  • SPESIFIKASI TEKNIS UMUM

    DAN

    SPESIFIKASI TEKNIS KHUSUS

    2014

    PEMERINTAH KABUPATEN BOGOR

    DINAS BINA MARGA DAN PENGAIRAN

    BIDANG PEMBANGUNAN DAN REHABLITASI

    JALAN DAN JEMBATAN

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR i

    SPESIFIKASI UMUM & KHUSUS

    JALAN DAN JEMBATAN

    DAFTAR ISI

    DIVISI 1 UMUM

    SEKSI 1.1 RINGKASAN PEKERJAAN.............................................................................. 1-1

    Pasal 1.1.1 CAKUPAN PEKERJAAN............................................................................................................. 1-1

    1.1.2 KLASIFIKASI PEKERJAAN KONSTRUKSI.......................................................................... 1-2

    1.1.3 KETENTUAN REKAYASA (ENGINEERING).................................................................... 1-6

    1.1.4 URUTAN PEKERJAAN............................................................................................................... 1-7

    1.1.5 PEMBAYARAN PEKERJAAN................................................................................................... 1-7

    SEKSI 1.2 MOBILISASI................................................................................................................... 1-10

    Pasal 1.2.1 UMUM ............................................................................................................................................. 1-10 1.2.2 PROGRAM MOBILISASI............................................................................................................ 1-11

    1.2.3 PENGUKURAN DAN PEMBAYARAN................................................................................... 1-12

    SEKSI 1.3 KANTOR LAPANGAN DAN FASILITASNYA................................................. 1-14

    Pasal 1.3.1 UMUM ............................................................................................................................................. 1-14

    1.3.2 KANTOR KONTRAKTOR DAN FASILITASNYA.............................................................. 1-15

    1.3.3 BENGKEL DAN GUDANG KONTRAKTOR......................................................................... 1-16

    1.3.4 KANTOR DAN AKOMODASI UNTUK DIREKSI PEKERJAAN..................................... 1-16

    1.3.5 PENGUKURAN DAN PEMBAYARAN.................................................................................. 1-16

    SEKSI 1.4 FASILITAS DAN PELAYANAN PENGUJIAN................................................. 1-17

    Pasal 1.4.1 UMUM ............................................................................................................................................. 1-17

    1.4.2 FASILITAS LABORATORIUM DAN PENGUJIAN............................................................ 1-18

    1.4.3 PROSEDUR PELAKSANAAN................................................................................................... 1-19

    1.4.4 PENGUKURAN DAN PEMBAYARAN................................................................................... 1-20

    SEKSI 1.5 TRANSPORTASI DAN PENANGANAN.................................................................... 1-22

    Pasal 1.5.1 UMUM............................................................................................................................................... 1-22 1.5.2 PELAKSANAAN............................................................................................................................. 1-22

    SEKSI 1.6 PEMBAYARAN SERTIFIKAT BULANAN..................................................... 1-24

    Pasal 1.6.1 UMUM .............................................................................................................................................. 1-24 1.6.2 PENYIAPAN DAN PENYERAHAN......................................................................................... 1-25

    1.6.3 PENGESAHAN OLEH DIREKSI PEKERJAAN.................................................................... 1-26

    SEKSI 1.7 PEMBAYARAN SEMENTARA (PROVISIAL SUMS)............................................ 1-28

    (TIDAK ADA PEMBAYARAN SEMENTARA DI DALAM KONTRAK INI)

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR ii

    SEKSI 1.8 PEMELIHARAAN DAN PENGATURAN LALU LINTAS................................ 1-29

    Pasal 1.8.1 UMUM ............................................................................................................................................. 1-29

    1.8.2 PERLINDUNGAN PEK. THD KERUSAKAN AKIBAT LALU LINTAS........................ 1-29

    1.8.3 PEKERJAAN JALAN ATAU JEMBATAN SEMENTARA................................................. 1-30

    1.8.4 PENGATURAN SEMENTARA UNTUK LALU LINTAS................................................... 1-31

    1.8.5 PEMELIHARAAN UNTUK KESELAMATAN LALU LINTAS......................................... 1-31

    1.8.6 DASAR PEMBAYARAN.............................................................................................................. 1-31

    SEKSI 1.9 REKAYASA LAPANGAN........................................................... 1-33

    Pasal 1.9.1 UMUM .............................................................................................................................................. 1-33

    1.9.2 PEK. SURVEY LAPANGAN UNTUK PENINJAUAN KEMBALI RANCANGAN ....... 1-33

    1.9.3 PEKERJAAN SURVEY PELAKSANAAN RUTIN...................................................... 1-37

    1.9.4 PENETAPAN TITIK PENGUKURAN..................................................................................... 1-37

    1.9.5 TENAGA AHLI REKAYASA LAPANGAN. 1-38 1.9.6 PENGENDALIAN MUTU BAHAN... 1-39

    1.9.7 DASAR PEMBAYARAN 1-39

    SEKSI 1.10 STANDAR RUJUKAN. 1-40

    Pasal 1.10.1 UMUM 1-40

    1.10.2 JAMINAN MUTU.. 1-40

    SEKSI 1.11 BAHAN DAN PENYIMPANAN 1-42

    Pasal 1.11.1 UMUM. 1-42

    1.11.2 PENGADAAN BAHAN 1-43

    1.11.3 PENYIMPANAN BAHAN.. 1-43

    1.11.4 PEMBAYARAN... 1-44

    SEKSI 1.12 JADWAL PELAKSANAAN.. 1-45

    Pasal 1.12.1 UMUM. 1-45

    1.12.2 DETAIL JADWAL PELAKSANAAN. 1-46

    1.12.3 REVISI JADWAL PELAKSANAAN... 1-47

    1.12.4 RAPAT PEMBUKTIAN KETERLAMBATAN (SHOW CAUSE MEETING).. 1-47

    SEKSI 1.13 PROSEDUR VARIASI 1-49

    Pasal 1.13.1 UMUM. 1-49

    1.13.2 PROSEDUR AWAL VARIASI.. 1-50 1.13.3 PELAKSANAAN VARIASI 1-51

    1.13.4 PELAKSANAAN ADDENDA 1-51

    SEKSI 1.14 PENUTUPAN KONTRAK 1-53

    Pasal 1.14.1 UMUM. 1-53

    1.14.2 BERITA ACARA PENYELESAIAN AKHIR... 1-53

    1.14.3 PENGAJUAN BERITA ACARA PEMBAYARAN AKHIR 1-54

    1.14.4 ADDENDUM PENUTUP 1-55

    SEKSI 1.15 DOKUMEN REKAMAN PROYEK 1-56

    Pasal 1.15.1 UMUM. 1-56

    1.15.2 DOKUMEN REKAMAN PROYEK. 1-56

    1.15.3 BAHAN REKAMAN PROYEK. 1-57

    1.15.4 PEMELIHARAAN DOKUMEN PELAKSANAAN PROYEK... 1-57

    1.15.5 DOKUMEN REKAMAN AKHIR. 1-59

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR iii

    SEKSI 1.16 PEKERJAAN PEMBERSIHAN.. 1-60

    Pasal 1.16.1 UMUM. 1-60

    1.16.2 PEMBERSIHAN SELAMA PELAKSANAAN 1-60

    1.16.3 PEMBERSIHAN AKHIR. 1-61

    1.16.4 DASAR PEMBAYARAN. 1-61

    SEKSI 1.17 ASPEK LINGKUNGAN HIDUP. 1-62

    Pasal 1.17.1 UMUM. 1-62

    1.17.2 UPAYA PENGELOLAAN LINGKUNGAN (UKL) 1-62

    1.17.3 DASAR PEMBAYARAN. 1-66

    SEKSI 1.18 RELOKASI UTILITAS DAN PELAYANAN YANG ADA 1-67

    Pasal 1.18.1 UMUM. 1-67

    1.18.2 PELAKSANAAN. 1-68 1.18.3 PENGUKURAN DAN PEMBAYARAN 1-70

    DIVISI 2 DRAINASE

    SEKSI 2.1 SELOKAN DAN SALURAN AIR.............................................................................. 2-1

    Pasal 2.1.1 UMUM............................................................................................................... 2-1

    2.1.2 BAHAN DAN JAMINAN MUTU........................................................................... 2-3

    2.1.3 PELAKSANAAN....................................................................... 2-4

    2.1.4 PENGUKURAN DAN PEMBAYARAN............................................................................. 2-5

    SEKSI 2.2 PASANGAN BATU DENGAN MORTAR.......................................................... 2-6

    Pasal 2.2.1 UMUM ............................................................................................................................................... 2-6

    2.2.2 BAHAN DAN JAMINAN MUTU................................................................................................. 2-8

    2.2.3 PELAKSANAAN...................................................................................... 2-9

    2.2.4 PENGUKURAN DAN PEMBAYARAN. 2-10

    SEKSI 2.3 GORONG-GORONG DAN DRAINASE BETON................................................. 2-12

    Pasal 2.3.1 UMUM ............................................................................................................................................... 2-12

    2.3.2 BAHAN.............................................................. 2-14

    2.3.3 PELAKSANAAN........................................................................... 2-15

    2.3.4 PENGUKURAN DAN PEMBAYARAN..................................... 2-18

    SEKSI 2.4 DRAINASE POROUS.................................................... 2-21

    Pasal 2.4.1 UMUM ............................................................................................................................................... 2-21

    2.4.2 BAHAN.............................................................. 2-23 2.4.3 PEMASANGAN DRAINASE POROUS.......................................................................... 2-26

    2.4.4 PENGUKURAN DAN PEMBAYARAN..................................................................................... 2-28

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR iv

    DIVISI 3 PEKERJAAN TANAH

    SEKSI 3.1 GALIAN.............................................................................. 3-1

    Pasal 3.1.1 UMUM............................................................................................................... 3-1

    3.1.2 PROSEDUR PENGGALIAN............................................................................ 3-7

    3.1.3 PENGUKURAN DAN PEMBAYARAN............................................................................. 3-9

    SEKSI 3.2 TIMBUNAN.......................................................... 3-13

    Pasal 3.2.1 UMUM ............................................................................................................................................... 3-13

