RENCANA ANGGARAN BIAYA Project : RUMAH JAGAKARSA Subyek : PEKERJAAN ARSITEKTURAL Total A ± 313.00 Average Project Cost / Sqm : ### NO DESCRIPTION UNIT PRICE JUMLAH vol. SAT (kg) (Rp.) (Rp.) 1 2 3 4 5 6 I PEKERJAAN DINDING ### Dinding bata merah 1/2 BT. ad 1 : 2 133.69 m2 135,000 18,048,150 ### Plester 1 : 2 133.69 m2 73,000 9,759,370 ### Dinding bata merah 1/2 BT. ad 1 : 4 298.60 m2 132,000 39,415,200 ### Plester 1 : 4 488.29 m2 71,000 34,668,590 ### Keramik Dinding KM 20/20cm setara Roman 101.42 m2 180,000 18,255,600 ### Plint Dinding 176.20 m2 68,000 11,981,600 JUMLAH ### II PEKERJAAN KUSEN DAN PINTU ### Pintu & kusen kayu 2 Daun, Pintu utama (P1) 1.00 bh. 5,430,000 5,430,000 ### Pintu & kusen kayu, panel kaca 8 mm, Pintu r t 5.00 bh. 3,000,000 15,000,000 ### Pintu & Kusen kayu 1 Daun (P3) 8.00 bh. 3,260,000 26,080,000 ### Pintu KM (P4) 2.00 bh. 2,900,000 5,800,000 ### Jendela r tidur utama (J1) 1.00 bh. 6,500,000 6,500,000 ### Jendela r tidur 3 + 4 (J1) 2.00 bh. 6,500,000 13,000,000 ### Jendela r makan (J2) 2.00 bh. 6,500,000 13,000,000 ### Jendela r Tamu & keluarga (J3) 3.00 bh. 6,500,000 19,500,000 ### Kusen kayu + kaca lantai loteng kamar 5 + 6 2.00 bh. 5,650,000 11,300,000 JUMLAH ### III PEKERJAAN PLAFOND ### Plafon gypsum 9 mm 371.00 m2 117,500 43,592,500 ### Drop Ceiling 55.00 m' 65,000 3,575,000 ### Cornice alumunium U 234.00 m' 18,000 4,212,000 JUMLAH 51,379,500 IV PEKERJAAN LANTAI ### Pemadatan tanah 54.60 m2 72,000 3,931,200 ### Rolaag lantai 44.00 m' 108,000 4,752,000 ### Screeding + lantai kerja Screeding lantai 3 cm 247.00 m2 84,000 20,748,000 ### Homogeneus Ceramic tile 60 x 60 R. Tamu & kelu 37.80 m2 310,000 11,718,000 ### Homogeneus Ceramic tile 40 x 40 R. Tidur utama 26.25 m2 235,000 6,168,750 ### Homogeneus Ceramic tile 40 x 40 r. Tidur 1 & 2 34.13 m2 235,000 8,019,375 ### Homogeneus Ceramic tile 40 x 40 r. Tidur 3 & 4 36.33 m2 235,000 8,537,550 ### Homogeneus Ceramic tile 40 x 40 . Makan + dapu 30.14 m2 235,000 7,081,725 ### Homogeneus Ceramic tile 40 x 40 teras 13.00 m2 235,000 3,055,000 ### Homogeneus Ceramic tile 40 x 40 R.selasar 65.00 m2 235,000 15,275,000 ### Homogeneus Ceramic tile 20 x 20 KM 23.52 m2 180,000 4,233,600 ### Parquette mezanin R. Tidur 3&4 24.00 m2 235,000 5,640,000 ### batu alam 10 x10 R.selasar samping 20.00 m2 165,000 3,300,000 JUMLAH ### V PEKERJAAN FINISHING DINDING ### Keramik dinding KM 101.20 m2 145,000 14,674,000 ### Batu alam dinding muka 14.40 m2 215,000 3,096,000 ### Pekerjaan Tangga kayu R tidur 3&4 2.00 unit 2,386,000 4,772,000 JUMLAH 22,542,000 V PEKERJAAN PENGECATAN ### Pekerjaan Cat dinding luar, ex ICI Dulux Weat 305.80 m2 28,000 8,562,400 ### Pekerjaan Cat dinding dalam, ex ICI Dulux 428.68 m2 22,000 9,430,960 ### Pekerjaan cat plafond 371.00 m2 22,000 8,162,000 JUMLAH 26,155,360 VI PEKERJAAN ATAP ### Rangka atap baja ringan 408.00 m2 135,000 55,080,000 ### Alumunium foil 408.00 m2 12,000 4,896,000 ### Genteng penutup atap, ex genteng mutiara 408.00 m2 115,000 46,920,000 ### Listplank 170.00 m' 120,000 20,400,000 ### Cat listplank 170.00 m' 36,000 6,120,000 JUMLAH ### VII PEKERJAAN SANITARI ### Monoblock Amstard + Accesories 6.00 bh. 2,400,000 14,400,000 ### Wash basin Amstard + Accesories 6.00 bh. 1,600,000 9,600,000 ### Shower head + kran 6.00 bh. 355,000 2,130,000 ### Floor Drain 12.00 bh. 185,000 2,220,000 JUMLAH 28,350,000 TOTAL ###

Upload: dbicrs

Post on 23-Dec-2015

37 views

Category:

Documents


4 download

DESCRIPTION

jk

TRANSCRIPT

Page 1: Penawaran jkJagakarsa

RENCANA ANGGARAN BIAYA

Project : RUMAH JAGAKARSASubyek : PEKERJAAN ARSITEKTURALTotal Area ± 313.00Average Project Cost / Sqm : Rp 1,955,404.38

NO DESCRIPTION UNIT PRICE JUMLAH

vol. SAT (kg) (Rp.) (Rp.)

