format opname pekerjaan borongan dan upah mingguan proyek

69
OPNAME No. : NO PEKERJAAN BORONGAN BOBOT MG LL Mandor : WONDO Papan Bouwplank 100% Pekerjaan Pondasi Telapak - Galian tanah 100% - Urugan tanah kembali + pemadatan 100% - Pasir urug bawah pondasi 10 cm 100% - Lantai kerja 5 cm 100% - Beton 100% - Bekisting pasangan batako 100% - Besi pondasi tapak 100% Pekerjaan Pondasi Batu Kali - Galian tanah 100% - Urugan tanah kembali + pemadatan 100% - Pasangan batu kali 100% - Pasir urug bawah pondasi 10 cm 100% Pekerjaan Tie Beam / Sloof - Beton K225 100% - Besi beton 100% - Bekisting 100% Struktur Kolom lantai dasar - Beton K225 100% - Bekisting 100% - Besi beton 100% Struktur Balok + Janggutan Lantai Atas - Beton K225 100% - Besi beton standard SNI 100% - Bekisting 100% Struktur Plat lantai Atas - Beton K225 100% - Besi beton standard SNI 100%

Upload: taurina-jemmy-irwanto

Post on 14-Aug-2015

9.371 views

Category:

Documents


1.916 download

DESCRIPTION

opname

TRANSCRIPT

Page 1: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

OPNAME PEKERJAAN BORONGANNo. : /SBP-OPB/ / /2012

NO PEKERJAAN BORONGANBOBOT BOBOTMG LL MG INI

Mandor : WONDO

Papan Bouwplank 100% 0%

Pekerjaan Pondasi Telapak

- Galian tanah 100% 0%

- Urugan tanah kembali + pemadatan 100% 0%

- Pasir urug bawah pondasi 10 cm 100% 0%

- Lantai kerja 5 cm 100% 0%

- Beton 100% 0%

- Bekisting pasangan batako 100% 0%

- Besi pondasi tapak 100% 0%

Pekerjaan Pondasi Batu Kali

- Galian tanah 100% 0%

- Urugan tanah kembali + pemadatan 100% 0%

- Pasangan batu kali 100% 0%

- Pasir urug bawah pondasi 10 cm 100% 0%

Pekerjaan Tie Beam / Sloof

- Beton K225 100% 0%

- Besi beton 100% 0%

- Bekisting 100% 0%

Struktur Kolom lantai dasar

- Beton K225 100% 0%

- Bekisting 100% 0%

- Besi beton 100% 0%

Struktur Balok + Janggutan Lantai Atas

- Beton K225 100% 0%

- Besi beton standard SNI 100% 0%

- Bekisting 100% 0%

Struktur Plat lantai Atas

- Beton K225 100% 0%

- Besi beton standard SNI 100% 0%

Page 2: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

- Bekisting 100% 0%

Struktur Canopy Lantai Atas

- Beton K225 100% 0%

- Besi beton standard SNI 100% 0%

- Bekisting 100% 0%

Struktur Kolom lantai Atas

- Beton K225 100% 0%

- Bekisting 100% 0%

- Besi beton 100% 0%

Struktur Plat lantai bawah

- Pemadatan tanah 100% 0%

- Rollag bata teras 100% 0%

- Plastik cor 100% 0%

- Beton K225 Plat t = 8 cm 100% 0%

- Besi Wire Mesh M - 6 standard SNI ( 1 Lapis ) 100% 0%

- Bekisting 100% 0%

Struktur Balok + Janggutan Atap

- Beton K225 100% 0%

- Besi beton standard SNI 100% 0%

- Bekisting 100% 0%

Struktur Plat Atap

- Beton K225 100% 0%

- Besi beton standard SNI 100% 0%

- Bekisting 100% 0%

Struktur Canopy Atap

- Beton K225 100% 0%

- Besi beton standard SNI 100% 0%

- Bekisting 100% 0%

Pekerjaan Pagar Luar Depan dan belakang

Pekerjaan Pondasi Batu Kali

- Galian tanah 100% 0%

- Urugan tanah kembali + pemadatan 100% 0%

- Pasangan batu kali 100% 0%

- Pasir urug bawah pondasi 10 cm 100% 0%

Pekerjaan Tie Beam / Sloof, kolom praktis dan Ringbalk

- Beton K225 100% 0%

- Besi beton standard SNI 100% 0%

- Bekisting 100% 0%

Pekerjaan pasangan dinding bata top level + 0,60 m 100% 0%

Screeding + Kawat Ayam Lantai Atas

Dak dan canopy 0%

Page 3: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

Screeding + Kawat Ayam Pelat Atap

Dak dan canopy 0%

PEKERJAAN DINDING + FINISHING

Pekerjaan Dinding Lantai - 1

Trasram pasangan bata , h = 30 cm 100% 0%

Pekerjaan pasangan dinding bata 100% 0%

Kolom praktis 11x11 cm 100% 0%

Balok latei termasuk Finishing openingnya. 100% 0%

Pekerjaan plesteran dinding + bawah tangga 20% 0%

Pekerjaan acian dinding + bawah tangga dengan MU 250 0% 0%

Pekerjaan plesteran + aci + tali air 2 cm pada dinding + 0% 0%

cat weathercoat `

Pekerjaan Dinding Lantai - 2

Trasram pasangan bata , h = 30 cm 0% 0%

Pekerjaan pasangan dinding bata 0% 50%

Kolom praktis 11x11 cm 0% 50%

Balok latei termasuk Finishing openingnya. 0% 0%

Pekerjaan plesteran dinding + bawah tangga 0% 0%

Pekerjaan acian dinding + bawah tangga dengan MU 250 0% 0%

Pekerjaan plesteran + aci + tali air 2 cm pada dinding + 0% 0%

cat weathercoat `

Struktur Tangga Utama

Beton K225 0% 0%

Besi beton standard SNI 0% 0%

Bekisting 0% 0%

Struktur Tangga Jemuran

Beton K225 0% 0%

Besi beton standard SNI 0% 0%

Bekisting 0% 0%

Disetujui Oleh :

PM

Page 4: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

Halaman Dari :Proyek xxxxxxxx RESIDENCELokasiMinggu Ke 17 - 18Tanggal 28 MEI S/D 6 JUNI

OPNAME PEKERJAAN BORONGANNo. : /SBP-OPB/ / /2012

VOLUME QUANTITY

HARGA SAT JUMLAH KETERANGANMg Ini

60.48 - 7,500.00 - SUDAH TERBAYAR

21.60 - 25,000.00 - SUDAH TERBAYAR 14.88 - 7,000.00 - SUDAH TERBAYAR 0.96 - 9,500.00 - SUDAH TERBAYAR 0.34 - 80,000.00 - SUDAH TERBAYAR 1.33 - 100,000.00 - SUDAH TERBAYAR 4.36 - 20,000.00 - SUDAH TERBAYAR 147.63 - 1,080.00 - SUDAH TERBAYAR

76.94 - 18,000.00 - SUDAH TERBAYAR 13.67 - 7,000.00 - SUDAH TERBAYAR 39.98 - 75,000.00 - SUDAH TERBAYAR 12.12 - 9,500.00 - SUDAH TERBAYAR

