    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : MOBILISASI

    SATUAN PEMBAYARAN : LS

    A. ALAT

    1. Excavator Standard Unit 2,000 30.000.000,00 60.000.000,00Rp

    2. Buldozer Unit 1,000 30.000.000,00 30.000.000,00Rp

    3. Vibrator Roller Unit 1,000 30.000.000,00 30.000.000,00Rp

    4. Dump Truck Unit 2,000 5.000.000,00 10.000.000,00Rp

    5. Generator Set Unit 1,000 500.000,00 500.000,00Rp

    6. Concrete Mixer Unit 4,000 500.000,00 2.000.000,00Rp

    B. JUMLAH HARGA 132.500.000,00Rp

    C. - BIAYA UMUM 1,0 % x B 1.325.000,00Rp

    - KEUNTUNGAN 9,0 % x B 11.925.000,00RpD. HARGA SATUAN PEKERJAAN ( B + C ) 145.750.000,00Rp

    E. HARGA SATUAN PEKERJAAN DIBULATKAN 145.750.000,00Rp

    ANALISA HARGA SATUAN PEKERJAAN

    NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

  • 7/26/2019 4. Analisa Harga

    2/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : PEMBERSIHAN LAHAN

    SATUAN PEMBAYARAN : M2

    A. TENAGA

    1. Pekerja OH 0,060 80.000,00 4.800,00Rp

    2. Mandor OH 0,006 110.000,00 660,00Rp

    5.460,00Rp

    B. BAHAN

    -Rp

    -Rp

    C. PERALATAN

    -Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 5.460,00Rp

    E. - BIAYA UMUM 1,0 % x D 54,60Rp

    - KEUNTUNGAN 9,0 % x D 491,40Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 6.006,00Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 6.006,00Rp

    NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

  • 7/26/2019 4. Analisa Harga

    3/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : GALIAN TANAH (ALAT BERAT)

    SATUAN PEMBAYARAN : M3

    A. TENAGA

    1. Pekerja OH 0,080 80.000,00 6.412,67Rp

    2. Mandor OH 0,016 110.000,00 1.763,48Rp

    8.176,15Rp

    B. BAHAN

    -Rp

    -Rp

    C. PERALATAN

    1. Excavator Jam 0,016 665.551,00 10.669,89Rp

    10.669,89Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 18.846,04Rp

    E. - BIAYA UMUM 1,0 % x D 188,46Rp

    - KEUNTUNGAN 9,0 % x D 1.696,14Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 20.730,65Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 20.730,00Rp

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

  • 7/26/2019 4. Analisa Harga

    4/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : GALIAN TANAH (MANUAL) SEDALAM < 1 m

    SATUAN PEMBAYARAN : M3

    A. TENAGA

    1. Pekerja OH 0,563 80.000,00 45.040,00Rp

    2. Mandor OH 0,056 110.000,00 6.193,00Rp

    51.233,00Rp

    B. BAHAN

    -Rp

    -Rp

    C. PERALATAN

    -Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 51.233,00Rp

    E. - BIAYA UMUM 1,0 % x D 512,33Rp

    - KEUNTUNGAN 9,0 % x D 4.610,97Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 56.356,30Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 56.356,00Rp

    HARGA JUMLAH HARGA

    JUMLAH HARGA PERALATAN

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. URAIAN SATUAN VOLUME

  • 7/26/2019 4. Analisa Harga

    5/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : TIMBUANAN TANAH (MANUAL)

    SATUAN PEMBAYARAN : M3

    A. TENAGA

    1. Pekerja OH 0,330 80.000,00 26.400,00Rp

    2. Mandor OH 0,033 110.000,00 3.630,00Rp

    30.030,00Rp

    B. BAHAN

    -Rp

    -Rp

    C. PERALATAN

    -Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 30.030,00Rp

    E. - BIAYA UMUM 1,0 % x D 300,30Rp

    - KEUNTUNGAN 9,0 % x D 2.702,70Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 33.033,00Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 33.033,00Rp

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

  • 7/26/2019 4. Analisa Harga

    6/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : PEKERJAAN TIMBUNAN TANAH COVERDAM

    SATUAN PEMBAYARAN : M3

    A. TENAGA

    1. Pekerja OH 0,045 80.000,00 3.634,57Rp

    2. Mandor OH 0,011 110.000,00 1.249,38Rp

    4.883,95Rp

    B. BAHAN

    -Rp

    C. PERALATAN

    1. Excavator Jam 0,011 665.551,00 7.559,34Rp4. Vibro Roller Jam 0,005 534.915,00 2.641,56Rp

    10.200,90Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 15.084,85Rp

    E. - BIAYA UMUM 1,0 % x D 150,85Rp

    - KEUNTUNGAN 9,0 % x D 1.357,64Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 16.593,34Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 16.593,00Rp

    ANALISA HARGA SATUAN PEKERJAAN

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA

  • 7/26/2019 4. Analisa Harga

    7/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : CLEARING dan GRUBBING

    SATUAN PEMBAYARAN : M2

    A. TENAGA

    1. Pekerja OH 0,060 80.000,00 4.800,00Rp

    2. Mandor OH 0,006 110.000,00 660,00Rp

    5.460,00Rp

    B. BAHAN

    -Rp

    -Rp

    C. PERALATAN

    -Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 5.460,00Rp

    E. - BIAYA UMUM 1,0 % x D 54,60Rp

    - KEUNTUNGAN 9,0 % x D 491,40Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 6.006,00Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 6.006,00Rp

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. URAIAN SATUAN VOLUME HARGA

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

    JUMLAH HARGA

  • 7/26/2019 4. Analisa Harga

    8/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : TEBAS TEBANG TANAMAN PERDU

    SATUAN PEMBAYARAN : M2

    A. TENAGA

    1. Pekerja OH 0,075 80.000,00 6.000,00Rp

    2. Mandor OH 0,008 110.000,00 825,00Rp

    6.825,00Rp

    B. BAHAN

    1. Minyak Tanah L 0,010 5.000,00 50,00Rp

    50,00Rp

    C. PERALATAN

    -Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 6.875,00Rp

    E. - BIAYA UMUM 1,0 % x D 68,75Rp

    - KEUNTUNGAN 9,0 % x D 618,75Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 7.562,50Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 7.562,00Rp

    NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

  • 7/26/2019 4. Analisa Harga

    9/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : CABUT TANGGUL TANAMAN KERAS ( dia 15 cm )

    SATUAN PEMBAYARAN : POHON

    A. TENAGA

    1. Pekerja OH 0,200 80.000,00 16.000,00Rp

    2. Mandor OH 0,020 110.000,00 2.200,00Rp

    18.200,00Rp

    B. BAHAN

    -Rp

    C. PERALATAN

    1. Chainsaw Jam 0,100 40.000,00 4.000,00Rp

    4.000,00Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 22.200,00Rp

    E. - BIAYA UMUM 1,0 % x D 222,00Rp

    - KEUNTUNGAN 9,0 % x D 1.998,00Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 24.420,00Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 24.420,00Rp

    JUMLAH HARGA

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

    NO. URAIAN SATUAN VOLUME HARGA

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

  • 7/26/2019 4. Analisa Harga

    10/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : GORONG - GORONG BETON DIA. 100 CM

    SATUAN PEMBAYARAN : BH

    A. TENAGA

    1. Pekerja OH 0,667 80.000,00 53.333,33Rp

    2. Mandor OH 0,167 110.000,00 18.333,33Rp

    71.666,67Rp

    B. BAHAN

    1. Gorong - gorong dia 1 M Buah 1,000 65.000,00 65.000,00Rp

    65.000,00Rp

    C. PERALATAN

    1. Tripod Jam 0,167 75.000,00 12.500,00Rp

    12.500,00Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 149.166,67Rp

    E. - BIAYA UMUM 1,0 % x D 1.491,67Rp

    - KEUNTUNGAN 9,0 % x D 13.425,00Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 164.083,33Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 164.083,00Rp

    HARGA JUMLAH HARGA

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. URAIAN SATUAN VOLUME

  • 7/26/2019 4. Analisa Harga

    11/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : PENGHAMPARAN TANAH DATANG TUBUH BENDUNG dan PEMADATANNYA

    SATUAN PEMBAYARAN : M3

    A. TENAGA

    1. Pekerja OH 0,160 80.000,00 12.825,33Rp

    2. Mandor OH 0,016 110.000,00 1.763,48Rp

    14.588,82Rp

    B. BAHAN

    1. Tanah Timbunan M 1,200 92.100,00 110.520,00Rp

    110.520,00Rp

    C. PERALATAN

    1. Excavator Jam 0,016 665.551,00 10.669,89Rp2. Dump Truck Jam 0,035 349.602,00 12.251,35Rp

    3. Buldozer Jam 0,041 812.207,00 33.126,28Rp

    4. Vibro Roller Jam 0,018 534.915,00 9.533,43Rp

    65.580,96Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 190.689,78Rp

    E. - BIAYA UMUM 1,0 % x D 1.906,90Rp

    - KEUNTUNGAN 9,0 % x D 17.162,08Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 209.758,76Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 209.758,00Rp

    NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

  • 7/26/2019 4. Analisa Harga

    12/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : PENGADAAN KAWAT BRONJONG

    SATUAN PEMBAYARAN : BH

    1. Kawat Bronjong (Pabrikasi) Ukuran Buah 1,000 400.000,00 400.000,00Rp

    2 x 1 x 0.5 m. Heavy Galvanized

    dia 3 mm

    2. Biaya Pengiriman Jakarta - Lokasi Buah 1,000 20.000,00 20.000,00Rp

    3. Biaya Bongkar Muat Buah 1,000 2.000,00 2.000,00Rp

    A. JUMLAH HARGA 422.000,00Rp

    B. DIBULATKAN 422.000,00Rp

    ANALISA HARGA SATUAN PEKERJAAN

    HARGA JUMLAH HARGA

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. KOMPONEN SATUANPERKIRAAN

    KUANTITAS

  • 7/26/2019 4. Analisa Harga

    13/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : PASANGAN BRONJONG PABRIKASI

