PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : MOBILISASI
SATUAN PEMBAYARAN : LS
A. ALAT
1. Excavator Standard Unit 2,000 30.000.000,00 60.000.000,00Rp
2. Buldozer Unit 1,000 30.000.000,00 30.000.000,00Rp
3. Vibrator Roller Unit 1,000 30.000.000,00 30.000.000,00Rp
4. Dump Truck Unit 2,000 5.000.000,00 10.000.000,00Rp
5. Generator Set Unit 1,000 500.000,00 500.000,00Rp
6. Concrete Mixer Unit 4,000 500.000,00 2.000.000,00Rp
B. JUMLAH HARGA 132.500.000,00Rp
C. - BIAYA UMUM 1,0 % x B 1.325.000,00Rp
- KEUNTUNGAN 9,0 % x B 11.925.000,00RpD. HARGA SATUAN PEKERJAAN ( B + C ) 145.750.000,00Rp
E. HARGA SATUAN PEKERJAAN DIBULATKAN 145.750.000,00Rp
ANALISA HARGA SATUAN PEKERJAAN
NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
-
7/26/2019 4. Analisa Harga
2/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : PEMBERSIHAN LAHAN
SATUAN PEMBAYARAN : M2
A. TENAGA
1. Pekerja OH 0,060 80.000,00 4.800,00Rp
2. Mandor OH 0,006 110.000,00 660,00Rp
5.460,00Rp
B. BAHAN
-Rp
-Rp
C. PERALATAN
-Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 5.460,00Rp
E. - BIAYA UMUM 1,0 % x D 54,60Rp
- KEUNTUNGAN 9,0 % x D 491,40Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 6.006,00Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 6.006,00Rp
NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
-
7/26/2019 4. Analisa Harga
3/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : GALIAN TANAH (ALAT BERAT)
SATUAN PEMBAYARAN : M3
A. TENAGA
1. Pekerja OH 0,080 80.000,00 6.412,67Rp
2. Mandor OH 0,016 110.000,00 1.763,48Rp
8.176,15Rp
B. BAHAN
-Rp
-Rp
C. PERALATAN
1. Excavator Jam 0,016 665.551,00 10.669,89Rp
10.669,89Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 18.846,04Rp
E. - BIAYA UMUM 1,0 % x D 188,46Rp
- KEUNTUNGAN 9,0 % x D 1.696,14Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 20.730,65Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 20.730,00Rp
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
-
7/26/2019 4. Analisa Harga
4/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : GALIAN TANAH (MANUAL) SEDALAM < 1 m
SATUAN PEMBAYARAN : M3
A. TENAGA
1. Pekerja OH 0,563 80.000,00 45.040,00Rp
2. Mandor OH 0,056 110.000,00 6.193,00Rp
51.233,00Rp
B. BAHAN
-Rp
-Rp
C. PERALATAN
-Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 51.233,00Rp
E. - BIAYA UMUM 1,0 % x D 512,33Rp
- KEUNTUNGAN 9,0 % x D 4.610,97Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 56.356,30Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 56.356,00Rp
HARGA JUMLAH HARGA
JUMLAH HARGA PERALATAN
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. URAIAN SATUAN VOLUME
-
7/26/2019 4. Analisa Harga
5/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : TIMBUANAN TANAH (MANUAL)
SATUAN PEMBAYARAN : M3
A. TENAGA
1. Pekerja OH 0,330 80.000,00 26.400,00Rp
2. Mandor OH 0,033 110.000,00 3.630,00Rp
30.030,00Rp
B. BAHAN
-Rp
-Rp
C. PERALATAN
-Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 30.030,00Rp
E. - BIAYA UMUM 1,0 % x D 300,30Rp
- KEUNTUNGAN 9,0 % x D 2.702,70Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 33.033,00Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 33.033,00Rp
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
-
7/26/2019 4. Analisa Harga
6/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : PEKERJAAN TIMBUNAN TANAH COVERDAM
SATUAN PEMBAYARAN : M3
A. TENAGA
1. Pekerja OH 0,045 80.000,00 3.634,57Rp
2. Mandor OH 0,011 110.000,00 1.249,38Rp
4.883,95Rp
B. BAHAN
-Rp
C. PERALATAN
1. Excavator Jam 0,011 665.551,00 7.559,34Rp4. Vibro Roller Jam 0,005 534.915,00 2.641,56Rp
10.200,90Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 15.084,85Rp
E. - BIAYA UMUM 1,0 % x D 150,85Rp
- KEUNTUNGAN 9,0 % x D 1.357,64Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 16.593,34Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 16.593,00Rp
ANALISA HARGA SATUAN PEKERJAAN
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA
-
7/26/2019 4. Analisa Harga
7/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : CLEARING dan GRUBBING
SATUAN PEMBAYARAN : M2
A. TENAGA
1. Pekerja OH 0,060 80.000,00 4.800,00Rp
2. Mandor OH 0,006 110.000,00 660,00Rp
5.460,00Rp
B. BAHAN
-Rp
-Rp
C. PERALATAN
-Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 5.460,00Rp
E. - BIAYA UMUM 1,0 % x D 54,60Rp
- KEUNTUNGAN 9,0 % x D 491,40Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 6.006,00Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 6.006,00Rp
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. URAIAN SATUAN VOLUME HARGA
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAH HARGA
-
7/26/2019 4. Analisa Harga
8/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : TEBAS TEBANG TANAMAN PERDU
SATUAN PEMBAYARAN : M2
A. TENAGA
1. Pekerja OH 0,075 80.000,00 6.000,00Rp
2. Mandor OH 0,008 110.000,00 825,00Rp
6.825,00Rp
B. BAHAN
1. Minyak Tanah L 0,010 5.000,00 50,00Rp
50,00Rp
C. PERALATAN
-Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 6.875,00Rp
E. - BIAYA UMUM 1,0 % x D 68,75Rp
- KEUNTUNGAN 9,0 % x D 618,75Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 7.562,50Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 7.562,00Rp
NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
-
7/26/2019 4. Analisa Harga
9/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : CABUT TANGGUL TANAMAN KERAS ( dia 15 cm )
SATUAN PEMBAYARAN : POHON
A. TENAGA
1. Pekerja OH 0,200 80.000,00 16.000,00Rp
2. Mandor OH 0,020 110.000,00 2.200,00Rp
18.200,00Rp
B. BAHAN
-Rp
C. PERALATAN
1. Chainsaw Jam 0,100 40.000,00 4.000,00Rp
4.000,00Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 22.200,00Rp
E. - BIAYA UMUM 1,0 % x D 222,00Rp
- KEUNTUNGAN 9,0 % x D 1.998,00Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 24.420,00Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 24.420,00Rp
JUMLAH HARGA
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
NO. URAIAN SATUAN VOLUME HARGA
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
-
7/26/2019 4. Analisa Harga
10/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : GORONG - GORONG BETON DIA. 100 CM
SATUAN PEMBAYARAN : BH
A. TENAGA
1. Pekerja OH 0,667 80.000,00 53.333,33Rp
2. Mandor OH 0,167 110.000,00 18.333,33Rp
71.666,67Rp
B. BAHAN
1. Gorong - gorong dia 1 M Buah 1,000 65.000,00 65.000,00Rp
65.000,00Rp
C. PERALATAN
1. Tripod Jam 0,167 75.000,00 12.500,00Rp
12.500,00Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 149.166,67Rp
E. - BIAYA UMUM 1,0 % x D 1.491,67Rp
- KEUNTUNGAN 9,0 % x D 13.425,00Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 164.083,33Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 164.083,00Rp
HARGA JUMLAH HARGA
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. URAIAN SATUAN VOLUME
-
7/26/2019 4. Analisa Harga
11/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : PENGHAMPARAN TANAH DATANG TUBUH BENDUNG dan PEMADATANNYA
