NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN 1 Permulaan V = p x l = 34 x 16 = 544 V = 2(p + l) = 2(28 + 16) = 88 V = p x l = 3 x 5 = 15 2 Penggalian V = p x l x t = 1,2 x 1 x 1 = 1,2 Jumlah = 2 Buah V = 2 x 1,2 = #VALUE! V = p x l x t = 1 x 0,85 x 0,9 = 0,765 Jumlah = 12 Buah V = 12 x 0,765 = 9180 I. PEKERJAAN PONDASI a. Pembersihan Lapangan m 2 b. Memasang Bouwplank m 2 c. Direksi Keet m 2 1. Pondasi Setempat m 3 m 3 m 3 m 3 P1 P2 Direksi Keet 5 5 90 17 Ø12-10 Ø12-15 Ø8-15 LantaiKerja CorBeton 1:3:5 PasirUrug Ø12-15 Ø12-10 Ø8-15 10 80 5 5 80 10 17 PasirUrug Lantai Kerja CorBeton 1:3:5

Upload: muhammad-iqbal

Post on 22-Oct-2015

62 views

Category:

Documents


4 download

DESCRIPTION

RAB ok

TRANSCRIPT

Page 1: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

1 Permulaan

V = p x l

= 34 x 16

= 544

V = 2(p + l)

= 2(28 + 16)

= 88

V = p x l

= 3 x 5

= 15

2 Penggalian

V = p x l x t

= 1,2 x 1 x 1

= 1,2

Jumlah = 2 Buah

V = 2 x 1,2

= #VALUE!

V = p x l x t

= 1 x 0,85 x 0,9

= 0,765

Jumlah = 12 Buah

V = 12 x 0,765

= 9180

I.    PEKERJAAN PONDASI

a.        Pembersihan Lapangan

m2

b.       Memasang Bouwplank

m2

c.        Direksi Keet

m2

1.        Pondasi Setempat

m3

m3

m3

m3

P1

P2

Direksi Keet

55

90

17

Ø12-10

Ø12-15

Ø8-15

Lantai Kerja Cor Beton 1:3:5

Pasir Urug

Ø12-15

Ø12-10

Ø8-15

10

80

55

8010

17

Pasir Urug

Lantai Kerja Cor Beton 1:3:5

Page 2: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

V = p x l x t

= 0,85 x 0,85 x 0,9

= 0,65025

Jumlah = 2 Buah

V = 2 x 0,65025

= #VALUE!

V = p x l x t

= 1,1 x 0,85 x 1

= 0,935

Jumlah = 2 Buah

V = 2 x 0,935

= 1870

V = p x l x t

= 0,95 x 0,85 x 0,9

= 0.72675

Jumlah = 3 Buah

V = 3 x 0,72675

= 2.18025

V = p x l x t

= = 0,95 x 0,7 x 0,9

= 0.5985

Jumlah = 1 Buah

V = 1 x 0.5985

= 0.5985

m3

m3

m3

m3

m3

m3

m3

m3

P2*

P3

P4

P4*

Ø12-15

Ø12-10

Ø8-15

10

80

55

8010

17

Pasir Urug

Lantai Kerja Cor Beton 1:3:5

65

55

80

10

Ø8-15

Ø12-10

Ø12-15

Pasir Urug

Lantai Kerja Cor Beton 1:3:5

17

10 90

55

90

10

Ø8-15

Ø12-10

Ø12-15

17

Pasir Urug

Lantai Kerja Cor Beton 1:3:5

17

10 75

55

80

Ø12-10

Ø12-15

10

Ø8-15

Pasir Urug

Lantai Kerja Cor Beton 1:3:5

Ø8-15

10

Ø12-15

Ø12-1080

55

60

17

Pasir Urug

Lantai Kerja Cor Beton 1:3:5

Page 3: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

V = p x l x t

= 1,1 x 1,1 x 1

= 1.21

Jumlah = 2 Buah

V = 2 x 1.21

= 2.42

V = p x l x t

= 0,9 x 0,9 x 0,9

= 0.729

Jumlah = 2 Buah

V = 2 x 0.729

= 1.458

V = p x l x t

= = 0,8 x 0,8 x 0,7

= 0.448

Jumlah = 2 Buah

V = 2 x 0.448

= 0.896

V = p x l x t

= 0,8 x 0,8 x 0,7

= 0.448

Jumlah = 25 Buah

V = 25 x 0.448

= 11.2

m3

m3

m3

m3

m3

P5

P6

P7

P8

55

90

109010

17

Pasir Urug

Lantai Kerja Cor Beton 1:3:5

10 70

80

10

Ø8-15

55

17

Pasir Urug

Lantai Kerja Cor Beton 1:3:5

17

10 60

55

60

10

Ø8-15

Ø12-15

Ø12-10

Pasir Urug

Lantai Kerja Cor Beton 1:3:5

Muka Tanah

Ø8-15

Ø12-10

10

Ø12-15

10

55

60

60

17

Pasir Urug

Lantai Kerja Cor Beton 1:3:5

Page 4: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

V = p x l x t

= 0,8 x 0,7 x 0,7

= 0.392

Jumlah = 5 Buah

V = 5 x 0.392

= 1.96

V = p x l x t

= 0,8 x 0,8 x 0,7

= 0.448

Jumlah = 12 Buah

V = 12 x 0.448

= 5.376

V = p x l x t

= 0,95 x 0,8 x 2,03

= 1.543

Jumlah = 8 Buah

V = = 8 x 1,543

= 12.344

m3

m3

m3

m3

m3

m3

P8*

P9

P10

P10

50

60

55

10

Ø8-15

Muka Tanah

17

Pasir Urug

Lantai Kerja Cor Beton 1:3:5

17

55

10

60

6010

Balok Lantai15/20

Pas. 1 bata25/25

Ø12-15

Ø12-10

Muka Lantai

Pasir Urug

Lantai Kerja Cor Beton 1:3:5

Ø12-15

Ø12-10

Ø12-15

75

60Ø12-10

27

27

Cerocok Kayu Mahang 10 Ø 12-15 cm

Ø8-15 4Ø12

15

15

240

2x2Ø12

15

25

2x2Ø14

17

55

193

10 75 10Pasir Urug

Lantai Kerja Cor Beton 1:3:5

Ø12-10

Ø12-15

Ø8-15

Skala 1 : 50

65

Page 5: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

V = p x l x t

= 1,77 x 0,8 x 0,7

= 0.9912

Jumlah = 1 Buah

V = 1 x 0.9912

= 0.9912

A = p x l

= 1,35 x 0,35

= 0.4725

Panjang = 1 195.5 m

V = 195.5 x 0.4725

= 92.37375

Total Tanah Galian #VALUE!

