alat tambahan pada wind turbin

Upload: erwin-bondan

Post on 02-Jun-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 alat tambahan pada Wind Turbin

    1/10

    General study of the control principles and dynamic fault behaviour of

    variable-speed wind turbine and wind farm generic models

    Tareq Saber Abuaisha*

    Institute for Electrical Power Supply with Integration of Renewable Energies, Technische Universitt Darmstadt, Landgraf-Georg-Strae 4, 64283 Darmstadt,

    Germany

    a r t i c l e i n f o

    Article history:

    Received 9 July 2013

    Accepted 9 January 2014

    Available online 28 February 2014

    Keywords:

    Generic model

    Doubly-fed induction generator

    Fully-rated converter

    Wind turbine

    Wind farm

    Synchronous induction machine

    a b s t r a c t

    The interest towards generic models or sometimes also called standard models of wind turbine gener-

    ators (WTGs) is signicantly increasing. Mainly due to their improved power quality, better controlla-

    bility and higher power extraction capability, variable-speed wind turbines driving a synchronous or an

    induction machine are capturing the global market. Throughout this paper, dynamic modelling and

    performance analysis of the generic models of the variable-speed W TGs, namely the doubly-fed in-

    duction generator and the fully-rated converter based WTGs, are achieved using integration between

    Matlab/Simulink and PSCAD/EMTDC simulation platforms. Later on, the performance of type-4 wind

    turbine driving a permanent magnet synchronous machine is analysed during fault and then compared

    with the case when driving a wound rotor induction machine. The differences in control principles and

    dynamic fault behaviour are highlighted. Afterwards, investigations on wind farm level are accom-

    plished. A case study during which the developed generic models and the generic model of the variable-

    speed machine are compared is conducted. Different arrangements for the construction of the generic

    wind farm are considered.

    2014 Elsevier Ltd. All rights reserved.

    1. Introduction

    With a signicant 20% renewable energy power share (including

    wind energy, hydro-power, photo-voltaics and others), today Ger-

    manyis already well on the way tomeeting the 2020 targetof a 35%

    renewable energy share. Sharing by 40% of all renewable energy

    sources, wind is already the dominant driver of renewable electric

    power generation and will be the motor for future growth [1].

    In fact the study of a large system such as the European network

    involves the simulation of many interconnected systems, which are

    operated by many different transmission and distribution system

    operators, and comprise wind turbines and wind farms from

    multiple manufacturers and technologies.This variety of wind turbine manufacturers existing in the global

    market would inevitably result in different manufacturer-specic

    wind turbine generator (WTG) models based on different ap-

    proaches and technologies. These differences would naturally

    result in different complexity and thus accuracy of the respective

    models. Additionally, access to these models requires a non-

    disclosure agreement between the dynamic model user and the

    turbine manufacturer[2].

    In response to these challenges, western electricity coordinating

    council (WE-CC) has initiated the development of generic positive

    sequence WTG dynamic models which are suitable for grid plan-

    ning studies[3]. A generic model refers to a non-proprietary dy-

    namic model that can be used to represent wind turbine generators

    (WTGs) with similar physical and control topology, using only

    different parametrization to represent a specic vendor equipment

    [3,4].

    Compared to xed-speed WTGs, doubly-fed induction gener-

    ator (DFIG) and fully rated converter (FRC) wind turbine generators

    are ultimately dominating the global market due to their higherenergy efciency, exible performance, higher power extraction

    capability and better controllability[5,6].

    In order todene the intended use and limitations and to insure

    a healthy development of the generic models; further research,

    investigation and improvement are highly recommended.

    In this paper, a general study on wind turbine and wind farm

    generic models is achieved. Atrst, the three-phase generic models

    of type-3 (DFIG) and type-4 (FRC) are implemented and simulated.

    In order to analyse the dynamic behaviour of the generic models, a

    balanced three-phase fault at the wind turbine generator terminal

    is enforced. The simulation results are then compared with

    * Tel.: 49 (0)176 32262014.

    E-mail addresses: [email protected],eng_abumosab@hotmail.

    com.

    Contents lists available atScienceDirect

    Renewable Energy

    j o u r n a l h o m e p a g e : w w w . e l s e v i e r . c o m/ l o c a t e / r e n e n e

    http://dx.doi.org/10.1016/j.renene.2014.01.004

    0960-1481/

    2014 Elsevier Ltd. All rights reserved.

    Renewable Energy 68 (2014) 245e254

    mailto:[email protected]:[email protected]:[email protected]://www.sciencedirect.com/science/journal/09601481http://www.elsevier.com/locate/renenehttp://dx.doi.org/10.1016/j.renene.2014.01.004http://dx.doi.org/10.1016/j.renene.2014.01.004http://dx.doi.org/10.1016/j.renene.2014.01.004http://dx.doi.org/10.1016/j.renene.2014.01.004http://dx.doi.org/10.1016/j.renene.2014.01.004http://dx.doi.org/10.1016/j.renene.2014.01.004http://www.elsevier.com/locate/renenehttp://www.sciencedirect.com/science/journal/09601481http://crossmark.crossref.org/dialog/?doi=10.1016/j.renene.2014.01.004&domain=pdfmailto:[email protected]:[email protected]:[email protected]
  • 8/10/2019 alat tambahan pada Wind Turbin

    2/10

    manufacturer-specic models in order to analyse the physical

    behaviour and characteristics. Later on, the implemented models

    were added to the Matlab/Simulink library to serve as basis for

    future research and development.

    Afterwards, the performance of type-4 wind turbine when it is

    driving a permanent magnet synchronous machine (PMSM) is

    investigated during fault and compared with the case when it is

    driving a wound rotor induction machine (WRIM). The differences

    in control principles and dynamic fault behaviour are highlighted.

