tugas akhir perancangan ulang tata letak ...repository.untag-sby.ac.id/4201/1/abstrak.pdfperencanaan...

17
TUGAS AKHIR PERANCANGAN ULANG TATA LETAK FASILITAS PRODUKSI UNTUK MEMINIMALKAN ONGKOS MATERIAL HANDLING (Studi Kasus UD. Karya Bersaudara Di Kec.Menganti) Oleh : Muhammad Akhsanul Anam 1411600083 PROGRAM STUDI TEKNIK INDUSTRI FAKULTAS TEKNIK UNIVERSITAS 17 AGUSTUS 1945 SURABAYA 2020

Upload: others

Post on 18-Jan-2021

34 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TUGAS AKHIR PERANCANGAN ULANG TATA LETAK ...repository.untag-sby.ac.id/4201/1/ABSTRAK.pdfperencanaan tata letak pabrik serta pada proses pemindahan bahan dalam suatu proses produksi

TUGAS AKHIR

PERANCANGAN ULANG TATA LETAK FASILITAS PRODUKSI

UNTUK MEMINIMALKAN ONGKOS MATERIAL HANDLING

(Studi Kasus UD. Karya Bersaudara Di Kec.Menganti)

Oleh :

Muhammad Akhsanul Anam

1411600083

PROGRAM STUDI TEKNIK INDUSTRI

FAKULTAS TEKNIK

UNIVERSITAS 17 AGUSTUS 1945 SURABAYA

2020

Page 2: TUGAS AKHIR PERANCANGAN ULANG TATA LETAK ...repository.untag-sby.ac.id/4201/1/ABSTRAK.pdfperencanaan tata letak pabrik serta pada proses pemindahan bahan dalam suatu proses produksi

ii

TUGAS AKHIR

PERANCANGAN ULANG TATA LETAK FASILITAS PRODUKSI

UNTUK MEMINIMALKAN ONGKOS MATERIAL HANDLING

(Studi Kasus UD. Karya Bersaudara Di Kec.Menganti)

Untuk Memperoleh Gelar Sarjana Strata Satu (S1)

Pada Program Studi Teknik Industri

Fakultas Teknik

Universitas 17 Agustus 1945 Surabaya

Oleh :

Muhammad Akhsanul Anam

1411600083

PROGRAM STUDI TEKNIK INDUSTRI

FAKULTAS TEKNIK

UNIVERSITAS 17 AGUSTUS 1945 SURABAYA

2020

Page 3: TUGAS AKHIR PERANCANGAN ULANG TATA LETAK ...repository.untag-sby.ac.id/4201/1/ABSTRAK.pdfperencanaan tata letak pabrik serta pada proses pemindahan bahan dalam suatu proses produksi
Page 4: TUGAS AKHIR PERANCANGAN ULANG TATA LETAK ...repository.untag-sby.ac.id/4201/1/ABSTRAK.pdfperencanaan tata letak pabrik serta pada proses pemindahan bahan dalam suatu proses produksi

iv

PROGRAM STUDI TEKNIK INDUSTRI

FAKULTAS TEKNIK

UNIVERSITAS 17 AGUSTUS 1945 SURABAYA

LEMBAR PENETAPAN PANITIA PENGUJI

Nama : Muhammad Akhsanul Anam

NBI : 1411600083

Prodi : Teknik Industri

Judul TA : Perancangan Ulang Tata Letak Fasilitas Produksi Untuk

Meminimalkan Ongkos Material Handling (Studi Kasus

UD.Karya Bersaudara Di Kec.Menganti)

