PROGRESS LAPANGAN Minggu :Tanggal :
Type 60/105
Blok / Nomor : B21
Mandor TAYO
Jenis Item Pekerjaan Volume Satuan Bobot
A Pekerjaaan Pondasi
1 Bowplank 60 Type 150,000 1.43% 100
2 Galian 4.68 m3 180,000 1.72% 100
3 Pondasi Batu kali 4.68 m3 500,000 4.78% 100
4 Cor sloof 42.5 m' 350,000 3.34% 100
5 Pasang Paralon 3" 12 m' 100,000 0.96% 100
6 Galian Septictank 1 ls 110,000 1.05% 100
7 Urugan elevasi lantai 9.375 m3 120,000 1.15%
B Pekerjaan Dinding 0.00%
1 Dinding Bata 128.65 m2 1,800,000 17.20% 100
2 Kusen + Daun Pintu,Jendela 11.79 m2 300,000 2.87% 100
3 Plesteran + Acian Dinding 187.71 m2 1,885,000 18.01% 100
4 Cor Kolom Praktis 30 m' 200,000 1.91% 100
5 Cor Ring Balk 42.5 m' 250,000 2.39% 100
7 Rooster 1 ls 100,000 0.96% 100
8 Dinding Bata Ampig 11.05 m2 300,000 2.87%
9 Cor Topi Panel 0.1 m3 150,000 1.43% 100
C Pekerjaan Kayu 0.00%
1 Gording 6/12 32 m' 0.00%
2 Usuk / reng 2/3 58 m2 0.00%
3 Pasang Genteng Morando 58 m2 300,000 2.87%
4 Nok / Karpusan 6 m' 100,000 0.96%
5 Pasang ListPlank 2/20 20 m' 100,000 0.96%
6 Ban-banan Atap Pembatas 20 m' 100,000 0.96%
7 Pasang Rangka Plafond 54 m2 205,000 1.96%
8 Pasang Plafond Enthernit 54 m2 205,000 1.96%
D Pekerjaaan Pintu & Jendela 0.00%
1 Pasang Engsel Jendela 5 Bh 85,000 0.81%
2 Pasang Engsel Pintu & Kunci 5 Bh 150,000 1.43%
3 Pasang Slot 5 Bh 25,000 0.24%
4 Pasang Hak angin 5 Bh 25,000 0.24%
E Keramik 0.00%
1 Keramik Lantai 40x40 60 m2 700,000 6.69%
2 Keramik Dinding 20x25 6 m2 150,000 1.43%
3 Keramik Lantai Kamar Mandi 2.5 m2 70,000 0.67%
4 Bak mandi Tempel 1 Bh 50,000 0.48%
5 Closed 1 Bh 50,000 0.48%
No.
Pembulatan Kontrak
171.500,-
Prestasi lapangan
6 Pintu Kamar Mandi 1 Bh 70,000 0.67%
7 Saringan Air 1 Bh 10,000 0.10%
8 Intalasi Air Bersih 4 m' 100,000 0.96%
F Pekerjaan Lain - lain 0.00%
1 Carport 5 m' 150,000 1.43%
2 Pemberesan 1 Bh 70,000 0.67%
G Pekerjaan Tambahan 0.00%
1 Canopi Enterance + Topi -topi 1 ls 750,000 7.17% 75
2 Plesteran + Acian Dinding 1 ls 175,000 1.67% 50
4 Pembesian ( Rp. 5500 X 60 M2 ) 1 ls 330,000 3.15% 100
NILAI KONTRAK 10,465,000 100.00%
Jumlah :
Retensi Pekerjaan ( 100 Hari ) = 5% -
Jumlah Tagihan Progrees Pekerjaan Minggu ini
Jumlah Tagihan Progrees Pekerjaan Minggu lalu
Total Tagihan Progrees Pekerjaan Minggu ini
Bobot minggu lalu =
Diajukan : Bobot minggu ini =
Bobot aktual =
150,000
180,000
500,000
350,000
100,000
110,000
-
1,800,000
300,000
1,885,000
200,000
250,000
100,000
-
150,000
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Jumlah ( Rp )
-
-
-
-
-
562,500
87,500
330,000
7,055,000
352,750
6,702,250
5,784,075
918,175
55.27
64.04
8.77
174,417
PROGRESS LAPANGAN Minggu :Tanggal :
Type 60/105
Blok / Nomor : B32
Mandor TAYO
No. Jenis Item Pekerjaan Volume Satuan Bobot
A Pekerjaaan Pondasi
1 Bowplank 60 Type 150,000 1.43%
2 Galian 4.68 m3 180,000 1.72%
3 Pondasi Batu kali 4.68 m3 500,000 4.78%
4 Cor sloof 42.5 m' 350,000 3.34%