1 2 3 4 5 6

I PEKERJAAN DINDING1. Dinding bata merah 1/2 BT. ad 1 : 2 133.69 m2 135,000 18,048,150 2. Plester 1 : 2 133.69 m2 73,000 9,759,370 3. Dinding bata merah 1/2 BT. ad 1 : 4 298.60 m2 132,000 39,415,200 4. Plester 1 : 4 488.29 m2 71,000 34,668,590 5. Keramik Dinding KM 20/20cm setara Roman 101.42 m2 180,000 18,255,600 6. Plint Dinding 176.20 m2 68,000 11,981,600

JUMLAH 132,128,510 II PEKERJAAN KUSEN DAN PINTU

1. Pintu & kusen kayu 2 Daun, Pintu utama (P1) 1.00 bh. 5,430,000 5,430,000 2. Pintu & kusen kayu, panel kaca 8 mm, Pintu r tidur (P2) 5.00 bh. 3,000,000 15,000,000 3. Pintu & Kusen kayu 1 Daun (P3) 8.00 bh. 3,260,000 26,080,000 4. Pintu KM (P4) 2.00 bh. 2,900,000 5,800,000 5. Jendela r tidur utama (J1) 1.00 bh. 6,500,000 6,500,000 6. Jendela r tidur 3 + 4 (J1) 2.00 bh. 6,500,000 13,000,000 7. Jendela r makan (J2) 2.00 bh. 6,500,000 13,000,000 8. Jendela r Tamu & keluarga (J3) 3.00 bh. 6,500,000 19,500,000 9. Kusen kayu + kaca lantai loteng kamar 5 + 6 2.00 bh. 5,650,000 11,300,000

JUMLAH 115,610,000 III PEKERJAAN PLAFOND

1. Plafon gypsum 9 mm 371.00 m2 117,500 43,592,500 2. Drop Ceiling 55.00 m' 65,000 3,575,000 3. Cornice alumunium U 234.00 m' 18,000 4,212,000

JUMLAH 51,379,500 IV PEKERJAAN LANTAI

1. Pemadatan tanah 54.60 m2 72,000 3,931,200 2. Rolaag lantai 44.00 m' 108,000 4,752,000 3. Screeding + lantai kerja Screeding lantai 3 cm 247.00 m2 84,000 20,748,000 4. Homogeneus Ceramic tile 60 x 60 R. Tamu & keluarga 37.80 m2 310,000 11,718,000 5. Homogeneus Ceramic tile 40 x 40 R. Tidur utama 26.25 m2 235,000 6,168,750 6. Homogeneus Ceramic tile 40 x 40 r. Tidur 1 & 2 34.13 m2 235,000 8,019,375 7. Homogeneus Ceramic tile 40 x 40 r. Tidur 3 & 4 36.33 m2 235,000 8,537,550 8. Homogeneus Ceramic tile 40 x 40 . Makan + dapur 30.14 m2 235,000 7,081,725 9. Homogeneus Ceramic tile 40 x 40 teras 13.00 m2 235,000 3,055,000

### Homogeneus Ceramic tile 40 x 40 R.selasar 65.00 m2 235,000 15,275,000 ### Homogeneus Ceramic tile 20 x 20 KM 23.52 m2 180,000 4,233,600 ### Parquette mezanin R. Tidur 3&4 24.00 m2 235,000 5,640,000 ### batu alam 10 x10 R.selasar samping 20.00 m2 165,000 3,300,000

JUMLAH 102,460,200 V PEKERJAAN FINISHING DINDING

1. Keramik dinding KM 101.20 m2 145,000 14,674,000 2. Batu alam dinding muka 14.40 m2 215,000 3,096,000 3. Pekerjaan Tangga kayu R tidur 3&4 2.00 unit 2,386,000 4,772,000

JUMLAH 22,542,000 V PEKERJAAN PENGECATAN

1. Pekerjaan Cat dinding luar, ex ICI Dulux Weathershield 305.80 m2 28,000 8,562,400 2. Pekerjaan Cat dinding dalam, ex ICI Dulux 428.68 m2 22,000 9,430,960 3. Pekerjaan cat plafond 371.00 m2 22,000 8,162,000

JUMLAH 26,155,360 VI PEKERJAAN ATAP

1. Rangka atap baja ringan 408.00 m2 135,000 55,080,000 2. Alumunium foil 408.00 m2 12,000 4,896,000 3. Genteng penutup atap, ex genteng mutiara 408.00 m2 115,000 46,920,000 4. Listplank 170.00 m' 120,000 20,400,000 5. Cat listplank 170.00 m' 36,000 6,120,000

JUMLAH 133,416,000 VII PEKERJAAN SANITARI

1. Monoblock Amstard + Accesories 6.00 bh. 2,400,000 14,400,000

Page 2: Penawaran jkJagakarsa

NO DESCRIPTION UNIT PRICE JUMLAH

vol. SAT (kg) (Rp.) (Rp.)