Tugas Akhir Ini Telah Diuji Pada : Tanggal, 03 juni 2020

Panitia penguji tugas akhir berdasarkan surat keputusan Dekan Fakultas Teknik

Universitas 17 Agustus 1945 Surabaya

Ketua Ir. Asmungi, MT NPP : 20410.96.0442

Anggota 1. Dr.Ir.Zainal Arief, MT NPP : 20410.86.0072

2. Istantyo Yuwono, ST.,MT Npp : 20410.94.0381

Page 5: TUGAS AKHIR PERANCANGAN ULANG TATA LETAK ...repository.untag-sby.ac.id/4201/1/ABSTRAK.pdfperencanaan tata letak pabrik serta pada proses pemindahan bahan dalam suatu proses produksi
Page 6: TUGAS AKHIR PERANCANGAN ULANG TATA LETAK ...repository.untag-sby.ac.id/4201/1/ABSTRAK.pdfperencanaan tata letak pabrik serta pada proses pemindahan bahan dalam suatu proses produksi
Page 7: TUGAS AKHIR PERANCANGAN ULANG TATA LETAK ...repository.untag-sby.ac.id/4201/1/ABSTRAK.pdfperencanaan tata letak pabrik serta pada proses pemindahan bahan dalam suatu proses produksi

vii

KATA PENGANTAR

Puji dan syukur penulis panjatkan kehadirat ALLAH SWT, atas segala

berkat dan rahmat-Nya sehingga penulis bisa menyelesaikan penulisan skripsi ini

yang berjudul “PERANCANGAN ULANG TATA LETAK FASILITAS

PRODUKSI UNTUK MEMINIMALKAN ONGKOS MATERIAL HANDLING

(STUDI KASUS UD.KARYA BERSAUDARA DI KEC.MENGANTI)”.

Penulisan skripsi ini dilakukan sebagai salah satu syarat kelulusan dalam

mencapai gelar Sarjana Teknik jurusan Teknik Industri pada Universitas 17

Agustus 1945 Surabaya. Penyelesaian skripsi ini tidak lepas dari bantuan yang

diterima penulis baik secara langsung maupun tidak langsung. Pada kesempatan

kali ini penulis ingin mengucapkan terimakasih yang sebesar-besarnya kepada :

1. Allah SWT yang telah memberikan kelancaran serta kesehatan sehingga

dapat menyelesaikan dalam penulisan tugas akhir ini tepat waktu.

2. Kedua orang tua tercinta, yang selalu memberikan motivasi, dukungan moral

maupun material dan yang selalu berdoa kepada saya selaku anaknya agar

diberikan kemudahan dalam penulisan tugas akhir.

3. Bapak Ir. Asmungi, MT selaku dosen pembimbing yang selalu memberikan

arahan dan ilmu serta membimbing dengan sabar dan ikhlas untuk penulisan

Tugas Akhir ini dari awal hingga akhir.

4. Bapak Hery Murnawan, S.T., M.T. selaku Kaprodi Teknik Industri

Universitas 17 Agustus 1945 Surabaya.

5. Bapak Dr. Ir. H. Sajiyo, M. kes selaku dekan di fakultas teknik Universitas

17 Agustus 1945 Surabaya.

6. Untuk semua bapak dan ibu dosen jurusan teknik industri yang selama ini

memberikan motivasi serta ilmunya selama proses perkuliahan.

7. Bapak fredi ismail selaku pemilik perusahaan UD.Karya Bersaudara yang

telah memberikan izin kepada penulis untuk melakukan kegiatan penelitian

tugas akhir ini.

8. Seluruh teman-teman se-angkatan 2016 terutama paido boys yang terdiri dari

habib, jatra, dwiki, dewangga, deni, donny, bryan, aditya yang selalu

memberi semangat selama penulisan tugas akhir ini serta terima kasih telah

menjadi teman yang baik dari awal semester hingga akhir semester yang

selalu kompak maupun dalam keadaan susah atau senang, tanpa kalian semua

mungkin perkuliahan ini hanya sebatas pelajaran kuliah saja.

9. Kepada teman-teman kontrakan cemara yang telah memberikan semangat

serta dukungan dalam penulisan tugas akhir. Serta terima kasih telah menjadi

Page 8: TUGAS AKHIR PERANCANGAN ULANG TATA LETAK ...repository.untag-sby.ac.id/4201/1/ABSTRAK.pdfperencanaan tata letak pabrik serta pada proses pemindahan bahan dalam suatu proses produksi

viii

teman yang baik dalam keadaan susah maupun senang semoga pertemanan

ini tetap berlanjut serta saling silahturahmi dan semoga kedepannya bisa

sukses bersama-sama.