10.13 - 100,000.00 - SUDAH TERBAYAR 1,049.70 - 1,080.00 - SUDAH TERBAYAR 84.82 - 30,000.00 - SUDAH TERBAYAR

47.68 - 100,000.00 - SUDAH TERBAYAR 1.16 - 30,000.00 - SUDAH TERBAYAR 1,403.89 - 1,080.00 - SUDAH TERBAYAR

13.26 - 100,000.00 - SUDAH TERBAYAR 1,764.13 - 1,080.00 - SUDAH TERBAYAR 136.97 - 30,000.00 - SUDAH TERBAYAR

- - 100,000.00 - SUDAH TERBAYAR - - 1,080.00 - SUDAH TERBAYAR

Page 5: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

- - 30,000.00 - SUDAH TERBAYAR

4.08 - 100,000.00 - SUDAH TERBAYAR 365.98 - 1,080.00 - SUDAH TERBAYAR 35.19 - 30,000.00 - SUDAH TERBAYAR

2.80 - 100,000.00 - SUDAH TERBAYAR 53.00 - 30,000.00 - SUDAH TERBAYAR 591.60 - 1,080.00 - SUDAH TERBAYAR

157.03 - 3,000.00 - SUDAH TERBAYAR 16.00 - 15,000.00 - SUDAH TERBAYAR 181.42 - 2,000.00 - SUDAH TERBAYAR 14.51 - 100,000.00 - SUDAH TERBAYAR 181.42 - 500.00 - SUDAH TERBAYAR 9.23 - 30,000.00 - SUDAH TERBAYAR

8.60 - 100,000.00 - SUDAH TERBAYAR 1,194.71 - 1,240.00 - SUDAH TERBAYAR 111.42 - 30,000.00 - SUDAH TERBAYAR

7.82 - 100,000.00 - SUDAH TERBAYAR 720.84 - 1,240.00 - SUDAH TERBAYAR 65.18 - 30,000.00 - SUDAH TERBAYAR

1.59 - 100,000.00 - SUDAH TERBAYAR 144.30 - 1,240.00 - SUDAH TERBAYAR 13.21 - 30,000.00 - SUDAH TERBAYAR

4.30 - 18,000.00 - SUDAH TERBAYAR 0.81 - 7,000.00 - SUDAH TERBAYAR 3.50 - 75,000.00 - SUDAH TERBAYAR 0.72 - 9,500.00 - SUDAH TERBAYAR

0.54 - 100,000.00 - SUDAH TERBAYAR 96.37 - 1,080.00 - SUDAH TERBAYAR 7.17 - 30,000.00 - SUDAH TERBAYAR 15.34 - 17,500.00 - SUDAH TERBAYAR

33.96 - 12,000.00 -

Page 6: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

78.21 - 12,000.00 -

27.46 - 17,500.00 - SUDAH TERBAYAR 200.95 - 17,500.00 - SUDAH TERBAYAR 70.40 - 7,500.00 - SUDAH TERBAYAR 8.40 - 9,000.00 - SUDAH TERBAYAR 456.82 - 15,000.00 - SUDAH TERBAYAR 297.56 - 5,000.00 - 7.62 - 24,000.00 -

27.46 - 17,500.00 - 200.95 100.48 17,500.00 1,758,312.50 70.40 35.20 21,000.00 739,200.00 8.40 - 9,000.00 - 456.82 - 12,500.00 - 297.56 - 19,500.00 - 7.62 - 6,500.00 -

1.70 - 100,000.00 - 305.15 - 1,080.00 - 10.73 - 30,000.00 -

1.26 - 100,000.00 - 150.01 - 1,080.00 - 5.43 - 30,000.00 -

TOTAL OPNAME : 2,497,512.50 Diperiksa Oleh : Dibuat Oleh :

Site Engineer Spv. Sipil

Page 7: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

OPNAME PEKERJAAN BORONGANNo. : /SBP-OPB/ / /2012

NO PEKERJAAN BORONGANBOBOT BOBOT

VOLUME MG LL MG INI

Mandor : WONDO ARUNDAYA Blok B 16

Papan Bouwplank 100% 0% 60.48

Pekerjaan Pondasi Telapak

- Galian tanah 100% 0% 21.60

- Urugan tanah kembali + pemadatan 100% 0% 14.88

- Pasir urug bawah pondasi 10 cm 100% 0% 0.96

- Lantai kerja 5 cm 100% 0% 0.34

- Beton 100% 0% 1.33

- Bekisting pasangan batako 100% 0% 4.36

- Besi pondasi tapak 100% 0% 140.60

Pekerjaan Pondasi Batu Kali

- Galian tanah 100% 0% 76.94

- Urugan tanah kembali + pemadatan 100% 0% 13.67

- Pasangan batu kali 100% 0% 39.98

- Pasir urug bawah pondasi 10 cm 100% 0% 12.12

Pekerjaan Tie Beam / Sloof

- Beton K225 100% 0% 10.13

- Besi beton 100% 0% 1,049.70

- Bekisting 100% 0% 84.82

Struktur Kolom lantai dasar

- Beton K225 100% 0% 47.68

- Bekisting 100% 0% 1.16

- Besi beton 100% 0% 1,403.89

Struktur Balok + Janggutan Lantai Atas

- Beton K225 100% 0% -

- Besi beton standard SNI 100% 0% -

- Bekisting 100% 0% -

Struktur Plat lantai Atas

- Beton K225 100% 0% -

- Besi beton standard SNI 100% 0% -

Page 8: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

- Bekisting 100% 0% -

Struktur Canopy Lantai Atas

- Beton K225 50% 0% 4.08

- Besi beton standard SNI 50% 0% 365.98

- Bekisting 50% 0% 35.19

Struktur Kolom lantai Atas

- Beton K225 100% 0% -

- Bekisting 100% 0% -

- Besi beton 100% 0% -

Struktur Plat lantai bawah

- Pemadatan tanah 100% 0% 157.03

- Rollag bata teras 100% 0% 16.00

- Plastik cor 100% 0% 181.42

- Beton K225 Plat t = 8 cm 100% 0% 14.51

- Besi Wire Mesh M - 6 standard SNI ( 1 Lapis ) 100% 0% 181.42

- Bekisting 100% 0% 9.23

Struktur Balok + Janggutan Atap

- Beton K225 0% 100% 8.60

- Besi beton standard SNI 100% 0% 1,194.71

- Bekisting 100% 0% 111.42

Struktur Plat Atap

- Beton K225 0% 100% 7.82

- Besi beton standard SNI 100% 0% 720.84

- Bekisting 100% 0% 65.18

Struktur Canopy Atap

- Beton K225 0% 100% 1.59

- Besi beton standard SNI 50% 50% 144.30

- Bekisting 50% 50% 13.21

Pekerjaan Pagar Luar Depan dan belakang

Pekerjaan Pondasi Batu Kali

- Galian tanah 100% 0% 4.30

- Urugan tanah kembali + pemadatan 100% 0% 0.81

- Pasangan batu kali 100% 0% 3.50

- Pasir urug bawah pondasi 10 cm 100% 0% 0.72

Pekerjaan Tie Beam / Sloof, kolom praktis dan Ringbalk

- Beton K225 100% 0% 0.54

- Besi beton standard SNI 100% 0% 96.37

- Bekisting 100% 0% 7.17

Pekerjaan pasangan dinding bata top level + 0,60 m 100% 0% 15.34

Screeding + Kawat Ayam Lantai Atas

Page 9: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

Dak dan canopy 33.96

Screeding + Kawat Ayam Pelat Atap

Dak dan canopy 0% 0% 78.21

PEKERJAAN DINDING + FINISHING

Pekerjaan Dinding Lantai - 1

Trasram pasangan bata , h = 30 cm 75% 0% 27.46

Pekerjaan pasangan dinding bata 25% 25% 200.95

Kolom praktis 11x11 cm 25% 25% 70.40

Balok latei termasuk Finishing openingnya. 0% 0% 8.40

Pekerjaan plesteran dinding + bawah tangga 20% 0% 456.82

Pekerjaan acian dinding + bawah tangga dengan MU 250 0% 0% 297.56

Pekerjaan plesteran + aci + tali air 2 cm pada dinding + 0% 0% 7.62

cat weathercoat ` `

Struktur Tangga Utama

Beton K225 1.70

Besi beton standard SNI 305.15

Bekisting 10.73

Struktur Tangga Jemuran

Beton K225 1.26

Besi beton standard SNI 150.01

Bekisting 5.43

Disetujui Oleh :

