perhitungan produktifitas alat berat
Post on 14-May-2017
249 Views
Preview:
TRANSCRIPT
1. Diketahui : = 5%
= 5%
= 26 ton
= 16 ton
= 4 ton
Ditanyakan :
K = 5% Jawab :
=
1.
TR =
= W x % K
= 1.3 ton
2.
TR = Tahanan Kelandaian (GR) + Tahanan Gelinding (RR)
=
= 2 ton
= 3.3 ton
2. Diketahui : = 8%
= 4500 kg
= 18 ton
= 4 ton
= 0.65
K = 8% Ditanyakan :
Jawab :
1.
TR =
= W x % K
= 1.44 ton
2.
TR = 4500 kg + Tahanan Kelandaian (GR)
=
= 4.82 ton
= 6.26 ton
= W x ct
= 11.7 ton
TK > TR = Mampu
Traksi Kritis Bulldozer (TK)
Mampukah Bulldozer menarik harraw ?
Tenaga yang dibutuhkan Bulldozer (TR)
Bulldozer ( Roda Rantai )
Tahanan Kelandaian (GR)
Scraper ( Roda Rantai )
4500 kg + ( W x % K )
1.Kelandaian ( K )
2.Harraw ditarik pada datar
3.Berat Bulldozer ( W )
4.Berat Harraw ( W )
5.Koef. Traksi Kritis ( ct )
ANALISA BEBAN DAN TENAGA
TUGAS
Tenaga yang dibutuhkan Beban Total ( TR )
Jadi tenaga yang dibutuhkan traktor adalah
1.Kelandaian ( K )
2.Koef. Tahanan Gelinding ( r )
3.Berat Traktor ( W )
4.Berat Scraper ( W )
5.Muatan Scraper
Berapa besar tenaga yang dibutuhkan untuk menarik scraper ?
Tahanan Kelandaian (GR)
Scraper ( Roda Karet )
( W x % K ) + ( W x % r )
Traktor ( Roda Rantai )
:
1. 0.83
p = 4000 m 2. Sweel = 20%
t = 1.8 m
p = 2000 m
t = 1.2 m
1. =
2. = 3.2 m
3. = 1.1 m
4. =
5. =
6. = 8 thn
7. = jam
8. =
9. =
=
1 =
2 =
3 = 0.83
4 = 4.5 km/jam =
5 = 6 km/jam =
6 =
7 = 140 jam
8 = 0.3 m
: 1
2
3
4
5
6
:
Diketahui
Tanah Biasa =
Durasi 20 hari @ 7 jam
a. Data Pekerjaan & alat
dari harga pembelian
Galian
Timbunan
Proyek jalan raya
Latihan 1
STA 00 STA 6000
= 24
galian timbunan galian timbunan galian
b. Kondisi Tanah
Alat Bulldozer type s
Lebar blade
Tinggi blade
Biaya Pemblian Rp19,000,000,000
Nilai Sisa
Waktu Investasi
Masa guna alat
Biaya Operasional
Biaya Investasi
10%
10000
Rp900,000
18%
Rp3,420,000,000
c. Metode kerja
Metode kerja
Waktu kerja 50 menit/jam
Operator Pandai
V mendorong
Slot and Dozing
V mundur
Bekerja waktu kemarau
75
100
Jawab
m/menit
m/menit
Ditanyakan Produksi alat dalam 1 jam ( Q )
Hitung jumlah alat
Biaya aktual apabila profit 10%
HSP pekerjaan
Biaya penawaran dengan pajak 15%
Jadwal
GALIAN
Perataan timbinan perlapis
● = m³
● =
● = Lm³
● = Lm³
● = m
0.02 m ( J )
● = menit
● =
1 Q = Q' x E
Q' = 60 x B
CT
= 232.32 = 164.571 Lm³/jam
1.412
Q = 134.949
2 = Lm³
= Jam
= Jam
Jam
Jumlah Alat = 10.9756 ~ 11 UNIT
3 BP
● =
● = +
BP = /jam
O = /jam
+
BP & O = /jam
=
=
=
= +
=
4 = Rp
m³
= Rp
m³
HSP Pekerjaan = Rp/m³
5 = + + Pajak 15%
Biaya Aktual Rp4,989,600,000
Rp28,875
Harga Penawaran Biaya Actual Profit
HSP Pekerjaan Biaya act + profit
vol . Bank
Rp4,989,600,000
172800
Rp453,600,000Profit 10 %
Rp4,536,000,000
Qx
207360
134.949x Rp2,952,000
BP & O
Jumlah Alat 1537
140
Biaya Aktual Vol. Loose
