    NO JENIS UPAH / BAHAN SATUAN 2013

    I. UPAH

    1 Mandor Orang/hari 177,100.0

    2 Tukang galian tanah Orang/hari 113,900.0

    3 Kepala tukang batu Orang/hari 151,800.0

    4 Tukang batu Orang/hari 113,900.0

    5 Pembantu tukang batu Orang/hari 95,900.0

    6 Kepala tukang kayu Orang/hari 151,800.0

    7 Tukang kayu Orang/hari 101,200.0

    8 Pembantu tukang kayu Orang/hari 75,900.0

    9 Kepala tukang besi Orang/hari 151,800.0

    10 Tukang besi Orang/hari 101,200.0

    11 Pembantu tukang besi Orang/hari 82,200.0

    12 Kepala tukang cat Orang/hari 151,800.0

    13 Tukang cat Orang/hari 94,900.0

    14 Pembantu tukang cat Orang/hari 75,900.0

    15 Tukang listrik Orang/hari 126,500.0

    II KOMPONEN BANGUNAN

    1 Atap bubungan zinculome collor (sakura) Lembar 31,200.0

    2 Atap zinculome collor ( Multi Roof ) lembar 89,900.0

    3 Bubungan genteng multi color Btg 29,900.0

    4 Balok kayu lanan M3 2,530,000.0

    5 Cat dasar untuk kayu indian kg 31,900.0

    6 Cat dasar kg 21,000.0

    7 Cat Kayu Mengkilat/Platone kg 53,600.0

    8 Cat Menie Platone kg 34,800.0

    9 Cat Tembok kg 27,200.0

    10 Kalciboar Uk. 6 mm lembar 125,200.0

    11 Lits gipsum 10 cm M' 15,450.0

    12 List kayu profil M' 10,200.0

    13 Engsel Jendela 3" Buah 14,300.0

    14 Engsel Pintu 4" Buah 22,500.0

    15 Grendel lokal Buah 17,800.0

    16 Hak angin Buah 19,300.0

    17 Kaca bening ukuran 5 mm M2 132,800.0

    18 Kayu kelas II 2 x 20 cm (Papan Lanan) M3 2,530,000.0

    19 Kayu ulin 5 x 10 cm M3 8,538,800.0

    20 Kayu ulin balok M3 8,855,000.0

    21 Papan kayu klas I M3 12,548,800.0

    22 Karpet M2 24,700.0

    DAFTAR HARGA BAHAN DAN UPAH

    HARGA

    DI KECAMATAN JEKAN RAYA, PAHANDUT & SABANGAU

  • 7/22/2019 Rab Posyandu

    2/19

    NO JENIS UPAH / BAHAN SATUAN 2013

    HARGA

    23 Kloset jongkok warna putih merek INA Buah 143,900.0

    24 Kran air stainless Buah 83,300.0

    25 Kunci Pintu Tanam Standard (Pintu utama) Buah 146,700.0

    26 Kunci Pintu Kamar Buah 87,300.0

    27 Lampu TL Bambu 20 watt Buah 113,900.0

    28 Lampu TL bulat Buah 41,100.0

    29 MCB 1 X 10 A - MC 45 A Buah 45,500.0

    30 Schakelar ( Standar ) Buah 36,400.0

    31 Dempul kayu mengkilap Kg 28,100.0

    32 Paku kayu kg 16,700.0

    33 Pipa PVC dia.3"/M1 M1 29,725.0

    34 Pipa PVC dia.3"(PERLENGKAPAN) Hrg 9,301.6

    35 Pipa PVC dia.4" batang 139,800.0

    36 Pipa PVC dia.4"/M1 M1 34,950.0

    37 Pipa PVC 4' (perlengkapan) hrg 13,632.3

    38 Pipa PVC dia.3/4" batang 28,600.0

    39 Pipa PVC dia.3/4"/M1 M1 7,150.0

    40 Pipa PVC 3/4 '(perlengkapan) hrg 2,656.5

    41 Plamur tembok kg 64,745.0

    42 Residu/teer Ltr 26,600.0

    43 Semen PC (50 Kg/zak) zak 81,600.0

    44 Semen PC (50 Kg/kg) kg 1,632.0

    45 Semen abu abu kg 4,680.0

    46 Semen warna kg 18,975.0

    47 Tarikan jendela buah 8,475.0

    48 Titik lampu + instalasi kayu titik 295,500.0

    49 Stop kontak+ instalasi kayu titik 85,400.0

    50 Stop kontak Btg 25,000.0

    51 MCB 1 X 10 A - NC 45 A Unit 40,000.0

  • 7/22/2019 Rab Posyandu

    3/19

    NO ANALISA BAHAN & UPAH SATUAN KOEFISIEN

    6 ANALIS BIAYA KONSTRUKSI ( ABK ) 6 - PEKERJAAN KAYU

    SNI.VI.6.1 1 M3 Pasang kosen pintu dan jendela Balok kayu KL I

    Tenaga

    Mandor OH 0.3000 @ Rp. 177,100.00 Rp.