    SATUAN PEMBAYARAN : M3

    A. TENAGA

    1. Pekerja OH 0,500 80.000,00 40.000,00Rp

    2. Mandor OH 0,050 110.000,00 5.500,00Rp

    45.500,00Rp

    B. BAHAN

    1. Batu Belah 10/15 cm M 1,400 333.100,00 466.340,00Rp

    2. Kawar Bronjong Bh 1,000 422.000,00 422.000,00Rp

    888.340,00Rp

    C. PERALATAN

    1. Tripod Jam 0,010 75.000,00 750,00Rp

    750,00Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 934.590,00Rp

    E. - BIAYA UMUM 1,0 % x D 9.345,90Rp

    - KEUNTUNGAN 9,0 % x D 84.113,10Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 1.028.049,00Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 1.028.049,00Rp

    HARGA JUMLAH HARGA

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. URAIAN SATUAN VOLUME

  • 7/26/2019 4. Analisa Harga

    14/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : PEKERJAAN GEOMEMBRAN

    SATUAN PEMBAYARAN : M2

    A. TENAGA

    1. Pekerja OH 0,100 80.000,00 8.000,00Rp

    2. Tukang OH 0,020 90.000,00 1.800,00Rp

    3. Mandor OH 0,010 110.000,00 1.100,00Rp

    10.900,00Rp

    B. BAHAN

    1. Geomembran M 1,050 65.000,00 68.250,00Rp

    68.250,00Rp

    C. PERALATAN

    -Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 79.150,00Rp

    E. - BIAYA UMUM 1,0 % x D 791,50Rp

    - KEUNTUNGAN 9,0 % x D 7.123,50Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 87.065,00Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 87.065,00Rp

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    JUMLAH HARGA

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

    NO. URAIAN SATUAN VOLUME HARGA

    ANALISA HARGA SATUAN PEKERJAAN

  • 7/26/2019 4. Analisa Harga

    15/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : PEKERJAAN GEOTEKSTIL

    SATUAN PEMBAYARAN : M2

    A. TENAGA

    1. Pekerja OH 0,100 80.000,00 8.000,00Rp

    2. Tukang OH 0,020 90.000,00 1.800,00Rp

    3. Mandor OH 0,010 110.000,00 1.100,00Rp

    10.900,00Rp

    B. BAHAN

    1. Geotekstil M 1,050 25.000,00 26.250,00Rp

    26.250,00Rp

    C. PERALATAN

    -Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 37.150,00Rp

    E. - BIAYA UMUM 1,0 % x D 371,50Rp

    - KEUNTUNGAN 9,0 % x D 3.343,50Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 40.865,00Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 40.865,00Rp

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

    NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

  • 7/26/2019 4. Analisa Harga

    16/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : PENGHAMPARAN PASIR KERIKIL DAN PEMADATANNYA T = 50 CM

    SATUAN PEMBAYARAN : M3

    A. TENAGA

    1. Pekerja OH 0,510 80.000,00 40.785,52Rp

    2. Mandor OH 0,051 110.000,00 5.608,01Rp

    46.393,53Rp

    B. BAHAN

    1. Batu Kerikil M 1,200 495.700,00 594.840,00Rp

    594.840,00Rp

    C. PERALATAN

    1. Buldozer Jam 0,051 812.207,00 41.407,85Rp2. Vibro Roller Jam 0,014 534.915,00 7.607,68Rp

    49.015,53Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 690.249,06Rp

    E. - BIAYA UMUM 1,0 % x D 6.902,49Rp

    - KEUNTUNGAN 9,0 % x D 62.122,42Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 759.273,97Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 759.273,00Rp

    HARGA

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. URAIAN SATUAN VOLUME JUMLAH HARGA

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

    ANALISA HARGA SATUAN PEKERJAAN

  • 7/26/2019 4. Analisa Harga

    17/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : BETON K. 225

    SATUAN PEMBAYARAN : M3

    A. TENAGA

    1. Pekerja OH 1,323 80.000,00 105.840,00Rp

    2. Tukang OH 0,189 90.000,00 17.010,00Rp

    3. Kepala Tukang OH 0,019 100.000,00 1.900,00Rp

    4. Mandor OH 0,132 110.000,00 14.520,00Rp

    139.270,00Rp

    B. BAHAN

    1. PC/ Portland Cement Kg 371,000 2.122,00 787.262,00Rp

    2. PB / Pasir Beton Kg 698,000 132,00 92.136,00Rp

    3. Kr / Kerikil Kg 1047,000 341,86 357.929,59Rp

    4. Air Liter 215,000 200,00 43.000,00Rp

    1.280.327,59Rp

    C. PERALATAN

    1. Concrete Mixer Jam 0,250 86.627,00 21.656,75Rp

    21.656,75Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.441.254,34Rp

    E. - BIAYA UMUM 1,0 % x D 14.412,54Rp

    - KEUNTUNGAN 9,0 % x D 129.712,89Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 1.585.379,77Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 1.585.379,00Rp

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    JUMLAH HARGA

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

    NO. URAIAN SATUAN VOLUME HARGA

  • 7/26/2019 4. Analisa Harga

    18/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : LANTAI KERJA

    SATUAN PEMBAYARAN : M3

    A. TENAGA

    1. Pekerja OH 1,320 80.000,00 105.600,00Rp

    2. Tukang OH 0,220 90.000,00 19.800,00Rp

    3. Kepala Tukang OH 0,022 100.000,00 2.200,00Rp

    4. Mandor OH 0,132 110.000,00 14.520,00Rp

    142.120,00Rp

    B. BAHAN

    1. PC/ Portland Cement Kg 247,000 2.122,00 524.134,00Rp

    2. PB / Pasir Beton Kg 993,600 132,00 131.155,20Rp

    3. Kr / Kerikil Kg 1073,000 341,86 366.818,00Rp

    4. Air Liter 215,000 200,00 43.000,00Rp

    1.065.107,20Rp

    C. PERALATAN

    1. Concrete Mixer Jam 0,250 86.627,00 21.656,75Rp

    21.656,75Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.228.883,95Rp

    E. - BIAYA UMUM 1,0 % x D 12.288,84Rp

    - KEUNTUNGAN 9,0 % x D 110.599,56Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 1.351.772,35Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 1.351.772,00Rp

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

    ANALISA HARGA SATUAN PEKERJAAN

    JUMLAH HARGA

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. URAIAN SATUAN VOLUME HARGA

  • 7/26/2019 4. Analisa Harga

    19/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : PEMBESIAN

    SATUAN PEMBAYARAN : Kg

    A. TENAGA

    1. Pekerja OH 0,0070 80.000,00 560,00Rp

    2. Tukang OH 0,0070 90.000,00 630,00Rp

    3. Kepala Tukang OH 0,0007 100.000,00 70,00Rp

    4. Mandor OH 0,0007 110.000,00 77,00Rp

    1.337,00Rp

    B. BAHAN

    1. Besi Beton (Polos / Ulir) Kg 1,050 21.100,00 22.155,00Rp

    2. Kawat Bendrat Kg 0,015 23.100,00 346,50Rp

    22.501,50Rp

    C. PERALATAN

    -Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 23.838,50Rp

    E. - BIAYA UMUM 1,0 % x D 238,39Rp

    - KEUNTUNGAN 9,0 % x D 2.145,47Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 26.222,35Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 26.222,00Rp

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA

  • 7/26/2019 4. Analisa Harga

    20/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : BEKISTING

    SATUAN PEMBAYARAN : M2

    A. TENAGA

    1. Pekerja OH 0,6000 80.000,00 48.000,00Rp

    2. Tukang OH 0,3000 90.000,00 27.000,00Rp

    3. Kepala Tukang OH 0,0300 100.000,00 3.000,00Rp

    4. Mandor OH 0,0600 110.000,00 6.600,00Rp

    84.600,00Rp

    B. BAHAN

    1. Papan Kelas II M 0,025 4.500.000,00 112.500,00Rp

    2. Kayu Kelas II M 0,011 2.500.000,00 27.500,00Rp

    3. Paku Kg 0,400 25.000,00 10.000,00Rp

    4. Minyak Bekisting Liter 0,200 10.000,00 2.000,00Rp

    152.000,00Rp

    C. PERALATAN

    -Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 236.600,00Rp

    E. - BIAYA UMUM 1,0 % x D 2.366,00Rp

    - KEUNTUNGAN 9,0 % x D 21.294,00Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 260.260,00Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 260.260,00Rp

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

  • 7/26/2019 4. Analisa Harga

    21/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : WIREMESH M5

    SATUAN PEMBAYARAN : Kg

    A. TENAGA

    1. Pekerja OH 0,00250 80.000,00 200,00Rp

    2. Tukang OH 0,00250 90.000,00 225,00Rp

    3. Kepala Tukang OH 0,00025 100.000,00 25,00Rp

    4. Mandor OH 0,00025 110.000,00 27,50Rp

    477,50Rp

    B. BAHAN

    1. Wiremesh Kg 1,020 25.000,00 25.500,00Rp

    2. Kawat Bendrat Kg 0,005 23.100,00 115,50Rp

    25.615,50Rp

    C. PERALATAN

    -Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 26.093,00Rp

    E. - BIAYA UMUM 1,0 % x D 260,93Rp

    - KEUNTUNGAN 9,0 % x D 2.348,37Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 28.702,30Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 28.702,00Rp