    To show resemblance to other research efforts which are con-

    ducted in this eld; a comparison between two different wind

    farms is conducted in a case study. While the rst wind farm

    consists of four wind turbines which are based on the implemented

    generic models, the second wind farm is based on the generic

    model of the variable-speed machine which is implemented in

    Refs.[7,8]. Different arrangements for the construction of the rst

    wind farm from generic wind turbine generators are considered.

    2. Power control strategies in variable-speed WTGs

    There are primarily two ways to control the power generated by

    variable-speed WTGs. The rst is the aerodynamic power control

    either by controlling the wind turbine blades or by yawing the

    complete nacelle, and the second is the electrical power control

    employed in the power electronics converters[9].

    The use of these two control strategies enables on one hand the

    extraction of maximum wind power during low wind speeds and

    on the other hand, the reduction of the mechanical stress on the

    shafts during high wind speeds[10,11].

    2.1. Aerodynamic power control

    The power extracted fromthe wind varies with the cube of wind

    speed, but the wind turbine can only extract a fraction of this

    amount which is given in Ref.[12]by

    P 1

    2rAv3wCpl;bW; (1)

    Wind turbines cannot extract all the kinetic energy from the

    wind, and the maximum extracted energy occurs with Cp 0.59,

    and is termed as Betz limit [12]. In practice, this powercoefcient is

    less than this value and also varies with the tip speed ratio l as

    shown inFig. 1.

    The idea of the aerodynamic power control is to achieve

    maximum power tracking. In order to accomplish this task, the

    turbine must operate at the peak ofCp/lcurve for all relevant wind

    speed values. This curve is unique to a particular design of wind

    turbine and thus it is given by the wind turbine manufacturer[13].

    Fig. 1shows a typical Cp/l curve. Since Pmax occurs at Cp,max, the

    wind turbine should follow the dashed curve to choose themaximum power coefcient valueCp,maxfor all relevant operating

    wind turbine speeds.

    Currently, pitch control is the most widely used control option

    especially for multi-megawatt WTGs. Almost all variable-speed

    wind turbine generation technologies use pitch control. When

    wind speed is below the rated speed, it is used to maximize the

    energy capture. And when it is above the rated speed, it is used to

    reduce the mechanical stress on the gearbox and the shafts[10,11].

    2.2. Electrical power control

    Fig. 2 shows the per-unit mechanical output power versus speed

    characteristics also in per-unit of a WTG for different wind speeds

    and zero pitch angle. The dashed-dotted black curve is termed as

    optimal tracking curve; which is the total amount of power exists in

    the wind. Whilst, the dashed green (in web version) curve is known

    as real tracking curve which is the real power extracted from the

    wind by the wind turbine.

    Fig. 2 compares between the real and the optimal power

    tracking, where the green (in web version) points on the curve

    represent the following[14]:

    e u1 is the minimum wind speed at which thewind turbine comes

    into operation (typically between 3 and 4 m/s)

    e uris the speed at which the wind turbine will produce its rated

    output power

    e u2is the maximum operating wind speed

    As stated in equation(1), at wind speeds above the cut-in speed

    and till the rated wind speed is reached, the wind turbine output

    Fig. 1. Power coefcientCpas a function of tip-speed ratio l for different blade pitchanglesb.

    Fig. 2. Turbine speed [p.u] versus the turbine output power [p.u] at different wind

    speeds and zero pitch angle b.

    T.S. Abuaisha / Renewable Energy 68 (2014) 245e254246

  • 8/10/2019 alat tambahan pada Wind Turbin

    3/10

    power increases due to a cubic relationship with wind speed.

    Moreover, the green (in web version) curve inFig. 2clearly shows

    the link between variable-speed operation (and thus speed control)

    and the amount of power that can be extracted from the wind.

    3. Modelling and simulation of variable-speed WTGs

    Fig. 3shows the dynamic model structure of type-3 and type-4WTGs including the individual subsystems together with the

    commands in between, as rstly described by WECC[2,4].

    The generic dynamic models are represented by a specic

    number of interactions among different subsystems to achieve the

    functionality of a typical WTG. This functionality should include the

    independent control of active (torque) and reactive power and the

    control of generator speed and blade pitch angles, in order to

    achieve maximum wind power extraction[4].

    These generic models are suitable for representing individual

    WTGs or the equivalent of a wind power plant where the wind

    speed is assumed to remain constant during the simulation time

    frame[15].

    3.1. Proposed generator/converter subsystem

    To show an example on the implemented modelling of variable-

    speed generic models, the proposed generator/converter subsys-

    tem is comprehensively described in Fig. 4. The physical concepts

    behind the proposed subsystem are presented in Section 4,along

    with the modelling and simulation of wind farms.

    Ref.[16] proved that the generator dynamics and power elec-

    tronics can be emulated by a regulated current source. In this paper,

    the proposed subsystem is represented by a regulated current

    source which injects proportional three-phase currents (Iaref, Ibrefand Icref) into the power system based on the control commands

    (Ipcmd& Eqcmd) from the converter control subsystem.

    Thereafter, it gives both the measured active and reactive power

    (Pgen & Qgen) to the converter control subsystem as feedback and

    also the measured active power (Pgen) to the wind turbine sub-

    system.

    As shown in Fig. 4, the desired instantaneous active and reactive

    power (Pgen & Qgen) are calculated using equations(2) and (3) as

    stated in Refs. [12,16], and then fed into the corresponding sub-

    systems.Fig. 5shows the instantaneous active and reactive power

    measured at the WTG terminal when the input voltage falls to 50%

    from its rated value. It is also seen that due to the voltage dip, the

    active power has also dropped to a comparable value. Additionally,

    the reactive powerhas increased to support the voltage as required.