    3.2.2 BAHAN................................................................................................... 3-17

    3.2.3 PENGHAMPARAN DAN PEMADATAN TIMBUNAN........................................................ 3-19

    3.2.4 JAMINAN MUTU... 3-22

    3.2.5 PENGUKURAN DAN PEMBAYARAN.............................................................................. 3-23

    SEKSI 3.3 PENYIAPAN BADAN JALAN................................................... 3-26

    Pasal 3.3.1 UMUM ............................................................................................................................................... 3-26

    3.3.2 BAHAN.............................................................. 3-28

    3.3.3 PELAKSANAAN DAN PENYIAPAN BADAN JALAN......................................................... 3-29

    3.3.4 PENGUKURAN DAN PEMBAYARAN..................................... 3-29

    SEKSI 3.4 PENGUPASAN PERMUKAAN PERKERASAN LAMA DAN DICAMPUR

    KEMBALI......................................................................................................................... 3-30

    Pasal 3.4.1 UMUM ............................................................................................................................................... 3-30

    3.4.2 PELAKSANAAN................................................................ 3-32 3.4.3 PENGUKURAN DAN PEMBAYARAN..................................................................................... 3-32

    DIVISI 4 PELEBARAN PERKERASAN DAN BAHU JALAN

    SEKSI 4.1 PELEBARAN PERKERASAN.............................................................................. 4-1

    Pasal 4.1.1 UMUM............................................................................................................... 4-1

    4.1.2 BAHAN............................................................................. 4-2

    4.1.3 PERSIAPAN UNTUK PELEBARAN PERKERASAN........................................................... 4-2

    4.1.4 PENGHAMPARAN & PEMADATAN BAHAN PELEBARAN PERKERASAN.. 4-4

    4.1.5 PENGUKURAN DAN PEMBAYARAN.............................................................................. 4-5

    SEKSI 4.2 BAHU JALAN.......................................................... 4-6

    Pasal 4.2.1 UMUM ............................................................................................................................................... 4-6

    4.2.2 BAHAN................................................................................................... 4-8

    4.2.3 PELAKSANAAN DAN PEMADATAN......................................................... 4-8

    4.2.4 PENGUKURAN DAN PEMBAYARAN.............................................................................. 4-8

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR v

    DIVISI 5 PERKERASAN BERBUTIR

    SEKSI 5.1 LAPIS PONDASI AGREGAT.............................................................................. 5-1

    Pasal 5.1.1 UMUM............................................................................................................... 5-1

    5.1.2 BAHAN............................................................................. 5-4

    5.1.3 PENGHAMPARAN & PEMADATAN LAPIS PONDASI AGREGAT.... 5-6

    5.1.4 PENGUKURAN DAN PEMBAYARAN............................................................................. 5-8

    SEKSI 5.2 LAPIS PONDASI JALAN TANPA PENUTUP ASPAL .............................................. 5-10

    Pasal 5.2.1 UMUM ............................................................................................................................................... 5-10

    5.2.2 BAHAN................................................................................................... 5-12

    5.2.3 PENGHAMPARAN DAN PEMADATAN LAPIS PONDASI JALAN TANPA

    PENUTUP ASPAL............................................................ 5-15

    5.2.4 PENGUJIAN.. 5-18

    5.2.5 PENGUKURAN DAN PEMBAYARAN.............................................................................. 5-18

    SEKSI 5.3 TIDAK TERDAPAT SEKSI 5.3 DALAM DIVISI INI

    SEKSI 5.4 LAPIS PONDASI SEMEN TANAH............................................................................... 5-21

    Pasal 5.4.1 UMUM ............................................................................................................................................... 5-21

    5.4.2 BAHAN................................................................................................... 5-26

    5.4.3 CAMPURAN....................................................................... 5-28

    5.4.4 PERCOBAAN LAPANGAN (FIELD TRIALS).. 5-30

    5.4.5 PENGHAMPARAN DAN PENCAMPURAN........................................................................... 5-33 5.4.6 PENGENDALIAN MUTU... 5-40

    5.4.7 PENGUKURAN DAN PEMBAYARAN. 5-44

    SEKSI 5.5 LAPIS BETON SEMEN PONDASI BAWAH (CEMENT TREATED SUBBASE /

    CTSB)............................................................................................................................... 5-47

    Pasal 5.5.1 UMUM ............................................................................................................................................... 5-47

    5.5.2 BAHAN................................................................................................... 5-48

    5.5.3 CAMPURAN....................................................................... 5-50

    5.5.4 PERALATAN DAN PERKAKAS..... 5-51

    5.5.5 PELAKSANAAN PENGGALIAN ATAU PENAMBANGAN............................................ 5-52

    5.5.6 PENYIAPAN AGREGAT. 5-52

    5.5.7 PENCAMPURAN DAN PENGHAMPARAN.. 5-53

    5.5.8 KERATAAN PERMUKAAN.. 5-55

    5.5.9 PEMELIHARAAN.. 5-56

    5.5.10 PENGUKURAN DAN PEMBAYARAN. 5-56

    SEKSI 5.6 LAPIS PONDASI AGREGAT DENGAN CEMENT TREATED BASE

    (CTB)............................................................................................................................... 5-57

    Pasal 5.6.1 UMUM ............................................................................................................................................... 5-57

    5.6.2 BAHAN................................................................................................... 5-60

    5.6.3 CAMPURAN DAN TAKARAN....................................................................... 5-61 5.6.4 PERCOBAAN LAPANGAN (FIELD TRIALS).. 5-62

    5.6.5 PENGHAMPARAN DAN PENCAMPURAN.. 5-62

    5.6.6 PENGANGKUTAN. 5-62

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR vi

    5.6.7 PENGHAMPARAN DAN PEMADATAN.... 5-63

    5.6.8 PENGENDALIAN MUTU (QUALITY CONTROL).... 5-64

    5.6.9 PENGUKURAN DAN PEMBAYARAN. 5-64

    DIVISI 6 PERKERASAN ASPAL

    SEKSI 6.1 LAPIS RESAP PENGIKAT DAN LAPIS PEREKAT................................... 6-1

    Pasal 6.1.1 UMUM......................................................................................................... 6-1

    6.1.2 BAHAN....................................................................... 6-3

    6.1.3 PERALATAN......... 6-4

    6.1.4 PELAKSANAAN PEKERJAAN........................................................................ 6-7

    6.1.5 PEMELIHARAAN DAN PEMBUKAAN BAGI LALU LINTAS... 6-10

    6.1.6 PENGENDALIAN MUTU DAN PENGUJIAN DI LAPANGAN... 6-11

    6.1.7 PENGUKURAN DAN PEMBAYARAN... 6-11

    SEKSI 6.2 LABURAN ASPAL SATU LAPIS (BURTU) DAN LABURAN ASPAL DUA

    LAPIS (BURDA)...... ................................................ 6-13Pasal 6.2.1 UMUM ......................................................................................................................................... 6-13

    6.2.2 BAHAN............................................................................................. 6-16

    6.2.3 JENIS PEKERJAAN PELABURAN.......................................................... 6-18

    6.2.4 PERALATAN.. 6-18

    6.2.5 PELAKSANAAN PEKERJAAN........................................................................... 6-19

    6.2.6 PENGENDALIAN MUTU DAN PENGUJIAN LAPANGAN.. 6-22

    6.2.7 PENGUKURAN DAN PEMBAYARAN... 6-23

    SEKSI 6.3 CAMPURAN BERASPAL PANAS.. 6-25

    Pasal 6.3.1 UMUM.......................................................................................................................................... 6-25

    6.3.2 BAHAN............................................................................................. 6-31

    6.3.3 CAMPURAN.......................................................... 6-37

    6.3.4 KETENTUAN INSTALASI PENCAMPUR ASPAL...... 6-44

    6.3.5 PEMBUATAN DAN PRODUKSI CAMPURAN ASPAL................................................. 6-52

    6.3.6 PENGHAMPARAN CAMPURAN..... 6-55

    6.3.7 PENGENDALIAN MUTU DAN PEMERIKSAAN DI LAPANGAN... 6-58

    6.3.8 PENGUKURAN DAN PEMBAYARAN... 6-62

    SEKSI 6.4 LASBUTAG DAN LATASBUSIR.......................................................................... 6-65

    Pasal 6.4.1 UMUM.......................................................................................................................................... 6-65

    6.4.2 BAHAN............................................................................................. 6-68

    6.4.3 CAMPURAN................................................................. 6-72 6.4.4 KETENTUAN PERALATAN PELAKSANAAN.. 6-77

    6.4.5 PEMBUATAN CAMPURAN............................................................................................... 6-83

    6.4.6 PENGHAMPARAN CAMPURAN..... 6-85

    6.4.7 PENGENDALIAN MUTU DAN PEMERIKSAAN DI LAPANGAN... 6-88

    6.4.8 PENGUKURAN DAN PEMBAYARAN... 6-89

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR vii

    SEKSI 6.5 CAMPURAN ASPAL DINGIN.................................................................................. 6-93

    Pasal 6.5.1 UMUM.......................................................................................................................................... 6-93

    6.5.2 BAHAN............................................................................................. 6-94

    6.5.3 CAMPURAN................................................................. 6-96

    6.5.4 KETENTUAN PERALATAN PELAKSANAAN.. 6-97

    6.5.5 PEMBUATAN CAMPURAN............................................................................................... 6-98

    6.5.6 PEMERAMAN DAN PENYIMPANAN CAMPURAN.. 6-99

    6.5.7 PENGHAMPARAN CAMPURAN..... 6-99

    6.5.8 PENGUKURAN DAN PEMBAYARAN... 6-100

    SEKSI 6.6 LAPIS PENETRASI MACADAM....................................................... 6-102

    Pasal 6.6.1 UMUM.......................................................................................................................................... 6-102

    6.6.2 BAHAN.................................................................................................... 6-103

    6.6.3 KUANTITAS AGREGAT DAN ASPAL..................................................................... 6-104 6.6.4 PERALATAN.. 6-105

    6.6.5 PELAKSANAAN... 6-105

    6.6.6 PENGENDALIAN MUTU DAN PENGUJIAN DI LAPANGAN... 6-108

    6.6.7 PENGUKURAN DAN PEMBAYARAN... 6-109

    SEKSI 6.7 PEMELIHARAAN DENGAN LABURAN ASPAL.................................................. 6-111

    Pasal 6.7.1 UMUM.......................................................................................................................................... 6-111

