estimasi biaya badru

78
DAFTAR HARGA SATUAN DASAR PERALATAN NO. JENIS ALAT SATUAN 1 Tandem Rooler 6 s/d 8 ton (5 jam/ hari) jam 100,000.00 2 Sewa Mesin Las Listrik 18 PK (8 jam/ hari) jam 35,000.00 3 bh/ hari 150,000.00 4 Water Tank 3000 - 4500 Liter unit/ hari 95,000.00 5 Pengaduk Beton (Beton Molen) unit/ jam 30,000.00 6 Sepeda motor unit/ hari 90,000.00 7 Truk / Pick Up unit/ hari 125,000.00 8 Rool Meter 50 Meter bh 55,000.00 9 Gergaji Listrik bh 35,000.00 10 Water Pass Alumunium bh 45,000.00 Bandung, 05 Juni 2012 Estimator, Riezqi Badruzaman & Teguh Firmansyah HARGA SATUAN (Rp.) Teodolith setara Top Con (Digital) DT 205

Upload: thisisghostactual

Post on 25-Oct-2015

64 views

Category:

Documents


7 download

TRANSCRIPT

Page 1: Estimasi Biaya Badru

DAFTAR HARGA SATUAN DASAR PERALATAN

NO. JENIS ALAT SATUAN

1 Tandem Rooler 6 s/d 8 ton (5 jam/ hari) jam 100,000.00

2 Sewa Mesin Las Listrik 18 PK (8 jam/ hari) jam 35,000.00

3 bh/ hari 150,000.00

4 Water Tank 3000 - 4500 Liter unit/ hari 95,000.00

5 Pengaduk Beton (Beton Molen) unit/ jam 30,000.00

6 Sepeda motor unit/ hari 90,000.00

7 Truk / Pick Up unit/ hari 125,000.00

8 Rool Meter 50 Meter bh 55,000.00

9 Gergaji Listrik bh 35,000.00

10 Water Pass Alumunium bh 45,000.00

Bandung, 05 Juni 2012 Estimator,

Riezqi Badruzaman & Teguh Firmansyah

HARGA SATUAN (Rp.)

