for proposals,clarifications/addenda to biddingdocument/request for proposals, minutes of bidopening, evaluation reports, contract award andfinal contract documents, and also for regularreview of accounting reports, including all
Done.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
RISKAREA
NoACTIONS STATUS (as of January, 2020)
supporting documents (i.e. travel report, receipts,etc.).
28 Regular interim audits conducted by third parties,which include review of procurement process andresults.
Done.
Sanc
tions
and
Rem
edie
s
29 Remedial actions and sanctions for cases of fraudand corruption that are reported and for whichevidence is found established by MPWH.
No cases of fraud and corruption have been encountered sofar. However, in one bidding process a bidder was rejectedbecause the bidding commission considered that some of thesubmitted information was not genuine.
30 Information regarding fraud, corruption, collusionand/or coercive practice cases (resulting in thetermination of the contract and possibly otherpenalties), where lessons are learned and funds areretrieved, widely disseminated.
It will be done if there are such cases.
31 Disbursement to any given contract/locationsuspended or stopped completely if cases ofcorruption not dealt with effectively.
It will be done if there are such cases.
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Appendix I
Performance Indicator
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Appendix IProject Development Objective Indicators
IndicatorName Core Unit of
MeasureBaseline(2010)
FY1 (2013)target
FY1 (2013)actual
FY2(2014)target
FY2 (2014)actual
FY3(2015)target
FY3 (2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)actual
FY6(2018)
end target
FY6(2018)actual
FY6(2019)actual
Increase ofAADT onproject roadsections (allvehicletypes)
Number Value 7,505 10,880 11,936 4,140 13,094 12,696 13,990 13,613 14,947 14,214 14,544 n.a. n.a.
Date 31-Dec-10 31-Dec-14 Mar-15 31-Dec-16 31-Dec-17 31-Dec-17 31-Dec-18 31-Oct-18 12-Dec-19
Comments 2010 baselineis the simpleaverage ofthe AADT ofthe 18WINRIPsections(page 41 ofPAD)
Resultsfrom IRMS
Resultsfrom statictrafficcounts on 6links in 4provinces
Results fromIRMS (from17 packages)
2017 targetcalculated usingthe growthforecasts forfour vehicletypes on page 39of the PAD,weighing themby the typicaltrafficcompositionfrom the 2010Master Plan forArterial RoadNetwork inSumatra Island
The PMU iscurrentlyfinetuningits trafficdatacollectionsystem andthe FY2017traffic datais not yetavailable.The figureabove iscalculatedby priordata inter-polation
The baselineand thetarget valuehave beenrecalculatedto reflect thereduction inthe numberof packagesfrom 19 to 18envisaged atthe SecondProjectRestructuring
The AADTfigures willonly beavailable at theend of theproject
AADT 2019Lampung &NorthSumateraProvince notavailable yet
IndicatorName
CoreUnit of
MeasureBaseline(2010)
FY1 (2013)target
FY1 (2013)actual
FY2(2014)target
FY2 (2014)actual
FY3(2015)target
FY3 (2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)actual
FY6(2018)
end target
FY6(2018)actual
FY6(2019)actual
Averagevehicleoperatingcost (VOC)for a typicalcar reducedby at least5% onproject road
Percentage Value 0.00 n.a. 3.00 n.a. n.a. 5.00 n.a. 5.00 n.a. n.a.