V = #VALUE!

= #VALUE!

3 Pemasangan Pondasi

V = p x l x t x Jumlah= 1,2 x 1 x 0,05 x 2= 0.12

V = p x l x t x Jumlah= 1 x 0,85 x 0,05 x 12= 0.51

V = p x l x t x Jumlah= 0,85 x 0,85 x 0,05 x 2= 0.07225

V = p x l x t x Jumlah= 1,1 x 0,85 x 0,05 x 2= 0.0935

V = p x l x t x Jumlah= 0,95 x 0,85 x 0,05 x 3= 0.121125

V = p x l x t x Jumlah= 0,95 x 0,7 x 0,05 x 1= 0.03325

V = p x l x t x Jumlah= 1,1 x 1,1 x 0,05 x 2= 0.121

m3

m3

2.        Pondasi Menerus

m2

m3

m3

3.        Urugan Kembali ¼ Galian

m3

–         Urugan Pasir Bawah Pondasi1.        P1 (Jumlah 2 Buah)

m3

2.        P2 (Jumlah 12 Buah)

m3

3.        P2* (Jumlah 2 Buah)

m3

4.        P3 (Jumlah 2 Buah)

m3

5.        P4 (Jumlah 3 Buah)

m3

6.        P4* (Jumlah 1 Buah)

m3

7.        P5 (Jumlah 2 Buah)

m3

Pondasi Tangga

Ø12-15

Ø12-10

Ø12-15

75

60Ø12-10

27

27

Cerocok Kayu Mahang 10 Ø 12-15 cm

Ø8-15 4Ø12

15

15

240

2x2Ø12

15

25

2x2Ø14

17

55

193

10 75 10Pasir Urug

Lantai Kerja Cor Beton 1:3:5

Ø12-10

Ø12-15

Ø8-15

Skala 1 : 50

65

125

60

17

90

60

10 10

55

Pasir Urug

5Ø 12 -15

30

90

Ø12-25Keramik 40X40

3

Ø12-25

12

95

10

25

Cerocok Kayu Mahang Ø 12-15 jarak 50 cm zig zag

35

Balok Lantai15/25

Pondasi Pas. 1 Bata Camp. 1:2Plesteran 1:2

3 Ø 12

Dinding Pas. 1/2 Bata

Muka Tanah- 0.90

45

25

Muka Lantai± 0.00

Page 6: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

V = p x l x t x Jumlah= 0,9 x 0,9 x 0,05 x 2= 0.081

V = p x l x t x Jumlah= 0,8 x 0,8 x 0,05 x 2= 0.064

V = p x l x t x Jumlah= 0,8 x 0,8 x 0,05 x 25= 0.8

V = p x l x t x Jumlah

= 0,8 x 0,7 x 0,05 x 5

= 0.14

V = p x l x t x Jumlah

= 0,8 x 0,8 x 0,05 x 12

= 0.384

V = p x l x t x Jumlah

= 0,95 x 0,8 x 0,05 x 8

= 0.304

V = p x l x t x Jumlah

= 1,77 x 0,8 x 0,05 x 1

= 0.0708

V = p x l x t

= 195,50 x 0,35 x 0,05

= 3.421

Total Urugan Pasir Bawah Pondasi 6.336

V = p x l x t x Jumlah

= 1,2 x 1 x 0,05 x 2

= 0.12

V = p x l x t x Jumlah

= 1 x 0,85 x 0,05 x 12

= 0.51

V = p x l x t x Jumlah

= 0,85 x 0,85 x 0,05 x 2

= 0.07225

V = p x l x t x Jumlah

= 1,1 x 0,85 x 0,05 x 2

= 0.0935

V = p x l x t x Jumlah

= 0,95 x 0,85 x 0,05 x 3

= 0.121125

V = p x l x t x Jumlah

= 0,95 x 0,7 x 0,05 x 1

= 0.03325

V = p x l x t x Jumlah

8.        P6 (Jumlah 2 Buah)

m3

9.        P7 (Jumlah 2 Buah)

m3

10.     P8 (Jumlah 25 Buah)

m3

11.     P8* (Jumlah 5 Buah)

m3

12.     P9 (Jumlah 12 Buah)

m3

13.     P10 (Jumlah 8 Buah)

m3

14.     Pondasi Tangga (Jumlah 1 Buah)

m3

15.     Pondasi Menerus (Panjang 195,50 m)

m3

m3

–         Lantai Kerja Cor Beton 1: 3: 5

1.        P1 (Jumlah 2 Buah)

m3

2.        P2 (Jumlah 12 Buah)

m3

3.        P2* (Jumlah 2 Buah)

m3

4.        P3 (Jumlah 2 Buah)

m3

5.        P4 (Jumlah 3 Buah)

m3

6.        P4* (Jumlah 1 Buah)

m3

7.        P5 (Jumlah 2 Buah)

