    1 | P r o g r e s s P e k e r j a a n E L a n g M a s 0 6 1 2 2 0 1 4

    DOKUMENTASI PEK. BAJA UNTUK PL9/PL10/PL11 (LT.18 & LT.BSMNT) , SL5

    (LT.18 & LT.BSMNT) , RAILLING TANGGA 3 HOTEL , SAFETY NET HOTEL

    06 DESEMBER 2014

    Pak Pieter (Surya Elang Mas)

    1.Lantai 18 (Roof Hotel) Pemasangan Pit Gantugan untuk PL9/PL10/PL11 & SL5

    - Pemasangan Pit Gantungan untuk PL9/PL10/PL11 & SL5

  • 7/25/2019 Progress Pekerjaan Pak Pieter 06122014

    2/4

    2 | P r o g r e s s P e k e r j a a n E L a n g M a s 0 6 1 2 2 0 1 4

    Volume Pekerjaan :

    - Pekerjaan Pemasangan Pelat/Bondek

    PL9/PL10/PL11 = 3 x 2.2m x 2.35m = 15.51 m2

    SL5 = 2.7m x 3.1m = 8.37 m2

    - Pekerjaan Pemasangan WF 300SL 5 (L) = 3.8 m

    - Pekerjaan Pemasangan Siku (L.60)

    PL9/PL10/PL11 = 3 x ( (4*2.2) + (4*2.35) ) = 3 x ( 8.8m + 9.4m) = 3 x 18.2m = 54.6m

    SL5 = (4*2.7) + (4*3.1) = (10.8 + 12.4) m = 23.2m

    Total Pemasangan Siku (L.60) = 54.6m + 23.2m = 77.8 m

    2.Lantai 18 (Roof Hotel) Tambahan Railling Tangga

    P = 1.75m

  • 7/25/2019 Progress Pekerjaan Pak Pieter 06122014

    3/4

    3 | P r o g r e s s P e k e r j a a n E L a n g M a s 0 6 1 2 2 0 1 4

    4.Lantai 8 (Hotel) Safety Net (15 unit)

  • 7/25/2019 Progress Pekerjaan Pak Pieter 06122014

    4/4

    4 | P r o g r e s s P e k e r j a a n E L a n g M a s 0 6 1 2 2 0 1 4

    5.Lantai Ground PL9/PL10

    Volume Pekerjaan :

    - Pekerjaan Pemasangan Pelat/Bondek

    PL9/PL10 = 2 x 2.2m x 2.35m = 10.34 m2

    - Pekerjaan Pemasangan H Beam 300

    PL9/PL10 = 2 x 2 x 2.2m = 8.8 m

    - Pekerjaan Pemasangan Siku (L.60)

    PL9/PL10 = 2 x ( (4*2.2) + (4*2.35) ) = 2 x ( 8.8m + 9.4m) = 2 x 18.2m = 36.4m

    6.Lantai Basement SL5

    - Pekerjaan Pemasangan Pelat/BondekSL5 = 2.7m x 3.1m = 8.37 m

    2

    - Pekerjaan Pemasangan H Beam 300

    SL5 = 2 x 3.1m = 6.2 m

    - Pekerjaan Pemasangan Siku (L.60)

    SL5 = (2*2.7) + (2*3.1) = 2 x ( 8.8m + 9.4m) = 2 x 18.2m = 36.4m

    7.Lantai Basement PL11

    - Pekerjaan Pemasangan Pelat/Bondek (untuk bordes)

    PL11 = 0.4m x 1.1m = 0.44 m2

    8.Lt.9 s/d Lt.12 (Tambahan Pelat + Siku , Spasi antara lantai Hotel dgn Dinding Precast /Braket)

    Volume = 4 Lantai x 14.734m / perlantai = 58.936 m