a glimpses of port of cirebon -...
TRANSCRIPT
Prepared by IPC Cirebon 21/09/17
A glimpses of Port of Cirebon
3 | Energizing Trade. Energizing Indonesia
Operation Area of Pelindo I,II,III and IV
We are ‘HERE’
4 | Energizing Trade. Energizing Indonesia
Port of Cirebon – Facility and Equipment
4
LAPANGAN
Lp. Muarajati : 4.480 M2
Lp. Pelita : 9.780 M2
Lp. Suryat Sumantri : 8.048 M2
Lp. Linggarjati : 5.600 M2
GUDANG
Gudang Muarajati : 4.000 M2
Gudang 101 : 1.806 M2
Gudang 102 : 1.500 M2
Gudang 103 : 306 M2
Gudang 104 : 1.050 M2
Gudang Terbuka Pelra : 1.200 M2
Dermaga Samadikun : 67 M / -4 MLWs
Dermaga Perniagaan I - IV : 44 M / -3 MLWs
Dermaga S. Sumantri I - V : 68 M / -3,5 MLWs
Dermaga Muara Jati I - III : 603 M / -5,5 sd -6 MLWs
Dermaga Linggar Jati I -II : 171 M / -4,5 MLWs
Dermaga Pelita I - III : 98 M / -5,5 MLWs
Kade Khusus Pelra : 150 M / -2 MLWs
Total Panjang Dermaga : 1,201 M
4
2
2
2
1
1
Dump Truck
Excavator Caterpilar
Excavator Hyundai
Excavator Komatsu
Jembatan Timbang
Mobil Crane IHI 25 Ton
1
1
3
1
1
1
Mobil PMK Kapasitas 5.000 m3
Forklift Kap.5 Ton
Rampdoor
Wheel Loader kap 3 Ton
Wheel Loader Kap.5 Ton
Wheel Loader Kap.5,1 M3 HL 780-7A Merk Hyundai
5 | Energizing Trade. Energizing Indonesia
Port of Cirebon - Ships Traffic
Dominate by Tug and Barge
2013 2014 2015 2016s/d Juli2017
GT 1.974.9 2.139.0 1.987.1 1.048.8 1.296.7
-
500.000
1.000.000
1.500.000
2.000.000
2.500.000
Gross Tonnage
2013 2014 2015 2016s/d Juli2017
UNIT 1.407 1.536 1.329 788 934
-
200
400
600
800
1.000
1.200
1.400
1.600
1.800
Unit
6 | Energizing Trade. Energizing Indonesia
Port of Cirebon – Cargo Throughput
Dominate by Dry Bulk Commodity
2013 2014 2015 2016 s/d Juli 2017
General Cargo - - 46.606 28.884 893
Curah Cair 331.169 322.516 313.100 288.568 200.059
Bag Cargo 264.029 144.709 115.021 108.955 61.775
Curah Kering 3.433.249 4.046.716 3.725.744 1.933.462 2.008.715
-
500.000
1.000.000
1.500.000
2.000.000
2.500.000
3.000.000
3.500.000
4.000.000
4.500.000
5.000.000
(Tonnage)
4,028,447
4,513,9414,200,471
2,359,869 2,271,442
Potential Market OpportunitiesDue to limited draft, the cargo is currently transit in some neighbouring ports.
8 | Energizing Trade. Energizing Indonesia
Strategic Market Opportunities
1
2
3
4
5
6
7
3 Biggest Animal Feed Factory in Cirebon have average production 1.000.000 tonnes
annually, currently it is unloaded at Ciwandan dan Cigadeng Port in Banten
Fertilizer company around Cirebon have average production up to 50.000 tonnes annually
More than 20 textile company and other industries moved from Bandung, Jakata, and
Tangerang to Cirebon-Indramayu-Majalengka-Kuningan (CIAYUMAJAKUNING)
Potential volume form salt, sugar, and cattle industry
Cargo handling of PLTU 2 & 3 project
Liquid bulk facility improvement potential
8 Domestik and international container services
Passenger Vessel & Roro services
WEST JAVA SPATIAL PLAN
Sumber : BAPPEDA JABAR
Kawasan Industri
West Jawa Saptial Structure Plan
PKN METRO
BANDUNG
PKN METRO
CIREBON
PKN METROPOLITAN
BODEBEK
PKW PELABUHAN
RATU
PKNp PANGANDA
RAN
PKWp RANCABUAYA
PKN, PKW : National/Regional Center of Activity
10
Pengembangan Kawasan Strategis Kabupaten Cirebon
Economic Growth Strategic Region (KSK) -
(Agro Region Arjawinangun)
Economic Growth
Strategic Region (KSK) -
(PlumbonRegion)
Social and Culture
Strategic Region
(GunungJati Region)
Economic Growth Strategic Region
(agro CiledugRegion)
KABUPATEN KUNINGAN
Cirebon Spatial Plan
Cirebon District Strategic
Region Plan
(KSK Cirebon) Sumber : BAPPEDA Kabupaten Cirebon
Java Sea
11
DLKR/DLKP Pelabuhan Cirebon
According to “Keputusan Bersama Menteri DalamNegeri dan Menteri Perhubungan No. 58 tahun 1988dan Nomor : KP 25/AL 108/PHB-88 tentang Batas-batas DLKR/DLKP Pelabuhan Cirebon”, it has beenstated that Cirebon Port have 51 ha DLKR dan 25 haDLKP, also 8.410,91 ha of Port Basin Area.
Port of Cirebon is currently can handle only for thevessel up to -6.5m. For the vessel that have morethan -6.5mlws has to be discharge at the outer areathat safe and recommended by Harbour Master.The future plan, Port of Cirebon expected bigvessels that have draft up to -10mlws to come anddischarge in the port.
Port of Cirebon
Port of Cirebon Development Plan
13 | Energizing Trade. Energizing Indonesia
Fairway Developmen Plan
before -5.5mlws to be -12mlws
CIREBON
BREBES
Gugusan
karang
Palung
Arah Arus Laut
Alur Eksisting
Alur Rencana – 12 MLws , jarak ±
36 KM / 18 Mil
DATA SURVEI ARUS DAN
GELOMBANG
Pelabuhan
Cirebon
14 | Energizing Trade. Energizing Indonesia
Project Detail
Pengembangan Pelabuhan Cirebon :
The development of Deep Sea Port that is integrated with Industrial estate to accommodate the cargo throughput growth, industrial estate development, and potential hinterland of Cirebon Port.
Informasi Proyek :IRR : 11,2 %Capital Expenditure: Rp 8,9 Triliun; Phase One: Rp 3,8 Triliun
Project Information
Port of Cirebon Development
15 | Energizing Trade. Energizing Indonesia
Master Plan of Port of Cirebon
16 | Energizing Trade. Energizing Indonesia
Port Development Plan
Phase I: 50 Ha
17 | Energizing Trade. Energizing Indonesia
Port Development Plan
Phase I (2018 – 2021)Reclamation Area : 50 HaBerth Area : 19.200 M2
Phase II (2022 – 2032)Reclamation Area : 153 HaBerth Area : 31.200 M2
Thank you