Page 7: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAANV

= 1,1 x 1,1 x 0,05 x 2

= 0.121

V = p x l x t x Jumlah

= 0,9 x 0,9 x 0,05 x 2

= 0.081

V = p x l x t x Jumlah

= 0,8 x 0,8 x 0,05 x 2

= 0.064

V = p x l x t x Jumlah

= 0,8 x 0,8 x 0,05 x 25

= 0.8

V = p x l x t x Jumlah

= 0,8 x 0,7 x 0,05 x 5

= 0.14

V = p x l x t x Jumlah

= 0,8 x 0,8 x 0,05 x 12

= 0.384

V = p x l x t x Jumlah

= 0,95 x 0,8 x 0,05 x 8

= 0.304

V = p x l x t x Jumlah

= 1,77 x 0,8 x 0,05 x 1

= 0.0708

Total Volume Lantai Kerja 2.915

V = p x l x t x Jumlah= 1,2 x 1 x 0,17 x 2= 0.408

V = p x l x t x Jumlah= 1 x 0,85 x 0,17 x 12= 1.734

V = p x l x t x Jumlah= 0,85 x 0,85 x 0,17 x 2= 0.24565

V = p x l x t x Jumlah= 1,1 x 0,85 x 0,17 x 2= 0.3179

V = p x l x t x Jumlah= 0,95 x 0,85 x 0,17 x 3= 0.411825

V = p x l x t x Jumlah= 0,95 x 0,7 x 0,17 x 1= 0.11305

V = p x l x t x Jumlah= 1,1 x 1,1 x 0,17 x 2= 0.4114

V = p x l x t x Jumlah= 0,9 x 0,9 x 0,17 x 2= 0.2754

7.        P5 (Jumlah 2 Buah)

m3

8.        P6 (Jumlah 2 Buah)

m3

9.        P7 (Jumlah 2 Buah)

m3

10.     P8 (Jumlah 25 Buah)

m3

11.     P8* (Jumlah 5 Buah)

m3

12.     P9 (Jumlah 12 Buah)

m3

13.     P10 (Jumlah 8 Buah)

m3

14.     Pondasi Tangga (Jumlah 1 Buah)

m3

m3

–         Pasang Pondasi Betona.        Tapak Pondasi1.        P1 (Jumlah 2 Buah)

m3

2.        P2 (Jumlah 12 Buah)

m3

3.        P2* (Jumlah 2 Buah)

m3

4.        P3 (Jumlah 2 Buah)

m3

5.        P4 (Jumlah 3 Buah)

m3

6.        P4* (Jumlah 1 Buah)

m3

7.        P5 (Jumlah 2 Buah)

m3

8.        P6 (Jumlah 2 Buah)

m3

Page 8: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

V = p x l x t x Jumlah= 0,8 x 0,8 x 0,17 x 2= 0.2176

V = p x l x t x Jumlah= 0,8 x 0,8 x 0,17 x 25= 2.72

V = p x l x t x Jumlah= 0,8 x 0,7 x 0,17 x 5= 0.476

V = p x l x t x Jumlah= 0,8 x 0,8 x 0,17 x 12= 1.306

V = p x l x t x Jumlah= 0,95 x 0,8 x 0,17 x 8= 1.034

V = p x l x t x Jumlah= 1,77 x 0,8 x 0,17 x 1= 0.24072

V = p x l x t = 195,50 x 0,35 x 0,10= 6.8425

Total Volume Tapak Pondasi 16.754

V = p x l x t x Jumlah= 0,5 x 0,3 x 1,25 x 2= 0.375

V = p x l x t x Jumlah= 0,3 x 0,15 x 1,25 x 12= 0.675

V = p x l x t x Jumlah= 0,3 x 0,15 x 1,25 x 2= 0.1125

V = p x l x t x Jumlah= 0,4 x 0,15 x 1,25 x 2= 0.15

V = p x l x t x Jumlah= 0,25 x 0,15 x 1,25 x 3= 0.141

V = p x l x t x Jumlah= 0,25 x 0,15 x 1,25 x 1= 0.047

V = p x l x t x Jumlah=

= 0.244

V = p x l x t x Jumlah= 0,2 x 0,2 x 1,25 x 2= 0.1

V = p x l x t x Jumlah= 0,3 x 0,15 x 1,25 x 2= 0.113

9.        P7 (Jumlah 2 Buah)

m3

10.     P8 (Jumlah 25 Buah)

m3

11.     P8* (Jumlah 5 Buah)

m3

12.     P9 (Jumlah 12 Buah)

m3

13.     P10 (Jumlah 8 Buah)

m3

14.     Pondasi Tangga (Jumlah 1 Buah)

m3

15.     Pondasi Menerus (Panjang 195,50 m)

m3

m3

b.       Tiang Pondasi1.        P1 (Jumlah 2 Buah)