    6.7.2 BAHAN.................................................................................................... 6-112

    6.7.3 KUANTITAS AGREGAT DAN ASPAL..................................................................... 6-112

    6.7.4 PERALATAN.. 6-113

    6.7.5 PELAKSANAAN... 6-113

    6.7.6 PENGUKURAN DAN PEMBAYARAN... 6-114

    DIVISI 7 STRUKTUR

    SEKSI 7.1 BETON............................................................................................................. 7-1

    Pasal 7.1.1 UMUM .................................................................................................................................................. 7-1

    7.1.2 BAHAN-BAHAN................................................................................................................................. 7-5

    7.1.3 PENCAMPURAN DAN PENAKARAN........................................................................................ 7-6

    7.1.4 PELAKSANAAN PENGECORAN................................................................................................. 7-10

    7.1.5 PEKERJAAN AKHIR......................................................................................................................... 7-14

    7.1.6 PENGENDALIAN MUTU DI LAPANGAN................................................................................ 7-16

    7.1.7 PENGUKURAN DAN PEMBAYARAN....................................................................................... 7-18

    SEKSI 7.2 BETON PRATEKAN......................................................................................... 7-20

    Pasal 7.2.1 UMUM .................................................................................................................................................. 7-20

    7.2.2 BAHAN.................................................................................................................................................. 7-23 7.2.3 PENGUJIAN........................................................................................................................................ 7-25

    7.2.4 PELAKSANAAN UNIT-UNIT........................................................................................................ 7-26

    7.2.5 METODE PENEGANGAN SEBELUM PENGECORAN (PRE-TENSION)...................... 7-29

    7.2.6 METODE PENEGANGAN SEBELUM PENGECORAN (POST-TENSION)..................... 7-33 7.2.7 PENANGANAN, PENGANGKUTAN DAN PENYIMPANAN UNIT-UNIT BETON

    PRACETAK...........................................................................................................................................

    7-37

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR viii

    7.2.8 PELAKSANAAN BALOK BETON PRATEKAN SEGMENTAL............................................ 7-38

    7.2.9 PEMASANGAN UNIT-UNIT BETON PRATEKAN................................................................. 7-40

    7.2.10 PENGUKURAN DAN PEMBAYARAN......................................................................................... 7-40

    SEKSI 7.3 BAJA TULANGAN............................................................................................. 7-43

    Pasal 7.3.1 UMUM .................................................................................................................................................. 7-43

    7.3.2 BAHAN.................................................................................................................................................. 7-45

    7.3.3 PEMBUATAN DAN PENEMPATAN.......................................................................................... 7-46

    7.3.4 PENGUKURAN DAN PEMBAYARAN......................................................................................... 7-47

    SEKSI 7.4 BAJA STRUKTUR............................................................................................. 7-49

    Pasal 7.4.1 UMUM .................................................................................................................................................. 7-49

    7.4.2 BAHAN................................................................................................................................................... 7-52

    7.4.3 KECAKAPAN KERJA........................................................................................................................ 7-53 7.4.4 PELAKSANAAN................................................................................................................................. 7-54

    7.4.5 PENGUKURAN DAN PEMBAYARAN......................................................................................... 7-57

    SEKSI 7.5 PEMASANGAN JEMBATAN RANGKA BAJA............................................................... 7-59

    Pasal 7.5.1 UMUM .................................................................................................................................................. 7-59

    7.5.2 BAHAN.................................................................................................................................................. 7-61

    7.5.3 PELAKSANAAN.................................................................................................................................. 7-64

    7.5.4 PENGUKURAN DAN PEMBAYARAN......................................................................................... 7-66

    SEKSI 7.6 TIANG PANCANG......................................................................................................... 7-69

    Pasal 7.6.1 UMUM .................................................................................................................................................. 7-69

    7.6.2 BAHAN................................................................................................................................................. 7-73

    7.6.3 TURAP.................................................................................................................................................. 7-74

    7.6.4 TIANG PANCANG KAYU................................................................................................................. 7-75

    7.6.5 TIANG PANCANG BETON PRACETAK.................................................................................... 7-76

    7.6.6 TIANG PANCANG BAJA STRUKTUR.......................................................................................... 7-79

    7.6.7 PEMANCANGAN TIANG................................................................................................................. 7-80

    7.6.8 TIANG BOR BETON COR LANGSUNG DI TEMPAT.............................................................. 7-83

    7.6.9 PENGUKURAN DAN PEMBAYARAN......................................................................................... 7-84

    SEKSI 7.7 PONDASI SUMURAN........................................................................................ 7-89

    Pasal 7.7.1 UMUM .................................................................................................................................................. 7-89 7.7.2 BAHAN.................................................................................................................................................. 7-90

    7.7.3 PELAKSANAAN................................................................................................................................. 7-90

    7.7.4 PENGUKURAN DAN PEMBAYARAN ........................................................................................ 7-92

    SEKSI 7.8 ADUKAN SEMEN............................................................................................. 7-93

    Pasal 7.8.1 UMUM .................................................................................................................................................. 7-93

    7.8.2 BAHAN CAMPURAN........................................................................................................................ 7-93

    7.8.3 PENCAMPURAN DAN PEMASANGAN..................................................................................... 7-94

    7.8.4 DASAR PEMBAYARAN ................................................................................................................... 7-94

    SEKSI 7.9 PASANGAN BATU........................................................................................... 7-95

    Pasal 7.9.1 UMUM .................................................................................................................................................. 7-95

    7.9.2 BAHAN.................................................................................................................................................. 7-96

    7.9.3 PELAKSANAAN PASANGAN BATU........................................................................................... 7-96

    7.9.4 PENGUKURAN DAN PEMBAYARAN......................................................................................... 7-98

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR ix

    SEKSI 7.10 PASANGAN BATU KOSONG DAN BRONJONG........................................................... 7-100

    Pasal 7.10.1 UMUM .................................................................................................................................................. 7-100

    7.10.2 BAHAN................................................................................................................................................... 7-101

    7.10.3 PELAKSANAAN.................................................................................................................................. 7-102

    7.10.4 PENGUKURAN DAN PEMBAYARAN......................................................................................... 7-103

    SEKSI 7.11 SAMBUNGAN EKSPANSI (EXPANSION JOINT).............................................. 7-104

    Pasal 7.11.1 UMUM .................................................................................................................................................. 7-104

    7.11.2 BAHAN.................................................................................................................................................. 7-105

    7.11.3 PELAKSANAAN................................................................................................................................. 7-106

    7.11.4 PENGUKURAN DAN PEMBAYARAN......................................................................................... 7-107

    SEKSI 7.12 PERLETAKAN (BEARING).............................................................................. 7-108Pasal 7.12.1 UMUM .................................................................................................................................................. 7-108

    7.12.2 BAHAN................................................................................................................................................... 7-113

    7.12.3 PELAKSANAAN.................................................................................................................................. 7-114

    7.12.4 PENGUKURAN DAN PEMBAYARAN......................................................................................... 7-117

    SEKSI 7.13 SANDARAN (RAILING)................................................................................... 7-118

    Pasal 7.13.1 UMUM .................................................................................................................................................. 7-118

    7.13.2 BAHAN.................................................................................................................................................. 7-119

    7.13.3 PERALATAN........................................................................................................................................ 7-120

    7.13.4 PELAKSANAAN................................................................................................................................... 7-120

    7.13.5 PENGUKURAN DAN PEMBAYARAN......................................................................................... 7-120

    SEKSI 7.14 PAPAN NAMA JEMBATAN................................................................................ 7-122

    Pasal 7.14.1 UMUM .................................................................................................................................................. 7-122

    7.14.2 BAHAN-BAHAN................................................................................................................................. 7-122

    7.14.3 PERALATAN......................................................................................................................................... 7-122

    7.14.4 PENGUKURAN DAN PEMBAYARAN......................................................................................... 7-122

    SEKSI 7.15 PEMBONGKARAN STRUKTUR........................................................................ 7-123

    Pasal 7.15.1 UMUM .................................................................................................................................................. 7-123

    7.15.2 PROSEDUR PEMBONGKARAN................................................................................................... 7-124

    7.15.3 PEMBUANGAN BAHAN BONGKARAN...................................................................... 7-124 7.15.4 PENGUKURAN DAN PEMBAYARAN......................................................................................... 7-125

    DIVISI 7 RIGID PAVEMENT

    SEKSI 7.16 PERKERASAN JALAN BETON.......................................................................... 7-1

    Pasal 7.1.1 UMUM .................................................................................................................................................. 7-1

    7.1.2 BAHAN-BAHAN................................................................................................................................. 7-4

    7.1.3 PENCAMPURAN DAN PENAKARAN........................................................................................ 7-5

    7.1.4 METODE KONSTRUKSI................................................................................................................. 7-10

    7.1.5 PEKERJAAN PENYELESAIAN...................................................................................................... 7-1

    7.1.6 SAMBUNGAN (JOINT).................................................................................................................... 7-4

    7.1.7 PENGENDALIAN KUALITAS DI LAPANGAN........................................................................ 7-5

    7.1.8 PENGUKURAN DAN PEMBAYARAN......................................................................................... 7-10

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR x

    SEKSI 7.17 WET LEAN CONCRETE................................................................................... 7-13

    Pasal 7.2.1 UMUM .................................................................................................................................................. 7-13

    7.2.2 BAHAN.................................................................................................................................................. 7-10

    7.2.3 PENCAMPURAN DAN PENAKARAN........................................................................................ 7-1

    7.2.4 METODE KONSTRUKSI................................................................................................................. 7-4

    7.2.5 PEKERJAAN PENYELESAIAN...................................................................................................... 7-5

    7.2.6 PENGENDALIAN KUALITAS DI LAPANGAN......................................................................... 7-14

    7.2.7 PENGUKURAN DAN PEMBAYARAN......................................................................................... 7-15

    DIVISI 8 PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR

    SEKSI 8.1 PENGEMBALIAN KONDISI PERKERASAN LAMA............................................ 8-1

    Pasal 8.1.1 UMUM .................................................................................................................................................. 8-1

    8.1.2 BAHAN ................................................................................................................................................ 8-4

    8.1.3 PELAKSANAAN.................................................................................................................................. 8-5

    8.1.4 PENGUKURAN DAN PEMBAYARAN......................................................................................... 8-10

    SEKSI 8.2 PENGEMBALIAN KONDISI BAHU JALAN LAMA PADA PERKERASAN

    BERPENUTUP ASPAL..................................................................................................... 8-13