PM

Page 10: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

Halaman Dari :Proyek xxxxxxxx RESIDENCELokasiMinggu Ke 17 - 18Tanggal 28 MEI S/D 6 JUNI

OPNAME PEKERJAAN BORONGANNo. : /SBP-OPB/ / /2012

QUANTITY HARGA SAT JUMLAH KETERANGAN

Mg Ini

- 7,500.00 - SUDAH TERBAYAR

- 25,000.00 - SUDAH TERBAYAR - 7,000.00 - SUDAH TERBAYAR - 9,500.00 - SUDAH TERBAYAR - 80,000.00 - SUDAH TERBAYAR - 100,000.00 - SUDAH TERBAYAR - 20,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR

- 18,000.00 - SUDAH TERBAYAR - 7,000.00 - SUDAH TERBAYAR - 75,000.00 - SUDAH TERBAYAR - 9,500.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR

Page 11: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

- 30,000.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR

- 3,000.00 - SUDAH TERBAYAR - 15,000.00 - SUDAH TERBAYAR - 2,000.00 - SUDAH TERBAYAR - 100,000.00 - SUDAH TERBAYAR - 500.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR

8.60 100,000.00 860,200.00 - 1,240.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR

7.82 100,000.00 782,100.00 - 1,240.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR

1.59 100,000.00 158,568.00 72.15 1,240.00 89,464.07 6.61 30,000.00 198,210.00

- 18,000.00 - SUDAH TERBAYAR - 7,000.00 - SUDAH TERBAYAR - 75,000.00 - SUDAH TERBAYAR - 9,500.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR - 17,500.00 - SUDAH TERBAYAR

Page 12: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

- 12,000.00 -

- 12,000.00 -

- 17,500.00 - SUDAH TERBAYAR 50.24 17,500.00 879,156.25 17.60 7,500.00 132,000.00 - 9,000.00 - SUDAH TERBAYAR - 15,000.00 - SUDAH TERBAYAR - 5,000.00 - SUDAH TERBAYAR - 24,000.00 - SUDAH TERBAYAR

- 100,000.00 - - 1,080.00 - - 30,000.00 -

-

- 100,000.00 - - 1,080.00 - - 30,000.00 -

TOTAL OPNAME : 3,099,698.32 Diperiksa Oleh : Dibuat Oleh :

Site Engineer Spv. Sipil

Page 13: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

OPNAME PEKERJAAN BORONGANNo. : /SBP-OPB/ / /2012

NO PEKERJAAN BORONGANBOBOT BOBOT

VOLUME MG LL MG INI

Mandor : SAJIO ARUNDAYA Blok B 15

Papan Bouwplank 100% 0% 60.48

Pekerjaan Pondasi Telapak

- Galian tanah 100% 0% 21.60

- Urugan tanah kembali + pemadatan 100% 0% 14.88

- Pasir urug bawah pondasi 10 cm 100% 0% 0.96

- Lantai kerja 5 cm 100% 0% 0.34

- Beton 100% 0% 1.33

- Bekisting pasangan batako 100% 0% 4.36

- Besi pondasi tapak 100% 0% 140.60

Pekerjaan Pondasi Batu Kali

- Galian tanah 100% 0% 76.94

- Urugan tanah kembali + pemadatan 100% 0% 13.67

- Pasangan batu kali 100% 0% 39.98

- Pasir urug bawah pondasi 10 cm 100% 0% 12.12

Pekerjaan Tie Beam / Sloof

- Beton K225 100% 0% 10.13

- Besi beton 100% 0% 1,049.70

- Bekisting 100% 0% 84.82

Struktur Kolom lantai dasar

- Beton K225 100% 0% 47.68

- Bekisting 100% 0% 1.16

- Besi beton 100% 0% 1,403.89

Struktur Balok + Janggutan Lantai Atas

- Beton K225 100% 0% -

- Besi beton standard SNI 100% 0% -

- Bekisting 100% 0% -

Struktur Plat lantai Atas

- Beton K225 100% 0% -

- Besi beton standard SNI 100% 0% -

Page 14: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

- Bekisting 100% 0% -

Struktur Canopy Lantai Atas

- Beton K225 50% 0% 4.08

- Besi beton standard SNI 50% 0% 365.98

- Bekisting 50% 0% 35.19

Struktur Kolom lantai Atas

- Beton K225 100% 0% -

- Bekisting 100% 0% -

- Besi beton 100% 0% -

Struktur Plat lantai bawah

- Pemadatan tanah 100% 0% 157.03

- Rollag bata teras 100% 0% 16.00

- Plastik cor 100% 0% 181.42

- Beton K225 Plat t = 8 cm 100% 0% 14.51

- Besi Wire Mesh M - 6 standard SNI ( 1 Lapis ) 100% 0% 181.42

- Bekisting 100% 0% 9.23

Struktur Balok + Janggutan Atap

- Beton K225 0% 0% 8.60

- Besi beton standard SNI 0% 100% 1,194.71

- Bekisting 20% 100% 111.42

Struktur Plat Atap

- Beton K225 0% 0% 7.82

- Besi beton standard SNI 0% 100% 720.84

- Bekisting 0% 100% 65.18

Struktur Canopy Atap

- Beton K225 0% 0% 1.59

- Besi beton standard SNI 0% 100% 144.30

- Bekisting 0% 100% 13.21

Pekerjaan Pagar Luar Depan dan belakang

Pekerjaan Pondasi Batu Kali

- Galian tanah 0% 0% 4.30

- Urugan tanah kembali + pemadatan 0% 0% 0.81

- Pasangan batu kali 0% 0% 3.50

- Pasir urug bawah pondasi 10 cm 0% 0% 0.72

Pekerjaan Tie Beam / Sloof, kolom praktis dan Ringbalk

- Beton K225 0% 0% 0.54

- Besi beton standard SNI 0% 0% 96.37

- Bekisting 0% 0% 7.17

Pekerjaan pasangan dinding bata top level + 0,60 m 0% 0% 15.34

Screeding + Kawat Ayam Lantai Atas

Page 15: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

Dak dan canopy 0% 0% 33.96

Screeding + Kawat Ayam Pelat Atap

Dak dan canopy 0% 0% 78.21

PEKERJAAN DINDING + FINISHING

Pekerjaan Dinding Lantai - 1

Trasram pasangan bata , h = 30 cm 0% 0% 27.46

Pekerjaan pasangan dinding bata 0% 20% 200.95

Kolom praktis 11x11 cm 0% 0% 70.40

Balok latei termasuk Finishing openingnya. 0% 0% 8.40

Pekerjaan plesteran dinding + bawah tangga 0% 0% 456.82

Pekerjaan acian dinding + bawah tangga dengan MU 250 0% 0% 297.56

Pekerjaan plesteran + aci + tali air 2 cm pada dinding + 0% 0% 7.62

cat weathercoat ` `

Struktur Tangga Utama

Beton K225 0% 0% 1.70

Besi beton standard SNI 0% 0% 305.15

Bekisting 0% 0% 10.73

Struktur Tangga Jemuran

Beton K225 0% 0% 1.26

Besi beton standard SNI 0% 0% 150.01

Bekisting 0% 0% 5.43

Disetujui Oleh :

