A. Labour Salary
Jurnal HSBB Edisi
34 Tahun 2015Other
1 Unskilled workers (Pekerja Tidak Terampil) OH 50,000 OH = Orang / Hari
2 Skilled workers (Pekerja Terampil) OH 70,000
3 Machinist Helper (Pembantu Masinis) OH 70,000
4 Warehouse Keeper (Penjaga Gudang) OH 100,000
5 Watchman (Penjaga Malam) OH 100,000
6 Carpenter (Tukang Kayu) OH 100,000
7 Mason (Tukang Batu) OH 100,000
8 Painter (Tukang Cat) OH 100,000
9 Electrician (Tukang Listrik) OH 100,000
10 Plumber (Tukang Pipa) OH 100,000
11 Vulcan (Tukang besi) OH 100,000
12 Foreman (Kepala Tukang) OH 125,000
13 Head Foreman (Mandor) OH 150,000
B. Material Prices 1 $ : 13,300Rp
URAIANJurnal HSBB Edisi
34 Tahun 2015Other
A. BASICLY MATERIAL
I. Sand
1.1 Sand fill (Pasir Urug / Timbunan) m3 89,000
1.2 Sand Pair (Pasir Pasang) m3 100,000
1.3 Sand for Concrete (Pasir Beton) m3 148,000
II. Red Soil m3 50,000 PT. BKS
III. Gravel (Kerikil) m3 277,000
IV. Sand Stone (Sirtu) m3 177,000
V Portland Cement (50 kg) zak 43,000
VI. White Cement (40kg) zak 53,000
VII. River Stone (Batu Kali)
7.1 Cobblestone (Batu bulat utuh) m3 152,000
7.2 Crushed Stone 7-10 cm m3 237,000
7.3 Crushed Stone 5-7 cm m3 256,000
7.4 Crushed Stone 3-5 cm m3 262,000
7.5 Crushed Stone 2-3 cm m3 267,000
7.6 Crushed Stone 1-2 cm m3 272,000
7.7 Rock m3 160,000
VIII. ROCK
1 Rock 10-300 kg m3 160,000 Assumptions
2 Rock 300-900 kg m3 192,000 Assumptions
3 Rock 900-1200 kg m3 220,000 PT. BKS
B. IRON MATERIAL
I. Plain Reinforcement (Besi Beton Polos)1.1 d = 4 mm btng 24,000
1.2 d = 6 mm btng 35,500
1.3 d = 8 mm btng 50,000
1.4 d = 10 mm btng 75,000
1.5 d = 12 mm btng 106,000
1.6 d = 14 mm btng 131,000
1.7 d = 16 mm btng 165,000
1.8 d = 19 mm btng 200,000
1.9 d = 22 mm btng 325,000
II. Screw Reinforcement (Besi Beton Ulir)
2.1 d = 13 mm btng 110,000
2.2 d = 16 mm btng 165,000
2.3 d = 29 mm btng 227,000
C.WOOD MATERIAL
I. WOOD CLASS I
1.1 Sawmil saws Beam m3 10,300,000
1.2 Sawmil saws Boards m3 10,550,000
1.3 Sansaw saws Beam m3 8,750,000
NO Unit Remark
Unit Price (Rp)
UNIT PRICES FOR MAKASSAR REGION
NO DESCRIPTION Unit
Unit Price (Rp)
Remark
-
7/24/2019 Harga Satuan Bahan Bangunan
2/2
1.4 Sansaw saws Boards m3 8,800,000
II. WOOD CLASS I I
2.1 Beam m3 4,800,000
2.2 Board m3 4,850,000
III. WOOD CLASS I I
3.1 Beam m3 2,900,000
3.2 Board m3 3,475,000
IV. TRIPLEKS UK. 122X244 CM
4.1 Tripleks 2 mm lmbr 53,500
4.2 Tripleks 3 mm lmbr 71,0004.3 Tripleks 6 mm lmbr 99,000
4.4 Tripleks 9 mm lmbr 131,000
4.5 Teakwood 3 mm lmbr 97,500
D. ROAD MATERIAL
I. Geotextile m2 37,300 Ord > 1 Container (Geosinindo)
II. Geotextile m2 43,500 Ord < 1 Container (Geosinindo)
III. Geomattress m2 40,000
IV. Aspal kg 16,000
E. FUEL
I. Solar ltr 10,700 Pertamina 15 Juni 2015
II. Premium ltr 8,600 Pertamina 15 Juni 2015
III Minyak Pelumas ltr 29,500
F. OTHER
I. Nail kg 17,500
II. Formwork Oil ltr 12,000
III. PVD GI-Drain 70 m' 3,100 PT. Geoforce Indonesia
IV. Drain Shoe bh 2,500 Assumptions
C. Rental Cost
Jurnal HSBB Edisi
34 Tahun 2015Other
1 Tug Boat Hour 810,000 P. Jawa Prices +30%
2 Barge Hour 1,667,415
3 Excavator Hour 360,000
4 Wheel loader Hour 315,000
5 Buldozer Hour 450,000
6 Square Pontoon Hour 193,500
7 Dump truck Hour 180,000
8 Crawler crane Hour 720,000
9 Theodolit Hour 50,000
10 Vibro Roller Hour 315,000
11 Sampan Hour 65,000
Note :
1
shelter / accommodation operator / mechanic, security, insurance and any taxes / levies
2 The minimum rental period 210 hours (1 month)
3 Production Year of Heavy Equipment 2008 - 2010
Responsibilities of tenants includes mobilization and demobilization equpments, fuel, meals allowance, eat operator,
NO DESCRIPTION Unit Remark
Unit Price (Rp)