SATUAN PEMBAYARAN : M3
A. TENAGA
1. Pekerja OH 0,160 80.000,00 12.825,33Rp
2. Mandor OH 0,016 110.000,00 1.763,48Rp
14.588,82Rp
B. BAHAN
1. Tanah Timbunan M 1,200 92.100,00 110.520,00Rp
110.520,00Rp
C. PERALATAN
1. Excavator Jam 0,016 665.551,00 10.669,89Rp2. Dump Truck Jam 0,035 349.602,00 12.251,35Rp
3. Buldozer Jam 0,041 812.207,00 33.126,28Rp
4. Vibro Roller Jam 0,018 534.915,00 9.533,43Rp
65.580,96Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 190.689,78Rp
E. - BIAYA UMUM 1,0 % x D 1.906,90Rp
- KEUNTUNGAN 9,0 % x D 17.162,08Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 209.758,76Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 209.758,00Rp
NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
-
7/26/2019 4. Analisa Harga
12/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : PENGADAAN KAWAT BRONJONG
SATUAN PEMBAYARAN : BH
1. Kawat Bronjong (Pabrikasi) Ukuran Buah 1,000 400.000,00 400.000,00Rp
2 x 1 x 0.5 m. Heavy Galvanized
dia 3 mm
2. Biaya Pengiriman Jakarta - Lokasi Buah 1,000 20.000,00 20.000,00Rp
3. Biaya Bongkar Muat Buah 1,000 2.000,00 2.000,00Rp
A. JUMLAH HARGA 422.000,00Rp
B. DIBULATKAN 422.000,00Rp
ANALISA HARGA SATUAN PEKERJAAN
HARGA JUMLAH HARGA
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. KOMPONEN SATUANPERKIRAAN
KUANTITAS
-
7/26/2019 4. Analisa Harga
13/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : PASANGAN BRONJONG PABRIKASI
SATUAN PEMBAYARAN : M3
A. TENAGA
1. Pekerja OH 0,500 80.000,00 40.000,00Rp
2. Mandor OH 0,050 110.000,00 5.500,00Rp
45.500,00Rp
B. BAHAN
1. Batu Belah 10/15 cm M 1,400 333.100,00 466.340,00Rp
2. Kawar Bronjong Bh 1,000 422.000,00 422.000,00Rp
888.340,00Rp
C. PERALATAN
1. Tripod Jam 0,010 75.000,00 750,00Rp
750,00Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 934.590,00Rp
E. - BIAYA UMUM 1,0 % x D 9.345,90Rp
- KEUNTUNGAN 9,0 % x D 84.113,10Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 1.028.049,00Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 1.028.049,00Rp
HARGA JUMLAH HARGA
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. URAIAN SATUAN VOLUME
-
7/26/2019 4. Analisa Harga
14/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : PEKERJAAN GEOMEMBRAN
SATUAN PEMBAYARAN : M2
A. TENAGA
1. Pekerja OH 0,100 80.000,00 8.000,00Rp
2. Tukang OH 0,020 90.000,00 1.800,00Rp
3. Mandor OH 0,010 110.000,00 1.100,00Rp
10.900,00Rp
B. BAHAN
1. Geomembran M 1,050 65.000,00 68.250,00Rp
68.250,00Rp
C. PERALATAN
-Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 79.150,00Rp
E. - BIAYA UMUM 1,0 % x D 791,50Rp
- KEUNTUNGAN 9,0 % x D 7.123,50Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 87.065,00Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 87.065,00Rp
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
JUMLAH HARGA
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
NO. URAIAN SATUAN VOLUME HARGA
ANALISA HARGA SATUAN PEKERJAAN
-
7/26/2019 4. Analisa Harga
15/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : PEKERJAAN GEOTEKSTIL
SATUAN PEMBAYARAN : M2
A. TENAGA
1. Pekerja OH 0,100 80.000,00 8.000,00Rp
2. Tukang OH 0,020 90.000,00 1.800,00Rp
3. Mandor OH 0,010 110.000,00 1.100,00Rp
10.900,00Rp
B. BAHAN
1. Geotekstil M 1,050 25.000,00 26.250,00Rp
26.250,00Rp
C. PERALATAN
-Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 37.150,00Rp
E. - BIAYA UMUM 1,0 % x D 371,50Rp
- KEUNTUNGAN 9,0 % x D 3.343,50Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 40.865,00Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 40.865,00Rp
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
-
7/26/2019 4. Analisa Harga
16/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : PENGHAMPARAN PASIR KERIKIL DAN PEMADATANNYA T = 50 CM
SATUAN PEMBAYARAN : M3
A. TENAGA
1. Pekerja OH 0,510 80.000,00 40.785,52Rp
2. Mandor OH 0,051 110.000,00 5.608,01Rp
46.393,53Rp
B. BAHAN
1. Batu Kerikil M 1,200 495.700,00 594.840,00Rp
594.840,00Rp
C. PERALATAN
1. Buldozer Jam 0,051 812.207,00 41.407,85Rp2. Vibro Roller Jam 0,014 534.915,00 7.607,68Rp
49.015,53Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 690.249,06Rp
E. - BIAYA UMUM 1,0 % x D 6.902,49Rp
- KEUNTUNGAN 9,0 % x D 62.122,42Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 759.273,97Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 759.273,00Rp
HARGA
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. URAIAN SATUAN VOLUME JUMLAH HARGA
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISA HARGA SATUAN PEKERJAAN
-
7/26/2019 4. Analisa Harga
17/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : BETON K. 225
SATUAN PEMBAYARAN : M3
A. TENAGA
1. Pekerja OH 1,323 80.000,00 105.840,00Rp
2. Tukang OH 0,189 90.000,00 17.010,00Rp
3. Kepala Tukang OH 0,019 100.000,00 1.900,00Rp
4. Mandor OH 0,132 110.000,00 14.520,00Rp
139.270,00Rp
B. BAHAN
1. PC/ Portland Cement Kg 371,000 2.122,00 787.262,00Rp
2. PB / Pasir Beton Kg 698,000 132,00 92.136,00Rp
3. Kr / Kerikil Kg 1047,000 341,86 357.929,59Rp
4. Air Liter 215,000 200,00 43.000,00Rp
1.280.327,59Rp
C. PERALATAN
1. Concrete Mixer Jam 0,250 86.627,00 21.656,75Rp
21.656,75Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.441.254,34Rp
E. - BIAYA UMUM 1,0 % x D 14.412,54Rp
- KEUNTUNGAN 9,0 % x D 129.712,89Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 1.585.379,77Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 1.585.379,00Rp
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
JUMLAH HARGA
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
NO. URAIAN SATUAN VOLUME HARGA
-
7/26/2019 4. Analisa Harga
18/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : LANTAI KERJA
SATUAN PEMBAYARAN : M3
A. TENAGA
1. Pekerja OH 1,320 80.000,00 105.600,00Rp
2. Tukang OH 0,220 90.000,00 19.800,00Rp
3. Kepala Tukang OH 0,022 100.000,00 2.200,00Rp
4. Mandor OH 0,132 110.000,00 14.520,00Rp
142.120,00Rp
B. BAHAN
1. PC/ Portland Cement Kg 247,000 2.122,00 524.134,00Rp
2. PB / Pasir Beton Kg 993,600 132,00 131.155,20Rp
3. Kr / Kerikil Kg 1073,000 341,86 366.818,00Rp
4. Air Liter 215,000 200,00 43.000,00Rp
1.065.107,20Rp
C. PERALATAN
1. Concrete Mixer Jam 0,250 86.627,00 21.656,75Rp
21.656,75Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.228.883,95Rp
E. - BIAYA UMUM 1,0 % x D 12.288,84Rp
- KEUNTUNGAN 9,0 % x D 110.599,56Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 1.351.772,35Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 1.351.772,00Rp
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISA HARGA SATUAN PEKERJAAN
JUMLAH HARGA
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. URAIAN SATUAN VOLUME HARGA
-
7/26/2019 4. Analisa Harga
19/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : PEMBESIAN
SATUAN PEMBAYARAN : Kg
A. TENAGA
1. Pekerja OH 0,0070 80.000,00 560,00Rp
2. Tukang OH 0,0070 90.000,00 630,00Rp
3. Kepala Tukang OH 0,0007 100.000,00 70,00Rp
4. Mandor OH 0,0007 110.000,00 77,00Rp
1.337,00Rp
B. BAHAN
