analisa penawaran harga raffles cbbr
TRANSCRIPT
-
7/23/2019 Analisa Penawaran Harga Raffles Cbbr
1/3
ANALISA HARGA
PENGADAAN FURNITURE RUANG SPA
RAFFLES HILLS - CIBUBUR
NO. ITEM PEKERJAAN TOTAL
REKAPITULASI
I PEKERJAAN FURNITURE RUANG SPA
A MEJA BAR JAMU Rp 13,759,500.00
B LEMARI BAR JAMU Rp 27,738,000.00C MEJA RECEPTIONIST Rp 14,807,340.00
TotalRp 56,304,840.00
Pembulatan Rp 56,300,000.00
-
7/23/2019 Analisa Penawaran Harga Raffles Cbbr
2/3
PT. Tri Asri Desindotama
Hal : 2
ANALISA HARGA SATUAN
PENGADAAN FURNITURE RUANG SPA
RAFFLES HILLS - CIBUBUR
NO URAIAN PEKERJAAN SAT VOL. HARGA JUMLAH BAHAN TOTALSATUAN & UPAH
A PEKERJAAN FURNITURE RUANG SPA
-
7/23/2019 Analisa Penawaran Harga Raffles Cbbr
3/3
PT. Tri Asri Desindotama
Hal : 3
NO URAIAN PEKERJAAN SAT VOL.HARGA JUMLAH BAHAN
TOTALSATUAN & UPAH
1. Meja Bar Jamu unit 1.00 13,759,500 13,759,500.00
- Melaminto 18mm ( 1 muka ) lbr 6.00 230,000 1,380,000.00
- Melaminto 18mm ( 2 muka ) lbr 4.00 250,000 1,000,000.00- HPL ex. Taco lbr 5.00 190,000 950,000.00
- Lem Kuning ltr 1.50 15,000 22,500.00
- Lem Kayu kg 0.25 15,000 3,750.00
- Skru bh 40.00 1,000 40,000.00
- Engsel Sendok bh 12.00 25,000 300,000.00
- Handle (huben) bh 6.00 25,000 150,000.00
- Granit Nero+ongkos tukang m2 1.70 1,300,000 2,210,000.00- Zink+kran (model standart) bh 1.00 2,500,000 2,500,000.00
- lampu TL T4 ttk 2.00 120,000 240,000.00
- LED strip rol 1.00 250,000 250,000.00
- Stop kontak ttk 3.00 95,000 285,000.00
- Saklar ttk 1.00 95,000 95,000.00
- Growmet ttk 4.00 20,000 80,000.00
- Acrilic 4mm lbr 1.00 750,000 750,000.00
- Tukang kayu m2 2.20 450,000 990,000.00- Mandor m2 2.20 100,000 220,000.00
11,466,250.00
Biaya Over Head & Profit Pelaksana ls 1.00 2,293,250 2,293,250.00
NB: Bagian dalam lemari menggunakan melaminto
NB:
2. Lemari Bar Jamu unit 1.00 27,738,000 27,738,000.00
- Melaminto 18mm ( 1 muka ) lbr 18.00 230,000 4,140,000.00
- Melaminto 18mm ( 2 muka ) lbr 24.00 250,000 6,000,000.00
- HPL ex. Taco lbr 13.00 190,000 2,470,000.00
- Lem Kunin ltr 10.00 15,000 150,000.00
- Lem Kayu kg 5.00 15,000 75,000.00
- Skrup bh 100.00 1,000 100,000.00
- Engsel Sendok bh 38.00 25,000 950,000.00
- Handle (huben) bh 18.00 25,000 450,000.00
- Kaca clear/bening 5 mm m2 7.20 150,000 1,080,000.00
- Tukang kayu m2 14.00 450,000 6,300,000.00
- Mandor m2 14.00 100,000 1,400,000.00
23,115,000.00
Biaya Over Head & Profit Pelaksana ls 1.00 4,623,000 4,623,000.00
NB: Bagian dalam lemari menggunakan melaminto
NB:
3. Meja Rceptionist unit 1.00 14,807,340 14,807,340.00
- Melaminto 18mm ( 1 muka ) lbr 7.00 230,000 1,610,000.00
- Melaminto 18mm ( 2 muka ) lbr 10.00 250,000 2,500,000.00
- HPL ex. Taco lbr 5.00 190,000 950,000.00
- Lem Kuning ltr 1.50 15,000 22,500.00
- Lem Kayu kg 0.25 15,000 3,750.00- Skrup bh 40.00 1,000 40,000.00
- Ensel Sendok bh 12.00 25,000 300,000.00
- Handle (huben) bh 6.00 25,000 150,000.00
- Granit Nero+ongkos tukang m2 1.70 1,300,000 2,210,000.00
- Pengecatan ex. Dulux m2 2.97 60,000 178,200.00- lampu TL T4 ttk 2.00 120,000 240,000.00
- LED strip rol 1.00 250,000 250,000.00
- Stop kontak ttk 3.00 95,000 285,000.00
- Saklar ttk 1.00 95,000 95,000.00
- Growmet ttk 4.00 20,000 80,000.00- Acrilic 4mm lbr 2.00 750,000 1,500,000.00
- Tukang kayu m2 3.50 450,000 1,575,000.00
- Mandor m2 3.50 100,000 350,000.00
12,339,450.00
Biaya Over Head & Profit Pelaksana ls 1.00 2,467,890 2,467,890.00
NB: Bagian dalam lemari menggunakan melaminto
NB:
GRAND TOTAL PEKERJAAN 56,304,840.00
Badan dan sisi lemari menggunakan solid multipleks dan tidak
menggunakan rangka seperti di gambar
Badan dan sisi lemari menggunakan solid multipleks dan tidak
menggunakan rangka seperti di gambar
Badan dan sisi lemari menggunakan solid multipleks dan tidak
menggunakan rangka seperti di gambar