5 Pasang Paralon 3" 12 m' 100,000 0.96%
6 Galian Septictank 1 ls 110,000 1.05%
7 Urugan elevasi lantai 9.375 m3 120,000 1.15%
B Pekerjaan Dinding 0.00%
1 Dinding Bata 128.65 m2 1,800,000 17.20%
2 Kusen + Daun Pintu,Jendela 11.79 m2 300,000 2.87%
3 Plesteran + Acian Dinding 187.71 m2 1,885,000 18.01%
4 Cor Kolom Praktis 30 m' 200,000 1.91%
5 Cor Ring Balk 42.5 m' 250,000 2.39%
7 Rooster 1 ls 100,000 0.96%
8 Dinding Bata Ampig 11.05 m2 300,000 2.87%
9 Cor Topi Panel 0.1 m3 150,000 1.43%
C Pekerjaan Kayu 0.00%
1 Gording 6/12 32 m' 0.00%
2 Usuk / reng 2/3 58 m2 0.00%
3 Pasang Genteng Morando 58 m2 300,000 2.87%
4 Nok / Karpusan 6 m' 100,000 0.96%
5 Pasang ListPlank 2/20 20 m' 100,000 0.96%
6 Ban-banan Atap Pembatas 20 m' 100,000 0.96%
7 Pasang Rangka Plafond 54 m2 205,000 1.96%
8 Pasang Plafond Enthernit 54 m2 205,000 1.96%
D Pekerjaaan Pintu & Jendela 0.00%
1 Pasang Engsel Jendela 5 Bh 85,000 0.81%
2 Pasang Engsel Pintu & Kunci 5 Bh 150,000 1.43%
3 Pasang Slot 5 Bh 25,000 0.24%
4 Pasang Hak angin 5 Bh 25,000 0.24%
E Keramik 0.00%
1 Keramik Lantai 40x40 60 m2 700,000 6.69%
2 Keramik Dinding 20x25 6 m2 150,000 1.43%
3 Keramik Lantai Kamar Mandi 2.5 m2 70,000 0.67%
4 Bak mandi Tempel 1 Bh 50,000 0.48%
5 Closed 1 Bh 50,000 0.48%
6 Pintu Kamar Mandi 1 Bh 70,000 0.67%
7 Saringan Air 1 Bh 10,000 0.10%
8 Intalasi Air Bersih 4 m' 100,000 0.96%
F Pekerjaan Lain - lain 0.00%
Pembulatan Kontrak
171.500,-
1 Carport 5 m' 150,000 1.43%
2 Pemberesan 1 Bh 70,000 0.67%
G Pekerjaan Tambahan 0.00%
1 Canopi Enterance + Topi -topi 1 ls 750,000 7.17%
2 Plesteran + Acian Dinding 1 ls 175,000 1.67%
4 Pembesian ( Rp. 5500 X 60 M2 ) 1 ls 330,000 3.15%
NILAI KONTRAK 10,465,000 100.00%
Retensi Pekerjaan ( 100 Hari ) = 5% -
Jumlah Tagihan Progrees Pekerjaan Minggu ini
Jumlah Tagihan Progrees Pekerjaan Minggu lalu
Total Tagihan Progrees Pekerjaan Minggu ini
Bobot minggu lalu =
Diajukan : Bobot minggu ini =
Bobot aktual =
100 150,000
100 180,000
100 500,000
100 350,000
100 100,000
-
-
100 1,800,000
100 300,000
100 1,885,000
100 200,000
100 250,000
100 100,000
-
100 150,000
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Prestasi lapangan
Jumlah
( Rp )
-
-
75 562,500
50 87,500
75 247,500
Jumlah : 6,862,500
343,125
###
###
###
Bobot minggu lalu = 49.77
Bobot minggu ini = 62.30
Bobot aktual = 12.53
REKAPAN PROGRESS DAN UPAH MANDORMinggu Ke : VITanggal : PT. Persada Bumi Kencana
No Jenis Kontrak Total Tagihan Pembayaran s/d hari ini Pembayaran Minggu ini
1 TAYO1 Rumah B21 10,465,000 8.77 55.27 64.04 7,055,000 352,750 5,784,075 6,702,250 918,175 2 Rumah B32 10,465,000 12.53 49.77 62.30 6,862,500 343,125 5,208,375 6,519,375 1,311,000
2,229,175
Rp 2,229,175
Cikunir, 06 Oktober 2011di Periksa Di Setujui Di Ajukan
Ujang C Mursidi AGUS
Nilai Kontrak
(Rp)
Bobot Aktual %
Bobot s.d minggu lalu
Bobot s.d minggu ini
Retensi 5%
Pembayaran s\d Minggu
lalu