Teodolith setara Top Con (Digital) DT 205

Page 2: Estimasi Biaya Badru

DAFTAR HARGA SATUAN UPAH KERJA

NO. JENIS PEKERJA BANGUNAN SATUAN WAKTU

1 Pekerja 35,000.00 1 ORANG/ HR/ 8 JAM

2 Pekerja Setengah Terampil 30,000.00 1 ORANG/ HR/ 8 JAM

3 Pekerja Terampil 50,000.00 1 ORANG/ HR/ 8 JAM

4 Tukang Gali 40,000.00 1 ORANG/ HR/ 8 JAM

5 Tukang Batu Setengah Terampil 35,000.00 1 ORANG/ HR/ 8 JAM

6 Tukang Batu Terampil 45,000.00 1 ORANG/ HR/ 8 JAM

1 Tukang Kayu Setengah Terampil 35,500.00 1 ORANG/ HR/ 8 JAM

2 Tukang Kayu Terampil 40,000.00 1 ORANG/ HR/ 8 JAM

1 Tukang Cat/ Pelitur Setengah Terampil 35,000.00 1 ORANG/ HR/ 8 JAM

2 Tukang Cat/ Pelitur Terampil 40,000.00 1 ORANG/ HR/ 8 JAM

1 Tukang Besi Beton Setengah Terampil 35,000.00 1 ORANG/ HR/ 8 JAM

2 Tukang Besi Beton Terampil 40,000.00 1 ORANG/ HR/ 8 JAM

1 Tukang Besi Profil Setengah Terampil 35,000.00 1 ORANG/ HR/ 8 JAM

2 Tukang Besi Profil Terampil 40,000.00 1 ORANG/ HR/ 8 JAM

1 Mandor 60,000.00 1 ORANG/ HR/ 8 JAM

1 Tukang Pipa Setengah Terampil 35,000.00 1 ORANG/ HR/ 8 JAM

2 Tukang Pipa Terampil 40,000.00 1 ORANG/ HR/ 8 JAM

3 Kepala Tukang Pipa 45,000.00 1 ORANG/ HR/ 8 JAM

4 Tukang Profil Batu/ Bata Setengah Terampil 35,000.00 1 ORANG/ HR/ 8 JAM

5 Tukang Profil Batu/ Bata Terampil 40,000.00 1 ORANG/ HR/ 8 JAM

6 Kepala Tukang Profil Batu/ Bata 45,000.00 1 ORANG/ HR/ 8 JAM

Bandung, 05 Juni 2012 Estimator,

Riezqi Badruzaman & Teguh F

HARGA

(Rp.)

Page 3: Estimasi Biaya Badru

DAFTAR HARGA SATUAN BAHAN

No JENIS BAHAN SATUAN

1 2 3 4

A. AGREGAT KASAR, BAHAN PEREKAT DAN BAHAN JADINYA1 Pasir Urug /Bawah lantai m3 95,000 2 Pasir pasang kali m3 105,000 3 Pasir Pasang /gunung pilihan m3 65,000 4 Pasir Beton m3 125,000 1 Batu Belah m3 120,000 2 Batu Pecah 1/2 m3 153,000 3 Batu Pecah 2/3 m3 142,000 4 Batu Pecah 3/5 m3 131,000 5 Batu Pecah 10/15 m3 92,000 6 Bata Merah bh 500 7 Semen Portland ( PC ) /50 Kg Zak 55,000 1 Beton ReadyMix K-225 m3 695,000 2 Beton ReadyMix K-175 m3 695,000

3 Roster Beton 15 x 30 Cm bh 3,500

1 Batu koral sikat kg 15,500

B. BAHAN LOGAM DAN BAHAN JADINYA1 Kg 10,000 2 Besi beton Deformasi/uril (ukuran rata-rata) Kg 11,000 3 Baja Siku / Profil DN Kg 20,000 1 Kawat Beton Kg 15,000 1 Kawat Las Kg 27,000 1 Daun pintu besi lengkap accsesories di cat finish m2 484,000 2 Pintu sliding garasi sheet 730,000 1 Propil Pintu Alumunium m' 45,000 1 Alumunium 0.10 mm Lbr 45,700 2 Alumunium 0.30 mm Lbr 100,100 1 Skrup,Fisher Psng 12,500 2 Sealent Bh 20,000 3 Karet M' 194,000 4 Kawar Ram 1 x 1 cm M2 13,000 5 Rangka hollow 40x40 @ 4m¹ btg 75,000 6 Rangka hollow 20x40 @ 4m¹ btg 55,000

HARGA (Rp.)

Besi Beton Polos (ukuran rata rata)

Page 4: Estimasi Biaya Badru

1 2 3 4C. BAHAN PERPIPAAN

1 Pipa Galvanis Ø 1/2" btg 55,000 2 Pipa Galvanis Ø 1" btg 85,000 3 Pipa Galvanis Ø 1 1/4" btg 160,000 4 Pipa Galvanis Ø 2 1/4" btg 250,000 5 Pipa Galvanis Ø 2 1/2" btg 275,000 6 Pipa Besi Ø 1 1/4" btg 24,000 7 Pipa PVC Ø 1/2" ( setara Maspion ) btg 5,000 8 Pipa PVC Ø 3/4" ( setara Maspion ) btg 11,000 9 Pipa PVC Ø 1" ( Setara Maspion ) btg 14,000

10 Pipa PVC Ø 1" 1/4 ( Setara Maspion ) btg 18,000 11 Pipa PVC Ø 1 1/2" ( Setara Maspion ) btg 21,000 12 Pipa PVC Ø 2" ( Setara Maspion ) btg 27,000 13 Pipa PVC Ø 2 1/2" ( Setara Maspion ) btg 30,000 14 Pipa PVC Ø 3 " ( Setara Maspion ) btg 56,000 15 Pipa PVC Ø 4" ( Setara Maspion ) btg 84,000