    Kepala tukang kayu OH 2.0000 @ Rp. 151,800.00 Rp.

    Tukang kayu OH 20.0000 @ Rp. 101,200.00 Rp.

    Pembantu tukang kayu OH 6.0000 @ Rp. 75,900.00 Rp.

    Bahan Rp.

    Kayu ulin balok m3 1.1000 @ Rp. 8,855,000.00 Rp.

    Rp.

    Rp.

    SNI.VI.6.7 1 M3 Pasang pintu panel Papan Papan Kayu KL I

    Tenaga

    Mandor OH 0.0500 @ Rp. 177,100.00 Rp.

    Kepala tukang kayu OH 0.2500 @ Rp. 151,800.00 Rp.Tukang kayu OH 2.5000 @ Rp. 101,200.00 Rp.

    Pembantu tukang kayu OH 1.0000 @ Rp. 75,900.00 Rp.

    Bahan Rp.

    Papan kayu klas I M3 0.0400 @ Rp. 12,548,800.00 Rp.

    Rp.

    Rp.

    SNI.VI.6.9 1 M3 Pasang pintu dan jendela kaca Papan kayu klas I

    Tenaga

    Mandor OH 0.0400 @ Rp. 177,100.00 Rp.

    Kepala tukang kayu OH 0.2000 @ Rp. 151,800.00 Rp.

    Tukang kayu OH 2.0000 @ Rp. 101,200.00 Rp.

    Pembantu tukang kayu OH 0.8000 @ Rp. 75,900.00 Rp.

    Bahan Rp.

    Papan kayu klas I M3 0.0350 @ Rp. 12,548,800.00 Rp.

    Rp.

    Rp.

    SNI.VI.6.19 1 M' List langit - langit kayu profil

    Tenaga

    Mandor OH 0.0030 @ Rp. 177,100.00 Rp.

    Kepala tukang kayu OH 0.0050 @ Rp. 151,800.00 Rp.

    Tukang kayu OH 0.0500 @ Rp. 101,200.00 Rp.

    Pembantu tukang kayu OH 0.0500 @ Rp. 75,900.00 Rp.

    Bahan Rp.List kayu profil M3 1.1000 @ Rp. 10,200.00 Rp.

    Paku Kayu Kg 0.0100 @ Rp. 16,700.00 Rp.

    Rp.

    Rp.

    DAFTAR ANALISA SNI

    HARGA SATUAN

    Hal -3

  • 7/22/2019 Rab Posyandu

    4/19

    NO ANALISA BAHAN & UPAH SATUAN KOEFISIEN HARGA SATUAN

    SNI.VI.6.31 1 M2 Pasang kaso + reng genteng metal ( Kayu Lanan )

    Tenaga

    Mandor OH 0.0050 @ Rp. 177,100.00 Rp.

    Kepala tukang kayu OH 0.0100 @ Rp. 151,800.00 Rp.

    Tukang kayu OH 0.1000 @ Rp. 101,200.00 Rp.

    Pembantu tukang kayu OH 0.1000 @ Rp. 75,900.00 Rp.Bahan Rp.

    Balok kayu lanan M3 0.0120 @ Rp. 2,530,000.00 Rp.

    Paku Kayu Kg 0.1500 @ Rp. 16,700.00 Rp.

    Rp.

    Rp.

    SNI.VI.6.39 1 M2 Pasang rangka langit - langit ( 60 x 120 cm ) - Kayu Lanan

    Tenaga

    Mandor OH 0.0750 @ Rp. 177,100.00 Rp.

    Kepala tukang kayu OH 0.0250 @ Rp. 151,800.00 Rp.

    Tukang kayu OH 0.2500 @ Rp. 101,200.00 Rp.

    Pembantu tukang kayu OH 0.1500 @ Rp. 75,900.00 Rp.

    Bahan Rp.

    Balok kayu lanan M3 0.0120 @ Rp. 2,530,000.00 Rp.

    Paku kayu kg 0.1000 @ Rp. 16,700.00 Rp.

    Rp.

    Rp.

    SNI.VI.6.51 1 M' Pasang lisplang Kayu Klas I

    Tenaga

    Mandor OH 0.0750 @ Rp. 177,100.00 Rp.

    Kepala tukang kayu OH 0.0250 @ Rp. 151,800.00 Rp.

    Tukang kayu OH 0.2500 @ Rp. 101,200.00 Rp.

    Pembantu tukang batu OH 0.1500 @ Rp. 95,900.00 Rp.

    Bahan Rp.Papan kayu klas I M3 0.0080 @ Rp. 12,548,800.00 Rp.

    Paku Kayu kg 0.0600 @ Rp. 16,700.00 Rp.

    Rp.

    Rp.

    SNI.VIII.6.32 1 M2 Pasang atap genteng metal

    Tenaga

    Mandor OH 0.0010 @ Rp. 177,100.00 Rp.

    Kepala tukang kayu OH 0.0100 @ Rp. 151,800.00 Rp.

    Tukang kayu OH 0.1000 @ Rp. 101,200.00 Rp.