    Pasal 8.2.1 UMUM .................................................................................................................................................. 8-13

    8.2.2 BAHAN DAN PELAKSANAAN..................................................................................................... 8-14

    8.2.3 PENGUKURAN DAN PEMBAYARAN......................................................................................... 8-15

    SEKSI 8.3 PENGEMBALIAN KONDISI SELOKAN, SALURAN AIR, GALIAN, TIMBUNAN

    DAN PENGHIJAUAN................................................................................................. 8-17

    Pasal 8.3.1 UMUM .................................................................................................................................................. 8-17

    8.3.2 BAHAN................................................................................................................................................... 8-18

    8.3.3 PELAKSANAAN.................................................................................................................................. 8-19

    8.3.4 PENGUKURAN DAN PEMBAYARAN......................................................................................... 8-22

    SEKSI 8.4 PERLENGKAPAN JALAN DAN PENGATUR LALU LINTAS.............................. 8-23

    Pasal 8.4.1 UMUM .................................................................................................................................................. 8-23

    8.4.2 BAHAN ................................................................................................................................................ 8-25

    8.4.3 PELAKSANAAN.................................................................................................................................. 8-27

    8.4.4 PENGUKURAN DAN PEMBAYARAN......................................................................................... 8-31

    SEKSI 8.5 PENGEMBALIAN KONDISI JEMBATAN.......................................................... 8-34

    Pasal 8.5.1 UMUM ................................................................................................................................................... 8-34

    8.5.2 CAKUPAN PEKERJAAN DAN PENGEMBALIAN KONDISI................................................ 8-37

    8.5.3 PENGEMBALIAN KONDISI KOMPONEN BETON............................................................... 8-38 8.5.4 PENGEMBALIAN KONDISI KOMPONEN KAYU................................................................ 8-42

    8.5.5 PENGEMBALIAN KONDISI KOMPONEN BAJA.................................................................... 8-48

    8.5.6 PENGUKURAN DAN PEMBAYARAN......................................................................................... 8-56

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR xi

    SEKSI 8.6 KERB PRACETAK PEMISAH JALAN (CONCRETE BARRIER)................................ 8-60

    Pasal 8.6.1 UMUM .................................................................................................................................................. 8-60

    8.6.2 BAHAN ................................................................................................................................................ 8-60

    8.6.3 PERLENGKAPAN DAN PERALATAN....................................................................................... 8-60

    8.6.4 PELAKSANAAN PEKERJAAN..................................................................................................... 8-61

    8.6.5 PEMASANGAN................................................................................................................................... 8-62

    8.6.6 PENGUKURAN DAN PEMBAYARAN......................................................................................... 8-63

    SEKSI 8.7 PENERANGAN JALAN DAN PEKERJAAN ELEKTRIKAL........................................ 8-64

    Pasal 8.7.1 UMUM .................................................................................................................................................. 8-64

    8.7.2 SATUAN PENERANGAN................................................................................................................. 8-66

    8.7.3 PANEL PENERANGAN................................................................................................................... 8-68

    8.7.4 TIANG-TIANG.................................................................................................................................... 8-70

    8.7.5 KABEL, GROUND, SAMBUNGAN DAN PIPA SALURAN KABEL (CONDUIT)........... 8-73 8.7.6 PENGUKURAN DAN PEMBAYARAN......................................................................................... 8-75

    SEKSI 8.8 PAGAR PEMISAH PEDESTRIAN.................................................................... 8-77

    Pasal 8.8.1 UMUM .................................................................................................................................................. 8-77

    8.8.2 BAHAN ................................................................................................................................................ 8-77

    8.8.3 PENGUKURAN DAN PEMBAYARAN......................................................................................... 8-79

    DIVISI 9 PEKERJAAN HARIAN

    SEKSI 9.1 PEKERJAAN HARIAN..................................................................................... 9-1

    Pasal 9.1.1 UMUM .............................................................................................................................................. 9-1

    9.1.2 BAHAN DAN PERALATAN....................................................................................................... 9-2

    9.1.3 PELAKSANAAN PEKERJAAN HARIAN................................................................................ 9-2

    9.1.4 PENGUKURAN DAN PEMBAYARAN.................................................................................... 9-3

    DIVISI 10 PEKERJAAN PEMELIHARAAN RUTIN

    SEKSI 10.1 PEMELIHARAAN RUTIN PERKERASAN, BAHU JALAN, DRAINASE,

    PERLENGKAPAN JALAN DAN JEMBATAN............................................... 10-1

    Pasal 10.1.1 UMUM ............................................................................................................................................. 10-1 10.1.2 PEMELIHARAAN RUTIN PERKERASAN........................................................................... 10-3

    10.1.3 PEMELIHARAAN RUTIN BAHU JALAN............................................................................. 10-6

    10.1.4 PEMELIHARAAN RUTIN SELOKAN, SALURAN AIR, GALIAN DAN

    TIMBUNAN................................................................................................................................... 10-6

    10.1.5 UMUM ............................................................................................................................................. 10-6

    10.1.6 PEMELIHARAAN RUTIN JEMBATAN................................................................................ 10-7

    10.1.7 PENGUKURAN DAN PEMBAYARAN................................................................................... 10-10

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR xii

    SEKSI 10.2 PEMELIHARAAN JALAN SAMPING DAN JEMBATAN................................ 10-12

    Pasal 10.2.1 UMUM ............................................................................................................................................. 10-12

    10.2.2 PEMELIHARAAN JALAN SAMPING DAN JEMBATAN YANG DIGUNAKAN

    OLEH KONTRAKTOR................................................................................................................

    10-12

    10.2.3 PEMELIHARAAN UNTUK KEAMANAN LALU LINTAS................................................ 10-13

    10.2.4 DASAR PEMBAYARAN.............................................................................................................. 10-13

  • 13

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR 1 - 1

    DIVISI 1

    UMUM

    SEKSI 1.1

    RINGKASAN PEKERJAAN

    1.1.1 CAKUPAN PEKERJAAN

    1) Cakupan pekerjaan dari Kontrak ini meliputi pelaksanaan pekerjaan jalan dan/atau jembatan, pada ruas jalan dan/atau jembatan tertentu dalam sistem jalan Kabupaten.

    Pekerjaan-pekerjaan yang dicakup di dalam Spesifikasi ini dibagi tiga kelompok,

    Pekerjaan Utama, Pekerjaan Pengembalian Kondisi dan Minor, dan Pekerjaan

    Pemeliharaaan Rutin.

    2) Kegiatan Pemeliharaan Rutin harus dimulai segera setelah periode Kontrak dimulai dan

    dimaksudkan untuk mencegah setiap kerusakan lebih lanjut pada jalan dan/atau

    jembatan minor. Kegiatan-kegiatan ini meliputi pekerjaan yang bersifat minor dan tidak

    dimaksudkan untuk mengembalikan kondisi jalan dan/atau jembatan ke kondisi semula

    yang lebih baik dan juga bukan memperbaiki kondisi jalan dan/atau jembatan ke kondisi

    yang lebih baik dari semula.

    3) Pekerjaan Pengembalian Kondisi harus dimulai sesegera mungkin selama periode

    mobilisasi dan dimaksudkan untuk mengembalikan jalan lama dan jembatan minor yang

    ada ke suatu kondisi yang dapat digunakan, konsisten dengan kebutuhan normal untuk

    jalan dan/atau jembatan menurut jenisnya. Jenis pekerjaan yang termasuk dalam pengembalian kondisi meliputi penambalan perkerasan, perbaikan tepi perkerasan,

    pelaburan permukaan yang retak, perataan berat pada jalan kerikil untuk menghilangkan

    keriting (corrugations) pada permukaan, perbaikan beton yang terkelupas atau retak,

    pengecatan kembali pada lapis pelindung yang terpengaruh cuaca untuk pekerjaan kayu

    dan baja, dsb.

    4) Pekerjaan Utama akan diterapkan pada ruas jalan termasuk jembatan minor yang pengembalian kondisinya telah selesai dan dimaksudkan untuk meningkatkan kondisi

    jalan termasuk jembatan minor ke kondisi yang lebih baik daripada sebelumnya.

    Pekerjaan Utama juga diterapkan untuk pembangunan jalan dan jembatan baru atau

    penggantian jembatan lama. Pekerjaan ini umumnya akan berupa overlay atau pelapisan kembali permukaan perkerasan, bila perlu, dilapisi terlebih dahulu dengan lapis

    perkuatan (strengthening layer). Pekerjaan semacam ini akan memperbaiki kerataan

    maupun bentuk permukaan jalan dan/atau meningkatkan proyeksi umur struktur

    perkerasan pada ruas jalan tersebut.

    5) Cakupan Kontrak ini juga mengharuskan Kontraktor untuk melakukan survei lapangan

    yang cukup detil selama periode mobilisasi agar Direksi Pekerjaan dapat melaksanakan

    revisi minor dan menyelesaikan detil pelaksanaan pekerjaan sebelum operasi

    pelaksanaan pekerjaan sebagaimana yang disyaratkan dalam Pasal 1.1.3 dari Spesifikasi

    ini.

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR 1 - 2

    1.1.2 KLASIFIKASI PEKERJAAN KONSTRUKSI

    1) Umum

    Dalam cakupan pekerjaan dari Kontrak ini, tiga kelompok pekerjaan yang berbeda yaitu

    pekerjaan utama, pekerjaan pengembalian kondisi dan minor, dan pekerjaan pemeliharan

    rutin, dapat terdiri dari, tetapi tidak terbatas pada, salah satu atau semua klasifikasi

    pekerjaan yang terdaftar di bawah ini.