PM

Page 16: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

Halaman Dari :Proyek xxxxxxx RESIDENCELokasiMinggu Ke 17 - 18Tanggal 28 MEI S/D 6 JUNI

OPNAME PEKERJAAN BORONGANNo. : /SBP-OPB/ / /2012

QUANTITY HARGA SAT JUMLAH KETERANGAN

Mg Ini

- 7,500.00 - SUDAH TERBAYAR

- 25,000.00 - SUDAH TERBAYAR - 7,000.00 - SUDAH TERBAYAR - 9,500.00 - SUDAH TERBAYAR - 80,000.00 - SUDAH TERBAYAR - 100,000.00 - SUDAH TERBAYAR - 20,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR

- 18,000.00 - SUDAH TERBAYAR - 7,000.00 - SUDAH TERBAYAR - 75,000.00 - SUDAH TERBAYAR - 9,500.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR

Page 17: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

- 30,000.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR

- 3,000.00 - SUDAH TERBAYAR - 15,000.00 - SUDAH TERBAYAR - 2,000.00 - SUDAH TERBAYAR - 100,000.00 - SUDAH TERBAYAR - 500.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR

- 100,000.00 - 1,194.71 1,240.00 1,481,446.07 111.42 30,000.00 3,342,600.00

- 100,000.00 - 720.84 1,240.00 893,836.02 65.18 30,000.00 1,955,250.00

- 100,000.00 - 144.30 1,240.00 178,928.13 13.21 30,000.00 396,420.00

- 18,000.00 - - 7,000.00 - - 75,000.00 - - 9,500.00 -

- 100,000.00 - - 1,080.00 - - 30,000.00 - - 17,500.00 -

Page 18: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

- 12,000.00 -

- 12,000.00 -

- 17,500.00 - 40.19 17,500.00 703,325.00 - 7,500.00 - - 9,000.00 - - 15,000.00 - - 5,000.00 - - 24,000.00 -

- 100,000.00 - - 1,080.00 - - 30,000.00 -

- 100,000.00 - - 1,080.00 - - 30,000.00 -

TOTAL OPNAME : 8,951,805.22 Diperiksa Oleh : Dibuat Oleh :

Site Engineer Spv. Sipil

Page 19: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

OPNAME PEKERJAAN BORONGANNo. : /SBP-OPB/ / /2012

NO PEKERJAAN BORONGANBOBOT BOBOT

VOLUME MG LL MG INI

Mandor : PARNO ARUNDAYA Blok B 12

Papan Bouwplank 100% 0% 60.48

Pekerjaan Pondasi Telapak

- Galian tanah 100% 0% 21.60

- Urugan tanah kembali + pemadatan 100% 0% 14.88

- Pasir urug bawah pondasi 10 cm 100% 0% 0.96

- Lantai kerja 5 cm 100% 0% 0.34

- Beton 100% 0% 1.33

- Bekisting pasangan batako 100% 0% 4.36

- Besi pondasi tapak 100% 0% 140.60

Pekerjaan Pondasi Batu Kali

- Galian tanah 100% 0% 76.94

- Urugan tanah kembali + pemadatan 100% 0% 13.67

- Pasangan batu kali 100% 0% 39.98

- Pasir urug bawah pondasi 10 cm 100% 0% 12.12

Pekerjaan Tie Beam / Sloof

- Beton K225 100% 0% 10.13

- Besi beton 100% 0% 1,049.70

- Bekisting 100% 0% 84.82

Struktur Kolom lantai dasar

- Beton K225 100% 0% 47.68

- Bekisting 100% 0% 1.16

- Besi beton 100% 0% 1,403.89

Struktur Balok + Janggutan Lantai Atas

- Beton K225 100% 0% -

- Besi beton standard SNI 100% 0% -

- Bekisting 100% 0% -

Struktur Plat lantai Atas

- Beton K225 100% 0% -

- Besi beton standard SNI 100% 0% -

Page 20: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

- Bekisting 100% 0% -

Struktur Canopy Lantai Atas

- Beton K225 50% 0% 4.08

- Besi beton standard SNI 50% 0% 365.98

- Bekisting 50% 0% 35.19

Struktur Kolom lantai Atas

- Beton K225 100% 0% -

- Bekisting 100% 0% -

- Besi beton 100% 0% -

Struktur Plat lantai bawah

- Pemadatan tanah 0% 100% 157.03

- Rollag bata teras 0% 100% 16.00

- Plastik cor 0% 100% 181.42

- Beton K225 Plat t = 8 cm 0% 100% 14.51

- Besi Wire Mesh M - 6 standard SNI ( 1 Lapis ) 0% 100% 181.42

- Bekisting 0% 100% 9.23

Struktur Balok + Janggutan Atap

- Beton K225 100% 0% 8.60

- Besi beton standard SNI 100% 0% 1,194.71

- Bekisting 100% 0% 111.42

Struktur Plat Atap

- Beton K225 100% 0% 7.82

- Besi beton standard SNI 100% 0% 720.84

- Bekisting 100% 0% 65.18

Struktur Canopy Atap

- Beton K225 0% 100% 1.59

- Besi beton standard SNI 0% 0% 144.30

- Bekisting 0% 0% 13.21

Pekerjaan Pagar Luar Depan dan belakang

Pekerjaan Pondasi Batu Kali

- Galian tanah 0% 0% 4.30

- Urugan tanah kembali + pemadatan 0% 0% 0.81

- Pasangan batu kali 0% 0% 3.50

- Pasir urug bawah pondasi 10 cm 0% 0% 0.72

Pekerjaan Tie Beam / Sloof, kolom praktis dan Ringbalk

- Beton K225 0% 0% 0.54

- Besi beton standard SNI 0% 0% 96.37

- Bekisting 0% 0% 7.17

Pekerjaan pasangan dinding bata top level + 0,60 m 0% 0% 15.34

Screeding + Kawat Ayam Lantai Atas

Page 21: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

Dak dan canopy 0% 0% 33.96

Screeding + Kawat Ayam Pelat Atap

Dak dan canopy 0% 0% 78.21

PEKERJAAN DINDING + FINISHING

Pekerjaan Dinding Lantai - 1

Trasram pasangan bata , h = 30 cm 0% 0% 27.46

Pekerjaan pasangan dinding bata 0% 35% 200.95

Kolom praktis 11x11 cm 0% 35% 70.40

Balok latei termasuk Finishing openingnya. 0% 0% 8.40

Pekerjaan plesteran dinding + bawah tangga 0% 0% 456.82

Pekerjaan acian dinding + bawah tangga dengan MU 250 0% 0% 297.56

Pekerjaan plesteran + aci + tali air 2 cm pada dinding + 0% 0% 7.62

cat weathercoat ` `

Struktur Tangga Utama

Beton K225 0% 0% 1.70

Besi beton standard SNI 0% 0% 305.15

Bekisting 0% 0% 10.73

Struktur Tangga Jemuran

Beton K225 0% 0% 1.26

Besi beton standard SNI 0% 0% 150.01

Bekisting 0% 0% 5.43

Disetujui Oleh :

PM

Page 22: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

Halaman Dari :Proyek xxxxxxx RESIDENCELokasiMinggu Ke 17 - 18Tanggal 28 MEI S/D 6 JUNI