Jarak Operasi Blade , dengan kedalaman 60.5
Kapasitas Blade ( B ) 3.872
Rp900,000
Rp2,952,000
CT 1.412
E 0.82
Lm³/jam
Durasi Alat 207360
134.9485714 Lm³/jam
1537
Depresiasi / jam
Investasi / jam
Rp1,710,000
Rp342,000
Rp2,052,000
Volume Pekerjaan Galian ( bank )
Volume Pekerjaan Galian ( loose )
172800
20%sweel
207360
= +
=
Rp4,989,600,000 Rp748,440,000
Rp5,738,040,000Harga Penawaran
m
TIMBUNAN
● = m³
● =
● = Lm³
● = Lm³
● = m
0.3 m ( J )
● = menit
● =
1 Q = Q' x E
Q' = 60 x B
CT
= 232.32 = 2468.571 Lm³/jam
0.094
Q = 2024.229
2 = Lm³
= Jam
Jumlah Alat = Jam
Jam
Jumlah Alat = 0.243902 ~ 1 UNIT
3 BP
● =
● =
BP =
O =
BP & O =
=
=
=
= +
=
4 HSP Pekerjaan = Rp
m³
= Rp
m³
HSP Pekerjaan = Rp/m³
5 = + +Pajak 15%
Volume Pekerjaan Galian ( bank ) 57600
sweel 20%
Volume Pekerjaan Galian ( loose ) 69120
Kapasitas Blade ( B ) 3.872
Jarak Operasi Blade , dengan kedalaman 4.033
Rp1,710,000
Investasi / jam Rp342,000
Rp2,052,000
CT 0.094
E 0.82
Lm³/jam
Durasi Alat 69120
2024.228571 Lm³/jam
Rp100,800,000
Profit 10 % Rp10,080,000
Biaya Aktual Rp110,880,000
Biaya act + profit
vol . Bank
Rp110,880,000
57600
Rp1,925
Harga Penawaran Biaya Actual Profit
Rp900,000
Rp2,952,000
Biaya Aktual Vol. Loosex BP & O
Q
69120x Rp2,952,000
2024.229
34
34
140
Depresiasi / jam
= +
=
Rp748,440,000 Rp110,880,000
Rp127,512,000Harga Penawaran
+
/jam
/jam
+
/jam
Pajak 15%
Rp16,632,000
4.47 CL
4 m
2 : 1
2.5 m
Diketahui : 1.
● =
● = 0.85 m³
2.
● = 2000 m
● = 1.1
● = 20%
● = 1
● = 15 detik
● = 0.83
● = 210 jam
● BP & O =
Ditanyakan : 1.
2.
3.
4.
5.
6.
Jawab : 1. = 22350 m³
= 26820 Lm³
Q = Q ' x E
Q' = 60 x q
CT (menit )
q = q ' x K
Q = 46.563
0.25
Q = 186.252 Lm³/jam
Volume pekerjaan galian ( loose )
Rp1,200,000
tanah biasa ( K )
sweel
digging condition 60 %
swing angle 70°
Koefisien efesiensi ( E ) "good"
panjang galian
Data alat
Excavator PC 180
Latihan 2
Data pekerjaan
Kapasitas ( q ' )
Jadwal
Durasi 30 hari @ 7 jam kerja
Produksi alat dalam 1 jam ( Q )
Hitung jumlah alat
Biaya aktual apabila profit 10%
HSP pekerjaan
Biaya penawaran dengan pajak 15%
Volume pekerjaan galian ( bank )
2. 26820 Lm³
186.252
= 143.998 Jam
Jumlah Alat = 143.998 Jam
210 Jam
Jumlah Alat = 0.685706922 ~ 1 UNIT
3. Biaya Aktual = Vol. Loose
Q
= 26820
186.252
= Rp172,798,144
Rp17,279,814 +
Biaya Aktual = Rp190,077,959
4. HSP pekerjaan = Biaya act + profit Rp
vol . Bank m³
= Rp190,077,959 Rp
22350 m³
HSP pekerjaan = Rp8,505 Rp/m³
5. Biaya actual + Profit +
= +
Rp218,589,653
X Rp1,200,000
Harga Penawaran =
Rp190,077,959
Durasi alat =
Lm³/jam
BP & OX
Harga Penawaran =
Profit 10% =
/jam
Pajak 15 %
Rp28,511,694
Tanah
12 m
12 m
:
1 = 138240 Lm³
2 = 3.4 m³
3 = 0.95
4 = /Jam
5 = 0.2 menit
6 = 0.83
1 = 12 m
2 = 2.5 km/jam = 41.67
3 = 4 km/jam = 66.67
4 = 210 jam
: 1.