    2) Pekerjaan Utama

    a) Pelapisan Struktural

    i) Overlay dengan lapisan aspal yang terdiri dari perataan dan perkuatan dari AC-

    BC atau HRS-Base atau lapisan lainnya yang ditunjukkan dalam Gambar dan

    dilanjutkan dengan pelapisan permukaan memakai AC-WC atau HRS-WC atau

    lapisan jenis lainnya yang ditunjukkan dalam Gambar.

    ii) Pekerjaan penghamparan Lapis Pondasi Agregat untuk rekonstruksi ruas jalan

    yang rusak berat terdiri dari Lapisan Pondasi Bawah, Lapis Pondasi Atas dan

    diikuti dengan salah satu jenis pelapisan permukaan yang disebutkan diatas.

    b) Pelapisan Non Struktural

    i) Overlay dengan satu lapis lapisan beraspal, seperti Latasir, HRS-WC, AC-WC,

    Lasbutag, Latasbusir atau Campuran Dingin untuk meratakan permukaan dan

    menutup perkerasan lama yang stabil. ii) Overlay dengan dua lapis lapisan beraspal, terdiri dari lapis perata AC-BC atau

    AC-Base atau HRS-Base, dan dilanjutkan dengan pelapisan permukaan memakai

    AC-WC atau HRS-WC atau lapisan jenis lainnya yang ditunjukkan dalam Gambar,

    untuk meratakan dan menutup perkerasan lama yang stabil.

    c) Pelaburan Non Struktural

    i) Pelaburan memakai BURTU atau BURDA pada perkerasan jalan lama dengan lalu

    lintas rendah, dimana permukaan perkerasan tersebut cukup rata dan

    mempunyai punggung jalan (camber) yang memenuhi.

    d) Pengerikilan Kembali Jalan Tanpa Berpenutup Aspal

    i) Pengerikilan kembali untuk mengganti kerikil yang hilang oleh lalu lintas dan

    meningkatkan kekuatan struktur perkerasan kerikil yang ada pada ruas jalan

    yang lemah.

    e) Penambahan / Rekonstruksi Bahu Jalan Sepanjang Jalan Berpenutup Aspal

    i) Bahu jalan berpenutup aspal yang terdiri dari Lapis Pondasi Agregat Kelas A

    yang dilapisi dengan BURTU.

    ii) Bahu jalan tanpa penutup aspal terdiri dari Lapis Pondasi Agregat Kelas B.

    f) Penambahan atau Rekonstruksi Pekerjaan Penunjang

    i) Selokan tanah.

    ii) Selokan dan drainase yang dilapisi.

    iii) Gorong-gorong pipa dari beton.

    iv) Gorong-gorong persegi dari beton.

    v) Pekerjaan tanah untuk perbaikan kelongsoran.

    vi) Peninggian elevasi permukaan jalan (grade raising), hanya bila benar-benar

    diperlukan dan dana dalam Kontrak masih mencukupi.

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR 1 - 3

    vii) Pekerjaan struktur lainnya, seperti jembatan kecil dan sebagainya.

    viii) Pekerjaan perlindungan talud, seperti pasangan batu kosong dengan atau tanpa

    adukan dan bronjong.

    ix) Re-alinyemen horisontal minor, hanya bila benar-benar diperlukan untuk alasan

    keamanan dan dana dalam Kontrak masih mencukupi.

    g) Pekerjaan Pembangunan Jembatan Baru atau Penggantian Jembatan Lama

    i) Pekerjaan pondasi, seperti sumuran, tiang pancang, dan sebagainya.

    ii) Pekerjaan bangunan bawah, seperti abutment dan pier jembatan.

    iii) Pekerjaan bangunan atas, seperti gelagar beton bertulang atau beton pratekan

    atau baja.

    3) Pekerjaan Pengembalian Kondisi dan Minor

    a) Pengembalian Kondisi Perkerasan i) Penambalan perkerasan, meliputi penggalian lokasi tertentu jalan yang

    berlubang-lubang atau rusak berat dan pengisian kembali, pemadatan dan

    pekerjaan penyelesaian dengan bahan pengembalian kondisi yang sesuai

    dengan bahan perkerasan lama.

    ii) Penutupan lubang-lubang yang besar pada perkerasan berpenutup aspal.

    iii) Perbaikan tepi perkerasan pada perkerasan berpenutup aspal.

    iv) Pelaburan setempat pada perkerasan berpenutup aspal yang retak-retak,

    dimana luas bagian yang retak lebih besar dari 10 % dan kurang dari 30 %

    terhadap luas total perkerasan.

    v) Pekerjaan perataan setempat baik pada jalan dengan atau tanpa berpenutup

    aspal untuk mengisi bagian yang ambles (depression) setempat dan untuk

    mengurangi kekasaran perkerasan sampai batas-batas yang diterima.

    vi) Perataan berat setempat pada jalan tanpa penutup aspal untuk menghilangkan

    ketidakrataan permukaan dan mempertahankan bentuk permukaan semula,

    dilanjutkan dengan pemadatan kembali dengan mesin gilas.

    b) Pengembalian Kondisi Bahu Jalan

    i) Sama dengan pengembalian kondisi perkerasan tetapi terbatas pada bahu jalan

    yang berlubang-lubang atau rusak berat.

    ii) Pengupasan bahu jalan yang lebih tinggi dari permukaan perkerasan yang telah

    selesai dikerjakan sehingga mencapai ketinggian yang benar.

    c) Pengembalian Kondisi Selokan, Saluran Air, Timbunan, Galian dan Penghijauan

    i) Penggalian dan pembentukan kembali saluran drainase tanpa pelapisan

    (unlined) yang runtuh atau alinyemen yang jelek pada lokasi tertentu agar

    kemampuan operasional sistem drainase dapat dikembalikan seperti semula.

    Seluruh pekerjaan rekonstruksi saluran yang tidak dilapisi akan diklasifikasikan

    sebagai pekerjaan utama menurut uraian pekerjaan (2)(f) diatas.

    ii) Perbaikan setempat pada beton non-struktural yang retak atau terkelupas,

    pasangan batu dengan mortar (mortared stonework) atau pasangan batu (stone

    masonry) untuk saluran yang dilapisi (lined) dan gorong-gorong. Perbaikan

    struktural pada saluran yang dilapisi (lined) dan gorong-gorong termasuk

    rekonstruksi seluruh atau sebagian dari ruas yang rusak akan diklasifikasikan

    sebagai pekerjaan utama menurut uraian pekerjaan (2)(f) diatas.

    iii) Pekerjaan galian minor atau penimbunan yang diperlukan untuk membentuk

    ulang dan meratakan kembali timbunan atau galian yang ada, dimana timbunan

    atau galian tersebut yang mengalami kelongsoran atau erosi.

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR 1 - 4

    iv) Stabilisasi dengan tanaman pada timbunan atau galian yang terekspos.

    v) Penanaman semak atau pohon baru sebagai pengganti tanaman lama yang

    ditebang untuk pelebaran jalan atau untuk tujuan lainnya.

    d) Perlengkapan Jalan dan Pengatur Lalu Lintas

    i) Pengecatan Marka Jalan.

    ii) Penyediaan dan pemasangan Rambu Jalan, Patok Pengarah dan Patok Kilometer.

    iii) Penyediaan dan pemasangan Rel Pengaman.

    iv) Penyediaan dan pemasangan Paku Jalan dan Mata Kucing.

    v) Penyediaan dan pemasangan Kerb dan Trotoar.

    vi) Penyediaan dan pemasangan Lampu Pengatur Lalu Lintas dan Lampu

    Penerangan Jalan.

    e) Pengembalian Kondisi Jembatan Perbaikan terbatas atau penggantian bagian-bagian dari struktur-atas jembatan yang

    menunjukkan tanda-tanda kerusakan struktural atau non-struktural. Perbaikan dapat

    dilakukan terhadap struktur jembatan beton, baja atau kayu dan dapat meliputi :

    i) Penyuntikan (grouting) pada beton yang retak.

    ii) Perbaikan pada beton yang terkelupas.

    iii) Pembuangan dan penggantian beton struktur yang rusak.

    iv) Penggantian baja yang tertanam seperti sambungan ekspansi.

    v) Perbaikan atau penggantian sandaran (hand railing) yang rusak.

    vi) Pembuangan dan penggantian baja struktur yang berkarat berat.

    vii) Pembuangan dan penggantian kayu yang lapuk.

    viii) Penggantian konektor yang berkarat.

    ix) Pembersihan dan pengecatan kayu atau baja struktur

    4) Pekerjaan Pemeliharaan Rutin

    a) Perkerasan Lama

    i) Penambalan lubang kecil dan pelaburan setempat pada permukaan perkerasan

    berpenutup aspal lama yang masih utuh (sound) dimana luas lokasi yang retak

    kurang dari 10 % terhadap luas total perkerasan.

    ii) Perataan ringan secara rutin dengan motor grader pada jalan tanpa penutup

    aspal untuk mengendalikan terjadinya lubang atau keriting (corrugations).

    b) Bahu Jalan Lama

    i) Penambalan lubang pada bahu jalan lama tanpa penutup aspal.

    ii) Penambalan lubang dan pelaburan retak pada bahu jalan lama berpenutup aspal.

    c) Selokan, Saluran Air, Galian dan Timbunan

    i) Pembersihan dan pembuangan lumpur secara rutin pada selokan dan saluran

    yang ada.

    ii) Pembuangan semua sampah dari sistem drainase yang ada setelah hujan lebat.

    iii) Pemotongan rumput secara rutin dan pengendalian pertumbuhan tanaman pada

    galian, timbunan, lereng dan berm.

    d) Perlengkapan Jalan

    i) Pengecatan ulang semua rambu jalan, patok tanda dan lainnya yang tidak

    terbaca.

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR 1 - 5

    ii) Pembersihan rutin terhadap semua perlengkapan jalan dan pengatur lalu lintas.

    iii) Perbaikan minor terhadap masing-masing jenis perlengkapan jalan.

    e) Jembatan

    i) Pemeriksaan dan pembersihan rutin pada semua komponen struktur

    jembatan dimana korosi pada baja atau pelapukan pada kayu dapat terjadi

    jika tidak dibersihkan.

    ii) Pemeriksaan dan pembersihan rutin kotoran dari semua saluran air

    dimana penggerusan terhadap timbunan atau pondasi jembatan dapat

    terjadi jika tidak dibersihkan.

    iii) Pemeriksaan dan pembersihan rutin semua kotoran dan sampah dari

    lubang-lubang drainase lantai jembatan dan pipa-pipa saluran.

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR 1 - 6

    1.1.3 KETENTUAN REKAYASA (ENGINEERING)

    1) Umum

    Sebelum pekerjaan survei dimulai Kontraktor harus mempelajari Gambar asli untuk

    dikonsultasikan dengan Direksi Pekerjaan, dan harus memastikan dan memperbaiki

    setiap kesalahan atau perbedaan yang terjadi, terutama yang berhubungan dengan

    lebar jalan lama, lokasi setiap pelebaran perkerasan dan struktur drainase.