1. Besi Beton (Polos / Ulir) Kg 1,050 21.100,00 22.155,00Rp
2. Kawat Bendrat Kg 0,015 23.100,00 346,50Rp
22.501,50Rp
C. PERALATAN
-Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 23.838,50Rp
E. - BIAYA UMUM 1,0 % x D 238,39Rp
- KEUNTUNGAN 9,0 % x D 2.145,47Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 26.222,35Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 26.222,00Rp
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA
-
7/26/2019 4. Analisa Harga
20/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : BEKISTING
SATUAN PEMBAYARAN : M2
A. TENAGA
1. Pekerja OH 0,6000 80.000,00 48.000,00Rp
2. Tukang OH 0,3000 90.000,00 27.000,00Rp
3. Kepala Tukang OH 0,0300 100.000,00 3.000,00Rp
4. Mandor OH 0,0600 110.000,00 6.600,00Rp
84.600,00Rp
B. BAHAN
1. Papan Kelas II M 0,025 4.500.000,00 112.500,00Rp
2. Kayu Kelas II M 0,011 2.500.000,00 27.500,00Rp
3. Paku Kg 0,400 25.000,00 10.000,00Rp
4. Minyak Bekisting Liter 0,200 10.000,00 2.000,00Rp
152.000,00Rp
C. PERALATAN
-Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 236.600,00Rp
E. - BIAYA UMUM 1,0 % x D 2.366,00Rp
- KEUNTUNGAN 9,0 % x D 21.294,00Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 260.260,00Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 260.260,00Rp
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
-
7/26/2019 4. Analisa Harga
21/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : WIREMESH M5
SATUAN PEMBAYARAN : Kg
A. TENAGA
1. Pekerja OH 0,00250 80.000,00 200,00Rp
2. Tukang OH 0,00250 90.000,00 225,00Rp
3. Kepala Tukang OH 0,00025 100.000,00 25,00Rp
4. Mandor OH 0,00025 110.000,00 27,50Rp
477,50Rp
B. BAHAN
1. Wiremesh Kg 1,020 25.000,00 25.500,00Rp
2. Kawat Bendrat Kg 0,005 23.100,00 115,50Rp
25.615,50Rp
C. PERALATAN
-Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 26.093,00Rp
E. - BIAYA UMUM 1,0 % x D 260,93Rp
- KEUNTUNGAN 9,0 % x D 2.348,37Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 28.702,30Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 28.702,00Rp
JUMLAH HARGA
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. URAIAN SATUAN VOLUME HARGA
-
7/26/2019 4. Analisa Harga
22/80
-
7/26/2019 4. Analisa Harga
23/80
-
7/26/2019 4. Analisa Harga
24/80
-
7/26/2019 4. Analisa Harga
25/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : KERAMIK 20 X 20 CM
SATUAN PEMBAYARAN : M2
A. TENAGA
1. Pekerja OH 0,700 80.000,00 56.000,00Rp
2. Tukang OH 0,350 90.000,00 31.500,00Rp
3. Kepala Tukang OH 0,035 100.000,00 3.500,00Rp
4. Mandor OH 0,070 110.000,00 7.700,00Rp
98.700,00Rp
B. BAHAN
1. PC/ Portland Cement Kg 8,000 2.122,00 16.976,00Rp
2. Pasir Pasang M 0,045 215.200,00 9.684,00Rp
3. Semen Warna Kg 2,000 5.000,00 10.000,00Rp
4. Keramik 20 x 20 Buah 25,000 7.500,00 187.500,00Rp
224.160,00Rp
C. PERALATAN
-Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 322.860,00Rp
E. - BIAYA UMUM 1,0 % x D 3.228,60Rp
- KEUNTUNGAN 9,0 % x D 29.057,40Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 355.146,00Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 355.146,00Rp
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
-
7/26/2019 4. Analisa Harga
26/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : PLESTERAN 1 PC : 3 PP
SATUAN PEMBAYARAN : M2
A. TENAGA
1. Pekerja OH 0,300 80.000,00 24.000,00Rp
2. Tukang OH 0,150 90.000,00 13.500,00Rp
3. Kepala Tukang OH 0,015 100.000,00 1.500,00Rp
4. Mandor OH 0,030 110.000,00 3.300,00Rp
42.300,00Rp
B. BAHAN
1. PC/ Portland Cement Kg 5,840 2.122,00 12.392,48Rp
2. Pasir Pasang M 0,016 215.200,00 3.443,20Rp
15.835,68Rp
C. PERALATAN
-Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 58.135,68Rp
E. - BIAYA UMUM 1,0 % x D 581,36Rp
- KEUNTUNGAN 9,0 % x D 5.232,21Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 63.949,25Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 63.949,00Rp
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
-
7/26/2019 4. Analisa Harga
27/80
-
7/26/2019 4. Analisa Harga
28/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : PEKERJAAN PEMASANGAN PINTU
SATUAN PEMBAYARAN : Bh
A. TENAGA
1. Pekerja OH 0,700 80.000,00 56.000,00Rp
2. Tukang OH 0,350 90.000,00 31.500,00Rp
3. Kepala Tukang OH 0,035 100.000,00 3.500,00Rp
4. Mandor OH 0,070 110.000,00 7.700,00Rp
98.700,00Rp
B. BAHAN
1. Pintu Panel Bh 1,000 850.000,00 850.000,00Rp
850.000,00Rp
C. PERALATAN
-Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 948.700,00Rp
E. - BIAYA UMUM 1,0 % x D 9.487,00Rp
- KEUNTUNGAN 9,0 % x D 85.383,00Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 1.043.570,00Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 1.043.570,00Rp
NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
-
7/26/2019 4. Analisa Harga
29/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : PEKERJAAN PEMASANGAN JENDELA
SATUAN PEMBAYARAN : Bh
A. TENAGA
1. Pekerja OH 0,500 80.000,00 40.000,00Rp
2. Tukang OH 0,250 90.000,00 22.500,00Rp
3. Kepala Tukang OH 0,025 100.000,00 2.500,00Rp
4. Mandor OH 0,050 110.000,00 5.500,00Rp
70.500,00Rp
B. BAHAN
1. Jendela Bh 1,000 500.000,00 500.000,00Rp
500.000,00Rp
C. PERALATAN
-Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 570.500,00Rp
E. - BIAYA UMUM 1,0 % x D 5.705,00Rp
- KEUNTUNGAN 9,0 % x D 51.345,00Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 627.550,00Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 627.550,00Rp
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
-
7/26/2019 4. Analisa Harga
30/80
-
7/26/2019 4. Analisa Harga
31/80
-
7/26/2019 4. Analisa Harga
32/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : PIPA PVC dia. 75 mm
SATUAN PEMBAYARAN : BH
A. TENAGA
1. Pekerja OH 0,080 80.000,00 6.400,00Rp
2. Tukang OH 0,040 90.000,00 3.600,00Rp
3. Kepala Tukang OH 0,004 100.000,00 400,00Rp
4. Mandor OH 0,008 110.000,00 880,00Rp
11.280,00Rp
B. BAHAN
1. Pipa PVC dia. 75 mm M' 1,000 50.000,00 50.000,00Rp
50.000,00Rp
C. PERALATAN
-Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 61.280,00Rp
E. - BIAYA UMUM 1,0 % x D 612,80Rp
- KEUNTUNGAN 9,0 % x D 5.515,20Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 67.408,00Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 67.408,00Rp
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA
-
7/26/2019 4. Analisa Harga
33/80
-
7/26/2019 4. Analisa Harga
34/80
-
7/26/2019 4. Analisa Harga
35/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : PASANGAN BATU KALI CAMP 1 PC : 3 PS
SATUAN PEMBAYARAN : M3
A. TENAGA
1. Pekerja OH 2,700 80.000,00 216.000,00Rp
2. Tukang OH 0,900 90.000,00 81.000,00Rp
3. Kepala Tukang OH 0,090 100.000,00 9.000,00Rp
4. Mandor OH 0,270 110.000,00 29.700,00Rp
335.700,00Rp
B. BAHAN
1. PC/ Portland Cement Kg 202,000 2.122,00 428.644,00Rp
2. Pasir Pasang M 0,485 215.200,00 104.372,00Rp
3. Batu Belah 10/15 cm M 1,200 333.100,00 399.720,00Rp
932.736,00Rp
C. PERALATAN
-Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.268.436,00Rp