2.
3.
4.
5.
6.
: 1. CT = J1 = J2
= 2J
kecp. Isi
= 0.576 + + 0.2
= 1.136
Latuhan 3
Diketahui
Pengangkutan tanah dengan Vol.
Pekerjaan 2/3 dari hasil galian
bulldozer
b. Metode kerja
V shape ,dengan jarak
Koefisien efesiensi ( E ) "good"
Bucket Kapasitas ( q ' )
Faktor Bucket ( K )
a. Data pekerjaan & alat
BP & O
FT
kecepatan isi
kecepatan kosong
waktu 30 hari @ 7 jam
Rp1,250,000
Produksi alat dalam 1 jam ( Q )Ditanyakan
Jawab
Hitung jumlah alat
Biaya aktual apabila profit 10%
HSP pekerjaan
Biaya penawaran dengan pajak 15%
Jadwal
2J + FT
0.36
+
menit
kecp. Kosong
DT
= 115200 m³
= 20%
= 138240 Lm³
Q = Q ' x E
Q' = 60 x q
CT (menit )
q = q ' x K
Q = 160.854
1.136
Q = 141.597
2. = Lm³
= jam
= jam
jam
= ~ 5
3. =
=
=
= +
=
4. = Rp
m³
= Rp
m³
= Rp/jam
5. = +
=
=
volume pekerjaan ( loose )
sweel
volume pekerjaan ( bank )
Lm³/jam
Durasi alat 138240
141.597
976.293
Lm³/jam
Jumlah alat 976.293
210
4.649014457
Biaya Aktual Vol. Loose
QX
Jumlah alat
141.597X Rp1,250,000
Rp1,220,366,295
BP&O
138240
Vol. Bank
Rp1,342,402,924
115200
Rp11,653
Profit 10% Rp122,036,629
Rp1,342,402,924
HSP Pekerjaan Biaya Act. + profit
Biaya Aktual
HSP Pekerjaan
Rp1,342,402,924
1,543,763,363Rp
Harga Penawaran Biaya Act. Profit
Harga Penawaran
m/menit
m/menit
UNIT
+
+
Rp1,250,000
Pajak 15%
201,360,439Rp Rp1,342,402,924
Profit
Latihan 4
10%
750 m
600 m
Diketahui : 1.
●
● = 27.2 ton
● = 52.3 ton
● = V max Flat = Isi = 40
Kosong = 60
= = Isi = 20
Kosong = 40
● = Rp2,100,000 /hari =
2.
● = 115200 m³
= 138240 lm³
● = Membawa sama dengan kembali
● = Kering dan kurang terpelihara =
● = 1.6 ton/m³
● =
● = Lancar Tanpa Ada Hambatan
● = Lancar Tanpa Ada Hambatan
Ditanyakan : 1
2
3
4
5
6
Jawab : 1 CT = T1 + T2 + T3 + T4 + T5
T1 = n X CT wheel loader
n =
Datar
Tabel T2 dan T4
tipe angkutSegmen
kondisi
Membawa (isi)q WL x K x γt
Managemen Baik
Dumping
Spot & Delay
Kondisi Jalan
γ Tanah
Volume Pekerjaan
q DT ( kg )
Sewa Dump Truck
Route Pengangkutan
Data Alat
Dump Truck HD 325
Berat Kosong
Jadwal
Produksi alat dalam 1 jam ( Q )
Hitung Durasi
Biaya aktual apabila profit 10%
HSP pekerjaan
Biaya penawaran dengan pajak 15%
Rp262,500
Data Pekerjaan
Berat Bermuatan Max