Date 31-Dec-10 31-Dec-14 10-Nov-15 9-Aug-16 31-Dec-17 31-Aug-17 31-Dec-18 31-Oct-18 12-Dec-19
Comments Base yearoperatingcost:US$0.19/veh-km
Target notassessedbecause noworkscompleted
Target notassessedbecause noworkscompleted
The VehicleOperatingCosts will beassessed atthe end ofthe project
The VehicleOperatingCosts will beassessed atthe end ofthe project
The VehicleOperatingCosts will beassessed at theend of theproject
AADT 2019Lampung &NorthSumateraProvince notavailable yet
Indicator Core Unit of Baseline FY1 (2013) FY1 (2013) FY2 FY2 (2014) FY3 FY3 (2015) FY4 FY4 (2016) FY5 (2017) FY5 (2017) FY6 FY6 FY6
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Name Measure (2010) target actual (2014)target
actual (2015)target
actual (2016)target
actual end target actual (2018)end target
(2018)actual
(2019)actual
Average VOCfor a typicalbus reducedby at least8% onproject roads
Percentage Value 0.00 n.a. 5.00 n.a. n.a. 8.00 n.a. 8.00 n.a n.a.
Date 31-Dec-10 31-Dec-14 10-Nov-15 9-Aug-16 31-Dec-17 31-Aug-17 31-Dec-18 31-Oct-18 12-Dec-19
Comments Base yearoperatingcost:US$0.35/veh-km
Target notassessedbecause noworkscompleted
Target notassessedbecause noworkscompleted
The vehicleoperatingcosts will beassessed atthe end ofthe project
Thisindicatorwill bemeasuredat the endproject
The VehicleOperatingCosts will beassessed at theend of theproject
AADT 2019Lampung &NorthSumateraProvince notavailable yet
IndicatorName
CoreUnit of
MeasureBaseline(2010)
FY1 (2013)target
FY1 (2013)actual
FY2(2014)target
FY2 (2014)actual
FY3(2015)target
FY3 (2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)actual
FY6(2018)
end target
FY6(2018)actual
FY6(2019)actual
Average VOCfor a typicalheavy truckreduced by10% onproject roads
Percentage Value 0.00 n.a. 7.00 n.a. n.a. 10.00 n.a. 10.00 n.a. n.a.
Date 31-Dec-10 31-Dec-14 10-Nov-15 9-Aug-16 31-Dec-17 31-Aug-17 31-Dec-18 31-Oct-18 12-Dec-19
Comments Base yearoperatingcost: US$0.65veh-km
Target notassessedbecause noworkscompleted
Target notassessedbecause noworkscompleted
The vehicleoperatingcosts will beassessed atthe end ofthe project
Thisindicatorwill bemeasuredat the endproject
The VehicleOperatingCosts will beassessed at theend of theproject
AADT 2019Lampung &NorthSumateraProvince notavailable yet
IndicatorName
CoreUnit of
MeasureBaseline(2010)
FY1 (2013)target
FY1 (2013)actual
FY2(2014)target
FY2 (2014)actual
FY3(2015)target
FY3 (2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)actual
FY6(2018)
end target
FY6(2018)actual
FY6(2019)actual
Averagepassengertravel timefor lightvehiclesreduced byat least 20%on projectroads
Percentage Value 0.00 0.00 -15.29 5.00 3.7 18.20 20.00 19.61 20.00 20.9 21.11
Date 31-Dec-10 31-Dec-13 31-Dec-14 10-Nov-15 31-Jan-17 31-Dec-17 31-Aug-17 31-Dec-18 31-Oct-18 12-Dec-19
Comments Base yearspeed: 51km/h
For 4ongoingworks only
For 9ongoingworks only
Results fromsite survey(from 17packages)
For 18ongoing andcompletedworks
For 18 ongoingand completedworks
IndicatorName
CoreUnit of
MeasureBaseline(2010)
FY1 (2013)target
FY1 (2013)actual