E. - BIAYA UMUM 1,0 % x D 12.684,36Rp
- KEUNTUNGAN 9,0 % x D 114.159,24Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 1.395.279,60Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 1.395.279,00Rp
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA
-
7/26/2019 4. Analisa Harga
36/80
-
7/26/2019 4. Analisa Harga
37/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : PENYAMBUNGAN PIPA HDPE 150 mm
SATUAN PEMBAYARAN : M'
A. TENAGA
1. Pekerja OH 2,096 80.000,00 167.680,00Rp
2. Tukang OH 1,048 90.000,00 94.320,00Rp
3. Mandor OH 0,210 110.000,00 23.100,00Rp
285.100,00Rp
B. BAHAN
1. Bensin Liter 0,650 10.000,00 6.500,00Rp
6.500,00Rp
C. PERALATAN
1. Butt Fusion Unit / Jam 0,062 150.000,00 9.300,00Rp2. Generator Set Unit / Jam 0,062 120.000,00 7.440,00Rp
16.740,00Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 308.340,00Rp
E. - BIAYA UMUM 1,0 % x D 3.083,40Rp
- KEUNTUNGAN 9,0 % x D 27.750,60Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 339.174,00Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 339.174,00Rp
JUMLAH HARGA
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. URAIAN SATUAN VOLUME HARGA
-
7/26/2019 4. Analisa Harga
38/80
-
7/26/2019 4. Analisa Harga
39/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : PEMASANGAN PIPA HDPE 160 MM
SATUAN PEMBAYARAN : M'
A. TENAGA
1. Pekerja OH 0,062 80.000,00 4.960,00Rp
2. Tukang OH 0,006 90.000,00 558,00Rp
3 Mandor OH 0,031 110.000,00 3.410,00Rp
8.928,00Rp
B. BAHAN
1. Pipa HDPE 160 mm M' 1,000 150.000,00 150.000,00Rp
150.000,00Rp
C. PERALATAN
1. Tripod Jam 0,019 75.000,00 1.425,00Rp
1.425,00Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 160.353,00Rp
E. - BIAYA UMUM 1,0 % x D 1.603,53Rp
- KEUNTUNGAN 9,0 % x D 14.431,77Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 176.388,30Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 176.388,00Rp
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
-
7/26/2019 4. Analisa Harga
40/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : PENYAMBUNGAN PIPA HDPE 160 mm
SATUAN PEMBAYARAN : M'
A. TENAGA
1. Pekerja OH 2,096 80.000,00 167.680,00Rp
2. Tukang OH 1,048 90.000,00 94.320,00Rp
3. Mandor OH 0,210 110.000,00 23.100,00Rp
285.100,00Rp
B. BAHAN
1. Bensin Liter 0,650 10.000,00 6.500,00Rp
6.500,00Rp
C. PERALATAN
1. Butt Fusion Unit / Jam 0,062 150.000,00 9.300,00Rp2. Generator Set Unit / Jam 0,062 120.000,00 7.440,00Rp
16.740,00Rp
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 308.340,00Rp
E. - BIAYA UMUM 1,0 % x D 3.083,40Rp
- KEUNTUNGAN 9,0 % x D 27.750,60Rp
F. HARGA SATUAN PEKERJAAN ( D + E ) 339.174,00Rp
G. HARGA SATUAN PEKERJAAN DIBULATKAN 339.174,00Rp
JUMLAH HARGA
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
NO. URAIAN SATUAN VOLUME HARGA
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
-
7/26/2019 4. Analisa Harga
41/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : PEKERJAAN PIPA HDPE 160 mm
SATUAN PEMBAYARAN : M'
1. Galian Tanah Biasa Manual M 0,3600 56.356,00 20.288,16Rp
2. Pemasangan Pipa HDPE 160 mm M' 1,0000 176.388,00 176.388,00Rp
3. Penyambunagn Pipa HDPE 160 mm Titik 0,1667 56.529,00 9.421,50Rp
4. Timbunan Tanah Kembali (manual) M 0,3522 33.033,00 11.634,22Rp
A. JUMLAH HARGA SATUAN 217.731,88Rp
B. HARGA SATUAN PEKERJAAN DIBULATKAN 217.731,00Rp
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA
-
7/26/2019 4. Analisa Harga
42/80
-
7/26/2019 4. Analisa Harga
43/80
PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA
SATKER :
LOKASI : KABUPATEN KUBU RAYA
THN. ANGGARAN : 2016
ITEM PEMBAYARAN NOMOR : -
JENIS PEKERJAAN : PEKERJAAN PIPA HDPE 63 mm
SATUAN PEMBAYARAN : M'
1. Galian Tanah Biasa Manual M 0,3600 56.356,00 20.288,16Rp
2. Pemasangan Pipa HDPE 160 mm M' 1,0000 40.001,00 40.001,00Rp
4. Timbunan Tanah Kembali (manual) M 0,3522 33.033,00 11.634,22Rp
A. JUMLAH HARGA SATUAN 71.923,38Rp
B. HARGA SATUAN PEKERJAAN DIBULATKAN 71.923,00Rp
JUMLAH HARGA
ANALISA HARGA SATUAN PEKERJAAN
NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN
PROVINSI KALIMANTAN BARAT
NO. URAIAN SATUAN VOLUME HARGA
-
7/26/2019 4. Analisa Harga
44/80
Satuan Kerja : Non Vertikal Tertentu Pelaksanaan Jaringan Sumber Air Kalimantan Provinsi Kalimantan BaratKegiatan : Prasarana Konservasi Sumber Daya Air
Pekerjaan : Pembangunan Embung Padu Empat Kab. Kubu Raya
Lokasi : Kabupaten Kubu Raya
Tahun Anggaran : 2016
Sumber Dana : APBN - Murni
No.HARGA SATUAN
UPAH / HARI
1 Kepala Tukang 100.000,00Rp
2 Tukang 90.000,00Rp
3 Tukang Pipa 90.000,00Rp
4 Mandor 110.000,00Rp
5 Pekerja 80.000,00Rp
6 Tenaga Pengukuran 110.000,00Rp
7 Operator 110.000,00Rp
8 Pembantu Operator 100.000,00Rp
9 Foreman Equipment 90.000,00Rp
10 Mekanik 110.000,00Rp
11 Pembantu Mekanik 100.000,00Rp
#REF!
Dibuat Oleh
#REF!
#REF!
#REF!
#REF!
DAFTAR HARGA DASAR SATUAN UPAH
JENIS TENAGA
Manokwari, 13 Desember 2015
Dibuat OlehPT. ANI SUBAM PERKASA
BENNY BAHO
Direktur
-
7/26/2019 4. Analisa Harga
45/80
-
7/26/2019 4. Analisa Harga
46/80
-
7/26/2019 4. Analisa Harga
47/80
-
7/26/2019 4. Analisa Harga
48/80
-
7/26/2019 4. Analisa Harga
49/80
No. U R A I A N KODE KOEF. SATUAN KET.
A. URAIAN PERALATAN
1. Jenis Peralatan E02
2 . Tenaga Pw 75,0 HP
3. Kapasitas Cp 5,4 M3
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 2.300.000.000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2.000,0 Jam
c. Harga Alat (*) B' 2.300.000.000 Rupiah
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 230.000.000 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,33438 -
(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 346.082,99 Rupiah
W'
b. Asuransi, dll = 0,02 x B' F 23.000,00 Rupiah
W'
Biaya Pasti per Jam = ( E + F ) G 369.082,99 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.12 s/d 0.175 ) x Pw x Ms H 135.000,00 Rupiah
2. Pelumas = (0.035 s/d 0.06 ) x Pw x Mp I 37.500,00 Rupiah
3. Spare part = (0.125 s/d 0.175) x B K1 143.750,00 Rupiah
W'
4. Workshop = (0.0625 s/d 0.0.0875) x B K2 100.625,00 Rupiah
W'
5. Operator = ( 1 Orang / Jam ) x U1 L 13.750,00 Rupiah
6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 12.500,00 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 443.125,00 Rupiah
D. LAIN - LAIN
1. Tingkat Suku Bunga i 20,00 % / Tahun
2. Upah Operator / Sopir U1 13.750,00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12.500,00 Rp./Jam
4. Bahan Bakar Bensin Mb 10.000,00 Liter
5. Bahan Bakar Solar Ms 15.000,00 Liter
6. Minyak Pelumas Mp 20.000,00 Liter
7. Koefisien bahan bakar Kbb 0,120 - Pek. Ringan
8. Koefisien pelumas Kp 0,025 - Pek. Ringan
9. Koefisien spare part Kpp 0,125 - Pek. Ringan
10. Koefisien workshop Kws 0,088 -
11. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pemilikan / Biaya pasti per jam B. 369.082,99
Biaya Operasi per jam C. 443.125,00
Biaya kepemilikan dan operasi B + C 812.207,99
Dibulatkan 812.207,00
URAIAN ANALISA ALAT
Buldozer
-
7/26/2019 4. Analisa Harga
50/80
No. U R A I A N KODE KOEF. SATUAN KET.