Batasan Kacapatan
V max
Turunan/
tanjakan
DUMP TRUCK
n =
n = 25100
5168
n = 4.8568111 ~ 5
T1 = 5 x 1,136 menit T3 = 0.6
T1 = 5.68 T5 = 0.15
CT = T1 + T2 + T3 + T4 + T5
CT = 8.69 menit
M = CT dt
n X CT wl
M = 8.69
5.68
M = 1.53 ~ 2 unit
Q = Q' x E x M E ( GOOD ) = 0.83
Q' = 60 x q DT
CT
q DT = n x q L
Q' = 60 x 9 x 3,4
8.69
Q' = 46.95
Q = 194,48 x 0,83 x 9
Q = 77.93
2
Volume ( Bank ) = 115200 m²
Sweel = 20%
Volume ( Loose ) = 138240 Lm³
Waktu Pelaksanaan = Vol. loose
Q
= 138240
77.93
= 1773.88 jam
Waktu Pelaksanaan = 253.41 Hari ~ 254 Hari
3. =
=
=
138240x Rp262,500
77.931
Rp465,644,005
Lm³/jam
Lm³/jam
Hitung Durasi
Biaya Aktual Vol. Loosex BP & O
Q
Tanjakan
menit
Datar
Datar
Turunan
Datar
Membawa (isi)
Kembali (
kosong )
(52,3 t - 27,2 t )x 1000
3,4 x 0,95 x 1600
= +
=
4. = Rp
m³
= Rp
m³
HSP Pekerjaan = Rp/m³
5. = +
=
=
Profit
Rp512,208,405
Harga Penawaran Rp589,039,666
vol . Bank
Rp512,208,405
115200
Rp4,446
Harga Penawaran Biaya Actual
Profit 10 % Rp46,564,400
Biaya Aktual Rp512,208,405
HSP Pekerjaan Biaya act + profit
350 m
= m/menit
= m/menit
= m/menit
= m/menit
/jam
8%
jarak RR GR TR F Vmax SF V rata2
600 8% 0% 8% 667 0.72 480
667
1000
333
667
T2
tahanan kecepatanTime
Datar
1.393443
Segmen
kondisi
Km/jam
Km/jam
Km/jam
Jadwal
Produksi alat dalam 1 jam ( Q )
Hitung Durasi
Biaya aktual apabila profit 10%
HSP pekerjaan
Biaya penawaran dengan pajak 15%
Km/jam
750 8% 10% 18% 333 0.78 260
350 8% 0% 8% 667 0.72 480
600 8% 0% 8% 1000 0.72 720
750 8% -10% -2% 667 0.78 520
350 8% 0% 8% 1000 0.72 720
menit
menit
Rp262,500
Hitung Durasi
BP & O
0.867347
T2
T4
Tanjakan
1.393443Datar
Datar
Turunan
Datar
+
+
Profit Pajak 15%
Rp512,208,405 Rp76,831,261
Return
Houling
Diketahui : 1.
● Kapasitas bowel (q ) = 10 m³
● Kecp. Digging (VD) = 1.5 km/jam = 25
● Kecp. Houling (VH) = 10 km/jam = 166.6667
● Kecp. Spreading (VS) = 3 km/jam = 50.00
● Kecp. Returning (VR) = 12 km/jam = 200
2.
● Jarak Digging (D) = 35 m
● Jarak Houling (H) = 175 m
● Jarak Spreading (S) = 25 m
● Jarak Returning (R) = 200 m
● Vulome Galian = 500000 m³
● Volume Urugan = 500000 m³
● Banyak Alat = 5 Unit
● BP & O = Rp1,500,000 per jam
● FT = 1
Ditanyakan : 1.
2.
3.
4.
5.
6.