FY2(2014)target
FY2 (2014)actual
FY3(2015)target
FY3 (2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)actual
FY6(2018)
end target
FY6(2018)actual
FY6(2019)actual
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Averagepassengertravel timefor largebusesreduced byat least 20%on projectroads
Percentage Value 0.00 0.00 -19.57 5.00 -2.17 13.81 20.00 15.22 20.00 20.6 20.72
Date 31-Dec-10 31-Dec-13 31-Dec-14 10-Nov-15 31-Jan-17 31-Dec-17 31-Aug-17 31-Dec-18 31-Oct-18 12-Dec-19
Comments Base yearspeed: 46km/h
No available For 4ongoingworks only
For 9ongoingworks only
Results fromsite survey(from 17packages)
For 18ongoing andcompletedworks
For 18 ongoingand completedworks
IndicatorName
CoreUnit of
MeasureBaseline(2010)
FY1 (2013)target
FY1 (2013)actual
FY2(2014)target
FY2 (2014)actual
FY3(2015)target
FY3 (2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)actual
FY6(2018)
end target
FY6(2018)actual
FY6(2019)actual
Averagepassengertravel timefor heavytrucksreduced byat least 20%on projectroads
Percentage Value 0.00 0.00 -17.50 5.00 -6.53 11.76 20.00 12.50 20.00 19.60 20.00
Date 31-Dec-10 31-Dec-13 31-Dec-14 10-Nov-15 31-Jan-17 31-Dec-17 31-Aug-17 31-Dec-18 31-Oct-18 12-Dec-19
Comments Base yearspeed: 40km/h
For 4ongoingworks only
For 9ongoingworks only
Results fromsite survey(from 17packages)
For 18ongoing andcompletedworks
For 18 ongoingand completedworks
Intermediate Results Indicators
IndicatorName
CoreUnit of
MeasureBaseline(2010)
FY1 (2013)target
FY1 (2013)actual
FY2(2014)target
FY2 (2014)actual
FY3(2015)target
FY3 (2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)actual
FY6(2018)
end target
FY6(2018)actual
FY6(2019)actual
Satisfactorycompletionof slopeprotectiondesigns
Number
Value 0.00 0.00 0 3.00 n.a. 3.00 3.00 5.00
Date 15-Dec-15 15-Dec-15 31-Jan-17 31-Dec-17 31-Aug-17 12-Jun-18 31-Oct-18 12-Dec-19
Comments Study incontractingphase
IndicatorName
CoreUnit of
MeasureBaseline(2010)
FY1 (2013)target
FY1 (2013)actual
FY2(2014)
FY2 (2014)actual
FY3(2015)
FY3 (2015)actual
FY4(2016)
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)actual
FY6(2018)
end target
FY6(2018)actual
FY6(2019)actual
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
target target target
Number ofkm ofimprovednationalroads in theprojectregion asplanned/Roadsrehabilitated,Rural
Kilometers
Value 0.00 0.00 0.00 5.00 5.38 80.00 134.54 380.00 322.00 640.00 414.00 578.00 570.00 578.00
Date 31-Dec-10 31-Dec-13 Dec-14 10-Nov-15 31-Jan-17 31-Dec-17 31-Aug-17 31-Dec-18 31-Oct-18 12-Dec-19
Comments Rev.Target
Rev.Target
Rev.Target
Rev. Target This targethas beenrecalculatedto reflect thereduction inthe numberof packagesfrom 19 to 18envisaged atthe SecondProjectRestructuring
IndicatorName
CoreUnit of
MeasureBaseline(2010)
FY1 (2013)target
FY1 (2013)actual
FY2(2014)target
FY2 (2014)actual
FY3(2015)target
FY3 (2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)actual
FY6(2018)
end target
FY6(2018)actual
FY6(2019)actual
Number ofmeters ofimprovedbridges
Meters