    JUMLAH HARGA

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. URAIAN SATUAN VOLUME HARGA

  • 7/26/2019 4. Analisa Harga

    22/80

  • 7/26/2019 4. Analisa Harga

    23/80

  • 7/26/2019 4. Analisa Harga

    24/80

  • 7/26/2019 4. Analisa Harga

    25/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : KERAMIK 20 X 20 CM

    SATUAN PEMBAYARAN : M2

    A. TENAGA

    1. Pekerja OH 0,700 80.000,00 56.000,00Rp

    2. Tukang OH 0,350 90.000,00 31.500,00Rp

    3. Kepala Tukang OH 0,035 100.000,00 3.500,00Rp

    4. Mandor OH 0,070 110.000,00 7.700,00Rp

    98.700,00Rp

    B. BAHAN

    1. PC/ Portland Cement Kg 8,000 2.122,00 16.976,00Rp

    2. Pasir Pasang M 0,045 215.200,00 9.684,00Rp

    3. Semen Warna Kg 2,000 5.000,00 10.000,00Rp

    4. Keramik 20 x 20 Buah 25,000 7.500,00 187.500,00Rp

    224.160,00Rp

    C. PERALATAN

    -Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 322.860,00Rp

    E. - BIAYA UMUM 1,0 % x D 3.228,60Rp

    - KEUNTUNGAN 9,0 % x D 29.057,40Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 355.146,00Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 355.146,00Rp

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

  • 7/26/2019 4. Analisa Harga

    26/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : PLESTERAN 1 PC : 3 PP

    SATUAN PEMBAYARAN : M2

    A. TENAGA

    1. Pekerja OH 0,300 80.000,00 24.000,00Rp

    2. Tukang OH 0,150 90.000,00 13.500,00Rp

    3. Kepala Tukang OH 0,015 100.000,00 1.500,00Rp

    4. Mandor OH 0,030 110.000,00 3.300,00Rp

    42.300,00Rp

    B. BAHAN

    1. PC/ Portland Cement Kg 5,840 2.122,00 12.392,48Rp

    2. Pasir Pasang M 0,016 215.200,00 3.443,20Rp

    15.835,68Rp

    C. PERALATAN

    -Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 58.135,68Rp

    E. - BIAYA UMUM 1,0 % x D 581,36Rp

    - KEUNTUNGAN 9,0 % x D 5.232,21Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 63.949,25Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 63.949,00Rp

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

  • 7/26/2019 4. Analisa Harga

    27/80

  • 7/26/2019 4. Analisa Harga

    28/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : PEKERJAAN PEMASANGAN PINTU

    SATUAN PEMBAYARAN : Bh

    A. TENAGA

    1. Pekerja OH 0,700 80.000,00 56.000,00Rp

    2. Tukang OH 0,350 90.000,00 31.500,00Rp

    3. Kepala Tukang OH 0,035 100.000,00 3.500,00Rp

    4. Mandor OH 0,070 110.000,00 7.700,00Rp

    98.700,00Rp

    B. BAHAN

    1. Pintu Panel Bh 1,000 850.000,00 850.000,00Rp

    850.000,00Rp

    C. PERALATAN

    -Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 948.700,00Rp

    E. - BIAYA UMUM 1,0 % x D 9.487,00Rp

    - KEUNTUNGAN 9,0 % x D 85.383,00Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 1.043.570,00Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 1.043.570,00Rp

    NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

  • 7/26/2019 4. Analisa Harga

    29/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : PEKERJAAN PEMASANGAN JENDELA

    SATUAN PEMBAYARAN : Bh

    A. TENAGA

    1. Pekerja OH 0,500 80.000,00 40.000,00Rp

    2. Tukang OH 0,250 90.000,00 22.500,00Rp

    3. Kepala Tukang OH 0,025 100.000,00 2.500,00Rp

    4. Mandor OH 0,050 110.000,00 5.500,00Rp

    70.500,00Rp

    B. BAHAN

    1. Jendela Bh 1,000 500.000,00 500.000,00Rp

    500.000,00Rp

    C. PERALATAN

    -Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 570.500,00Rp

    E. - BIAYA UMUM 1,0 % x D 5.705,00Rp

    - KEUNTUNGAN 9,0 % x D 51.345,00Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 627.550,00Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 627.550,00Rp

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

  • 7/26/2019 4. Analisa Harga

    30/80

  • 7/26/2019 4. Analisa Harga

    31/80

  • 7/26/2019 4. Analisa Harga

    32/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : PIPA PVC dia. 75 mm

    SATUAN PEMBAYARAN : BH

    A. TENAGA

    1. Pekerja OH 0,080 80.000,00 6.400,00Rp

    2. Tukang OH 0,040 90.000,00 3.600,00Rp

    3. Kepala Tukang OH 0,004 100.000,00 400,00Rp

    4. Mandor OH 0,008 110.000,00 880,00Rp

    11.280,00Rp

    B. BAHAN

    1. Pipa PVC dia. 75 mm M' 1,000 50.000,00 50.000,00Rp

    50.000,00Rp

    C. PERALATAN

    -Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 61.280,00Rp

    E. - BIAYA UMUM 1,0 % x D 612,80Rp

    - KEUNTUNGAN 9,0 % x D 5.515,20Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 67.408,00Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 67.408,00Rp

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA

  • 7/26/2019 4. Analisa Harga

    33/80

  • 7/26/2019 4. Analisa Harga

    34/80

  • 7/26/2019 4. Analisa Harga

    35/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : PASANGAN BATU KALI CAMP 1 PC : 3 PS

    SATUAN PEMBAYARAN : M3

    A. TENAGA

    1. Pekerja OH 2,700 80.000,00 216.000,00Rp

    2. Tukang OH 0,900 90.000,00 81.000,00Rp

    3. Kepala Tukang OH 0,090 100.000,00 9.000,00Rp

    4. Mandor OH 0,270 110.000,00 29.700,00Rp

    335.700,00Rp

    B. BAHAN

    1. PC/ Portland Cement Kg 202,000 2.122,00 428.644,00Rp

    2. Pasir Pasang M 0,485 215.200,00 104.372,00Rp

    3. Batu Belah 10/15 cm M 1,200 333.100,00 399.720,00Rp

    932.736,00Rp

    C. PERALATAN

    -Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1.268.436,00Rp

    E. - BIAYA UMUM 1,0 % x D 12.684,36Rp

    - KEUNTUNGAN 9,0 % x D 114.159,24Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 1.395.279,60Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 1.395.279,00Rp

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

    NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA

  • 7/26/2019 4. Analisa Harga

    36/80

  • 7/26/2019 4. Analisa Harga

    37/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : PENYAMBUNGAN PIPA HDPE 150 mm

    SATUAN PEMBAYARAN : M'

    A. TENAGA

    1. Pekerja OH 2,096 80.000,00 167.680,00Rp

    2. Tukang OH 1,048 90.000,00 94.320,00Rp

    3. Mandor OH 0,210 110.000,00 23.100,00Rp

    285.100,00Rp

    B. BAHAN

    1. Bensin Liter 0,650 10.000,00 6.500,00Rp

    6.500,00Rp

    C. PERALATAN

    1. Butt Fusion Unit / Jam 0,062 150.000,00 9.300,00Rp2. Generator Set Unit / Jam 0,062 120.000,00 7.440,00Rp

    16.740,00Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 308.340,00Rp

    E. - BIAYA UMUM 1,0 % x D 3.083,40Rp

    - KEUNTUNGAN 9,0 % x D 27.750,60Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 339.174,00Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 339.174,00Rp

    JUMLAH HARGA

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. URAIAN SATUAN VOLUME HARGA

  • 7/26/2019 4. Analisa Harga

    38/80

  • 7/26/2019 4. Analisa Harga

    39/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : PEMASANGAN PIPA HDPE 160 MM

    SATUAN PEMBAYARAN : M'

    A. TENAGA

    1. Pekerja OH 0,062 80.000,00 4.960,00Rp

    2. Tukang OH 0,006 90.000,00 558,00Rp

    3 Mandor OH 0,031 110.000,00 3.410,00Rp

    8.928,00Rp

    B. BAHAN

    1. Pipa HDPE 160 mm M' 1,000 150.000,00 150.000,00Rp

    150.000,00Rp

    C. PERALATAN

    1. Tripod Jam 0,019 75.000,00 1.425,00Rp

    1.425,00Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 160.353,00Rp

    E. - BIAYA UMUM 1,0 % x D 1.603,53Rp

    - KEUNTUNGAN 9,0 % x D 14.431,77Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 176.388,30Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 176.388,00Rp

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

  • 7/26/2019 4. Analisa Harga

    40/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : PENYAMBUNGAN PIPA HDPE 160 mm

    SATUAN PEMBAYARAN : M'

    A. TENAGA

    1. Pekerja OH 2,096 80.000,00 167.680,00Rp

    2. Tukang OH 1,048 90.000,00 94.320,00Rp

    3. Mandor OH 0,210 110.000,00 23.100,00Rp

    285.100,00Rp

    B. BAHAN

    1. Bensin Liter 0,650 10.000,00 6.500,00Rp

    6.500,00Rp

    C. PERALATAN

    1. Butt Fusion Unit / Jam 0,062 150.000,00 9.300,00Rp2. Generator Set Unit / Jam 0,062 120.000,00 7.440,00Rp

    16.740,00Rp

    D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 308.340,00Rp

    E. - BIAYA UMUM 1,0 % x D 3.083,40Rp

    - KEUNTUNGAN 9,0 % x D 27.750,60Rp

    F. HARGA SATUAN PEKERJAAN ( D + E ) 339.174,00Rp

    G. HARGA SATUAN PEKERJAAN DIBULATKAN 339.174,00Rp

    JUMLAH HARGA

    JUMLAH HARGA TENAGA

    JUMLAH HARGA BAHAN

    JUMLAH HARGA PERALATAN

    NO. URAIAN SATUAN VOLUME HARGA

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

  • 7/26/2019 4. Analisa Harga

    41/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : PEKERJAAN PIPA HDPE 160 mm