Dijawab : 1. CT =
CT = 35 175 25 +
HSP pekerjaan
Biaya penawaran dengan pajak 15%
Jadwal
+ +
Biaya aktual apabila profit 10%
Latihan 5
Data Alat
Data Pekerjaan
Produksi alat dalam 1 jam ( Q )
Hitung waktu pelaksanaa
175 m
200 m
𝐷
𝑉𝐷 +
𝐻
𝑉𝐻 +
𝑆
𝑉𝑆+
𝑅
𝑉𝑅 + FT
25 166.67 50.00
CT = 4.95 menit
E = E1 X E2 X E3 Dimana : E1 = Waktu Kerja 50m/j
E = 1.008 E2 = Operator Baik
E3 = Tanah Biasa
Q' = 60 X q
CT
Q' = 600
4.95
Q' = 121.212121
Q' = Q' X E
Q = 122.181818
2. Volume ( Bank ) = 500000 m³
Sweel = 20%
Volume ( Loose ) = 600000 Lm³
Waktu Pelaksanaan = Vol. loose
Q
= 600000
122.18
= 4910.71 jam / 5 unit
= 982.14 per unit
Waktu Pelaksanaan = 140.31 Hari ~ 141
3. =
=
=
= +
=
4. = Rp
m³
= Rp
m³
HSP Pekerjaan = Rp/m³
500000
Rp16,205
Biaya Aktual Rp8,102,678,571
HSP Pekerjaan Biaya act + profit
vol . Bank
Rp8,102,678,571
600000x Rp1,500,000
122.182
Rp7,366,071,429
Profit 10 % Rp736,607,143
Lm³/jam
Lm³/jam
Biaya Aktual Vol. Loosex BP & O
Q
+ + +
5. = +
=
=
Rp8,102,678,571
Harga Penawaran Rp9,318,080,357
Harga Penawaran Biaya Actual Profit
m/menit
m/menit
m/menit
m/menit
200 + 1
𝐷
𝑉𝐷 +
𝐻
𝑉𝐻 +
𝑆
𝑉𝑆+
𝑅
𝑉𝑅 + FT
200
= 0.84
= 1
= 1.2
Hari
Rp1,500,000
+ 1
BP & O
+
+Rp8,102,678,571 Rp1,215,401,786
Profit Pajak 15%
lo
L
α
Diketahui : 1.
● Lebar Blade ( L ) = 3.1 m
● Sudut Kerja ( α ) = 60 °
● Kecepatan rata2 = 4 km/jam =
● BP & O / jam =
● Jumlah alat = 1 unit
2.
● Lebar lapisan = 12 m
● Laluan Subgrade (n) = 6 kali
● Laluan sub base (n) = 4 kali
● Laluan base course (n) = 3 kali
● Lebar overlap (lo) = 0.25 m
● E faktor ( good ) = 0.83
Ditanyakan : 1.
2.
3.
4.
5.
6.
Dijawab : 1. Q = Q' X E
Q' = le = sin α x L
le = sin 60 x 3,1
Q' = le = 2.68
Q' = 9720
6
Q' = 1620.00
Q = 1620 x 0,83
Q = 1344.60 m²/jam
2. Luas Perataan = 72000 m²
Waktu Pelaksanaan = Luas
Q
SUBGRADE
le6
6000
Data Alat
Rp2,200,000
Data Pekerjaan
6
Produksi alat dalam 1 jam ( Q )
Hitung waktu pelaksanaa
Biaya aktual apabila profit 10%
HSP pekerjaan
Biaya penawaran dengan pajak 15%
Jadwal
60 X V .( le - lo )
n
60 x 66,67 . ( 2,68 - 0,25 )
6
= 72000
1344.60
= 53.55 jam
= 53.55 per unit
Waktu Pelaksanaan = 7.65 Hari ~
3. =
=
=
= +
=
4. = Rp
m²
= Rp
m²
HSP Pekerjaan = Rp/m²
5. = +
=
=
Biaya Aktual Luasx
Q
72000x
1344.600
Rp117,804,552
Profit 10 % Rp11,780,455
Harga Penawaran Rp149,022,758
Rp1,800
Harga Penawaran Biaya Actual
Biaya Aktual Rp129,585,007
HSP Pekerjaan Biaya act + profit
Luas
Rp129,585,007
72000
Rp129,585,007
66.67 m/menit
1.
sin 60 x 3,1
m
2.
SUB BASE
8 Hari
3.
4.
+ 5.