1 2 3 4 5 6

2. Wash basin Amstard + Accesories 6.00 bh. 1,600,000 9,600,000 3. Shower head + kran 6.00 bh. 355,000 2,130,000 4. Floor Drain 12.00 bh. 185,000 2,220,000

JUMLAH 28,350,000 TOTAL 612,041,570.00

Page 3: Penawaran jkJagakarsa

RENCANA ANGGARAN BIAYA

Project : RUMAH JAGAKARSASubyek : PEKERJAAN STRUKTUR Total Area : ± 270.00Average Project Cost / Sqm : 606,919

NO DESCRIPTION UNIT PRICE JUMLAH

vol. SAT (kg) (Rp.) (Rp.)

1 2 3 4 5 6

I PEKERJAAN PERSIAPAN1. Pengukuran 1.00 ls 3,579,000 3,579,000 2. Dokumentasi & Administrasi 1.00 ls 2,148,000 2,148,000 3. Bedeng pekerja + gudang 30.00 m2 931,000 27,930,000 4. Pas. Bauwplak 103.00 m' 144,000 14,832,000 5. Mobilisasi & Demobilisasi Alat Kerja 1.00 ls 11,453,000 11,453,000 6. Kebersihan Lokasi Kerja 1.00 ls 4,295,000 4,295,000

JUMLAH 64,237,000 II PEKERJAAN PONDASI

A PEKERJAAN GALIAN1. Galian pondasi 18.94 m3 108,000 2,045,952 2. Pemadatan Tanah 37.00 m2 36,000 1,332,000 3. Urugan Kembali Ex. Galian 16.46 m3 108,000 1,778,112 4. Pasir Urug Bawah Pondasi 3.70 m3 454,000 1,679,800 5. Pekerjaan Anti Rayap 37.00 m2 60,000 2,220,000

B PEKERJAAN PONDASI 1. Pekerjaan pondasi P1 2.48 m3 5,350,000 13,268,000 2. Pekerjaan pondasi P2 0.62 m3 5,350,000 3,295,600 3. Pekerjaan Sloof 4.35 m3 4,440,000 19,314,000

JUMLAH 44,933,464 III PEKERJAAN STRUKTUR

1. Kolom 15 X 15 0.93 m3 5,360,000 4,984,800 2. Kolom Praktis 102.00 m' 86,400 8,812,800 3. Ringbalk 10 x 15 2.04 m3 4,850,000 9,894,000 4. Plat atap 60.00 m2 415,000 24,900,000

JUMLAH 48,591,600 IV PEKERJAAN SEPTIC TANK

1. M3 Galian tanah 6.50 84,000 546,000 2. M3Urug kembali tanah (1/4 galian) 2.00 36,000 72,000 1. M3 Pasang batu bata 1:2 1.50 1,241,000 1,861,500 2. M2 Plesteran 1:2 14.50 84,000 1,218,000 1. Beton tumbuk 1:2:3. 0.35 1,182,000 413,700 2. M3 Beton bertulang 123 0.10 5,309,000 530,900 1. Kerikil keringan 0.75 358,000 268,500 2. M3 Pasir saringan 1.00 418,000 418,000 1. M' Pasang pipa besi O 2" 0.50 60,000 30,000 2. M' Pasang pipa PVC O 15 Cm 2.50 227,000 567,500 1. Kg Ijuk Saringan 10.00 12,000 120,000 2. Alat - alat bantu 1.00 60,000 60,000

JUMLAH 6,106,100 total 163,868,164

LANTAI DASAR ( EL. ± 0.00)

Page 4: Penawaran jkJagakarsa

RENCANA ANGGARAN BIAYA

Project : Hotel Maven Fatmawati Subyek : PEKERJAAN M & E Total Area : ± 324.00

Rp 180,025.62

NO DESCRIPTION UNIT PRICE JUMLAH

vol. SAT (kg) (Rp.) (Rp.)

1 2 3 4 5 6

I PEMASANGAN PANEL1 PANEL PENERANGAN

A LANTAI DASAR ( EL. ± 0.00)- Panel box (800x600x250) mm 1.00 bh 3,300,000 3,300,000 - Busbar+Wiring Material 1.00 lot 2,340,000 2,340,000 Input- MCB 3P 80 A 1.00 bh 990,000 990,000 MCCB in 3P, 100AF/63AT, 25kA 1.00 Bh 779,400 779,400 MCB out 3P, 20A, 10 kA 3.00 Bh 360,000 1,080,000 - Pilot Lamp Tlmq+MCB 1P 2A 3.00 set 96,600 289,800 Output- MCB 3P 32A 4.00 bh 390,000 1,560,000

JUMLAH 10,339,200 II ELEKTRIKALA LANTAI DASAR ( EL. ± 0.00)

1 INSTALASI PENERANGAN/LAMPU LT-2A Installasi

1. Lampu drop ceiling LED T 8 20.00 ttk 156,000 3,120,000 2. Lampu dinding 12 W 3.00 bh 156,000 468,000 3. Lampu taman 3.00 ttk 156,000 468,000 4. Down Light 18 W 67.00 ttk 156,000 10,452,000 5. stop kontak 31.00 ttk 144,000 4,464,000 6. Stop kontak AC 5.00 bh 144,000 720,000 7. Saklar ganda 17.00 bh 144,000 2,448,000

B Material1. Lampu drop ceiling LED T 8 20.00 bh 174,000 3,480,000 2. Lampu dinding 12 W 3.00 bh 150,000 450,000 3. Lampu taman 3.00 bh 240,000 720,000 4. Down Light 18 W 67.00 bh 84,000 5,628,000 5. stop kontak 31.00 bh 27,600 855,600 6. Stop kontak AC 5.00 bh 30,000 150,000 7. Saklar ganda 17.00 bh 30,000 510,000

JUMLAH 33,933,600 III PEKERJAAN PLUMBING

A INSTALASI PLUMBING LANTAI . DASAR1 Instalasi Pipa Air bersih Lt . Dasar a. Pipa PVC, Class AW Standard JIS K 6741/2, 10 Kg/cm2, etc.