A. URAIAN PERALATAN
1. Jenis Peralatan E03
2 . Tenaga Pw 96,0 HP
3. Kapasitas Cp 1,5 M3
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 1.500.000.000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2.000,0 Jam
c. Harga Alat (*) B' 1.500.000.000 Rupiah
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 150.000.000 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,33438 -
(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 225.706,30 Rupiah
W'
b. Asuransi, dll = 0,02 x B' F 15.000,00 Rupiah
W'
Biaya Pasti per Jam = ( E + F ) G 240.706,30 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.12 s/d 0.175 ) x Pw x Ms H 172.800,00 Rupiah
2. Pelumas = (0.035 s/d 0.06 ) x Pw x Mp I 48.000,00 Rupiah
3. Spare part = (0.125 s/d 0.175) x B K1 93.750,00 Rupiah
W'
4. Workshop = (0.0625 s/d 0.0.0875) x B K2 65.625,00 Rupiah
W'
5. Operator = ( 1 Orang / Jam ) x U1 L 13.750,00 Rupiah
6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 12.500,00 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 406.425,00 Rupiah
D. LAIN - LAIN
1. Tingkat Suku Bunga i 20,00 % / Tahun
2. Upah Operator / Sopir U1 13.750,00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12.500,00 Rp./Jam
4. Bahan Bakar Bensin Mb 10.000,00 Liter
5. Bahan Bakar Solar Ms 15.000,00 Liter
6. Minyak Pelumas Mp 20.000,00 Liter
7. Koefisien bahan bakar Kbb 0,120 - Pek. Ringan
8. Koefisien pelumas Kp 0,025 - Pek. Ringan
9. Koefisien spare part Kpp 0,125 - Pek. Ringan
10. Koefisien workshop Kws 0,088 -
11. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pemilikan / Biaya pasti per jam B. 240.706,30
Biaya Operasi per jam C. 406.425,00
Biaya kepemilikan dan operasi B + C 647.131,30
Dibulatkan 647.131,00
URAIAN ANALISA ALAT
Wheel Loader
-
7/26/2019 4. Analisa Harga
51/80
-
7/26/2019 4. Analisa Harga
52/80
-
7/26/2019 4. Analisa Harga
53/80
-
7/26/2019 4. Analisa Harga
54/80
No. U R A I A N KODE KOEF. SATUAN KET.
A. URAIAN PERALATAN
1. Jenis Peralatan E07
2. Tenaga Pw 100,0 HP
3. Kapasitas Cp 4.000,0 Liter
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 250.000.000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2.000,0 Jam
c. Harga Alat (*) B' 250.000.000 Rupiah
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 25.000.000 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,33438 -
(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 37.617,72 Rupiah
W'
b. Asuransi, dll = 0,02 x B' F 2.500,00 Rupiah
W'
Biaya Pasti per Jam = ( E + F ) G 40.117,72 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.12 s/d 0.175 ) x Pw x Ms H 180.000,00 Rupiah
2. Pelumas = (0.035 s/d 0.06 ) x Pw x Mp I 50.000,00 Rupiah
3. Spare part = (0.125 s/d 0.175) x B K1 15.625,00 Rupiah
W'
4. Workshop = (0.0625 s/d 0.0.0875) x B K2 10.937,50 Rupiah
W'
5. Operator = ( 1 Orang / Jam ) x U1 L 13.750,00 Rupiah
6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 12.500,00 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 282.812,50 Rupiah
D. LAIN - LAIN
1. Tingkat Suku Bunga i 20,00 % / Tahun
2. Upah Operator / Sopir U1 13.750,00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12.500,00 Rp./Jam
4. Bahan Bakar Bensin Mb 10.000,00 Liter
5. Bahan Bakar Solar Ms 15.000,00 Liter
6. Minyak Pelumas Mp 20.000,00 Liter
7. Koefisien bahan bakar Kbb 0,120 - Pek. Ringan
8. Koefisien pelumas Kp 0,025 - Pek. Ringan
9. Koefisien spare part Kpp 0,125 - Pek. Ringan
10. Koefisien workshop Kws 0,088 -
11. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pemilikan / Biaya pasti per jam B. 40.117,72
Biaya Operasi per jam C. 282.812,50
Biaya kepemilikan dan operasi B + C 322.930,22
Dibulatkan 322.930,00
URAIAN ANALISA ALAT
Water Tank truck
-
7/26/2019 4. Analisa Harga
55/80
No. U R A I A N KODE KOEF. SATUAN KET.
A. URAIAN PERALATAN
1. Jenis Peralatan E08
2 . Tenaga Pw 20,0 HP
3. Kapasitas Cp 500,00 liter
4. Alat Baru : a. Umur Ekonomis A 2,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 35.000.000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 2,0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2.000,0 Jam
c. Harga Alat (*) B' 35.000.000 Rupiah
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 3.500.000 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,65455 -
(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 10.309,09 Rupiah
W'
b. Asuransi, dll = 0,02 x B' F 350,00 Rupiah
W'
Biaya Pasti per Jam = ( E + F ) G 10.659,09 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.12 s/d 0.175 ) x Pw x Ms H 36.000,00 Rupiah
2. Pelumas = (0.035 s/d 0.06 ) x Pw x Mp I 10.000,00 Rupiah
3. Spare part = (0.125 s/d 0.175) x B K1 2.187,50 Rupiah
W'
4. Workshop = (0.0625 s/d 0.0.0875) x B K2 1.531,25 Rupiah
W'
5. Operator = ( 1 Orang / Jam ) x U1 L 13.750,00 Rupiah
6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 12.500,00 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 75.968,75 Rupiah
D. LAIN - LAIN
1. Tingkat Suku Bunga i 20,00 % / Tahun
2. Upah Operator / Sopir U1 13.750,00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12.500,00 Rp./Jam
4. Bahan Bakar Bensin Mb 10.000,00 Liter
5. Bahan Bakar Solar Ms 15.000,00 Liter
6. Minyak Pelumas Mp 20.000,00 Liter
7. Koefisien bahan bakar Kbb 0,120 - Pek. Ringan
8. Koefisien pelumas Kp 0,025 - Pek. Ringan
9. Koefisien spare part Kpp 0,125 - Pek. Ringan
10. Koefisien workshop Kws 0,088 -
11. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pemilikan / Biaya pasti per jam B. 10.659,09
Biaya Operasi per jam C. 75.968,75
Biaya kepemilikan dan operasi B + C 86.627,84
Dibulatkan 86.627,00
URAIAN ANALISA ALAT
Concrete Mixer
-
7/26/2019 4. Analisa Harga
56/80
No. U R A I A N KODE KOEF. SATUAN KET.