Value 0.00 0.00 0.00 0.00 0.00 48.00 0.00 96.00 100.00 160.00 100.00 160.00 160.00 160.00
Date 31-Dec-10 31-Dec-13 10-Nov-15 31-Jan-17 31-Dec-17 31-Aug-17 31-Dec-18 31-Oct-18 12-Dec-19
Comments Rehabilitated,rural
Rev.Target
Rev.Target
Rev.Target
Rev. Target
IndicatorName
CoreUnit of
MeasureBaseline(2010)
FY1 (2013)target
FY1 (2013)actual
FY2(2014)target
FY2 (2014)actual
FY3(2015)target
FY3 (2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)actual
FY6(2018)
end target
FY6(2018)actual
FY6(2019)actual
Satisfactorycompletionof technicalaudits for allroad projectsofcomponent 1
Percentage
Value 0.00 0.00 0.00 0.00 0.00 20.00 16.00 60.00 66.67 100.00 100.00 100.00 100.00 100.00
Date 31-Dec-10 31-Dec-13 31-Jan-17 31-Dec-17 31-Aug-17 31-Dec-18 31-Oct-18 12-Dec-19
Comments Rev.Target
0 out of 19 Rev.Target
3 out of 19 Rev.Target
12 out of 19TFAC visit
TFAC firstfield visitreportcompletedfor the 18packages
18 out of 18TFACinspection (atleast firstinspection)
IndicatorName
CoreUnit of
MeasureBaseline(2010)
FY1 (2013)target
FY1 (2013)actual
FY2(2014)target
FY2 (2014)actual
FY3(2015)target
FY3 (2015)actual
FY4(2016)target
FY4 (2016)actual
FY5 (2017)end target
FY5 (2017)actual
FY6(2018)
end target
FY6(2018)actual
FY6(2019)actual
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Satisfactorycompletionof roadsafety auditscarried outby CTC orTLKJ for allroad projectsofcomponent 1
Percentage
Value 0.00 0.00 0.00 40.00 80.00 90.00 100 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Date 31-Dec-10 31-Dec-13 Dec-14 31-Jan-17 31-Dec-17 31-Aug-17 31-Dec-18 31-Oct-18 12-Dec-19
Comments 16 out of 19 Rev.Target
19 out of 19 Rev.Target
18 out of 18for DetailEng. Design
Road safetyauditscarried outfor the 18packages
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Appendix J
Correspondence
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Appendix J Correspondence
Correspondence
Date From To Activity
January 02, 2020 PT. Perentjana Djaja
Kasatker PembinaanAdministrasi danPelaksanaanPengendalian PHLN
Remobilization personnel fpr CTCof WINRIP (Traffic Engineer)
January 02, 2020 PPK Palu BANK DUNIASurat Peringatan KeterlambatanMobilisasi Personil KonsultanSupervisi (CSC)
January 07, 2020 BALAI Palu PreservasiSurat Laporan Sosialisasi danPemilihan Wakil Pemantau dariPihak KetigaTPM Paket WINRIPRR01 dan RR02 di Prov. Sulteng
January 07, 2020 DPJJ BANK DUNIAProposed Replacement ofEnvironmental Specialist of CoreTeam Consultant (CTC)
January 13, 2020
KasatkerPembinaanAdministrasi danPelaksanaanPengendalian PHLN
CTC WINRIPUndangan Penyusunan LaporanKeuangan Pinjaman Luar Negeri TA2019
January 13, 2020 SSE CTC WINRIP Laporan Monitoring Package 05A.10 Januari 2020
January 13, 2020 SSE CTC WINRIP Laporan Monitoring Package 05A.11 Januari 2020
January 13, 2020 Ishak CTC WINRIP Surat Sakit Ishak
January 13, 2020 Gunawan CTC WINRIP Surat Sakit Gunawan
January 13, 2020 DPJJ BANK DUNIASubmission of Revision Assessmentand Action Plan LARAP Documentfor Package RR02
January 13, 2020 BANK DUNIA DPJJResponse to GOI disposisi. Re.Reports of the Estimated Cost tothe Fulfillment of Road SafetyAspect at WINRIP Road
