HARGA PERKIRAAN SENDIRI

( HPS )

PEMERINTAH KABUPATEN SIGI

DINAS PEKERJAAN UMUM DAERAH

BIDANG BINA MARGA

2015

PAKET PEKERJAAAN :

PEMBANGUNAN TALUD PENGAMAN TEBING

DESA OO PARESE KEC. KULAWI SELATAN

Kegiatan : -

Pekerjaan : Talud Pengaman Tebing

Lokasi : Desa Oo Parese Kec. Kulawi Selatan

Tahun Anggaran : 2015

I.

1 Pembersihan Lapangan M2 906.500 11,250.00Rp 10,198,125.00Rp

2 Pengukuran Dan Pasang Bouwplank M' 181.380 55,765.00Rp 10,114,655.70Rp

20,312,780.70Rp

III.

1 Galian Tanah Biasa dalam 1 meter M3 243.676 58,125.00Rp 14,163,682.03Rp

2 Urugan Sirtu M3 43.801 270,625.00Rp 11,853,510.31Rp

26,017,192.34Rp

VI.

1 Pasangan Batu Kali 1 Pc : 3 Ps M3 243.601 946,875.00Rp 230,660,004.61Rp

2 Finishing Siar Pas. Batu Kali adukan 1 Pc : 2 Pp M2 424.505 51,428.00Rp 21,831,443.14Rp

252,491,447.75Rp

VII

1 Papan Proyek Ls 1.000 250,000.00Rp 250,000.00Rp

2 Dokumentasi dan Pelaporan Ls 1.000 1,000,000.00Rp 1,000,000.00Rp

1,250,000.00Rp

(A) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 300,071,420.79Rp

(B) Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 30,007,142.08Rp

(C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B) 330,078,562.87Rp

(D) DIBULATKAN 330,078,000.00Rp

Terbilang :

PEKERJAAN TANAH

PEKERJAAN STRUKTUR

PEKERJAAN LAIN-LAIN

HARGA PERKIRAAN SENDIRI (HPS)

No URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN

Tiga Ratus Tiga Puluh Juta Tujuh Puluh Delapan Ribu

JUMLAH HARGA

PEKERJAAN PERSIAPAN

1 Pasir Pasang (Sedang) M3 250,000.00

2 Pasir Urug (ada unsur lempung) M3 250,000.00

3 Batu Kali M3 280,000.00

4 Agregat Kasar M3 250,000.00

5 Agregat Halus M3 250,000.00

6 F i l l e r Kg 1,300.00

7 Batu Belah / Kerakal M3 200,000.00

8 Batu Pecah 2/3 M3 300,000.00

9 Batu Pecah 3/5 M3 300,000.00

10 Abu Batu M3 125,000.00

11 G r a v e l M3 200,000.00

12 Bahan Tanah Timbunan M3 90,000.00

13 Bahan Pilihan M3 100,000.00

14 Aspal KG 14,500.00

15 Kerosen / Minyak Tanah LITER 15,000.00

16 Semen / PC (50kg) Zak 85,000.00

17 Semen / PC (kg) Kg 1,700.00

18 Kayu Kelas I M3 2,500,000.00

19 Kayu Kelas II M3 2,000,000.00

20 Kayu Perancah M3 1,000,000.00

21 B e n s i n ( Industri ) LITER 11,000.00

22 S o l a r ( Industri ) LITER 11,000.00

23 Minyak Pelumas / Olie LITER 35,000.00

24 Besi Beton D-8 mm Btng 57,000.00

25 Besi Beton D-10 mm Btng 84,000.00

26 Besi Beton D-12 mm Btng 125,850.00

27 Besi Beton D-14 mm Btng 178,875.00

28 Besi Beton D-16 mm Btng 256,125.00

29 Besi Plat 5 mm M 27,500.00

30 Bendrat/Kawat Beton Kg 15,000.00

31 Paku Biasa 5 s/d 10" Kg 27,000.00

32 Paku Beton Kg 85,000.00

33 Besi Penggatung D-14 mm M 203,000.00

34 Besi Strip / Klem Bh 8,500.00

35 Besi Kabel /Sling Utama D- 1 1/2" M 178,000.00

36 Besi Kabel /Sling D- 1" M 78,000.00

37 Besi Strip / Klem Penggatung Bawah 3 mm Set 153,000.00

38 Besi Strip / Klem Penggatung Atas 3 mm Set 153,000.00

39 Baut Mur 12 Bh 6,000.00

40 Kawat Harmonika M2 25,000.00

41 Cat Kayu Kg 57,000.00

42 Cat Tembok Kg 22,750.00

43 Cat Besi Kg 59,800.00

44 Cat Meny Kg 19,500.00

45 Minyak Cat Kg 21,000.00

46 Minyak Bekisting Ltr 19,500.00

47 Residu / Ter Ltr 188,500.00

48 Kertas Pasir Lbr 13,000.00

49 Kawat Bronjong Kg 20,000.00

50 Seng Gelombang Lbr 73,000.00

51 Seng Plat Lbr 53,500.00

52 Paku Seng Kg 30,000.00

1 Pekerja HOK 75,000Rp

2 Tukang HOK 80,000Rp

2 Kepala Tukang HOK 85,000Rp

3 M a n d o r HOK 75,000Rp

UPAH Satuan

Bahan Satuan

DAFTAR UPAH, MATERIAL DAN BAHAN

HARGA SATUAN

No HARGA SATUAN

No

SNI 03-2835-2002 1 M²

Tenaga

0.100 Oh Pekerja @ Rp. 75,000.00 Rp. 7,500.00

0.050 Oh Mandor @ Rp. 75,000.00 Rp. 3,750.00

Jumlah Rp. 11,250.00

SNI 03-2835-2002 1 M'