    SATUAN PEMBAYARAN : M'

    1. Galian Tanah Biasa Manual M 0,3600 56.356,00 20.288,16Rp

    2. Pemasangan Pipa HDPE 160 mm M' 1,0000 176.388,00 176.388,00Rp

    3. Penyambunagn Pipa HDPE 160 mm Titik 0,1667 56.529,00 9.421,50Rp

    4. Timbunan Tanah Kembali (manual) M 0,3522 33.033,00 11.634,22Rp

    A. JUMLAH HARGA SATUAN 217.731,88Rp

    B. HARGA SATUAN PEKERJAAN DIBULATKAN 217.731,00Rp

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. URAIAN SATUAN VOLUME HARGA JUMLAH HARGA

  • 7/26/2019 4. Analisa Harga

    42/80

  • 7/26/2019 4. Analisa Harga

    43/80

    PEKERJAAN : PEMBANGUNAN EMBUNG PADU EMPAT KAB. KUBU RAYA

    SATKER :

    LOKASI : KABUPATEN KUBU RAYA

    THN. ANGGARAN : 2016

    ITEM PEMBAYARAN NOMOR : -

    JENIS PEKERJAAN : PEKERJAAN PIPA HDPE 63 mm

    SATUAN PEMBAYARAN : M'

    1. Galian Tanah Biasa Manual M 0,3600 56.356,00 20.288,16Rp

    2. Pemasangan Pipa HDPE 160 mm M' 1,0000 40.001,00 40.001,00Rp

    4. Timbunan Tanah Kembali (manual) M 0,3522 33.033,00 11.634,22Rp

    A. JUMLAH HARGA SATUAN 71.923,38Rp

    B. HARGA SATUAN PEKERJAAN DIBULATKAN 71.923,00Rp

    JUMLAH HARGA

    ANALISA HARGA SATUAN PEKERJAAN

    NON VERTIKAL TERTENTU PELAKSANAAN JARINGAN SUMBER AIR KALIMANTAN

    PROVINSI KALIMANTAN BARAT

    NO. URAIAN SATUAN VOLUME HARGA

  • 7/26/2019 4. Analisa Harga

    44/80

    Satuan Kerja : Non Vertikal Tertentu Pelaksanaan Jaringan Sumber Air Kalimantan Provinsi Kalimantan BaratKegiatan : Prasarana Konservasi Sumber Daya Air

    Pekerjaan : Pembangunan Embung Padu Empat Kab. Kubu Raya

    Lokasi : Kabupaten Kubu Raya

    Tahun Anggaran : 2016

    Sumber Dana : APBN - Murni

    No.HARGA SATUAN

    UPAH / HARI

    1 Kepala Tukang 100.000,00Rp

    2 Tukang 90.000,00Rp

    3 Tukang Pipa 90.000,00Rp

    4 Mandor 110.000,00Rp

    5 Pekerja 80.000,00Rp

    6 Tenaga Pengukuran 110.000,00Rp

    7 Operator 110.000,00Rp

    8 Pembantu Operator 100.000,00Rp

    9 Foreman Equipment 90.000,00Rp

    10 Mekanik 110.000,00Rp

    11 Pembantu Mekanik 100.000,00Rp

    #REF!

    Dibuat Oleh

    #REF!

    #REF!

    #REF!

    #REF!

    DAFTAR HARGA DASAR SATUAN UPAH

    JENIS TENAGA

    Manokwari, 13 Desember 2015

    Dibuat OlehPT. ANI SUBAM PERKASA

    BENNY BAHO

    Direktur

  • 7/26/2019 4. Analisa Harga

    45/80

  • 7/26/2019 4. Analisa Harga

    46/80

  • 7/26/2019 4. Analisa Harga

    47/80

  • 7/26/2019 4. Analisa Harga

    48/80

  • 7/26/2019 4. Analisa Harga

    49/80

    No. U R A I A N KODE KOEF. SATUAN KET.

    A. URAIAN PERALATAN

    1. Jenis Peralatan E02

    2 . Tenaga Pw 75,0 HP

    3. Kapasitas Cp 5,4 M3

    4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun

    b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam

    c. Harga Alat B 2.300.000.000 Rupiah

    5. Alat Yang Dipakai : a. Umur Ekonomis A' 5,0 Tahun

    b. Jam Kerja Dalam 1 Tahun W' 2.000,0 Jam

    c. Harga Alat (*) B' 2.300.000.000 Rupiah

    B. BIAYA PASTI PER JAM KERJA

    1. Nilai Sisa Alat = 10 % x B C 230.000.000 Rupiah

    2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,33438 -

    (1 + i)^A' - 1

    3. Biaya Pasti per Jam :

    a. Biaya Pengembalian Modal = ( B' - C ) x D E 346.082,99 Rupiah

    W'

    b. Asuransi, dll = 0,02 x B' F 23.000,00 Rupiah

    W'

    Biaya Pasti per Jam = ( E + F ) G 369.082,99 Rupiah

    C. BIAYA OPERASI PER JAM KERJA

    1. Bahan Bakar = (0.12 s/d 0.175 ) x Pw x Ms H 135.000,00 Rupiah

    2. Pelumas = (0.035 s/d 0.06 ) x Pw x Mp I 37.500,00 Rupiah

    3. Spare part = (0.125 s/d 0.175) x B K1 143.750,00 Rupiah

    W'

    4. Workshop = (0.0625 s/d 0.0.0875) x B K2 100.625,00 Rupiah

    W'

    5. Operator = ( 1 Orang / Jam ) x U1 L 13.750,00 Rupiah

    6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 12.500,00 Rupiah

    Biaya Operasi per Jam = (H+I+K+L+M) P 443.125,00 Rupiah

    D. LAIN - LAIN

    1. Tingkat Suku Bunga i 20,00 % / Tahun

    2. Upah Operator / Sopir U1 13.750,00 Rp./Jam

    3. Upah Pembantu Operator / Pmb.Sopir U2 12.500,00 Rp./Jam

    4. Bahan Bakar Bensin Mb 10.000,00 Liter

    5. Bahan Bakar Solar Ms 15.000,00 Liter

    6. Minyak Pelumas Mp 20.000,00 Liter

    7. Koefisien bahan bakar Kbb 0,120 - Pek. Ringan

    8. Koefisien pelumas Kp 0,025 - Pek. Ringan

    9. Koefisien spare part Kpp 0,125 - Pek. Ringan

    10. Koefisien workshop Kws 0,088 -

    11. PPN diperhitungkan pada lembar Rekapitulasi

    Biaya Pemilikan / Biaya pasti per jam B. 369.082,99

    Biaya Operasi per jam C. 443.125,00

    Biaya kepemilikan dan operasi B + C 812.207,99

    Dibulatkan 812.207,00

    URAIAN ANALISA ALAT

    Buldozer

  • 7/26/2019 4. Analisa Harga

    50/80

    No. U R A I A N KODE KOEF. SATUAN KET.

    A. URAIAN PERALATAN

    1. Jenis Peralatan E03

    2 . Tenaga Pw 96,0 HP

    3. Kapasitas Cp 1,5 M3

    4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun

    b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam

    c. Harga Alat B 1.500.000.000 Rupiah

    5. Alat Yang Dipakai : a. Umur Ekonomis A' 5,0 Tahun

    b. Jam Kerja Dalam 1 Tahun W' 2.000,0 Jam

    c. Harga Alat (*) B' 1.500.000.000 Rupiah

    B. BIAYA PASTI PER JAM KERJA

    1. Nilai Sisa Alat = 10 % x B C 150.000.000 Rupiah

    2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,33438 -

    (1 + i)^A' - 1

    3. Biaya Pasti per Jam :

    a. Biaya Pengembalian Modal = ( B' - C ) x D E 225.706,30 Rupiah

    W'

    b. Asuransi, dll = 0,02 x B' F 15.000,00 Rupiah

    W'

    Biaya Pasti per Jam = ( E + F ) G 240.706,30 Rupiah

    C. BIAYA OPERASI PER JAM KERJA

    1. Bahan Bakar = (0.12 s/d 0.175 ) x Pw x Ms H 172.800,00 Rupiah

    2. Pelumas = (0.035 s/d 0.06 ) x Pw x Mp I 48.000,00 Rupiah

    3. Spare part = (0.125 s/d 0.175) x B K1 93.750,00 Rupiah

    W'

    4. Workshop = (0.0625 s/d 0.0.0875) x B K2 65.625,00 Rupiah

    W'

    5. Operator = ( 1 Orang / Jam ) x U1 L 13.750,00 Rupiah

    6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 12.500,00 Rupiah

    Biaya Operasi per Jam = (H+I+K+L+M) P 406.425,00 Rupiah

    D. LAIN - LAIN

    1. Tingkat Suku Bunga i 20,00 % / Tahun

    2. Upah Operator / Sopir U1 13.750,00 Rp./Jam

    3. Upah Pembantu Operator / Pmb.Sopir U2 12.500,00 Rp./Jam

    4. Bahan Bakar Bensin Mb 10.000,00 Liter

    5. Bahan Bakar Solar Ms 15.000,00 Liter

    6. Minyak Pelumas Mp 20.000,00 Liter

    7. Koefisien bahan bakar Kbb 0,120 - Pek. Ringan

    8. Koefisien pelumas Kp 0,025 - Pek. Ringan

    9. Koefisien spare part Kpp 0,125 - Pek. Ringan

    10. Koefisien workshop Kws 0,088 -

    11. PPN diperhitungkan pada lembar Rekapitulasi

    Biaya Pemilikan / Biaya pasti per jam B. 240.706,30

    Biaya Operasi per jam C. 406.425,00

    Biaya kepemilikan dan operasi B + C 647.131,30

    Dibulatkan 647.131,00

    URAIAN ANALISA ALAT

    Wheel Loader

  • 7/26/2019 4. Analisa Harga

    51/80

  • 7/26/2019 4. Analisa Harga

    52/80

  • 7/26/2019 4. Analisa Harga

    53/80

  • 7/26/2019 4. Analisa Harga

    54/80

    No. U R A I A N KODE KOEF. SATUAN KET.