    Pt 3

    2,

    Vdt Idt Vqt Iqt

    MW (2)

    Qt 3

    2,

    VqtIdtVdtIqt

    Mvar (3)

    The functions of the subsystems of type-4 generic model are

    almost identical to those of type-3[7]. However, the wind turbine

    subsystem of type-4 WTG employs a simplied mechanical model.This is mainly due tothe fact, that in type-4 generic model the fully-

    rated converter completely decouples both the generator transients

    and grid faults from affecting each other and thus smoother

    connection to the grid is enabled[7,8].

    The proposed generator/converter subsystem along with all the

    other subsystems are implemented and simulated in Matlab/

    Simulink based on the parameters provided by WECC and general

    electric (GE) for type-3 and type-4 generic models [4,15,17]. In the

    following subsection, the control strategies followed in the voltage

    source converters of the generic models are explained. The FRC-

    based wind turbine is chosen as a case study.

    3.2. Control strategies of voltage source converters in type-4 genericmodel

    The typical structure of a fully rated converter WTG as imple-

    mented in PSCAD/EMTDC is depicted in Fig. 6. It consists of a

    generator, two pulse width modulated (PWM) voltage source

    converters (VSC) with a back-to-back DC link, wind turbine and a

    control system. The inductor L is used to couple the grid-side VSC

    with the grid.

    The generatorcan have a woundeld, wound rotor synchronous

    generator (WRSG) or can use permanent magnets, permanent

    magnet synchronous generator (PMSG) to provide the rotating

    magneticeld. Or it can even be an induction generator. A purpose

    of thisresearch work is to compare between the performance of the

    synchronous and induction machines in terms of control principles

    and dynamic fault analysis.

    When a WRSG is employed, the required DC excitation can be

    taken from the DC link. However, one attraction of the PMSM is its

    high efciency since no magnetizing or eld current is necessary to

    provide the magnetic eld. The control system shown in Fig. 6is

    used to insure the desired functionality of the FRC-based wind

    turbine as follows:

    Pitch angle (b) command is used to insure maximum wind

    power extraction by the turbine blades. Since the wind speed is

    Fig. 3. Dynamic model structure for variable-speed wind turbine generator technologies [4].

    T.S. Abuaisha / Renewable Energy 68 (2014) 245e254 247

  • 8/10/2019 alat tambahan pada Wind Turbin

    4/10

    Fig. 4. Detailed description of the proposed generator/converter subsystem for variable-speed generic models.

    0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8-1

    -0.5

    0

    0.5

    1

    1.5

    time [sec]

    Active&R

    eactivePower[pu]

    PgenQgen

    (a) Instantaneous active and reactive power measured

    at type-3 WTG terminal

    0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8-1

    -0.5

    0

    0.5

    1

    1.5

    time [sec]Active&R

    eactivepower[pu]

    PgenQgen

    (b) Instantaneous active and reactive power measured

    at type-4 WTG terminal

    Fig. 5. Instantaneous active and reactive power (Pgen& Qgen) measured at WTG terminal during a 50% voltage dip.

    T.S. Abuaisha / Renewable Energy 68 (2014) 245e254248

  • 8/10/2019 alat tambahan pada Wind Turbin

    5/10

    assumed to be constant during the simulation time frame, this

    command was not implemented.

    Voltage signal (Vrc) command is intended to control the rotor-

    side VSC. Voltage signal (Vgc) command is intended to control the grid-

    side VSC.

    The role of these two signals in controlling the VSCs depends on

    the type of the employed machine i.e. synchronous or induction

    machine as will be shown later.

    The variable magnitude, variable frequency output voltage of

    the generator (Vr) is converted to a xed magnitude, xed fre-

    quency voltage (Vs) by the fully-rated converter consisting of a

    rotor-side VSC, a grid-side VSC and a DC link capacitor. Both con-

    verters are designed to handle the full rated power of the wind

    turbine. The proposed control strategy is achieved through con-

    trolling the modulation indices (Mg and Mr) of the PWM using

    equation(4).

    Mg kg,

    Vgabc

    Vdc

    !;

    Mr kr,Vrabc

    Vdc

    !;

    (4)

    whereMg and Mrare the modulation indices of the grid and ma-

    chine side converters respectively;kgandkr are the proportionality

    constants.

    The above explained strategy is shown in Fig. 7. In order to

    highlight the differences in control principles and dynamic fault

    behaviour, a balanced three-phase to ground fault was caused atthe low voltage side of the transformer. Afterwards, the perfor-

    mance of the FRC wind turbine driving a PMSM is analysed during

    fault and then compared with the case when driving a WRIM.

    Fig. 8 shows the simulation results of the FRC wind turbine

    when it is driving a PMSM compared with the case when it is

    driving a WRIM. Note that the fault duration is relatively high and it

    is not in accordance with most grid codes. This is because the goalof this research is to highlight different machine control principles;

    it is not in any case to test the low voltage ride through (LVRT)

    capability of the wind turbine generator.

    Due to the three-phase balanced fault, the voltage falls down

    and the current rises up for both machines. This can be seen in

    Fig. 8a and b respectively.

    As a result to increased rotor currents, the DC-link voltage tends

    to increase (see magnied parts ofFig. 8a). Thus, the grid side VSC

    will try to balance the DC-link voltage by forcing it to decrease

    again, hence the reactive power will increase negative increase or

    capacitive effect. This control action can be clearly realized in

    Fig. 8c. However due to the additional reactive power requirement

    of the induction machine, the reactive power and in accordance the

    active power curves tend to oscillate. This effect is shown in theright hand side ofFig. 8c.

    Moreover, the machine side converter in the PMSM will control

    the active and reactive power by forcing them to stabilize at their

    reference values. This control action is obvious in left hand side of

    Fig. 8d. In comparison, the WRIM absorbs reactive power

    depending on its characteristics and operating point. Thus when a

    reactive power control that does not match the machine require-

    ment is forced, the machine can enter an unstable situation.

