LAPORAN MINGGUAN BULAN KE : 4 ( EMPAT ) MINGGU KE : 14 (Empat belas) PERIODE : 30 Agustus s/d 05 September 2015 PEKERJAAN PEMBANGUNAN GEDUNG KELAS POLITEKNIK KESEHATAN BENGKULU KEGIATAN PEMBANGUNAN GEDUNG KELAS LOKASI JL. INDRAGIRI No. 3 PADANG HARAPAN BENGKULU TH. ANGGARAN 2015 KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA CV. SENTRA REKAYASA KEMENTERIAN KESEHATAN REPUBLIK INDONESIA POLITEKNIK KESEHATAN BENGKULU Jalan Indragiri No. 03 Padang Harapan Kota Bengkulu Kode Pos 38225 Telp. 0736 – 341212 Fax. 0736 – 21514/25343 E-mail : [email protected] Website : www.poltekkes-kemenkes-bengkulu.ac.id

Upload: fakhrur-rozi

Post on 17-Feb-2016

223 views

Category:

Documents


3 download

DESCRIPTION

contoh format laporan mingguan

TRANSCRIPT

Page 1: Gedung Kelas_Minggu 14

LAPORAN MINGGUANBULAN KE : 4 ( EMPAT ) MINGGU KE : 14 (Empat belas) PERIODE : 30 Agustus s/d 05 September 2015

PEKERJAAN PEMBANGUNAN GEDUNG KELAS POLITEKNIK KESEHATAN BENGKULU

KEGIATANPEMBANGUNAN GEDUNG KELAS

LOKASIJL. INDRAGIRI No. 3 PADANG HARAPAN BENGKULU

TH. ANGGARAN

KONSULTAN PENGAWAS

KONTRAKTOR PELAKSANA

CV. SENTRA REKAYASA

KEMENTERIAN KESEHATAN REPUBLIK INDONESIAPOLITEKNIK KESEHATAN BENGKULU

Jalan Indragiri No. 03 Padang Harapan Kota Bengkulu Kode Pos 38225 Telp. 0736 – 341212 Fax. 0736 – 21514/25343E-mail : [email protected] Website : www.poltekkes-kemenkes-bengkulu.ac.id

Page 2: Gedung Kelas_Minggu 14

LAPORAN MINGGUAN 4 ( EMPAT ) 14 (Empat belas) 30 Agustus s/d 05 September 2015

PEKERJAAN PEMBANGUNAN GEDUNG KELAS POLITEKNIK KESEHATAN BENGKULU

KEGIATANPEMBANGUNAN GEDUNG KELAS

LOKASIJL. INDRAGIRI No. 3 PADANG HARAPAN BENGKULU

TH. ANGGARAN

2015

KONSULTAN PENGAWAS

KONTRAKTOR PELAKSANA

CV. SENTRA REKAYASA

KEMENTERIAN KESEHATAN REPUBLIK INDONESIAPOLITEKNIK KESEHATAN BENGKULU

Jalan Indragiri No. 03 Padang Harapan Kota Bengkulu Kode Pos 38225 Telp. 0736 – 341212 Fax. 0736 – 21514/25343E-mail : [email protected] Website : www.poltekkes-kemenkes-bengkulu.ac.id

Page 3: Gedung Kelas_Minggu 14

Pemilik Kegiatan : Kontraktor Pelaksana :

Hari '= …………………………………………………

Tanggal '= …………………………………………………

KEGIATAN : #REF! PEKERJAAN : 0 Minggu Ke = 1 (Satu) LOKASI : 0 TAHUN ANGGARAN : #REF! Periode = 01 Juni s/d 06 Juni 2015 JANGKA WAKTU :

TENAGA BAHAN - BAHAN PERALATAN

Keahlian Jumlah M a c a m Jumlah Jumlah macam JumlahDiterima Ditolak1 2 3 4 5 6 7

Pelaksana orang Logistik orang Mandor orang Kepala Tukang orang Tukang orang Pekerja orang Operator orang Driver orang Penjaga orang

Pekerjaan yang dikerjakan hari ini

Hari ini Sepenuhnya dapat Dipergunakan untuk bekerja CUACA DALAM KEADAANSebagian tidak dapat

Jam Kerja = s/d. Wib. Disetujui Oleh : Dibuat Oleh :

- - - -

- - - -

Page 4: Gedung Kelas_Minggu 14

PEKERJAAN : PEMBANGUNAN GEDUNG KELAS POLITEKNIK KESEHATAN BENGKULU PEKERJAAN : PEMBANGUNAN GEDUNG KELAS LOKASI : JL. INDRAGIRI No. 3 PADANG HARAPAN BENGKULU MINGGU KE : 14 (Empat belas) TAHUN ANGGARAN : 2015 TANGGAL : 30 Agustus s/d 05 September 2015 JANGKA WAKTU : #REF! KONTRAKTOR PELAKS. : #REF! KONSULTAN PENGAWAS : #REF!

H A R I JML. TENAGA J A M K E R J A KETERANGANKERJA KAMIS JUMAT SABTU MINGGU SENIN SELASA RABU 15.00 s/d. 16.00

JUMAT Orang = CERAHSABTU OrangMINGGU Orang = HUJANSENIN OrangSELASA Orang = ISTIRAHATRABU OrangKAMIS Orang

Bengkulu, 05 September 2015

Diperiksa/Disetujui Oleh: 0 Dibuat Oleh : 0 0 Konsultan Pengawas 0 0 CV. UTAKA ESSA KONSULTAN

0 0 00 0 -

Page 5: Gedung Kelas_Minggu 14

PEKERJAAN : PEMBANGUNAN GEDUNG KELAS POLITEKNIK KESEHATAN BENGKULUKEGIATAN : PEMBANGUNAN GEDUNG KELASLOKASI : JL. INDRAGIRI No. 3 PADANG HARAPAN BENGKULUTH. ANGGARAN : 2015

MINGGU LALU MINGGU INI NO U R A I A N P E K E R J A A N

I PEKERJAAN PERSIAPAN 1.142 0.980 0.023 II PEKERJAAN TANAH DAN PASIR 2.103 2.077 - III PEKERJAAN BETON MUTU K225 58.641 52.399 2.080 IV PEKERJAAN PASANGAN 15.976 2.651 1.251 V PEKERJAAN KAYU, BESI, ALUMUNIUM & KACA 6.008 - - VI PEKERJAAN ATAP 3.322 - - VII PEKERJAAN PLAFOND 1.941 - - VIII PEKERJAAN KUNCI / PENGGANTUNG 1.354 - - IX PEKERJAAN SANITASI DAN SANITAIR 1.411 0.112 - X PEKERJAAN INSTALASI LISTRIK 3.176 0.812 0.298 XI PEKERJAAN PENGECATAN 3.362 - - XII PEKERJAAN PENANGKAL PETIR 0.372 - - XIII PENGADAAN AIR BERSIH BANGUNAN 0.686 0.543 - XIV PEKERJAAN LAIN - LAIN 0.506 0.330 -

100.000 59.905 3.652 #REF!Catatan :

Pelaksanaan Pekerjaan Pada :Bulan Ke : 4 ( EMPAT )

14 (Empat belMinggu Ke : 14 (Empat belas) Periode : 30 Agustus s/d 05 September 2015 Realisasi Pekerjaan Kontraktor Mengalami : Lambat Dari Rencana % %

79.957 63.557

Bengkulu, 05 September 2015 Disetujui Oleh: Dibuat Oleh :

Kontraktor Pelaksana Konsultan Pengawas CV. SENTRA REKAYASA CV. UTAKA ESSA KONSULTAN

SUDARSO ZULFIKAR HANANI, ST Direktur Inspector

Diperiksa/Disetujui Oleh:Pengelola Teknis

Dinas Pekerjaan Umum Provinsi Bengkulu

EDY IDHAM, ST Nip. 19620503 198703 1 014

BOBOT KONTRAK

%

MINGGU KE :

RENCANA REALISASI

KEMENTERIAN KESEHATAN REPUBLIK INDONESIAPOLITEKNIK KESEHATAN BENGKULU

Jalan Indragiri No. 03 Padang Harapan Kota Bengkulu Kode Pos 38225 Telp. 0736 – 341212 Fax. 0736 – 21514/25343E-mail : [email protected] Website : www.poltekkes-kemenkes-bengkulu.ac.id

Page 6: Gedung Kelas_Minggu 14

LAPORAN KEMAJUAN FISIKPEKERJAAN = PEMBANGUNAN GEDUNG KELAS POLITEKNIK KESEHATAN BENGKULUKEGIATAN = PEMBANGUNAN GEDUNG KELASLOKASI = JL. INDRAGIRI No. 3 PADANG HARAPAN BENGKULUTH. ANGGARAN = 2015

Nomor : 69/UKE-LAP/BKL/IX/2015Lampiran : 1 EksPerihal : Laporan Fisik Minggu Ke 14 (Empat belas)

Kepada Yth ;

Pejabat Pembuat KomitmenPoliteknik Kesehatan Kemenkes Bengkuludi - Bengkulu

Dengan ini kami beritahukan bahwa pelaksanaan pekerjaan sampai minggu ini :

Bulan Ke : 4 ( EMPAT ) Minggu Ke : 14 (Empat belas) Periode : 30 Agustus s/d 05 September 2015

BOBOT FISIKKONTRAKTOR PELAKSANA RENCANA REALISASI DEVIASI

% % LAMBAT (%)

CV. SENTRA REKAYASA 79.957 63.557 -16.400

Demikian laporan ini sampaikan, agar dapat dipergunakan sebagai monitoring kegiatan dilapangan.

Bengkulu, 05 September 2015

Konsultan Pengawas CV. UTAKA ESSA KONSULTAN

ZULFIKAR HANANI, ST Inspector

Page 7: Gedung Kelas_Minggu 14

S/D MINGGU INI

1.004 2.077 54.479 3.902 - - - - 0.112 1.110 - - 0.543 0.330

63.557

TERLAMBAT %

-16.400

Bengkulu, 05 September 2015

Konsultan Pengawas CV. UTAKA ESSA KONSULTAN

ZULFIKAR HANANI, ST

KEMENTERIAN KESEHATAN REPUBLIK INDONESIAPOLITEKNIK KESEHATAN BENGKULU

Jalan Indragiri No. 03 Padang Harapan Kota Bengkulu Kode Pos 38225 Telp. 0736 – 341212 Fax. 0736 – 21514/25343E-mail : [email protected] Website : www.poltekkes-kemenkes-bengkulu.ac.id

Page 8: Gedung Kelas_Minggu 14

LAPORAN KEMAJUAN FISIK

BOBOT FISIK DEVIASI

LAMBAT (%)

-16.400

Bengkulu, 05 September 2015

CV. UTAKA ESSA KONSULTAN

Page 9: Gedung Kelas_Minggu 14

TIME SCHEDULEPEKERJAAN : PEMBANGUNAN GEDUNG KELAS POLITEKNIK KESEHATAN BENGKULUKEGIATAN : PEMBANGUNAN GEDUNG KELAS Minggu ke : 14 (Empat belas)

LOKASI : JL. INDRAGIRI No. 3 PADANG HARAPAN BENGKULU Periode Ke : 30 Agustus s/d 05 September 2015

TH. ANGGARAN : 2015 Bulan Ke : 4 ( EMPAT )

JANGKA WAKTU PELAKSANAAN 150 ( SERATUS LIMA PULUH ) HARI KALENDER

URAIAN PEKERJAAN

BOBOT JUNI JULI AGUSTUS SEPTEMBER OKTOBER

NO. % BULAN KE 1 BULAN KE 2 BULAN KE 3 BULAN KE 4 BULAN KE 5

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

01 - 06 07 - 13 14 - 20 21 - 27 28 - 04 05 - 11 18 - 12 19 - 25 26 - 01 02 - 18 09 - 15 16 - 22 23 - 29 30 - 05 06 - 12 13 - 19 20 - 26 27 - 03 04 - 10

I PEKERJAAN PERSIAPAN 1.142 0.054 0.054 0.054 0.054 0.054 0.054 0.054 0.054 0.054 0.054 0.054 0.054 0.054 0.054 0.054 0.054 0.054 0.054 0.054 0.449 0.277 0.023 0.023 0.023 0.023 0.023 0.023 0.023 0.023 0.023 0.023 0.023 0.023

II PEKERJAAN TANAH DAN PASIR 2.103 0.263 0.263 0.263 0.263 0.263 0.263 0.263 0.263 0.445 0.691 0.071 0.058 0.362 0.378 0.072

III PEKERJAAN BETON MUTU K225 58.641 2.189 3.689 4.689 5.689 5.689 5.689 5.689 5.689 5.689 4.689 3.689 3.689 1.877 0.803 1.949 3.120 7.190 2.946 3.235 2.937 2.848 9.308 4.848 3.531 9.686 2.080

IV PEKERJAAN PASANGAN 15.976 1.141 1.141 1.141 1.141 1.141 1.141 1.141 1.141 1.141 1.141 1.141 1.141 1.141 1.141 0.267 0.599 1.786 1.251