Ø 1 1/2" 127.00 m' 25,000 3,175,000 Ø 3/4" 55.00 m' 27,500 1,512,500 b. Tee Gip Medium

- Tee Ø 1 1/2" 4.00 bh 7,500 30,000 - Tee Ø 1 1/2 x 3/4" 7.00 bh 3,500 24,500

c. Reducer Gip Medium - - Red. Ø 2 x 1 1/4" 4.00 bh 9,000 36,000

Page 5: Penawaran jkJagakarsa

NO DESCRIPTION UNIT PRICE JUMLAH

vol. SAT (kg) (Rp.) (Rp.)

1 2 3 4 5 6- Red. Ø 1 1/4 x 3/4" 20.00 bh 3,500 70,000

d. Brown Valve (Type Gate Valve/Flange End, Float Valve, Clas 150 Lbs, Std. ANSI/MSS, etc.)- Gate Valve Ø 1 1/4" 3.00 bh 75,000 225,000

e. Fittings, Class MediumStandard SNI-0039.87 / BS-1387-67, etc.Elbow 90 o- Elbow Ø 1 1/2" 10.00 bh 6,500 65,000 - Elbow Ø 3/4 " 40.00 bh 2,500 100,000

f. Kran Taman- Ø 1/2 " 3.00 bh 31,000 93,000

2 Instalasi Pipa Air kotor Lt . Dasara. Pipa PVC, Class AW

Standard JIS K 6741/2, 10 Kg/cm2, etc. Ø 4" 45.00 m' 88,000 3,960,000

Ø 3" 58.00 m' 60,000 3,480,000 b. Fittings, Class AW

Standard JIS K 6745 / K 6739, etc.Elbow 90 o- Elbow Ø 4" 4.00 bh 28,000 112,000 - Elbow Ø 3" 9.00 bh 13,500 121,500

c. Tee y, Pvc Class AWStandard JIS K 6745 / K 6739, etc.- Tee Ø 4 x 4 " 4.00 bh 51,000 204,000 - Tee Ø 3 x 3" 3.00 bh 50,000 150,000 - Tee Ø 2 1/2 x 2 1/2 " 2.00 bh 13,000 26,000

d. Tee T, Pvc Class AWStandard JIS K 6745 / K 6739, etc.- Tee Ø 4 x 4 " 3.00 bh 51,000 153,000 - Tee Ø 3 x 3" 5.00 bh 50,600 253,000

e. reducer , Pvc Class AWStandard JIS K 6745 / K 6739, etc.- Ø 3x 2 " 3.00 bh 19,000 57,000

f. P trap - Ø 4" 4.00 bh 16,000 64,000

g. Clean out - Ø 4" 6.00 bh 24,000 144,000

JUMLAH 14,055,500 TOTAL 58,328,300

Page 6: Penawaran jkJagakarsa

RENCANA ANGGARAN BIAYA

Project : RUMAH JAGAKARSASubyek : PEKERJAAN AREA SERVISTotal Area : ± 27.50Average Project Cost / Sqm : 2,718,023

NO DESCRIPTION UNIT PRICE JUMLAH

vol. SAT (kg) (Rp.) (Rp.)

1 2 3 4 5 6

I PEKERJAAN PONDASIA PEKERJAAN GALIAN

1. Galian pondasi 1.70 m3 108,000 183,600 2. Pemadatan Tanah 37.00 m2 36,000 1,332,000 3. Urugan Kembali Ex. Galian 1.30 m3 108,000 140,400

B PEKERJAAN PONDASI 1. Pekerjaan pondasi P2 0.36 m3 5,350,000 1,926,000 2. Pekerjaan Sloof 0.62 m3 4,440,000 2,747,250

JUMLAH 6,329,250 II PEKERJAAN STRUKTUR

1. Kolom 15 X 15 0.19 m3 5,360,000 996,960 2. Kolom Praktis 6.40 m' 86,400 552,960 3. Ringbalk 10 x 15 0.25 m3 4,850,000 1,200,375 4. Tangga putar 1.00 lot 3,200,000 3,200,000 5. Plat atap 24.00 m2 415,000 9,960,000

JUMLAH 15,910,295 III PEKERJAAN DINDING

1. Dinding bata merah 1/2 BT. ad 1 : 4 60.00 m2 132,000 7,920,000 2. Plester 1 : 4 154.80 m2 71,000 10,990,800 3. Keramik Dinding KM 20/20cm setara Roman 16.17 m2 122,000 1,972,740 4. Plint Dinding 32.00 m' 72,000 2,304,000

JUMLAH 23,187,540 IV PEKERJAAN KUSEN DAN PINTU

1. Pintu & Kusen kayu 1 Daun 2.00 bh. 3,000,000 6,000,000 2. Pintu KM 1.00 bh. 2,800,000 2,800,000

JUMLAH 8,800,000 V PEKERJAAN PLAFOND

1. Plafon gypsum 9 mm 27.50 m2 117,500 3,231,250 2. Cornice alumunium U 25.00 m' 18,000 450,000

JUMLAH 3,681,250 VI PEKERJAAN LANTAI

1. Pemadatan tanah 27.50 m2 72,000 1,980,000 2. Screeding + lantai kerja Screeding lantai 3 cm 27.50 m2 64,000 1,760,000 3. Homogeneus Ceramic tile 30 x 30 R. Tidur utama 27.50 m2 135,000 3,712,500