    Due to this fact, for the case of WRIM topology the machine side

    VSCcannot perform control on reactive power, as a result the active

    and reactive power at the machine terminal will not stabilize at

    their reference values during the fault as seen in the right hand side

    ofFig. 8, which is not the case for the PMSM shown in the left hand

    side.The simulation results proved that when a WRIM is employed,

    in this case the machine side VSC cannot perform control on

    reactive power otherwise the machine can go unstable. Whereas

    Fig. 6. Detailed structure of an FRC-based wind turbine as implemented in PSCAD/EMTDC.

    Fig. 7. Calculation of the modulation indices in FRC-WTG generic model as implemented in PSCAD/EMTDC.

    T.S. Abuaisha / Renewable Energy 68 (2014) 245e254 249

  • 8/10/2019 alat tambahan pada Wind Turbin

    6/10

    reactive power control, and thus an indirect voltage control, on

    machine side VSC is possible for the FRC wind turbine driving a

    PMSM. Note that the control principles applied on the case of FRC

    wind turbine driving a WRIM, will be also followed for the case of

    DFIG driving an induction machine.

    4. Modelling and simulation of variable-speed wind farms

    Typical wind farms may consist of tens to hundreds of identical

    wind turbines. As a consequence, representing a wind farm withindividual wind turbines for power system stability studies in-

    creases the complexity of the model and requires time consuming

    simulations. With this background, aggregated representation of

    wind farms is essential.

    4.1. Case study: aggregated model of a wind farm

    Ref. [7] proposed a generic model of the variable-speed ma-

    chine. This aggregated model was built based on a third order

    quasi-sinusoidal model. The quasi steady-state (QSS) model can be

    derived from the full order model by assuming that the transformer

    voltage in the stator winding can be neglected against the much

    greater speed voltage, as shown in equation(5).

    jusJs[

    dJs

    dt

    (5)Based on this assumption and solving for the original equations

    of the full order model, equations (6) and (7)will be obtained for

    the quasi stationary model.

    Stator voltage equation:

    (6)

    Rotor ux equation:

    dJrdt

    RrLr

    jusur

    Jr kRRris vr (7)

    where:

    L0 LsL2m

    Lr

    kr Lm

    Lr

    Fig. 8. Control principles of an FRC wind turbine driving a PMSM (left hand side) compared with the case when driving a WRIM (right hand side) during a balanced three-phase

    fault and constant wind speed.

    T.S. Abuaisha / Renewable Energy 68 (2014) 245e254250

  • 8/10/2019 alat tambahan pada Wind Turbin

    7/10

    As shown in the phase estimation channel ofFig. 4, in the pro-

    posed generator/converter model the stator ux angle is calculated

    using equation(8).

    8>>>>>>>>>>>>>:

    Jsa

    Z vsaRsisadt

    ; qf tan1Jsb

    Jsa

    Jsb

    ZvsbRsisb

    dt

    (8)

    The above two equations along with the equation of motion

    constitute the third order model. Equation(7) can be rewritten in

    dq reference frame to generate the direct and quadrature compo-

    nents in equations(9) and (10) respectively.

    dJrddt

    RrLr

    us urJrqkRRrisd vrd (9)

    dJrqdt

    RrLr

    usurJrdkRRrisq vrq (10)

    Equations(9) and (10)are used in the machine side converter tocontrol the voltage and torque (active power) of the machine. The

    DC-link voltage is assumed to remain constant around its rated

    value, and thus the grid side converter is not considered explicitly

    in the quasi stationary model.

    Simplifying the quasi stationary model will generate the

    aggregated model of the variable-speed machine shown in Fig. 9.

    This is a representation of the core control functions, but for a

    complete implementation the required key elements have to be

    added. The complete generic model of a variable-speed machine

    along with all the employed key elements is shown inFig. 10.

    The model as a whole (both with and without the inclusion of

    the detailed model) constitutes the simplied model. The only

    difference between the two options (including or excluding the

    detailed model) is the level of simplication which one may chooseto adopt for a particular simulation. The generic model of the var-

    iable speed machine shown inFig. 10operates as follows:

    The reference values Uref, Pref& Qref are usually being deter-

    mined from load-ow initialization. Though, they can be set to

    empirical values based on experience.

    The voltage channel will increase or decrease the reactive power

    in-feed whenever the voltage exits a dead-band of 10% above or

    below the rated value.

    The reactive power channel will determine the desired current

    command iQ,ref [p.u], while the active power channel will

    determine the desired current command iP,ref[p.u].

    Thereafter, reactive power priority is applied. Mainly, because

    the generic model is designed to analyse fault situations.

    After that, the user e or more appropriately the system operator

    e chooses whether to include or exclude the generic model.

    Based on that choice, the desired active and reactive power Q(t)

    &P(t)will be calculated.

    The generic model of the variable-speed machine is imple-

    mentedusing Matlab/Simulink. A graphical user interface (GUI) has

    been designed to control the whole operation dynamically during

    simulation. The GUI will assign the values ofUref, Pref& Qref based

    on the operators choice. It also gives the operator the ability to

    include or exclude the detailed model and then determines the

    initial conditions required and feeds them into the corresponding

    transfer functions and integrators.

    4.2. Variable-speed generic wind farm model

    The proposed wind farm consists of four WTGs. Each of these

    WTGs has a capacity of 1.5 MW and thus the whole wind farm

    capacity is 6 MW. This wind farm will be built based on the generic

    models of type-3 and type-4 WTGs developed in Section3.

    All the different possible arrangements are studied, in the rstarrangement all the four WTGs are FRC-based. In the second

    arrangement they are assumed to be DFIG-based. Whereas in the

    last arrangement, two WTGs are DFIG-based and the other two are

    FRC-based.