1 Gravel 1/2 Dia 20 cm m' 19,000 2 Gravel 1/2 Dia 30 cm m' 23,000 3 Buis beton dia 20 cm bh 34,000 4 Buis beton dia 30 cm bh 41,000 5 Bio tank bh 1,200,000 6 Ground Tank Full shet bh 1,950,000 7 Tutup Plat bordes + Engsel bh 235,000

1 Bambu Diameter 5 s/d 7 cm btg 6,000 2 Bambu Diameter 7 s/d 10 cm btg 9,000 3 Bambu Gombong m2 21,000 4 Dolken 5 s.d 7 m2 27,000 5 Dolken 7 s.d 10 m2 81,000 6 Kayu Balok Borneo 6/12, 8/12, 8/15 * m2 4,600,000 7 Kayu Balok Borneo Super m2 4,600,000 8 Kayu Balok Damar Laut 6/12, 8/12, 8/15* m2 8,800,000 9 Kayu Balok Kamper Banjar 6/12, 8/12, 8/15* m2 6,300,000

10 Kayu Balok Kamper Medan ( Kruing ) m2 8,800,000 11 Kayu Balok Kamper Medan 6/12, 8/12, 8/15* m2 9,200,000 12 Kayu Balok Kamper Samarinda m2 10,100,000 13 Kayu Balok Rasamala* m2 4,000,000

1 Kayu Jati Jabar Tua Lepas Mata dari Ø 80 CM ke atas m2 8,100,000 2 Kayu Jati Jateng Tua Lepas Mata dari Ø 80 CM ke atas bh 16,000,000 3 Kayu Jati Jatim Lepas Mata dari Ø 80 CM ke atas bh 16,000,000 4 Kayu Kamper Singkil /Kapur ( Kamper Samarinda Kls II ) bh 9,200,000 5 Kayu Kaso 5/7, 5/10 Borneo* bh 4,000,000 6 Kayu Kaso 5/7, 5/10 Kamper Banjar* Zak 6,300,000 7 Kayu Kaso 5/7, 5/10 Kamper Medan* Zak 8,100,000 8 Kayu Balok Kayu Gunung Klas II 6/12, 8/12, 8/15* m3 2,400,000 9 Kayu Kaso 5/7, 5/10 Kayu Gunung Klas II* m3 2,400,000

10 Kayu Balok /Kayu Gunung Klas III ( Albasia )* m3 1,400,000 11 Kayu Papan bekisting t 2 cm kayu Albasia m3 1,400,000 12 Kayu Papan Kayu Lokal Kls II m3 2,400,000 13 List Profil kayu lokal kls II 5 cm m' 7,000 14 List Profil kayu Kamper 7 cm m' 43,000 15 List Profil gypsum 7 cm m' 70,000 16 Gypsun 120 x 240 cm , t = 9 mm ex DN lbr 72,000 17 Fornika ukuran 120x240 cm Lbr 86,000 18 Jabar Wood 4 mm Lbr 82,000 19 Melamin 4 mm 120 x 240 Lbr 79,000 20 Multiplek 6 mm 120 x 240 Lbr 93,000 21 Multiplek 9 mm 120 x 240 Lbr 139,000 22 Multiplek 12 mm 120 x 240 Lbr 173,000 23 Multiplek 18 mm 120 x 240 Lbr 226,000

D. BAHAN KAYU BERIKUT BAHAN JADINYA

Page 5: Estimasi Biaya Badru

1 2 3 424 Plywood 4 mm 120 x 240 Lbr 58,000 25 Plywood 9mm 120 x 240 Lbr 127,000 26 Plywood 18 mm 120 x 240 Lbr 192,000 27 Teakwood 3 mm 120 x 240 Lbr 93,000 28 Teakwood 3 mm Uk/ Pintu Lbr 161,000 29 Teakwood 4 mm 120 x 240 Lbr 135,000 30 Teakwood 4 mm Uk/ Pintu Lbr 111,000 31 Triplek 3 mm lbr 50,000 32 Ijuk kg 8,000 33 Plastik Cor m2 15,500