m3

2.        P2 (Jumlah 12 Buah)

m3

3.        P2* (Jumlah 2 Buah)

m3

4.        P3 (Jumlah 2 Buah)

m3

5.        P4 (Jumlah 3 Buah)

m3

6.        P4* (Jumlah 1 Buah)

m3

7.        P5 (Jumlah 2 Buah)(0,42 – 0,252) x 1,25 x 2

m3

8.        P6 (Jumlah 2 Buah)

m3

9.        P7 (Jumlah 2 Buah)

m3

Page 9: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

V = p x l x t x Jumlah= 0,15 x 0,15 x 1,25 x 25= 0.703

V = p x l x t x Jumlah= 0,15 x 0,15 x 1,25 x 5= 0.141

V = p x l x t x Jumlah= 0,8 x 0,8 x 1,25 x 12= 9.6

V = p x l x t x Jumlah= 0,95 x 0,8 x 2,40x 8= 14.592

V = p x l x t x Jumlah

= 1,2 x 0,15 x 1,25 x 1

= 0.225

V = p x l x t = 195,50 x 0,25 x 1= 48.875

Total Volume Tiang Pondasi 76.0935

V = Banyak Kayu x Jumlah= 13 x 2= 26 Buah

V = Banyak Kayu x Jumlah= 10 x 12= 120 Buah

V = Banyak Kayu x Jumlah= 10 x 2= 20 Buah

V = Banyak Kayu x Jumlah= 12 x 2= 24 Buah

V = Banyak Kayu x Jumlah= 10 x 3= 30 Buah

V = Banyak Kayu x Jumlah= 10 x 1= 10 Buah

V = Banyak Kayu x Jumlah= 13 x 2= 26 Buah

V = Banyak Kayu x Jumlah= 8 x 2= 16 Buah

V = Banyak Kayu x Jumlah= 5 x 2= 10 Buah

V = Banyak Kayu x Jumlah= 5 x 25= 125 Buah

V = Banyak Kayu x Jumlah= 5 x 5= 25 Buah

V = Banyak Kayu x Jumlah= 5 x 12= 60 Buah

V = Banyak Kayu x Jumlah= 10 x 8= 80 Buah

V = Banyak Kayu x Jumlah

= 12 x 1= 12 Buah

V = Banyak Kayu x Jumlah= 195,50 : 0,25= 782 Buah

V = Banyak Kayu x Jumlah= 127 x 1= 127 Buah

Total Cerocok Kayu Mahang 1493 Buah

1 Beton Bertulang

V = p x l x t= 98,6057 x 0,25 x 0,15= 3.698

V = p x l x t= 96,893 x 0,40 x 0,15

10.     P8 (Jumlah 25 Buah)

m3

11.     P8* (Jumlah 5 Buah)

m3

12.     P9 (Jumlah 12 Buah)

m3

13.     P10 (Jumlah 8 Buah)

m3

14.     Pondasi Tangga (Jumlah 1 Buah)

m3

c.        Pondasi Menerus (Pasang Bata)

m3

m3

–         Cerocok Kayu Mahang1.        P1 (Jumlah 2 Buah)

2.        P2 (Jumlah 12 Buah)

3.        P2* (Jumlah 2 Buah)

4.        P3 (Jumlah 2 Buah)

5.        P4 (Jumlah 3 Buah)

6.        P4* (Jumlah 1 Buah)

7.        P5 (Jumlah 2 Buah)

8.        P6 (Jumlah 2 Buah)

9.        P7 (Jumlah 2 Buah)

10.     P8 (Jumlah 25 Buah)

11.     P8* (Jumlah 5 Buah)

12.     P9 (Jumlah 12 Buah)

13.     P10 (Jumlah 8 Buah)

14.     Pondasi Tangga (Jumlah 1 Buah)

15.     Pondasi Menerus

16.     Pelat Lantai Bak Tampung

II.  PEKERJAAN BETON/DINDING LT. 1

a.        Balok Sloof

m3

15

25Ø 8-12,5

2x3 Ø 12

2Ø 14

Ø 8-12,5

2Ø 14

40

15

4Ø 12

Page 10: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

= 5.814

V = p x l x t= 118,2 x 0,20 x 0,15= 3.546

Total Balok Sloof 13.058

V = p x l x t x Jumlah= 0,5 x 0,3 x 4,75 x 2= 1.425

V = p x l x t x Jumlah= 0,3 x 0,15 x 4,75 x 14= 2.993

V = p x l x t x Jumlah= 0,4 x 0,15 x 4,75 x 2= 0.57

V = p x l x t x Jumlah= 0,25 x 0,15 x 4,75 x 4= 0.713

V = p x l x t x Jumlah=

= 0.926

V = p x l x t x Jumlah= 0,2 x 0,2 x 4,75 x 2= 0.38

V = p x l x t x Jumlah= 0,3 x 0,15 x 4,75 x 2= 0.428

V = p x l x t x Jumlah= 0,15 x 0,15 x 4,75 x 30= 3.206

V = p x l x t x Jumlah= 0,2 x 0,2 x 4,75 x 12= 2.28

Total Kolom Lantai 1 12.921

V = p x l x t= 4,25 x 2,75 x 0,12 = 1.403

1I Pekerjaan DindingA = p x tA = 6 x 4,35

= 26.1

A = 2 (3 x 4,35)= 26.1

A = 1,75 x 4,35= 7.613

A = 6,25 x 4,35= 27.188

A = 1,5 x 4,35= 6.525

A = 4,5 x 4,35= 19.575

A = 2 (3,75 x 4,35)= 32.625

A = 3,5 x 4,35= 15.225

A = 3,5 x 4,35= 15.225

A = 6,25 x 4,35= 27.188

A = 2 (2,75 x 4,35)= 11.963

A = 2 x 4,35= 8.7

A = 2,25 x 4,35

m3

m3

m3

b.       Tiang Praktis (Kolom) Lantai 11.        K1 (Jumlah 2 Buah)