V PEKERJAAN KAYU, BESI, ALUMUNIUM & KACA 6.008 0.858 0.858 0.858 0.858 0.858 0.858 0.858

VI PEKERJAAN ATAP 3.322 0.664 0.664 0.664 0.664 0.664

VII PEKERJAAN PLAFOND 1.941 0.388 0.388 0.388 0.388 0.388

VIII PEKERJAAN KUNCI / PENGGANTUNG 1.354 0.271 0.271 0.271 0.271

IX PEKERJAAN SANITASI DAN SANITAIR 1.411 0.235 0.235 0.235 0.235 0.235 0.235 0.001 0.055 0.055

X PEKERJAAN INSTALASI LISTRIK 3.176 0.529 0.529 0.529 0.529 0.529 0.150 0.662 0.298

XI PEKERJAAN PENGECATAN 3.362 0.840 0.840 0.840

XII PEKERJAAN PENANGKAL PETIR 0.372 0.093 0.093 0.093 0.093

XIII PENGADAAN AIR BERSIH BANGUNAN 0.686 0.114 0.114 0.114 0.114 0.114 0.455 0.088

XIV PEKERJAAN LAIN - LAIN 0.506 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.099 0.099 0.099 0.033

Jumlah Bobot = ……… 100.000 1 Rencana = ……… - 0.317 0.317 2.506 4.006 5.006 7.147 7.147 7.147 7.158 8.117 8.681 7.975 7.069 7.363 4.801 3.488 4.035 3.082 2.695 2 Rencana Komulatif = ……… - 0.317 0.635 3.141 7.147 12.152 19.300 26.447 33.594 40.752 48.869 57.550 65.525 72.594 79.957 84.758 88.246 92.281 95.363 98.058 3 Realisasi = ……… - 0.894 2.226 2.131 3.201 7.575 3.349 3.329 2.960 2.971 9.580 5.292 4.903 11.495 3.652 4 Realisasi Komulatif = ……… - 0.894 3.119 5.251 8.452 16.027 19.376 22.705 25.665 28.635 38.215 43.507 48.410 59.905 63.557

Deviasi = ……… Lambat 0.576 2.485 2.110 1.305 3.874 0.076 -3.742 -7.929 -12.117 -10.654 -14.043 -17.115 -12.689 -16.400

3.74 37.78

Diperiksa/Disetujui Oleh: Disetujui Oleh: Pengelola Teknis Kontraktor Pelaksana

Dinas Pekerjaan Umum Provinsi Bengkulu CV. SENTRA REKAYASA

EDY IDHAM, ST SUDARSO Nip. 19620503 198703 1 014 Direktur

Page 10: Gedung Kelas_Minggu 14

TIME SCHEDULE

JANGKA WAKTU PELAKSANAAN 150 ( SERATUS LIMA PULUH ) HARI KALENDER KETERANGAN

OKTOBER PROSENT.

BULAN KE 5 ( % )

20 21

11 - 17 18 - 29

0.054 0.054 100 %

75 %

50 % 0.271

0.529

0.840 25 %

0.114

0.039 0.039

0 %

Keterangan : 1.848 0.093 99.907 100.000 Rencana.

Realisasi. 100.000

Bengkulu, 05 September 2015

Dibuat Oleh : Konsultan Pengawas

CV. UTAKA ESSA KONSULTAN

ZULFIKAR HANANI, ST Inspector

Page 11: Gedung Kelas_Minggu 14

KEMENTERIAN KESEHATAN RIPOLITEKNIK KESEHATAN BENGKULU

PEKERJAAN : PEMBANGUNAN GEDUNG KELAS POLITEKNIK KESEHATAN BENGKULU

LAPORAN MINGGUAN KEGIATAN : PEMBANGUNAN GEDUNG KELAS

LOKASI : JL. INDRAGIRI No. 3 PADANG HARAPAN BENGKULU

TH. ANGGARAN : 2015

KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA

CV. SENTRA REKAYASA Minggu ke : 14 (Empat belas) Periode Ke : 30 Agustus s/d 05 September 2015 Bulan Ke : 4 ( EMPAT )

NO. URAIAN PEKERJAAN

KONTRAK KEMAJUAN FISIK PEKERJAAN

VOLUME BOBOT MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT VOLUME PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN % PELAKSANAAN

1 2 3 4 5 6 7 8 9 10 11

I PEKERJAAN PERSIAPAN1 Pek. Pembersihan Lokasi 510 m2 0.253 510.000 100.000 0.253 - - - 510.000 2 Pek. Pengukuran/Pasangan Bauwplank 80 m' 0.192 80.000 100.000 0.192 - - - 80.000 3 Pek. Barak Kerja dan Gudang Bahan/Peralatan 1 unit 0.220 1.000 100.000 0.220 - - - 1.000 4 Biaya Administrasi / Dokumentasi dan Astek 1 unit 0.440 0.650 65.000 0.286 0.050 5.000 0.022 0.700 5 Pas. Papan Nama Proyek 1 unit 0.015 1.000 100.000 0.015 - - - 1.000 6 Biaya PPPK 1 unit 0.022 0.650 65.000 0.014 0.050 5.000 0.001 0.700

Sub Jumlah I 1.142 0.980 0.023 II PEKERJAAN TANAH DAN PASIR

1 Pek. Pemotongan Tanah 75 m3 0.207 75.000 100.000 0.207 - - - 75.000 2 Pek. Galian Tanah Pondasi 384.56 m3 1.063 384.560 100.000 1.063 - - - 384.560 3 Pek. Urugan Tanah Kembali 294.51 m3 0.483 294.510 100.000 0.483 - - - 294.510 4 Pek. Urugan Tanah Bawah Lantai 30.94 m3 0.051 30.940 100.000 0.051 - - - 30.940 5 Pek. Urugan Pasir Bawah pondasi Plat Menerus 17.92 m3 0.130 17.920 100.000 0.130 - - - 17.920 6 Pek. Urugan Pasir Bawah Lantai 19.76 m3 0.143 19.760 100.000 0.143 - - - 19.760 7 Pek. Urugan Pasir Bawah Rabat Keliling Bangunan 3.64 m3 0.026 - - - - - - -

Sub Jumlah II 2.103 2.077 -

Page 12: Gedung Kelas_Minggu 14

NO. URAIAN PEKERJAAN

KONTRAK KEMAJUAN FISIK PEKERJAAN

VOLUME BOBOT MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT VOLUME PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN % PELAKSANAAN

1 2 3 4 5 6 7 8 9 10 11

III PEKERJAAN BETON MUTU K225A LANTAI BASEMEN ( Elv. ± 0,00 s/d + 3,50 )

1 Pek. Beton Lantai Kerja K. 100 Bawah Pondasi Plat T. 10 cm 8.96 m3 0.253 8.960 100.000 0.253 - - - 8.960 2 Pek. Beton Lantai Kerja K. 100 Bawah Lantai T. 6 cm 11.17 m3 0.316 11.170 100.000 0.316 - - - 11.170 3 Pek. Beton Rabat K. 100 Keliling Bangunan T. 8 cm 6.41 m3 0.181 - - - - - - - 4 Pek. Pondasi Siklop, 60% Beton Campuran 1Sp : 2Pb : 3Kr & 40% Batu Belah ø 60 26.16 m3 2.675 26.160 100.000 2.675 - - - 26.160 5 Pek. Beton Pondasi Plat Menerus Type P1 40.32 m3 4.823 40.320 100.000 4.823 - - - 40.320 6 Pek. Beton Balok Rib Pondasi Plat Menerus (30/50) 16.8 m3 3.585 16.800 100.000 3.585 - - - 16.800 7 Pek. Beton Tiang Pondasi Plat K.1 (35/35) 6.05 m3 1.725 6.050 100.000 1.725 - - - 6.050 8 Pek. Beton Sloof SL2 (20/30) 0.57 m3 0.110 0.570 100.000 0.110 - - - 0.570 9 Pek. Beton Sloof SL2 (30/40) 14.64 m3 2.988 14.640 100.000 2.988 - - - 14.640

10 Pek. Beton Kolom Praktis KP (13/13) 0.32 m3 0.111 0.160 50.000 0.056 - - - 0.160 11 Pek. Beton Kolom K.1 (35/35) 12.91 m3 3.680 12.910 100.000 3.680 - - - 12.910 12 Pek. Beton Kolom K.2 (25/25) 0.59 m3 0.177 0.590 100.000 0.177 - - - 0.590 13 Pek. Beton Balok BL. 1 (30/40) 12.24 m3 3.046 12.240 100.000 3.046 - - - 12.240 14 Pek. Beton Balok BL. 2 (30/40+ 12/80) 4.48 m3 1.243 4.480 100.000 1.243 - - - 4.480 15 Pek. Beton Balok BL. 3 (30/50) 5.4 m3 1.248 5.400 100.000 1.248 - - - 5.400 16 Pek. Beton Balok BA.2 (20/30) 0.58 m3 0.150 0.580 100.000 0.150 - - - 0.580 17 Pek. Beton Balok BA.1 (20/40) 1.92 m3 0.527 1.920 100.000 0.527 - - - 1.920 18 Pek. Beton Balok Bordes ( 20/30 ) 0.47 m3 0.102 0.470 100.000 0.102 - - - 0.470 19 Pek. Beton Balok Latei ( 13/13 ) 0.65 m3 0.223 0.650 100.000 0.223 - - - 0.650 20 Pek. Beton Lantai Basemen T. 12 cm 18.57 m3 1.847 18.570 100.000 1.847 - - - 18.570 21 Pek. Beton Plat/Dak Lantai T. 12 cm 18.54 m3 4.332 18.540 100.000 4.332 - - - 18.540 22 Pek. Beton Tangga dan Bordes T. 15 cm 2.35 m3 0.546 - - - 0.470 20.000 0.109 0.470 23 Pek. Beton Plat Cantilever T. 10 cm 1.52 m3 0.349 1.520 100.000 0.349 - - - 1.520

Jumlah A 34.237 33.454 0.109 B LANTAI - 1 ( Elv + 7,00 )

1 Pek. Beton Kolom Praktis KP (13/13) 0.32 m3 0.117 - - - - - - - 2 Pek. Beton Kolom K.1 (35/35) 12.91 m3 3.864 12.910 100.000 3.864 - - - 12.910 3 Pek. Beton Kolom K.2 (25/25) 0.59 m3 0.186 0.590 100.000 0.186 - - - 0.590 4 Pek. Beton Balok BL. 1A (30/40) 12.24 m3 3.198 12.240 100.000 3.198 - - - 12.240 5 Pek. Beton Balok BL. 1B (30/40+ 12/80) 4.48 m3 1.305 4.480 100.000 1.305 - - - 4.480 6 Pek. Beton Balok BL. 3 (30/50) 5.4 m3 1.310 5.400 100.000 1.310 - - - 5.400 7 Pek. Beton Balok BA.2 (20/30) 0.58 m3 0.158 0.580 100.000 0.158 - - - 0.580 8 Pek. Beton Balok BA.1 (20/40) 1.92 m3 0.554 1.920 100.000 0.554 - - - 1.920 9 Pek. Beton Balok Bordes ( 20/30 ) 0.48 m3 0.109 - - - - - - -

10 Pek. Beton Balok Latei ( 13/13 ) 0.61 m3 0.220 - - - - - - - 11 Pek. Beton Plat/Dak Lantai T. 12 cm 18.54 m3 4.549 18.540 100.000 4.549 - - - 18.540 12 Pek. Beton Tangga dan Bordes T. 15 cm 2.35 m3 0.574 - - - - - - - 13 Pek. Beton Plat Cantilever T. 10 cm 1.52 m3 0.366 1.520 100.000 0.366 - - - 1.520

Jumlah B 16.509 15.489 -

Page 13: Gedung Kelas_Minggu 14

NO. URAIAN PEKERJAAN

KONTRAK KEMAJUAN FISIK PEKERJAAN

VOLUME BOBOT MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT VOLUME PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN % PELAKSANAAN

1 2 3 4 5 6 7 8 9 10 11

C LANTAI - 2 ( Elv +10,50 )1 Pek. Beton Kolom Praktis KP (13/13) 0.37 m3 0.138 - - - - - - - 2 Pek. Beton Kolom K.1 (35/35) 13.33 m3 4.066 11.331 85.000 3.456 1.999 15.000 0.610 13.330 3 Pek. Beton Balok BL (25/40) 1.26 m3 0.309 - - - 1.260 100.000 0.309 1.260 4 Pek. Beton Ring Balok RB (20/30) 4.92 m3 1.434 - - - 1.476 30.000 0.430 1.476 5 Pek. Beton Ring Balok RB.1 (20/30 + 12/80) 3.16 m3 1.008 - - - 0.948 30.000 0.302 0.948 6 Pek. Beton Ring Balok RB.2 (15/20) 0.45 m3 0.131 - - - - - - - 7 Pek. Beton Balok Latei ( 13/13 ) 0.61 m3 0.224 - - - - - - - 8 Pek. Beton Tangga T. 15 cm 1.07 m 0.266 - - - - - - - 9 Pek. Beton Plat /Dak Tandon T. 15 cm 1.6 m3 0.320 - - - 1.600 100.000 0.320 1.600

Jumlah C 7.895 3.456 1.971 Sub Jumlah III 58.641 52.399 2.080

IV PEKERJAAN PASANGANA LANTAI - BASEMEN ( Elv. ± 0,00 s/d + 3,50 )

1 Pek. Pasangan 1/2 Batu Bata 1 : 2 25.32 m2 0.109 25.320 100.000 0.109 - - - 25.320 2 Pek. Pasangan 1/2 Batu Bata 1 : 4 196.74 m2 0.780 186.903 95.000 0.741 - - - 186.903 3 Pek. Plesteran 1 : 2 50.63 m2 0.113 48.098 95.000 0.108 - - - 48.099 4 Pek. Plesteran 1 : 4 393.47 m2 0.809 373.797 95.000 0.768 - - - 373.797 5 Pek. Acian Dinding dan Kolom 677.06 m2 0.814 541.648 80.000 0.651 - - - 541.648 6 Pek. Acian Expose Plat Dak 226.15 m2 0.272 203.535 90.000 0.245 - - - 203.535 7 Pek. Pasangan Jalusi Lobang ( Batu Roster ) 5 bh 0.017 - - - - - - - 8 Pek. Pasangan Lantai Keramik 40/40 cm Kwalitas Baik 210.71 m2 1.751 - - - - - - - 9 Pek. Pasangan Lantai Keramik 20/20 cm Km/Wc 5.64 m2 0.046 - - - - - - -