JUMLAH 7,452,500 VII PEKERJAAN FINISHING DAN CAT

1. Pekerjaan Cat dinding luar, ex Nippon paint 51.90 m2 22,000 1,141,800 2. Pekerjaan Cat dinding dalam, ex Nippon paint 57.00 m2 18,000 1,026,000 3. Pekerjaan cat plafond 27.00 m2 18,000 486,000

JUMLAH 2,653,800 VIII PEKERJAAN SANITARI

1. WC Jongkok 1.00 bh. 500,000 500,000 2. Floor Drain 1.00 bh. 251,000 251,000 3. Kran air 2.00 bh. 72,000 144,000 4. Floor Drain 1.00 bh. 310,000 310,000

JUMLAH 1,205,000 IX PEKERJAAN PLUMBING + Septic tank

1. Pekerjaan plumbing 1.00 lot 560,000 560,000 2. Pekerjaan Septic tank 1.00 lot 3,150,000 3,150,000

JUMLAH 3,710,000 X PEKERJAAN ME

1. Lampu downlight 5.00 lot 227,000 1,135,000 2. Saklar Ganda 3.00 lot 227,000 681,000

JUMLAH 1,816,000 total 74,745,635

LANTAI DASAR ( EL. ± 0.00)

Page 7: Penawaran jkJagakarsa

RENCANA ANGGARAN BIAYA

Project : RUMAH JAGAKARSASubyek : PEKERJAAN GAZEBO MUSHOLLATotal Area : ± 23.00Average Project Cost / Sqm : 1,028,013.04

NO DESCRIPTION Harga JUMLAH

vol. SAT Satuan (kg) (Rp.) (Rp.)

1 2 3 4 5 6

I PEKERJAAN PONDASIA PEKERJAAN GALIAN

1. Galian pondasi 0.50 m3 108,000 54,000 2. Pemadatan Tanah 37.00 m2 36,000 1,332,000

B PEKERJAAN PONDASI 1. Pekerjaan pondasi umpak batu kali 0.20 m3 1,862,000 372,400 2. Pekerjaan Sloof 0.53 m3 5,297,000 2,780,925

JUMLAH 4,539,325 II PEKERJAAN STRUKTUR

1. Kolom 15 X 15 0.28 m3 6,395,000 1,784,205 2. Ringbalk 10 x 15 0.21 m3 5,787,000 1,215,270

JUMLAH 2,999,475 III PEKERJAAN ATAP

1. Rangka atap baja ringan 21.00 m2 145,000 3,045,000 2. Alumunium foil 21.00 m2 12,000 252,000 3. Genteng penutup atap, ex genteng mutiara 21.00 m2 132,000 2,772,000 4. Listplank 20.00 m' 120,000 2,400,000 5. Cat listplank 20.00 m' 36,000 720,000

JUMLAH 9,189,000 IV PEKERJAAN PLAFOND

1. Plafon gypsum 9 mm 23.00 m2 117,500 2,702,500 2. Cornice alumunium U 25.00 m' 18,000 450,000

JUMLAH 3,152,500 V PEKERJAAN LANTAI

1. Homogeneus Ceramic tile 40 x 40 15.00 m2 145,000 2,175,000 JUMLAH 2,175,000

VI PEKERJAAN SANITARI1. Kran air 2.00 bh. 72,000 144,000 2. Floor Drain 1.00 bh. 310,000 310,000

JUMLAH 454,000 VII PEKERJAAN ME

1. Lampu downlight 4.00 lot 227,000 908,000 2. Saklar Ganda 1.00 lot 227,000 227,000

JUMLAH 1,135,000 total 23,644,300

LANTAI DASAR ( EL. ± 0.00)

Page 8: Penawaran jkJagakarsa

I PEKERJAAN PAGAR KELILING1. Pondasi batu kali 37.50 m3 792,000 29,700,000 2. Sloof 144.00 bh. 93,500 13,464,000 3. Kolom Praktis 125.00 m' 79,200 9,900,000 4. Pagar batako 360.00 m2 132,000 47,520,000 5. Ring balk 144.00 bh. 93,500 13,464,000

JUMLAH 114,048,000 TOTAL 114,048,000

Page 9: Penawaran jkJagakarsa

REKAPITULASI BIAYA

NAMA KEGIATAN : REKAP TOTAL NO KODE : 0

NO JENIS PEKERJAAN SUB TOTAL TOTAL

1 PEKERJAAN ARSITEKTURAL 612,041,570

2 PEKERJAAN STRUKTUR 163,868,164

3 PEKERJAAN M & E 58,328,300

4 PEKERJAAN AREA SERVIS 74,745,635

5 PEKERJAAN GAZEBO MUSHOLLA 23,644,300

932,627,969

LUAS BANGUNAN = 324 Harga konstruksi /m2 = 2,878,481

NoteLuas Bangunan Utama = 270 Luas Mezanin R. Tidur 3 &4 = 12 Luas bangunan Servis = 20 Luas Gazebo Musholla = 22

total 324

Page 10: Penawaran jkJagakarsa

NO DESCRIPTION BOBOT OKTOBER

vol. SAT 2 (kg) (Rp.) M-1

ARSITEKTURI PEKERJAAN PERSIAPAN

1. Pengukuran 1.00 ls 0.30 2. Dokumentasi & Administrasi 1.00 ls 0.18 3. Bedeng pekerja + gudang 30.00 m2 2.33 4. Pas. Bauwplak 103.00 m' 1.23 5. Mobilisasi & Demobilisasi Alat Kerja 1.00 ls 0.95 6. Kebersihan Lokasi Kerja 1.00 ls 0.36