10. Dan semua pihak yang yang ikut serta dalam membantu penulisan tugas akhir

ini yang tidak bisa penulis sebutkan satu persatu.

Semoga dengan dibuatnya tugas akhir ini dapat memberikan manfaat bagi

perusahaan ataupun bagi semua pihak yang membutuhkan. Saya mengucapkan

terima kasih dan mohon maaf yang sebesar-besarnya bilamana terdapat kesalahan

maupun kekurangan dalam penulisan ini. Akhir kata saya mengucapkan terima

kasih dan semoga tugas akhir ini bermanfaat bagi kita semua.

Surabaya, 03 Juni 2020

Penulis

Muhammad Akhsanul Anam

Page 9: TUGAS AKHIR PERANCANGAN ULANG TATA LETAK ...repository.untag-sby.ac.id/4201/1/ABSTRAK.pdfperencanaan tata letak pabrik serta pada proses pemindahan bahan dalam suatu proses produksi

ix

ABSTRAK

UD.Karya Bersaudara merupakan perusahaan yang bergerak dalam

bidang manufaktur yang berdiri pada tahun 2000, yang memproduksi berbagai

jenis produk rumah tangga seperti baskom dan wakul yang terbuat dari bahan baku

biji plastik.

Permasalahan yang dihadapi oleh UD.Karya Bersaudara saat ini adalah

dalam tata letak fasilitas produksi kurang diperhatikan, sehingga mengakibatkan

jarak pemindahan bahan menjadi sangat panjang dan bagaimana cara

memperpendek jarak pemindahan bahan tersebut.

Adapun tujuan dari penelitian ini adalah untuk memberikan usulan

perbaikan pada tata letak fasilitas produksi sehingga dapat memperpendek jarak

pemindahan bahan, dapat mengurangi ongkos material handling (OMH).

Metode yang digunakan dalam perancangan tata letak fasilitas produksi

adalah Activity Realtionship Chart (ARC) yang berfungsi untuk merencanakan

dan analisis dalam hubungan kedekatan antar masing-masing departemen.

Diharapkan bisa memperlancar proses produksi serta memperpendek jarak

material handling. Serta menggunakan From To Chart yang berfungsi untuk

perencanaan tata letak pabrik serta pada proses pemindahan bahan dalam suatu

proses produksi.

Hasil yang diperoleh dalam penelitian ini adalah memperpendek jarak

perpindahan material dari 102 m menjadi 59,4 m serta menurunkan ongkos

material handling dari Rp.8.327.071 menjadi Rp.3.518.516.

Kata Kunci : Tata Letak Fasilitas, Activity Realtionship Chart (ARC), From To

Chart, Ongkos Material Handling.

Page 10: TUGAS AKHIR PERANCANGAN ULANG TATA LETAK ...repository.untag-sby.ac.id/4201/1/ABSTRAK.pdfperencanaan tata letak pabrik serta pada proses pemindahan bahan dalam suatu proses produksi

x

ABSTRACT

UD. Karya Bersaudara is a company enggaged in manufacturing which

was founded in 2000, which manufactures various types of household products

such as baskom and wakul made from plastic raw materials.

The problem faced by UD. Karya Bersaudara currently is that in the

layout of the production facilities they are not given enough attention, so that the

material transfer distance becomes very long and how to shorten the material

transfer distance.

As for the purpose of this research is to propose improvement to the layout

of production facilities so that it can shorten the distance of material transfer, can

reduce the cost of material handling.

The method used in the design of the layout of production facilities is the

Activity Realtionship Chart (ARC) which functions to plan and analyze the

closeness between each department. Is expected to expedite the production

process and shorten the distance of material handling. As well as using From To

Chart that functions for planning the layout of the plant and in the process of

moving materials in a production process.

The results obtained from this research are shortening the distance of

material transfer from 102 m to 59,4 m and reducing material handling cost from

Rp.8.327.071 to Rp.3.518.516.

Keywords : Facility Layout, Activity Realtionship Chart (ARC), From To Chart,

Material Handling Cost.