January 14, 2020 SSE CTC WINRIP Laporan Monitoring Package 05A.13 Januari 2020
January 14, 2020 PPK Palu Satker PJN I, SatkerPJN II,
Mobilisasi Personil KonsultanSupervisi CSC
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
January 15, 2020 SSE CTC WINRIPLaporan Monitoring Package 05A.14 Januari 2020
January 15, 2020 SSE CTC WINRIPLaporan Monitoring Package 05A.15 Januari 2020
January 15, 2020 BANK DUNIA DPJJResponse to GOI Re. ProposedReplacement of EnvironmentalSpecialist of CTC
January 16, 2020 Gunawan CTC WINRIP Surat Sakit Gunawan
January 16, 2020 Direktur PengelolaKas Negara CTC WINRIP
Undangan Rekonsiliasi Pinjamandan Hibah Periode Triwulan IV T.A.2019
January 16, 2020 DPJJ PreservasiPenyampaian Laporan TindakLanjut TFAC Package 17Pg.Tampak-Sp.Gunung Kemala diProvinsi Lampung
January 16, 2020 SSE CTC WINRIPLaporan Monitoring Package 05A.16 Januari 2020
January 16, 2020 BBPJN III PreservasiPenjelasaan (kronologis) TerhadapPenyelesaian Pekerjaan Package05A Penanganan Lereng Ruas JalanRampa - Poriaha
January 17, 2020 SSE CTC WINRIPLaporan Monitoring Package 05A.17 Januari 2020
January 17, 2020 BPJN III DPJJPenyampaian Laporan TindakLanjut Temuan Audit TFAC Paket 19Bintuan-Lais Bengkulu
January 17, 2020 DPJJ BANK DUNIA
Submission of Follow up ReportsTFAC Findings Package No. 17Pugung Tampak - Sp. GunungKemala
January 20, 2020 SSE CTC WINRIPLaporan Monitoring Package 05A.18 Januari 2020
January 20, 2020Kepala BiroKeuangan
CTC WINRIPUndangan Konsolidasi PenyusunanLaporan keuangan Pinjaman LN TA2019 Bersumber dari WB dan ADB
January 20, 2020 SSE CTC WINRIPLaporan Monitoring Package 05A.20 Januari 2020
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
January 20, 2020 PT. Perentjana Djaja
Kasatker PembinaanAdministrasi danPelaksanaanPengendalian PHLN
Mobilization enviromentalspecialist personnel for CTC
January 21, 2020 BPJN III PreservasiPenyampaian Laporan TindakLanjut TFAC PAKET 20 Lubuk Alung– Kuraitaji di Provinsi Bengkulu
January 21, 2020 SSE CTC WINRIPLaporan Monitoring Package 05A.21 Januari 2020
January 21, 2020Kepala SubditLingkungan danKeselamatan Jalan
CTC WINRIPUndangan Pemaparan Hasil DesainPada Ruas-Ruas Usulan Road SafetyImprovement Program
January 21, 2020Inspektur IIIInspektorat JendralKementrian PUPR
CTC WINRIP
Undangan Penjelasan GuidelinesProcurement Under IBDR Loan danDokumen Pengadaan PaketPekerjaan WINRIP
January 22, 2020
KasatkerPembinaanAdministrasi danPelaksanaanPengendalian PHLN
CTC WINRIPLeave for Absence To Renew WorkVisa For Team Leader CTC WINTIP
January 22, 2020 SSE CTC WINRIPLaporan Monitoring Package 05A.22 Januari 2020
January 23, 2020 SSE CTC WINRIPLaporan Monitoring Package 05A.23 Januari 2020
January 24, 2020 BANK DUNIA DPJJ
Response to GOI Re. Submission ofRevised Assessment and ActionPlan LARAP Document for PackageRR02 in Central Sulawesi
January 27, 2020 SSE CTC WINRIPLaporan Monitoring Package 05A.24 Januari 2020
January 27, 2020 SSE CTC WINRIPLaporan Monitoring Package 05A.27 Januari 2020