    A. URAIAN PERALATAN

    1. Jenis Peralatan E07

    2. Tenaga Pw 100,0 HP

    3. Kapasitas Cp 4.000,0 Liter

    4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun

    b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam

    c. Harga Alat B 250.000.000 Rupiah

    5. Alat Yang Dipakai : a. Umur Ekonomis A' 5,0 Tahun

    b. Jam Kerja Dalam 1 Tahun W' 2.000,0 Jam

    c. Harga Alat (*) B' 250.000.000 Rupiah

    B. BIAYA PASTI PER JAM KERJA

    1. Nilai Sisa Alat = 10 % x B C 25.000.000 Rupiah

    2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,33438 -

    (1 + i)^A' - 1

    3. Biaya Pasti per Jam :

    a. Biaya Pengembalian Modal = ( B' - C ) x D E 37.617,72 Rupiah

    W'

    b. Asuransi, dll = 0,02 x B' F 2.500,00 Rupiah

    W'

    Biaya Pasti per Jam = ( E + F ) G 40.117,72 Rupiah

    C. BIAYA OPERASI PER JAM KERJA

    1. Bahan Bakar = (0.12 s/d 0.175 ) x Pw x Ms H 180.000,00 Rupiah

    2. Pelumas = (0.035 s/d 0.06 ) x Pw x Mp I 50.000,00 Rupiah

    3. Spare part = (0.125 s/d 0.175) x B K1 15.625,00 Rupiah

    W'

    4. Workshop = (0.0625 s/d 0.0.0875) x B K2 10.937,50 Rupiah

    W'

    5. Operator = ( 1 Orang / Jam ) x U1 L 13.750,00 Rupiah

    6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 12.500,00 Rupiah

    Biaya Operasi per Jam = (H+I+K+L+M) P 282.812,50 Rupiah

    D. LAIN - LAIN

    1. Tingkat Suku Bunga i 20,00 % / Tahun

    2. Upah Operator / Sopir U1 13.750,00 Rp./Jam

    3. Upah Pembantu Operator / Pmb.Sopir U2 12.500,00 Rp./Jam

    4. Bahan Bakar Bensin Mb 10.000,00 Liter

    5. Bahan Bakar Solar Ms 15.000,00 Liter

    6. Minyak Pelumas Mp 20.000,00 Liter

    7. Koefisien bahan bakar Kbb 0,120 - Pek. Ringan

    8. Koefisien pelumas Kp 0,025 - Pek. Ringan

    9. Koefisien spare part Kpp 0,125 - Pek. Ringan

    10. Koefisien workshop Kws 0,088 -

    11. PPN diperhitungkan pada lembar Rekapitulasi

    Biaya Pemilikan / Biaya pasti per jam B. 40.117,72

    Biaya Operasi per jam C. 282.812,50

    Biaya kepemilikan dan operasi B + C 322.930,22

    Dibulatkan 322.930,00

    URAIAN ANALISA ALAT

    Water Tank truck

  • 7/26/2019 4. Analisa Harga

    55/80

    No. U R A I A N KODE KOEF. SATUAN KET.

    A. URAIAN PERALATAN

    1. Jenis Peralatan E08

    2 . Tenaga Pw 20,0 HP

    3. Kapasitas Cp 500,00 liter

    4. Alat Baru : a. Umur Ekonomis A 2,0 Tahun

    b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam

    c. Harga Alat B 35.000.000 Rupiah

    5. Alat Yang Dipakai : a. Umur Ekonomis A' 2,0 Tahun

    b. Jam Kerja Dalam 1 Tahun W' 2.000,0 Jam

    c. Harga Alat (*) B' 35.000.000 Rupiah

    B. BIAYA PASTI PER JAM KERJA

    1. Nilai Sisa Alat = 10 % x B C 3.500.000 Rupiah

    2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,65455 -

    (1 + i)^A' - 1

    3. Biaya Pasti per Jam :

    a. Biaya Pengembalian Modal = ( B' - C ) x D E 10.309,09 Rupiah

    W'

    b. Asuransi, dll = 0,02 x B' F 350,00 Rupiah

    W'

    Biaya Pasti per Jam = ( E + F ) G 10.659,09 Rupiah

    C. BIAYA OPERASI PER JAM KERJA

    1. Bahan Bakar = (0.12 s/d 0.175 ) x Pw x Ms H 36.000,00 Rupiah

    2. Pelumas = (0.035 s/d 0.06 ) x Pw x Mp I 10.000,00 Rupiah

    3. Spare part = (0.125 s/d 0.175) x B K1 2.187,50 Rupiah

    W'

    4. Workshop = (0.0625 s/d 0.0.0875) x B K2 1.531,25 Rupiah

    W'

    5. Operator = ( 1 Orang / Jam ) x U1 L 13.750,00 Rupiah

    6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 12.500,00 Rupiah

    Biaya Operasi per Jam = (H+I+K+L+M) P 75.968,75 Rupiah

    D. LAIN - LAIN

    1. Tingkat Suku Bunga i 20,00 % / Tahun

    2. Upah Operator / Sopir U1 13.750,00 Rp./Jam

    3. Upah Pembantu Operator / Pmb.Sopir U2 12.500,00 Rp./Jam

    4. Bahan Bakar Bensin Mb 10.000,00 Liter

    5. Bahan Bakar Solar Ms 15.000,00 Liter

    6. Minyak Pelumas Mp 20.000,00 Liter

    7. Koefisien bahan bakar Kbb 0,120 - Pek. Ringan

    8. Koefisien pelumas Kp 0,025 - Pek. Ringan

    9. Koefisien spare part Kpp 0,125 - Pek. Ringan

    10. Koefisien workshop Kws 0,088 -

    11. PPN diperhitungkan pada lembar Rekapitulasi

    Biaya Pemilikan / Biaya pasti per jam B. 10.659,09

    Biaya Operasi per jam C. 75.968,75

    Biaya kepemilikan dan operasi B + C 86.627,84

    Dibulatkan 86.627,00

    URAIAN ANALISA ALAT

    Concrete Mixer

  • 7/26/2019 4. Analisa Harga

    56/80

    No. U R A I A N KODE KOEF. SATUAN KET.

    A. URAIAN PERALATAN

    1. Jenis Peralatan E09

    2. Tenaga Pw 5,5 HP

    3. Kapasitas Cp 25,0 -

    4. Alat Baru : a. Umur Ekonomis A 4,0 Tahun

    b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam

    c. Harga Alat B 12.500.000 Rupiah

    5. Alat Yang Dipakai : a. Umur Ekonomis A' 4,0 Tahun

    b. Jam Kerja Dalam 1 Tahun W' 2.000,0 Jam

    c. Harga Alat (*) B' 12.500.000 Rupiah

    B. BIAYA PASTI PER JAM KERJA

    1. Nilai Sisa Alat = 10 % x B C 1.250.000 Rupiah

    2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,38629 -

    (1 + i)^A' - 1

    3. Biaya Pasti per Jam :

    a. Biaya Pengembalian Modal = ( B' - C ) x D E 2.172,88 Rupiah

    W'

    b. Asuransi, dll = 0,02 x B' F 125,00 Rupiah

    W'

    Biaya Pasti per Jam = ( E + F ) G 2.297,88 Rupiah

    C. BIAYA OPERASI PER JAM KERJA

    1. Bahan Bakar = (0.12 s/d 0.175 ) x Pw x Ms H 9.900,00 Rupiah

    2. Pelumas = (0.035 s/d 0.06 ) x Pw x Mp I 2.750,00 Rupiah

    3. Spare part = (0.125 s/d 0.175) x B K1 781,25 Rupiah

    W'

    4. Workshop = (0.0625 s/d 0.0.0875) x B K2 546,88 Rupiah

    W'

    5. Operator = ( 1 Orang / Jam ) x U1 L 13.750,00 Rupiah

    6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 12.500,00 Rupiah

    Biaya Operasi per Jam = (H+I+K+L+M) P 40.228,13 Rupiah

    D. LAIN - LAIN

    1. Tingkat Suku Bunga i 20,00 % / Tahun

    2. Upah Operator / Sopir U1 13.750,00 Rp./Jam

    3. Upah Pembantu Operator / Pmb.Sopir U2 12.500,00 Rp./Jam

    4. Bahan Bakar Bensin Mb 10.000,00 Liter

    5. Bahan Bakar Solar Ms 15.000,00 Liter

    6. Minyak Pelumas Mp 20.000,00 Liter

    7. Koefisien bahan bakar Kbb 0,120 - Pek. Ringan

    8. Koefisien pelumas Kp 0,025 - Pek. Ringan

    9. Koefisien spare part Kpp 0,125 - Pek. Ringan

    10. Koefisien workshop Kws 0,088 -

    11. PPN diperhitungkan pada lembar Rekapitulasi

    Biaya Pemilikan / Biaya pasti per jam B. 2.297,88

    Biaya Operasi per jam C. 40.228,13

    Biaya kepemilikan dan operasi B + C 42.526,00

    Dibulatkan 42.526,00

    URAIAN ANALISA ALAT

    Concrete Vibrator

  • 7/26/2019 4. Analisa Harga

    57/80

  • 7/26/2019 4. Analisa Harga

    58/80

  • 7/26/2019 4. Analisa Harga

    59/80

    No. U R A I A N KODE KOEF. SATUAN KET.

