PERHITUNGAN VOLUME

A. PEKERJAAN PONDASI

1. Pekerjaan Permulaan

a. Pembersihan Lahan

p = 25,5 m

l = 21,95 m

L= 25,5 x 21,95 = 559,725 m2

Vol pekerjaan = 559,725m2

b. Pemasangan Bouwplank

P = 19,5 m

L= 15,95 m

Keliling = 2 . (19,5 + 15,95) = 70,9 m

1

Page 2: Perhitungan Volume Lezian

c. Direksi Keet

P = 4 m

L= 6 m

V = 4 x 6 = 24 m2

d. Bengkel Kerja

P = 4 m

l = 6 m

V = 4 x 6 = 24 m2

e. Barak pekerja

P=6 m

L= 4 m

Luas = 6 x 4 = 24 m2

f. Gudang material

P = 4 m

L= 6 m

V = 4 x 6 = 24 m2

g. Penimbunan Material Agregat

P = 6 m

L= 3 m

V= (6 x 3) = 18 m2

2

Page 3: Perhitungan Volume Lezian

2. Pekerjaan Galian

a. Galian Pondasi Batu Kali

Penampang galian:

Luas penampang : 0,8 m x 1 m = 0,8 m2

Volume galian : 0,8 x 100,8 m = 80,64 m3

b. Urugan Kembali ¼ galian

Volume galian : 80,64 m2

Volume urugan : ¼ x 80,64 = 20,16 m3

3. Pekerjaan Pasangan Pondasi Batu kali

a. Urugan Pasir Bawah Pondasi

T = 0,1 m

l = 0,8 m

p = 100,8 m

v = 0,1 x 0,8 x 100,8 = 8,064 m3

b. Pas. Aanstampeng

T = 0,2 m

L = 0,8 m

P = 100,8 m

Vol = 0,2 x 0,8 x 100,8 = 16,128 m3

c. Pas. Pondasi batu kali

Luas penampang = (0,3+0,6) x 0,6 x ½ = 0,27 m2

Volume = 0,27 m2 x 100,8 m =

3

Page 4: Perhitungan Volume Lezian

4. Pekerjaan Pasangan Pondasi Telapak

a. Galian pondasi

Volume = (1,7 m x 1,7 m x 2,4 m) x 12

= 76,752 m3

b. Lantai Kerja

Volume = (1,7 m x 1,7 m x 0,08 m) x 12

= 2,774 m3

c. Pasangan pondasi telapak

1. Vol = [

]

= 0,93925 m3

2. Kolom = (0,4 x 0,6 x 1,92)

= 0,4608 m3

Total = (0,93925 + 0,4608) x 12

= 16,81 m3

5. Pekerjaan Pasangan Pondasi Tangga

4

Page 5: Perhitungan Volume Lezian

B. PEKERJAAN BETON

1. Beton Bertulang

a. Beton Sloof

Volume = 0,25 m x 0,4 m x 88,85 m

= 8,885 m3

b. Kolom 40/60 (lantai 1)

Volume = (0,4m x 0,6 m x 4 m) x 12

= 11,52 m3

c. Kolom praktis 15/15 (lantai 1)

Volume = (0,15m x 0,15 m x 4 m) x 25

= 2,25 m3

d. Balok induk 40/50

Volume = (0,4m x 0,5 m x 17 m) x 4

= 13,6 m3

e. Balok induk 20/40

Volume = (0,2m x 0,4 m x 10,95 m) x 3

= 2,628 m3

f. Balok anak 20/40

Volume = (0,2m x 0,4 m x 10,95 m) x 2

5

Page 6: Perhitungan Volume Lezian

= 1,752 m3

g. Balok anak 15/30

Volume = (0,15m x 0,3 m x 10,95 m) x 2

= 0,9855 m3

h. Balok ring 15/15

Volume = 0,15m x 0,15 m x 100,8 m

= 2,268 m3

i. Kolom 40/60 (lantai 2)

Volume = 0,4m x 0,6 m x 8

= 7,68 m3

j. Kolom praktis 15/15 (lantai 2)