m3

2.        K2 (Jumlah 14 Buah)

m3

3.        K3 (Jumlah 2 Buah)

m3

4.        K4 (Jumlah 4 Buah)

m3

5.        K5 (Jumlah 2 Buah)(0,42 – 0,252)x 4,75 x 2

m3

6.        K6 (Jumlah 2 Buah)

m3

7.        K7 (Jumlah 2 Buah)

m3

8.        K8 (Jumlah 30 Buah)

m3

9.        K9 (Jumlah 12 Buah)

m3

m3

c.        Pelat Lantai Beton Bak Tampung

m3

a.        Luas Dinding1.        A – H

m2

2.        A – D m2

3.        A – B m2

4.        B – K m2

5.        M – O m2

6.        K – O m2

7.        E – J m2

8.        A – E m2

9.        L – O m2

10.     A – I m2

11.     N – P m2

12.     A – C m2

13.     L – N

2Ø 14

Ø 8-12,5

2Ø 14

40

15

4Ø 12

2x4 Ø 12

Ø 8-12,520

15

Page 11: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

= 9.788

A = 4,5 x 4,35= 19.575

A = 7 x 4,35= 30.45

A = 1 x 4,35= 4.35

A = 21,5 x 4,35= 93.525

A = 2 x 4,35= 8.7

A = 3 (2,5 x 4,35)= 32.625

A = 3 x 4,35= 13.05

A = 2,25 x 4,35= 9.788

A = 6,5 x 4,35= 28.275

A = 8,75 x 4,35= 38.063

A = 0,5 x 4,35= 2.175

13.     L – N m2

14.     A – F m2

15.     G – O m2

16.     F – G m2

17.     1 – 14 m2

18.     2 – 4 m2

19.     12 – 13 m2

20.     1 – 2 m2

21.     3 – 6 m2

22.     7 – 12 m2

23.     12 – 16 m2

24.     15 – 16 m2

Page 12: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

A = 4,5 x 4,35= 19.575

A = 5,25 x 4,35= 22.838

A = 2 (1,75 x 4,35)= 15.225

A = 3,25 x 4,35= 14.138

A = 2 (5,75 x 4,35)= 28.75

A = 10 x 4,35= 43.5

Luas Dinding 658.417

A = p x tA = 6 x 1,5

= 9

A = 3 x 1,5= 4.5

A = 3 x 0,20= 0.6

A = 1,75 x 1,5= 2.625

A = 5 x 0,20= 1

A = 2 (1,5 x 1,50)= 4.5

A = 3 x 0,20= 0.6

A = 2 (3,75 x 0,20)= 1.5

A = 3,5 x 0,2= 0.7

A = 3,5 x 0,2= 0.7

A = 2 x 1,5 + 4,25 x 0,2= 3.85

A = 2 (2,75 x 1,5)= 8.25

A = 2 x 1,5= 3

A = 2,25 x 0,2= 0.45

A = 4,5 x 0,2= 0.9

A = 7 x 0,2= 1.4

A = 1 x 0,2= 0.2

A = 4,5 x 1,5 + 17 x 0,2= 10.15

A = 2 x 1,5= 3

A = 3 (2,5 x 1,5)= 11.25

A = 3 x 1,5= 4.5

A = 2,25 x 0,2= 4.5

A = 6,5 x 0,2= 1.3

A = 8,75 x 0,2= 1.75

A = 0,5 x 0,2= 0.1

A = 4,5 x 1,5= 6.75

A = 5,25 x 0,2= 1.05

A = 1,75 x 1,5 + 1,75 x 0,2= 2.975

A = 3,25 x 0,2= 0.65

A = 2 (5,75 x 0,2)= 2.3

A = 1,75 x 1,5 + 8,25 x 0,2

25.     1 – 3 m2

26.     7 – 11 m2

27.     3 – 5 m2

28.     5 – 9 m2

29.     13 – 15 m2

30.     3 – 12 m2

m2

b.        Pasangan Tembok 1 : 21.        A – H

m2

2.        A – D m2

3.        A – D m2

4.        A – B m2

5.        B – K m2

6.        M – O m2

7.        K – M m2

8.        E – J m2

9.        A – E m2

10.     L – O m2

11.     A – I m2

12.     N – P m2

13.     A – C m2

14.     L – N m2

15.     A – F m2

16.     G – O m2

17.     F – G m2

18.     1 – 14 m2

19.     2 – 4 m2

20.     12 – 13 m2

21.     1 – 2 m2

22.     3 – 6 m2

23.     7 – 12 m2

24.     12 – 16 m2

25.     15 – 16 m2

26.     1 – 3 m2

27.     7 – 11 m2

28.     3 – 5 m2

29.     5 – 9 m2

30.     13 – 15 m2

31.     3 – 12

Page 13: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

= 4.275

Luas Tembok 1 : 2 98.325

A = p x tA = 3.0789

A = 3.9452

A = 0

A = 3.8544

A = 0

31.     3 – 12 m2

m2

c.       Bidang Kunsen1.        A – H m2

2.        A – D m2

3.        A – B

4.        B – K m2

5.        M – O

Page 14: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

A = 2.2812

A = 0

A = 6.1356

A = 0

A = 0.96

A = 2.2812

A = 0

A = 2.5052

A = 8.1462

A = 17.8981

A = 0

A = 0

A = 1.9612

A = 1.9612

A = 0.48

A = 2.2812

A = 6.1578