    A. URAIAN PERALATAN

    1. Jenis Peralatan E12

    2. Tenaga Pw 175,0 HP

    3. Kapasitas Cp 20,0 Ton

    4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun

    b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam

    c. Harga Alat B 1.200.000.000 Rupiah

    5. Alat Yang Dipakai : a. Umur Ekonomis A' 5,0 Tahun

    b. Jam Kerja Dalam 1 Tahun W' 2.000,0 Jam

    c. Harga Alat (*) B' 1.200.000.000 Rupiah

    B. BIAYA PASTI PER JAM KERJA

    1. Nilai Sisa Alat = 10 % x B C 120.000.000 Rupiah

    2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,33438 -

    (1 + i)^A' - 1

    3. Biaya Pasti per Jam :

    a. Biaya Pengembalian Modal = ( B' - C ) x D E 180.565,04 Rupiah

    W'

    b. Asuransi, dll = 0,02 x B' F 12.000,00 Rupiah

    W'

    Biaya Pasti per Jam = ( E + F ) G 192.565,04 Rupiah

    C. BIAYA OPERASI PER JAM KERJA

    1. Bahan Bakar = (0.12 s/d 0.175 ) x Pw x Ms H 315.000,00 Rupiah

    2. Pelumas = (0.035 s/d 0.06 ) x Pw x Mp I 87.500,00 Rupiah

    3. Spare part = (0.125 s/d 0.175) x B K1 75.000,00 Rupiah

    W'

    4. Workshop = (0.0625 s/d 0.0.0875) x B K2 52.500,00 Rupiah

    W'

    5. Operator = ( 1 Orang / Jam ) x U1 L 13.750,00 Rupiah

    6. Pembantu Operator = ( 3 Orang / Jam ) x U2 M 37.500,00 Rupiah

    Biaya Operasi per Jam = (H+I+K+L+M) P 581.250,00 Rupiah

    D. LAIN - LAIN

    1. Tingkat Suku Bunga i 20,00 % / Tahun

    2. Upah Operator / Sopir U1 13.750,00 Rp./Jam

    3. Upah Pembantu Operator / Pmb.Sopir U2 12.500,00 Rp./Jam

    4. Bahan Bakar Bensin Mb 10.000,00 Liter

    5. Bahan Bakar Solar Ms 15.000,00 Liter

    6. Minyak Pelumas Mp 20.000,00 Liter

    7. Koefisien bahan bakar Kbb 0,120 - Pek. Ringan

    8. Koefisien pelumas Kp 0,025 - Pek. Ringan

    9. Koefisien spare part Kpp 0,125 - Pek. Ringan

    10. Koefisien workshop Kws 0,088 -

    11. PPN diperhitungkan pada lembar Rekapitulasi

    Biaya Pemilikan / Biaya pasti per jam B. 192.565,04

    Biaya Operasi per jam C. 581.250,00

    Biaya kepemilikan dan operasi B + C 773.815,04

    Dibulatkan 773.815,00

    URAIAN ANALISA ALAT

    TRAILER 20 TON

  • 7/26/2019 4. Analisa Harga

    60/80

    No. U R A I A N KODE KOEF. SATUAN KET.

    A. URAIAN PERALATAN

    1. Jenis Peralatan E12 2 . Tenaga Pw 40,0 HP

    3. Kapasitas Cp 250,0 Ton

    4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun

    b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam

    c. Harga Alat B 200.000.000 Rupiah

    5. Alat Yang Dipakai : a. Umur Ekonomis A' 5,0 Tahun

    b. Jam Kerja Dalam 1 Tahun W' 2.000,0 Jam

    c. Harga Alat (*) B' 200.000.000 Rupiah

    B. BIAYA PASTI PER JAM KERJA

    1. Nilai Sisa Alat = 10 % x B C 20.000.000 Rupiah

    2. Faktor Angsuran Modal = i x (1 + i)^A' D 0,33438 -

    (1 + i)^A' - 1

    3. Biaya Pasti per Jam :

    a. Biaya Pengembalian Modal = ( B' - C ) x D E 30.094,17 Rupiah

    W'

    b. Asuransi, dll = 0,02 x B' F 2.000,00 Rupiah

    W'

    Biaya Pasti per Jam = ( E + F ) G 32.094,17 Rupiah

    C. BIAYA OPERASI PER JAM KERJA

    1. Bahan Bakar = (0.12 s/d 0.175 ) x Pw x Ms H 72.000,00 Rupiah

    2. Pelumas = (0.035 s/d 0.06 ) x Pw x Mp I 20.000,00 Rupiah

    3. Spare part = (0.125 s/d 0.175) x B K1 12.500,00 Rupiah

    W'

    4. Workshop = (0.0625 s/d 0.0.0875) x B K2 8.750,00 Rupiah

    W'

    5. Operator = ( 1 Orang / Jam ) x U1 L 13.750,00 Rupiah

    6. Pembantu Operator = ( 3 Orang / Jam ) x U2 M 37.500,00 Rupiah

    Biaya Operasi per Jam = (H+I+K+L+M) P 164.500,00 Rupiah

    D. LAIN - LAIN

    1. Tingkat Suku Bunga i 20,00 % / Tahun

    2. Upah Operator / Sopir U1 13.750,00 Rp./Jam

    3. Upah Pembantu Operator / Pmb.Sopir U2 12.500,00 Rp./Jam4. Bahan Bakar Bensin Mb 10.000,00 Liter

    5. Bahan Bakar Solar Ms 15.000,00 Liter

    6. Minyak Pelumas Mp 20.000,00 Liter

    7. Koefisien bahan bakar Kbb 0,120 - Pek. Ringan

    8. Koefisien pelumas Kp 0,025 - Pek. Ringan

    9. Koefisien spare part Kpp 0,125 - Pek. Ringan

    10. Koefisien workshop Kws 0,088 -

    11. PPN diperhitungkan pada lembar Rekapitulasi

    Biaya Pemilikan / Biaya pasti per jam B. 32.094,17

    Biaya Operasi per jam C. 164.500,00

    Biaya kepemilikan dan operasi B + C 196.594,17

    Dibulatkan 196.594,00

    URAIAN ANALISA ALAT

    WELDING SET

  • 7/26/2019 4. Analisa Harga

    61/80

  • 7/26/2019 4. Analisa Harga

    62/80

    Jenis : Pasir Pasang

    Lokasi : Quarry

    Tujuan : Base Camp

    HARGA

    No. URAIAN KODE KOEF. SATUAN SATUAN

    (Rp.)

    I. ASUMSI

    1 Menggunakan alat berat

    2 Kondisi Jalan : sedang / baik

    3 Jarak Quarry ke lokasi Base Camp L 5,00 Km

    4 Harga satuan pasir di Quarry RpM01 1,00 M3 150.000,00

    5 Harga Satuan Dasar Excavator RpE01 1,00 Jam 665.551,00

    6 Harga Satuan Dasar Dump Truck RpE06 1,00 Jam 349.602,00

    II. URUTAN KERJA

    1 Pasir digali dengan Excavator

    2 Excavator sekaligus memuat pasir hasil

    galian ke dalam Dump Truck

    3 Dump Truck mengangkut pasir ke lokasi

    Base Camp

    III. PERHITUNGAN

    EXCAVATOR E01

    Kapasitas Bucket V 0,90 M3

    Faktor Bucket Fb 0,80 Muat Sedang

    Faktor Efisiensi alat Fa 0,75 - Kondisi Baik

    Faktor Pengembangan Bahan Fh 1,10 Asli - Lepas

    Waktu siklus / Cycle Time CT

    - Waktu Gali T1 15,00 Detik

    - Waktu Buang / Muat T2 8,00 Detik

    - Waktu Swing T3 8,00 Detik

    CT 31,00 Detik

    Kap. Prod. / jam =

    V x Fb x Fa x 60 Q1 57,01 M3 / Jam

    Ts1 x Fh

    Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 11.674,53 Rupiah

    DUMP TRUCK E06

    Kapasitas bak V 3,00 M3

    Faktor efisiensi alat Fa 0,75 - Kondisi Baik

    Kecepatan rata-rata bermuatan v1 40,00 KM/Jam

    Kecepatan rata-rata kosong v2 60,00 KM/Jam

    Waktu siklus Ts2

    - Waktu tempuh isi = (L/v1) x 60 T1 7,50 menit

    - Waktu tempuh kosong = (L/v2) x 60 T2 5,00 menit

    - Muat = (V/Q1) x 60 T3 3,16 menit

    - Lain-lain T4 5,00 menit

    Ts2 20,66 menit

    ANALISA HARGA DASAR SATUAN BAHAN

  • 7/26/2019 4. Analisa Harga

    63/80

    Jenis : Pasir Pasang

    Lokasi : Quarry

    Tujuan : Base Camp

    HARGA

    No. URAIAN KODE KOEF. SATUAN SATUAN

    (Rp.)