JUMLAHII PEKERJAAN PONDASI

A PEKERJAAN GALIAN1. Galian pondasi 18.94 m3 0.17 2. Pemadatan Tanah 37.00 m2 0.11 3. Urugan Kembali Ex. Galian 16.37 m3 0.15 4. Pasir Urug Bawah Pondasi 3.70 m3 0.14 5. Pekerjaan Anti Rayap 37.00 m2 0.18

B PEKERJAAN PONDASI 1. Pekerjaan pondasi P1 2.57 m3 1.37 2. Pekerjaan pondasi P2 0.61 m3 0.33 3. Pekerjaan Sloof 5.89 m3 2.60

JUMLAHIII PEKERJAAN STRUKTUR

1. Kolom 15 X 15 2.79 m3 1.49 2. Kolom Praktis 114.00 m' 1.02 3. Ringbalk 10 x 15 2.34 m3 1.13 4. Plat atap 118.00 m2 5.05 5. Atap penutup tangga putar 6.00 m2 0.39

JUMLAHIV PEKERJAAN SEPTIC TANK

1. M3 Galian tanah 6.50 0.05 2. M3Urug kembali tanah (1/4 galian) 2.00 0.01 1. M3 Pasang batu bata 1:2 1.50 0.16 2. M2 Plesteran 1:2 14.50 0.10 1. Beton tumbuk 1:2:3. 0.35 0.03 2. M3 Beton bertulang 123 0.10 0.04 1. Kerikil keringan 0.75 0.02 2. M3 Pasir saringan 1.00 0.03 1. M' Pasang pipa besi O 2" 0.50 0.00

LANTAI DASAR ( EL. ± 0.00)

Page 11: Penawaran jkJagakarsa

2. M' Pasang pipa PVC O 15 Cm 2.50 0.05 1. Kg Ijuk Saringan 10.00 0.01 2. Alat - alat bantu 1.00 0.00

JUMLAHI PEKERJAAN DINDING

1. Dinding bata merah 1/2 BT. ad 1 : 2 133.69 m2 1.69 2. Plester 1 : 2 133.69 m2 0.81 3. Dinding bata merah 1/2 BT. ad 1 : 4 298.60 m2 3.78 4. Plester 1 : 4 488.29 m2 2.94 5. Keramik Dinding KM 20/20cm setara Roman 101.42 m2 1.97 6. Plint Dinding 176.20 m2 0.99

JUMLAHII PEKERJAAN KUSEN DAN PINTU

1. Pintu & kusen kayu 2 Daun, Pintu utama (P1) 1.00 bh. 0.48 2. Pintu & kusen kayu, panel kaca 8 mm, Pintu r tidur ( 5.00 bh. 1.55 3. Pintu & Kusen kayu 1 Daun (P3) 8.00 bh. 2.29 4. Pintu KM (P4) 2.00 bh. 0.67 5. Jendela r tidur utama (J1) 1.00 bh. 0.64 6. Jendela r tidur 3 + 4 (J1) 2.00 bh. 1.29 7. Jendela r makan (J2) 4.00 bh. 2.58 8. Jendela r Tamu & keluarga (J3) 4.00 bh. 2.58 9. Kusen kayu + kaca lantai loteng kamar 5 + 6 2.00 bh. 0.99

JUMLAHIII PEKERJAAN PLAFOND

1. Plafon gypsum 9 mm 371.00 m2 4.06 2. Drop Ceiling 55.00 m' 0.33 3. Cornice alumunium U 234.00 m' 0.70

JUMLAHIV PEKERJAAN LANTAI

1. Pemadatan tanah 54.60 m2 0.33 2. Rolaag lantai 44.00 m' 0.39 3. Screeding + lantai kerja Screeding lantai 3 cm 273.00 m2 1.90 4. Homogeneus Ceramic tile 60 x 60 R. Tamu & keluarg 42.00 m2 1.17 5. Homogeneus Ceramic tile 40 x 40 R. Tidur utama 26.50 m2 0.66 6. Homogeneus Ceramic tile 40 x 40 r. Tidur 1 & 2 32.50 m2 0.81 7. Homogeneus Ceramic tile 40 x 40 r. Tidur 3 & 4 35.00 m2 0.87 8. Homogeneus Ceramic tile 40 x 40 . Makan + dapur 29.00 m2 0.72 9. Homogeneus Ceramic tile 40 x 40 teras 13.00 m2 0.32

10. Homogeneus Ceramic tile 40 x 40 R.selasar 65.00 m2 1.62 11. Homogeneus Ceramic tile 20 x 20 KM 19.50 m2 0.39 12. Parquette mezanin R. Tidur 3&4 43.00 m2 1.09 13. batu alam 10 x10 R.selasar samping 20.00 m2 0.40

JUMLAHV PEKERJAAN FINISHING DINDING

1. Keramik dinding KM 101.20 m2 2.01 2. Batu alam dinding muka 14.40 m2 0.26 3. Pekerjaan Tangga kayu R tidur 3&4 2.00 unit 0.40