    The generic models of wind turbines will be employed to

    represent the four individual wind turbines within the wind farm.

    Then the resulted wind farm will be simulated and the results will

    be compared with that of the aggregated wind farm developed in

    Section4.1.

    The implemented wind farm in Matlab/Simulink is depicted in

    Fig. 11while the comparison results are shown inFig.12. The input

    voltage is subjected to 50% voltage dip due to a balanced three-

    phase fault.

    As shown in Fig. 12, the active power dip is deeper in theaggregated model, and the reactive powersupport is higheras well.

    One conrmed reason for this fact is that the two models apply

    different approaches on the provision of reactive power support

    during the voltage dip.

    In the aggregated wind farm model, the proportional gain factor

    between voltage and reactive power (K) is considered (refer to

    Fig. 10). While, in the detailed model the proportional gain is not

    considered and thus reactive power support will not be propor-

    tional to the voltage dip[19].

    The results of the comparison representa comparablebehaviour

    between the aggregated and the generic wind farm models. But

    specically, the smooth behaviour of the aggregated wind farm

    model is better matched with the constellation of four FRC-based

    machines than other constellations, this is because the FRC de-couples the generator transients to yield a smoother response.

    5. Conclusions

    Doubly fed induction generator (DFIG) and fully rated converter

    (FRC) wind turbine generators offer many advantages over thexed

    speed technology including exible performance and better

    controllability. In this paper, the three-phase dynamic generic

    models of type-3 (DFIG) and type-4 (FRC) have been implemented

    and simulated.

    The performance of the FRC wind turbine driving a permanent

    magnet synchronous machine (PMSM) is analysed during fault and

    then compared with the case when it is driving a wound rotor in-

    duction machine (WRIM). Different control strategies in the voltage

    Fig. 9. Core of the aggregated generator model of machine and current control

    (reproduced from Ref. [5]).

    T.S. Abuaisha / Renewable Energy 68 (2014) 245e254 251

  • 8/10/2019 alat tambahan pada Wind Turbin

    8/10

    source converters (VSCs) for the two mentioned topologies should

    be applied.

    The simulation results proved that when a WRIM is employed,

    in this case the machine side VSC cannot perform control on

    reactive power otherwise the machine can go unstable. Whereas

    reactive power control, and thus an indirect voltage control, on

    machine side VSC is possible for the FRC wind turbine driving a

    PMSM.

    Afterwards, a generic wind farm model consists of four wind

    turbine generators (WTGs) is implemented and simulated. In order

    to show resemblance to other research efforts which are conducted

    in this eld, the simulation results are then compared with that of

    the aggregated model of the variable speed machine implemented

    in Ref.[7].

    The detailed model represents a better match to the real phys-

    ical behaviour of the machine, however, the increased complexity

    Fig. 10. Quasi steady-state generic model of the variable speed machine (reproduced from Ref. [18]).

    Fig. 11. Generic Matlab/Simulink model of a wind farm consisting of four WTGs (1.5 MW each).

    T.S. Abuaisha / Renewable Energy 68 (2014) 245e254252

  • 8/10/2019 alat tambahan pada Wind Turbin

    9/10

    will inevitably demand greater modelling efforts and larger simu-

    lation time. Apart from that, the simulation results showed that a

    comparable behaviour between the aggregated and the generic

    wind farm model can be obtained.

    Acknowledgements

    The authors would like to thank Manitoba HVDC ResearchCenter for the technical conversations and the exchange of ideas.

    They are also grateful to the anonymous reviewers for their valu-

    able comments and suggestions to improve the quality of the paper.

    Nomenclature

    r density of air in kg/m3

    A area swept by the rotor blades in m2

    vw wind speed in m/s

    b blade pitch angle in degrees

    l ratio of the rotor tip speedurto the wind speed vwCp coefcient of performance of the turbine

    v,i,J complex voltage, current and ux vectors

    Rs,Rr stator, rotor winding resistancesLs,Lr,Lls,Llr stator, rotor winding self and leakage inductances

    Lm magnetizing inductance

    us,ur synchronous, rotor angular frequencies

    P,Q active and reactive power

    Vgabc three-phase complex voltages at the grid side converter

    Vrabc three-phase complex voltages at the rotor side converter

    qf stator-ux vector position

    Superscripts/subscripts

    s, r stator, rotor

    d,q direct, quadrature axis component

    a,b alpha, beta axis component

    g, c grid, converter side value

    n, ref nominal, reference value

    Appendix A. Simulation parameters

    Fig. 12. Comparing the active (left hand side) and reactive (right hand side) power of an aggregated wind farm model with a generic model consisting of four WTGs during a

    balanced three-phase fault and constant wind speed.

    Table A.1

    Parameters of variable-speed WTGs (seeFigs. 3 and 4).

    Parameter DFIG FRC

    Nominal RMS voltage 690 V 690 V

    Nominal power 1.5 MW 1.5 MW

    Nominal frequency 50 Hz 50 HzGain ofux calculation channel 1 p.u 1 p.u

    Lag time ofux calculation channel (Tk) 0.03 s 0.005 s

    Lag time of injected current channel (Tg) 0.02 s 0.03 s

    Equivalent reactance (X0

    )a 1 p.u 1 p.u

    a The rest of the parameters are as reported by GE and WECC [15,17].

    Table A.2

    Parameters used in PSCAD to simulate the FRC wind turbine (seeFig. 6).