    Kontraktor dan Direksi Pekerjaan harus mencapai kesepakatan dalam menentukan

    ketepatan setiap perubahan yang dibuat dalam Gambar ini.

    Kuantitas dalam Daftar Kuantitas dan Harga dapat diubah oleh Direksi Pekerjaan

    setelah revisi minor terhadap seluruh rancangan telah selesai, dimana revisi minor

    ini harus berdasarkan data survei lapangan yang dikumpulkan oleh Kontraktor

    sebagai bagian dari cakupan perkerjaan dalam Kontrak.

    2) Survei Lapangan oleh Kontraktor

    Selama periode mobilisasi pada saat dimulainya Kontrak, Kontraktor harus

    melaksanakan survei lapangan yang lengkap terhadap kondisi fisik dan struktur

    pada perkerasan jalan lama, bahu jalan lama dan semua ciri-ciri tambahan lainnya

    seperti sistem drainase, jembatan dan struktur minor lainnya, marka jalan, rambu lalu lintas, dan lain sebagainya. Ketentuan survei lapangan yang lengkap dan detil

    terdapat dalam Seksi 1.9, Rekayasa Lapangan.

    Setelah pekerjaan survei lapangan ini selesai, Kontraktor harus menyiapkan dan menyerahkan laporan lengkap dan detil dari hasil survei ini kepada Direksi

    Pekerjaan, tidak lebih dari tanggal yang ditentukan dalam Pasal 1.1.4 dari Spesifikasi

    ini. Tanggal penyerahan ini akan merupakan tonggak yang sangat penting bagi

    dimulainya pekerjaan dalam Kontrak dengan lebih dini dan berhasil.

    3) Revisi oleh Direksi Pekerjaan

    Detil pelaksanaan yang lengkap pada setiap mata pekerjaan dalam cakupan Kontrak

    ini akan diterbitkan secara bertahap untuk Kontraktor dan bilamana detil

    pelaksanaan ini telah disiapkan, dapat mencakup, tetapi tidak boleh terbatas pada,

    sebagian atau seluruh hal-hal berikut :

    a) Revisi minor terhadap rancangan perkerasan dan/atau jembatan.

    b) Detil peningkatan bahu jalan.

    c) Detil setiap perbaikan alinyemen yang diperlukan, jika ada.

    d) Detil setiap pelebaran jalur lalu lintas (carriageway), jika ada.

    e) Detil perbaikan selokan atau drainase.

    f) Detil struktur drainase

    g) Detil pekerjaan pengendalian lereng, pasangan batu kosong, pekerjaan

    stabilisasi timbunan atau galian.

    h) Detil marka jalan.

    i) Detil rambu jalan, patok pengaman dan rel pengaman dan lain sebagainya, baik

    pemasangan baru maupun penggantian.

    j) Detil pekerjaan pengembalian kondisi jembatan.

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR 1 - 7

    1.1.4 URUTAN PEKERJAAN

    1) Cakupan pekerjaan dalam Kontrak ini mensyaratkan bahwa kegiatan tertentu harus

    diselesaikan secara berurutan menurut tongak-tonggak yang telah ditetapkan

    sebelumnya. Kecuali jika ditentukan lain oleh Direksi Pekerjaan, tanggal yang

    menjadi tonggak utama bagi kegiatan yang kritis adalah sebagai berikut :

    a) Survei lapangan termasuk peralatan

    pengujian yang diperlukan dan

    penyerahan laporan oleh Kontraktor.

    : 30 hari setelah pengambilalihan

    lapangan oleh Kontraktor

    b) Revisi Minor oleh Direksi Pekerjaan

    telah selesai.

    : 60 hari setelah pengambilalihan

    lapangan oleh Kontraktor, walau

    keluarnya detil pelaksanaan

    dapat bertahap setelah tanggal

    ini.

    c) Pekerjaan pengembalian kondisi

    perkerasan dan bahu jalan selesai.

    : 60 hari setelah pengambilalihan

    lapangan oleh Kontraktor.

    d) Pekerjaan minor pada selokan,

    saluran air, galian dan timbunan, pemasangan perlengkapan jalan

    dan pekerjaan pengembalian

    kondisi jembatan.

    : 90 hari setelah pengambilalihan

    lapangan oleh Kontraktor.

    e) Pekerjaan drainase selesai. : Sebelum dimulainya setiap

    overlay.

    2) Diagram yang menjelaskan lingkup dan urutan kegiatan dalam pekerjaan dari

    berbagai pekerjaan utama diberikan dalam Lampiran 1.1.A pada akhir Seksi ini.

    1.1.5 PEMBAYARAN PEKERJAAN

    1) Kontraktor harus melaksanakan Pekerjaan sesuai dengan detil yang diberikan

    dalam Gambar, dan sebagaimana yang diperintahkan oleh Direksi Pekerjaan, dimana

    sebagian besar pekerjaan tersebut akan dibayar menurut sistem Harga Satuan.

    Pembayaran kepada Kontraktor harus dilakukan berdasarkan kuantitas aktual yang

    diukur pada masing-masing Mata Pembayaran dalam Kontrak yang telah

    dilaksanakan sesuai dengan Seksi yang berkaitan dari Spesifikasi ini, baik cara

    pengukuran maupun pembayarannya. Pembayaran juga akan dilakukan

    berdasarkan pengukuran dan pembayaran Lump Sum untuk mata pembayaran

    Mobilisasi, Relokasi Utilitas dan Pelayanan Yang Ada, Cofferdam, Penyokong,

    Pengaku, dan pekerjan yang terkait, dan Pekerjaan Pemeliharaan Rutin, serta

    pengukuran dan pembayaran untuk pekerjaan yang diperintahkan atas dasar

    Pekerjaan Harian.

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR 1 - 8

    2) Pembayaran yang diberikan kepada Kontraktor harus mencakup kompensasi penuh

    untuk seluruh biaya yang dikeluarkan seluruh pekerja, bahan, peralatan konstruksi,

    pengorganisasian pekerjaan, biaya tak terduga, keuntungan, retribusi, pajak,

    pengamanan pekerjaan yang telah selesai dikerjakan, pembayaran kepada pihak

    ketiga untuk tanah atau untuk penggunaan atas tanah, atau untuk kerusakan

    bangunan (property), maupun untuk semua biaya pekerjaan tambah yang tidak

    dibayar secara terpisah, seperti pembuatan drainase sementara untuk melindungi

    pekerjaan selama pelaksanaan, pengangkutan, perkakas, peledakan dan bahan

    untuk peledakan, penurapan, penyangga, pembuatan tempat kerja (staging),

    pembuatan tanda sumbu (centering) dan penopang dan lain-lain biaya yang

    diperlukan atau lazim dipakai untuk pelaksanaan dan penyelesaian yang

    sebagaimana mestinya dari Pekerjaan tersebut.

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR 1 - 9

    SEKSI 1.2

    MOBILISASI

    1.2.1 UMUM

    1) Uraian

    Cakupan kegiatan mobilisasi yang diperlukan dalam Kontrak ini akan tergantung

    pada jenis dan volume pekerjaan yang harus dilaksanakan, sebagaimana disyaratkan di bagian-bagian lain dari Dokumen Kontrak, dan secara umum harus memenuhi

    berikut :

    a) Ketentuan Mobilisasi untuk semua Kontrak

    i) Penyewaan atau pembelian sebidang lahan yang diperlukan untuk base

    camp Kontraktor dan kegiatan pelaksanaan.

    ii) Mobilisasi Kepala Pelaksana (General Superintentent) yang memenuhi

    jaminan kualifikasi (sertifikasi) menurut cakupan pekerjaannya

    (pembangunan, atau peningkatan jalan / penggantian jembatan, atau

    pemeliharaan berkala).

    iii) Mobilisasi semua staf pelaksana dan pekerja yang diperlukan dalam

    pelaksanaan dan penyelesaian pekerjaan dalam Kontrak.

    iv) Mobilisasi dan pemasangan peralatan sesuai dengan daftar peralatan yang

    tercantum dalam Penawaran, dari suatu lokasi asal ke tempat pekerjaan

    dimana peralatan tersebut akan digunakan menurut Kontrak ini.

    v) Penyediaan dan pemeliharaan base camp Kontraktor, jika perlu termasuk

    kantor lapangan, tempat tinggal, bengkel, gudang, dan sebagainya.

    vi) Perkuatan jembatan lama untuk pengangkutan alat-alat berat.

    b) Ketentuan mobilisasi Kantor Lapangan dan Fasilitasnya untuk Direksi Pekerjaan

    Kebutuhan ini akan disediakan dalam Kontrak lain.

    c) Ketentuan mobilisasi Fasilitas Pengendalian Mutu

    Penyediaan dan pemeliharaan laboratorium lapangan harus memenuhi ketentuan yang disyaratkan dalam Seksi 1.4 dari Spesifikasi ini bersama dengan

    peralatan laboratorium lapangan yang tercantum dalam Lampiran 1.4.A. Gedung

    laboratorium dan peralatannya, yang dipasok menurut Kontrak ini, akan tetap

    menjadi milik Kontraktor pada waktu proyek selesai.

    d) Kegiatan Demobilisasi untuk semua Kontrak

    Pembongkaran tempat kerja oleh Kontraktor pada saat akhir Kontrak, termasuk

    pemindahan semua instalasi, peralatan dan perlengkapan dari tanah milik

    Pemerintah dan pengembalian kondisi tempat kerja menjadi kondisi seperti

    semula sebelum Pekerjaan dimulai.

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR 1 - 10

    2) Pekerjaan Seksi Lain Yang Berkaitan Dengan Seksi Ini

    a) Syarat-syarat Kontrak (Bab 3 dari Dokumen Kontrak) : Pasal-pasal yang

    berkaitan

    b) Kantor Lapangan dan Fasilitasnya : Seksi 1.3

    c) Pelayanan Pengujian Laboratorium : Seksi 1.4

    d) Rekayasa Lapangan : Seksi 1.9

    e) Jadwal Pelaksanaan : Seksi 1.12

    f) Pekerjaan Pembersihan : Seksi 1.16

    g) Selokan dan Saluran Air : Seksi 2.1

    h) Gorong-gorong : Seksi 2.3

    i) Pemeliharaan Jalan Samping dan Jembatan : Seksi 10.2

    3) Periode Mobilisasi

    Mobilisasi dari seluruh mata pekerjaan yang terdaftar dalam Pasal 1.2.1.(1) harus

    diselesaikan dalam jangka waktu 60 hari terhitung mulai tanggal mulai kerja, kecuali

    penyediaan Fasilitas dan Pelayanan Pengendalian Mutu harus diselesaikan dalam

    waktu 45 hari.

