Pekerjaan Bore PilePekerjaan Bore Pile
El -24,00
Bore Pile
Min 8m
Pagar ProyekPagar Batas Lahan Penduduk
Min 1m
![Page 2: Metode Konstruksi Bored Pile](https://reader036.vdokumen.com/reader036/viewer/2022082314/55cf9847550346d03396b258/html5/thumbnails/2.jpg)
LANGKAH - 1
LANGKAH - 2
LANGKAH - 3
LANGKAH - 4
LANGKAH - 5
LANGKAH - 6
TAHAPAN PEKERJAAN BORE PILETAHAPAN PEKERJAAN BORE PILE
![Page 3: Metode Konstruksi Bored Pile](https://reader036.vdokumen.com/reader036/viewer/2022082314/55cf9847550346d03396b258/html5/thumbnails/3.jpg)
PEMASANGAN CASING
PT. TATAMULIA NUSANTARA INDAHGENERAL CONTRACTOR
Ngagel Jaya Selatan blok K30 –32 , RMI Manyar Surabaya
![Page 4: Metode Konstruksi Bored Pile](https://reader036.vdokumen.com/reader036/viewer/2022082314/55cf9847550346d03396b258/html5/thumbnails/4.jpg)
PEKERJAAN PENGEBORAN
PT. TATAMULIA NUSANTARA INDAHGENERAL CONTRACTOR
Ngagel Jaya Selatan blok K30 –32 , RMI Manyar Surabaya
![Page 5: Metode Konstruksi Bored Pile](https://reader036.vdokumen.com/reader036/viewer/2022082314/55cf9847550346d03396b258/html5/thumbnails/5.jpg)
PENGECORAN BORE PILE
PT. TATAMULIA NUSANTARA INDAHGENERAL CONTRACTOR
Ngagel Jaya Selatan blok K30 –32 , RMI Manyar Surabaya
![Page 6: Metode Konstruksi Bored Pile](https://reader036.vdokumen.com/reader036/viewer/2022082314/55cf9847550346d03396b258/html5/thumbnails/6.jpg)
PILE INTEGRATION TEST
PT. TATAMULIA NUSANTARA INDAHGENERAL CONTRACTOR
Ngagel Jaya Selatan blok K30 –32 , RMI Manyar Surabaya
![Page 7: Metode Konstruksi Bored Pile](https://reader036.vdokumen.com/reader036/viewer/2022082314/55cf9847550346d03396b258/html5/thumbnails/7.jpg)
PDA TEST
PT. TATAMULIA NUSANTARA INDAHGENERAL CONTRACTOR
Ngagel Jaya Selatan blok K30 –32 , RMI Manyar Surabaya