+
BP & O
Rp2,200,000
Profit Pajak 15%
Rp129,585,007 Rp19,437,751
Q = Q' X E
Q' = le = sin α x L
le = sin 60 x 3,1
Q' = le = 2.68 m
Q' = 9720
4
Q' = 2430.00
Q = 2430 x 0,83
Q = 2016.90 m²/jam
Luas Perataan = 72000 m²
Waktu Pelaksanaan = Luas
Q
SUB BASE
60 X V .( le - lo )
n
60 x 66,67 . ( 2,68 - 0,25 )
4
= 72000
2016.90
= 35.70 jam
= 35.70 per unit
Waktu Pelaksanaan = 5.10 Hari ~ 6 Hari
=
=
=
= +
=
= Rp
m²
= Rp
m²
HSP Pekerjaan = Rp/m²
= +
=
=
Rp86,390,004
Harga Penawaran Rp99,348,505
Rp1,200
Harga Penawaran Biaya Actual Profit
HSP Pekerjaan Biaya act + profit
Luas
Rp86,390,004
72000
Rp78,536,368
Profit 10 % Rp7,853,637
Biaya Aktual Rp86,390,004
Luasx BP & O
Q
72000x Rp2,200,000
2016.900
Biaya Aktual
1. Q = Q' X E
Q' =
Q' =
Q' = 9720
3
Q' = 3240.00
Q = 3240 x 0,83
Q = 2689.20 m²/jam
2. Luas Perataan =
Waktu Pelaksanaan =
BASE COURSE
60 X V .( le - lo )
n
60 x 66,67 . ( 2,68 - 0,25 )
3
=
=
=
Waktu Pelaksanaan =
3. =
=
=
=
=
4. =
=
HSP Pekerjaan =
+ 5. =
+ =
=
Profit 10 %
Biaya Aktual
Rp12,958,501
Biaya Aktual
HSP Pekerjaan
Harga Penawaran
Harga Penawaran
Pajak 15%
BP & O
Rp2,200,000
le = sin α x L
le = sin 60 x 3,1
le = 2.68 m
72000 m²
Luas
Q
72000
2689.20
26.77 jam
26.77 per unit
3.82 Hari ~ 4 Hari
+
Rp
m²
Rp
m²
Rp/m²
+ +
+
Rp74,511,379
Biaya Actual Profit Pajak 15%
Rp64,792,503 Rp9,718,876
Biaya act + profit
Luas
Rp64,792,503
72000
Rp900
Rp58,902,276
Rp5,890,228
Rp64,792,503
Luasx BP & O
Q
72000x Rp2,200,000
2689.200
Pajak 15%
Rp9,718,876
Diketahui : 1.
● Lebar roda (w) = 2 m
● Kecp. Rata2 = 3 km/jam =
● Overlap (wo) = 0.3 m
● BP & O = Rp2,000,000 /jam
2.
● Laluan Subgrade = 4 kali
● Laluan Subbase = 3 kali
● Laluan Base course = 3 kali
Ditanyakan : 1.
2.
3.
4.
5.
6.
Dijawab : 1. Q= Q' X E
Q'=
Q'=
Q'= 21250 m²/jam
Q= Q' X E E faktor ( good ) =
Q= 21250 x 0,83
Q= 17637.5 m²/jam
2. Luas Perataan = 72000 m²
Waktu Pelaksanaan = Luas
Q
= 72000
17637.50
= 4.08 jam
= 4.08 per unit
Waktu Pelaksanaan = 0.58 Hari ~
3. =
=
=
= +
=
SUBGRADE
Biaya Aktual Luasx
Rp8,164,422
Profit 10 % Rp816,442
Biaya Aktual Rp8,980,865
Q
72000x
17637.500
4
Data Alat
Data Pekerjaan
Produksi alat dalam 1 jam ( Q )
Hitung waktu pelaksanaa
Biaya aktual apabila profit 10%
HSP pekerjaan
Biaya penawaran dengan pajak 15%
Jadwal
1000 . V . ( w - Wo )
n
85000
4. = Rp
m²
= Rp
m²
HSP Pekerjaan = /m²
5. = +
=
=
Rp8,980,865
Harga Penawaran Rp10,327,994
Luas
Rp8,980,865
72000
Rp125
Harga Penawaran Biaya Actual
HSP Pekerjaan Biaya act + profit
50 m/menit
1.
0.83
2.
1 Hari
3.
SUB BASE
BP & O
Rp2,000,000
4.
+ 5.