A = 5.1162

A = 0

A = 3.0789

A = 2.5052

A = 3.5632

A = 2.5052

A = 0.48

A = 13.5842

Bidang Kunsen 94.760

d = a - (b + c) = 465.332

V =

= 658,417 x 0,15 - 94,760 x 0,15

= 84.549

6.        K – O m2

7.        E – J

8.        A – E m2

9.        L – O

10.     A – I m2

11.     N – P m2

12.     A – C

13.     L – N m2

14.     A – F m2

15.     G – O m2

16.     F – G

17.     1 – 14

18.     2 – 4 m2

19.     12 – 13 m2

20.     1 – 2 m2

21.     3 – 6 m2

22.     7 – 12 m2

23.     12 – 16 m2

24.     15 – 16

25.     1 – 3 m2

26.     7 – 11 m2

27.     3 – 5 m2

28.     5 – 9 m2

29.     13 – 15 m2

30.     3 – 12 m2

m2

d.        Luas Tembok 1 : 4 m2

d.        Pasang Bata Vdinding - Vkusen

m3

Page 15: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

III Kusen

Jumlah = 1 Buah

p = 20 m

P = 20 m

Jumlah = 1 Buah

p = 18.2 m

P = 18.2 m

Jumlah = 1 Buah

p = 10.5 m

P = 10.5 m

Jumlah = 6 Buah

p = 8.5 m

P = 51 m

Jumlah = 2 Buah

p = 8.4 m

P = 16.8 m

Jumlah = 4 Buah

p = 5.2 m

P = 20.8 m

Jumlah = 1 Buah

p = 17.1 m

P = 17.1 m

Jumlah = 1 Buah

p = 10.75 m

P = 10.75 m

Jumlah = 1 Buah

p = 23.7 m

P = 23.7 m

Jumlah = 3 Buah

p = 13.15 m

P = 39.45 m

Jumlah = 5 Buah

p = 11.5 m

P = 57.5 m

Jumlah = 8 Buah

p = 4.8 m

P = 38.4 m

Jumlah = 1 Buah

a.     Kusen Pintu dan Jendela

1.        Tipe P1 + J1

2.        Tipe P1

3.        Tipe P3

4.        Tipe P5

5.        Tipe P6

6.        Tipe P7

7.        Tipe PG

8.        Tipe J1

9.        Tipe J3 + J4

10.      Tipe J7

11.      Tipe J8

12.      Tipe V1

13.      Tipe V2

3.7500

2.0000

5.0000

3.7500

14.0000

5.0000

1.7500

3.0000

2.5000

5.2500

3.2500

2.5000

5.7500

3.0000

4.5000 3.5000

2.5000

3.5000

12.5000

3.5000

4.5000

1.5000

1.7500

4.5000

3.0000

1.7500

1.5000

4.5000

2.5000

2.0000

1.7678

1.5000

1.5000

3.0000

23.2500

1.5000

1.7500

12.5000

1.0000

3.5000

1.50003.00002.0000

1.2500

1.2500

2.5000

1.7500

3.0000

12

34

56

78

910

1112

1314

1516

Page 16: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

p = 3.2 m

P = 3.2 m

Total Panjang Kusen 327.4 m

10% Kayu Hilang 32.74 m

Volume Kusen 4.60979

Jumlah = 1 Buah

p = 13.5935 m

P = 13.5935 m

Jumlah = 1 Buah

p = 10.6729 m

P = 10.6729 m

Jumlah = 1 Buah

p = 7.24 m

P = 7.24 m

Jumlah = 6 Buah

p = 6.44 m

P = 38.64 m

Jumlah = 2 Buah

p = 6.24 m

P = 12.48 m

Jumlah = 4 Buah

p = 6.24 m

P = 24.96 m

Jumlah = 1 Buah

p = 12.28 m

m3

b.     Memeni Kayu yang Menyentuh Pasangan

1.        Tipe P1 + J1

2.        Tipe P1

3.        Tipe P3

4.        Tipe P5

5.        Tipe P6

6.        Tipe P7

7.        Tipe PG

Page 17: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

P = 12.28 m

Jumlah = 1 Buah

p = 12.32 m

P = 12.32 m

Jumlah = 1 Buah

p = 13.38 m

P = 13.38 m

Jumlah = 3 Buah

p = 8.96 m

P = 26.88 m

Jumlah = 5 Buah

p = 7.86 m

P = 39.3 m

Jumlah = 8 Buah

p = 4.8 m

P = 38.4 m

Jumlah = 1 Buah

p = 3.2 m

P = 3.2 m

Total Panjang Kusen 253.3464 m

Volume 253.346 x 0.15

= 38.00196

Pemasangan Angkur

Jumlah 168 Buah

Volume V = n x p x berat besi

= 92.904 kg

Bagian 1

Kayu 6/12

= 2,85 x 2 + 2,85 x 2

= 11.4 m

Kayu 5/7

= 2,85 x 2 + 2,85 x 2

= 11.4 m

Bagian 2

Kayu 6/12

= 2,85 x 2 + 1,25 + 4,10 + 1,35+ 3,0 + 4,35

= 19.75 m

Kayu 5/7

= 4,35 x 2 + 1,35 x 2 + 2,85

= 14.25 m

8.        Tipe J1

9.        Tipe J3 + J4

10.      Tipe J7

11.      Tipe J8

12.      Tipe V1

13.      Tipe V2