10 Pek. Pasangan Dinding Keramik 20/25 cm Km/wc 26.67 m2 0.203 - - - - - - - 11 Pek. Pasangan Plin Keramik 10/40 cm 128.1 m' 0.198 - - - - - - - 12 Pek. Plasteran Rabat Beton Keliling Bangunan 80.08 m2 0.165 - - - - - - - 13 Pek. Acian Rabat Beton Keliling Bangunan 80.08 m2 0.096 - - - - - - - 14 Pek. Saluran Keliling Bangunan 77.6 m' 0.598 3.880 5.000 0.030 3.880 5.000 0.030 7.760 15 Pek. Bak Kontrol Pada Saluran Keliling Bangunan 4 unit 0.026 - - - - - - -

Jumlah A 5.997 2.651 0.030 B LANTAI - 1 ( Elv + 7,00 )

1 Pek. Pasangan 1/2 Batu Bata 1 : 4 222.16 m2 0.880 - - - 177.728 80.000 0.704 177.728 2 Pek. Plesteran 1 : 4 444.33 m2 0.913 - - - - - - - 3 Pek. Acian Dinding dan Kolom 677.29 m2 0.814 - - - - - - - 4 Pek. Acian Expose Plat Dak 226.15 m2 0.272 - - - 56.538 25.000 0.068 56.538 5 Pek. Pasangan Jalusi Lobang ( Batu Roster ) 5 bh 0.017 - - - - - - - 6 Pek. Reling Teras Pasangan Batu Bata 1 : 4 + Profilan 23.2 m' 0.128 - - - - - - - 7 Pek. Pasangan Plin Keramik 10/40 cm 143.37 m' 0.222 - - - - - - - 8 Pek. Pasangan Lantai Keramik 40/40 Kwalitas Baik 198.96 m2 1.653 - - - - - - - 9 Pek. Pasangan Lantai Keramik 20/20 Km/Wc 5.64 m2 0.046 - - - - - - -

10 Pek. Pasangan Dinding Keramik 20/25 Km/wc 26.67 m2 0.203 - - - - - - - Jumlah B 5.149 - 0.772

Page 14: Gedung Kelas_Minggu 14

NO. URAIAN PEKERJAAN

KONTRAK KEMAJUAN FISIK PEKERJAAN

VOLUME BOBOT MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT VOLUME PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN % PELAKSANAAN

1 2 3 4 5 6 7 8 9 10 11

C LANTAI - 2 ( Elv +10,50 )1 Pek. Pasangan 1/2 Batu Bata 1 : 4 226.44 m2 0.897 - - - 113.220 50.000 0.449 113.220 2 Pek. Plesteran 1 : 4 452.89 m2 0.931 - - - - - - - 3 Pek. Acian Dinding dan Kolom 594.04 m2 0.714 - - - - - - - 4 Pek. Acian Expose Plat Dak 11.11 m2 0.013 - - - - - - - 5 Pek. Pasangan Jalusi Lobang ( Batu Roster ) 5 m2 0.017 - - - - - - - 6 Pek. Reling Teras Pasangan Batu Bata 1 : 4 + Profilan 23.2 m' 0.128 - - - - - - - 7 Pek. Pasangan Plin Keramik 10/40 cm 146.87 m' 0.227 - - - - - - - 8 Pek. Pasangan Lantai Keramik 40/40 Kwalitas Baik 198.96 m2 1.653 - - - - - - - 9 Pek. Pasangan Lantai Keramik 20/20 Km/Wc 5.64 m2 0.046 - - - - - - -

10 Pek. Pasangan Dinding Keramik 20/25 Km/wc 26.67 m2 0.203 - - - - - - - Jumlah C 4.830 - 0.449

Sub Jumlah IV 15.976 2.651 1.251 V PEKERJAAN KAYU, BESI, ALUMUNIUM & KACAA LANTAI - BASEMEN ( Elv. ± 0,00 s/d + 3,50 )

1 Pek. Kusen Pintu dan Jendela Profil Alumunium setara "ALEXINDO" 129.71 m' 0.531 - - - - - - - 2 Pek. Pintu Panil Kaca Raybend 8 mm Rangka Profil Alumunium Type P1 8.82 m2 0.328 - - - - - - - 3 Pek. Pintu Panil ACP Profil Alumunium Km/Wc Type P2 5.88 m2 0.246 - - - - - - - 4 Pek. Pintu Panil ACP Profil Alumunium Gudang P3 0.98 m2 0.041 - - - - - - - 5 Pek. Bovenlight Kaca Raybend 5 mm Rangka Casement 4.27 m2 0.159 - - - - - - - 6 Pek. Jendela Hidup Kaca Raybend 5 mm Rangka Casement 5.4 m2 0.201 - - - - - - - 7 Pek. Ventilasi Kaca Raybend 5 mm Rangka Casement 6.48 m2 0.241 - - - - - - - 8 Pek. Reling Tangga Stenliss Stile 6.5 m' 0.258 - - - - - - -

Jumlah A 2.006 - - B LANTAI - 1 ( Elv + 7,00 )

1 Pek. Kusen Pintu dan Jendela Profil Alumunium setara "ALEXINDO" 126.13 m' 0.517 - - - - - - - 2 Pek. Pintu Panil Kaca Raybend 8 mm Rangka Profil Alumunium Type P1 8.82 m2 0.328 - - - - - - - 3 Pek. Pintu Panil ACP Rangka Alumunium Km/Wc Type P2 5.88 m2 0.246 - - - - - - - 4 Pek. Bovenlight Kaca Bening 5 mm Rangka Casement 4.27 m2 0.159 - - - - - - - 5 Pek. Jendela Hidup Kaca Bening 5 mm Rangka Casement 5.4 m2 0.201 - - - - - - - 6 Pek. Ventilasi Kaca Bening 5 mm Rangka Casement 6.48 m2 0.241 - - - - - - - 7 Pek. Reling Tangga Stenliss Stile 6.5 m' 0.258 - - - - - - -

Jumlah B 1.950 - - C LANTAI - 2 ( Elv +10,50 )

1 Pek. Kusen Pintu dan Jendela Profil Alumunium setara "ALEXINDO" 164.07 m' 0.672 - - - - - - - 2 Pek. Pintu Panil Kaca Raybend 8 mm Rangka Profil Alumunium Type P1 8.82 m2 0.328 - - - - - - - 3 Pek. Pintu Panil ACP Rangka Alumunium Km/Wc Type P2 5.88 m2 0.246 - - - - - - - 4 Pek. Pintu Panil ACP Rangka Alumunium Type P2 1.47 m2 0.061 - - - - - - - 5 Pek. Bovenlight Kaca Bening 5 mm Rangka Casement 4.27 m2 0.159 - - - - - - - 6 Pek. Jendela Hidup Kaca Bening 5 mm Rangka Casement 5.4 m2 0.201 - - - - - - - 7 Pek. Ventilasi Kaca Bening 5 mm Rangka Casement 6.48 m2 0.241 - - - - - - - 8 Pek. Reling Tangga Stenliss Stile 3.6 m' 0.143 - - - - - - -

Jumlah C 2.052 - - Sub Jumlah V 6.008 - -

Page 15: Gedung Kelas_Minggu 14

NO. URAIAN PEKERJAAN

KONTRAK KEMAJUAN FISIK PEKERJAAN

VOLUME BOBOT MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT VOLUME PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN % PELAKSANAAN

1 2 3 4 5 6 7 8 9 10 11

VI PEKERJAAN ATAP1 Pek. Rangka Atap Baja Ringan + Reng C. 75 R. 40/45 325.16 m2 1.646 - - - - - - - 2 Pas. Atap Genteng Metal Calor T.0,25 mm 336.8 m2 1.466 - - - - - - - 3 Pas. Nok Atas Bulat 42 m' 0.134 - - - - - - - 4 Pas. Listplank Papan 2,8/15 + 2,8/20 28.56 m2 0.075 - - - - - - -

Sub Jumlah VI 3.322 - - VII PEKERJAAN PLAFOND

1 Pek. Pasangan Plafond Bagian Dalam Gypsum 9 mm 138.59 m2 0.294 - - - - - - - 2 Pek. Rangka Plafond Hollow 2/4 + 4/4 138.59 m2 0.571 - - - - - - - 3 Pek. Pasangan Plafond Bagian Luar Plywood 6 mm 128.85 m2 0.310 - - - - - - - 4 Pek. Kayu Rangka Plafond 128.85 m2 0.546 - - - - - - - 5 Pek. Pasangan List Plafond Kayu Profil 253.24 m' 0.221 - - - - - - -

Sub Jumlah VII 1.941 - - VIII PEKERJAAN KUNCI / PENGGANTUNGA LANTAI - BASEMEN ( Elv. ± 0,00 s/d + 3,50 )

1 Pas. Kunci Double Cylinder setara "Dekson" 3 bh 0.029 - - - - - - - 2 Pas. Kunci Double Cylinder + Handle setara "Dekson" 5 bh 0.060 - - - - - - - 3 Pas. Engsel Pintu Alumunium setara "Dekson" 33 bh 0.051 - - - - - - - 4 Pas. Engsel Casement 10 " setara "Dekson" 39 ps 0.103 - - - - - - - 5 Pas. Engsel Casement 16 " setara "Dekson" 9 ps 0.030 - - - - - - - 6 Pas. Handel Pintu Alumunium 6 ps 0.020 - - - - - - - 7 Pas. Door closer Pintu Alumunium 6 bh 0.066 - - - - - - - 8 Pas. Gerendel Pintu Tanam setara "Dekson" 6 bh 0.012 - - - - - - - 9 Pas. Gerendel Jendela Casement setara "Dekson" 48 bh 0.085 - - - - - - -

Jumlah A 0.457 - - B LANTAI - 1 ( Elv + 7,00 )

1 Pas. Kunci Double Cylinder setara "Dekson" 3 bh 0.029 - - - - - - - 2 Pas. Kunci Double Cylinder + Handle setara "Dekson" 4 bh 0.048 - - - - - - - 3 Pas. Engsel Pintu Alumunium setara "Dekson" 30 bh 0.047 - - - - - - - 4 Pas. Engsel Casement 10 " setara "Dekson" 39 ps 0.103 - - - - - - - 5 Pas. Engsel Casement 16 " setara "Dekson" 9 ps 0.030 - - - - - - - 6 Pas. Handel Pintu Alumunium 6 ps 0.020 - - - - - - - 7 Pas. Door closer Pintu Alumunium 6 bh 0.066 - - - - - - - 8 Pas. Gerendel Pintu Tanam setara "Dekson" 6 bh 0.012 - - - - - - - 9 Pas. Gerendel Jendela Casement setara "Dekson" 48 bh 0.085 - - - - - - -

Jumlah B 0.440 - -

Page 16: Gedung Kelas_Minggu 14

NO. URAIAN PEKERJAAN

KONTRAK KEMAJUAN FISIK PEKERJAAN

VOLUME BOBOT MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT VOLUME PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN % PELAKSANAAN

1 2 3 4 5 6 7 8 9 10 11

C LANTAI - 2 ( Elv +10,50 )1 Pas. Kunci Double Cylinder setara "Dekson" 3 bh 0.029 - - - - - - - 2 Pas. Kunci Double Cylinder + Handle setara "Dekson" 5 bh 0.060 - - - - - - - 3 Pas. Engsel Pintu Alumunium setara "Dekson" 33 bh 0.051 - - - - - - - 4 Pas. Engsel Casement 10 " setara "Dekson" 39 ps 0.103 - - - - - - - 5 Pas. Engsel Casement 16 " setara "Dekson" 9 ps 0.030 - - - - - - - 6 Pas. Handel Pintu Alumunium 6 ps 0.020 - - - - - - - 7 Pas. Door closer Pintu Alumunium 6 bh 0.066 - - - - - - - 8 Pas. Gerendel Pintu Tanam setara "Dekson" 6 bh 0.012 - - - - - - - 9 Pas. Gerendel Jendela Casement setara "Dekson" 48 bh 0.085 - - - - - - -

Jumlah C 0.457 - - Sub Jumlah VIII 1.354 - -

IX PEKERJAAN SANITASI DAN SANITAIRA LANTAI - BASEMEN ( Elv. ± 0,00 s/d + 3,50 )

1 Pas. Kloset Jongkok "setara American Standard" 2 bh 0.047 - - - - - - - 2 Pas. Wastafel "setara American Standard" 1 bh 0.083 - - - - - - - 3 Pas. Urinoir "setara American Standard" 2 bh 0.158 - - - - - - - 4 Pas. Kran Air Stanlis Stell 2 bh 0.006 - - - - - - - 5 Pas. Stop Kran 1 bh 0.004 - - - - - - - 6 Pas. Floor Drain 4 bh 0.011 - - - - - - - 7 Pas. Penyekat porslin 1 bh 0.033 - - - - - - - 8 Kaca Cermin uk 800 x 1.200 1 bh 0.011 - - - - - - - 9 Pek. Instalasi Air Bersih Pipa PVC ø 1/2" 8 m' 0.006 0.400 5.000 0.000 - - - 0.400