Page 6: Estimasi Biaya Badru

1 2 3 4E. BAHAN PENUTUP RANGKA PLAFOND

1 Eternit 1x1 M2 bh 5,700 2 Eternit 1x1 M2 peti 57,000 3 Asbes semen 1x1 M2 bh 26,000 4 Plat Kalsiboard (1.2x2.4)m tebal 4 mm lbr 45,000 5 Cornis Zak 85,000 6 Kumpon Kg 4,200 7 Plester @ roll 20 m Rol 75,000

F. BAHAN FINISHING : LABURAN, PENGISIAN DAN ALATNYA1 Ampelas Lbr 1,700 1 Gall 78,000 2 Kg 15,000 3 Kg 14,400 4 Kg 115,000 5 Kg 90,000 6 Dempul Kayu Kg 15,000 7 Dempul plastik Kg 27,500 1 Kuas 3 " bh 9,000 2 Kuas 4 " bh 12,100 1 Plamir Cat Kg 14,000 2 Plamir Tembok Kg 24,000 3 Rol cat Tembok Bh 12,000 4 Spirtus Ltr 14,000 1 Tiner A Ltr 8,400 2 Ltr 19,300 1 Lem kayu (fox) 0 12,600 2 Water Profing Emulision Kg 66,000 3 Finishing melamic dop/ gloss ls 15,000

G. BAHAN KACA1 Kaca Polos 2 mm m2 30,000 2 Kaca Polos 3 mm m2 48,000 3 Kaca Polos 5 mm m2 58,000 4 Kaca Rayban 5 mm m2 70,000 5 Kaca cermin 5 mm bh 55,000 6 Karet Kaca m1 65,000

H. BAHAN PAKU DAN MUR-BAUT1 Baut /Mur Kg 14,500 2 Beugel Kuda-kuda Kg 30,200 3 Dak Angker Kg 5,700 4 Kg 16,000 5 Paku Beton 2 cm s/d 5 cm bh 500 6 Rangka atap baja ringan m2 160,000

I. BAHAN SANITER1 Bak fibreglass Bh 220,000 2 bh 157,000 3 Closet Jongkok Porselin Warna bh 175,000 4 TOTO CW 420J/SW 420JP 2 tanki Warna Putih (full shet) bh 850,000 5 CLOSET JONGKOK set CE7 bh 199,300 6 Kran Tembok 3/4 " bh 18,000 7 Kran Leher angsa 1/2 " TOTO bh 85,000

Cat Tembok setara SanlexCat Tembok setara SanlexCat Tembok setara Sanlex ( Putih )Cat Tembok setara DuluxCat Tembok setara Vinilex

Tiner setara ND

Paku (berbagai macam ukuran /rata-rata)

Closet Jongkok Porselin Putih ( standar )

Page 7: Estimasi Biaya Badru

1 2 3 48 Stop Kran Tembok 1/2 " setara TOTO bh 30,000 9 Stop Kran Tembok 3/4 " setara TOTO bh 60,000 1 Kitchen Zink Stailess Non Standar franke ( 1 Lobang ) Set 225,000 2 Kitchen Zink Stailess Non Standar franke ( 2 Lobang ) Set 350,000 3 Set 351,000 4 Set 465,000 5 Seal tape Set 2,000 6 Pompa air 125 watt Unit 453,000 7 Pompa air 250 watt otomatic Unit 1,262,000 8 Pintu Fiber KM/WC Set 285,000 1 Water Drain + Assessoris set 115,000 2 Sumur Gali Ls 1,500,000 3 Instalasi Pompa + Stop kontak Ls 150,000 4 Foot Valve Dia 1" bh 25,000 5 Water Level Kontrol Unit 135,000 6 Water level kontrol NYM 2 X 2.5 MM2 ttk 125,000 7 Fitting accessories ls 98,000 8 Shower (tanpa tiang) bh 85,000 9 Shower Tube bh 120,000

