conexiones para madera

Upload: pauloandressepulveda

Post on 14-Apr-2018

229 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 Conexiones Para Madera

    1/10

    Failure of Wood Connections and the Evolution of Connection Design

    Jaret Lynch, P.E.1

    & John Cocca, P.E.2

    1Wiss, Janney, Elstner Associates, Inc., 2 Trap Falls Road, Suite 502, Shelton, CT

    06484; PH (203) 944-9424; FAX (203) 944-6997; email: [email protected], Janney, Elstner Associates, Inc., 2 Trap Falls Road, Suite 502, Shelton, CT

    06484; PH (203) 944-9424; FAX (203) 944-6997; email: [email protected]

    ABSTRACT

    Wood has been used as a construction material long before concrete and steel wereavailable as structural materials. Wood is easy to work with and can be used for many

    different types of framing. Wood trusses have been used for long span roof framing in

    the United States since the 1800s. Over time the material, wood, has remainedlargely unchanged; however, the connections have evolved as well as the standards to

    which they are designed.

    Before the 1850s, truss connections typically consisted of mortise and tenon joinery.These connections make good use of the inherent strength of the wood members with

    little or no reliance on fasteners or engineering analysis. During the late 1800s and

    early 1900s these connections evolved into side lapped joints with steel bolts whichbear on the wood in order to transfer shear through the joint. During the mid 1900s

    the invention of shear plates and split rings allowed joint forces to be transferred with

    fewer bolts. During the late 1900s pressed plate connections were developed whichpermited wood trusses to be readily pre-fabricated.

    In addition to the evolution of the connections, advancements in the testing of

    materials and creation of design standards have evolved into what they are today.

    This paper provides examples of actual woods connection failures from the different

    time periods mentioned above and discusses the cause of the failures. Also provided

    is a comparison of historic references versus modern design methods for the

    evaluation of the failed connections.

    INTRODUCTION

    Below are examples of four wood connections dating from 1843 to 1955 that do not

    have adequate capacity to resist the anticipated loading. These examples demonstrate

    the deficiencies typically found in these types of joinery. Comparisons are madebetween historical references and modern day design standards for each of these

    connections.

    1843 TIMBER FRAME

    In January of 2011, WJE was hired to assess the condition of a 2-1/2 story rectory in

    northwestern Connecticut. This timber-framed structure dates from 1843. The wood

    1970Structures Congress 2012 ASCE 2012

    Structures Congress 2012

  • 7/27/2019 Conexiones Para Madera

    2/10

    ap

    pur

    spa

    frome

    wastrto t

    ha

    Th

    sin

    shoof

    ten

    maan

    Alt

    tim

    bra

    doap

    by

    the

    ears to be

    lins which

    ced at fifte

    one lengmber at a ti

    l formed bts are usedhe attic flo

    e failed cau

    struts are

    le oak peg

    ulder of thehe joint rev

    sile force de

    erial behinis caused b

    hough the

    ber frames

    ces transmit

    etail or a lropriate for

    connecting

    useable spa

    oak. The r

    onnect to t

    n feet on c

    th of timbe instead

    the posts eto resolve tr framing.

    sing the kne

    onnected to

    is used to s

    tenon and taled that th

    veloped in t

    the peg hy insufficie

    roportions

    f the period

    ting compre

    rger mortisthis tension

    the rafter ta

    ce in the atti

    oof structur

    ree timber-

    nter. The

    r suggestinf being rai

    tending abe thrust crJEs asse

    e walls to le

    igure 1: Tim

    the wall po

    ecure each

    he mortisee oak peg h

    he strut (Fi

    le is knowt end distan

    of this con

    , this type o

    ssion forces

    e and tenonbrace conn

    ils directly

    c is reduce

    e consists

    framed ben

    connecting

    g that theed as comp

    ve the levelated by thesment foun

    an outward

    ber Frame C

    st with tradi

    onnection.

    t the top od torn out t

    ure 2). Thi

    as a relisce on the te

    nection are

    f mortise an

    through dir

    with morection. This

    o the frami

    .

    f hand he

    s. The ben

    girts (wall t

    roof framileted bents.

    of the atticrafters by tthat both

    at their cent

    onnection

    tonal morti

    A gap had

    the wall pohe end of th

    s type of bl

    failure (Mnon.