OPNAME PEKERJAAN BORONGANNo. : /SBP-OPB/ / /2012

QUANTITY HARGA SAT JUMLAH KETERANGAN

Mg Ini

- 7,500.00 - SUDAH TERBAYAR

- 25,000.00 - SUDAH TERBAYAR - 7,000.00 - SUDAH TERBAYAR - 9,500.00 - SUDAH TERBAYAR - 80,000.00 - SUDAH TERBAYAR - 100,000.00 - SUDAH TERBAYAR - 20,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR

- 18,000.00 - SUDAH TERBAYAR - 7,000.00 - SUDAH TERBAYAR - 75,000.00 - SUDAH TERBAYAR - 9,500.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR

Page 23: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

- 30,000.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR

157.03 3,000.00 471,090.00 SUDAH TERBAYAR 16.00 15,000.00 240,000.00 SUDAH TERBAYAR 181.42 2,000.00 362,840.00 SUDAH TERBAYAR 14.51 100,000.00 1,451,360.00 SUDAH TERBAYAR 181.42 500.00 90,710.00 SUDAH TERBAYAR 9.23 30,000.00 276,900.00 SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 1,240.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 1,240.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR

1.59 100,000.00 158,568.00 - 1,240.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR

- 18,000.00 - - 7,000.00 - - 75,000.00 - - 9,500.00 -

- 100,000.00 - - 1,080.00 - - 30,000.00 - - 17,500.00 -

Page 24: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

- 12,000.00 -

- 12,000.00 -

- 17,500.00 - 70.33 17,500.00 1,230,818.75 24.64 7,500.00 184,800.00 - 9,000.00 - - 15,000.00 - - 5,000.00 - - 24,000.00 -

- 100,000.00 - - 1,080.00 - - 30,000.00 -

- 100,000.00 - - 1,080.00 - - 30,000.00 -

TOTAL OPNAME : 4,467,086.75 Diperiksa Oleh : Dibuat Oleh :

Site Engineer Spv. Sipil

Page 25: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

OPNAME PEKERJAAN BORONGANNo. : /SBP-OPB/ / /2012

NO PEKERJAAN BORONGANBOBOT BOBOT

VOLUME MG LL MG INI

Mandor : SAJIO ARUNDAYA Blok B 11

Papan Bouwplank 100% 0% 60.48

Pekerjaan Pondasi Telapak

- Galian tanah 100% 0% 21.60

- Urugan tanah kembali + pemadatan 100% 0% 14.88

- Pasir urug bawah pondasi 10 cm 100% 0% 0.96

- Lantai kerja 5 cm 100% 0% 0.34

- Beton 100% 0% 1.33

- Bekisting pasangan batako 100% 0% 4.36

- Besi pondasi tapak 100% 0% 140.60

Pekerjaan Pondasi Batu Kali

- Galian tanah 100% 0% 76.94

- Urugan tanah kembali + pemadatan 100% 0% 13.67

- Pasangan batu kali 100% 0% 39.98

- Pasir urug bawah pondasi 10 cm 100% 0% 12.12

Pekerjaan Tie Beam / Sloof

- Beton K225 100% 0% 10.13

- Besi beton 100% 0% 1,049.70

- Bekisting 100% 0% 84.82

Struktur Kolom lantai dasar

- Beton K225 100% 0% 47.68

- Bekisting 100% 0% 1.16

- Besi beton 100% 0% 1,403.89

Struktur Balok + Janggutan Lantai Atas

- Beton K225 100% 0% -

- Besi beton standard SNI 100% 0% -

- Bekisting 100% 0% -

Struktur Plat lantai Atas

- Beton K225 100% 0% -

- Besi beton standard SNI 100% 0% -

Page 26: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

- Bekisting 100% 0% -

Struktur Canopy Lantai Atas

- Beton K225 50% 0% 4.08

- Besi beton standard SNI 50% 0% 365.98

- Bekisting 50% 0% 35.19

Struktur Kolom lantai Atas

- Beton K225 100% 0% -

- Bekisting 100% 0% -

- Besi beton 100% 0% -

Struktur Plat lantai bawah

- Pemadatan tanah 100% 0% 157.03

- Rollag bata teras 100% 0% 16.00

- Plastik cor 100% 0% 181.42

- Beton K225 Plat t = 8 cm 100% 0% 14.51

- Besi Wire Mesh M - 6 standard SNI ( 1 Lapis ) 100% 0% 181.42

- Bekisting 100% 0% 9.23

Struktur Balok + Janggutan Atap

- Beton K225 0% 0% 8.60

- Besi beton standard SNI 0% 50% 1,194.71

- Bekisting 20% 50% 111.42

Struktur Plat Atap

- Beton K225 0% 0% 7.82

- Besi beton standard SNI 25% 10% 720.84

- Bekisting 25% 10% 65.18

Struktur Canopy Atap

- Beton K225 0% 0% 1.59

- Besi beton standard SNI 25% 5% 144.30

- Bekisting 25% 5% 13.21

Pekerjaan Pagar Luar Depan dan belakang

Pekerjaan Pondasi Batu Kali

- Galian tanah 0% 0% 4.30

- Urugan tanah kembali + pemadatan 0% 0% 0.81

- Pasangan batu kali 0% 0% 3.50

- Pasir urug bawah pondasi 10 cm 0% 0% 0.72

Pekerjaan Tie Beam / Sloof, kolom praktis dan Ringbalk

- Beton K225 0% 0% 0.54

- Besi beton standard SNI 0% 0% 96.37

- Bekisting 0% 0% 7.17

Pekerjaan pasangan dinding bata top level + 0,60 m 0% 0% 15.34

Screeding + Kawat Ayam Lantai Atas

Page 27: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

Dak dan canopy 33.96

Screeding + Kawat Ayam Pelat Atap

Dak dan canopy 0% 0% 78.21

PEKERJAAN DINDING + FINISHING

Pekerjaan Dinding Lantai - 1

Trasram pasangan bata , h = 30 cm 0% 0% 27.46

Pekerjaan pasangan dinding bata 0% 25% 200.95

Kolom praktis 11x11 cm 0% 25% 70.40

Balok latei termasuk Finishing openingnya. 0% 0% 8.40

Pekerjaan plesteran dinding + bawah tangga 0% 0% 456.82

Pekerjaan acian dinding + bawah tangga dengan MU 250 0% 0% 297.56

Pekerjaan plesteran + aci + tali air 2 cm pada dinding + 0% 0% 7.62

cat weathercoat `

Struktur Tangga Utama

Beton K225 0% 0% 1.70

Besi beton standard SNI 0% 0% 305.15

Bekisting 0% 0% 10.73

Struktur Tangga Jemuran

Beton K225 0% 0% 1.26

Besi beton standard SNI 0% 0% 150.01

Bekisting 0% 0% 5.43

Disetujui Oleh :

PM

Page 28: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

Halaman Dari :Proyek xxxxxx RESIDENCELokasiMinggu Ke 19 - 20Tanggal 14 juni s/d 20 juni 2012

OPNAME PEKERJAAN BORONGANNo. : /SBP-OPB/ / /2012

QUANTITY HARGA SAT JUMLAH KETERANGAN

Mg Ini

- 7,500.00 - SUDAH TERBAYAR

- 25,000.00 - SUDAH TERBAYAR - 7,000.00 - SUDAH TERBAYAR - 9,500.00 - SUDAH TERBAYAR - 80,000.00 - SUDAH TERBAYAR - 100,000.00 - SUDAH TERBAYAR - 20,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR

- 18,000.00 - SUDAH TERBAYAR - 7,000.00 - SUDAH TERBAYAR - 75,000.00 - SUDAH TERBAYAR - 9,500.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR

Page 29: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

- 30,000.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR

- 100,000.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR - 1,080.00 - SUDAH TERBAYAR