    Kapasitas Produksi / Jam =

    V x Fa x 60 Q2 6,54 M3 / Jam

    Ts2

    Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 53.495,34 Rupiah

    IV. HARGA SATUAN DASAR BAHAN

    DI LOKASI BASE CAMP

    Harga Satuan Dasar Pasir =

    ( RpM01 + Rp1 + Rp2 ) M01 215.169,87 Rupiah

    Dibulatkan : M01 215.200,00 Rupiah

    dipindahkan ke Daftar Harga Satuan Upah, Bahan

    dan peralatan

    ANALISA HARGA DASAR SATUAN BAHAN

  • 7/26/2019 4. Analisa Harga

    64/80

    Jenis : Pasir Beton

    Lokasi : Quarry

    Tujuan : Base Camp

    HARGA

    No. URAIAN KODE KOEF. SATUAN SATUAN

    (Rp.)

    I. ASUMSI

    1 Menggunakan alat berat

    2 Kondisi Jalan : sedang / baik

    3 Jarak Quarry ke lokasi Base Camp L 5,00 Km

    4 Harga satuan pasir di Quarry RpM01 1,00 M3 150.000,00

    5 Harga Satuan Dasar Excavator RpE01 1,00 Jam 665.551,00

    6 Harga Satuan Dasar Dump Truck RpE06 1,00 Jam 349.602,00

    II. URUTAN KERJA

    1 Pasir digali dengan Excavator

    2 Excavator sekaligus memuat pasir hasil

    galian ke dalam Dump Truck

    3 Dump Truck mengangkut pasir ke lokasi

    Base Camp

    III. PERHITUNGAN

    EXCAVATOR E01

    Kapasitas Bucket V 0,90 M3

    Faktor Bucket Fb 1,00 Muat Sedang

    Faktor Efisiensi alat Fa 0,75 - Kondisi Baik

    Faktor Pengembangan Bahan Fh 1,10 Asli - Lepas

    Waktu siklus / Cycle Time CT

    - Waktu Gali T1 15,00 Detik

    - Waktu Buang / Muat T2 8,00 Detik

    - Waktu Swing T3 8,00 Detik

    CT 31,00 Detik

    Kap. Prod. / jam =

    V x Fb x Fa x 60 Q1 71,26 M3 / Jam

    Ts1 x Fh

    Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 9.339,63 Rupiah

    DUMP TRUCK E06

    Kapasitas bak V 3,00 M3

    Faktor efisiensi alat Fa 0,75 - Kondisi Baik

    Kecepatan rata-rata bermuatan v1 40,00 KM/Jam

    Kecepatan rata-rata kosong v2 60,00 KM/Jam

    Waktu siklus Ts2

    - Waktu tempuh isi = (L/v1) x 60 T1 7,50 menit

    - Waktu tempuh kosong = (L/v2) x 60 T2 5,00 menit

    - Muat = (V/Q1) x 60 T3 2,53 menit

    - Lain-lain T4 5,00 menit

    Ts2 20,03 menit

    ANALISA HARGA DASAR SATUAN BAHAN

  • 7/26/2019 4. Analisa Harga

    65/80

  • 7/26/2019 4. Analisa Harga

    66/80

    Jenis : Koral Beton

    Lokasi : Quarry

    Tujuan : Base Camp

    HARGA

    No. URAIAN KODE KOEF. SATUAN SATUAN

    (Rp.)

    I. ASUMSI

    1 Menggunakan alat berat

    2 Kondisi Jalan : sedang / baik

    3 Jarak Quarry ke lokasi Base Camp L 5,00 Km

    4 Harga satuan koral beton di Quarry RpM01 1,00 M3 250.000,00

    5 Harga Satuan Dasar Excavator RpE01 1,00 Jam 665.551,00

    6 Harga Satuan Dasar Dump Truck RpE06 1,00 Jam 349.602,00

    II. URUTAN KERJA

    1 Koral digali dengan Excavator

    2 Excavator sekaligus memuat koral hasil

    galian ke dalam Dump Truck

    3 Dump Truck mengangkut koral ke lokasi

    Base Camp

    III. PERHITUNGAN

    EXCAVATOR E01

    Kapasitas Bucket V 0,90 M3

    Faktor Bucket Fb 0,60 Muat Sulit

    Faktor Efisiensi alat Fa 0,75 - Kondisi Baik

    Faktor Pengembangan Bahan Fh 1,25 Asli - Lepas

    Waktu siklus / Cycle Time CT

    - Waktu Gali T1 15,00 Detik

    - Waktu Buang / Muat T2 8,00 Detik

    - Waktu Swing T3 8,00 Detik

    CT 31,00 Detik

    Kap. Prod. / jam =

    V x Fb x Fa x 60 Q1 37,63 M3 / Jam

    Ts1 x Fh

    Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 17.688,68 Rupiah

    DUMP TRUCK E06

    Kapasitas bak V 3,00 M3

    Faktor efisiensi alat Fa 0,75 - Kondisi Baik

    Kecepatan rata-rata bermuatan v1 40,00 KM/Jam

    Kecepatan rata-rata kosong v2 60,00 KM/Jam

    Waktu siklus Ts2

    - Waktu tempuh isi = (L/v1) x 60 T1 7,50 menit

    - Waktu tempuh kosong = (L/v2) x 60 T2 5,00 menit

    - Muat = (V/Q1) x 60 T3 4,78 menit

    - Lain-lain T4 5,00 menit

    Ts2 22,28 menit

    ANALISA HARGA DASAR SATUAN BAHAN

  • 7/26/2019 4. Analisa Harga

    67/80

    Jenis : Koral Beton

    Lokasi : Quarry

    Tujuan : Base Camp

    HARGA

    No. URAIAN KODE KOEF. SATUAN SATUAN

    (Rp.)

    Kapasitas Produksi / Jam =

    V x Fa x 60 Q2 6,06 M3 / Jam

    Ts2

    Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 57.707,51 Rupiah

    IV. HARGA SATUAN DASAR BAHAN

    DI LOKASI BASE CAMP

    Harga Satuan Dasar Pasir =

    ( RpM01 + Rp1 + Rp2 ) M01 325.396,19 Rupiah

    Dibulatkan : M01 325.400,00 Rupiah

    dipindahkan ke Daftar Harga Satuan Upah, Bahan

    dan peralatan

    ANALISA HARGA DASAR SATUAN BAHAN

  • 7/26/2019 4. Analisa Harga

    68/80

  • 7/26/2019 4. Analisa Harga

    69/80

  • 7/26/2019 4. Analisa Harga

    70/80

  • 7/26/2019 4. Analisa Harga

    71/80

    Jenis : Batu Pecah M esin 2/3

    Lokasi : Stone Craser

    Tujuan : Base Camp

    HARGA

    No. URAIAN KODE KOEF. SATUAN SATUAN

    (Rp.)

    Kapasitas Produksi / Jam =

    V x Fa x 60 Q2 4,11 M3 / Jam

    Ts2

    Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 85.122,57 Rupiah

    IV. HARGA SATUAN DASAR BAHAN

    DI LOKASI BASE CAMP

    Harga Satuan Dasar Pasir =

    ( RpM01 + Rp1 + Rp2 ) M01 495.735,78 Rupiah

    Dibulatkan : M01 495.700,00 Rupiah

    dipindahkan ke Daftar Harga Satuan Upah, Bahan

    dan peralatan

    ANALISA HARGA DASAR SATUAN BAHAN

  • 7/26/2019 4. Analisa Harga

    72/80

  • 7/26/2019 4. Analisa Harga

    73/80

    Jenis : Batu Belah 10/15 cm

    Lokasi : Quarry

    Tujuan : Base Camp

    HARGA

    No. URAIAN KODE KOEF. SATUAN SATUAN

    (Rp.)

    Kapasitas Produksi / Jam =

    V x Fa x 60 Q2 3,48 M3 / Jam

    Ts2

    Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 100.516,57 Rupiah

    IV. HARGA SATUAN DASAR BAHAN

    DI LOKASI BASE CAMP

    Harga Satuan Dasar Pasir =

    ( RpM01 + Rp1 + Rp2 ) M01 333.109,40 Rupiah

    Dibulatkan : M01 333.100,00 Rupiah

    dipindahkan ke Daftar Harga Satuan Upah, Bahan

    dan peralatan

    ANALISA HARGA DASAR SATUAN BAHAN

  • 7/26/2019 4. Analisa Harga

    74/80

    Jenis : Semen ( 50 Kg/Zak)

    Lokasi : Kota

    Tujuan : Base camp

    HARGA

    No. URAIAN KODE KOEF. SATUAN SATUAN

    (Rp.)