    Pembantu tukang kayu OH 0.2000 @ Rp. 75,900.00 Rp.

    Bahan Rp.

    Atap multi sirap - merk multi roof m2 1.0000 @ Rp. 107,500.00 Rp.

    Paku kayu kg 0.2000 @ Rp. 16,700.00 Rp.

    Rp.

    Rp.

    Hal -4

  • 7/22/2019 Rab Posyandu

    5/19

    NO ANALISA BAHAN & UPAH SATUAN KOEFISIEN HARGA SATUAN

    SNI.VIII.6.36 1 M' Pasang bubungan genteng metal

    Tenaga

    Mandor OH 0.0130 @ Rp. 177,100.00 Rp.

    Kepala tukang kayu OH 0.0150 @ Rp. 151,800.00 Rp.

    Tukang kayu OH 0.1500 @ Rp. 101,200.00 Rp.

    Pembantu tukang kayu OH 0.2500 @ Rp. 75,900.00 Rp.Bahan Rp.

    Bubungan genteng multi color Lbr 1.1000 @ Rp. 29,900.00 Rp.

    Paku kayu kg 0.0500 @ Rp. 16,700.00 Rp.

    Rp.

    Rp.

    SNI.VI.6.24 1 M2 Langit - langit calsiboard - tebal 6 mm

    Tenaga

    Mandor OH 0.0050 @ Rp. 177,100.00 Rp.

    Kepala tukang kayu OH 0.0050 @ Rp. 151,800.00 Rp.

    Tukang kayu OH 0.0500 @ Rp. 101,200.00 Rp.

    Pembantu tukang kayu OH 0.1000 @ Rp. 75,900.00 Rp.

    Bahan Rp.

    Kalciboar Uk. 6 mm Lbr 0.3640 @ Rp. 125,200.00 Rp.

    Paku sekrup kg 0.1100 @ Rp. 45,250.00 Rp.

    Rp.

    Rp.

    SNI 12.3.1 1 M' List gipsum

    Tenaga

    Mandor OH 0.0060 @ Rp. 177,100.00 Rp.

    Kepala Tukang Kayu OH 0.0100 @ Rp. 151,800.00 Rp.

    Tukang Kayu OH 0.1000 @ Rp. 101,200.00 Rp.

    Pembantu Tukang Kayu OH 0.1000 @ Rp. 75,900.00 Rp.

    Bahan Total upah Rp.Lits gipsum 10 cm M' 1.0500 @ Rp. 15,450.00 Rp.

    Paku Sekrup KG 0.0220 @ Rp. 45,250.00 Rp.

    Total bahan Rp.

    Total upah + bahan Rp.

    10 ANALIS BIAYA KONSTRUKSI ( ABK ) 10 - PEKERJAAN SANITASI

    SNI.X.6.2 Memasang 1 buah Kloset jongkok porselen

    Tenaga

    Mandor OH 0.1600 @ Rp. 177,100.00 Rp.

    Kepala tukang batu OH 1.5000 @ Rp. 151,800.00 Rp.

    Tukang batu OH 1.5000 @ Rp. 113,900.00 Rp.

    Pembantu tukang batu OH 1.0000 @ Rp. 95,900.00 Rp.

    Bahan Rp.

    Kloset jongkok porselen Bh 1.0000 @ Rp. 143,900.00 Rp.

    Semen PC (50 Kg/kg) kg 6.0000 @ Rp. 1,632.00

    Pasir ayak untuk beton/ pasir pasang (loka m3 0.0100 @ Rp. 108,400.00 Rp.

    Rp.

    Rp.

    Hal -5

  • 7/22/2019 Rab Posyandu

    6/19

    NO ANALISA BAHAN & UPAH SATUAN KOEFISIEN HARGA SATUAN

    SNI.X.6.20 Memasang 1m' Instalasi Air Kotor PVC AW 3/4"

    Tenaga

    Mandor OH 0.0041 @ Rp. 177,100.00 Rp.

    Kepala tukang kayu OH 0.0135 @ Rp. 151,800.00 Rp.

    Tukang batu OH 0.1350 @ Rp. 113,900.00 Rp.

    Pembantu tukang kayu OH 0.0810 @ Rp. 75,900.00 Rp.Bahan Rp.

    Pipa PVC dia.3/4"/M1 m' 1.2000 @ Rp. 7,150.00 Rp.

    Pipa PVC 3/4 '(perlengkapan) Hrg 0.3500 @ Rp. 2,502.50 Rp.

    Rp.

    Rp.

    SNI.X.6.31 Memasang 1m' Instalasi Air Kotor PVC AW 3"

    Tenaga

    Mandor OH 0.0041 @ Rp. 177,100.00 Rp.

    Kepala tukang kayu OH 0.0135 @ Rp. 151,800.00 Rp.

    Tukang batu OH 0.1350 @ Rp. 113,900.00 Rp.

    Pembantu tukang kayu OH 0.0810 @ Rp. 75,900.00 Rp.

    Bahan Rp.

    Pipa PVC dia.3"/M1 m' 1.2000 @ Rp. 29,725.00 Rp.