    simialar t

    d tenon is i

    ect bearing

    shear pegscondition i

    ng at the at

    n common

    ts are 24-fe

    op plate) ar

    g was assThere is a

    floor. Diaging the toptruts on the

    ers (Figure

    e and tenon

    developed

    st. Closere tenon due

    ck shear ru

    iller & Sch

    those fou

    eally reser

    on the woo

    would haves often avoi

    ic floor lev

    rafters and

    t wide and

    e fashioned

    mbled oneshort knee-

    onal timberof the postcenter bent

    1).

    joinery. A

    etween the

    xaminationto the large

    pture of the

    idt, 2004)

    d in other

    ed for knee

    . A lapped

    been moreed entirely

    l, although

    1971Structures Congress 2012 ASCE 2012

    Structures Congress 2012

  • 7/27/2019 Conexiones Para Madera

    3/10

    18

    In

    maco

    reswo

    at

    Th

    bea

    (Pi

    hortyp

    not

    the

    ironar

    thithe

    WJ

    coout

    2 SCISSO

    une of 201

    sonry wallsdition date

    rain the sprsened in re

    ne of the ti

    roof of th

    ring walls.

    ea sp.).

    izontal tieically side

    able except

    sloping top

    fixtures.row soffits

    k unreinforlevel of the

    Es assess

    nections wward. The

    TRUSS

    0, WJE wa

    at a churchback to a

    reading of tcent years, i

    rod anchor

    church is

    Samples t

    he trusses

    eams. Thlapped and

    on is the lo

    chord and i

    shallow bunning the

    ced brick msidewalk.

    ent found

    as causingalls were f

    Figure 2:

    hired to i

    in New Jersleast 1902

    he north ancluding lo

    ages.

    upported b

    aken from

    are varian

    trusses arbolted wit

    wer horizo

    s drawn up

    arrel vaultelength of th

    asonry and

    that wid

    the roof tund to be l

    Failed Conn

    vestigate t

    ey. The owhen thre

    d south wacalized fail

    nine woo

    the truss m

    s of a sci

    e comprise5/8-inch

    tal tie bea

    ight with s

    ceiling (wnorth and

    ise to a hei

    spread fail

    sag andeaning a m

    ection

    e cause of

    ner reportee metal tie

    lls. The cre of the m

    trusses sp

    embers we

    ssor truss

    of machiiameter sq

    which en

    uare heade

    ood lathe asouth walls.

    ght of appr

    ure of th

    hrust theaximum of

    two outwar

    that the hirods were

    ndition hasasonry and

    nning 46-f

    e identified

    hich inco

    e sawn luuare heade

    ages a bird

    bolts and

    d plaster) sThe walls

    ximately 3

    bolted s

    asonry beapproximat

    dly leaning

    tory of thisinstalled to

    reportedlylaster wall

    et between

    as Spruce

    porate two

    ber that isbolts. A

    s mouth in

    and forged

    rings fromare 16-inch

    -feet above

    issor truss

    aring wallsly 5-inches

    1972Structures Congress 2012 ASCE 2012

    Structures Congress 2012

  • 7/27/2019 Conexiones Para Madera

    4/10

    eac

    loc

    at

    an

    Altofpro

    Thfor

    lu

    meap

    topthr

    h with muc

    ated approx

    ll nine of t

    implement

    hough damthe scissorblem. Thes

    two slopi. Each sc

    ber measur

    mber is faroximately

    chord hasugh two fa

    of the tilt

    imately 28

    he roof trus

    ed.

    ge was fouchord connconnection

    g bottomissor chord

    ing approxi

    shioned fro3-7/8 inche

    ailed in nuteners in a

    ccurring a

    t. below the

    ses. The ro

    d throughoction to ths are locate

    Figure 3

    hord memmember is

    ately 2-1/4

    m one cowide by 9-

    erous locatow.