A. URAIAN PERALATAN
1. Jenis Peralatan E09
2. Tenaga Pw 5,5 HP
3. Kapasitas Cp 25,0 -
4. Alat Baru : a. Umur Ekonomis A 4,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 12.500.000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4,0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2.000,0 Jam
c. Harga Alat (*) B' 12.500.000 Rupiah
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 1.250.000 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,38629 -
(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 2.172,88 Rupiah
W'
b. Asuransi, dll = 0,02 x B' F 125,00 Rupiah
W'
Biaya Pasti per Jam = ( E + F ) G 2.297,88 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.12 s/d 0.175 ) x Pw x Ms H 9.900,00 Rupiah
2. Pelumas = (0.035 s/d 0.06 ) x Pw x Mp I 2.750,00 Rupiah
3. Spare part = (0.125 s/d 0.175) x B K1 781,25 Rupiah
W'
4. Workshop = (0.0625 s/d 0.0.0875) x B K2 546,88 Rupiah
W'
5. Operator = ( 1 Orang / Jam ) x U1 L 13.750,00 Rupiah
6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 12.500,00 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 40.228,13 Rupiah
D. LAIN - LAIN
1. Tingkat Suku Bunga i 20,00 % / Tahun
2. Upah Operator / Sopir U1 13.750,00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12.500,00 Rp./Jam
4. Bahan Bakar Bensin Mb 10.000,00 Liter
5. Bahan Bakar Solar Ms 15.000,00 Liter
6. Minyak Pelumas Mp 20.000,00 Liter
7. Koefisien bahan bakar Kbb 0,120 - Pek. Ringan
8. Koefisien pelumas Kp 0,025 - Pek. Ringan
9. Koefisien spare part Kpp 0,125 - Pek. Ringan
10. Koefisien workshop Kws 0,088 -
11. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pemilikan / Biaya pasti per jam B. 2.297,88
Biaya Operasi per jam C. 40.228,13
Biaya kepemilikan dan operasi B + C 42.526,00
Dibulatkan 42.526,00
URAIAN ANALISA ALAT
Concrete Vibrator
-
7/26/2019 4. Analisa Harga
57/80
-
7/26/2019 4. Analisa Harga
58/80
-
7/26/2019 4. Analisa Harga
59/80
No. U R A I A N KODE KOEF. SATUAN KET.
A. URAIAN PERALATAN
1. Jenis Peralatan E12
2. Tenaga Pw 175,0 HP
3. Kapasitas Cp 20,0 Ton
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 1.200.000.000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2.000,0 Jam
c. Harga Alat (*) B' 1.200.000.000 Rupiah
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 120.000.000 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,33438 -
(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 180.565,04 Rupiah
W'
b. Asuransi, dll = 0,02 x B' F 12.000,00 Rupiah
W'
Biaya Pasti per Jam = ( E + F ) G 192.565,04 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.12 s/d 0.175 ) x Pw x Ms H 315.000,00 Rupiah
2. Pelumas = (0.035 s/d 0.06 ) x Pw x Mp I 87.500,00 Rupiah
3. Spare part = (0.125 s/d 0.175) x B K1 75.000,00 Rupiah
W'
4. Workshop = (0.0625 s/d 0.0.0875) x B K2 52.500,00 Rupiah
W'
5. Operator = ( 1 Orang / Jam ) x U1 L 13.750,00 Rupiah
6. Pembantu Operator = ( 3 Orang / Jam ) x U2 M 37.500,00 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 581.250,00 Rupiah
D. LAIN - LAIN
1. Tingkat Suku Bunga i 20,00 % / Tahun
2. Upah Operator / Sopir U1 13.750,00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12.500,00 Rp./Jam
4. Bahan Bakar Bensin Mb 10.000,00 Liter
5. Bahan Bakar Solar Ms 15.000,00 Liter
6. Minyak Pelumas Mp 20.000,00 Liter
7. Koefisien bahan bakar Kbb 0,120 - Pek. Ringan
8. Koefisien pelumas Kp 0,025 - Pek. Ringan
9. Koefisien spare part Kpp 0,125 - Pek. Ringan
10. Koefisien workshop Kws 0,088 -
11. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pemilikan / Biaya pasti per jam B. 192.565,04
Biaya Operasi per jam C. 581.250,00
Biaya kepemilikan dan operasi B + C 773.815,04
Dibulatkan 773.815,00
URAIAN ANALISA ALAT
TRAILER 20 TON
-
7/26/2019 4. Analisa Harga
60/80
No. U R A I A N KODE KOEF. SATUAN KET.
A. URAIAN PERALATAN
1. Jenis Peralatan E12 2 . Tenaga Pw 40,0 HP
3. Kapasitas Cp 250,0 Ton
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 200.000.000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W' 2.000,0 Jam
c. Harga Alat (*) B' 200.000.000 Rupiah
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 20.000.000 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,33438 -
(1 + i)^A' - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = ( B' - C ) x D E 30.094,17 Rupiah
W'
b. Asuransi, dll = 0,02 x B' F 2.000,00 Rupiah
W'
Biaya Pasti per Jam = ( E + F ) G 32.094,17 Rupiah
C. BIAYA OPERASI PER JAM KERJA
1. Bahan Bakar = (0.12 s/d 0.175 ) x Pw x Ms H 72.000,00 Rupiah
2. Pelumas = (0.035 s/d 0.06 ) x Pw x Mp I 20.000,00 Rupiah
3. Spare part = (0.125 s/d 0.175) x B K1 12.500,00 Rupiah
W'
4. Workshop = (0.0625 s/d 0.0.0875) x B K2 8.750,00 Rupiah
W'
5. Operator = ( 1 Orang / Jam ) x U1 L 13.750,00 Rupiah
6. Pembantu Operator = ( 3 Orang / Jam ) x U2 M 37.500,00 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 164.500,00 Rupiah
D. LAIN - LAIN
1. Tingkat Suku Bunga i 20,00 % / Tahun
2. Upah Operator / Sopir U1 13.750,00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12.500,00 Rp./Jam4. Bahan Bakar Bensin Mb 10.000,00 Liter
5. Bahan Bakar Solar Ms 15.000,00 Liter
6. Minyak Pelumas Mp 20.000,00 Liter
7. Koefisien bahan bakar Kbb 0,120 - Pek. Ringan
8. Koefisien pelumas Kp 0,025 - Pek. Ringan
9. Koefisien spare part Kpp 0,125 - Pek. Ringan
10. Koefisien workshop Kws 0,088 -
11. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pemilikan / Biaya pasti per jam B. 32.094,17
Biaya Operasi per jam C. 164.500,00
Biaya kepemilikan dan operasi B + C 196.594,17
Dibulatkan 196.594,00
URAIAN ANALISA ALAT
WELDING SET
-
7/26/2019 4. Analisa Harga
61/80
-
7/26/2019 4. Analisa Harga
62/80
Jenis : Pasir Pasang
Lokasi : Quarry
Tujuan : Base Camp
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : sedang / baik
3 Jarak Quarry ke lokasi Base Camp L 5,00 Km
4 Harga satuan pasir di Quarry RpM01 1,00 M3 150.000,00
5 Harga Satuan Dasar Excavator RpE01 1,00 Jam 665.551,00
6 Harga Satuan Dasar Dump Truck RpE06 1,00 Jam 349.602,00
II. URUTAN KERJA
1 Pasir digali dengan Excavator
2 Excavator sekaligus memuat pasir hasil
galian ke dalam Dump Truck
3 Dump Truck mengangkut pasir ke lokasi
Base Camp
III. PERHITUNGAN
EXCAVATOR E01
Kapasitas Bucket V 0,90 M3
Faktor Bucket Fb 0,80 Muat Sedang
Faktor Efisiensi alat Fa 0,75 - Kondisi Baik
Faktor Pengembangan Bahan Fh 1,10 Asli - Lepas
Waktu siklus / Cycle Time CT
- Waktu Gali T1 15,00 Detik
- Waktu Buang / Muat T2 8,00 Detik
- Waktu Swing T3 8,00 Detik
CT 31,00 Detik
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 57,01 M3 / Jam
Ts1 x Fh
Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 11.674,53 Rupiah
DUMP TRUCK E06
Kapasitas bak V 3,00 M3
Faktor efisiensi alat Fa 0,75 - Kondisi Baik
Kecepatan rata-rata bermuatan v1 40,00 KM/Jam
Kecepatan rata-rata kosong v2 60,00 KM/Jam
Waktu siklus Ts2
- Waktu tempuh isi = (L/v1) x 60 T1 7,50 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 5,00 menit