JUMLAHV PEKERJAAN PENGECATAN

1. Pekerjaan Cat dinding luar, ex ICI Dulux Weathershi 305.80 m2 0.91

Page 12: Penawaran jkJagakarsa

2. Pekerjaan Cat dinding dalam, ex ICI Dulux 428.68 m2 0.85 3. Pekerjaan cat plafond 371.00 m2 0.74

JUMLAHVI PEKERJAAN ATAP

1. Rangka atap baja ringan 408.00 m2 6.09 2. Alumunium foil 408.00 m2 0.41 3. Genteng penutup atap, ex genteng mutiara 408.00 m2 4.46 4. Listplank 170.00 m' 1.69 5. Cat listplank 170.00 m' 0.51

JUMLAHVII PEKERJAAN SANITARI

1. Monoblock Amstard + Accesories 6.00 bh. 1.56 2. Wash basin Amstard + Accesories 6.00 bh. 1.03 3. Shower head + kran 6.00 bh. 0.23 4. Floor Drain 12.00 bh. 0.25

JUMLAHVIII PEKERJAAN PAGAR KELILING

1. Pondasi batu kali 37.50 m3 - 2. Sloof 144.00 bh. - 3. Kolom Praktis 125.00 m' - 4. Pagar batako 360.00 m2 - 5. Ring balk 144.00 bh. -

JUMLAHI PEMASANGAN PANEL

1 PANEL PENERANGANA LANTAI DASAR ( EL. ± 0.00)

- Panel box (800x600x250) mm 1.00 bh 0.33 - Busbar+Wiring Material 1.00 lot 0.23 Input - - MCB 3P 80 A 1.00 bh 0.10 MCCB in 3P, 100AF/63AT, 25kA 1.00 Bh 0.08 MCB out 3P, 20A, 10 kA 6.00 Bh 0.21 - Pilot Lamp Tlmq+MCB 1P 2A 3.00 set 0.03 Output - - MCB 3P 32A 4.00 bh 0.16

JUMLAHII ELEKTRIKALA LANTAI DASAR ( EL. ± 0.00)

1 INSTALASI PENERANGAN/LAMPU LT-2A Installasi

1. Lampu drop ceiling LED T 8 20.00 ttk 0.32 2. Lampu dinding 12 W 3.00 bh 0.05 3. Lampu taman 3.00 ttk 0.05 4. Down Light 18 W 67.00 ttk 1.07 5. stop kontak 31.00 ttk 0.46 6. Stop kontak AC 5.00 bh 0.07 7. Saklar ganda 17.00 bh 0.25

B Material

Page 13: Penawaran jkJagakarsa

1. Lampu drop ceiling LED T 8 20.00 bh 0.36 2. Lampu dinding 12 W 3.00 bh 0.04 3. Lampu taman 3.00 bh 0.07 4. Down Light 18 W 67.00 bh 0.60 5. stop kontak 31.00 bh 0.09 6. Stop kontak AC 5.00 bh 0.01 7. Saklar ganda 17.00 bh 0.05

JUMLAHIII PEKERJAAN PLUMBING

A INSTALASI PLUMBING LANTAI . DASAR1 Instalasi Pipa Air bersih Lt . Dasar a. Pipa PVC, Class AW Standard JIS K 6741/2, 10 Kg/cm2, etc.

Ø 1 1/2" 127.00 m' 0.38 Ø 3/4" 55.00 m' 0.16 b. Tee Gip Medium

- Tee Ø 1 1/2" 4.00 bh 0.00 - Tee Ø 1 1/2 x 3/4" 7.00 bh 0.01

c. Reducer Gip Medium- Red. Ø 2 x 1 1/4" 4.00 bh 0.00 - Red. Ø 1 1/4 x 3/4" 20.00 bh 0.02

d. Brown Valve (Type Gate Valve/Flange End, Float Valve, Clas 150 Lbs, Std. ANSI/MSS, etc.)- Gate Valve Ø 1 1/4" 3.00 bh 0.02

e. Fittings, Class MediumStandard SNI-0039.87 / BS-1387-67, etc.Elbow 90 o- Elbow Ø 1 1/2" 10.00 bh 0.01 - Elbow Ø 3/4 " 40.00 bh 0.04

f. Kran Taman- Ø 1/2 " 3.00 bh 0.01

2 Instalasi Pipa Air kotor Lt . Dasara. Pipa PVC, Class AW

Standard JIS K 6741/2, 10 Kg/cm2, etc. Ø 4" 45.00 m' 0.45

Ø 3" 58.00 m' 0.40 b. Fittings, Class AW

Standard JIS K 6745 / K 6739, etc.Elbow 90 o- Elbow Ø 4" 4.00 bh 0.01 - Elbow Ø 3" 9.00 bh 0.02

c. Tee y, Pvc Class AWStandard JIS K 6745 / K 6739, etc.- Tee Ø 4 x 4 " 4.00 bh 0.02 - Tee Ø 3 x 3" 3.00 bh 0.02 - Tee Ø 2 1/2 x 2 1/2 " 2.00 bh 0.004

d. Tee T, Pvc Class AWStandard JIS K 6745 / K 6739, etc.- Tee Ø 4 x 4 " 3.00 bh 0.02 - Tee Ø 3 x 3" 5.00 bh 0.03

Page 14: Penawaran jkJagakarsa

e. reducer , Pvc Class AWStandard JIS K 6745 / K 6739, etc.- Ø 3x 2 " 3.00 bh 0.01

f. P trap - Ø 4" 4.00 bh 0.01

g. Clean out - Ø 4" 6.00 bh 0.02

JUMLAH I PEKERJAAN PONDASI

A PEKERJAAN GALIAN1. Galian pondasi 3.58 m3 0.03 2. Pemadatan Tanah 37.00 m2 0.11 3. Urugan Kembali Ex. Galian 3.24 m3 0.03 4. Pasir Urug Bawah Pondasi 3.70 m3 0.14 5. Pekerjaan Anti Rayap 37.00 m2 0.18