    Parameter PMSM WRIM

    Machine parameters

    Nominal RMS voltage 600 V 600 V

    Nominal power 1.5 MW 1.5 MW

    Nominal frequency 50 Hz 50 Hz

    Stator resistance 0.017 p.u 0.02 p.u

    Leakage reactance 0.064 p.u 0.1 p.u

    Control parameters of grid side VSCPro po rti on al ga in of AC vo lta ge regulat or 0 .1 p. u 0 .1 p.u

    Integral gain of AC voltage regulator 0.02 p.u 0.02 p.u

    Pro po rti on al ga in of D C vol ta ge r egula to r 0 .8 p. u 0 .8 p.u

    Integral gain of DC voltage regulator 0.1 p.u 0.1 p.u

    Control parameters of machine side VSCePMSM

    Reactive power regulator

    Max quadrature current (Iq,max) 5 p.u

    Min quadrature current (Iq,min) 5 p.u

    Proportional gain (KpQ) 0.1 p.u

    Integral gain (KiQ) 0.02 p.u

    Active power regulator

    Max direct current (Id,max) 5 p.u

    Min direct current (Id,min) 5 p.u

    Proportional gain (KpP) 0.1 p.u

    Integral gain (KiP) 0.02 p.u

    T.S. Abuaisha / Renewable Energy 68 (2014) 245e254 253

  • 8/10/2019 alat tambahan pada Wind Turbin

    10/10

    References

    [1] EEG. German renewable energy sources act [Online],http://www.eeg-aktuell.de/; 2012.

    [2] Corporation, N.A.E.R.. Standard models for variable generation. Tech. Rep. 116-390 Village Blvd., Princeton, NJ 08540-5721, USA: NERC; 2010

    [3] Asmine M, Brochu J, Fortmann J, Gagnon R, Kazachkov Y, Langlois CE, et al.Model validation for wind turbine generator models. IEEE Trans Power Syst2011;26(3):887e91.

    [4] Ellis A, Kazachkov Y, Muljadi E, Pourbeik P, Sanchez-Gasca J. Description andtechnical specications for generic WTG models e a status report. In: IEEE/PESPower Systems Conference and Exposition (PSCE); 2011. pp. 524e9. WECCWorking Group on Dynamic Performance of Wind Power Generation & IEEEWorking Group on Dynamic Performance of Wind Power Generation .

    [5] Hu J, Yuan X. VSC-based direct torque and reactive power control of doublyfed induction generator. Renew Energy 2012;40(1):13e23.

    [6] Caliao ND. Dynamic modelling and control of fully rated converter windturbines. Renew Energy 2011;36(8):2287e97.

    [7] Fortmann J, Engelhardt S, Kretschmann J, Felters C, Janssen M, Neumann T,et al. Generic simulation model for DFIG and full size converter based windturbines. In: 9th International Workshop on Large-Scale Integration of WindPower, Quebec/Canada; 2010.

    [8] Fortmann J, Engelhardt S, Kretschmann J, Felters C, Erlich I. New genericmodel of DFG based wind turbines for RMS type simulation. IEEE Trans Energy

    Convers; 2013 ISSN: 0885-8969:99.[9] Blaabjerg F, Chen Z, Teodorescu R, Iov F. Power electronics in wind turbine

    systems. In: 5th International Power Electronics and Motion Control Confer-ence (IPEMC), vol. 1; 2006. pp. 1e11.

    [10] Boukhezzar B, Lupu L, Siguerdidjane H, Hand M. Multivariable control strategyfor variable speed, variable pitch wind turbines. Renew Energy 2007;32(8):1273e87.

    [11] Lee J, Son E, Hwang B, Lee S. Blade pitch angle control for aerodynamic per-formance optimization of a wind farm. Renew Energy 2013;54:124e30[AFORE].

    [12] Machowski J, Bialek JW, Bumby JR. Power system dynamics: stability & con-trol; chap. 7. 2nd ed. UK, Poland: John Wiley & Sons Ltd; 2008. pp. 265e97.

    [13] Price WW, Sanchez-Gasca JJ. Simplied wind turbine generator aerodynamicmodels for transient stability studies. In: IEEE PES Power Systems Conferenceand Exposition (PSCE 2006); 2006. pp. 986e92.

    [14] Kusiak A, Verma A, Wei X. Wind turbine capacity frontier from SCADA. WindSyst Mag 2012;3(9):36e9.

    [15] Behnke M, Ellis A, Kazachkov Y, McCoy T, Muljadi E, Price W, et al. Devel-opment and validation of WECC variable speed wind turbine dynamic modelsfor grid integration studies. In: AWEA Wind Power Conference. Los Angeles,California: National Renewable Energy Laboratory e NREL; 2007. pp. 1e5.

    [16] Faria KJ. Doubly-fed induction generator based wind power plant models.Masters thesis. Austin, Texas, USA: The University of Texas at Austin; 2009.

    [17] Clark K, Miller NW, Sanchez-Gasca JJ. Modelling of GE wind turbine-generators for grid studies. Tech. Rep. Schenectady, NY, 12345 USA: GeneralElectric International, Inc.; 2010

    [18] van Custem T. Algorithmic and modelling improvements for simpliedsimulation, validation on industrial cases. Tech. Rep. 2. PEGASE; 2011. pp. 41e8.

    [19] Abuaisha TS. Methods for the provision of dynamic models for distributedenergy resources. Masters thesis. Aachen, Germany: RWTH-Aachen Univer-sity; 2012.

    Table A.3

    Parameter list of the aggregated wind farm model in Matlab/Simulink (seeFig.10).

