otc asia 2014 petronas

26
OTC-24721-MS A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field John R Wright Jr. Polyflow LLC, Khairul Anuar Karim, PETRONAS Carigali and Steve Kennedy, SCG Oil and Gas

Upload: steven-kennedy

Post on 10-Feb-2017

309 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: OTC Asia 2014 Petronas

OTC-24721-MS

A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow

Line in the East Malaysia Samarang Field

John R Wright Jr. Polyflow LLC, Khairul Anuar Karim, PETRONAS Carigali and Steve

Kennedy, SCG Oil and Gas

Page 2: OTC Asia 2014 Petronas

Agenda

1) Background 2) Steps and Analysis for Successful Rehabilitation 3) Details of the Installation 4) Benefits Analysis 5) Areas for Improvement 6) Q & A

Slide 2

OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,

Kennedy

Page 3: OTC Asia 2014 Petronas

Background

• PL-112 Pipeline • 52 Km off Labuan in Samarang Field • 8-10 Meters of Water • 6” API -5L X-42 Steel Pipe Installed in 1977 • Approximately 1Kilometer

• Anchor Hooked Pipe Causing a Kink in 2009 • Repairs Made with Misalignment Flanges • Difficulty in Maintenance and Loss of Wall Thickness

Concluded Repairs as Temporary • Current Infield Drilling

• Required New Pipeline for Next 25 Years • New Steel Pipeline Replacement and Reinforced Thermoplastic

Pipe Rehabilitation were Evaluated • Future Flowing Conditions

• 1,800bbl – 5,000bbl/day Depending upon Field Requirements • Concern with SRB’s in Future • Low Formation Pressure

OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,

Kennedy

Page 4: OTC Asia 2014 Petronas

Analysis and Planning Steps for RTP Rehab

• Sizing of the New Flow Line • Material Selection • Pull Force Analysis • Selection of Pulling Equipment • Detailed Layout of Project

OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,

Kennedy

Page 5: OTC Asia 2014 Petronas

Proper Sizing of Pipe Slide 5

• Sized for Desired Production Fits Inside of Existing Steel Acceptable Pressure Drop

for Formation Ideally Fits Through Existing

Risers • Design for Maintaining

Minimum Velocities 0.61m/s will Carry Solids in

Liquids Reduces Ongoing

Maintenance (Pigging) • Selected 3.5” RTP (2.95” ID)

Acceptable Pressure Drops Minimal Velocities for Range

of Flow Risers Have to be Modified

Modified Riser with 12D Bend

OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,

Kennedy

Existing Riser with 5D Bend

Page 6: OTC Asia 2014 Petronas

Pressure Drops and Critical Velocities for 3.5” RTP

Velocity at 1,800bbl/day is 2 ft./sec (0.61 m/sec)

Typical Production Volume Pressure Drop of 15.3 psi @ 1,800bbl/day

Maximum Production Pressure drop 96.4 psi @ 5,000bbl/day

OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,

Kennedy

Page 7: OTC Asia 2014 Petronas

Material Selection

• RTP Components Inner Liner- Fluid Compatibility Reinforcement- Strength Jacket- Protects Reinforcement

• Liner- PPS/Fortron Hydrocarbon CO2, H2S, Brine

Resistance (Norsok 710 Testing) Low Permeation

• Reinforcement - Aramid/Twaron Static/Cyclic Strength Resistance to the Environment

• Outer Jacket- Nylon Abrasion Resistance Hydrocarbon Resistance

Aramid Reinforcement

PPS Liner

Volume (%) Composition 30 3% CO2, 2% H2S, 95% CH4 10 Distilled water (conductivity < 5 µS) 60 70% heptane, 20% cyclohexane, 10% toluene

Composition of NORSOK M710 Solution

OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,

Kennedy

Nylon Jacket

RTP Components

Page 8: OTC Asia 2014 Petronas

Chemical Resistance and Permeation of PPS/Fortron

30

35

40

45

50

55

60

0 20 40 60 80 100 120

190C170C160C150C

Tensile Strength of Fortron PPS (MPa) as a function of Ageing (Days) from 140-190C

OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,

Kennedy

Page 9: OTC Asia 2014 Petronas

OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,

Kennedy

Pre-Planning Project Layout

Spool off Location

Riser Termination

Page 10: OTC Asia 2014 Petronas

Project Pre-planning

• Gauging Pig for Existing Line • Pull Force Analysis

• Wet vs. Dry • 1,818 Kg Pull Force Wet • Synthetic Rope (5X Safety Factor)

• Project Layout • Platform Space vs. Boat • Individual Steps • Responsible Party • Underwater Work

• Riser Bottom Bend Modifications • Subsea Bend Modification

• Top Side Spools Modifications • Project Scheduling • Capabilities of Platform Equipment

OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,

Kennedy

Page 11: OTC Asia 2014 Petronas

OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,

Kennedy

Platform A Platform B Existing Pipeline Plastic Insert Pipe Messenger Pig

Cross-section

Messenger pig

Winch Spool Reel

Installation Method: Planning

Page 12: OTC Asia 2014 Petronas

OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,

Kennedy

Installation Method: Planning

Winch

Existing Pipeline Plastic Insert Pipe Messenger Pig

Spool Reel

Cross-section

Plastic Insert Pipe

Platform A Platform B

Page 13: OTC Asia 2014 Petronas

Messenger wire

Winch

Platform A Platform B

Cross-section

Existing PL 112 Plastic Insert Pipe Messenger Wire

OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,

Kennedy

Installation Method: Actual

Page 14: OTC Asia 2014 Petronas

Winch

Platform A Platform B

Cross-section

Existing PL 112 Plastic Insert Pipe Messenger Wire

OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,

Kennedy

Installation Method: Actual

Spool Reel

Vessel

Plastic Insert Pipe

Page 15: OTC Asia 2014 Petronas

Installing the RTP

• Cleaning the Line – Scrape Both Directions

• Erect Scaffolding to Align Pipe from Boat

• Foam Pig Synthetic Rope Through Pipeline

• Set up Winch for Pulling • Align Pulleys over Flange Opening • Attach Pulling Cone to Pipe and

Cable

OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,

Kennedy

Erecting Scaffolding

Cleaning Activity for Existing Line RTP Pull Thru Activity

Page 16: OTC Asia 2014 Petronas

Pulling the RTP and Splice Joints

• Pull Rate – 20m/min • Cable Passed Through Load Cell

• Pull Force At Expected Value • Indicator for Hang-ups

• Spliced Couplings • 300 Meters Per Pipe Length • Duplex 2205 Joint Splices

• End Connections • Double Faced RTJ Flanged • Seal off Annular Space • Port on Annulus with Pressure Gage

Boat to Scaffold

OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,

Kennedy

RTP Pulling Activity

Jointing between two portions of RTP pipe Splice Coupling

Page 17: OTC Asia 2014 Petronas

Inspection of the RTP After Pull Through • Inspect Pulled RTP

• Inspect for Gouges & Jacket Breaches

• Deformation in Pipe • Cut to Length & Install

Termination • Hydro- Test at 2X MAOP for 24

Hours (360PSI) • Design Pressure – 1,440PSI

OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,

Kennedy

Final Pull Out of RTP

Final Spool Make-up Hydrotest Pressure Chart

Page 18: OTC Asia 2014 Petronas

Analysis of Benefits

• After One Year of Operation Flowing 1,800bb – 7,000bbl/day

• 7,000bbl/day Causing Excessive Back Pressure

No Chemical Treatment No Pigging/ Cleanout

• CAPEX 67% Lower than New Steel Line Eliminating Riser Modifications &

Pulling from Boat Creates 80+ % Savings

• Benefit to Environment compared to conventional steel replacement Minimum disturbance to seafloor &

marine life Reused of existing steel pipeline

• Existing Steel Line Remains Part of the System and is not Abandoned

OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,

Kennedy

Page 19: OTC Asia 2014 Petronas

Lessons Learned – Areas for Improvement

• Improvement in Planning • Changed from Platform to Platform vs Boat to Platform • Platform Deck Space Availability • Crane on Platform Inoperable

• Making Sure Continuous Back Tension on Pipe During Pulling • Sharp Changes in Tension can Kink Pipe

OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,

Kennedy

Kink Portion Observed During Pulling Activity

Page 20: OTC Asia 2014 Petronas

Lessons Learned – Areas for Improvement cont.

• Better Pulling Rope Design to Minimize Damage During Pulling • Nylon Jacket on Rope too Thin • Tore As Pulled Through Riser

• Rub on Sharp Flange • Wrinkling Create Hang-up • No Issue with Pipe

• Rope Broke 1 Meter from End of Pull – Finish with Cable

• Jacket Tears Hung Up in Load Cell

OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,

Kennedy

Final Pull Out of RTP

Wrinkling of Pulling Rope When Bent Damage layer of Pulling Rope

Page 21: OTC Asia 2014 Petronas

Lessons Learned – Areas for Improvement cont.

• Alternative Rope Designs • Heavier Nylon Jacket • Braided Jacket • Braided Jacket with Nylon Jacket

• Testing Ongoing

OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,

Kennedy

Page 22: OTC Asia 2014 Petronas

Acknowledgements

Slide 22

Special thanks to: a) P&E Management, PCSB b) SBO Management, PCSB - Maintenance & Operation, SBO c) Samarang Operations d) Technology Provider - Polyflow Inc. e) Contractors

Page 23: OTC Asia 2014 Petronas

Acknowledgements / Thank You / Questions

Slide 23

Page 24: OTC Asia 2014 Petronas

Appendix

Page 25: OTC Asia 2014 Petronas
Page 26: OTC Asia 2014 Petronas