Volume = (0,15m x 0,15 m x 4 m) x 25

= 2,25 m3

k. Plat beton

Luas = 17 m x 10, 95 m = 186,15 m2

Void = 3,65 m x 5 m = 18,25

Volume = (186,15-18,25 m) x 0,12 m = 20,148 m3

l. Tangga

» Bordes

Volume = 3,65 m x 1,7 m x 0,12 m = 0,7446 m3

» Pelat tangga

Volume = (3,86 m x 1,825 m x 0,12 m) x2 = 1,7 m3

» Anak tangga

Langkah naik = 17 cm = 0,17 m

6

Page 7: Perhitungan Volume Lezian

Langkah datar = 30 cm = 0,3 m

Jumlah anak tangga = 22

Volume = (1/2 x 0,17 m x 0,3 m) x 1,825 m x 22 =

= 1,024 m3

2. Dinding

3. Kusen

C. PEKERJAAN ATAP

1. Kap dan Rangka Atap

a. Pekerjaan kuda-kuda

IWF 300.150.6,5.9

» Panjang kuda-kuda = (9,815 m x 4) x 2 = 78,52 m

» Berat kuda-kuda = 36,7 kg/m

» Volume = 36,7 kg/m x 78,52 m =

2881,684 kg

b. Pekerjaan gording

C 125.50.20. 4,5

» Panjang gording = (12,95 m x 8) x 2 = 207,2 m

» Berat gording = 8,32 kg/m

» Volume = 8,32 kg/m x 207,2 m =

1732,904 kg

c. Pekerjaan trekstang 10 mm

» Panjang trekstang =

» Berat trekstang = 0,627 kg/m

7

Page 8: Perhitungan Volume Lezian

» Volume = 0,627 kg/m x m =

kg

d. Pekerjaan ikatan angin Ø 12

» Panjang ikatan angin =

» Berat ikatan angin =

» Volume = kg/m x m =

kg

e. Pekerjaan lisplank

f. Talang

2. Pemasangan atap

a.Genteng

P = 240 cm = 2,4 m

L = 210 cm = 2,1 m

Overlap atas bawah = 10 cm = 0,1 m

Overlap kiri kanan = 10 cm = 0,1 m

Luas = (2,4 – (2 x 0,1)) – (2,1 – (2 x 0,1)) = 4,18 m2

Luas atap seluruhnya = 2 x luas atap 1 sisi

= 2 x panjang kuda-kuda x panjang atap

= 2 x 9,815 x 12,95

= 254,209 m2

b. Bubungan

Panjang bubungan = panjang atap = 12,95 m

8

Page 9: Perhitungan Volume Lezian

D. PEKERJAAN KAP dan ATAP

1. Kap dan Rangka Atap

a. Pekerjaan kuda – kuda

IWF 175 x 125 x 5,5 x 8 dengan berat g = 23,3 kg/m

- Panjang kuda – kuda satu sisi = 9,654 m

- Panjang kuda – kuda satu portal = 2 x 9,654 m = 19,308 m

- Jumlah portal = 8 buah

- Total panjang kuda – kuda = 8 x 19,308 m = 154,464 m

- Volume kuda – kuda = 154,464 m x 23,3 kg/m = 3599,011 kg

b. Pekerjaan gording

Dimensi Gording [ 150 x 50 x 20 x 4,5

- Berat gording g = 9,2 kg/m

- Jumlah = 8 buah

- Panjang = 44 m

- Volume gording = 2 x 8 x 44 x 9,2 = 6476,8 kg

c. Pekerjaan trekstang

Dimensi trekstang = Ø 10

- Berat g = 0,627 kg/m (Soedrajat; hal: 90)

- Panjang trekstang miring = 28 buah x = 64,232 m

- Volume miring = 64,232 x 0,627 = 40,2735 kg

- Panjang trekstang tegak = 168 buah x 1,379 = 231,672 m

- Volume tegak = 231,672 x 0,627 = 145,2583 kg

- Volume total = 40,2735 + 145,2583 = 185,5318 kg

d. Pekerjaan ikatan angin

Dimensi ikatan angin = Ø 10

- Berat g = 0,627 kg/m

- Jumlah medan portal = 7 medan

9

Page 10: Perhitungan Volume Lezian

- Jarak kuda – kuda = 5,5 m

- Panjang ikatan tanpa overstek = 6,894 m

- Panjang ikatan angin = = 8,819 m

- Panjang ikatan angin silang = 2 x 8,819 = 17,638 m

- Panjang ikatan angin total = 17,638 x 7 = 123,466 m

- Volume ikatan angin = 123,466 x 0,627 = 77,413 kg

e. Pekerjaan listplank

Dimensi papan listplank

b = 2 cm = 0,02 m

h = 20 cm = 0,2 m

- Luas penampang listplank = 0,02 x 0,2 = 0,004 m2

- Panjang listplank = 2 x panjang kapstang = 2 x 19,308 =

38,616 m

- Volume listplank = 38,616 x 0,004 = 0,1545 kg

f. Pekerjaan talang

- Panjang 1 sisi = 44m

- Panjang 2 sisi = 44 x 2 = 88 m

2. Memasang Atap

c. Atap

Jenis atap = genteng

P = 240 cm = 2,4 m

L = 210 cm = 2,1 m

Overlap atas bawah = 10 cm = 0,1 m

Overlap kiri kanan = 10 cm = 0,1 m

Luas = (2,4 – (2 x 0,1)) – (2,1 – (2 x 0,1)) = 4,18 m2

Luas tap seluruhnya = 2 x luas atap 1 sisi

= 2 x panjang kuda – kuda x panjang atap

= 2 x 9,654 x 44

= 849,552 m2

d. Bubungan

Panjang bubungan = panjang atap = 44 m

10

Page 11: Perhitungan Volume Lezian

e. Usuk

Dimensi = b = 5 cm = 0,05 m

= h = 7 cm = 0,07 m

Luas penampang = 0,05 x 0,07 = 0,0035 m2

Panjang 1 buah usuk = panjang kuda – kuda 1 sisi = 9,654 m

Jarak antar usuk = 50 cm = 0,5 m

Jumlah usuk pada 1 sisi = + 1 = + 1 = 89 buah

Jumlah usuk = 2 x 89 = 178 buah

Panjang usuk seluruhnya = 9,654 x 178 = 1718,412 m

Volume usuk = 1718,412 x 0,0035 = 6,014 m3

f. Reng

Dimensi = b = 2 cm = 0,02 m

= h = 3 cm = 0,03 m

Luas penampang = 0,02 x 0,03 = 0,0006 m2

Panjang 1 buah reng = 44 m

Jarak antar reng = 24 cm = 0,24 m

Jumlah reng pada 1 sisi = + 1

= + 1 = 41,225 = 42 buah

Jumlah reng pada atap = 2 x 42 = 84 buah

Panjang reng seluruhnya = 44 x 84 = 3696 m

Volume reng = 3696 x 0,0006 = 2,218 m3

11