10 Pek. Instalasi Air Kotor Pipa PVC ø 2" 4 m' 0.008 0.200 5.000 0.000 - - - 0.200 11 Pek. Instalasi Air Kotor Pipa PVC ø 4" 4 m' 0.016 0.200 5.000 0.001 - - - 0.200 12 Pek. Septicktank + Resapan 1 unit 0.220 0.500 50.000 0.110 - - - 0.500

Jumlah A 0.602 0.112 - B LANTAI - 1 ( Elv + 7,00 )

1 Pas. Kloset Jongkok "setara American Standard" 2 bh 0.047 - - - - - - - 2 Pas. Wastafel "setara American Standard" 1 bh 0.083 - - - - - - - 3 Pas. Urinoir "setara American Standard" 2 bh 0.158 - - - - - - - 4 Pas. Kran Air Stanlis Stell 2 bh 0.006 - - - - - - - 5 Pas. Stop Kran 1 bh 0.004 - - - - - - - 6 Pas. Floor Drain 4 bh 0.011 - - - - - - - 7 Pas. Penyekat porslin 1 bh 0.033 - - - - - - - 8 Kaca Cermin uk 800 x 1.200 1 bh 0.011 - - - - - - - 9 Pek. Instalasi Air Bersih Pipa PVC ø 1/2" 8 m' 0.006 - - - - - - -

10 Pek. Instalasi Air Kotor Pipa PVC ø 2" 8 m' 0.015 - - - - - - - 11 Pek. Instalasi Air Kotor Pipa PVC ø 4" 8 m' 0.032 - - - - - - -

Jumlah B 0.406 - -

Page 17: Gedung Kelas_Minggu 14

NO. URAIAN PEKERJAAN

KONTRAK KEMAJUAN FISIK PEKERJAAN

VOLUME BOBOT MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT VOLUME PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN % PELAKSANAAN

1 2 3 4 5 6 7 8 9 10 11

C LANTAI - 2 ( Elv +10,50 )1 Pas. Kloset Jongkok "setara American Standard" 2 bh 0.047 - - - - - - - 2 Pas. Wastafel "setara American Standard" 1 bh 0.083 - - - - - - - 3 Pas. Urinoir "setara American Standard" 2 bh 0.158 - - - - - - - 4 Pas. Penyekat porslin 1 bh 0.033 - - - - - - - 5 Pas. Kran Air Stanlis Stell 2 bh 0.006 - - - - - - - 6 Pas. Stop Kran 1 bh 0.004 - - - - - - - 7 Pas. Floor Drain 4 bh 0.011 - - - - - - - 8 Kaca Cermin uk 800 x 1.200 1 bh 0.011 - - - - - - - 9 Pek. Instalasi Air Bersih Pipa PVC ø 1/2" 4 m' 0.003 - - - - - - -

10 Pek. Instalasi Air Kotor Pipa PVC ø 2" 8 m' 0.015 - - - - - - - 11 Pek. Instalasi Air Kotor Pipa PVC ø 4" 8 m' 0.032 - - - - - - -

Jumlah C 0.403 - - - Sub Jumlah IX 1.411 0.112 -

X PEKERJAAN INSTALASI LISTRIKA LANTAI - BASEMEN ( Elv. ± 0,00 s/d + 3,50 )

1 Pas. Lampu SL 18 Watt 31 bh 0.068 15.500 50.000 0.034 - - - 15.500 2 Pas. Saklar Tunggal 1 bh 0.001 0.500 50.000 0.001 - - - 0.500 3 Pas. Saklar Ganda 6 bh 0.008 3.000 50.000 0.004 - - - 3.000 4 Pas. Stop Kontak 25 bh 0.033 12.500 50.000 0.017 - - - 12.500 5 Pas. Instalasi Titik Api ( Kabel NYM 3 x 2.5 mm di dalam conduit ) 56 Ttk 0.432 16.800 30.000 0.129 - - - 16.800 6 Pas. Panel Box 3 phase + MCB 3 Group setara "Merlin Gerin" 1 bh 0.066 0.500 50.000 0.033 - - - 0.500 7 Pek. Pemasangan KWH 15.000 VA 15000 va 1.189 7,500.000 50.000 0.594 - - - 7,500.000

Jumlah A 1.797 0.812 - B LANTAI - 1 ( Elv + 7,00 )

1 Pas. Lampu SL 18 Watt 30 bh 0.066 - - - 15.000 50.000 0.033 15.000 2 Pas. Saklar Ganda 6 bh 0.008 - - - 3.000 50.000 0.004 3.000 3 Pas. Stop Kontak 25 bh 0.033 - - - 12.500 50.000 0.017 12.500 4 Pas. Instalasi Titik Api ( Kabel NYM 3 x 2.5 mm di dalam conduit ) 55 Ttk 0.424 - - - 27.500 50.000 0.212 27.500 5 Pas. Panel Box 3 phase + MCB 3 Group setara "Merlin Gerin" 1 bh 0.066 - - - 0.500 50.000 0.033 0.500

Jumlah B 0.597 - 0.298 C LANTAI - 2 ( Elv +10,50 )

1 Pas. Lampu Downlight PLC 18 Watt 26 bh 0.172 - - - - - - - 2 Pas. Lampu SL 18 Watt 11 bh 0.024 - - - - - - - 3 Pas. Saklar Ganda 7 bh 0.009 - - - - - - - 4 Pas. Stop Kontak 25 bh 0.033 - - - - - - - 5 Pas. Instalasi Titik Api ( Kabel NYM 3 x 2.5 mm di dalam conduit ) 62 Ttk 0.478 - - - - - - - 6 Pas. Panel Box 3 phase + MCB 3 Group setara "Merlin Gerin" 1 bh 0.066 - - - - - - -

Jumlah C 0.782 - - Sub Jumlah X 3.176 0.812 0.298

Page 18: Gedung Kelas_Minggu 14

NO. URAIAN PEKERJAAN

KONTRAK KEMAJUAN FISIK PEKERJAAN

VOLUME BOBOT MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT VOLUME PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN % PELAKSANAAN

1 2 3 4 5 6 7 8 9 10 11

XI PEKERJAAN PENGECATAN1 Pek. Cat Tembok dan Kolom ( interior ) 1169.15 m2 1.371 - - - - - - - 2 Pek. Cat Tembok dan Kolom Wheater Shield (exterior) 779.36 m2 1.182 - - - - - - - 3 Pek. Cat Expose Beton Plat Dak ( interior ) 463.41 m2 0.544 - - - - - - - 4 Pek. Cat Plafond 267.44 m2 0.207 - - - - - - - 5 Pek. Cat Kayu 28.56 m2 0.058 - - - - - - -

Sub Jumlah XI 3.362 - - XII PEKERJAAN PENANGKAL PETIR

1 Splitzen tembaga Ø 1" c/w pipa GIP Ø 1" tinggi 1 m 2 bh 0.022 - - - - - - - 2 Kabel BC 50 mm2 40 m' 0.132 - - - - - - - 3 Pipa PVC Ø 1" 20 m' 0.009 - - - - - - - 4 Klem kabel BC 1 lot 0.011 - - - - - - - 5 Pas. Batu Bata, Plasteran, Acian, Tutup Plat Beton Bak Kontrol 1 bh 0.022 - - - - - - - 6 Pentanahan (copper rod Ø 1", tahanan 0,5 ohm) 1 ttk 0.055 - - - - - - - 7 Material bantu 1 lot 0.033 - - - - - - - 8 Testing & Commissioning 1 lot 0.088 - - - - - - -

Sub Jumlah XII 0.372 - - XIII PENGADAAN AIR BERSIH BANGUNAN

1 Sumur Bor Sedalam 50 m' 50 m' 0.220 50.000 100.000 0.220 - - - 50.000 2 Pipa Cesing PVC AW ø 4" 36 m' 0.143 36.000 100.000 0.143 - - - 36.000 3 Roof Tank Kapasitas 0,5 m3 setara Tedmond 2 bh 0.088 - - - - - - - 4 Pompa Air Setara Shimizu PC502BIT 1 unit 0.088 1.000 100.000 0.088 - - - 1.000 5 Pipa Hisap PVC AW ø 1" 88 m' 0.092 88.000 100.000 0.092 - - - 88.000 6 Pipa Distribusi PVC AW ø 3/4" 16 m' 0.011 - - - - - - - 7 Rumah Pompa 1 unit 0.044 - - - - - - -

Sub Jumlah XIII 0.686 0.543 - XIV PEKERJAAN LAIN - LAIN

1 Steger Kerja/Skpolding 1 unit 0.330 1.000 100.000 0.330 - - - 1.000 2 Pek. Shaff 1 unit 0.110 - - - - - - - 3 Pek. Pembersihan Akhir 1 unit 0.066 - - - - - - -

Sub Jumlah XIV 0.506 0.330 -

JUMLAH KESELURUHAN PEKERJAAN = …………………… 100.000 59.905 3.652

Page 19: Gedung Kelas_Minggu 14

KEMENTERIAN KESEHATAN RIPOLITEKNIK KESEHATAN BENGKULU

PEKERJAAN : PEMBANGUNAN GEDUNG KELAS POLITEKNIK KESEHATAN BENGKULU

LAPORAN MINGGUAN KEGIATAN : PEMBANGUNAN GEDUNG KELAS

LOKASI : JL. INDRAGIRI No. 3 PADANG HARAPAN BENGKULU

TH. ANGGARAN : 2015

KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA

CV. SENTRA REKAYASA Minggu ke : 14 (Empat belas) Periode Ke : 30 Agustus s/d 05 September 2015 Bulan Ke : 4 ( EMPAT )

NO. URAIAN PEKERJAAN

KONTRAK KEMAJUAN FISIK PEKERJAAN

VOLUME BOBOT MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN %

1 2 3 4 5 6 7 8 9 10 11 12 13

I PEKERJAAN PERSIAPAN1 Pek. Pembersihan Lokasi 510 m2 0.253 510.000 100.000 0.253 - - - 510.000 100.000 0.253 2 Pek. Pengukuran/Pasangan Bauwplank 80 m' 0.192 80.000 100.000 0.192 - - - 80.000 100.000 0.192 3 Pek. Barak Kerja dan Gudang Bahan/Peralatan 1 unit 0.220 1.000 100.000 0.220 - - - 1.000 100.000 0.220 4 Biaya Administrasi / Dokumentasi dan Astek 1 unit 0.440 0.650 65.000 0.286 0.050 5.000 0.022 0.700 70.000 0.308 5 Pas. Papan Nama Proyek 1 unit 0.015 1.000 100.000 0.015 - - - 1.000 100.000 0.015 6 Biaya PPPK 1 unit 0.022 0.650 65.000 0.014 0.050 5.000 0.001 0.700 70.000 0.015

Sub Jumlah I 1.142 0.980 0.023 1.004 II PEKERJAAN TANAH DAN PASIR

1 Pek. Pemotongan Tanah 75 m3 0.207 75.000 100.000 0.207 - - - 75.000 100.000 0.207 2 Pek. Galian Tanah Pondasi 384.56 m3 1.063 384.560 100.000 1.063 - - - 384.560 100.000 1.063 3 Pek. Urugan Tanah Kembali 294.51 m3 0.483 294.510 100.000 0.483 - - - 294.510 100.000 0.483 4 Pek. Urugan Tanah Bawah Lantai 30.94 m3 0.051 30.940 100.000 0.051 - - - 30.940 100.000 0.051 5 Pek. Urugan Pasir Bawah pondasi Plat Menerus 17.92 m3 0.130 17.920 100.000 0.130 - - - 17.920 100.000 0.130 6 Pek. Urugan Pasir Bawah Lantai 19.76 m3 0.143 19.760 100.000 0.143 - - - 19.760 100.000 0.143 7 Pek. Urugan Pasir Bawah Rabat Keliling Bangunan 3.64 m3 0.026 - - - - - - - - -

Sub Jumlah II 2.103 2.077 - 2.077

Page 20: Gedung Kelas_Minggu 14

NO. URAIAN PEKERJAAN

KONTRAK KEMAJUAN FISIK PEKERJAAN

VOLUME BOBOT MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN %

1 2 3 4 5 6 7 8 9 10 11 12 13

III PEKERJAAN BETON MUTU K225A LANTAI BASEMEN ( Elv. ± 0,00 s/d + 3,50 )

1 Pek. Beton Lantai Kerja K. 100 Bawah Pondasi Plat T. 10 cm 8.96 m3 0.253 8.960 100.000 0.253 - - - 8.960 100.000 0.253 2 Pek. Beton Lantai Kerja K. 100 Bawah Lantai T. 6 cm 11.17 m3 0.316 11.170 100.000 0.316 - - - 11.170 100.000 0.316 3 Pek. Beton Rabat K. 100 Keliling Bangunan T. 8 cm 6.41 m3 0.181 - - - - - - - - - 4 Pek. Pondasi Siklop, 60% Beton Campuran 1Sp : 2Pb : 3Kr & 40% Batu Belah ø 60 26.16 m3 2.675 26.160 100.000 2.675 - - - 26.160 100.000 2.675 5 Pek. Beton Pondasi Plat Menerus Type P1 40.32 m3 4.823 40.320 100.000 4.823 - - - 40.320 100.000 4.823 6 Pek. Beton Balok Rib Pondasi Plat Menerus (30/50) 16.8 m3 3.585 16.800 100.000 3.585 - - - 16.800 100.000 3.585 7 Pek. Beton Tiang Pondasi Plat K.1 (35/35) 6.05 m3 1.725 6.050 100.000 1.725 - - - 6.050 100.000 1.725 8 Pek. Beton Sloof SL2 (20/30) 0.57 m3 0.110 0.570 100.000 0.110 - - - 0.570 100.000 0.110 9 Pek. Beton Sloof SL2 (30/40) 14.64 m3 2.988 14.640 100.000 2.988 - - - 14.640 100.000 2.988