m2

III.  PEKERJAAN PLAFOND

1.      Balok Plafond

6/12

6/12

5/7

5/7

5/7

5/7

6/12

6/12

2.8500

2.8500

3.0000

6/12

6/12

6/12

6/12

6/12

6/12

6/12

5/75/7

5/7

5/7

5/7

5/7

4.3500

4.1000

1.3500

1.2500

Page 18: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

Bagian 3

Kayu 6/12

= 1,85 x 2 + 1,60 x 2

= 6.9 m

Kayu 5/7

= 1,85 x 2 + 1,60 x 2

= 6.9 m

Bagian 4

Kayu 6/12

= 2,85 + 1,10 + 1,75 + 2,1 + 0,5 + 1,5

= 9.8 m

Kayu 5/7

= 2,1 + 2,85 + 1,6

= 6.55 m

Bagian 5

Kayu 6/12

= 4,85 x 2 + 1,395 + 2,154 + 1,175 + 1 + 3,1

+ 3,783 + 1,35 + 1,5

= 25.157 m

Kayu 5/7

= 3,25 x 3 + 2,72 + 4,85 + 5,4 + 1,25

= 23.97 m

Bagian 6

Kayu 6/12

= 2,883 + 3,6 + 1,154 + 1,395 + 2,35

= 11.382 m

Kayu 5/7

= 3,6 + 3,03 + 2,13 + 2,35 x 2

= 13.46 m

1.8500

1.6000

5/7

5/76/12

6/12

6/12

6/12

2.8500

2.1000

1.7500 1.1000

1.6000

5/7

5/7

5/7

6/12

6/12

6/12

6/12

6/12

6/12

4.8500

1.7500

3.1000

1.3500

1.5000

2.1542

1.3945

3.7825

1.0000

6/12

6/12

6/12

6/12

6/12

6/12

6/12

6/12

6/12

6/12

5/7

5/7

5/7

5/7 5/7

5/7

5/7

1.3945

1.1542

2.3500

3.6000

2.8825

6/12

6/12

6/12

6/12

6/12

5/7

5/7

5/7

5/7

5/7

Page 19: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

Bagian 7 Kayu 6/12

= 3,6 x 2 + 3,35 x 2

= 13.9 m

Kayu 5/7

= 3,6 x 3 + 3,35 x 3

= 20.85 m

Bagian 8

Kayu 6/12

= 3,6 + 1,644 + 1,706 + 2,394 + 2,85

= 12.194 m

Kayu 5/7

= 2,85 x 2 + 2,198 + 3,6 + 3,198

= 14.696 m

Bagian 9

Kayu 6/12

= 3,10 x 2 + 3,35 x 2

= 12.9 m

Kayu 5/7

= 3,10 x 2 + 3,35 x 2

= 12.9 m

Bagian 10

Kayu 6/12

= 5 x 2 + 5 x 2 + 3,75 + 3,737 + 1,777

= 29.264 m

Kayu 5/7

= 5 x 3 + 5 x 3 + 4,122 + 4,125

= 38.247 m

3.6000

3.3500

6/12

6/12

6/126/12

5/7

5/75/7

5/7

5/7

5/7

1.7056

2.3939

1.6439

3.6000

2.8500

5/7

5/7

5/7

5/7

5/7

6/12

6/12

6/12

6/12

6/12

3.3500

3.1000

6/12

6/12

6/12

6/12

5/7

5/7

5/7

5/7

1.7765

3.7376

5.0000

5.0000

3.7500

6/12

6/12

6/12

6/12

6/12

6/12

5/7

5/7

5/7

5/7

5/7

5/7

5/7

5/7

Page 20: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

Bagian 11

Kayu 6/12

= 8,6 + 5,75 + 2,35 + 0,5 + 0,85 + 3,5 + 2,25

2,456 + 1,724 x 2 + 1,706 + 8,473 + 4,3

= 44.183 m

Kayu 5/7

= 6,5 x 2 + 4,3 x 4 + 8 + 8,823 + 3,073 x 2

= 53.169 m

Bagian 12

Kayu 6/12

= 2,6 x 2 + 2,35 x 2

= 9.9 m

Kayu 5/7

= 2,6 x 2 + 2,35 x 2

= 9.9 m

Bagian 13

Kayu 6/12

= 3,35 x 3 + 5,6 x 2

= 21.25 m

Kayu 5/7

= 3,35 x 4 + 5,6 x 3

= 30.2 m

Bagian 14

Kayu 6/12

= 1,85 x 2 + 2,35 x 2

= 8.4 m

Kayu 5/7

= 1,85 + 2,35

= 4.2 m

Bagian 15

Kayu 6/12

0.8500

0.5000

3.5000

8.6000

1.7061

1.7238 1.7238

2.4561

2.3500

2.2500

5.7500

6/12

6/12

6/126/12

6/12

6/12

6/12

6/126/12

6/12

6/12

6/12

6/12

5/7

5/7

5/7

5/7

5/7

5/7

5/7

5/7

5/75/7

2.6000

2.3500

6/12

6/12

6/12

6/12 5/7

5/7

5/7

5/7

5.6000

3.3500

6/12

6/12

6/12

6/12

6/12

5/7

5/7

5/7

5/7

5/7

5/7

5/7

1.8500

2.3500

6/12

5/7

6/125/7

5/7

5/7

5/7

5/7

6/12

6/12

6/12

6/12

6/12

6/12

2.0000 2.3500

6.8500

4.3500

4.3500

2.5000

6/12

5/7

5/75/7

5/7

5/7

5/7

Page 21: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

= 4,35 + 2,35 x 2 + 2 + 2,5 + 4,35 +6,85

= 24.75 m

Kayu 5/7

= 4,35 x 2 + 6,85 x 2 + 2,35 x 2 + 4,35 x 4

= 44.5 m

Bagian 16

Kayu 6/12

= 1,35 x 2 + 1,6 x 2

= 5.9 m

Kayu 5/7

= 1,35 x 1

= 1.35 m

Kayu 6/12 267.03 m

Kayu 5/7 306.542 m

Pekerjaan Lis Profil Panjang seluruhnya :