A. Bahan

0.012 M³ Kayu 5/7 ( Klas III ) @ Rp. 2,000,000.00 Rp. 24,000.00

0.020 Kg Paku Biasa 5 s/d 10" @ Rp. 27,000.00 Rp. 540.00

0.007 M³ Papan 3/20 ( Kls III ) @ Rp. 2,000,000.00 Rp. 14,000.00

Jumlah A Rp. 38,540.00

B. Tenaga

0.100 Oh Tukang Kayu @ Rp. 85,000.00 Rp. 8,500.00

0.100 Oh Pekerja @ Rp. 75,000.00 Rp. 7,500.00

0.010 Oh Kepala Tukang @ Rp. 85,000.00 Rp. 850.00

0.005 Oh Mandor @ Rp. 75,000.00 Rp. 375.00

Jumlah B Rp. 17,225.00

Jumlah A + B Rp. 55,765.00

SNI : 2835:2008 1 M³

Tenaga

0.750 Oh Pekerja @ Rp. 75,000.00 Rp. 56,250.00

0.025 Oh Mandor @ Rp. 75,000.00 Rp. 1,875.00

Jumlah Rp. 58,125.00

Anl. SNI 1 M³

A. Bahan

1.100 M³ Batu Kali @ Rp. 280,000.00 Rp. 308,000.00

202.000 Kg Semen Portland @ Rp. 1,700.00 Rp. 343,400.00

0.485 M³ Pasir Pasang @ Rp. 250,000.00 Rp. 121,250.00

Jumlah A Rp. 772,650.00

B. Tenaga

1.500 Oh Pekerja @ Rp. 75,000.00 Rp. 112,500.00

0.600 Oh Tukang Batu @ Rp. 85,000.00 Rp. 51,000.00

0.060 Oh Kepala Tukang @ Rp. 85,000.00 Rp. 5,100.00

0.075 Oh Mandor @ Rp. 75,000.00 Rp. 5,625.00

Jumlah B Rp. 174,225.00

Jumlah A + B Rp. 946,875.00

Anl. SNI 1 M³

A. Bahan

1.000 M³ Pasir urug @ Rp. 250,000.00 Rp. 250,000.00

Jumlah A Rp. 250,000.00

B. Tenaga

0.250 Oh Pekerja @ Rp. 75,000.00 Rp. 18,750.00

0.025 Oh Mandor @ Rp. 75,000.00 Rp. 1,875.00

Jumlah B Rp. 20,625.00

Jumlah A + B Rp. 270,625.00

Anl. SNI 1 M²

A. Bahan

6.340 Kg Semen Portland @ Rp. 1,700.00 Rp. 10,778.00

0.012 M³ Pasir Pasang @ Rp. 250,000.00 Rp. 3,000.00

Jumlah A Rp. 13,778.00

B. Tenaga

0.300 Oh Pekerja @ Rp. 75,000.00 Rp. 22,500.00

0.150 Oh Tukang Batu @ Rp. 85,000.00 Rp. 12,750.00

0.015 Oh Kepala Tukang @ Rp. 85,000.00 Rp. 1,275.00

0.015 Oh Mandor @ Rp. 75,000.00 Rp. 1,125.00

Jumlah B Rp. 37,650.00

Jumlah A + B Rp. 51,428.00

Daftar Analisa Satuan Harga

Pembersihan Lapangan

Pengukuran Dan Pasang Bouwplank

Galian Tanah Biasa dalam 1 meter

Pasangan Batu Kali 1 Pc : 3 Ps

Urugan Sirtu

Finishing Siar Pas. Batu Kali adukan 1 Pc : 2 Pp

KEGIATAN : -

NAMA PAKET : Talud Pengaman Tebing

LOKASI : Desa Oo Parese Kec. Kulawi Selatan

TAHUN ANGGARAN : 2015

1 Pekerjaan Galian Tanah

A. Pek. Talud 1 A. TALUD 1

i. Koporan Talud

Panjang = 35.00 m

Lebar = 1.90 m

Tinggi = 0.75 m

Volume = P x L x T

= 35 x 1.9 x 0.75

= 49.875 m3

ii. Talud

Luasan I

Panjang = 35.00 m

Lebar = 0.73 m

Tinggi = 1.61 m

Volume = P x ( 1/2 x L x T )

= 35 x ( 1/2 x 0.73 x 1.61 )

= 20.57 m3

Luasan II

Panjang = 35.00 m

Lebar Atas = 0.73 m

Lebar Bawah = 0.45 m

Tinggi = 1.39 m

Volume = P x ( (La+Lb)/2 x T )

= 35 x ( (0.73+0.45)/2 x 1.39 )

= 28.70 m3 B. TALUD 2

B. Pek. Talud 2

i. Koporan Talud 1

Panjang = 43.00 m

Lebar = 0.30 m

Tinggi = 0.50 m

Volume = P x L x T

= 43 x 0.3 x 0.5

= 6.45 m3

ii. Koporan Talud 2

Panjang = 46.00 m

Lebar = 1.40 m

Tinggi = 0.50 m

Volume = P x ( 1/2 x L x T )

= 46 x ( 1/2 x 1.4 x 0.5 )

= 16.10 m3

iii. Koporan Talud 3

Panjang = 49.00 m

Lebar = 0.50 m

Tinggi = 0.50 m

Volume = P x L x T

= 49 x 0.5 x 0.5

= 12.25 m3

iv. Talud

Luasan I Panjang = 43.00 m

Lebar = 0.46 m

Tinggi = 3.50 m

Volume = P x ( L x T )

= 43 x ( 0.46 x 3.5 )

= 69.23 m3

C. Pek. Bronjong

Panjang = 36.00 m

Lebar = 1.50 m

Tinggi = 1.50 m

Volume = P x ( 1/2 x L x T )

= 36 x ( 1/2 x 1.5 x 1.5 )

= 40.50 m3

Total Volume = 243.68 m3

2 Pekerjaan Pasangan Batu

A. Pek. Talud 1

i. Koporan Talud

Panjang = 35.00 m

Lebar = 1.90 m

Tinggi = 0.45 m

Volume = P x L x T

= 35 x 1.9 x 0.45

= 29.925 m3

BACKUP PEKERJAAN PENGAMAN TEBING

NO URAIAN SKETSA

1.61

1.00

0.30

0.45

0.30

0.45 0.45

1.00

1.90

LUBANG PERESAPAN

DIPASANG PER 3 M SECARA HORISONTAL

PER 1 M SECARA VERTIKAL

PIPA PVC Ø 3"

TIMBUNAN PILIHAN PORUS

(PASIR KERIKIL), t = 10 cm

DITUTUP DENGAN

IJUK

TALUD PASANGAN

BATU KALI

1.39

0.73

KEGIATAN : -

NAMA PAKET : Talud Pengaman Tebing

LOKASI : Desa Oo Parese Kec. Kulawi Selatan

TAHUN ANGGARAN : 2015

BACKUP PEKERJAAN PENGAMAN TEBING

NO URAIAN SKETSA

ii. Talud

Luasan I

Panjang = 35.00 m A. TALUD 1

Lebar Atas = 0.30 m

Lebar Bawah = 1.00 m

Tinggi = 3.00 m

Volume = P x ( (La+Lb)/2 x T )

= 35 x ( (0.3+1)/2 x 3 )

= 68.25 m3

B. Pek. Talud 2

i. Koporan Talud Atas

Panjang = 43.00 m

Lebar = 0.30 m

Tinggi = 0.50 m

Volume = P x L x T

= 43 x 0.3 x 0.5

= 6.45 m3

ii. Koporan Talud Tengah

Panjang = 46.00 m

Lebar Atas = 0.95 m

Lebar Bawah = 1.40 m

Tinggi = 0.50 m

Volume = P x ( (La+Lb)/2 x T )

