PEMBANGUNAN GEDUNG PKSC - BORROMEUS

Januari – Juli 2016

METODE KERJA PRECASTPAKET 1 - PEKERJAAN PONDASI DALAM(INNER-BORE SYSTEM)

Page 2: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

OUTLINE

■ Lokasi Proyek

■ Scope yang diminta oleh Owner

■ Lingkup Pekerjaan

■ Gambar Denah

■ Alur Kerja

■ Metode Pelaksanaan Pondasi dengan Inner-Bore System

■ Time Schedule

■ Produktivitas

■ Dokumentasi

Page 3: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

LOKASI PROYEK

Lokasi Proyek St. Carolus

Page 4: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

FOTO SEBELUM PROYEK DIMULAI

Area Pintu Masuk Proyek

Page 5: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

Area Existing Proyek

FOTO SEBELUM PROYEK DIMULAI

Page 6: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

BATAS YANG DIMINTA OLEH OWNER

Page 7: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

LINGKUP PEKERJAAN

SCOPE

Persiapan

Inner Bore

Tiang Pancang

ø800 A1 (68 titik)

ø800 A0 (42 titik)

Ø1200 (96 titik)

(Total = 206 titik)

PC Wall (L=24,6 m) Elevasi -26,00

(Total = 304 titik ; total = 250 m’)

Test Inner Bore

(Test Keantledge)

Page 8: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

Konsep Daya Dukung Tiang Metode Inner

Bore (Hyper-NAKS).

Pada zona ini bekerja tahanan friksi tanah

eksisting.

Pada zona ini tahanan friksi tanah dengan

injeksi hardening liquid.

Pada zona ini tahanan ujung tanah dengan

injeksi base hardening liquid.

Page 9: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

St. CAROLUS HOSPITAL PROJECT - JAKARTA

Page 10: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

KONDISI LAPISAN TANAH (PROYEK RS

ST.CAROLUS)

Page 11: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

GAMBARAN PONDASI

INNER-BORE PILE DAN BORE PILE

Page 12: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

• Komparasi Pengurangan Jumlah Titik

(studi kasus Proyek St. Carolus)

Jlh Bore Pile dia. 800 mm = 306

titik

Sebelum

Value Engineering

Page 13: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

Jlh Titik Pancangdia. 800 mm = 110 ttk

dia. 1200 mm = 96 ttk

Total = 206 ttk

Setelah

Value Engineering

• Komparasi Pengurangan Jumlah Titik

(studi kasus Proyek St. Carolus)

Page 14: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

DENAH TIANG PANCANG DAN PC-WALL

■ Tiang Pancang

– Ø800 A0 = 42 batang

– Ø800 A1 = 68 batang

– Ø1200 A0 = 96 batang

■ PC-WALL

– 800 x 800 = 304 batang

TP DIA. 800 A0

Page 15: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

DENAH TIANG PANCANG DAN PC-WALL

■ Tiang Pancang

– Ø800 A0 = 42 batang

– Ø800 A1 = 68 batang

– Ø1200 A0 = 96 batang

■ PC-WALL

– 800 x 800 = 304 batang

TP DIA. 800 A1

Page 16: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

DENAH TIANG PANCANG DAN PC-WALL

■ Tiang Pancang

– Ø800 A0 = 42 batang

– Ø800 A1 = 68 batang

– Ø1200 A0 = 96 batang

■ PC-WALL

– 800 x 800 = 304 batang

TP DIA. 1200 A0

Page 17: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

• Pile Testing Result Using Static Load.

– Spun Dia. 1200mm (Carolus Salemba Project)

21

m

920 Ton –

200% Load

20.97 mm deformation

Page 18: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

Piling Perform- Location : St. Carolus Hospital, Salemba, Jakarta Pusat

Soil Log

Spun Pile Dia : 1200 mm;

L=11m

Tip level depth : -21 m

(prebore 12m)

Installed using Inner Bore

System

pre

bo

re

Page 19: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

Piling Perform- Location : St. Carolus Hospital, Salemba, Jakarta Pusat

Project : Rumah Sakit St. Carolus Salemba

Pile Number : 98 C74

Testing Standard : ASTM D1143/07

Loading System : Kentledge

Loading Procedure : Siklik

Pile Dia. 1200 mm

Test Load (100%) 460 Ton

Total Settlement 4.88 mm

Elastic Settlement 4.47 mm

Net Settlement 0.41 mm

Work Load (200%) 920 Ton

Total Settlement 18.14 mm

Elastic Settlement 12.79 mm

Net Settlement 5.35 mm

Page 20: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

Due to

prebore until

-12m with

diameter

auger same

as spun

diameter

Piling Perform- Location : St. Carolus Hospital, Salemba, Jakarta Pusat

Page 21: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

Piling Perform- Location : St. Carolus Hospital, Salemba, Jakarta Pusat

Spun Pile Dia. 1200 mm

Davisson Method :

Qult = 954 Ton

Mazurkiewich Method :

Qult = 1081 Ton

Chin Method :

Qult = 1333 Ton

Page 22: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …
Page 23: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

• Produk tiang pancang dibuat di

pabrik (mutu tersertifikasi).

• Getaran dan kebisingan yang dihasilkan relatif

rendah.

• Kebersihan lokasi proyek lebih terjamin (tanah

hasil galian ditampung pada hopper).

• Menggunakan teknologi beton mutu tinggi.

• Penampang hollow mengurangi pemakaian

material (komparasi dengan bore pile).

• Tidak perlu menggunakan casing.

• Kepastian dalam perencanaan

pondasi.

• Presisi dalam proses instalasi.

• Tepat digunakan pada area dengan

residensi tinggi (perkotaan).

Page 24: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

Lapisan Tanah Keras

Lapisan Tanah Lunak-Sedang

Zona Desain

Soket Proteksi

Ujung Tiang

Page 25: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

0. Setting Alat, Silo dan Mixer

Page 26: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

1. Persiapan Segmen Tiang Pancang dan Auger Set

(Screw & Drill Bit).

Tiang pancang

untuk segmen

bawah (bottom

pile) disiapkan

kemudian auger

set dimasukkan

kedalam sumbu

as tiang pancang.

Page 27: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

2. Marking Sumbu As Titik Instalasi Pondasi

Page 28: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

3. Install Tiang ke Alat Pancang

Page 29: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

4. Install Tiang ke Alat Pancang (cont’d)

Page 30: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

5. Set-Up Tiang pada Sumbu As Titik Pancang

Cek Posisi Tiang terhadap Sumbu as titik pancang dengan

bantuan mal/penggaris yang diberi selotip untuk memastikan

jarak yang tepat terhadap patok referensi.

Page 31: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

6. Set-Up Tiang pada Sumbu As Titik Pancang

Cek vertikalitas tiang dengan bantuan 2 theodolith pada arah sumbu yang

berbeda. Dan pastikan tiang harus tegak lurus dan sejajar dengan leader

pancang serta terus dimonitoring selama pemancangan berlangsung.

Adapun dengan cara Manual menggunakan Benang yang di bandul

tenggelam di air.

Page 32: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …
Page 33: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …
Page 34: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

Soil mobilized

Closed (Normal Mode) Drill Bit Auger

Page 35: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

Soil mobilized

Open (Expand Mode) Drill Bit Auger

Page 36: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

Soil mobilized

Page 37: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …
Page 38: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …
Page 39: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …
Page 40: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

DOKUMENTASI AKTIVITAS INNERBORE

Bottom Plate dengan Steel Collar

Pile Tip Socket Form

Page 41: METODE KERJA PAKET 1 PEKERJAAN PONDASI INNER-BORE …

TERIMA KASIH