    Setiap kegagalan Kontraktor dalam memobilisasi Fasilitas dan Pelayanan

    Pengendalian Mutu sebagimana disebutkan diatas, akan membuat Direksi Pekerjaan

    melaksanakan pekerjaan semacam ini yang dianggap perlu dan akan membebankan

    seluruh biaya tersebut ditambah sepuluh persen pada Kontraktor, dimana biaya

    tersebut akan dipotongkan dari setiap uang yang dibayarkan atau akan dibayarkan

    kepada Kontraktor menurut Kontrak ini. Malahan, pemotongan sebagaimana yang

    disebutkan dalam Pasal 1.2.2.(2) tetap berlaku.

    4) Pengajuan Kesiapan Kerja

    Kontraktor harus menyerahkan kepada Direksi Pekerjaan suatu program mobilisasi

    menurut detil dan waktu yang disyaratkan dalam Pasal 1.2.2 dari Spesifikasi ini.

    Bilamana perkuatan jembatan lama atau pembuatan jembatan darurat atau

    pembuatan timbunan darurat pada jalan yang berdekatan dengan proyek,

    diperlukan untuk memperlancar pengangkutan peralatan, instalasi atau bahan milik Kontraktor, detil pekerjaan darurat ini juga harus diserahkan bersama dengan

    program mobilisasi sesuai dengan ketentuan Seksi 10.2 dari Spesifikasi ini.

    1.2.2 PROGRAM MOBILISASI

    1) Dalam waktu 7 hari setelah Penandatangan Kontrak, Kontraktor harus

    melaksanakan Rapat Pra Pelaksanaan (Pre Construction Meeting) yang dihadiri

    Pemilik, Direksi Pekerjaan, Wakil Direksi Pekerjaan (bila ada) dan Kontraktor untuk

    membahas semua hal baik yang teknis maupun yang non teknis dalam proyek ini.

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR 1 - 11

    2) Dalam waktu 14 hari setelah Rapat Pra Pelaksanaan, Kontraktor harus

    menyerahkan Program Mobilisasi (termasuk program perkuatan jembatan, bila ada)

    dan Jadwal Kemajuan Pelaksanaan kepada Direksi Pekerjaan untuk dimintakan

    persetujuannya.

    3) Program mobilisasi harus menetapkan waktu untuk semua kegiatan mobilisasi yang

    disyaratkan dalam Pasal 1.2.1.(1) dan harus mencakup informasi tambahan berikut :

    a) Lokasi base camp Kontraktor dengan denah lokasi umum dan denah detil di

    lapangan yang menunjukkan lokasi kantor Kontraktor, bengkel, gudang, mesin

    pemecah batu dan instalasi pencampur aspal, serta laboratorium bilamana

    fasilitas tersebut termasuk dalam cakupan Kontrak.

    b) Jadwal pengiriman peralatan yang menunjukkan lokasi asal dari semua

    peralatan yang tercantum dalam Daftar Peralatan yang diusulkan dalam

    Penawaran, bersama dengan usulan cara pengangkutan dan jadwal kedatangan

    peralatan di lapangan.

    c) Setiap perubahan pada peralatan maupun personil yang diusulkan dalam

    Penawaran harus memperoleh persetujuan dari Direski Pekerjaan.

    d) Suatu daftar detil yang menunjukkan struktur yang memerlukan perkuatan agar

    aman dilewati alat-alat berat, usulan metodologi pelaksanaan dan jadwal tanggal

    mulai dan tanggal selesai untuk perkuatan setiap struktur.

    e) Suatu jadwal kemajuan yang lengkap dalam format bagan balok (bar chart) yang

    menunjukkan tiap kegiatan mobilisasi utama dan suatu kurva kemajuan untuk

    menyatakan persentase kemajuan mobilisasi.

    1.2.3 PENGUKURAN DAN PEMBAYARAN

    1) Pengukuran

    Pengukuran kemajuan mobilisasi akan ditentukan oleh Direksi Pekerjaan atas dasar

    jadwal kemajuan mobilisasi yang lengkap dan telah disetujui seperti yang diuraikan

    dalam Pasal 1.2.2.(2) diatas.

    2) Dasar Pembayaran

    Mobilisasi harus dibayar atas dasar lump sum menurut jadwal pembayaran yang

    diberikan di bawah, dimana pembayaran tersebut merupakan kompensasi penuh

    untuk penyediaan dan pemasangan semua peralatan, dan untuk semua pekerja,

    bahan, perkakas, dan biaya lainnya yang perlu untuk menyelesaikan pekerjaan yang

    diuraikan dalam Pasal 1.2.1.(1) dari Spesifikasi ini. Walaupun demikian Direksi

    Pekerjaan dapat, setiap saat selama pelaksanaan pekerjaan, memerintahkan

    Kontraktor untuk menambah peralatan yang dianggap perlu tanpa menyebabkan

    perubahan harga lump sum untuk Mobilisasi.

    Pembayaran biaya lump sum ini akan dilakukan dalam tiga angsuran sebagai

    berikut :

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR 1 - 12

    a) 50 % (lima puluh persen) bila mobilisasi 50 % selesai, dan pelayanan atau

    fasilitas pengujian laboratorium telah lengkap dimobilisasi.

    b) 20 % (dua puluh persen) bila semua peralatan utama berada di lapangan dan

    diterima oleh Direksi Pekerjaan.

    c) 30 % (tiga puluh persen) bila demobilisasi selesai dilaksanakan.

    Bilamana Kontraktor tidak menyelesaikan mobilisasi sesuai dengan salah satu dari

    kedua batas waktu yang disyaratkan dalam Pasal 1.2.1.(3) maka jumlah yang

    disahkan Direksi Pekerjaan untuk pembayaran adalah persentase angsuran penuh

    dari harga lump sum Mobilisasi dikurangi sejumlah dari 1 % (satu persen) nilai

    angsuran untuk setiap keterlambatan satu hari dalam penyelesaian sampai

    maksimum 50 (lima puluh) hari.

    Nomor Mata

    Pembayaran Uraian

    Satuan

    Pengukuran

    1.2 Mobilisasi Lump Sum

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR 1 - 13

    SEKSI 1.3

    KANTOR LAPANGAN DAN FASILITASNYA

    1.3.1 UMUM

    1) Uraian Pekerjaan

    Menurut Seksi ini, Kontraktor harus membangun, menyediakan, memasang,

    memelihara, membersihkan, menjaga, dan pada saat selesainya Kontrak harus memindahkan atau membuang semua bangunan kantor darurat, gudang-gudang

    penyimpanan, barak-barak pekerja dan bengkel-bengkel yang dibutuhkan untuk

    pengelolaan dan pengawasan proyek.

    2) Pekerjaan Seksi Lain Yang Berkaitan Dengan Seksi Ini

    a) Mobilisasi : Seksi 1.2

    b) Bahan dan Penyimpanan : Seksi 1.11

    c) Pekerjaan Pembersihan : Seksi 1.16

    3) Ketentuan Umum

    a) Kontraktor harus mentaati semua peraturan-peraturan Nasional maupun

    Daerah.

    b) Kantor dan fasilitasnya harus ditempatkan sesuai dengan Lokasi Umum dan

    Denah Lapangan yang telah disetujui dan merupakan bagian dari Program

    Mobilisasi seperti dirinci dalam Pasal 1.2.2.(2), dimana penempatannya harus

    diusahakan sedekat mungkin dengan daerah kerja (site) dan telah mendapat

    persetujuan dari Direksi Pekerjaan.

    c) Bangunan untuk kantor dan fasilitasnya harus ditempatkan sedemikian rupa

    sehingga terbebas dari polusi yang dihasilkan oleh kegiatan pelaksanaan.

    d) Bangunan yang dibuat harus mempunyai kekuatan struktural yang baik, tahan

    cuaca, dan elevasi lantai yang lebih tinggi dari tanah di sekitarnya.

    e) Bangunan untuk penyimpanan bahan harus diberi bahan pelindung yang cocok

    sehingga bahan-bahan yang disimpan tidak akan mengalami kerusakan.

    f) Sesuai pilihan Kontraktor, bangunan dapat dibuat di tempat atau dirakit dari

    komponen-komponen pra-fabrikasi. g) Kantor lapangan dan gudang sementara harus didirikan diatas pondasi yang

    mantap dan dilengkapi dengan penghubung dengan untuk pelayanan utilitas.

    h) Bahan, peralatan dan perlengkapan yang digunakan untuk bangunan dapat baru

    atau bekas pakai, tetapi dengan syarat harus dapat berfungsi, cocok dengan

    maksud pemakaiannya dan tidak bertentangan dengan perundang-undangan

    dan peraturan yang berlaku.

    i) Lahan untuk kantor lapangan dan semacamnya harus ditimbun dan diratakan

    sehingga layak untuk ditempati bangunan, bebas dari genangan air, diberi pagar

    keliling, dan dilengkapi minimum dengan jalan masuk dari kerikil serta tempat

    parkir.

    j) Kontraktor harus menyediakan alat pemadam kebakaran dan kebutuhan P3K

    yang memadai di seluruh barak, kantor, gudang dan bengkel.

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR 1 - 14

    1.3.2 KANTOR KONTRAKTOR DAN FASILITASNYA

    1) Umum

    Kontraktor harus menyediakan akomodasi dan fasilitas kantor yang cocok dan

    memenuhi kebutuhan proyek sesuai Seksi dari Spesifikasi ini.

    2) Ukuran

    Ukuran kantor dan fasilitasnya sesuai untuk kebutuhan umum Kontraktor dan harus

    menyediakan sebuah ruangan yang digunakan untuk rapat kemajuan pekerjaan.