10 Jetwasher bh 150,000 11 Waterheater 250 watt Unit 2,000,000 12 Kompor gas (MODENA Freestanding Cooker Type FC 7300) Unit 2,950,000 13 Penghisap asap (MODENA slim ExsausetHoodType SX 9002) Unit 1,850,000 14 Instalasi AS+Stop Kontak AC+AC LG 0,5 PK+ saluran pembuang air set 3,000,000

J. BAHAN PENUTUP ATAP1 Atap Genteng Beton Warna 14,5/m2 m2 91,000 2 Atap Genteng Beton Warna bh 6,276 3 Pipa PVC Diameter 315 mm/ Ø 12 " ( Setara Pralon P.6 m S.10 Plain End/Ts. End m2 37,500 4 Lbr 19,000 5 Bubung Asbes bh 24,900 1 Bubungan Genteng palentong bh 2,500 2 Bubungan Genteng pres bh 26,000 3 Genteng Morando Glatsur 18 bh/m2 bh 1,850 4 Genteng Morando Natural 18 bh/m2 bh 1,300 5 Genteng alumunium tebal 0.55 m2 1,500 6 Genteng palentong bh 1,200

K. BAHAN ELEKTRIKAL 1 Lampu Pijar 25 Watt bh 4,800 2 Lampu Pijar 40 Watt bh 8,400 3 Lampu PLC 18 watt bh 32,600 4 Lampu TKO 2x18 watt set 65,200 1 Saklar Ganda Broco bh 15,700 2 Saklar tunggal Broco bh 11,400 1 Stop kontak Broco bh 12,100 2 Plafond fitting Broco bh 13,000 3 Instalasi titik stop kontak Broco kabel (3x2.5mm2) skw Prima Ttk 95,000 4 Instalasi Titik Cahaya/penerangan dgn kabel Prima (2x2.5mm2) Ttk 110,000 5 Box panel Lengkap bh 300,000

Wastafel setara merk INA ( lengkap )Wastafel setara merk TOTO

Atap Plastik 80 x 180 ( Gelombang )

Page 8: Estimasi Biaya Badru

1 2 3 41 Box Presto 8 group Unit 75,000 2 MCB induk 10 A bh 55,000 3 MCB induk 6 A bh 45,000 4 Otomatis Radar pompair + Pelampung 0 57,500 5 Soket Antena bh 18,000 6 Soket Telepon bh 17,000 7 BP Telepon 1 Line Ls 1,000,000 8 BP Listrik 3600 VA Ls 3,500,000 9 UJL Listrik 3600 VA Ls 2,000,000

10 Kabel NYY 2x2,5mm m 10,000 11 Kabel NYY 3x2,5mm m 11,500 12 Kabel NYY 3x6,5mm m 30,000 13 Kabel NYY 3x10mm m 45,000 14 Solatif kabel roll 5,500 15 T - Dus bh 5,500 16 Inbow - dus bh 7,500 17 Kabel telephone m1 7,000 18 Kabel TV m1 6,500 19 Kabel Tuvur 3x6 m m1 11,000 20 Kabel Tuvur 3x2,5 m m1 9,000 21 Kabel tembaga bc 5 m1 4,500 22 Fiting lampu Down Ligt exs Artolite RD 150 m1 20,000 23 Fiting Lampu Bundar exs Artolite B 79923 m1 21,500 24 Fitting Lampu gantung exs artolite HLG CF BG C3 m1 22,000 25 Fitting Lampu exs Artolite RD 3HALOGEN REFF m1 25,000 26 Fiting Lampu Taman exs Artolite GL PILAR DAIKO KOTAK m1 30,000 27 Fiting Lampu Tempel Kolom exs Artolite WL DAICO m1 32,000 28 Fiting Lampu exs Artolite RD 21- 1 HALLOGEN m1 35,000 29 Lampu Down Ligt exs Philips cool dayligt 20 W TORNADO m1 45,000 30 Lampu Bundar exs Philips cool daylight CIRCLEuntuk dalam ruangan m1 34,000 31 Lampu gantung exs philips Incandescent E 27 25 W m1 40,000 32 Lampu exs QR-CBC51 GU 5.3 20 W m1 42,000 33 Lampu Taman exs philips Essential E 27 - 18 W m1 30,000 34 Lampu Tempel Kolom exs philips Essential E 27 8 W m1 28,000 35 Lampu exs QR-CBC 51 GU 5.3 20 W m1 35,000