- 3,000.00 - SUDAH TERBAYAR - 15,000.00 - SUDAH TERBAYAR - 2,000.00 - SUDAH TERBAYAR - 100,000.00 - SUDAH TERBAYAR - 500.00 - SUDAH TERBAYAR - 30,000.00 - SUDAH TERBAYAR

- 100,000.00 - 597.36 1,240.00 740,723.03 55.71 30,000.00 1,671,300.00

- 100,000.00 - 72.08 1,240.00 89,383.60 6.52 30,000.00 195,525.00

- 100,000.00 - 7.21 1,240.00 8,946.41 0.66 30,000.00 19,821.00

- 18,000.00 - - 7,000.00 - - 75,000.00 - - 9,500.00 -

- 100,000.00 - - 1,080.00 - - 30,000.00 - -

Page 30: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

- 12,000.00 -

- 12,000.00 -

- 17,500.00 - 50.24 17,500.00 879,156.25 17.60 7,500.00 132,000.00 - 9,000.00 - - 15,000.00 - - 5,000.00 - - 24,000.00 -

- 100,000.00 - - 1,080.00 - - 30,000.00 -

- 100,000.00 - - 1,080.00 - - 30,000.00 -

TOTAL OPNAME : 3,736,855.29 Diperiksa Oleh : Dibuat Oleh :

Site Engineer Spv. Sipil

Page 31: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

HARGA PENAWARAN UPAH BORONGANProyek : Pembangunan Rumah Masal xxxxxx ResidenceTanggal : 21 Desember 2011

No. URAIAN PEKERJAAN UNIT

I PEKERJAAN PERSIAPAN 1 Papan Bouwplank m'

II. PEKERJAAN PONDASI & STRUKTUR II.A Pekerjaan Tanah & Pondasi

1 Pekerjaan Pondasi Telapak - Galian tanah 2-3 M m3 - Urugan tanah kembali + pemadatan m3 - Pasir urug bawah pondasi 10 cm m3 - Lantai kerja 5 cm m3 - Plastik Cor m2 - Beton m3 - Bekisting pasangan batako m2 - Besi pondasi tapak kg

2 Pekerjaan Pondasi Batu Kali - Galian tanah m3 - Urugan tanah kembali + pemadatan m3 - Pasangan batu kali m3 - Pasir urug bawah pondasi 10 cm m3

3 Pekerjaan Tie Beam / Sloof - Beton K225 - Besi beton standard SNI termasuk besi angkur ke pondasi batu kali kg - Bekisting plywood 9 mm - Pasir urug bawah pondasi 10 cm m3 - Lantai kerja 5 cm m3

4 Buang tanah kelebihan eks galian --> keluar lokasi proyek m3

II.B Pekerjaan Struktur Lantai Dasar 1 Struktur Plat lantai bawah

- Pemadatan tanah m2 - Plastik cor m2 - Beton K225 Plat t = 8 cm - Besi Wire Mesh M - 6 standard SNI ( 1 Lapis ) m2

2 Struktur Kolom - Beton K225 - Besi beton standard SNI kg - Bekisting

3 Struktur Canopy (Plat & balok Overstek) as B/1-5,B/4-6,G/6-7,G-H/5,4/B-D - Beton K225 - Besi beton standard SNI kg - Bekisting

m3

m2

m3

m3

m2

m3

m2

Page 32: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

4 Struktur Tangga ( termasuk balok bordes ) - Beton K225 - Besi beton standard SNI kg - Bekisting - Galian m3 - Urug tanah kembali + pemadatan m3 - Buang sisa tanah m3

5 Waterproofing coating ex Sika Top - Lantai toilet Lt. bawah + dinding toilet setinggi 20cm

- Dak dan canopy + dinding keliling setinggi 10cm

II.C Pekerjaan Struktur Lantai Atas 1 Struktur Kolom

- Beton K225 - Besi beton standard SNI kg - Bekisting

2 Struktur Balok + Janggutan - Beton K225 - Besi beton standard SNI kg - Bekisting

3 Struktur Plat lantai - Beton K225 - Besi beton standard SNI kg - Bekisting

4 Struktur Canopy (Plat & balok Overstek) as G/5-7,D/1-3,G-H/5 - Beton K225 - Besi beton standard SNI kg - Bekisting

5 Waterproofing coating ex Sika Top - Lantai toilet Lt. Atas + dinding toilet setinggi 20cm

- Dak dan canopy + dinding keliling setinggi 10cm

6 Screeding + Kawat Ayam - Dak dan canopy

II.D Pekerjaan Struktur Lantai Atap 1 Struktur Balok + Janggutan

- Beton K225 - Besi beton standard SNI kg - Bekisting

2 Struktur Plat lantai - Beton K225 - Besi beton standard SNI kg - Bekisting

3 Waterproofing coating ex Sika Top - Dak + dinding keliling setinggi 10cm

m3

m2

m2

m2

m3

m2

m3

m2

m3

m2

m3

m2

m2

m2

m2

m3

m2

m3

m2

m2

Page 33: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

4 Screeding + Kawat Ayam - Dak dan canopy

III PEKERJAAN DINDING + FINISHING III.A Pekerjaan Dinding Lantai - 1

1 Pekerjaan pasangan dinding bata m2 2 Kolom praktis 11x11 cm m'

3 Balok latei keliling seluruh Kusen Pintu & jendela termasuk Finishing openingnya. m'

4 Pekerjaan plesteran dinding + bawah tangga m2 5 Pekerjaan acian dinding + bawah tangga dengan MU 250 m2 6 Pekerjaan plesteran + aci + tali air 2 cm pada dinding + cat weathercoat m2 7 Pekerjaan cat dinding dalam eks Mowilex tipe cendana m2 8 Pekerjaan cat dinding luar eks Mowilex tipe weathercoat m2 9 Pasangan dinding batu Paras Jogja m2

III.B Pekerjaan Dinding Lantai - 2 1 Pekerjaan pasangan dinding bata m2 2 Kolom praktis 11x11 cm m'

3 Balok latei keliling seluruh Kusen Pintu & jendela termasuk Finishing openingnya. m'

4 Pekerjaan plesteran dinding m2 5 Pekerjaan acian dinding dengan MU 250 m2 6 Pekerjaan plesteran + aci + tali air 2 cm pada dinding + cat weathercoat m2 7 Pekerjaan cat dinding dalam eks Mowilex tipe cendana m2 8 Pekerjaan cat dinding luar eks Mowilex tipe weathercoat m2 9 Plester + aci kasar + cat weathershield m2 10 Profilan bawah kusen jendela utama depan m'

III.C Pekerjaan Dinding Lantai - Atap Dak Beton Parapet 1 Pekerjaan pasangan dinding bata m2 2 Pekerjaan plesteran dinding m2 3 Pekerjaan acian dinding dengan MU 250 m2 4 Pekerjaan cat dinding luar eks Mowilex tipe weathercoat m2

IV. PEKERJAAN FINISHING LANTAI IV.A Pekerjaan Finishing Lantai Dasar

1 Homogenous Tile Indogress uk. 80x80 cm type Grigio Travertino (K1) - Living room, dining room, pantry,Guest bedroom m2

3 Homogenous Tile Niro Granite uk. 60x60 cm type Nordic Stone Brown/Black (K3) m2

- Teras Depan dan Teras Belakang

4 Koral sikat (K9) - Selasar Depan m2

5 Homogenous Tile Niro Granite uk. 60x60 cm type Nordic Stone Brown/Black (K3)

- Selasar Depan m2

6 Keramik Roman uk. 30 x 30 cm ; tipe 337102 (K4) - Service area m2

8 Finishing Anak Tangga Papan Jati t=3 cm & list t=2 cm

m2

Page 34: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

finish melamic open pour : - Area Tangga Antrede (injakan) m2 - Area Tangga Optrede (trap) m2

