TEKNIK SUMBERDAYA ALAM & LINGKUNGAN UNIVERSITAS BRAWIJAYA LAMPIRAN : MASS BALANCE BOD, COD, DAN TSS WASTE WATER TREATMENT  PT CJI, PASURUAN Removal: BOD=30% COD=0% TSS=40% in PC LSB recycle produksi Out sedimentasi Sedimentasi-2A “Sedimentation” Removal: BOD=50% COD=60% TSS=50% Removal: BOD=5% COD=55% TSS=0% !a"asitas:2#2#$2 m 3 Dt = 0$2 &a'i Tin((i=4$3m) d=2m !a"asitas: 2#2#$2 m 3 Dt = 0$2 &a'i Tin((i=4$3m ) d=2m !a"asitas: #320 m 3 Dt = 0$#2 &a'i 25*#2*5$5 m !a"asitas: #33+$ m 3 Dt = 0$#3 &a'i Tin((i=5m ) d=20 m !a"asitas: 432 m 3 Dt = 0$04 &a'i 2$5*$,5*5$5 m Removal #% MBOD = 1194.27 kg/hari MCOD=1089.49 kg/hari MTSS=729.49 kg/hari MBOD = 835.89 kg/hari MCOD=1089.49kg/hari MTSS=437.62 kg/hari MBOD = 417.99 kg/hari MCOD=435.80kg/hari MTSS= 218.81 kg/hari MBOD = 4777.06 kg/hari MCOD=2421.09 kg/hari MTSS=2431.23 kg/hari MBOD = 9554.125 kg/hari MCOD=6052.725 kg/hari MTSS=4862.46 3 kg/hari .n"/t = o/t"/ t Colletio n "ond MBOD = 4777.06 kg/hari MCOD=2421.09 kg/hari MTSS=2431.23 kg/hari inffluent Out sedimentasi i n out sedimentas i 1RT-B 1ond “!oa(-lo( Sedimentasi” STA D Sto'a(e Tan-A7 “89/aliation” Ae'ation 1ond “Ativated Sl/d(e” Sedimentation-3A “!oa(-lo( Sedimentasi” Removal : BOD=50 % COD=60 % TSS=50 % !a"asitas: #6000 m 3 Dt = #$5 &a'i 25*,*5 m

Upload: tyultia

Post on 17-Oct-2015

18 views

Category:

Documents


0 download

DESCRIPTION

mass balance

TRANSCRIPT

TEKNIK SUMBERDAYA ALAM & LINGKUNGAN UNIVERSITAS BRAWIJAYA

TEKNIK SUMBERDAYA ALAM & LINGKUNGAN UNIVERSITAS BRAWIJAYA

LAMPIRAN : MASS BALANCE BOD, COD, DAN TSS WASTE WATER TREATMENT PT CJI, PASURUANKapasitas:2121.2 m3

Dt = 0.2 hari

Tinggi=4.3m; d=27m

Kapasitas: 2121.2 m3

Dt = 0.2 hari

Tinggi=4.3m ; d=27m

Kapasitas: 1320 m3

Dt = 0.12 hari

25*12*5.5 m

Kapasitas: 1339.7 m3

Dt = 0.13 hari

Tinggi=5m ; d=20 m

Kapasitas: 432 m3

Dt = 0.04 hari

2.5*7.85*5.5 m

Removal