10 Pek. Beton Kolom Praktis KP (13/13) 0.32 m3 0.111 0.160 50.000 0.056 - - - 0.160 50.000 0.056 11 Pek. Beton Kolom K.1 (35/35) 12.91 m3 3.680 12.910 100.000 3.680 - - - 12.910 100.000 3.680 12 Pek. Beton Kolom K.2 (25/25) 0.59 m3 0.177 0.590 100.000 0.177 - - - 0.590 100.000 0.177 13 Pek. Beton Balok BL. 1 (30/40) 12.24 m3 3.046 12.240 100.000 3.046 - - - 12.240 100.000 3.046 14 Pek. Beton Balok BL. 2 (30/40+ 12/80) 4.48 m3 1.243 4.480 100.000 1.243 - - - 4.480 100.000 1.243 15 Pek. Beton Balok BL. 3 (30/50) 5.4 m3 1.248 5.400 100.000 1.248 - - - 5.400 100.000 1.248 16 Pek. Beton Balok BA.2 (20/30) 0.58 m3 0.150 0.580 100.000 0.150 - - - 0.580 100.000 0.150 17 Pek. Beton Balok BA.1 (20/40) 1.92 m3 0.527 1.920 100.000 0.527 - - - 1.920 100.000 0.527 18 Pek. Beton Balok Bordes ( 20/30 ) 0.47 m3 0.102 0.470 100.000 0.102 - - - 0.470 100.000 0.102 19 Pek. Beton Balok Latei ( 13/13 ) 0.65 m3 0.223 0.650 100.000 0.223 - - - 0.650 100.000 0.223 20 Pek. Beton Lantai Basemen T. 12 cm 18.57 m3 1.847 18.570 100.000 1.847 - - - 18.570 100.000 1.847 21 Pek. Beton Plat/Dak Lantai T. 12 cm 18.54 m3 4.332 18.540 100.000 4.332 - - - 18.540 100.000 4.332 22 Pek. Beton Tangga dan Bordes T. 15 cm 2.35 m3 0.546 - - - 0.470 20.000 0.109 0.470 20.000 0.109 23 Pek. Beton Plat Cantilever T. 10 cm 1.52 m3 0.349 1.520 100.000 0.349 - - - 1.520 100.000 0.349

Jumlah A 34.237 33.454 0.109 33.563 B LANTAI - 1 ( Elv + 7,00 )

1 Pek. Beton Kolom Praktis KP (13/13) 0.32 m3 0.117 - - - - - - - - - 2 Pek. Beton Kolom K.1 (35/35) 12.91 m3 3.864 12.910 100.000 3.864 - - - 12.910 100.000 3.864 3 Pek. Beton Kolom K.2 (25/25) 0.59 m3 0.186 0.590 100.000 0.186 - - - 0.590 100.000 0.186 4 Pek. Beton Balok BL. 1A (30/40) 12.24 m3 3.198 12.240 100.000 3.198 - - - 12.240 100.000 3.198 5 Pek. Beton Balok BL. 1B (30/40+ 12/80) 4.48 m3 1.305 4.480 100.000 1.305 - - - 4.480 100.000 1.305 6 Pek. Beton Balok BL. 3 (30/50) 5.4 m3 1.310 5.400 100.000 1.310 - - - 5.400 100.000 1.310 7 Pek. Beton Balok BA.2 (20/30) 0.58 m3 0.158 0.580 100.000 0.158 - - - 0.580 100.000 0.158 8 Pek. Beton Balok BA.1 (20/40) 1.92 m3 0.554 1.920 100.000 0.554 - - - 1.920 100.000 0.554 9 Pek. Beton Balok Bordes ( 20/30 ) 0.48 m3 0.109 - - - - - - - - -

10 Pek. Beton Balok Latei ( 13/13 ) 0.61 m3 0.220 - - - - - - - - - 11 Pek. Beton Plat/Dak Lantai T. 12 cm 18.54 m3 4.549 18.540 100.000 4.549 - - - 18.540 100.000 4.549 12 Pek. Beton Tangga dan Bordes T. 15 cm 2.35 m3 0.574 - - - - - - - - - 13 Pek. Beton Plat Cantilever T. 10 cm 1.52 m3 0.366 1.520 100.000 0.366 - - - 1.520 100.000 0.366

Jumlah B 16.509 15.489 - 15.489

Page 21: Gedung Kelas_Minggu 14

NO. URAIAN PEKERJAAN

KONTRAK KEMAJUAN FISIK PEKERJAAN

VOLUME BOBOT MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN %

1 2 3 4 5 6 7 8 9 10 11 12 13

C LANTAI - 2 ( Elv +10,50 )1 Pek. Beton Kolom Praktis KP (13/13) 0.37 m3 0.138 - - - - - - - - - 2 Pek. Beton Kolom K.1 (35/35) 13.33 m3 4.066 11.331 85.000 3.456 1.999 15.000 0.610 13.330 100.000 4.066 3 Pek. Beton Balok BL (25/40) 1.26 m3 0.309 - - - 1.260 100.000 0.309 1.260 100.000 0.309 4 Pek. Beton Ring Balok RB (20/30) 4.92 m3 1.434 - - - 1.476 30.000 0.430 1.476 30.000 0.430 5 Pek. Beton Ring Balok RB.1 (20/30 + 12/80) 3.16 m3 1.008 - - - 0.948 30.000 0.302 0.948 30.000 0.302 6 Pek. Beton Ring Balok RB.2 (15/20) 0.45 m3 0.131 - - - - - - - - - 7 Pek. Beton Balok Latei ( 13/13 ) 0.61 m3 0.224 - - - - - - - - - 8 Pek. Beton Tangga T. 15 cm 1.07 m 0.266 - - - - - - - - - 9 Pek. Beton Plat /Dak Tandon T. 15 cm 1.6 m3 0.320 - - - 1.600 100.000 0.320 1.600 100.000 0.320

Jumlah C 7.895 3.456 1.971 5.427 Sub Jumlah III 58.641 52.399 2.080 54.479

IV PEKERJAAN PASANGANA LANTAI - BASEMEN ( Elv. ± 0,00 s/d + 3,50 )

1 Pek. Pasangan 1/2 Batu Bata 1 : 2 25.32 m2 0.109 25.320 100.000 0.109 - - - 25.320 100.000 0.109 2 Pek. Pasangan 1/2 Batu Bata 1 : 4 196.74 m2 0.780 186.903 95.000 0.741 - - - 186.903 95.000 0.741 3 Pek. Plesteran 1 : 2 50.63 m2 0.113 48.098 95.000 0.108 - - - 48.099 95.000 0.108 4 Pek. Plesteran 1 : 4 393.47 m2 0.809 373.797 95.000 0.768 - - - 373.797 95.000 0.768 5 Pek. Acian Dinding dan Kolom 677.06 m2 0.814 541.648 80.000 0.651 - - - 541.648 80.000 0.651 6 Pek. Acian Expose Plat Dak 226.15 m2 0.272 203.535 90.000 0.245 - - - 203.535 90.000 0.245 7 Pek. Pasangan Jalusi Lobang ( Batu Roster ) 5 bh 0.017 - - - - - - - - - 8 Pek. Pasangan Lantai Keramik 40/40 cm Kwalitas Baik 210.71 m2 1.751 - - - - - - - - - 9 Pek. Pasangan Lantai Keramik 20/20 cm Km/Wc 5.64 m2 0.046 - - - - - - - - -

10 Pek. Pasangan Dinding Keramik 20/25 cm Km/wc 26.67 m2 0.203 - - - - - - - - - 11 Pek. Pasangan Plin Keramik 10/40 cm 128.1 m' 0.198 - - - - - - - - - 12 Pek. Plasteran Rabat Beton Keliling Bangunan 80.08 m2 0.165 - - - - - - - - - 13 Pek. Acian Rabat Beton Keliling Bangunan 80.08 m2 0.096 - - - - - - - - - 14 Pek. Saluran Keliling Bangunan 77.6 m' 0.598 3.880 5.000 0.030 3.880 5.000 0.030 7.760 10.000 0.060 15 Pek. Bak Kontrol Pada Saluran Keliling Bangunan 4 unit 0.026 - - - - - - - - -

Jumlah A 5.997 2.651 0.030 2.681 B LANTAI - 1 ( Elv + 7,00 )

1 Pek. Pasangan 1/2 Batu Bata 1 : 4 222.16 m2 0.880 - - - 177.728 80.000 0.704 177.728 80.000 0.704 2 Pek. Plesteran 1 : 4 444.33 m2 0.913 - - - - - - - - - 3 Pek. Acian Dinding dan Kolom 677.29 m2 0.814 - - - - - - - - - 4 Pek. Acian Expose Plat Dak 226.15 m2 0.272 - - - 56.538 25.000 0.068 56.538 25.000 0.068 5 Pek. Pasangan Jalusi Lobang ( Batu Roster ) 5 bh 0.017 - - - - - - - - - 6 Pek. Reling Teras Pasangan Batu Bata 1 : 4 + Profilan 23.2 m' 0.128 - - - - - - - - - 7 Pek. Pasangan Plin Keramik 10/40 cm 143.37 m' 0.222 - - - - - - - - - 8 Pek. Pasangan Lantai Keramik 40/40 Kwalitas Baik 198.96 m2 1.653 - - - - - - - - - 9 Pek. Pasangan Lantai Keramik 20/20 Km/Wc 5.64 m2 0.046 - - - - - - - - -

10 Pek. Pasangan Dinding Keramik 20/25 Km/wc 26.67 m2 0.203 - - - - - - - - - Jumlah B 5.149 - 0.772 0.772

Page 22: Gedung Kelas_Minggu 14

NO. URAIAN PEKERJAAN

KONTRAK KEMAJUAN FISIK PEKERJAAN

VOLUME BOBOT MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN %

1 2 3 4 5 6 7 8 9 10 11 12 13

C LANTAI - 2 ( Elv +10,50 )1 Pek. Pasangan 1/2 Batu Bata 1 : 4 226.44 m2 0.897 - - - 113.220 50.000 0.449 113.220 50.000 0.449 2 Pek. Plesteran 1 : 4 452.89 m2 0.931 - - - - - - - - - 3 Pek. Acian Dinding dan Kolom 594.04 m2 0.714 - - - - - - - - - 4 Pek. Acian Expose Plat Dak 11.11 m2 0.013 - - - - - - - - - 5 Pek. Pasangan Jalusi Lobang ( Batu Roster ) 5 m2 0.017 - - - - - - - - - 6 Pek. Reling Teras Pasangan Batu Bata 1 : 4 + Profilan 23.2 m' 0.128 - - - - - - - - - 7 Pek. Pasangan Plin Keramik 10/40 cm 146.87 m' 0.227 - - - - - - - - - 8 Pek. Pasangan Lantai Keramik 40/40 Kwalitas Baik 198.96 m2 1.653 - - - - - - - - - 9 Pek. Pasangan Lantai Keramik 20/20 Km/Wc 5.64 m2 0.046 - - - - - - - - -

10 Pek. Pasangan Dinding Keramik 20/25 Km/wc 26.67 m2 0.203 - - - - - - - - - Jumlah C 4.830 - 0.449 0.449

Sub Jumlah IV 15.976 2.651 1.251 3.902 V PEKERJAAN KAYU, BESI, ALUMUNIUM & KACAA LANTAI - BASEMEN ( Elv. ± 0,00 s/d + 3,50 )

1 Pek. Kusen Pintu dan Jendela Profil Alumunium setara "ALEXINDO" 129.71 m' 0.531 - - - - - - - - - 2 Pek. Pintu Panil Kaca Raybend 8 mm Rangka Profil Alumunium Type P1 8.82 m2 0.328 - - - - - - - - - 3 Pek. Pintu Panil ACP Profil Alumunium Km/Wc Type P2 5.88 m2 0.246 - - - - - - - - - 4 Pek. Pintu Panil ACP Profil Alumunium Gudang P3 0.98 m2 0.041 - - - - - - - - - 5 Pek. Bovenlight Kaca Raybend 5 mm Rangka Casement 4.27 m2 0.159 - - - - - - - - - 6 Pek. Jendela Hidup Kaca Raybend 5 mm Rangka Casement 5.4 m2 0.201 - - - - - - - - - 7 Pek. Ventilasi Kaca Raybend 5 mm Rangka Casement 6.48 m2 0.241 - - - - - - - - - 8 Pek. Reling Tangga Stenliss Stile 6.5 m' 0.258 - - - - - - - - -

Jumlah A 2.006 - - - B LANTAI - 1 ( Elv + 7,00 )

1 Pek. Kusen Pintu dan Jendela Profil Alumunium setara "ALEXINDO" 126.13 m' 0.517 - - - - - - - - - 2 Pek. Pintu Panil Kaca Raybend 8 mm Rangka Profil Alumunium Type P1 8.82 m2 0.328 - - - - - - - - - 3 Pek. Pintu Panil ACP Rangka Alumunium Km/Wc Type P2 5.88 m2 0.246 - - - - - - - - - 4 Pek. Bovenlight Kaca Bening 5 mm Rangka Casement 4.27 m2 0.159 - - - - - - - - - 5 Pek. Jendela Hidup Kaca Bening 5 mm Rangka Casement 5.4 m2 0.201 - - - - - - - - - 6 Pek. Ventilasi Kaca Bening 5 mm Rangka Casement 6.48 m2 0.241 - - - - - - - - - 7 Pek. Reling Tangga Stenliss Stile 6.5 m' 0.258 - - - - - - - - -