Page 11: TUGAS AKHIR PERANCANGAN ULANG TATA LETAK ...repository.untag-sby.ac.id/4201/1/ABSTRAK.pdfperencanaan tata letak pabrik serta pada proses pemindahan bahan dalam suatu proses produksi

xi

DAFTAR ISI

LEMBAR PENGESAHAN TUGAS AKHIR .................................................... iii

LEMBAR PENETAPAN PANITIA PENGUJI .................................................. iv

LEMBAR PERNYATAAN ORIGINALITAS TUGAS AKHIR ......................... v

LEMBAGA PERNYATAAN PERSETUJUAN PUBLIKASI ........................... vi

KATA PENGANTAR ....................................................................................... vii

ABSTRAK .......................................................................................................... ix

ABSTRACT .......................................................................................................... x

DAFTAR ISI ....................................................................................................... xi

DAFTAR TABEL ............................................................................................... xv

DAFTAR GAMBAR ....................................................................................... xvii

BAB 1 PENDAHULUAN .................................................................................... 1

1.1 Latar Belakang ............................................................................. 1

1.2 Rumusan Masalah ........................................................................ 5

1.3 Tujuan Penelitian .......................................................................... 5

1.4 Ruang Lingkup Penelitian ............................................................ 6

1.4.1 Batasan Masalah ............................................................... 6

1.4.2 Asumsi .............................................................................. 6

1.5 Manfaat Penelitian ........................................................................ 7

BAB 2 TINJAUAN PUSTAKA ........................................................................... 9

2.1 Tata Letak Fasilitas Pabrik ........................................................... 9

Page 12: TUGAS AKHIR PERANCANGAN ULANG TATA LETAK ...repository.untag-sby.ac.id/4201/1/ABSTRAK.pdfperencanaan tata letak pabrik serta pada proses pemindahan bahan dalam suatu proses produksi

xii

2.1.1 Ruang Lingkup Rancang Fasilitas ................................. 10

2.1.2 Pentingnya Rancang Fasilitas Produksi ......................... 10

2.1.3 Langkah-Langkah Perencanaan Tata Letak Pabrik ....... 11

2.1.4 Tujuan Pengaturan Tata Letak Pabrik ............................ 12

2.2 Analisis Proses Manufakturing .................................................. 14

2.2.1 Peta Proses (process Chart) ........................................... 14

2.2.2 Peta Proses Operasi (OPC) ............................................ 15

2.2.3 Multi Part Process Chart (MPPC)................................. 18

2.3 Pemindahan Bahan .................................................................... 19

2.3.1 Pengertian Material Handling ....................................... 19

2.3.2 Tujuan Material Handling ............................................. 20

2.3.3 Aspek-Aspek Biaya Pemindahan Bahan ........................ 21

2.3.4 Ongkos Material Handling (OMH) ............................... 22

2.3.5 Prinsip-Prinsip Pemindahan ........................................... 23

2.3.6 Peralatan Pemindah Barang / Bahan .............................. 24

2.3.7 Pola Aliran Pemindahan Bahan ..................................... 24

2.4 Alat-alat perancangan ................................................................ 27

2.5 Penelitian Terdahulu .................................................................. 33

BAB 3 METODOLOGI PENELITIAN ............................................................. 35

3.1 Penjelasan Tentang Metode Penelitian ...................................... 35

3.1.1 Identifikasi Permasalahan .............................................. 35

Page 13: TUGAS AKHIR PERANCANGAN ULANG TATA LETAK ...repository.untag-sby.ac.id/4201/1/ABSTRAK.pdfperencanaan tata letak pabrik serta pada proses pemindahan bahan dalam suatu proses produksi