- Muat = (V/Q1) x 60 T3 3,16 menit
- Lain-lain T4 5,00 menit
Ts2 20,66 menit
ANALISA HARGA DASAR SATUAN BAHAN
-
7/26/2019 4. Analisa Harga
63/80
Jenis : Pasir Pasang
Lokasi : Quarry
Tujuan : Base Camp
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
Kapasitas Produksi / Jam =
V x Fa x 60 Q2 6,54 M3 / Jam
Ts2
Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 53.495,34 Rupiah
IV. HARGA SATUAN DASAR BAHAN
DI LOKASI BASE CAMP
Harga Satuan Dasar Pasir =
( RpM01 + Rp1 + Rp2 ) M01 215.169,87 Rupiah
Dibulatkan : M01 215.200,00 Rupiah
dipindahkan ke Daftar Harga Satuan Upah, Bahan
dan peralatan
ANALISA HARGA DASAR SATUAN BAHAN
-
7/26/2019 4. Analisa Harga
64/80
Jenis : Pasir Beton
Lokasi : Quarry
Tujuan : Base Camp
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : sedang / baik
3 Jarak Quarry ke lokasi Base Camp L 5,00 Km
4 Harga satuan pasir di Quarry RpM01 1,00 M3 150.000,00
5 Harga Satuan Dasar Excavator RpE01 1,00 Jam 665.551,00
6 Harga Satuan Dasar Dump Truck RpE06 1,00 Jam 349.602,00
II. URUTAN KERJA
1 Pasir digali dengan Excavator
2 Excavator sekaligus memuat pasir hasil
galian ke dalam Dump Truck
3 Dump Truck mengangkut pasir ke lokasi
Base Camp
III. PERHITUNGAN
EXCAVATOR E01
Kapasitas Bucket V 0,90 M3
Faktor Bucket Fb 1,00 Muat Sedang
Faktor Efisiensi alat Fa 0,75 - Kondisi Baik
Faktor Pengembangan Bahan Fh 1,10 Asli - Lepas
Waktu siklus / Cycle Time CT
- Waktu Gali T1 15,00 Detik
- Waktu Buang / Muat T2 8,00 Detik
- Waktu Swing T3 8,00 Detik
CT 31,00 Detik
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 71,26 M3 / Jam
Ts1 x Fh
Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 9.339,63 Rupiah
DUMP TRUCK E06
Kapasitas bak V 3,00 M3
Faktor efisiensi alat Fa 0,75 - Kondisi Baik
Kecepatan rata-rata bermuatan v1 40,00 KM/Jam
Kecepatan rata-rata kosong v2 60,00 KM/Jam
Waktu siklus Ts2
- Waktu tempuh isi = (L/v1) x 60 T1 7,50 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 5,00 menit
- Muat = (V/Q1) x 60 T3 2,53 menit
- Lain-lain T4 5,00 menit
Ts2 20,03 menit
ANALISA HARGA DASAR SATUAN BAHAN
-
7/26/2019 4. Analisa Harga
65/80
-
7/26/2019 4. Analisa Harga
66/80
Jenis : Koral Beton
Lokasi : Quarry
Tujuan : Base Camp
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : sedang / baik
3 Jarak Quarry ke lokasi Base Camp L 5,00 Km
4 Harga satuan koral beton di Quarry RpM01 1,00 M3 250.000,00
5 Harga Satuan Dasar Excavator RpE01 1,00 Jam 665.551,00
6 Harga Satuan Dasar Dump Truck RpE06 1,00 Jam 349.602,00
II. URUTAN KERJA
1 Koral digali dengan Excavator
2 Excavator sekaligus memuat koral hasil
galian ke dalam Dump Truck
3 Dump Truck mengangkut koral ke lokasi
Base Camp
III. PERHITUNGAN
EXCAVATOR E01
Kapasitas Bucket V 0,90 M3
Faktor Bucket Fb 0,60 Muat Sulit
Faktor Efisiensi alat Fa 0,75 - Kondisi Baik
Faktor Pengembangan Bahan Fh 1,25 Asli - Lepas
Waktu siklus / Cycle Time CT
- Waktu Gali T1 15,00 Detik
- Waktu Buang / Muat T2 8,00 Detik
- Waktu Swing T3 8,00 Detik
CT 31,00 Detik
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 37,63 M3 / Jam
Ts1 x Fh
Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 17.688,68 Rupiah
DUMP TRUCK E06
Kapasitas bak V 3,00 M3
Faktor efisiensi alat Fa 0,75 - Kondisi Baik
Kecepatan rata-rata bermuatan v1 40,00 KM/Jam
Kecepatan rata-rata kosong v2 60,00 KM/Jam
Waktu siklus Ts2
- Waktu tempuh isi = (L/v1) x 60 T1 7,50 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 5,00 menit
- Muat = (V/Q1) x 60 T3 4,78 menit
- Lain-lain T4 5,00 menit
Ts2 22,28 menit
ANALISA HARGA DASAR SATUAN BAHAN
-
7/26/2019 4. Analisa Harga
67/80
Jenis : Koral Beton
Lokasi : Quarry
Tujuan : Base Camp
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
Kapasitas Produksi / Jam =
V x Fa x 60 Q2 6,06 M3 / Jam
Ts2
Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 57.707,51 Rupiah
IV. HARGA SATUAN DASAR BAHAN
DI LOKASI BASE CAMP
Harga Satuan Dasar Pasir =
( RpM01 + Rp1 + Rp2 ) M01 325.396,19 Rupiah
Dibulatkan : M01 325.400,00 Rupiah
dipindahkan ke Daftar Harga Satuan Upah, Bahan
dan peralatan
ANALISA HARGA DASAR SATUAN BAHAN
-
7/26/2019 4. Analisa Harga
68/80
-
7/26/2019 4. Analisa Harga
69/80
-
7/26/2019 4. Analisa Harga
70/80
-
7/26/2019 4. Analisa Harga
71/80
Jenis : Batu Pecah M esin 2/3
Lokasi : Stone Craser
Tujuan : Base Camp
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
Kapasitas Produksi / Jam =
V x Fa x 60 Q2 4,11 M3 / Jam
Ts2
Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 85.122,57 Rupiah
IV. HARGA SATUAN DASAR BAHAN
DI LOKASI BASE CAMP
Harga Satuan Dasar Pasir =
( RpM01 + Rp1 + Rp2 ) M01 495.735,78 Rupiah
Dibulatkan : M01 495.700,00 Rupiah
dipindahkan ke Daftar Harga Satuan Upah, Bahan
dan peralatan
ANALISA HARGA DASAR SATUAN BAHAN
-
7/26/2019 4. Analisa Harga
72/80
-
7/26/2019 4. Analisa Harga
73/80
Jenis : Batu Belah 10/15 cm
Lokasi : Quarry
Tujuan : Base Camp
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
Kapasitas Produksi / Jam =
V x Fa x 60 Q2 3,48 M3 / Jam
Ts2
Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 100.516,57 Rupiah
IV. HARGA SATUAN DASAR BAHAN
DI LOKASI BASE CAMP
Harga Satuan Dasar Pasir =
( RpM01 + Rp1 + Rp2 ) M01 333.109,40 Rupiah
Dibulatkan : M01 333.100,00 Rupiah
dipindahkan ke Daftar Harga Satuan Upah, Bahan
dan peralatan
ANALISA HARGA DASAR SATUAN BAHAN
-
7/26/2019 4. Analisa Harga
74/80
Jenis : Semen ( 50 Kg/Zak)
Lokasi : Kota
Tujuan : Base camp
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
1 Menggunakan Kendaran roda empat
2 Kondisi Jalan : sedang / baik
3 Jarak toko ke lokasi Kerja L 20,00 Km
4 Harga satuan Semen di RpM09 1,00 Zak 80.000,00
5 Harga Satuan Dasar Dump Truck RpE06 1,00 Jam 349.602,00
II. URUTAN KERJA
1
2 Setelah semen sampai di lokasi kerja dimasukan
dalam gudang
III. PERHITUNGAN
Biaya pembelian semen di . Rp.01 1.600,00 kg
Biaya menaikan dan menurunkan semen di truck Rp.02 100,00 kg
Biaya Penggudangan Rp.03 100,00 kg
DUMP TRUCK (E08)
Kapasitas bak V 3.500,00 KgFaktor efisiensi alat Fa 0,75 - Kondisi Baik
Kecepatan rata-rata bermuatan v1 40,00 KM/Jam
Kecepatan rata-rata kosong v2 60,00 KM/Jam
Waktu siklus Ts2
- Waktu tempuh isi = (L/v1) x 60 T1 30,00 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 20,00 menit
- Waktu bongkar Muat T3 90,00 menit
- Lain-lain T4 5,00 menit
TsL 145,00 menit
Kapst Produksi/Jam =
V x Fa x 60 Q1 1.086,21 Kg/Jam
Tsl
Biaya Dump Truck/Kg = (L1/Q1) x Rp. E 08 Rp.04 321,86 Rp/Kg
IV HARGA SATUAN DASAR SEMEN DI LOKASI KERJA
Harga Satuan Semen
= (Rp.01 + Rp.02 + Rp.03 + Rp. 04) M09 2.121,86 Kg/Rp
M09 106.092,79 Zak/Rp
Dibulatkan : M09 106.100,00 Rupiah
dipindahkan ke Daftar Harga Satuan Upah,
Bahan dan Peralatan
Semen dibeli di ..., diangkut dengan menggunakan
tenaga manusia kemudian diangkut ke lokasi kerja
dengan truck
ANALISA HARGA DASAR SATUAN BAHAN
-
7/26/2019 4. Analisa Harga
75/80
Jenis : Baja Tulangan
Lokasi : Kota .