Jumlah B 1.950 - - - C LANTAI - 2 ( Elv +10,50 )

1 Pek. Kusen Pintu dan Jendela Profil Alumunium setara "ALEXINDO" 164.07 m' 0.672 - - - - - - - - - 2 Pek. Pintu Panil Kaca Raybend 8 mm Rangka Profil Alumunium Type P1 8.82 m2 0.328 - - - - - - - - - 3 Pek. Pintu Panil ACP Rangka Alumunium Km/Wc Type P2 5.88 m2 0.246 - - - - - - - - - 4 Pek. Pintu Panil ACP Rangka Alumunium Type P2 1.47 m2 0.061 - - - - - - - - - 5 Pek. Bovenlight Kaca Bening 5 mm Rangka Casement 4.27 m2 0.159 - - - - - - - - - 6 Pek. Jendela Hidup Kaca Bening 5 mm Rangka Casement 5.4 m2 0.201 - - - - - - - - - 7 Pek. Ventilasi Kaca Bening 5 mm Rangka Casement 6.48 m2 0.241 - - - - - - - - - 8 Pek. Reling Tangga Stenliss Stile 3.6 m' 0.143 - - - - - - - - -

Jumlah C 2.052 - - - Sub Jumlah V 6.008 - - -

Page 23: Gedung Kelas_Minggu 14

NO. URAIAN PEKERJAAN

KONTRAK KEMAJUAN FISIK PEKERJAAN

VOLUME BOBOT MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN %

1 2 3 4 5 6 7 8 9 10 11 12 13

VI PEKERJAAN ATAP1 Pek. Rangka Atap Baja Ringan + Reng C. 75 R. 40/45 325.16 m2 1.646 - - - - - - - - - 2 Pas. Atap Genteng Metal Calor T.0,25 mm 336.8 m2 1.466 - - - - - - - - - 3 Pas. Nok Atas Bulat 42 m' 0.134 - - - - - - - - - 4 Pas. Listplank Papan 2,8/15 + 2,8/20 28.56 m2 0.075 - - - - - - - - -

Sub Jumlah VI 3.322 - - - VII PEKERJAAN PLAFOND

1 Pek. Pasangan Plafond Bagian Dalam Gypsum 9 mm 138.59 m2 0.294 - - - - - - - - - 2 Pek. Rangka Plafond Hollow 2/4 + 4/4 138.59 m2 0.571 - - - - - - - - - 3 Pek. Pasangan Plafond Bagian Luar Plywood 6 mm 128.85 m2 0.310 - - - - - - - - - 4 Pek. Kayu Rangka Plafond 128.85 m2 0.546 - - - - - - - - - 5 Pek. Pasangan List Plafond Kayu Profil 253.24 m' 0.221 - - - - - - - - -

Sub Jumlah VII 1.941 - - - VIII PEKERJAAN KUNCI / PENGGANTUNGA LANTAI - BASEMEN ( Elv. ± 0,00 s/d + 3,50 )

1 Pas. Kunci Double Cylinder setara "Dekson" 3 bh 0.029 - - - - - - - - - 2 Pas. Kunci Double Cylinder + Handle setara "Dekson" 5 bh 0.060 - - - - - - - - - 3 Pas. Engsel Pintu Alumunium setara "Dekson" 33 bh 0.051 - - - - - - - - - 4 Pas. Engsel Casement 10 " setara "Dekson" 39 ps 0.103 - - - - - - - - - 5 Pas. Engsel Casement 16 " setara "Dekson" 9 ps 0.030 - - - - - - - - - 6 Pas. Handel Pintu Alumunium 6 ps 0.020 - - - - - - - - - 7 Pas. Door closer Pintu Alumunium 6 bh 0.066 - - - - - - - - - 8 Pas. Gerendel Pintu Tanam setara "Dekson" 6 bh 0.012 - - - - - - - - - 9 Pas. Gerendel Jendela Casement setara "Dekson" 48 bh 0.085 - - - - - - - - -

Jumlah A 0.457 - - - B LANTAI - 1 ( Elv + 7,00 )

1 Pas. Kunci Double Cylinder setara "Dekson" 3 bh 0.029 - - - - - - - - - 2 Pas. Kunci Double Cylinder + Handle setara "Dekson" 4 bh 0.048 - - - - - - - - - 3 Pas. Engsel Pintu Alumunium setara "Dekson" 30 bh 0.047 - - - - - - - - - 4 Pas. Engsel Casement 10 " setara "Dekson" 39 ps 0.103 - - - - - - - - - 5 Pas. Engsel Casement 16 " setara "Dekson" 9 ps 0.030 - - - - - - - - - 6 Pas. Handel Pintu Alumunium 6 ps 0.020 - - - - - - - - - 7 Pas. Door closer Pintu Alumunium 6 bh 0.066 - - - - - - - - - 8 Pas. Gerendel Pintu Tanam setara "Dekson" 6 bh 0.012 - - - - - - - - - 9 Pas. Gerendel Jendela Casement setara "Dekson" 48 bh 0.085 - - - - - - - - -

Jumlah B 0.440 - - -

Page 24: Gedung Kelas_Minggu 14

NO. URAIAN PEKERJAAN

KONTRAK KEMAJUAN FISIK PEKERJAAN

VOLUME BOBOT MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN %

1 2 3 4 5 6 7 8 9 10 11 12 13

C LANTAI - 2 ( Elv +10,50 )1 Pas. Kunci Double Cylinder setara "Dekson" 3 bh 0.029 - - - - - - - - - 2 Pas. Kunci Double Cylinder + Handle setara "Dekson" 5 bh 0.060 - - - - - - - - - 3 Pas. Engsel Pintu Alumunium setara "Dekson" 33 bh 0.051 - - - - - - - - - 4 Pas. Engsel Casement 10 " setara "Dekson" 39 ps 0.103 - - - - - - - - - 5 Pas. Engsel Casement 16 " setara "Dekson" 9 ps 0.030 - - - - - - - - - 6 Pas. Handel Pintu Alumunium 6 ps 0.020 - - - - - - - - - 7 Pas. Door closer Pintu Alumunium 6 bh 0.066 - - - - - - - - - 8 Pas. Gerendel Pintu Tanam setara "Dekson" 6 bh 0.012 - - - - - - - - - 9 Pas. Gerendel Jendela Casement setara "Dekson" 48 bh 0.085 - - - - - - - - -

Jumlah C 0.457 - - - Sub Jumlah VIII 1.354 - - -

IX PEKERJAAN SANITASI DAN SANITAIRA LANTAI - BASEMEN ( Elv. ± 0,00 s/d + 3,50 )

1 Pas. Kloset Jongkok "setara American Standard" 2 bh 0.047 - - - - - - - - - 2 Pas. Wastafel "setara American Standard" 1 bh 0.083 - - - - - - - - - 3 Pas. Urinoir "setara American Standard" 2 bh 0.158 - - - - - - - - - 4 Pas. Kran Air Stanlis Stell 2 bh 0.006 - - - - - - - - - 5 Pas. Stop Kran 1 bh 0.004 - - - - - - - - - 6 Pas. Floor Drain 4 bh 0.011 - - - - - - - - - 7 Pas. Penyekat porslin 1 bh 0.033 - - - - - - - - - 8 Kaca Cermin uk 800 x 1.200 1 bh 0.011 - - - - - - - - - 9 Pek. Instalasi Air Bersih Pipa PVC ø 1/2" 8 m' 0.006 0.400 5.000 0.000 - - - 0.400 5.000 0.000

10 Pek. Instalasi Air Kotor Pipa PVC ø 2" 4 m' 0.008 0.200 5.000 0.000 - - - 0.200 5.000 0.000 11 Pek. Instalasi Air Kotor Pipa PVC ø 4" 4 m' 0.016 0.200 5.000 0.001 - - - 0.200 5.000 0.001 12 Pek. Septicktank + Resapan 1 unit 0.220 0.500 50.000 0.110 - - - 0.500 50.000 0.110

Jumlah A 0.602 0.112 - 0.112 B LANTAI - 1 ( Elv + 7,00 )

1 Pas. Kloset Jongkok "setara American Standard" 2 bh 0.047 - - - - - - - - - 2 Pas. Wastafel "setara American Standard" 1 bh 0.083 - - - - - - - - - 3 Pas. Urinoir "setara American Standard" 2 bh 0.158 - - - - - - - - - 4 Pas. Kran Air Stanlis Stell 2 bh 0.006 - - - - - - - - - 5 Pas. Stop Kran 1 bh 0.004 - - - - - - - - - 6 Pas. Floor Drain 4 bh 0.011 - - - - - - - - - 7 Pas. Penyekat porslin 1 bh 0.033 - - - - - - - - - 8 Kaca Cermin uk 800 x 1.200 1 bh 0.011 - - - - - - - - - 9 Pek. Instalasi Air Bersih Pipa PVC ø 1/2" 8 m' 0.006 - - - - - - - - -

10 Pek. Instalasi Air Kotor Pipa PVC ø 2" 8 m' 0.015 - - - - - - - - - 11 Pek. Instalasi Air Kotor Pipa PVC ø 4" 8 m' 0.032 - - - - - - - - -

Jumlah B 0.406 - - -

Page 25: Gedung Kelas_Minggu 14

NO. URAIAN PEKERJAAN

KONTRAK KEMAJUAN FISIK PEKERJAAN

VOLUME BOBOT MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN %

1 2 3 4 5 6 7 8 9 10 11 12 13

C LANTAI - 2 ( Elv +10,50 )1 Pas. Kloset Jongkok "setara American Standard" 2 bh 0.047 - - - - - - - - - 2 Pas. Wastafel "setara American Standard" 1 bh 0.083 - - - - - - - - - 3 Pas. Urinoir "setara American Standard" 2 bh 0.158 - - - - - - - - - 4 Pas. Penyekat porslin 1 bh 0.033 - - - - - - - - - 5 Pas. Kran Air Stanlis Stell 2 bh 0.006 - - - - - - - - - 6 Pas. Stop Kran 1 bh 0.004 - - - - - - - - - 7 Pas. Floor Drain 4 bh 0.011 - - - - - - - - - 8 Kaca Cermin uk 800 x 1.200 1 bh 0.011 - - - - - - - - - 9 Pek. Instalasi Air Bersih Pipa PVC ø 1/2" 4 m' 0.003 - - - - - - - - -

10 Pek. Instalasi Air Kotor Pipa PVC ø 2" 8 m' 0.015 - - - - - - - - - 11 Pek. Instalasi Air Kotor Pipa PVC ø 4" 8 m' 0.032 - - - - - - - - -

Jumlah C 0.403 - - - - Sub Jumlah IX 1.411 0.112 - 0.112

X PEKERJAAN INSTALASI LISTRIKA LANTAI - BASEMEN ( Elv. ± 0,00 s/d + 3,50 )

1 Pas. Lampu SL 18 Watt 31 bh 0.068 15.500 50.000 0.034 - - - 15.500 50.000 0.034 2 Pas. Saklar Tunggal 1 bh 0.001 0.500 50.000 0.001 - - - 0.500 50.000 0.001 3 Pas. Saklar Ganda 6 bh 0.008 3.000 50.000 0.004 - - - 3.000 50.000 0.004 4 Pas. Stop Kontak 25 bh 0.033 12.500 50.000 0.017 - - - 12.500 50.000 0.017 5 Pas. Instalasi Titik Api ( Kabel NYM 3 x 2.5 mm di dalam conduit ) 56 Ttk 0.432 16.800 30.000 0.129 - - - 16.800 30.000 0.129 6 Pas. Panel Box 3 phase + MCB 3 Group setara "Merlin Gerin" 1 bh 0.066 0.500 50.000 0.033 - - - 0.500 50.000 0.033 7 Pek. Pemasangan KWH 15.000 VA 15000 va 1.189 7,500.000 50.000 0.594 - - - 7,500.000 50.000 0.594

Jumlah A 1.797 0.812 - 0.812 B LANTAI - 1 ( Elv + 7,00 )

1 Pas. Lampu SL 18 Watt 30 bh 0.066 - - - 15.000 50.000 0.033 15.000 50.000 0.033 2 Pas. Saklar Ganda 6 bh 0.008 - - - 3.000 50.000 0.004 3.000 50.000 0.004 3 Pas. Stop Kontak 25 bh 0.033 - - - 12.500 50.000 0.017 12.500 50.000 0.017 4 Pas. Instalasi Titik Api ( Kabel NYM 3 x 2.5 mm di dalam conduit ) 55 Ttk 0.424 - - - 27.500 50.000 0.212 27.500 50.000 0.212 5 Pas. Panel Box 3 phase + MCB 3 Group setara "Merlin Gerin" 1 bh 0.066 - - - 0.500 50.000 0.033 0.500 50.000 0.033

Jumlah B 0.597 - 0.298 0.298 C LANTAI - 2 ( Elv +10,50 )

1 Pas. Lampu Downlight PLC 18 Watt 26 bh 0.172 - - - - - - - - - 2 Pas. Lampu SL 18 Watt 11 bh 0.024 - - - - - - - - - 3 Pas. Saklar Ganda 7 bh 0.009 - - - - - - - - - 4 Pas. Stop Kontak 25 bh 0.033 - - - - - - - - - 5 Pas. Instalasi Titik Api ( Kabel NYM 3 x 2.5 mm di dalam conduit ) 62 Ttk 0.478 - - - - - - - - - 6 Pas. Panel Box 3 phase + MCB 3 Group setara "Merlin Gerin" 1 bh 0.066 - - - - - - - - -