    I. ASUMSI

    1 Menggunakan Kendaran roda empat

    2 Kondisi Jalan : sedang / baik

    3 Jarak toko ke lokasi Kerja L 20,00 Km

    4 Harga satuan Semen di RpM09 1,00 Zak 80.000,00

    5 Harga Satuan Dasar Dump Truck RpE06 1,00 Jam 349.602,00

    II. URUTAN KERJA

    1

    2 Setelah semen sampai di lokasi kerja dimasukan

    dalam gudang

    III. PERHITUNGAN

    Biaya pembelian semen di . Rp.01 1.600,00 kg

    Biaya menaikan dan menurunkan semen di truck Rp.02 100,00 kg

    Biaya Penggudangan Rp.03 100,00 kg

    DUMP TRUCK (E08)

    Kapasitas bak V 3.500,00 KgFaktor efisiensi alat Fa 0,75 - Kondisi Baik

    Kecepatan rata-rata bermuatan v1 40,00 KM/Jam

    Kecepatan rata-rata kosong v2 60,00 KM/Jam

    Waktu siklus Ts2

    - Waktu tempuh isi = (L/v1) x 60 T1 30,00 menit

    - Waktu tempuh kosong = (L/v2) x 60 T2 20,00 menit

    - Waktu bongkar Muat T3 90,00 menit

    - Lain-lain T4 5,00 menit

    TsL 145,00 menit

    Kapst Produksi/Jam =

    V x Fa x 60 Q1 1.086,21 Kg/Jam

    Tsl

    Biaya Dump Truck/Kg = (L1/Q1) x Rp. E 08 Rp.04 321,86 Rp/Kg

    IV HARGA SATUAN DASAR SEMEN DI LOKASI KERJA

    Harga Satuan Semen

    = (Rp.01 + Rp.02 + Rp.03 + Rp. 04) M09 2.121,86 Kg/Rp

    M09 106.092,79 Zak/Rp

    Dibulatkan : M09 106.100,00 Rupiah

    dipindahkan ke Daftar Harga Satuan Upah,

    Bahan dan Peralatan

    Semen dibeli di ..., diangkut dengan menggunakan

    tenaga manusia kemudian diangkut ke lokasi kerja

    dengan truck

    ANALISA HARGA DASAR SATUAN BAHAN

  • 7/26/2019 4. Analisa Harga

    75/80

    Jenis : Baja Tulangan

    Lokasi : Kota .

    Tujuan : Base Camp

    HARGA

    No. URAIAN KODE KOEF. SATUAN SATUAN

    (Rp.)

    I. ASUMSI

    1 Menggunakan Kendaran roda empat

    2 Kondisi Jalan : sedang / baik

    3 Jarak toko ke lokasi Kerja L 20,00 Km

    4 Harga satuan Baja tulangan di RpM10 1,00 Kg 20.000,00

    5 Harga Satuan Dasar Dump Truck RpE08 1,00 Jam 349.602,00

    II. URUTAN KERJA

    1

    III. PERHITUNGAN

    Biaya pembelian Baja Tulangan di .. Rp.01 20.000,00 kg

    Biaya menaikan dan menurunkan Baja Tulangan di truck Rp.02 500,00 kg

    Biaya Penggudangan Rp.02 100,00 kg

    DUMP TRUCK (E08)

    Kapasitas bak V 3.500,00 Kg

    Faktor efisiensi alat Fa 0,75 - Kondisi Baik

    Kecepatan rata-rata bermuatan v1 40,00 KM/Jam

    Kecepatan rata-rata kosong v2 50,00 KM/Jam

    Waktu siklus Ts2

    - Waktu tempuh isi = (L/v1) x 60 T1 30,00 menit

    - Waktu tempuh kosong = (L/v2) x 60 T2 24,00 menit

    - Waktu bongkar Muat T3 120,00 menit

    - Lain-lain T4 30,00 menit

    TsL 204,00 menit

    Kapst Produksi/Jam =

    V x Fa x 60 Q1 772,06 Kg/Jam

    Tsl

    Biaya Dump Truck/Kg = (L1/Q1) x Rp. E 08 Rp.04 452,82 Rp/Kg

    IV HARGA SATUAN DASAR BAJA TULANGAN DI LOKASI KERJA

    Harga Satuan Semen

    = (Rp.01 + Rp.02 + Rp.03 + Rp. 04) M10 21.052,82 Kg/Rp

    Dibulatkan : M10 21.100,00 Rupiah

    dipindahkan ke Daftar Harga Satuan Upah,

    Bahan dan Peralatan

    ANALISA HARGA DASAR SATUAN BAHAN

    Baja Tulangan dibeli di ..., diangkut dengan

    menggunakan tenaga manusia kemudian diangkut ke

    lokasi kerja

  • 7/26/2019 4. Analisa Harga

    76/80

    Jenis : Kawat Ikat Beton

    Lokasi : Kota .

    Tujuan : Base Camp

    HARGA

    No. URAIAN KODE KOEF. SATUAN SATUAN

    (Rp.)

    I. ASUMSI

    1 Menggunakan Kendaran roda empat

    2 Kondisi Jalan : sedang / baik

    3 Jarak toko ke lokasi Kerja L 20,00 Km

    4 Harga satuan Baja tulangan di RpM10 1,00 Kg 22.000,00

    5 Harga Satuan Dasar Dump Truck RpE08 1,00 Jam 349.602,00

    II. URUTAN KERJA

    1

    III. PERHITUNGAN

    Biaya pembelian Baja Tulangan di .. Rp.01 22.000,00 kg

    Biaya menaikan dan menurunkan Baja Tulangan di truck Rp.02 500,00 kg

    Biaya Penggudangan Rp.02 100,00 kg

    DUMP TRUCK (E08)

    Kapasitas bak V 3.500,00 Kg

    Faktor efisiensi alat Fa 0,75 - Kondisi Baik

    Kecepatan rata-rata bermuatan v1 40,00 KM/Jam

    Kecepatan rata-rata kosong v2 50,00 KM/Jam

    Waktu siklus Ts2

    - Waktu tempuh isi = (L/v1) x 60 T1 30,00 menit

    - Waktu tempuh kosong = (L/v2) x 60 T2 24,00 menit

    - Waktu bongkar Muat T3 120,00 menit

    - Lain-lain T4 30,00 menit

    TsL 204,00 menit

    Kapst Produksi/Jam =

    V x Fa x 60 Q1 772,06 Kg/Jam

    Tsl

    Biaya Dump Truck/Kg = (L1/Q1) x Rp. E 08 Rp.04 452,82 Rp/Kg

    IV HARGA SATUAN DASAR BAJA TULANGAN DI LOKASI KERJA

    Harga Satuan Semen

    = (Rp.01 + Rp.02 + Rp.03 + Rp. 04) M10 23.052,82 Kg/Rp

    Dibulatkan : M10 23.100,00 Rupiah

    dipindahkan ke Daftar Harga Satuan Upah,

    Bahan dan Peralatan

    ANALISA HARGA DASAR SATUAN BAHAN

    Baja Tulangan dibeli di ..., diangkut dengan

    menggunakan tenaga manusia kemudian diangkut ke

    lokasi kerja

  • 7/26/2019 4. Analisa Harga

    77/80

  • 7/26/2019 4. Analisa Harga

    78/80

    Jenis : Sirtu

    Lokasi : Quarry

    Tujuan : Base Camp

    HARGA

    No. URAIAN KODE KOEF. SATUAN SATUAN

    (Rp.)

    Kapasitas Produksi / Jam =

    V x Fa x 60 Q2 2,30 M3 / Jam

    Ts2

    Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 151.721,99 Rupiah

    IV. HARGA SATUAN DASAR BAHAN

    DI LOKASI BASE CAMP

    Harga Satuan Dasar Pasir =

    ( RpM01 + Rp1 + Rp2 ) M01 289.988,51 Rupiah

    Dibulatkan : M01 290.000,00 Rupiah

    dipindahkan ke Daftar Harga Satuan Upah, Bahan

    dan peralatan

    ANALISA HARGA DASAR SATUAN BAHAN

  • 7/26/2019 4. Analisa Harga

    79/80

    Jenis : Tanah Timbunan

    Lokasi : Quarry

    Tujuan : Base Camp

    HARGA

    No. URAIAN KODE KOEF. SATUAN SATUAN

    (Rp.)

    I. ASUMSI

    1 Menggunakan alat berat

    2 Kondisi Jalan : sedang / baik

    3 Jarak Quarry ke lokasi Base Camp L 3,00 Km

    4 Harga satuan tanah di Quarry RpM01 1,00 M3 50.000,00

    5 Harga Satuan Dasar Excavator RpE01 1,00 Jam 665.551,00

    6 Harga Satuan Dasar Dump Truck RpE06 1,00 Jam 349.602,00

    II. URUTAN KERJA

    1 Tanah digali dengan Excavator

    2 Excavator sekaligus memuat tanh hasil

    galian ke dalam Dump Truck

    3 Dump Truck mengangkut tanah ke lokasi

    Base Camp

    III. PERHITUNGAN

    EXCAVATOR E01

    Kapasitas Bucket V 0,90 M3

    Faktor Bucket Fb 0,80 Muat Sedang

    Faktor Efisiensi alat Fa 0,75 - Kondisi Baik

    Faktor Pengembangan Bahan Fh 1,25 Asli - Lepas

    Waktu siklus / Cycle Time CT

    - Waktu Gali T1 8,00 Detik

    - Waktu Buang / Muat T2 8,00 Detik

    - Waktu Swing T3 8,00 Detik

    CT 24,00 Detik

    Kap. Prod. / jam =

    V x Fb x Fa x 60 Q1 64,80 M3 / Jam

    Ts1 x Fh

    Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 10.270,85 Rupiah

    DUMP TRUCK E06

    Kapasitas bak V 3,00 M3

    Faktor efisiensi alat Fa 0,75 - Kondisi Baik

    Kecepatan rata-rata bermuatan v1 40,00 KM/Jam

    Kecepatan rata-rata kosong v2 60,00 KM/Jam

    Waktu siklus Ts2

    - Waktu tempuh isi = (L/v1) x 60 T1 4,50 menit

    - Waktu tempuh kosong = (L/v2) x 60 T2 3,00 menit

    - Muat = (V/Q1) x 60 T3 2,78 menit

    - Lain-lain T4 2,00 menit

    Ts2 12,28 menit

    ANALISA HARGA DASAR SATUAN BAHAN

  • 7/26/2019 4. Analisa Harga

    80/80