Tujuan : Base Camp
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
1 Menggunakan Kendaran roda empat
2 Kondisi Jalan : sedang / baik
3 Jarak toko ke lokasi Kerja L 20,00 Km
4 Harga satuan Baja tulangan di RpM10 1,00 Kg 20.000,00
5 Harga Satuan Dasar Dump Truck RpE08 1,00 Jam 349.602,00
II. URUTAN KERJA
1
III. PERHITUNGAN
Biaya pembelian Baja Tulangan di .. Rp.01 20.000,00 kg
Biaya menaikan dan menurunkan Baja Tulangan di truck Rp.02 500,00 kg
Biaya Penggudangan Rp.02 100,00 kg
DUMP TRUCK (E08)
Kapasitas bak V 3.500,00 Kg
Faktor efisiensi alat Fa 0,75 - Kondisi Baik
Kecepatan rata-rata bermuatan v1 40,00 KM/Jam
Kecepatan rata-rata kosong v2 50,00 KM/Jam
Waktu siklus Ts2
- Waktu tempuh isi = (L/v1) x 60 T1 30,00 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 24,00 menit
- Waktu bongkar Muat T3 120,00 menit
- Lain-lain T4 30,00 menit
TsL 204,00 menit
Kapst Produksi/Jam =
V x Fa x 60 Q1 772,06 Kg/Jam
Tsl
Biaya Dump Truck/Kg = (L1/Q1) x Rp. E 08 Rp.04 452,82 Rp/Kg
IV HARGA SATUAN DASAR BAJA TULANGAN DI LOKASI KERJA
Harga Satuan Semen
= (Rp.01 + Rp.02 + Rp.03 + Rp. 04) M10 21.052,82 Kg/Rp
Dibulatkan : M10 21.100,00 Rupiah
dipindahkan ke Daftar Harga Satuan Upah,
Bahan dan Peralatan
ANALISA HARGA DASAR SATUAN BAHAN
Baja Tulangan dibeli di ..., diangkut dengan
menggunakan tenaga manusia kemudian diangkut ke
lokasi kerja
-
7/26/2019 4. Analisa Harga
76/80
Jenis : Kawat Ikat Beton
Lokasi : Kota .
Tujuan : Base Camp
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
1 Menggunakan Kendaran roda empat
2 Kondisi Jalan : sedang / baik
3 Jarak toko ke lokasi Kerja L 20,00 Km
4 Harga satuan Baja tulangan di RpM10 1,00 Kg 22.000,00
5 Harga Satuan Dasar Dump Truck RpE08 1,00 Jam 349.602,00
II. URUTAN KERJA
1
III. PERHITUNGAN
Biaya pembelian Baja Tulangan di .. Rp.01 22.000,00 kg
Biaya menaikan dan menurunkan Baja Tulangan di truck Rp.02 500,00 kg
Biaya Penggudangan Rp.02 100,00 kg
DUMP TRUCK (E08)
Kapasitas bak V 3.500,00 Kg
Faktor efisiensi alat Fa 0,75 - Kondisi Baik
Kecepatan rata-rata bermuatan v1 40,00 KM/Jam
Kecepatan rata-rata kosong v2 50,00 KM/Jam
Waktu siklus Ts2
- Waktu tempuh isi = (L/v1) x 60 T1 30,00 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 24,00 menit
- Waktu bongkar Muat T3 120,00 menit
- Lain-lain T4 30,00 menit
TsL 204,00 menit
Kapst Produksi/Jam =
V x Fa x 60 Q1 772,06 Kg/Jam
Tsl
Biaya Dump Truck/Kg = (L1/Q1) x Rp. E 08 Rp.04 452,82 Rp/Kg
IV HARGA SATUAN DASAR BAJA TULANGAN DI LOKASI KERJA
Harga Satuan Semen
= (Rp.01 + Rp.02 + Rp.03 + Rp. 04) M10 23.052,82 Kg/Rp
Dibulatkan : M10 23.100,00 Rupiah
dipindahkan ke Daftar Harga Satuan Upah,
Bahan dan Peralatan
ANALISA HARGA DASAR SATUAN BAHAN
Baja Tulangan dibeli di ..., diangkut dengan
menggunakan tenaga manusia kemudian diangkut ke
lokasi kerja
-
7/26/2019 4. Analisa Harga
77/80
-
7/26/2019 4. Analisa Harga
78/80
Jenis : Sirtu
Lokasi : Quarry
Tujuan : Base Camp
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
Kapasitas Produksi / Jam =
V x Fa x 60 Q2 2,30 M3 / Jam
Ts2
Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 151.721,99 Rupiah
IV. HARGA SATUAN DASAR BAHAN
DI LOKASI BASE CAMP
Harga Satuan Dasar Pasir =
( RpM01 + Rp1 + Rp2 ) M01 289.988,51 Rupiah
Dibulatkan : M01 290.000,00 Rupiah
dipindahkan ke Daftar Harga Satuan Upah, Bahan
dan peralatan
ANALISA HARGA DASAR SATUAN BAHAN
-
7/26/2019 4. Analisa Harga
79/80
Jenis : Tanah Timbunan
Lokasi : Quarry
Tujuan : Base Camp
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : sedang / baik
3 Jarak Quarry ke lokasi Base Camp L 3,00 Km
4 Harga satuan tanah di Quarry RpM01 1,00 M3 50.000,00
5 Harga Satuan Dasar Excavator RpE01 1,00 Jam 665.551,00
6 Harga Satuan Dasar Dump Truck RpE06 1,00 Jam 349.602,00
II. URUTAN KERJA
1 Tanah digali dengan Excavator
2 Excavator sekaligus memuat tanh hasil
galian ke dalam Dump Truck
3 Dump Truck mengangkut tanah ke lokasi
Base Camp
III. PERHITUNGAN
EXCAVATOR E01
Kapasitas Bucket V 0,90 M3
Faktor Bucket Fb 0,80 Muat Sedang
Faktor Efisiensi alat Fa 0,75 - Kondisi Baik
Faktor Pengembangan Bahan Fh 1,25 Asli - Lepas
Waktu siklus / Cycle Time CT
- Waktu Gali T1 8,00 Detik
- Waktu Buang / Muat T2 8,00 Detik
- Waktu Swing T3 8,00 Detik
CT 24,00 Detik
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 64,80 M3 / Jam
Ts1 x Fh
Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 10.270,85 Rupiah
DUMP TRUCK E06
Kapasitas bak V 3,00 M3
Faktor efisiensi alat Fa 0,75 - Kondisi Baik
Kecepatan rata-rata bermuatan v1 40,00 KM/Jam
Kecepatan rata-rata kosong v2 60,00 KM/Jam
Waktu siklus Ts2
- Waktu tempuh isi = (L/v1) x 60 T1 4,50 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 3,00 menit
- Muat = (V/Q1) x 60 T3 2,78 menit
- Lain-lain T4 2,00 menit
Ts2 12,28 menit
ANALISA HARGA DASAR SATUAN BAHAN
-
7/26/2019 4. Analisa Harga
80/80