    3) Alat Komunikasi

    a) Kontraktor harus menyediakan suatu saluran langsung.

    b) Bilamana sambungan saluran telepon tidak mungkin disediakan, atau tidak

    dapat disediakan dalam periode mobilisasi, maka Kontraktor harus

    menyediakan pengganti telpon satelit (menggunakan sistem satelit Inmarsat

    atau Iridium atau sejenis) yang dapat berkomunikasi 2 arah (2-way) dengan

    jelas dan dapat diandalkan antara kantor Pemilik di Ibukota Propinsi, kantor

    Tim Supervisi Lapangan dan titik terjauh di lapangan. Sistem telpon harus dipasang di kantor utama dan semua kantor cabang serta digunakan sesuai

    dengan petunjuk dari Direksi Pekerjaan.

    c) Bilamana ijin atau perijinan dari instansi Pemerintah yang terkait diperlukan untuk pemasangan dan pengoperasian sistem telopon satelit semacam ini,

    Direski Pekerjaan akan melakukan semua pengaturan, tetapi semua biaya yang

    timbul harus dibayar oleh Kontraktor.

    4) Perlengkapan dalam Ruang Rapat dan Ruang Penyimpanan Dokumentasi Proyek

    a) Meja rapat dengan kursi untuk paling sedikit 8 orang.

    b) Rak atau laci untuk penyimpanan gambar dan arsip untuk Dokumentasi Proyek

    secara vertikal atau horisontal, yang ditempatkan di dalam atau dekat dengan

    ruang rapat.

    5) Kantor Pendukung

    Bilamana Kontraktor menganggap perlu untuk mendirikan satu kantor pendukung

    atau lebih, yang akan digunakan untuk keperluan sendiri pada jarak 50 km atau

    lebih dari kantor utama di lapangan, maka Kontraktor harus menyediakan,

    memelihara dan melengkapi satu ruangan pada setiap kantor pendukung dengan

    ukuran sekitar 12 meter persegi yang akan digunakan oleh Staf Direksi Pekerjaan

    untuk setiap kantor pendukung.

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR 1 - 15

    1.3.3 BENGKEL DAN GUDANG KONTRAKTOR

    1) Kontraktor harus menyediakan sebuah bengkel di lapangan yang diberi

    perlengkapan yang memadai serta dilengkapi dengan daya listrik, sehingga dapat

    digunakan untuk memperbaiki peralatan yang digunakan dalam pelaksanaan

    Pekerjaan. Sebuah gudang untuk penyimpanan suku cadang juga harus disediakan.

    2) Bengkel tersebut harus dikelola oleh seorang kepala bengkel yang mampu

    melakukan perbaikan mekanis dan memiliki sejumlah tenaga pembantu yang

    terlatih.

    1.3.4 KANTOR DAN AKOMODASI UNTUK DIREKSI PEKERJAAN

    Ketentuan ini disediakan dalam Kontrak lain yang terpisah.

    1.3.5 PENGUKURAN DAN PEMBAYARAN

    Bangunan yang diuraikan dalam Seksi ini akan dibayar menurut pembayaran Lump Sum

    untuk Mobilisasi sesuai dengan Seksi 1.2 dari Spesifikasi ini, dimana pembayaran harus

    dianggap kompensasi penuh untuk pembuatan, penyediaan, pelayanan, pemeliharaan,

    pembersihan dan pembongkaran semua bangunan tersebut setelah Pekerjaan selesai.

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR 1 - 16

    SEKSI 1.4

    FASILITAS DAN PELAYANAN PENGUJIAN

    1.4.1 UMUM

    1) Uraian

    a) Pengujian yang dilaksanakan oleh Kontraktor

    Kontraktor sebagaimana disyaratkan dalam kontrak harus menyediakan tempat

    kerja, bahan, fasilitas, pekerja, pelayanan dan pekerjaan lainnya yang diperlukan

    untuk pemalkasanakn pengujian yang diperlukan. Umumnya Kontraktor di

    bawah perintah dan pengawasan Direksi Pekerjaan akan melakukan semua

    pengujian sehubungan dengan pengendalian mutu bahan baku, campuran dan

    bahan yang diproses untuk menjamin bahwa bahan-bahan tersebut memenuhi

    mutu bahan, kepadatan dari pemadatan. Daftar Peralatan Laboratorium yang

    digunakan dalam pengujian terhadap pekerjaan ini diberikan dalam Lampiran

    1.4.A.

    b) Pengujian yang dilaksanakan oleh Direksi Pekerjaan

    Kontraktor harus membangun dan melengkapi, memelihara, membersihkan,

    menjaga dan pada akhir Kontrak membongkar atau menyingkirkan bangunan

    yang disebutkan dalam lembar 1.05.2 dari Gambar, yang digunakan sebagai

    laboratorium lapangan untuk digunakan semata-mata hanya oleh Direksi

    Pekerjaan, dan memasok dan memasang peralatan laboratorium di laboratorium

    Direksi Pekerjaan untuk pelaksanaan pengujian yang terdaftar dalam Spesifikasi

    Standar. Daftar Peralatanyang digunakan untuk pengujian terhadap pekerjaan

    ini diberikan dalam Lampiran 1.4.A.

    Direksi Pekerjaan akan bertanggungjawab atas semua pengujian yang dilakukan

    untuk pekerjaan yang sudah selesai. Hasil pengujian-pengujian ini akan menjadi

    dasar persetujuan atau penolakan dari pekerjaan terkait.

    2) Pekerjaan Seksi Lain Yang Berkaitan Dengan Seksi Ini

    a) Syarat-syarat Kontrak (Bab 3 dari Dokumen Kontrak) : Pasal-pasal yang

    berkaitan

    b) Mobilisasi : Seksi 1.2

    c) Rekayasa Lapangan : Seksi 1.9

    d) Ketentuan-ketentuan tersendiri lainnya untuk

    pengujian seperti didefinisikan dalam Seksi

    lain yang berhubungan dalam Spesifikasi ini

    3) Pekerjaan Yang Tidak Termasuk Dalam Seksi Ini

    Ketentuan dalam Pasal ini tidak digunakan.

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR 1 - 17

    4) Pengajuan Kesiapan Kerja

    Kontraktor diwajibkan untuk menyerahkan :

    a) Usulan mobilisasi Laboratorium Pengujian : detil dari mobilisasi laboratorium

    dan peralatannya sebagai bagian dari program mobilisasi sesuai dengan

    ketentuan pada Seksi 1.2 dari Spesifikasi ini, harus disediakan oleh Kontraktor.

    b) Usulan personil penguji : daftar beserta Daftar Riwayat Hidup semua teknisi

    laboratorium yang diusulkan Kontraktor untuk pelaksanaan pengujian menurut

    Kontrak ini.

    c) Jadwal pengujian : jadwal induk (master schedule) semua pekerjaan yang akan

    diuji. Dengan jadwal pelaksanaan (construction schedule) yang ada dapat ditentukan tanggal sementara untuk masing-masing kegiatan pengujian. Jadwal

    kegiatan pengujian ini harus diserahkan kepada Direksi Pekerjaan dalam

    formulir pendahuluan (preliminary form) untuk dievaluasi pada setiap awal

    bulan.

    d) Formulir pengujian : usulan formulir pengujian standar yang akan digunakan

    dalam Kontrak ini untuk semua jenis pengujian yang disyaratkan dalam

    Spesifikasi, harus diserahkan kepada Direksi Pekerjaaan dalam waktu 45 hari

    terhitung sejak Tanggal Mulai Kerja, untuk mendapat persetujuan dari Direksi

    Pekerjaan.

    1.4.2 FASILITAS LABORATORIUM DAN PENGUJIAN

    1) Kontraktor harus menyediakan pelayanan pengujian dan/atau fasilitas laboratorium

    sebagaimana disyaratkan untuk memenuhi seluruh ketentuan pengendalian mutu

    dari Spesifikasi ini.

    2) Bilamana secara khusus dimasukkan dalam lingkup Kontrak ini, maka Kontraktor

    harus menyediakan dan memelihara sebuah laboratorium lengkap dengan

    peralatannya di lapangan, sesuai dengan ketentuan berikut :

    a) Tempat Kerja

    i) Laboratorium haruslah merupakan bangunan terpisah (sebagaimana

    disebutkan dalam Pasal 1.4.1.(1)) yang ditempatkan sesuai dengan Lokasi

    Umum dan Denah Tempat Kerja yang telah disetujui dan merupakan bagian dari program mobilisasi sesuai dengan Pasal 1.2.2.(2). Lokasi

    laboratorium harus ditempatkan sedemikian rupa sehingga mempunyai

    jarak tertentu dari peralatan konstruksi, bebas dari polusi dan gangguan

    berupa getaran selama pengoperasian peralatan.

    ii) Bangunan harus dilengkapi dengan lantai beton beserta fasilitas

    pembuangan air kotor, dan dilengkapi dengan dua buah pendingin udara

    (air conditioning) masing-masing berkapasitas 1,5 PK, serta harus

    memenuhi semua ketentuan lainnya dalam Pasal 1.3.1.(3) dari Spesifikasi

    ini.

  • SPESIFIKASI UMUM JALAN DAN JEMBATAN

    DINAS BINA MARGA DAN PENGAIRAN

    KABUPATEN BOGOR 1 - 18

    iii) Perlengkapan di dalam ruangan bangunan harus terdiri atas meja kerja,

    lemari, ruang penyimpan yang dapat dikunci, tangki perawatan, laci arsip

    (filing cabinet), meja dan kursi dengan mutu standar dan jumlah yang

    mencukupi kebutuhan.

    b) Peralatan dan Perlengkapan

    Peralatan dan perlengkapan laboratorium yang terdaftar dalam Lampiran 1.4.A

    dari Spesifikasi ini harus sudah disediakan dalam waktu 45 hari terhitung sejak

    Tanggal Mulai Kerja, sehingga pengujian sumber bahan dapat dimulai sesegera

    mungkin.

    Alat-alat ukur seperti timbangan, proving ring, dan lainnya harus dikalibrasi

    oleh instansi yang berwenang dengan menunjukkan sertifikat kalibrasi.

    1.4.3 PROSEDUR PELAKSANAAN

    1) Peraturan dan Rujukan

    Standard Nasional Indonesia (SNI), sebagaimana diberikan dalam Lampiran 1.4.B

    dalam Spesifikasi ini harus digunakan untuk pelaksanaan pekerjaan. Dalam segala hal, Kontraktor harus menggunakan SNI yang relevan atau setara untuk

    menggantikan standar-standar lain yang mungkin ditunjukkan dalam Spesifikasi ini..

    Bilamana standar tersebut tid