xiii

3.1.2 Studi Lapangan ............................................................... 35

3.1.3 Studi Literatur ................................................................. 35

3.1.4 Pengumpulan Data .......................................................... 35

3.1.5 Pengolahan Data ............................................................. 36

3.1.6 Tempat Penelitian ........................................................... 37

3.1.7 Kesimpulan dan saran ..................................................... 38

3.2 Flowchart Penelitian .................................................................. 38

3.3 Jadwal Penelitian ........................................................................ 39

BAB 4 DATA DAN PENGOLAHAN DATA ................................................... 41

4.1 Seputar perusahaan ..................................................................... 41

4.1.1 Produk-produk di UD.Karya Bersaudara ....................... 41

4.2 Pengumpulan data ...................................................................... 42

4.2.1 Aktivitas proses produksi di UD. Karya Bersaudara ...... 43

4.2.2 Operation proses chart .................................................... 44

4.2.3 Data produksi .................................................................. 46

4.2.4 Data Pekerja .................................................................... 46

4.2.5 Layout awal di UD. Karya Bersaudara ........................... 47

4.2.6 Jarak perpindahan material layout awal ......................... 48

4.2.7 Luas lantai produksi ....................................................... 49

4.2.8 Data Permesinan ............................................................. 49

4.3 Pengolahan data .......................................................................... 50

Page 14: TUGAS AKHIR PERANCANGAN ULANG TATA LETAK ...repository.untag-sby.ac.id/4201/1/ABSTRAK.pdfperencanaan tata letak pabrik serta pada proses pemindahan bahan dalam suatu proses produksi

xiv

4.3.1 Metode Activity relationship chart (ARC) ..................... 50

4.3.2 Metode From To Chart layout awal .............................. 67

4.3.3 Perancangan layout usulan ............................................. 68

4.3.4 Perhitungan ongkos material handling ........................... 71

4.3.5 Estimasi perhitungan biaya pada layout usulan ............. 89

BAB 5 KESIMPULAN DAN SARAN .............................................................. 91

5.1 Kesimpulan ................................................................................ 91

5.2 Saran .......................................................................................... 91

DAFTAR PUSTAKA ......................................................................................... 93

LAMPIRAN ....................................................................................................... 95

Page 15: TUGAS AKHIR PERANCANGAN ULANG TATA LETAK ...repository.untag-sby.ac.id/4201/1/ABSTRAK.pdfperencanaan tata letak pabrik serta pada proses pemindahan bahan dalam suatu proses produksi

xv

DAFTAR TABEL

Tabel 1. 1 Daftar macam-macam produk jadi UD.Karya Bersaudara........ 1

Tabel 1. 2 Jenis-Jenis Mesin Produksi UD. Karya Bersaudara .................. 2

Tabel 1. 3 Urutan aliran proses produksi .................................................... 4

Tabel 1. 4 Luas departemen pada UD. Karya Bersaudara .......................... 4

Tabel 2. 1 Standard penggambaran derajat hubungan aktivitas ............... 29

Tabel 2. 2 Volume material yang dipindahkan dan aliran pemindahannya

.................................................................................................................. 30

Tabel 2. 3 Luas area departement ............................................................. 31

Tabel 2. 4 Volume material dipindahkan antar departement ................... 31

Tabel 2. 5 Volume produk berdasarkan jarak diagonal ............................ 32

Tabel 2. 6 penelitian terdahulu ................................................................. 33

Tabel 3. 1 Jadwal penelitian ..................................................................... 39

Tabel 4. 1 macam-macam produk pada UD.Karya Bersaudara ............... 41

Tabel 4. 2 Waktu proses produksi ............................................................ 44

Tabel 4. 3 Data produksi bulan januari sampai april 2020 ....................... 46

Tabel 4. 4 Jumlah tenaga kerja di UD.Karya Bersaudara ........................ 47

Tabel 4. 5 Jarak perpindahan material layout awal .................................. 48

Tabel 4. 6 luas departemen layout awal ................................................... 49

Tabel 4. 7 nama,ukuran,dan jumlah mesin-mesin produksi ..................... 50

Tabel 4. 8 Alasan penetapan derajat kedekatan aktivitas ......................... 51

Tabel 4. 9 volume handling dan aliran pemindahan ................................. 67

Tabel 4. 10 analisis from to chart ............................................................. 67

Tabel 4. 11 Menghitung volume jarak dan momen jarak ......................... 67

Tabel 4. 12 Jarak antar fasilitas pada layout awal .................................... 67

Tabel 4. 13 Momen handling (volume handling x jarak antar fasilitas)... 68

Page 16: TUGAS AKHIR PERANCANGAN ULANG TATA LETAK ...repository.untag-sby.ac.id/4201/1/ABSTRAK.pdfperencanaan tata letak pabrik serta pada proses pemindahan bahan dalam suatu proses produksi

xvi

Tabel 4. 14 Urutan aliran proses produksi ............................................... 70