January 29, 2020 SSE CTC WINRIPLaporan Monitoring Package 05A.28 Januari 2020
January 29, 2020 Preservasi DPJJPenyampaian Laporan SosialisasiThird Party Monitoring TPM RR01dan RR02 Prov.Sulteng
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
January 29, 2020 Preservasi BALAI XIV PaluPenyampaian Kontrak Paket RR01,RR02 dan CSC Palu di Prov. Sulteng
January 30, 2020 SSE CTC WINRIPLaporan Monitoring Package 05A.29 Januari 2020
January 30, 2020 Lut CTC WINRIP Surat Sakit Lut
January 30, 2020 SSE CTC WINRIPLaporan Monitoring Package 05A.30 Januari 2020
January 31, 2020 SSE CTC WINRIPLaporan Monitoring Package 05A.31 Januari 2020
ReportDate From To Activity
January 07,2020
BALAI Palu PreservasiSurat Laporan Sosialisasi danPemilihan Wakil Pemantau dariPihak KetigaTPM Paket WINRIPRR01 dan RR02 di Prov. Sulteng
January 13,2020
SSE CTC WINRIP Laporan Monitoring Package 05A.10 Januari 2020
January 13,2020
SSE CTC WINRIP Laporan Monitoring Package 05A.11 Januari 2020
January 13,2020
DPJJ BANK DUNIASubmission of Revision Assessmentand Action Plan LARAP Documentfor Package RR02
January 14,2020
SSE CTC WINRIP Laporan Monitoring Package 05A.13 Januari 2020
January 15,2020
SSE CTC WINRIPLaporan Monitoring Package 05A.14 Januari 2020
January 15,2020
SSE CTC WINRIPLaporan Monitoring Package 05A.15 Januari 2020
January 16,2020
DPJJ PreservasiPenyampaian Laporan TindakLanjut TFAC Package 17Pg.Tampak-Sp.Gunung Kemala diProvinsi Lampung
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
January 16,2020
SSE CTC WINRIPLaporan Monitoring Package 05A.16 Januari 2020
January 17,2020
SSE CTC WINRIPLaporan Monitoring Package 05A.17 Januari 2020
January 17,2020
BPJN III DPJJPenyampaian Laporan TindakLanjut Temuan Audit TFAC Paket 19Bintuan-Lais Bengkulu
January 17,2020
DPJJ BANK DUNIA
Submission of Follow up ReportsTFAC Findings Package No. 17Pugung Tampak - Sp. GunungKemala
January 20,2020
SSE CTC WINRIPLaporan Monitoring Package 05A.18 Januari 2020
January 20,2020
SSE CTC WINRIPLaporan Monitoring Package 05A.20 Januari 2020
January 21,2020
BPJN III PreservasiPenyampaian Laporan TindakLanjut TFAC PAKET 20 Lubuk Alung– Kuraitaji di Provinsi Bengkulu
January 21,2020
SSE CTC WINRIPLaporan Monitoring Package 05A.21 Januari 2020
January 22,2020
SSE CTC WINRIPLaporan Monitoring Package 05A.22 Januari 2020
January 23,2020
SSE CTC WINRIPLaporan Monitoring Package 05A.23 Januari 2020
January 24,2020
BANK DUNIA DPJJ
Response to GOI Re. Submission ofRevised Assessment and ActionPlan LARAP Document for PackageRR02 in Central Sulawesi
January 27,2020
SSE CTC WINRIPLaporan Monitoring Package 05A.24 Januari 2020
January 27,2020
SSE CTC WINRIPLaporan Monitoring Package 05A.27 Januari 2020
January 29,2020
SSE CTC WINRIPLaporan Monitoring Package 05A.28 Januari 2020
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
January 29,2020
Preservasi DPJJPenyampaian Laporan SosialisasiThird Party Monitoring TPM RR01dan RR02 Prov.Sulteng
January 30,2020
SSE CTC WINRIPLaporan Monitoring Package 05A.29 Januari 2020
January 30,2020