9 Step nosing tangga - Tangga utama m' - Tangga service m'

10 Finishing Anak Tangga Service(K4) - Area Tangga Antrede (injakan) m2 - Area Tangga Optrede (trap) m2

11 Keramik Toilet Powder Room - Lantai granite Indo Gress uk. 40x40 cm ; tipe Zirconium Unpolished (K10)

- Lantai Granite Indo Gress uk. 60x60 cm ; tipe Aurora (K11)

- Dinding granite Indo Gress uk. 40x40 cm ; tipe Zirconium Polished (K12) - Meja wastafel lebar 60 cm m' - Finish meja ; granite Black Galaxi lebar 60 cm m'

12 Area Kitchen : - Meja dapur lebar 80 cm m' - Keramik meja dapur 20x20 cm tipe Lucido Bianco W. 20106 m2

- Keramik dinding dapur 20x20 cm tinggi 80 cm, tipe Lucido Bianco W. 20106 m2

- Keramik List dinding dapur 6 x 20 cm Tipe Listello Strawberry m'

13 Area Pantry : --->meja + wastafel by Other (Interior)

IV.B Pekerjaan Finishing Lantai Atas 1 Homogenous Tile Indogress uk. 80x80 cm type Grigio Travertino (K1)

- Master bedroom, kiddie room1&2,hall m2

3 Keramik Toilet Master Bathroom - Lantai HT Indo Gress uk. 40x40 cm ; tipe Zirconium Unpolished (K10) - Lantai HT Indo Gress uk. 60x60 cm ; tipe Aurora (K11) m2 - Koral terazo Ø 2-4 cm (K18) m2 - Dinding HT Indo Gress uk. 40x40 cm ; tipe Zirconium Polished (K12) - Meja wastafel lebar 60 cm m' - Finish meja ; granite Black Galaxi lebar 60 cm m' - List granite Black Galaxi uk. 2x10 cm dipinggul m'

4 Keramik Toilet Kiddie room - Lantai ex. Indo Gress uk. 40x40 cm ; tipe Zirconium Unpolished (K10)

- Lantai ex. Indo Gress uk. 60x60 cm ; tipe Aurora (K11)

- Dinding ex. Indo Gress uk. 40x40 cm ; tipe Zirconium Polished (K12) - Meja wastafel lebar 60 cm m' - Finish meja granite Black Galaxy lebar 60 cm (incl. pinggulan) m'

5 Homogenous Tile Niro Granite uk. 60x60 cm type Nordic Stone Brown/Black (K3)

- Balkon Depan dan belakang

6 Keramik Roman uk. 30 x 30 cm ; tipe 337102 (K4) m2 - Service area & maid room

m2

m2

m2

m2

m2

m2

m2

m2

m2

Page 35: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

8 Keramik Toilet Service - Keramik lantai ex. Roman uk. 20x20 cm warna putih (K16)

- Keramik dinding ex. Roman uk. 20x20 cm warna putih (K17)

9 Keramik Tile Roman uk. 30x30 cm type 337409 (K8) m2 - Drying Area

VI. PEKERJAAN RAILLING & TANGGA SERVICE 1

m' 2 Railing pas. Bata + plester + aci + cat Cendana ex. Mowilex

tinggi 900 mm - Tangga service area m'

3 tinggi 3,20 m lapis Zincromat Finish cat besi semi duco unit

VIII. PEKERJAAN ATAP 1 Rangka atap Baja Ringan zincalum m2

- Talang seng jurai rata BJLS 20 m' 2 Insulation seng rata BJLS 20 3 Penutup atap genteng ex. Cisangkan

- Genteng badan - Genteng nok termasuk karpusan + cat m' - Genteng nok 3 arah bh - Genteng nok ujung bh

4 Woodplank motif urat kayu m' 5 Glass block 20/20 bh

IX. PEKERJAAN SANITARY IX.A Pekerjaan Sanitary Lantai - 1

1 Toilet Powder room - Shower ex. Toto ; TX 488 S + TX 468 SES set - Closet duduk ex. Toto ; type CW 421 J / SW 420 JP set - Jet washer w/. Stop valve ex. Toto ; TX 403 SMCRB set - Wastafel ex. Toto ; type LW 641 J W/F komplit + kran TX 119 LES set - Floor drain ex. Toto ; TX 1 BN bh

2 Kitchen - Kitchen sink stainlees steel ex. Lokal/cina+ Avoer unit - Kran sink ex. Toto ; tipe TX 603 KM, flexible hose, stopvalve set

4 Carport, taman depan dan belakang - Kran taman eks Toto ; tipe T 23 B13 V7NB bh

IX.B Pekerjaan Sanitary Lantai - 2 1 Master bathroom :

- Bathtube ex. Toto ; FB 1700 - 70 complete + 9005 unit - Kran bath tub & shower set ex. Toto ; TX 445 SESM set

m2

m2

Railing tangga utama rangka hollow 40x40 + 40x20 + 20x20 t=2mm, plat dudukan handrail, plat t=3 mm finish Duco + handrail kamper oven dgn uk. Jadi 4x6 cm, pingulan finish melamic open pour

Tangga monyet untuk maintenance dak atap + watertorn pipa besi ∅ 2"+ 1"∅

m2

m2

Page 36: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

- Shower ex. Toto ; TX 488 S + TX 468 SES set - Closet duduk ex. Toto ; type CW 823 J W/F-V2 set - Jet washer w/. Stop valve ex. Toto ; TX 403 SMCRB set - Wastafel ex. Toto ; type LW 548 W/F komplit + kran Toto TX 119 LES set - Floor drain ex. Toto ; TX 1 BN bh

2 Kiddie bathroom : - Shower ex. Toto ; TX 488 S + TX 468 SES set - Closet duduk ex. Toto ; type CW 421 J / SW 420 JP set - Jet washer w/. Stop valve ex. Toto ; TX 403 SMCRB set - Wastafel ex. Toto ; type LW 641 J W/F komplit + kran TOTO TX 119 LES set - Floor drain ex. Toto ; TX 1 BN bh

3 Toilet service - Closet Jongkok CE6 set - Kran tembok eks Toto ; tipe T 23 B13 V7NB bh - Floor drain ex. Toto ; TX 1 BN bh

4 Washing Area - Kran tembok eks Toto ; tipe T 23 B13 V7NB bh - Floor drain ex. Toto ; TX 1 BN bh

X. PEKERJAAN PLUMBING X.A. Pekerjaan Instalasi Air Bersih

1 Equipment

ttk

- Pompa jetpump EX. Shimizu ; 250 w ; tangki putih utk daya suction 30m unit

- Pompa distribusi Shimizu 100 W (Lokal) + Valve unit - Roof tank fiberglass ; kap. 1 m3 + WLC + pengkabelan + valve unit - Bak kontrol pompa ; uk. 60x60x60 unit

2 Supply - Dari sumur pantek ke pompa PVC AW dia. 1" m' - Dari pompa ke Roof Tank ; PVC AW Ø 1" m' - Dari PAM ke Roof tank ; PVC AW Ø1" (Dop dia 1") m'

3 Distribusi dari Roof tank ke Lantai Atas - PVC AW dia. 1" m' - PVC AW dia. 3/4" m' - PVC AW dia. 1/2" m'

4 Distribusi dari Roof tank ke Lantai Dasar - PVC AW dia. 1" m' - PVC AW dia. 3/4" m' - PVC AW dia. 1/2" m'

5 Fitting dan Assesoris (termasuk ball valve, dll) Ls

X.B. Pekerjaan Instalasi Air Panas Lt. Dasar & Lt. Atas 1 Pipa distribusi pipa HDPE