= 46 x ( (0.95+1.4)/2 x 0.5 ) B. TALUD 2

= 27.03 m3 B. TALUD 2

iii. Koporan Talud Bawah

Panjang = 49.00 m

Lebar = 0.50 m

Tinggi = 1.00 m

Volume = P x L x T

= 49 x 0.5 x 1

= 24.50 m3

iii. Talud 1

Panjang 1 = 43.00 m

Panjang 2 = 46.00 m

Lebar Atas = 0.17 m

Lebar Bawah = 0.36 m

Tinggi = 3.84 m

Volume = ((P1+P2)/2) x ( (La+Lb)/2 x T )

= ((43+46)/2) x ( (0.17+0.36)/2 x 3.84 )

= 45.28 m3

iv. Talud 2

Panjang 1 = 46.00 m

Panjang 2 = 49.00 m

Lebar Atas = 0.17 m

Lebar Bawah = 0.36 m

Tinggi 1 = 4.20 m

Tinggi 2 = 2.50 m

Volume = ((P1+P2)/2) x ((La+Lb)/2) x ((T1+T2)/2)

= ((46+49)/2) x ((0.17+0.36)/2) x ((4.2+F130)/2)

= 42.17 m3

Total Volume = 243.60 m3

3 Pekerjaan Bronjong

i. Bronjong 1

Panjang = 36.00 m

Lebar = 1.50 m

Tinggi = 1.00 m

Volume = P x L x T

= 36 x 1.5 x 1

= 54.00 m3

ii. Bronjong 2

Panjang = 36.00 m

Lebar = 1.25 m

Tinggi = 0.50 m

Volume = P x L x T

= 36 x 1.25 x 0.5

= 22.50 m3

iii. Bronjong 3

Panjang = 36.00 m

Lebar = 1.00 m

Tinggi = 0.50 m

Volume = P x L x T

= 36 x 1 x 0.5

= 18.00 m3

Total Volume = 91.81 m3

1.61

1.00

0.30

0.45

0.30

0.45 0.45

1.00

1.90

LUBANG PERESAPAN

DIPASANG PER 3 M SECARA HORISONTAL

PER 1 M SECARA VERTIKAL

PIPA PVC Ø 3"

TIMBUNAN PILIHAN PORUS

(PASIR KERIKIL), t = 10 cm

DITUTUP DENGAN

IJUK

TALUD PASANGAN

BATU KALI

1.39

0.73

KEGIATAN : -

NAMA PAKET : Talud Pengaman Tebing

LOKASI : Desa Oo Parese Kec. Kulawi Selatan

TAHUN ANGGARAN : 2015

BACKUP PEKERJAAN PENGAMAN TEBING

NO URAIAN SKETSA

4 Pekerjaan Timbunan Porus

i. Talud 1

Panjang = 36.00 m A. TALUD 1

Lebar = 0.10 m

Tinggi = 3.00 m

Volume = P x L x T

= 36 x 0.1 x 3

= 10.80 m3

ii. Talud 2 Atas

Panjang = 44.50 m

Lebar = 0.10 m

Tinggi = 3.84 m

Volume = P x L x T

= 44.5 x 0.1 x 3.84

= 17.09 m3

iii. Talud 2 Bawah

Panjang = 47.50 m

Lebar = 0.10 m

Tinggi = 3.35 m

Volume = P x L x T

= 47.5 x 0.1 x 3.35

= 15.91 m3

Total Volume = 43.80 m3

5 Pekerjaan Pemasangan Bouplank

i. Talud 1 B. TALUD 2

Panjang = 36.00 m

Lebar = 1.50 m

Volume = ( 2 x P ) + ( 2 x L )

= ( 2 x 36 ) + ( 2 x 1.5 )

= 75.00 m'

ii. Talud 2

Panjang Atas = 43.00 m

Panjang Bawah = 49.00 m

Lebar Kiri = 8.04 m

Lebar Kanan = 6.34 m

Volume = ( 2 x ((Pa+Pb)/2) + ( 2 x ((Lki+Lka)/2)

= ( 2 x ((43+49)/2) ) + ( 2 x ((8.04+6.34)/2) )

= 106.38 m'

Total Volume = 181.38 m'