SSE CTC WINRIPLaporan Monitoring Package 05A.30 Januari 2020
January 31,2020
SSE CTC WINRIPLaporan Monitoring Package 05A.31 Januari 2020
MeetingDate From To Activity
January 13, 2020
KasatkerPembinaanAdministrasi danPelaksanaanPengendalian PHLN
CTC WINRIPUndangan Penyusunan LaporanKeuangan Pinjaman Luar Negeri TA2019
January 16, 2020 Direktur PengelolaKas Negara CTC WINRIP
Undangan Rekonsiliasi Pinjamandan Hibah Periode Triwulan IV T.A.2019
January 20, 2020Kepala BiroKeuangan
CTC WINRIPUndangan Konsolidasi PenyusunanLaporan keuangan Pinjaman LN TA2019 Bersumber dari WB dan ADB
January 21, 2020Kepala SubditLingkungan danKeselamatan Jalan
CTC WINRIPUndangan Pemaparan Hasil DesainPada Ruas-Ruas Usulan Road SafetyImprovement Program
January 21, 2020Inspektur IIIInspektorat JendralKementrian PUPR
CTC WINRIP
Undangan Penjelasan GuidelinesProcurement Under IBDR Loan danDokumen Pengadaan PaketPekerjaan WINRIP
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Outgoing Letter
Correspondence
Date From To Activity
January 07, 2020 CTC WINRIP Officer in Charge PMUWINRIP
Proposal of Extension of CTC -Geotechnical Engineer Assignment
January 08, 2020 CTC WINRIP Officer in Charge PMUWINRIP
Estimate Remaining Loan ofWINRIP status as of the end ofDecember 2019
January 08, 2020 CTC WINRIP Officer in Charge PMUWINRIP
Submission of BAPPENAS TW. IV2019 - Progres Pelaksanaan AndLaporan Pelaksanaan KegiatanPinjaman Hibah Luar Negeri;Winrip
January 08, 2020 CTC WINRIP Kasatker PembinaanAdministrasi danPelaksanaanPengendalian PHLN
Leave of Absence to Renew WorkVisa 2020
January 09, 2020 CTC WINRIP Officer in Charge PMUWINRIP
Explanation of Updating ofAssessment and Action PlanLARAP Document for Paket RR-02in the Central Sulawesi
January 27, 2020 CTC WINRIP Kasatker PembinaanAdministrasi danPelaksanaanPengendalian PHLN
Home Leave Team Leader CTC(Februari 2020)
January 29, 2020 CTC WINRIP Officer in Charge PIUWINRIP, Officer inCharge PMU WINRIP
Recommendable preference ofexecution plan of Package No. RR-02, Central Sulawesi Province
January 30, 2020 CTC WINRIP Officer in Charge PIUWINRIP, Officer inCharge PMU WINRIP
Transmission of Quality InspectionReport for package No. 12:Kambang Indrapura and packageNo. 14 Painan – Kambang
January 30, 2020 CTC WINRIP Director of RoadPreservation, DGH
Submission of Grievance RedressMechanism (GRM) Document ofPalu Disaster Recovery Works
January 30, 2020 CTC WINRIP Officer in Charge PIUWINRIP, Officer inCharge PMU WINRIP
Submission of Draft Addendum No.7 of Contract Agreement of Designand Supervision Consultant (DSC)
January 31, 2020 CTC WINRIP Kasatker PembinaanAdministrasi danPelaksanaanPengendalian PHLN
Revised Home Leave Team Leader
Monthly Progress Report January 2020
Western Indonesia National Roads Improvement Project
Report
Date From To Activity
January 30, 2020 CTC WINRIP Officer in Charge PIUWINRIP, Officer inCharge PMUWINRIP
Transmission of QualityInspection Report for packageNo. 12: Kambang Indrapura andpackage No. 14 Painan –Kambang
Meeting
Date From To Activity