- dia. 1/2" m'

- Pantek sumur u/. Jet pump 30m+ pipa casing dia. 4" 28 m' + Pipa Suction Dia. 1.25" & Dia. 1"

Page 37: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

X.C. Pekerjaan Instalasi Air Hujan, Air Bekas & Air Kotor 1 Equipment

- Septictank Bio tank BK 08 STD Kap. tangki 2.25 m3 unit

- Biaya Pasang termasuk galian tanah, urugan kembali, pondasi septictank unit

2 Pekerjaan instalasi pipa lantai dasar : - PVC AW - dia. 6" m' - PVC AW - dia. 4" m' - PVC AW - dia. 3" m' - PVC AW - dia. 2" m' - PVC AW - dia. 2" (pipa vent) m'

3 Pekerjaan instalasi pipa lantai atas : - PVC AW - dia. 4" m' - PVC AW - dia. 3" m' - PVC AW - dia. 2" m' - PVC AW - dia. 2" (pipa vent) m'

4 Pipa drain AC PVC AW dia. 1" m'

5 Perlengkapan lain - Roof drain Antasan type tutup cambung dia. 3" bh - Floor drain di drying area ex. Toto ; TX 1 BN bh - Bak kontrol air hujan; uk. 40x40x40 unit - Fitting & Assesoris Ls

6 Sumur Resapan Buis Beton precast Ø80 cm kedalaman 2 m' unit

X.D. Pekerjaan Sparing + Pancingan Instalasi SRTR, MATV

1 Sparing pipa PVC dia. 2" tipe - AW dibawah Drive Way searah saluran (2Jalur ) m'

XII. PEKERJAAN LUAR DAN HALAMAN 4 Struktur Carport & Path Way

- Lantai kerja t = 5 cm m3 - Beton K225 tebal 8 cm - Besi beton standard SNI dia. 8 - 15 cm - 1 lapis / wire mesh M6 kg - Paving block tipe Altstadt pola design 6 cm m2 (90% nat, 10% warna khusus)

6 Bak sampah pasangan bata finish plester aci cat Weathercoat dan unit tutup dari plat besi

9 Pekerjaan Pagar Luar Depan dan belakang Pekerjaan Pondasi Batu Kali - Galian tanah m3 - Urugan tanah kembali + pemadatan m3 - Pasangan batu kali m3 - Pasir urug bawah pondasi 10 cm m3 Pekerjaan Tie Beam / Sloof, kolom praktis dan Ringbalk - Beton K225 - Besi beton standard SNI termasuk besi angkur ke pondasi batu kali kg - Bekisting

10 Pekerjaan pasangan dinding bata top level + 0,60 m dari Peil lantai m2 11 Pekerjaan plesteran + aci + tali air 2 cm pada dinding + cat weathercoat m2 12 Finishing Facade Depan batu Paras Jogya 15/60 lapis Coating Ex. Mowilex m2

m3

m3

m2

Page 38: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

13 Finishing dinding Facade nat tali air 1,5 x 2 cm Finish Cat Ex. Mowilex Weathercoat m2

Page 39: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

VOLUME HARGA SAT UPAH TOTAL

7,500.00 -

25,000.00 - 7,000.00 - 9,500.00 - 80,000.00 - 2,000.00 - 100,000.00 - 20,000.00 - 1,080.00 -

18,000.00 - 7,000.00 - 75,000.00 - 9,500.00 -

100,000.00 - 1,080.00 - 30,000.00 - 9,500.00 - 80,000.00 -

10,000.00 -

3,000.00 - 2,000.00 - 100,000.00 - 500.00 -

100,000.00 - 1,080.00 - 30,000.00 -

- -

100,000.00 - 1,080.00 - 30,000.00 -

-

Page 40: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

- 100,000.00 - 1,080.00 - 30,000.00 - 18,000.00 - 7,000.00 - 10,000.00 -

- - -

5,000.00 - - - - -

100,000.00 - 1,080.00 - 30,000.00 -

- -

100,000.00 - 1,080.00 - 30,000.00 -

- -

100,000.00 - 1,080.00 - 30,000.00 -

- -

100,000.00 - 1,080.00 - 30,000.00 -

- -

5,000.00 -

5,000.00 - - -

12,000.00 - - - -

100,000.00 - 1,080.00 - 30,000.00 -

- -

100,000.00 - 1,080.00 - 30,000.00 -

- -

5,000.00 - -

Page 41: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

- 12,000.00 -

- - - -

17,500.00 - 7,500.00 -

9,000.00 -

15,000.00 - 5,000.00 - 24,000.00 -

- -

35,000.00 - - - -

21,000.00 - 9,000.00 -

12,500.00 -

19,500.00 - 6,500.00 - 26,000.00 -

- -

24,000.00 - 8,000.00 -

- - -

25,000.00 - 23,000.00 - 7,500.00 -

- - - - -

30,000.00 - -

30,000.00 -

- - -

18,000.00 - -

-

30,000.00 - - -

30,000.00 - - -

Page 42: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

- - - - -

6,000.00 - 6,000.00 -

- -

30,000.00 - 30,000.00 -

- -

30,000.00 -

30,000.00 -

39,000.00 - -

15,000.00 - - - -

30,000.00 -

39,000.00 -

6,000.00 - - - - - - -

30,000.00 - - -

30,000.00 - 30,000.00 -

- 39,000.00 -

- 15,000.00 - 15,000.00 -

- -

30,000.00 -

30,000.00 -

39,000.00 - -

15,000.00 - -

-

- -

30,000.00 - - -

Page 43: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

- 30,000.00 -

39,000.00 - -

30,000.00 - - - - - - - - - - - - - - - - - - - - -

22,000.00 - 20,000.00 -

- 15,000.00 - 22,000.00 - 8,000.00 - 8,000.00 - 8,000.00 - 25,000.00 -

-

20,000.00 - 150,000.00 - 10,000.00 - 105,000.00 - 5,000.00 -

15,000.00 - 5,000.00 -

5,000.00 -

190,000.00 - 20,000.00 -

Page 44: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

20,000.00 - 150,000.00 - 10,000.00 - 105,000.00 - 5,000.00 -

20,000.00 - 150,000.00 - 10,000.00 - 105,000.00 - 5,000.00 -

160,000.00 - 5,000.00 - 5,000.00 -

5,000.00 - 5,000.00 -

-

- -

- - - - 100,000.00 -

3,825.00 - 3,825.00 - 3,825.00 -

3,800.00 - 3,800.00 - 3,800.00 -

3,800.00 - 3,800.00 - 3,800.00 -

-

7,000.00 -

Page 45: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

-

185,000.00 -

10,000.00 - 10,000.00 - 10,000.00 - 6,000.00 - 6,000.00 -

- -

10,000.00 - 10,000.00 - 6,000.00 - 6,000.00 -

- 3,800.00 -

- -

5,000.00 - 5,000.00 - 70,000.00 - 125,000.00 -

-

6,000.00 -

80,000.00 - 100,000.00 - 1,080.00 - 30,000.00 -

175,000.00 -

18,000.00 - 7,000.00 - 75,000.00 - 9,500.00 -

- 100,000.00 - 1,080.00 - 30,000.00 - 17,500.00 - 24,000.00 - 20,000.00 -

Page 46: Format Opname Pekerjaan Borongan Dan Upah Mingguan Proyek

25,000.00 -

-

-