    Figure 4:

    ove the lev

    truss beari

    of was sho

    t the trussee top chorat Joints 2

    Truss Geo

    ers of eacashioned fr

    inches wid

    tinuous le5/8 inches

    ons. Figur

    Splitting F

    el of the sa

    g. Failed

    ed until re

    s, our analywas likel& 4 as sho

    etry

    truss exeom one con

    by 9 inche

    ngth of saeep. The s

    4 shows a

    ilure

    ctuary floo

    onnections

    airs could

    is indicatedthe root cn in Figure

    plify the stinuous len

    s deep. Eac

    n lumberissor conne

    splitting fail

    diaphragm

    were found

    e designed

    that failureause of the3.

    cissor trussth of sawn

    h top chord

    measuringction to the

    ure passing

    1973Structures Congress 2012 ASCE 2012

    Structures Congress 2012

  • 7/27/2019 Conexiones Para Madera

    5/10

    Fig

    the

    wa

    Ouov

    an

    be

    stawit

    bol

    acctru

    It icau

    ins

    fouitse

    191

    In

    in

    buisty

    bet

    ure 5 show

    remaining

    hers.

    r analysis inrstressed fo

    snow load

    carrying th

    dards. Noth insufficie

    ts were let i

    ommodates members.

    s importantse of the ro

    ead of trad

    nd in the trlf.

    8 King Pos

    he winter o

    upstate Ne

    lding code.e roof that

    een unrei

    one squar

    two bolts a

    Figure

    dicated thatr dead load

    on the roo

    ee to four

    only were tt distance

    n to the thi

    bolts which

    to realize tof truss fail

    itional timb

    ss member

    t Truss

    f 2009, WJ

    York to

    The mainis supporte

    forced bric

    headed bo

    re tilted an

    : Splitting

    the truss malone and s

    . More imp

    times what

    here not enrom the ed

    kness of th

    were too s

    at the seveure. The bu

    er joinery i

    would not

    was asked

    erify its a

    uilding waby six tim

    masonry

    lt which ha

    d crushing

    ailure with

    mbers (in tgnificantly

    ortantly, th

    would be

    ugh bolts,ge and/or e

    e side mem

    hort to pas

    rely overstrilders relia

    s notewort

    have been

    to analyze

    bility to ca

    s originallyber trusses

    earing wall

    split free

    the wood f

    Crushing

    eir undamaoverstresse

    bolted con

    ermitted b

    ut many ofnd of the

    ber by chis

    through t

    essed boltence on thro

    y because

    nough to p

    the roof of

    rry loads s

    constructehat span in

    s. Wood p

    rom the me

    ibers benea

    olts

    ged state)for the ex

    nections we

    modern

    the bolts wember. Se

    ling away t

    e full thick

    connectiough bolted

    the level o

    recipitate th

    an existing

    ecified in

    in 1918the east/we

    rlins span

    mber while

    h the plate

    ere slightlyected wind

    re shown to

    ood design

    re installederal of the

    he wood to

    ness of the

    s were theonnections

    overstress

    e failure by

    rain station

    the current

    ith a gablest direction

    etween the

    1974Structures Congress 2012 ASCE 2012

    Structures Congress 2012

  • 7/27/2019 Conexiones Para Madera

    6/10

    tru

    spa

    bot

    in.di

    7 iwoan

    Th

    apint

    tha

    ofnot

    co

    traAt

    by

    Strthe

    AScap

    bot

    snolar

    the

    pre

    De

    valno

    ses in the

    n approxim

    tom chord

    x 12 in. Tensions of

    . x 9 in. aod memberits membe

    top chor

    roximatelythe top of

    pass throu

    onnectionch in the

    trols the d

    sfer force tthe time of

    hand.

    ctural analadequacy o

    CE-7-02. Tacity to res

    tom chords

    w loads ine splits in t

    bottom ch

    dicted by o

    ign refere

    es for thisexcess capa

    orth/south

    ately 40.5

    f the truss i

    e top chorin. x 14 i

    d the cente(Figure 6).s were grad

    Fi

    to botto

    1 in. thick.the bottom

    h the top a

    he thrust frottom chor

    sign of thi

    hrough theur inspecti

    sis of the ef the truss t

    he truss mist the dead

    was found t

    luded in thhe wood sp

    ord (Figur

    r analysis o

    ces from t

    type of conity for win

    irection su

    . and bear

    fashioned

    of the tru. The diago

    vertical mThe wooded using vis

    gure 6: Typi

    chord c

    The platechord. Add

    d bottom c

    om the topd. Shear a

    type of c

    onnection,n, the bolts

    ntire truss ao carry bot

    embers anload of the

    o be signifi

    present dnning from

    8). This

    f the connec

    is time fr

    ection howor snow lo

    porting the

    on blueston

    of two mem

    s is fashional web me

    ember is awas identifal observat

    al Truss and

    nnection c

    raps the eitionally, th

    ords near t

    chord is resd bearing

    nnection.