    Name Value Unit Description

    Active and reactive power control

    Vn 20 kV Nominal voltage

    Sn 2 MVA Nominal apparent powe r

    Uref e kV Assigned automatically from GUI

    Pref e MW Assigned automatically from GUI

    Qref e

    Mvar Assigned automatically from GUIDBmax 1.1 p.u Upper deadband limit

    DBmin 0.9 p.u Upper deadband limit

    Ku 2 p.u Gain in voltage channel

    Imax 1 p.u Converter current limit

    Tv 60 s First time constant in reactive power channel

    Tq 20 s Second time constant in reactive power channel

    Detailed model parameters (orange box)

    Iimmax 5 p.u Upper limit applied to imaginary current

    Iimmin 5 p.u Lower limit applied to imaginary current

    Iremax 5 p.u U pper li mi t a pplied to r ea l c urrent

    Iremin 5 p.u L ower l imi t a pplied t o real curr ent

    Ti1 0.005 p.u Time delay applied in upper branch

    Ti2 0.03 p.u Time delay applied in lower branch

    X 0.5 p.u Equivalent instantaneous reactance

    T.S. Abuaisha / Renewable Energy 68 (2014) 245e254254

    http://www.eeg-aktuell.de/http://www.eeg-aktuell.de/http://refhub.elsevier.com/S0960-1481(14)00033-0/sref2http://refhub.elsevier.com/S0960-1481(14)00033-0/sref2http://refhub.elsevier.com/S0960-1481(14)00033-0/sref3http://refhub.elsevier.com/S0960-1481(14)00033-0/sref3http://refhub.elsevier.com/S0960-1481(14)00033-0/sref3http://refhub.elsevier.com/S0960-1481(14)00033-0/sref3http://refhub.elsevier.com/S0960-1481(14)00033-0/sref4http://refhub.elsevier.com/S0960-1481(14)00033-0/sref4http://refhub.elsevier.com/S0960-1481(14)00033-0/sref4http://refhub.elsevier.com/S0960-1481(14)00033-0/sref4http://refhub.elsevier.com/S0960-1481(14)00033-0/sref4http://refhub.elsevier.com/S0960-1481(14)00033-0/sref4http://refhub.elsevier.com/S0960-1481(14)00033-0/sref4http://refhub.elsevier.com/S0960-1481(14)00033-0/sref4http://refhub.elsevier.com/S0960-1481(14)00033-0/sref4http://refhub.elsevier.com/S0960-1481(14)00033-0/sref5http://refhub.elsevier.com/S0960-1481(14)00033-0/sref5http://refhub.elsevier.com/S0960-1481(14)00033-0/sref5http://refhub.elsevier.com/S0960-1481(14)00033-0/sref5http://refhub.elsevier.com/S0960-1481(14)00033-0/sref6http://refhub.elsevier.com/S0960-1481(14)00033-0/sref6http://refhub.elsevier.com/S0960-1481(14)00033-0/sref6http://refhub.elsevier.com/S0960-1481(14)00033-0/sref7http://refhub.elsevier.com/S0960-1481(14)00033-0/sref7http://refhub.elsevier.com/S0960-1481(14)00033-0/sref7http://refhub.elsevier.com/S0960-1481(14)00033-0/sref7http://refhub.elsevier.com/S0960-1481(14)00033-0/sref7http://refhub.elsevier.com/S0960-1481(14)00033-0/sref8http://refhub.elsevier.com/S0960-1481(14)00033-0/sref8http://refhub.elsevier.com/S0960-1481(14)00033-0/sref8http://refhub.elsevier.com/S0960-1481(14)00033-0/sref8http://refhub.elsevier.com/S0960-1481(14)00033-0/sref9http://refhub.elsevier.com/S0960-1481(14)00033-0/sref9http://refhub.elsevier.com/S0960-1481(14)00033-0/sref9http://refhub.elsevier.com/S0960-1481(14)00033-0/sref9http://refhub.elsevier.com/S0960-1481(14)00033-0/sref9http://refhub.elsevier.com/S0960-1481(14)00033-0/sref10http://refhub.elsevier.com/S0960-1481(14)00033-0/sref10http://refhub.elsevier.com/S0960-1481(14)00033-0/sref10http://refhub.elsevier.com/S0960-1481(14)00033-0/sref10http://refhub.elsevier.com/S0960-1481(14)00033-0/sref11http://refhub.elsevier.com/S0960-1481(14)00033-0/sref11http://refhub.elsevier.com/S0960-1481(14)00033-0/sref11http://refhub.elsevier.com/S0960-1481(14)00033-0/sref11http://refhub.elsevier.com/S0960-1481(14)00033-0/sref12http://refhub.elsevier.com/S0960-1481(14)00033-0/sref12http://refhub.elsevier.com/S0960-1481(14)00033-0/sref12http://refhub.elsevier.com/S0960-1481(14)00033-0/sref13http://refhub.elsevier.com/S0960-1481(14)00033-0/sref13http://refhub.elsevier.com/S0960-1481(14)00033-0/sref13http://refhub.elsevier.com/S0960-1481(14)00033-0/sref13http://refhub.elsevier.com/S0960-1481(14)00033-0/sref13http://refhub.elsevier.com/S0960-1481(14)00033-0/sref13http://refhub.elsevier.com/S0960-1481(14)00033-0/sref14http://refhub.elsevier.com/S0960-1481(14)00033-0/sref14http://refhub.elsevier.com/S0960-1481(14)00033-0/sref14http://refhub.elsevier.com/S0960-1481(14)00033-0/sref15http://refhub.elsevier.com/S0960-1481(14)00033-0/sref15http://refhub.elsevier.com/S0960-1481(14)00033-0/sref15http://refhub.elsevier.com/S0960-1481(14)00033-0/sref15http://refhub.elsevier.com/S0960-1481(14)00033-0/sref15http://refhub.elsevier.com/S0960-1481(14)00033-0/sref15http://refhub.elsevier