6 Pekerjaan Pembersihan Lokasi

i. Talud 1

Panjang = 49.00 m

Lebar = 18.50 m

Volume = P x L

= 49 x 18.5

= 906.50 m2

1.61

1.00

0.30

0.45

0.30

0.45 0.45

1.00

1.90

LUBANG PERESAPAN

DIPASANG PER 3 M SECARA HORISONTAL

PER 1 M SECARA VERTIKAL

PIPA PVC Ø 3"

TIMBUNAN PILIHAN PORUS

(PASIR KERIKIL), t = 10 cm

DITUTUP DENGAN

IJUK

TALUD PASANGAN

BATU KALI

1.39

0.73

SHOP DRAWING( GAMBAR KERJA)

PAKET PEKERJAAAN :

PEMBANGUNAN TALUD PENGAMAN TEBING

DESA OO PARESE KEC. KULAWI SELATAN

PEMERINTAH KABUPATEN SIGI

DINAS PEKERJAAN UMUM DAERAHBIDANG BINA MARGA

2015

36.00

35.00

43.00

49.25

A

A

B

C

B

C

JA

LA

N T

RA

NS

K

UL

AW

I - G

IM

PU

46.83

KEGIATAN

PEMERINTAH KABUPATEN SIGI

DINAS PEKERJAAN UMUM

BIDANG BINA MARGA

JL. TRANS PALU - PALOLO KM 14 SIDERA KEC. SIGI BIROMARU

TELP. (0451) 4791666

JML. LBRKODE NO. LBR

U

PEKERJAAN

LOKASI

.........................................

.........................................

DI GAMBAR

.........................................

DI PERIKSA

ASISTEN TEKNIS

........................................

NIP.

MENGETAHUI/MENYETUJUI

PPTK

........................................

NIP.

KEPALA DINAS

H. ISKANDAR NONGTJI

PEMBINA

NIP. 19560606 199603 1 004

LEGENDA

PASANGAN BATU

TIMBUNAN PILIHAN

GALIAN BIASA

LPA KELAS B

BANGUNAN UTAMA

TEPI SUNGAI

GAMBAR SKALA

LAYOUT

1 : 350

1.00

1.25

1.50

0.50

0.50

0.50

0.50

1.00

0.50

0.15

2.50

H variasi

0.30

0.50

0.30

0.50

0.17

0.17

0.50

1.40

1.00

0.30

0.45

0.30

0.45

0.45

1.00

1.90

1.00

1

1.7

LUBANG PERESAPAN

DIPASANG PER 3 M

PIPA PVC Ø 3"

DITUTUP DENGAN

IJUK

LUBANG PERESAPAN

DIPASANG PER 3 M

PIPA PVC Ø 3"

DITUTUP DENGAN

IJUK

TIMBUNAN PILIHAN PORUS

(PASIR KERIKIL), t = 10 cm

TIMBUNAN PILIHAN PORUS

(PASIR KERIKIL), t = 10 cm

LUBANG PERESAPAN

DIPASANG PER 3 M SECARA HORISONTAL

PER 1 M SECARA VERTIKAL

PIPA PVC Ø 3"

TIMBUNAN PILIHAN PORUS

(PASIR KERIKIL), t = 10 cm

DITUTUP DENGAN

IJUK

TALUD PASANGAN

BATU KALI

TALUD PASANGAN

BATU KALI

TALUD PASANGAN

BATU KALI

POTONGAN A - A

0.40

0.50

1.00

BAK KONTROL SALURAN

PIPA PEMBUANGAN

PIPA PVC AW Ø 6"

KEGIATAN

PEMERINTAH KABUPATEN SIGI

DINAS PEKERJAAN UMUM

BIDANG BINA MARGA

JL. TRANS PALU - PALOLO KM 14 SIDERA KEC. SIGI BIROMARU

TELP. (0451) 4791666

PEKERJAAN

LOKASI

.........................................

.........................................

DI GAMBAR

.........................................

DI PERIKSA

ASISTEN TEKNIS

........................................

NIP.

MENGETAHUI/MENYETUJUI

PPTK

........................................

NIP.