= 231.924 m

Ruang 1

A = 9

Ruang 2

A = 15.375

Ruang 3

A = 3.5

Ruang 4

A = 5.875

Ruang 5

A = 21.031

Ruang 6

A = 8.906

Ruang 7

A = 13.125

Ruang 8

A = 10.469

Ruang 9

A = 11.375

Ruang 10

A = 25.677

Ruang 11

A = 44.813

Ruang 12

A = 6.875

Ruang 13

A = 20.125

Ruang 14

A = 5

2.      Memasang Plafond

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

5/7

5/7

5/7

5/7

6/12

6/12

6/12

6/12

6/12

6/12

2.0000 2.3500

6.8500

4.3500

4.3500

2.5000

6/12

5/7

5/75/7

5/7

5/7

5/7

1.6000

1.3500

5/7

6/12

6/12

6/12

6/12

1 23

4 56

7

8

9

10

11 12

13

14

15

16 1.7500

3.2500

5.0000

5.7500

2.5000

21.5000

3.0000

2.0000

4.2500

7.0000

2.5000

3.50003.50001.00004.5000

6.0000

2.0000 3.0000 1.5000

Page 22: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

Ruang 15

A = 24.498

Ruang 16

A = 2.625

Volume 228.269

Luas Tembok 1 : 4 465.332

Volume 930.663

Luas Tembok 1 : 2 98.325

Volume 196.65

m2

m2

m2

IV.  PEKERJAAN PLESTERAN

a.      Plesteran dinding 1 : 4

m2

m2

b.      Plesteran dinding 1 : 2

m2

m2

Page 23: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

Ruang 1

A = 9

Ruang 2

A = 15.375

Ruang 3

A = 3.5

Ruang 4

A = 5.875

Ruang 5

A = 21.031

Ruang 6

A = 8.906

Ruang 7

A = 13.125

Ruang 8

A = 10.469

Ruang 9

A = 11.375

Ruang 10

A = 25.677

Ruang 11

A = 44.813

Ruang 12

A = 6.875

Ruang 13

A = 20.125

Ruang 14

A = 5

Ruang 15

A = 24.498

Ruang 16

A = 2.625

Jumlah 229.057

Tebal Urugan Tanah 0.1 m2

Volume 22.9057

Teras Depan

V = p x l x t

= 3,5 x 2,25 x 0,1

= 0.7875

Teras Samping

V = p x l x t

= 3 x 1,825 x 0,1

= 0.5475

Teras Belakang

V = p x l x t

= 3 x 1,75 x 0,1

= 0.525

Volume Tanah di bawah Lantai Teras 1.860

Volume Tanah di bawah Lantai 24.766

a. Dibawah Lantai

Jumlah 229.057

Tebal Urugan Tanah 0.1

Volume 22.9057

b. Dibawah Lantai Teras

Volume Tanah di bawah Lantai Teras 1.860

Volume Urugan Pasir di bawah Lantai 24.766

V.  PEKERJAAN LANTAI

1.     Urugan Tanah dibawah Lantai

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m3

m3

m3

m3

m3

m3

2.     Urugan Pasir dibawah Lantai

m2

m2

m3

m3

m3

1 23

4 56

7

8

9

10

11 12

13

14

15

16 1.7500

3.2500

5.0000

5.7500

2.5000

21.5000

3.0000

2.0000

4.2500

7.0000

2.5000

3.50003.50001.00004.5000

6.0000

2.0000 3.0000 1.5000

Page 24: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

Pasang Ubin Pc Alur

Kamar Mandi A = 18.000

Ubin A. Ubin = 0,2 x 0,2

= 0.04

Jumlah Ubin 450 Buah

Pasang Ubin Pc Polos

Ruang selain Kamar Mandi A = 211.057

Ubin A. Ubin = 0,4 x 0,4

= 0.16

Jumlah Ubin 1320 Buah

Mencat Lis Profil 231.924 m

Mencat Plafond dengan Teak Oil 228.269

Mencat Dinding ###

Mencat Kusen dan Jalusi

Panjang total 580.746 m

Keliling 2 (0,06 + 0,15) 0.42

Volume 243.913

Closet Duduk Porselen 6 Buah

Bath Tub 6 Buah

Instalasi air bersih d = 1/2'

Panjang = 58.65 m

Instalasi air kotor d = 2'

Panjang = 63.46 m

Kran 17 Buah

Flour Drain 9 Buah

2.     Pasang Lantai

m2

m2

m2

m2

VI.  PEKERJAAN CAT/KAPURAN

1.     Mencat Kayu yang Kelihatan

m2

m2

m2

m3

VII.  SANITASI DAN INSTALASI AIR

Page 25: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

Lantai 1

Pondasi

V = Banyak pondasi x n x t

P1 V = 10.8 m

P2 V = 64.8 m

P2* V = 10.8 m

P3 V = 10.8 m

P4 V = 16.2 m

P4* V = 5.4 m

P5 V = 27 m

P6 V = 10.8 m

P7 V = 0 m

P8 V = 0 m

P8* V = 0 m

P9 V = 0 m

P10 V = 0 m

Total 156.6 m

V = Banyak pondasi x n x t

P1 V = 21.6 m

P2 V = 64.8 m

P2* V = 10.8 m

P3 V = 10.8 m

P4 V = 16.2 m

P4* V = 5.4 m

P5 V = 18.9 m

P6 V = 5.4 m

P7 V = 10.8 m

P8 V = 135 m

P8* V = 27 m

P9 V = 0 m

P10 V = 0 m

Total 326.7 m

V = Banyak pondasi x n x t

P1 V = 23.8 m

P2 V = 228 m

P2* V = 36.2 m

P3 V = 38.5 m

P4 V = 52.65 m

P4* V = 20.7 m

P5 V = 42 m

P6 V = 31.2 m

P7 V = 24 m

P8 V = 300 m

P8* V = 52.5 m

P9 V = 144 m

P10 V = 126 m

Total 1119.55 m

Ø8 V = Banyak pondasi x n x t

VII.  PEMBESIAN

Ø14

Ø12

Ø12

Page 26: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

P1 V = 28.8 m

P2 V = 16.2 m

P2* V = 16.2 m

P3 V = 19.8 m

P4 V = 21.6 m

P4* V = 7.2 m

P5 V = 28.8 m

P6 V = 14.4 m

P7 V = 16.2 m

P8 V = 135 m

P8* V = 27 m

P9 V = 0 m

P10 V = 102.4 m

Total 433.6 m

Balok Sloof V = Panjang Sloof x n

Ø12

A V = 591.66 m

B V = 387.6 m

C V = 472.8 m

Ø14 V = Panjang Sloof x n

B V = 387.6 m

Ø8 V = banyak sengkang x panjang sengkang

A V = 631.2 m

B V = 853.6 m

C V = 662.2 m

Kolom

Ø14 V = n x banyak Kolom x tinggi

K1 V = 64 m

K2 V = 448 m

K3 V = 64 m

K4 V = 224 m

K5 V = 160 m

K6 V = 36 m

Total 996 m

Ø12 V = n x banyak Kolom x tinggi

K1 V = 128 m

K2 V = 448 m

K3 V = 64 m

K4 V = 224 m

K5 V = 112 m

K6 V = 18 m

K7 V = 64 m

K8 V = 1088 m

K9 V = 216 m

Total 2362 m

Ø8 V = n x panjang senggkang x jumlah kolom

K1 V = 204.8 m

K2 V = 806.4 m

K3 V = 140.8 m

K4 V = 819.2 m

K5 V = 204.8 m

K6 V = 204.8 m

K7 V = 64.8 m

K8 V = 1305.6 m

K9 V = 345.6 m

Total 4096.8 m

Balok

Ø12 V = panjang x jumlah tulangan

15 x 20 V = 48 m

15 x 25 V = 240 m

Page 27: Perhitungan Volume LT.1

NO SKETSA & JENIS PEKERJAAN VOLUME / PEKERJAAN

15 x 40 V = 704 m

Total 992 m

Ø12 V = panjang senglang x jumlah

15 x 20 V = 67.2 m

15 x 25 V = 256 m

15 x 40 V = 774.4 m

Total 1097.6 m