Jumlah C 0.782 - - - Sub Jumlah X 3.176 0.812 0.298 1.110

Page 26: Gedung Kelas_Minggu 14

NO. URAIAN PEKERJAAN

KONTRAK KEMAJUAN FISIK PEKERJAAN

VOLUME BOBOT MINGGU LALU MINGGU INI SAMPAI DENGAN MINGGU INI

VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT VOLUME PERSENTASE BOBOT PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN % PELAKSANAAN PELAKSANAAN %

1 2 3 4 5 6 7 8 9 10 11 12 13

XI PEKERJAAN PENGECATAN1 Pek. Cat Tembok dan Kolom ( interior ) 1169.15 m2 1.371 - - - - - - - - - 2 Pek. Cat Tembok dan Kolom Wheater Shield (exterior) 779.36 m2 1.182 - - - - - - - - - 3 Pek. Cat Expose Beton Plat Dak ( interior ) 463.41 m2 0.544 - - - - - - - - - 4 Pek. Cat Plafond 267.44 m2 0.207 - - - - - - - - - 5 Pek. Cat Kayu 28.56 m2 0.058 - - - - - - - - -

Sub Jumlah XI 3.362 - - - XII PEKERJAAN PENANGKAL PETIR

1 Splitzen tembaga Ø 1" c/w pipa GIP Ø 1" tinggi 1 m 2 bh 0.022 - - - - - - - - - 2 Kabel BC 50 mm2 40 m' 0.132 - - - - - - - - - 3 Pipa PVC Ø 1" 20 m' 0.009 - - - - - - - - - 4 Klem kabel BC 1 lot 0.011 - - - - - - - - - 5 Pas. Batu Bata, Plasteran, Acian, Tutup Plat Beton Bak Kontrol 1 bh 0.022 - - - - - - - - - 6 Pentanahan (copper rod Ø 1", tahanan 0,5 ohm) 1 ttk 0.055 - - - - - - - - - 7 Material bantu 1 lot 0.033 - - - - - - - - - 8 Testing & Commissioning 1 lot 0.088 - - - - - - - - -

Sub Jumlah XII 0.372 - - - XIII PENGADAAN AIR BERSIH BANGUNAN

1 Sumur Bor Sedalam 50 m' 50 m' 0.220 50.000 100.000 0.220 - - - 50.000 100.000 0.220 2 Pipa Cesing PVC AW ø 4" 36 m' 0.143 36.000 100.000 0.143 - - - 36.000 100.000 0.143 3 Roof Tank Kapasitas 0,5 m3 setara Tedmond 2 bh 0.088 - - - - - - - - - 4 Pompa Air Setara Shimizu PC502BIT 1 unit 0.088 1.000 100.000 0.088 - - - 1.000 100.000 0.088 5 Pipa Hisap PVC AW ø 1" 88 m' 0.092 88.000 100.000 0.092 - - - 88.000 100.000 0.092 6 Pipa Distribusi PVC AW ø 3/4" 16 m' 0.011 - - - - - - - - - 7 Rumah Pompa 1 unit 0.044 - - - - - - - - -

Sub Jumlah XIII 0.686 0.543 - 0.543 XIV PEKERJAAN LAIN - LAIN

1 Steger Kerja/Skpolding 1 unit 0.330 1.000 100.000 0.330 - - - 1.000 100.000 0.330 2 Pek. Shaff 1 unit 0.110 - - - - - - - - - 3 Pek. Pembersihan Akhir 1 unit 0.066 - - - - - - - - -

Sub Jumlah XIV 0.506 0.330 - 0.330

JUMLAH KESELURUHAN PEKERJAAN = …………………… 100.000 59.905 3.652 63.557

Page 27: Gedung Kelas_Minggu 14

BLN MINGGU KE TANGGAL

MINGGU 1 (Satu) 01 Juni s/d 06 Juni 20151 MINGGU 2 (Dua) 07 Juni s/d 13 Juni 2015

MINGGU 3 (Tiga) 14 Juni s/d 20 Juni 2015MINGGU 4 (Empat) 21 Juni s/d 27 Juni 2015

BULAN 1 ( SATU ) 01 Juni s/d 27 Juni 2015

2 MINGGU 5 (Lima) 28 Juni s/d 04 Juli 2015MINGGU 6 (Enam) 05 Juli s/d 11 Juli 2015MINGGU 7 (Tujuh) 12 Juli s/d 18 Juli 2015MINGGU 8 (Delapan) 19 Juli s/d 25 Juli 2015

BULAN 2 ( DUA ) 28 Juni s/d 25 Juli 2015

MINGGU 9 (Sembilan) 26 Juli s/d 01 Agustus 2015

3 MINGGU 10 (Sepuluh) 02 Agustus s/d 08 Agustus 2015

MINGGU 11(Sebelas) 09 Agustus s/d 15 Agustus 2015

MINGGU 12 (Dua belas) 16 Agustus s/d 22 Agustus 2015

BULAN 3 ( TIGA ) 26 Juli s/d 22 Agustus 2015

4 MINGGU 13 (Tiga belas) 23 Agustus s/d 29 Agustus 2015MINGGU 14 (Empat belas) 30 Agustus s/d 05 September 2015MINGGU 15 (Lima belas) 06 September s/d 12 September 2015MINGGU 16 (Enam belas) 13 September s/d 19 September 2015

BULAN 4 ( EMPAT ) 23 Agustus s/d 19 September 2015

MINGGU 17 (Tujuh belas) 20 September s/d 26 September 20155 MINGGU 18 (Delapan belas) 27 September s/d 03 Oktober 2015

MINGGU 19 (Sembilan belas) 04 Oktober s/d 10 Oktober 2015MINGGU 20 (Dua Puluh) 11 Oktober s/d 17 Oktober 2015MINGGU 21 (Dua Puluh Satu) 18 Oktober s/d 29 Oktober 2015

BULAN 5 ( LIMA ) 20 September s/d 29 Oktober 2015

Page 28: Gedung Kelas_Minggu 14

Mengetahui/Menyetujui : Disetujui Oleh:Pejabat Pembuat Komitmen Kontraktor Pelaksana

Politeknik Kesehatan Kemenkes RI CV. SENTRA REKAYASAProvinsi Bengkulu

NS. AGUNG RIYADI, S.Kep.M.Kes SUDARSONip. 19681007 198803 1 005 Direktur

Diperiksa/Disetujui Oleh:Pengelola Teknis

Dinas Pekerjaan Umum Provinsi Bengkulu

EDY IDHAM, STNip. 19620503 198703 1 014

Diperiksa/Disetujui Oleh:Pejabat Pelaksana Teknis Kegiatan

Dinas Pekerjaan Umum Kota Bengkulu

EMRALD BALAPUTRA, ST. MTNip. 19740809 200212 1 001

Page 29: Gedung Kelas_Minggu 14

BULAN BULAN NOMOR SURAT

01 - 06 Bengkulu, 06 Juni 2015 30/UKE-LAP/BKL/VI/20151 ( SATU ) 07 - 13 Bengkulu, 13 Juni 2015 33/UKE-LAP/BKL/VI/2015

14 - 20 Bengkulu, 20 Juni 2015 34/UKE-LAP/BKL/VI/201521 - 27 Bengkulu, 27 Juni 2015 36/UKE-LAP/BKL/VI/2015

37/UKE-LAP/BKL/VI/2015

2 ( DUA ) 28 - 04 Bengkulu, 04 Juli 2015 39/UKE-LAP/BKL/VII/201505 - 11 Bengkulu, 11 Juli 2015 41/UKE-LAP/BKL/VII/201518 - 12 Bengkulu, 18 Juli 2015 45/UKE-LAP/BKL/VII/201519 - 25 Bengkulu, 25 Juli 2015 48/UKE-LAP/BKL/VII/2015

49/UKE-LAP/BKL/VII/2015

3 ( TIGA ) 26 - 01 Bengkulu, 01 Agustus 2015 51/UKE-LAP/BKL/VIII/2015

02 - 18 Bengkulu, 08 Agustus 2015 54/UKE-LAP/BKL/VIII/2015

09 - 15 Bengkulu, 15 Agustus 2015 60/UKE-LAP/BKL/VIII/2015

16 - 22 Bengkulu, 22 Agustus 2015 66/UKE-LAP/BKL/VIII/2015

67/UKE-LAP/BKL/VIII/2015

4 ( EMPAT ) 23 - 29 Bengkulu, 29 Agustus 2015 68/UKE-LAP/BKL/VIII/201530 - 05 Bengkulu, 05 September 2015 69/UKE-LAP/BKL/IX/201506 - 12 Bengkulu, 12 September 2015 70/UKE-LAP/BKL/IX/201513 - 19 Bengkulu, 19 September 2015 72/UKE-LAP/BKL/IX/2015

73/UKE-LAP/BKL/IX/2015

5 ( LIMA ) 20 - 26 Bengkulu, 26 September 2015 74/UKE-LAP/BKL/IX/201527 - 03 Bengkulu, 03 Oktober 2015 75/UKE-LAP/BKL/X/201504 - 10 Bengkulu, 10 Oktober 2015 76/UKE-LAP/BKL/X/201511 - 17 Bengkulu, 17 Oktober 2015 78/UKE-LAP/BKL/X/201518 - 29 Bengkulu, 29 Oktober 2015 84/UKE-LAP/BKL/X/2015

85/UKE-LAP/BKL/X/2015

Page 30: Gedung Kelas_Minggu 14

Dibuat Oleh :Konsultan Pengawas

CV. UTAKA ESSA KONSULTAN

ZULFIKAR HANANI, STInspector

Page 31: Gedung Kelas_Minggu 14

Monday, June 1, 2015150

Thursday, October 29, 2015

Page 32: Gedung Kelas_Minggu 14

SATUAN KERJA : Pengembangan Kawasan Pemukiman dan Penataan Bangunan BengkuluPELAKSANA KEGIATAN : Pengembangan Kawasan Pemukiman BengkuluNAMA PAKET : Pembangunan Infrastruktur Permukiman Kumuh Nelayan Kawasan Melebero,Sumur Melele ,Bajak,Berkas dan Kampung Melayu Kota bengkuluLOKASI : Kawasan Kota Bengkulu

NO.MATA PEMBY URAIAN

a b

DIVISI 1.UMUM

1.2 Mobilisasi

DIVISI 2.DRAINASE

2.1 Galian Untuk Selokan Drainase dan Saluran Air2.2 Pasangan Batu Dengan Mortar 2.3 Gorong-Gorong dan Drainase Beton2.4 Drainase Porous

DIVISI 3.PEKERJAAN TANAH

3.1 Galian Biasa 3.2 Timbunan Biasa

3.2.1 Timbunan Pilihan/Sirtu3.2.2 Timbunan Pilihan/Telfort3.3 Penyiapan Badan Jalan3.4 Pembersihan dan Pengupasan Lahan

DIVISI 4.PELEBARAN PERKERASAN DAN BAHU JALAN

4.1 Pelebaran Pekerjaan4.2 Bahu Jalan

DIVISI 5.PERKERASAN BERBUTIR

5.1 Lapis Pondasi Agregat 5.1.1 Lapis Pondasi Agregat Kelas B5.2 Lapis Pondasi Perkerasan Tanpa Penutup Semen

Jumlah Harga Pekejaan DIVISI 1 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

Jumlah Harga Pekerjaan DIVISI 2(masuk pada Rekapitulasi Perkiraan Harga Pekerjaan )

Jumlah Pekerjaan DIVISI 3 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

Jumlah Pekerjaan DIVISI 4 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

Page 33: Gedung Kelas_Minggu 14

5.2.1 Lapis Pondasi Agregat Kelas c5.3 Perkerasan Beton Semen

5.3.1 Perkerasan Beton Semen Dengan Anyaman Tulangan Tunggal5.4 Lapis Pondasi Semen Tanah5.5 Lapis Beton Semen Pondasi dan Pondasi Bawah (cement Treated Base

(CTB) dan Cement Treated Sub Base (CTSB)

DIVISI 6. PERKERASAN ASPAL

6.1 Lapis Resap Pengikat Dan Lapis Pengikat6.2.2 Laburan Aspal Satu Lapis (burtu) dan Laburan Aspal Dua Lapis (Burda)6.2.3 Bahan Aspal Untuk Pekerjaan Pelaburan6.3 Campuran Beraspal Panas6.4 Lasbutag dan Latasbusir6.5 Campuran Aspal Dingin Untuk Pelapisan6.6 Lapis Permukaan Penetrasi Macadam6.7 Pemeliharaan Dengan Leburan Aspal

DIVISI 7. STRUKTUR

7.1.5 Beton K.1257.2 Beton Pratekan7.3 Baja Tulangan7.4 Baja Struktur7.5 Pemasangan Jembatan Kerangka Baja7.6 Pondasi Tiang7.7 Pondasi Sumuran7.8 Adukan Semen7.9 Pasangan Batu

7.10 Pasangan Batu Kosong dan Beronjong7.11 Sambungan Ekspansi (Ekspansion Joint)7.12 Perletakan Logam 7.13 Sandaran (Ralling)7.14 Papan Nama Jembatan 7.15 Pembongkaran Struktur 7.16 Drainase Lantai Jembatan