    hey are mewere found

    nd its conneuniform a

    connectioroof; howe

    antly overs

    y design cthe tip of t

    distress is

    tion.

    me (Kidde

    ever in theads.

    common r

    e pads at t

    bers with n

    ed of twombers have

    teel rod enied as densions of the

    Geometry

    onsists of

    d of the toere are four

    eir bearing

    isted by thef the woo

    he purpose

    ely there toto be loose

    ctions wasd unbalanc

    ns were fover, the co

    ressed whe

    des. Closee notched c

    consistent

    r 1916) pr

    oofs curren

    afters. The

    e top of th

    ominal dim

    members wnominal di

    cased by nograined sooods natu

    an end pl

    chord and, 7/8 in. dia

    (Figure 7).

    cantilevered parallel t

    of the bol

    keep the pand the nut

    erformed ted loads as

    und to havnection of

    subjected

    up inspectionnection t

    ith the fa

    vide allow

    t configurat

    oof trusses

    e wall. The

    nsions of 4

    ith nominalensions of

    n-structuraluthern pineral defects.

    ate that is

    is notchedmeter bolts

    In this type

    d plate andthe grain

    s is not to

    rts aligned.removable

    determinespecified in

    e adequatethe top and

    o wind and

    n revealedthe end of

    ilure mode

    ble design

    on, there is

    1975Structures Congress 2012 ASCE 2012

    Structures Congress 2012

  • 7/27/2019 Conexiones Para Madera

    7/10

    Fig

    Figur

    re 7: Truss

    e 8: Location

    onnection

    of Split in F

    onfiguration

    ield Inspecti

    n

    1976Structures Congress 2012 ASCE 2012

    Structures Congress 2012

  • 7/27/2019 Conexiones Para Madera

    8/10

    19

    WJ

    Ne

    res

    Th

    sou

    unrwe

    parCotop

    co

    co

    Str

    ch

    sigtyp

    stri

    ad

    A s

    thiof

    pro

    sno

    sno

    5: BOW S

    E was calle

    York tha

    lted in 39 i

    roof was

    th direction

    einforced he fashione

    abolic arch.nections bchord to bo

    nectors. Th

    sists of stee

    ctural anal

    rd of the tr

    ificantly ee of failure

    ng trusses

    ition of live

    econd type

    particularnbalanced

    vide provisi

    w. The co

    w load ac

    RING TR

    d to investi

    t occurred

    n. of snow i

    Fi

    onstructed

    and spaced

    llow concrof glue l

    Web memtween thettom chord

    e bottom ch

    l side plates

    sis verifie

    ss. The fail

    ceeded thender heavy

    ypically pr

    load, (i.e. s

    of failure c

    xample isload from

    ons for esti

    es typicall

    oss the en

    SS

    ate the cau

    during a

    less than a

    gure 9: Bo

    of wood bo

    at 8 ft. on

    te masonryaminated l

    ers were faeb member

    connection

    ord is splic

    on each sid

    our obser

    re was loc

    capacity osnow load i

    ovide adeq

    now and wi

    mmon to t

    ailure of thrifting sno

    ating the u

    only prov

    ire roof sp

    e of a bow

    ajor snow

    48 hour pe

    string Trus

    wstring tru

    center. The

    unit (CMUmber with

    shioned fros and chordonsists of a

    d 3 ft. fro

    e of the me

    ations that

    ted at the s

    the shears not unco

    ate capacit

    d) can resu

    ese bowstri

    web mem. Prior to

    nbalanced l

    ded guidan

    an. These

    tring truss

    storm in th

    iod (Figure

    Collapse

    ses spanni

    ends of th

    ) walls. Thethe top ch

    m solid saconsist ofsteel beari

    the center

    ber and bo

    the failure

    lice conne

    late connemon in our

    y under de

    lt in membe

    ng trusses t

    er to chord1980, most

    oads on roo

    ce for the

    unbalanced

    roof collaps

    e winter o

    9).