L. BAHAN ALAT PENGGANTUNG KUNCI1 bh 9,600 2 bh 13,500 3 bh 9,600 4 bh 13,500 5 Engsel Casement Anderberg 24 " Bh 12,000 6 Engsel Angin Bh 9,600 7 Grendel 15 cm bh 20,700 8 Grendel 5 cm bh 4,000 9 Hak Angin Biasa bh 9,000

10 Hak Angin Stainless bh 12,500 11 Kunci 2 Slaag ukuran sedang bh 78,600 12 bh 139,100 13 bh 165,000 14 bh 150,000 15 Kunci Km/ WC bh 75,000 16 Kunci Gembok (lengkap) bh 4,800 17 Kunci Sek. Alpha bh 66,000 18 Kunci tanam Antik bh 33,300 19 Slot Jendela bh 4,800 20 Slot Pintu tanam Set 3,000 21 Grendel stainless 6" bh 17,000 22 Grendel stainless 12" bh 21,000 23 Door Holder/ tarikan pintu bh 22,600 24 Door Stoper bh 18,700

Engsel Jendela setara UNIONEngsel Jendela setara HINGES Engsel Pintu setara UNIONEngsel Pintu setara HINGES

Kunci tanam setara TESAKunci tanam 2 slaag 2 pintu setara HINGESKunci tanam 2 slaag 1 pintu setara HINGES

Page 9: Estimasi Biaya Badru

1 2 3 425 Window Lock bh 6,000 26 Floor Hinge bh 13,500 27 Handle Alumunium Psng 50,000 28 kait Angin alumunium Psng 41,600 29 Ripet Psng 7,500 30 Kunci Silinder Kaca bh 33,300 31 Springknip (stainless steel) bh 21,000 32 Rel, engsel, handle, kunci pintu sliding (lengkap) set 1,500,000 33 Alumunium Foil m2 20,000

Page 10: Estimasi Biaya Badru

1 2 3 4M. BAHAN LANTAI DAN PELAPIS DINDING

1 m2 /Dus 52,500 2 Keramik 40 x 40 ROMAN Warna m2 /Dus 54,000 3 bh 38,000 4 Keramik 30 x 30 KW I DN Warna KW 1 bh 42,000 5 Keramik 30 x 30 KW I DN POLOS KW II bh 50,000 6 Keramik 30 x 30 ROMAN Vivaldi Garnet m2 /Dus 48,900 7 Keramik 30 x 30 ROMAN Strata Black m2 /Dus 50,000 8 Keramik 30 x 30 ROMAN Colonial Sabia m2 /Dus 45,000 9 Keramik 33 x 33 ROMAN Columbus Beige m2 /Dus 46,000

10 Keramik 25 x 33 ROMAN Aquila Crema m2 /Dus 45,000 11 Keramik 25 x 33 ROMAN Aquila Bruno m2 /Dus 42,000 12 bh 39,000 13 Keramik 20 x 20 KW I DN Warna bh 44,000 14 Keramik 20 x 20 KW I DN Warna anti slip bh 47,000 15 Keramik 20 x 20 ROMAN Troy Bruno m2 /Dus 52,000 16 Keramik 20 x 20 ROMAN Giada Beige m2 /Dus 51,500 17 Keramik 20 x 20 ROMAN Venere Crème m2 /Dus 50,000 18 bh 41,000 19 Keramik 20 x 25 KW I DN Warna bh 47,000 20 Keramik 20 x 25 ROMAN Canossa Dark m2 /Dus 48,000 21 Keramik 20 x 25 ROMAN Canossa Beige m2 /Dus 48,000 22 Keramik 10 x 40 ROMAN m1 /Dus 24,000 23 Keramik 10 x 30 ROMAN Vivaldi Garnet m1 /Dus 24,000 24 Keramik 10 x 30 ROMAN Strata Black m1 /Dus 24,000 25 Keramik 10 x 30 ROMAN colonial sabia m1 /Dus 23,500 26 Keramik 7 x 25 ROMAN Tulip Aquila Crema Listello m1 /Dus 30,000 27 Keramik 7 x 25 ROMAN Tulip Aquila Crema Listello bh 7,500 28 Keramik 6 x 20 ROMAN Marigold Marmara Beige m1 /Dus 22,500 29 Keramik 6 x 20 ROMAN Marigold Marmara Beige bh 4,500 30 Keramik 6 x 20 Light new zhutilani beige mulia bh 9,600 31 Step nosing 30 cm Bh 3,750 32 Border Keramik 20 cm Bh 2,500