DIVISI 8. PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR

8.1 Pengembalian Kondisi Perkerasan Lama8.2 Pengembalian KonDISI Bahu Jalan Pada Perkerasan Aspal

Jumlah Pekerjaan DIVISI 5 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

Jumlah Pekerjaan DIVISI 6 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

Jumlah Pekerjaan DIVISI 7 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

Page 34: Gedung Kelas_Minggu 14

8.3 Pengembalian Kondisi Selokan Saluran Air,Galian,Timbunan, dan Penghijauan 8.4 Perlengkapan Jalan dan Pengatur Lalu Lintas8.5 Pengembalian Kondisi Jembatan8.6 Korb Pracetak Pemisah Jalan ( concroto Barrior )8.7 Penerangan Jalan dan Pekerjaan Elektrikal8.8 Pagar Pemisah Pedestrian

DIVISI 9. PEKERJAAN HARIAN

9.1 Pekerjaan Harian

DIVISI 10.PEKERJAAN PEMELIHARAAN RUTIN

10.1 Pemeliharaan Rutin Perkerasan ,Bahu Jalan,Drainase,Perlengkapan Jalan & Jembatan10.2 Pemeliharaan Jalan Samping Dan Jembatan

Jumlah Pekerjaan DIVISI 9 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

Jumlah Pekerjaan DIVISI 10 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

Page 35: Gedung Kelas_Minggu 14
Page 36: Gedung Kelas_Minggu 14

Pengembangan Kawasan Pemukiman dan Penataan Bangunan BengkuluPengembangan Kawasan Pemukiman BengkuluPembangunan Infrastruktur Permukiman Kumuh Nelayan Kawasan Melebero,Sumur Melele ,Bajak,Berkas dan Kampung Melayu Kota bengkulu

URAIAN SAT VOLUME

b c d

DIVISI 1.UMUM

Mobilisasi Ls 1.00

DIVISI 2.DRAINASE

m3 6,097.40m3 5,020.28m3m1m1

DIVISI 3.PEKERJAAN TANAH

Galian Biasa m3 193.56Timbunan Biasa m3Timbunan Pilihan/Sirtu m3Timbunan Pilihan/Telfort m3 169.75Penyiapan Badan Jalan m2 5,820.00Pembersihan dan Pengupasan Lahan m2

DIVISI 4.PELEBARAN PERKERASAN DAN BAHU JALAN

Pelebaran Pekerjaan M3Bahu Jalan M3

DIVISI 5.PERKERASAN BERBUTIR

Lapis Pondasi Agregat M3Lapis Pondasi Agregat Kelas B M3 1,942.63Lapis Pondasi Perkerasan Tanpa Penutup Semen M3

(masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

(masuk pada Rekapitulasi Perkiraan Harga Pekerjaan )

(masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

(masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

Page 37: Gedung Kelas_Minggu 14

Lapis Pondasi Agregat Kelas c M3 612.50Perkerasan Beton Semen M3 376.30Perkerasan Beton Semen Dengan Anyaman Tulangan Tunggal M3Lapis Pondasi Semen Tanah M3Lapis Beton Semen Pondasi dan Pondasi Bawah (cement Treated Base M3

DIVISI 6. PERKERASAN ASPAL

Lapis Resap Pengikat Dan Lapis Pengikat LiterLaburan Aspal Satu Lapis (burtu) dan Laburan Aspal Dua Lapis (Burda) M2Bahan Aspal Untuk Pekerjaan Pelaburan LiterCampuran Beraspal Panas TonLasbutag dan Latasbusir M2Campuran Aspal Dingin Untuk Pelapisan M3Lapis Permukaan Penetrasi Macadam M3 1,412.16Pemeliharaan Dengan Leburan Aspal M3

DIVISI 7. STRUKTUR

Beton K.125 M3 23.52Beton Pratekan M3Baja Tulangan Kg 6,806.10Baja Struktur KgPemasangan Jembatan Kerangka Baja BuahPondasi Tiang M'Pondasi Sumuran M'Adukan Semen M3Pasangan Batu M3 317.82Pasangan Batu Kosong dan Beronjong M3Sambungan Ekspansi (Ekspansion Joint) M'Perletakan Logam BuahSandaran (Ralling) M'Papan Nama Jembatan BuahPembongkaran Struktur M3Drainase Lantai Jembatan M'

DIVISI 8. PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR

Pengembalian Kondisi Perkerasan Lama M3Pengembalian KonDISI Bahu Jalan Pada Perkerasan Aspal M3

(masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

(masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

(masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

Page 38: Gedung Kelas_Minggu 14

Pengembalian Kondisi Selokan Saluran Air,Galian,Timbunan, dan Penghijauan M2Perlengkapan Jalan dan Pengatur Lalu Lintas BuahPengembalian Kondisi Jembatan M2Korb Pracetak Pemisah Jalan ( concroto Barrior ) M'Penerangan Jalan dan Pekerjaan Elektrikal BuahPagar Pemisah Pedestrian M'

DIVISI 9. PEKERJAAN HARIAN

Pekerjaan Harian Jam

DIVISI 10.PEKERJAAN PEMELIHARAAN RUTIN

Pemeliharaan Rutin Perkerasan ,Bahu Jalan,Drainase,Perlengkapan Jalan & Jembatan LsPemeliharaan Jalan Samping Dan Jembatan Ls

(masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

(masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

Page 39: Gedung Kelas_Minggu 14
Page 40: Gedung Kelas_Minggu 14

Pengembangan Kawasan Pemukiman dan Penataan Bangunan BengkuluPengembangan Kawasan Pemukiman BengkuluPembangunan Infrastruktur Permukiman Kumuh Nelayan Kawasan Melebero,Sumur Melele ,Bajak,Berkas dan Kampung Melayu Kota bengkulu

BOBOT MINGGU LALU

VOLUME PERSENTASE BOBOT PELAKSANAAN PELAKSANAAN %

g h i j

0.500 0

0.500

1.70645.484

47.19

0.104

0.5630.2510.000

0.9

6.102

Page 41: Gedung Kelas_Minggu 14

1.6945.432

13.229

33.580

33.580

0.219

1.689

2.676

4.585

Page 42: Gedung Kelas_Minggu 14
Page 43: Gedung Kelas_Minggu 14

MINGGU INI SAMPAI DENGAN MINGGU INI VOLUME PERSENTASE BOBOT VOLUME

PELAKSANAAN PELAKSANAAN % PELAKSANAAN k l m n

Page 44: Gedung Kelas_Minggu 14
Page 45: Gedung Kelas_Minggu 14
Page 46: Gedung Kelas_Minggu 14

SAMPAI DENGAN MINGGU INI PERSENTASE BOBOT

PELAKSANAAN % o p

Page 47: Gedung Kelas_Minggu 14
Page 48: Gedung Kelas_Minggu 14
Page 49: Gedung Kelas_Minggu 14

SATUAN KERJA : Pengembangan Kawasan Pemukiman dan Penataan Bangunan BengkuluPELAKSANA PEKERJAAN : MOBILISASI

NO URAIAN

A Sewa Tanah

B PERALATANPeriksa Lembar 1.2-1

C FASILITAS KONTRAKTOR1 Base Camp2 Kantor3 Barak4 Bengkel5 Gudang,dan lain-lain

D FASILITAS LABORATORIUM1 Ruang Laboratorium2 Peralatan Laboratorium3 Perabotan dan Layanan

E MOBILISASI LAINYAE.I PEKERJAAN DARURAT

1 Jembatan Darurat2 Perkuatan Jembatan Lama3 Pemeliharaan Jalan Kerja/Samping

E.II LAIN-LAIN1 Papan Nama Proyek2 As Built Drawing3 Administrasi dan Dokumen

F DEMOBILISASI

Total Biaya MobilisasiCatatan : Jumlah yang tercantum pada masing -masing item mobilisasi di atas sudah termasuk

over head dan laba serta seluruh pajak dan bea (kecuali PPn), dan pengeluaran lainya

Page 50: Gedung Kelas_Minggu 14

Pengembangan Kawasan Pemukiman dan Penataan Bangunan BengkuluMOBILISASI

Lembar 1.2-1

URAIAN SATUAN VOLHARGA JUMLAHSATUAN HARGA

(Rp) (Rp)

Sewa Tanah m2

PERALATANLs 1.00 17,500,000.00 17,500,000.00 Periksa Lembar 1.2-1

FASILITAS KONTRAKTORLs 3.00 2,500,000.00 7,500,000.00 LsLsLsLs

FASILITAS LABORATORIUMm2

Peralatan Laboratorium setPerabotan dan Layanan set

MOBILISASI LAINYAPEKERJAAN DARURAT

Perkuatan Jembatan LamaPemeliharaan Jalan Kerja/Samping

LAIN-LAINBuah 2.00 500,000.00 1,000,000.00

Ls 3.00 750,000.00 2,250,000.00 Administrasi dan Dokumen Ls 1.00 5,000,000.00 5,000,000.00

DEMOBILISASI Ls 1.00 12,000,000.00 12000000

Total Biaya Mobilisasi 45,250,000.00 Jumlah yang tercantum pada masing -masing item mobilisasi di atas sudah termasukover head dan laba serta seluruh pajak dan bea (kecuali PPn), dan pengeluaran lainya

Page 51: Gedung Kelas_Minggu 14

Pengembangan Kawasan Pemukiman dan Penataan Bangunan BengkuluMOBILISASI

Lembar 1.2-1JUMLAHHARGA

(Rp)

17,500,000.00

7,500,000.00

1,000,000.00 2,250,000.00 5,000,000.00

12000000

45,250,000.00

Page 52: Gedung Kelas_Minggu 14

PEMBAYARAN NO. : Pengembangan Kawasan Pemukiman dan Penataan Bangunan BengkuluPELAKSANA PEKERJAAN : MOBILISASI

NO JENIS ALATKODE

SATUANALAT

B PERALATAN

1 CONCRETE MIXER 0.3-0.6 M3 E06 Unit2 CRANE 10-15 TON E07 Unit3 DUMP TRUCK 3-4 M3 E08 Unit4 DUMP TRUCK E09 Unit5 EXAVATO 80-140 HP E10 Unit6 FLAT BED TRUCK 3-4 M3 E11 Unit7 GENERATOR SET E12 Unit8 MOTOR GREDER SET E13 Unit9 MOTOR GREDER > 100 HP E14 Unit10 TRACK LOADER 75-100 HP E15 Unit11 WHEEK LOADER 1.0-1.6 M3 E16 Unit12 THREE WHEEL ROLLER 6-8 T E17 Unit13 TANDEM ROLLER 6-8 T E18 Unit14 VIBRATORY ROLLER 10-12 T E19 Unit15 CONCRETE VIBRATOR E20 Unit16 STONE CRUSHER E21 Unit17 WATER PUMP 70-100 mm E22 Unit18 WATER TANKER 3000-4500 L E23 Unit19 PEDESTRIAN ROLLER E24 Unit20 TAMPER E25 Unit

Total Untuk Item B Pada Lembar 1

Page 53: Gedung Kelas_Minggu 14
Page 54: Gedung Kelas_Minggu 14

Pengembangan Kawasan Pemukiman dan Penataan Bangunan BengkuluMOBILISASI

Lembar 1.2-2

VOLHARGA HARGASATUAN SATUAN

(Rp) (Rp)

15.00 500,000.00 7,500,000.00

2.00 5,000,000.00 10,000,000.00

Total Untuk Item B Pada Lembar 1 17,500,000.00

Page 55: Gedung Kelas_Minggu 14
Page 56: Gedung Kelas_Minggu 14

Pengembangan Kawasan Pemukiman dan Penataan Bangunan BengkuluMOBILISASI

Page 57: Gedung Kelas_Minggu 14

REKAPITULASIDAFTAR KUANTITAS DAN HARGA

PEMBAYARAN NO. : Pengembangan Kawasan Permukiman dan Penataan Bangunan BengkuluPELAKSANA PEKERJAAN : Pengembangan Kawasan Permukima BengkuluNAMA PAKET : Pembangunan Infrastruktur Permukiman Kumuh Nelayan Kawasan

Malebero, Sumer Melele, Bajak, Berkas Dan Kampung Melayu Kota BengkuluLOKASI : Kawasan Kota Bengkulu

NO. DIVISI URAIAN

1 UMUM2 DRAINASE3 PEKERJAAN TANAH4 PEBAIKAN TEPI PERKERASAN DAN BAHU JALAN5 PEKERASAN BERBUTIR6 PERKERASAN ASPAL7 STRUKTUR8 PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR9 PEKERJAAN HARIAN

10 PEKERJAAN PEMELIHARAAN RUTIN

(A) JUMLAH HARGA PEKERJAAN (termasuk Biaya Umum dan Keuntungan)

(B) PAJAK PERTAMBAHAN NILAI (PPn) = 10% x (A)

(C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B)

(D) JUMLAH TOTAL HARGA PEKERJAAN = ( DIBULATKAN )

Page 58: Gedung Kelas_Minggu 14

Pengembangan Kawasan Permukiman dan Penataan Bangunan BengkuluPengembangan Kawasan Permukima BengkuluPembangunan Infrastruktur Permukiman Kumuh Nelayan Kawasan Malebero, Sumer Melele, Bajak, Berkas Dan Kampung Melayu Kota Bengkulu

JUMLAH HARGA (Rp)

45,250,000.00 4,268,235,536.65 82,939,877.73

1,196,498,831.49 3,037,220,918.12 414,690,633.88

9,044,835,797.87

Page 59: Gedung Kelas_Minggu 14

Pengembangan Kawasan Permukiman dan Penataan Bangunan BengkuluPengembangan Kawasan Permukima Bengkulu