+
Profit Pajak 15%
Rp8,980,865 Rp1,347,130
Q= Q' X E
Q'=
Q'=
Q'= 28333.33 m²/jam
Q= Q' X E E faktor ( good ) = 0.83
Q= 28333,3 x 0,83
Q= 23516.67 m²/jam
Luas Perataan = 72000 m²
Waktu Pelaksanaan = Luas
Q
= 72000
23516.67
= 3.06 jam
= 3.06 per unit
Waktu Pelaksanaan = 0.44 Hari ~ 1 Hari
=
=
=
= +
=
SUB BASE
Rp6,123,317
Profit 10 % Rp612,332
Biaya Aktual Rp6,735,648
Luasx BP & O
Q
72000x Rp2,000,000
23516.667
1000 . V . ( w - Wo )
n
85000
3
Biaya Aktual
= Rp
m²
= Rp
m²
HSP Pekerjaan = Rp/m²
= +
=
=
Rp6,735,648
Harga Penawaran Rp7,745,996
Rp94
Harga Penawaran Biaya Actual Profit
HSP Pekerjaan Biaya act + profit
Luas
Rp6,735,648
72000
1. Q= Q' X E
Q'=
Q'=
Q'= 28333.33 m²/jam
Q= Q' X E
Q= 28333,3 x 0,83
Q= 23516.67 m²/jam
2. Luas Perataan =
Waktu Pelaksanaan =
=
=
=
Waktu Pelaksanaan =
3. =
=
=
=
=
BASE COURSE
Profit 10 %
Biaya Aktual
1000 . V . ( w - Wo )
n
85000
3
Biaya AktualBP & O
Rp2,000,000
4. =
=
HSP Pekerjaan =
+ 5. =
+ =
=
Rp1,010,347
HSP Pekerjaan
Harga Penawaran
Harga Penawaran
Pajak 15%
E faktor ( good ) = 0.83
72000 m²
Luas
Q
72000
23516.67
3.06 jam
3.06 per unit
0.44 Hari ~ 1 Hari
+
Rp6,123,317
Rp612,332
Rp6,735,648
Luasx BP & O
Q
72000x Rp2,000,000
23516.667
Rp
m²
Rp
m²
Rp/m²
+ +
+
Rp7,745,996
Biaya Actual Profit Pajak 15%
Rp6,735,648 Rp1,010,347
Biaya act + profit
Luas
Rp6,735,648
72000
Rp94
Pajak 15%
Rp1,010,347
Diketahui : 1.
● Lebar roda (w) = 3 m
● Kecp. Rata2 = 2.5 km/jam =
● BP & O = Rp2,500,000 /jam
2.
● Tebal = 5 cm
Ditanyakan : 1.
2.
3.
4.
5.
6.
Dijawab : 1. Q = Q' X E
Q' = 60 X V X W
Q' = 60 X 41,67 X 3
Q' = 7500 m²/jam
Q = Q' X E E faktor ( good ) =
Q = 7500 X 0,83
Q = 6225 m²/jam
2. Luas Permukaan = 72000 m²
Waktu Pelaksanaan = Luas
Q
= 72000
6225.00
= 11.57 jam
= 11.57 per unit
Waktu Pelaksanaan = 1.65 Hari ~
3. =
=
=
= +
=
4. = Rp
m²
Biaya Aktual Rp31,807,229
HSP Pekerjaan Biaya act + profit
vol . Bank
72000x
6225.000
Rp28,915,663
Profit 10 % Rp2,891,566
Biaya penawaran dengan pajak 15%
Jadwal
Biaya Aktual Luasx
Q
Data Alat
Data Pekerjaan
Produksi alat dalam 1 jam ( Q )
Hitung waktu pelaksanaa
Biaya aktual apabila profit 10%
HSP pekerjaan
= Rp
m²
HSP Pekerjaan = m²
5. = +
=
=
Rp31,807,229
Harga Penawaran Rp36,578,313
72000
Rp442
Harga Penawaran Biaya Actual
Rp31,807,229
41.66667 m/menit
0.83
2 Hari
Rp2,500,000
BP & O
+
+Rp31,807,229 Rp4,771,084
Profit Pajak 15%
Pemancangan pada abutmen jembatan dengan data sebagai berikut
Diketahui : 1.
● Ukuran = 14 inchi x 14 inchi
● Panjang = 50 Ft
● Bj Beton = 150 Cuft/ton
● Jumlah 1 abutmen = 36 batang
● Berat Pondasi ( P ) = ton
● BP & O = 5,000,000Rp /jam
● Daya dukung pondasi = 40 ton
● Faktor keamanan = 1.2
2.
● Type Vulcan size 1 (SAS)
● Waktu setting = 10 menit
● BP & O = 5,000,000Rp /jam
● Berat Hammer (w) = 9700 lbs
● Tinggi Jatuh Hammer ( h ) = 36 inches
● Faktor Hammer (e) = 0.8
● Nilai Restritusi (k) = 0.25
Ditanyakan : 1. Apakah Hammer sudah memadai ? Jika tidak , tentukan hammer yang memadai .