JML. LBRKODE NO. LBR

KEPALA DINAS

H. ISKANDAR NONGTJI

PEMBINA

NIP. 19560606 199603 1 004

GAMBAR SKALA

POTONGAN A-A

1 : 100

LEGENDA

PASANGAN BATU

TIMBUNAN BIASA

GALIAN TANAH

BRONJONG

1.00

1.25

1.50

0.50

0.50

0.50

0.501.00

0.50

0.15

2.50

H variasi

0.30

0.50

0.30

0.50

0.17

0.17

0.50

1.61

1.40

1.00

0.30

0.45

0.30

0.45

0.45

1.00

1.90

1.00

1

1.7

LUBANG PERESAPAN

DIPASANG PER 3 M

PIPA PVC Ø 3"

DITUTUP DENGAN

IJUK

LUBANG PERESAPAN

DIPASANG PER 3 M

PIPA PVC Ø 3"

DITUTUP DENGAN

IJUK

TIMBUNAN PILIHAN PORUS

(PASIR KERIKIL), t = 10 cm

TIMBUNAN PILIHAN PORUS

(PASIR KERIKIL), t = 10 cm

LUBANG PERESAPAN

DIPASANG PER 3 M SECARA HORISONTAL

PER 1 M SECARA VERTIKAL

PIPA PVC Ø 3"

TIMBUNAN PILIHAN PORUS

(PASIR KERIKIL), t = 10 cm

DITUTUP DENGAN

IJUK

TALUD PASANGAN

BATU KALI

TALUD PASANGAN

BATU KALI

TALUD PASANGAN

BATU KALI

1.39

0.73

0.46

0.46

3.63

0.95

0.36

KEGIATAN

PEMERINTAH KABUPATEN SIGI

DINAS PEKERJAAN UMUM

BIDANG BINA MARGA

JL. TRANS PALU - PALOLO KM 14 SIDERA KEC. SIGI BIROMARU

TELP. (0451) 4791666

PEKERJAAN

LOKASI

.........................................

.........................................

DI GAMBAR

.........................................

DI PERIKSA

ASISTEN TEKNIS

........................................

NIP.

MENGETAHUI/MENYETUJUI

PPTK

........................................

NIP.

JML. LBRKODE NO. LBR

KEPALA DINAS

H. ISKANDAR NONGTJI

PEMBINA

NIP. 19560606 199603 1 004

GAMBAR SKALA

POTONGAN B-B

1 : 100

LEGENDA

PASANGAN BATU

TIMBUNAN BIASA

GALIAN TANAH

BRONJONG

1.00

0.50

0.15

0.30

0.50

0.30

0.50

0.17

0.17

1.00

0.30

0.45

0.30

0.45

0.45

1.00

1.90

1.40

2.50

H variasi

1.7

1

1.00

LUBANG PERESAPAN

DIPASANG PER 3 M

PIPA PVC Ø 3"

DITUTUP DENGAN

IJUK

TIMBUNAN PILIHAN PORUS

(PASIR KERIKIL), t = 10 cm

TIMBUNAN PILIHAN PORUS

(PASIR KERIKIL), t = 10 cm

LUBANG PERESAPAN

DIPASANG PER 3 M SECARA HORISONTAL

PER 1 M SECARA VERTIKAL

PIPA PVC Ø 3"

LUBANG PERESAPAN

DIPASANG PER 3 M SECARA HORISONTAL

PER 1 M SECARA VERTIKAL

PIPA PVC Ø 3"

TIMBUNAN PILIHAN PORUS

(PASIR KERIKIL), t = 10 cm

DITUTUP DENGAN

IJUK

TIMBUNAN PILIHAN PORUS

(PASIR KERIKIL), t = 10 cm

DITUTUP DENGAN

IJUK

3.00

TALUD PASANGAN

BATU KALI

TALUD PASANGAN

BATU KALI

TALUD PASANGAN

BATU KALI

POTONGAN C - C

LUBANG PERESAPAN

DIPASANG PER 3 M

PIPA PVC Ø 3"

DITUTUP DENGAN

IJUK

KEGIATAN

PEMERINTAH KABUPATEN SIGI

DINAS PEKERJAAN UMUM

BIDANG BINA MARGA

JL. TRANS PALU - PALOLO KM 14 SIDERA KEC. SIGI BIROMARU

TELP. (0451) 4791666

PEKERJAAN

LOKASI

.........................................

.........................................

DI GAMBAR

.........................................

DI PERIKSA

ASISTEN TEKNIS

........................................

NIP.

MENGETAHUI/MENYETUJUI

PPTK

........................................

NIP.

JML. LBRKODE NO. LBR

KEPALA DINAS

H. ISKANDAR NONGTJI

PEMBINA

NIP. 19560606 199603 1 004

GAMBAR SKALA

POTONGAN C-C

1 : 100

LEGENDA

PASANGAN BATU

TIMBUNAN BIASA

GALIAN TANAH

BRONJONG