kurva s
DESCRIPTION
contoh kurva sTRANSCRIPT
![Page 1: kurva s](https://reader036.vdokumen.com/reader036/viewer/2022081716/55309a48550346310f8b47e6/html5/thumbnails/1.jpg)
SATUAN KERJA : SNVT PELAKSANAAN JARINGAN PEMANFAATAN AIR SUMATERA - I
KEGIATAN : IRIGASI DAN RAWA-II
TAHUN ANGGARAN : 2012
SATUAN
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
0.175 0.175 0.175
0.046 0.046
0.134 0.134 0.134 0.134 0.134 0.134 0.134 0.134
II DAFTAR 2 : MATA PEMBAYARAN PEKERJAAN UTAMA
A PEKERJAAN SALURAN AIR
0.315 0.315
2.388 2.388 2.388 2.388 2.388 2.388 2.388 2.388
0.397 0.397 0.397 0.397
1.626 1.626 1.626 1.626
1.427 1.427 1.427 1.427 1.427
1.055 1.055 1.055 1.055
2.130 2.130 2.130 2.130 2.130 2.130 2.130 2.130 2.130 2.130 2.130
1.237 1.237 1.237 1.237
0.710 0.710
1.215 1.215
0.368 0.368
0.056 0.056 0.056 0.056 0.056 0.056 0.056 0.056 0.056 0.056 0.056
B PEKERJAAN BANGUNAN
0.033 0.033
0.110 0.110
0.014
1.689 1.689
0.327
0.238 0.238
0.705
0.494 0.494
0.023 0.023
10 Pintu sorong baja 2 (dua) draat stang/spindle 3 (tiga) set roda gigi
(pengadaan, sand blasting, printing, angkut dan pemasangan)
0.674 0.674
11 Pintu sorong baja 1 (satu) draat stang/spindle no gear
(pengadaan, sand blasting, printing, angkut dan pemasangan)
0.628 0.628
1.072 1.072
1.516 1.516
3.676 3.676
C
1.402 1.402 1.402
TOTAL BOBOT 3,264,323,119.48 100.00
Progres Rencana Mingguan (%) 0.18 0.22 0.36 2.70 2.39 2.39 2.39 2.39 4.01 4.01 5.57 5.37 3.61 4.67 4.80 3.37 4.46 3.77 4.63 4.66 3.85 4.67 3.08 10.47 8.98 1.40 1.40 0.18
Progres Rencana Komulatif Mingguan (%) 0.18 0.40 0.76 3.46 5.85 8.24 10.62 13.01 17.02 21.04 26.61 31.99 35.60 40.27 45.07 48.44 52.90 56.67 61.30 65.96 69.82 74.48 77.57 88.04 97.02 98.42 99.82 100.00
Banda Aceh, 02 Februari 2012
PT. USAHA SEJAHTERA MANIKAM
T. ALI BADRISYAH
Direktur Utama
SELUAS 83,15 HA (662 HA)
PEKERJAAN PEMBANGUNAN JARINGAN IRIGASI D.I. KRUENG JREUE/KEULILING PAKET-II
99,000,000.00
B=0,40 m; H=0,60 m; Ht =1,70 m Bh 8.00 240,000,000.00
2.00 70,000,000.00
Drain hole dia. 1,5" (lengkap ijuk)
B=1,00 m; H=1,20 m; Ht =2,30 m Bh 1.00 41,000,000.00
B=0,70 m; H=1,15 m; Ht =2,20 m Bh
Bh 100.00 1,520,700.00
B=1,50 m; H=1,20 m; Ht =2,30 m Bh 1.00 44,000,000.00
Pekerjaan Pembesian (besi polos) (upah + bahan) Kg 1,760.00 22,999,680.00
Bekesting M2 264.00 32,228,592.00
Plesteran 1 : 3, t = 15 mm M2 350.00 10,658,200.00 0.33
Beton K-175 M3 16.00 15,512,544.00 0.48
Urug Kembali M3 31.00 445,005.00 0.01
Pasangan batu 1 : 4 M3 213.00 110,255,190.00 3.38
Galian Tanah Biasa (MP) M3 50.00 2,165,600.00 0.07
Galian Tanah (AB) M3 277.50 7,190,580.00 0.22
12 Drain hole dia. 1,5" (lengkap ijuk) Bh 1,318.00 20,042,826.00 0.61
10 Pekerjaan Pembesian (besi polos) (upah + bahan) Kg 6,071.49 79,342,231.32 2.43
9 Beton K-225 M3 42.76 46,330,203.44 1.42
8 Plesteran 1 : 3, t = 15 mm M2 5,303.51 161,502,486.52 4.95
7 Pasangan batu 1 : 4 M3 1,477.59 764,844,911.70 23.43
6 Pembuangan tanah hasil galian diratakan M3 4,309.36 137,705,598.80 4.22
5 Timbunan tanah hasil galian (diangkut ± 250m) dan dipadatkan (AB) M3 7,746.17 232,834,377.86 7.13
1.59
4 Timbunan tanah hasil galian dipadatkan (AB) M3 7,325.29 212,352,831.81 6.51
Galian Tanah (AB) M3 24,064.07 623,548,181.84 19.10
3 Urug Kembali M3 3,609.61 51,815,951.55
0.63
BULAN - VII
1
2
I DAFTAR 1 : MATA PEMBAYARAN UMUM
2
3
4
5
6
Galian Tanah Biasa (MP)
JADWAL WAKTU PELAKSANAAN
NO. URAIAN KEGIATAN JUMLAH HARGA (Rp) BOBOT (%)
W A K T U P E L A K S A N A A N
KET.BULAN - I BULAN - II BULAN - III
KUANTITAS
9 0.05
1 Mobilisasi dan Demobilisasi 17,160,000.00 0.53
1 M3
2
B=0,5 m; H=1,00 m; Ht =2,20 m Bh 3.00
1 Gebalan Rumput
DAFTAR 3 : MATA PEMBAYARAN LAIN-LAIN
4.21M2 137,306,686.44
Barak Pekerja 3,000,000.00 0.09
Ls
Ls 1.00
3 Dewatering/Pengalihan Air 35,000,000.00 1.07
BULAN - VIBULAN - V
Ls
1.00
UKURAN BULAN - IV
1.26
4,786.54
1.00
474.70
1.35
20,560,206.40
8
7 0.70
7.35
3.03
2.14
0.99
11 Bekisting M2 196.60 24,000,534.80 0.74
100
90
80
70
60
50
40
30
20
10
0