    g 71 feet i

    trusses be

    top and boord curved

    n dimensioolted shearg shoe with

    of the truss.

    lted shear pl

    occurred in

    tion where

    ctors (Figurexperience.

    ad load alo

    r or connect

    at was not

    connectionbuilding co

    fs as a resul

    inclusion o

    loads can

    e in upstate

    2008 that

    the north-

    r on 12 in.

    tom chordsto form a

    nal lumber.plates. Theshear plate

    The splice

    ates.

    the bottom

    the demand

    e 10). ThisThese bow

    ne, but the

    ion failure.

    observed in

    as a resultdes did not

    t of drifting

    a uniform

    cause web

    1977Structures Congress 2012 ASCE 2012

    Structures Congress 2012

  • 7/27/2019 Conexiones Para Madera

    9/10

    me

    res

    C

    De

    moco

    we

    ana

    Ti

    Atjoi

    str

    du

    Re

    firs

    pufor

    waofred

    Fusta

    Wco

    mbers to ca

    lting in fail

    NCLUSIO

    ign of woo

    rtise and tstructed by

    l as knowl

    lyzing and

    ber Frame

    the beginniery becam

    sses publis

    to the larg

    earch and a

    t National

    lished in tthis is that

    determineood memb

    uced by a

    thermore, cdards.

    en evaluatinections an

    rry loads m

    ure of the m

    Fig

    NS

    d connectio

    enon joineskilled cra

    edge passe

    designing t

    ngineering

    g of the 19tavailable,

    ed in these

    factors of s

    dvancement

    esign Spec

    is NDS areuntil the m

    using a coers were deproximatel

    onnection

    g existingd their abilit

    uch greater

    embers and

    re 10: Fail

    s has evolv

    y were gtsmen usin

    down thr

    imber fram

    Council (T

    h Century,first in Eur

    references

    afety which

    of wood te

    ification (N

    significantlid-1960s, t

    relation toeloped and

    40% co

    apacities w

    ood structy to resist t

    than those

    or connecti

    ed Bottom

    ed over tim

    nerally noknowledg

    ugh the g

    ed connecti

    EC 1-07).

    esign referope, then l

    are surprisi

    were histor

    hnology br

    DS) for wo

    y higher thhe allowabl

    he bendingperformed,pared to

    ere also re

    res, particue anticipate

    required by

    ons.

    hord Splic

    e. The earli

    engineeregained th

    enerations.

    ons have b

    nces for wter in Ame

    gly close t

    ically appli

    ought about

    od in 1944.

    n currentlye tensile str

    stress. Oncthe allowa

    current sta

    uced com

    lar attentiond loads.

    the unifor

    st connecti

    d. These jough trial a

    Current gui

    een develo

    od construrica. The s

    the curren

    d.

    the develop

    The allowa

    permitted.ess for woo

    full scale tle tensile stdards (Kri

    ared to cur

    should be

    load case

    ns, such as

    oints werend error as

    delines for

    ed by The

    tion and itsfe working

    guidelines

    ment of the

    ble stresses

    One reasond members

    ension testsresses werestie 1996).

    rent design

    iven to the

    1978Structures Congress 2012 ASCE 2012

    Structures Congress 2012

  • 7/27/2019 Conexiones Para Madera

    10/10

    REFERENCES

    Kidder, F. E. (1916).Architects and builders pocket-book, Wiley, New York.Kristie, R. J., and Johnson, A. P. (1996). Investigating and repairing wood bowstring

    trusses.Pract. Period. Struct. Des. Constr., ASCE, 1(1), 25-30.

    Miller J. F. and Schmidt, R. J. (2004). Capacity of pegged mortise and tenonjoinery. Research Report, Dept. of Civil & Arch. Engineering, University of

    Wyoming, Laramie, Wyoming.American Forest & Paper Association (AFPA). (2005). National design specification

    for wood construction, Washington, D.C.American Society of Civil Engineers (ASCE). (2002). Minimum design loads for

    buildings and other structures, New York.Timber Frame Engineering Council. (2007). Standard for design of timber frame

    structures and commentary, Becket, Mass.

    1979Structures Congress 2012 ASCE 2012