Tabel 4. 15 Luas departemen pada layout usulan .................................... 71

Tabel 4. 16 Frekuensi material handling ................................................. 73

Tabel 4. 17 jarak perpindahan material handling layout awal ................ 74

Tabel 4. 18 Panjang lintasan perpindahan dengan alat angkut gerobak .. 75

Tabel 4. 19 Panjang lintasan perpindahan dengan manusia ..................... 75

Tabel 4. 20 Perhitungan ongkos perpindahan material dengan manusia . 76

Tabel 4. 21 Total ongkos material handling (OMH) perbulan pada layout

awal .......................................................................................................... 76

Tabel 4. 22 jarak perpindahan material handling layout usulan ............. 79

Tabel 4. 23 volume handling dan aliran pemindahan .............................. 80

Tabel 4. 24 analisis from to chart ............................................................. 80

Tabel 4. 25 Menghitung volume jarak dan momen jarak ........................ 80

Tabel 4. 26 Jarak antar fasilitas pada layout usulan ................................. 80

Tabel 4. 27 Momen handling (volume handling x jarak antar fasilitas) .. 81

Tabel 4. 28 Frekuensi material handling ................................................. 84

Tabel 4. 29 Panjang lintasan perpindahan dengan alat angkut gerobak .. 85

Tabel 4. 30 Panjang lintasan perpindahan dengan manusia ..................... 85

Tabel 4. 31 Perhitungan ongkos perpindahan material dengan manusia . 86

Tabel 4. 32 Total ongkos material handling (OMH) perbulan pada layout

usulan ....................................................................................................... 86

Tabel 4. 33 Perbandingan ongkos material handling awal dengan layout

usulan ....................................................................................................... 87

Tabel 4. 34 Rekapitulasi perbandingan layout awal dan layout usulan ... 88

Tabel 4. 35 Estimasi perhitungan biaya layout usulan ............................. 89

Tabel 5 1 Kesimpulan .............................................................................. 91

Page 17: TUGAS AKHIR PERANCANGAN ULANG TATA LETAK ...repository.untag-sby.ac.id/4201/1/ABSTRAK.pdfperencanaan tata letak pabrik serta pada proses pemindahan bahan dalam suatu proses produksi

xvii

DAFTAR GAMBAR

Gambar 1. 1 Layout awal di UD. Karya Bersaudara .................................. 3

Gambar 1. 2 Gudang Bahan Baku dan Produk Jadi UD. Karya Bersaudara

.................................................................................................................... 5

Gambar 2. 1 Contoh peta proses operasi pembuatan bracket kaca .......... 17

Gambar 2. 2 Multipart Process Chart untuk pembuatan berbagai macam

komponen ................................................................................................. 19

Gambar 2. 3 Aliran material pola straight line ......................................... 25

Gambar 2. 4 Aliran material pola zig-zag (s-shaped) ............................... 25

Gambar 2. 5 Aliran material pola U-shape ............................................... 26

Gambar 2. 6 Aliran material pola Circular ............................................... 26

Gambar 2. 7 Aliran material pola Odd-Angle .......................................... 27

Gambar 2. 8 Contoh peta hubungan aktivitas dalam sebuah industri

manufaktur ................................................................................................ 28

Gambar 3. 1 Activity Realtionship Chart (ARC) ..................................... 36

Gambar 3. 2 contoh opc ............................................................................ 37

Gambar 3. 3 Flowchart Penelitian ............................................................ 38

Gambar 4 1 Baskom 16 ............................................................................ 42

Gambar 4 2 wakul tradisi 12..................................................................... 42

Gambar 4 3 peta proses operasi produk wakul ......................................... 44

Gambar 4 4 peta proses operasi produk baskom ...................................... 45

Gambar 4 5 layout awal pada UD. Karya Bersaudara

.................................................................................................................. 48

Gambar 4 6 ARC derajat hubungan tiap departemen ............................... 66

Gambar 4 7 layout usulan ........................................................................ 70

Gambar 4 8 Alat angkut gerobak .............................................................. 82