.com/S0960-1481(14)00033-0/sref16http://refhub.elsevier.com/S0960-1481(14)00033-0/sref16http://refhub.elsevier.com/S0960-1481(14)00033-0/sref16http://refhub.elsevier.com/S0960-1481(14)00033-0/sref16http://refhub.elsevier.com/S0960-1481(14)00033-0/sref17http://refhub.elsevier.com/S0960-1481(14)00033-0/sref17http://refhub.elsevier.com/S0960-1481(14)00033-0/sref17http://refhub.elsevier.com/S0960-1481(14)00033-0/sref18http://refhub.elsevier.com/S0960-1481(14)00033-0/sref18http://refhub.elsevier.com/S0960-1481(14)00033-0/sref18http://refhub.elsevier.com/S0960-1481(14)00033-0/sref18http://refhub.elsevier.com/S0960-1481(14)00033-0/sref18http://refhub.elsevier.com/S0960-1481(14)00033-0/sref19http://refhub.elsevier.com/S0960-1481(14)00033-0/sref19http://refhub.elsevier.com/S0960-1481(14)00033-0/sref19http://refhub.elsevier.com/S0960-1481(14)00033-0/sref19http://refhub.elsevier.com/S0960-1481(14)00033-0/sref19http://refhub.elsevier.com/S0960-1481(14)00033-0/sref19http://refhub.elsevier.com/S0960-1481(14)00033-0/sref19http://refhub.elsevier.com/S0960-1481(14)00033-0/sref19http://refhub.elsevier.com/S0960-1481(14)00033-0/sref18http://refhub.elsevier.com/S0960-1481(14)00033-0/sref18http://refhub.elsevier.com/S0960-1481(14)00033-0/sref18http://refhub.elsevier.com/S0960-1481(14)00033-0/sref17http://refhub.elsevier.com/S0960-1481(14)00033-0/sref17http://refhub.elsevier.com/S0960-1481(14)00033-0/sref17http://refhub.elsevier.com/S0960-1481(14)00033-0/sref16http://refhub.elsevier.com/S0960-1481(14)00033-0/sref16http://refhub.elsevier.com/S0960-1481(14)00033-0/sref15http://refhub.elsevier.com/S0960-1481(14)00033-0/sref15http://refhub.elsevier.com/S0960-1481(14)00033-0/sref15http://refhub.elsevier.com/S0960-1481(14)00033-0/sref15http://refhub.elsevier.com/S0960-1481(14)00033-0/sref15http://refhub.elsevier.com/S0960-1481(14)00033-0/sref15http://refhub.elsevier.com/S0960-1481(14)00033-0/sref14http://refhub.elsevier.com/S0960-1481(14)00033-0/sref14http://refhub.elsevier.com/S0960-1481(14)00033-0/sref14http://refhub.elsevier.com/S0960-1481(14)00033-0/sref13http://refhub.elsevier.com/S0960-1481(14)00033-0/sref13http://refhub.elsevier.com/S0960-1481(14)00033-0/sref13http://refhub.elsevier.com/S0960-1481(14)00033-0/sref13http://refhub.elsevier.com/S0960-1481(14)00033-0/sref12http://refhub.elsevier.com/S0960-1481(14)00033-0/sref12http://refhub.elsevier.com/S0960-1481(14)00033-0/sref12http://refhub.elsevier.com/S0960-1481(14)00033-0/sref11http://refhub.elsevier.com/S0960-1481(14)00033-0/sref11http://refhub.elsevier.com/S0960-1481(14)00033-0/sref11http://refhub.elsevier.com/S0960-1481(14)00033-0/sref11http://refhub.elsevier.com/S0960-1481(14)00033-0/sref10http://refhub.elsevier.com/S0960-1481(14)00033-0/sref10http://refhub.elsevier.com/S0960-1481(14)00033-0/sref10http://refhub.elsevier.com/S0960-1481(14)00033-0/sref10http://refhub.elsevier.com/S0960-1481(14)00033-0/sref9http://refhub.elsevier.com/S0960-1481(14)00033-0/sref9http://refhub.elsevier.com/S0960-1481(14)00033-0/sref9http://refhub.elsevier.com/S0960-1481(14)00033-0/sref9http://refhub.elsevier.com/S0960-1481(14)00033-0/sref8http://refhub.elsevier.com/S0960-1481(14)00033-0/sref8http://refhub.elsevier.com/S0960-1481(14)00033-0/sref8http://refhub.elsevier.com/S0960-1481(14)00033-0/sref7http://refhub.elsevier.com/S0960-1481(14)00033-0/sref7http://refhub.elsevier.com/S0960-1481(14)00033-0/sref7http://refhub.elsevier.com/S0960-1481(14)00033-0/sref7http://refhub.elsevier.com/S0960-1481(14)00033-0/sref6http://refhub.elsevier.com/S0960-1481(14)00033-0/sref6http://refhub.elsevier.com/S0960-1481(14)00033-0/sref6http://refhub.elsevier.com/S0960-1481(14)00033-0/sref5http://refhub.elsevier.com/S0960-1481(14)00033-0/sref5http://refhub.elsevier.com/S0960-1481(14)00033-0/sref5http://refhub.elsevier.com/S0960-1481(14)00033-0/sref4http://refhub.elsevier.com/S0960-1481(14)00033-0/sref4http://refhub.elsevier.com/S0960-1481(14)00033-0/sref4http://refhub.elsevier.com/S0960-1481(14)00033-0/sref4http://refhub.elsevier.com/S0960-1481(14)00033-0/sref4http://refhub.elsevier.com/S0960-1481(14)00033-0/sref4http://refhub.elsevier.com/S0960-1481(14)00033-0/sref4http://refhub.elsevier.com/S0960-1481(14)00033-0/sref3http://refhub.elsevier.com/S0960-1481(14)00033-0/sref3http://refhub.elsevier.com/S0960-1481(14)00033-0/sref3http://refhub.elsevier.com/S0960-1481(14)00033-0/sref3http://refhub.elsevier.com/S0960-1481(14)00033-0/sref2http://refhub.elsevier.com/S0960-1481(14)00033-0/sref2http://www.eeg-aktuell.de/http://www.eeg-aktuell.de/