2. Hitung waktu untuk memancang tiap batang !
3. Hitung untuk semua pek. Pemancangan .
4. Hitung biaya pek. Pemancangan .
5. Hitung HSP
6. Hitung biaya penawaran.
Ditanyakan :
→Energi yang dihasilkan hammer
E= e x w x h
E= 0,8 x 9700 x 36
E= 279360 inch-lb
→Energi yang hilang
● akibat pukulan (I)
I = e x w x h x p x 1 - k²
w + p
I = 0,8 x 9700 x 36 x 8166,67 x 1 - 0,25²
9700 + 8166,67
I = 119711.78 inch-lb
● akibat head tiang pancang (CL)
U = daya dukung pondasi x faktor keamanan
U = 240000 x 1,2
U = 288000
CL = U x C 1 C1 = tekanan izin sementara kepada kepala tiang dan cap
Data Tiang Pancang
Data Hammer
2 C1 = 0.01
CL = 288000 x 0,394
2
CL = 113385.83
2
CL = 56692.91
● akibat tiang pancang (PL)
PL = U x C 2 C2 = simpanan tiang akibat tekana izin sementara
2 C2 = 0.005
PL = 288000 x 0,197
2
PL = 56692.91
2.00
PL = 28346.46
● akibat ujung tiang pancang (SL)
SL = U x C 3 C3 = tekanan izin sementara
2 C3 = 0.003
SL = 288000 x 0,118
2
SL = 34015.75
2
SL = 17007.87
→Energi bersih yang dapat digunakan
US = e x w x h - I - CL - PL - SL
US = 279360 - 119711,78 -56692,91 - 28346,46 - 17007,87
1. US = 57600.98 hammer memadai
S = US / U
S = 57600,98 / 288000
S = 0.200 inchi
S = 0.0051 meter
T = Le Le = 2/3 dari L
S x V xFo Le = 33.33
T = 10.16 Le = 10.16
0,0051 x 60 x 0,83 V = 60
T = 40.16 Menit Fo = 0.83
2. →Waktu yang dibutuhkan untuk memancang 1 tiang pancang adalah =
3. →Waktu yang dibutuhkan untuk memancang semua tiang pancang adalah =
4. waktu pek. Pemancangan X BP&O
= 30,10 jam X Rp. 5.000.000/jam
Biaya pemancangan =
150,479,886.44Rp =
Profit 10% = +
5. = Rp
m²
= Rp
m²
HSP Pekerjaan = /batang
6. = +
=
=
Rp165,527,875
Harga Penawaran Rp190,357,056
Jumlah tiang pancang
Rp165,527,875
36
Rp4,597,997
Harga Penawaran Biaya Actual
15,047,988.64Rp
Biaya pemancangan = 165,527,875.09Rp
HSP Pekerjaan Biaya act + profit
=
= 8166.67 lb
= 240000 lb
Apakah Hammer sudah memadai ? Jika tidak , tentukan hammer yang memadai .
tekanan izin sementara kepada kepala tiang dan cap
m 0.394 Inchi
simpanan tiang akibat tekana izin sementara
m 0.197 Inchi
tekanan izin sementara
m 0.118 Inchi
ft
meter
50.16 menit
30.10 jam
+
+
Profit Pajak 15%
Rp165,527,875 Rp24,829,181
ITEM NUMBER : Sta. 0+000 s/d 20+000
UNIT OF WORK : Cu.m
QUANTITY OF WORK :
DAILY/HOURLY OUTPUT :
NO. DESCRIPTION UNIT ALAT QUANTITY UNIT
A. Pekerjaan Badan Jalan (Subgrade)
A.1 Penggalian Badan Jalan
Buldozer 11 172,800 M3
A.2 Pengangkutan Galian
Wheel Loader 5 138,240 M3
Dump Truck 10 138,240 M3
A.3 Pemadatan Badan Jalan
Tandem Roller 1 72,000 M3
A.4 Perapian Badan Jalan
Motor Grader 1 72,000 M2
B. Pekerjaan Tebing
B.1 Penggalian Tebing
Excavator PC 200 1 22,350 M3
Sub Total = (A + B )
Overhead and Profit
TOTAL Before Tax
Tax
TOTAL
UNIT PRICE ANALYSIS
Sub Total
Sub Total
Q BP & O Real Cost Durasi
( m3/hour) (Rp/hour) (Rp/m3) hari
134.95 2,952,000 240,625.00 20.0
141.60 1,250,000 44,139.41 33.5
77.93 262,500 33,683.74 30.4
17,637.50 2,000,000 113.39 0.7
1,344.60 2,200,000 1,636.17 9.2
320,197.71
186.25 1,200,000 6,442.88 0.7
6,442.88
326,640.60
% Profit = 15% 48,996.09
375,636.69
% Tax = 15% 56,345.50
431,982.19
UNIT PRICE ANALYSIS