B PEKERJAAN PONDASI 1. Pekerjaan pondasi P1 0.34 m3 0.18

Pekerjaan pondasi P2 0.15 m3 0.08 2. Pekerjaan Sloof 1.24 m3 0.55

JUMLAHII PEKERJAAN STRUKTUR

1. Kolom 15 X 15 0.28 m3 0.15 2. Kolom Praktis 21.00 m' 0.19 3. Ringbalk 10 x 15 0.45 m3 0.22 4. Tangga putar 1.00 lot 0.27 5. Plat atap 34.00 m2 1.45

JUMLAHIII PEKERJAAN DINDING

1. Dinding bata merah 1/2 BT. ad 1 : 4 52.20 m2 0.67 2. Plester 1 : 4 139.20 m2 0.97 3. Keramik Dinding KM 20/20cm setara Roman 15.48 m2 0.20 4. Plint Dinding 25.00 m' 0.15

JUMLAHIV PEKERJAAN KUSEN DAN PINTU

1. Pintu & Kusen kayu 1 Daun 2.00 bh. 0.64 2. Pintu KM 1.00 bh. 0.30

JUMLAHV PEKERJAAN PLAFOND

1. Plafon gypsum 9 mm 27.50 m2 0.30 2. Cornice alumunium U 25.00 m' 0.07

JUMLAHVI PEKERJAAN LANTAI

1. Pemadatan tanah 27.50 m2 0.16 2. Screeding + lantai kerja Screeding lantai 3 cm 27.50 m2 0.19 3. Homogeneus Ceramic tile 30 x 30 R. Tidur 27.50 m2 0.46

JUMLAHVII PEKERJAAN FINISHING DAN CAT

1. Pekerjaan Cat dinding luar, ex ICI Dulux Weathershi 38.40 m2 0.11

LANTAI DASAR ( EL. ± 0.00)

Page 15: Penawaran jkJagakarsa

2. Pekerjaan Cat dinding dalam, ex ICI Dulux 108.00 m2 0.21 3. Pekerjaan cat plafond 31.00 m2 0.06

JUMLAHVIII PEKERJAAN SANITARI

1. WC Jongkok 1.00 bh. 0.04 2. Floor Drain 1.00 bh. 0.02 3. Kran air 2.00 bh. 0.01 4. Floor Drain 1.00 bh. 0.03

JUMLAHIX PEKERJAAN PLUMBING + Septic tank

1. Pekerjaan plumbing 1.00 lot 0.12 2. Pekerjaan Septic tank 2.00 lot 0.53

JUMLAHX PEKERJAAN ME

1. Lampu downlight 7.00 lot 0.13 2. Saklar Ganda 3.00 lot 0.06

JUMLAHI PEKERJAAN PONDASI

A PEKERJAAN GALIAN1. Galian pondasi 0.50 m3 0.00 2. Pemadatan Tanah 37.00 m2 0.11

B PEKERJAAN PONDASI 1. Pekerjaan pondasi umpak batu kali 0.20 m3 0.03 2. Pekerjaan Sloof 0.53 m3 0.23

JUMLAHII PEKERJAAN STRUKTUR

1. Kolom 15 X 15 0.28 m3 0.15 2. Ringbalk 10 x 15 0.21 m3 0.10

JUMLAHIII PEKERJAAN ATAP

1. Rangka atap baja ringan 21.00 m2 0.31 2. Alumunium foil 21.00 m2 0.02 3. Genteng penutup atap, ex genteng mutiara 21.00 m2 0.23 4. Listplank 20.00 m' 0.20 5. Cat listplank 20.00 m' 0.06

JUMLAHIV PEKERJAAN PLAFOND

1. Plafon gypsum 9 mm 23.00 m2 0.25 2. Cornice alumunium U 25.00 m' 0.07

JUMLAHV PEKERJAAN LANTAI

1. Homogeneus Ceramic tile 40 x 40 15.00 m2 0.37 JUMLAH

VI PEKERJAAN SANITARI1. Kran air 2.00 bh. 0.01 2. Floor Drain 1.00 bh. 0.03

JUMLAHVII PEKERJAAN ME

LANTAI DASAR ( EL. ± 0.00)

Page 16: Penawaran jkJagakarsa

1. Lampu downlight 4.00 lot 0.08 2. Saklar Ganda 1.00 lot 0.02

JUMLAH

100.00

Page 17: Penawaran jkJagakarsa

OKTOBER NOV DEC JAN2 3 4 1 2 3 4 1 2 3 4 1

M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12

Page 18: Penawaran jkJagakarsa
Page 19: Penawaran jkJagakarsa
Page 20: Penawaran jkJagakarsa
Page 21: Penawaran jkJagakarsa
Page 22: Penawaran jkJagakarsa
Page 23: Penawaran jkJagakarsa
Page 24: Penawaran jkJagakarsa

JAN FEB MAR1 2 3 4 1 2 3 4 1 2 3 4

M-12 M-13 M-14 M-15 M-16 M-17 M-18 M-19 M-20 M-21 M-22 M-23

Page 25: Penawaran jkJagakarsa

MAR APRIL MEI JUNI4 1 2 3 4 1 2 3 4 1 2

M-23 M-24 M-25 M-26 M-27 M-28 M-29 M-30 M-31 M-32 M-33

Page 26: Penawaran jkJagakarsa

JUNI3 4

M-34 M-35