N. HARGA BBM1 Premium Ltr 4,500 2 Minyak Solar Ltr 4,300 1 Minyak Bakar Ltr 7,500 2 Pelumas Bekisting Ltr 12,600 3 Olie SAE (Mesran, Pertamina) Ltr 19,000

Bandung, 05 Juni 2012 Estimator,

Riezqi BadruzamanTeguh Firmansyah

Keramik 40 x 40 ROMAN ( polos)

Keramik 30 x 30 KW I DN Putih ( polos) KW 1

Keramik 20 x 20 KW I DN Putih ( polos)

Keramik 20 x 25 KW I DN ( Polos )

Page 11: Estimasi Biaya Badru

ANALISA HARGA SATUAN PEKERJAAN

NO. URAIAN KOEF. SAT.

1 2 3 4 5 6 = (3 x 5) A1 1 M2 PEK. PEMBERSIHAN LOKASI

Pekerja 0.01 org 35,000 350

Mandor 0.00 org 60,000 60

Alat Bantu 0.10 lot 47,500 4,750

Jumlah 5,160

Keuntungan Maksimal 10% 516

Jumlah Total 5,676

Dibulatkan 5,650

HARGA SATUAN

Rp.

JUMLAH HARGA Rp.

Page 12: Estimasi Biaya Badru

1 2 3 4 5 6 = (3 x 5) A2 1 M1 PEK. PASANGAN BOUWPLANK

Kayu Terentang 0.01 m3 1,400,000 14,000

Paku 5-7 0.04 kg 16,000 640

Ongkos Pasang 0.20 lot 14,160 2,832

Jumlah 17,472

Keuntungan Maksimal 10% 1,747

Jumlah Total 19,219

Dibulatkan 19,200

A3 1 M3 PEK. GALIAN TANAH PONDASI MAX KEDALAMAN 1 M¹

Tukang Gali 0.40 org 40,000 16,000

Mandor 0.04 org 60,000 2,400

Alat Bantu 0.10 lot 10,000 1,000

Jumlah 19,400

Keuntungan Maksimal 10% 1,940

Jumlah Total 21,340

Dibulatkan 21,300

A4 1 M3 URUGAN PASIR URUG

Pasir urug 1.20 m3 95,000 114,000

Pekerja 0.15 org 35,000 5,250

Mandor 0.01 org 60,000 600

Jumlah 119,850

Keuntungan Maksimal 10% 11,985

Jumlah Total 131,835

Dibulatkan 131,800

A5 1 M3 URUGAN TANAH KEMBALI DIPADATKAN

Tukang Gali 0.19 org 40,000 7,600

Mandor 0.02 org 60,000 1,200

Alat Bantu 0.10 lot 10,000 1,000

Jumlah 9,800

Keuntungan Maksimal 10% 980

Jumlah Total 10,780

Dibulatkan 10,750

A6 1 M3 PASANGAN AANSTAMPING BATU BELAH

Batu Belah 1.20 m3 120,000 144,000

Pasir Pasang 0.10 m3 65,000 6,500

Pekerja 0.50 org 35,000 17,500

Tk. Batu setengah terampil 0.56 org 35,000 19,600

Mandor 0.06 org 60,000 3,600

Jumlah 191,200

Keuntungan Maksimal 10% 19,120

Jumlah Total 210,320

Dibulatkan 210,300

A7 1 M3 PASANGAN BATU BELAH 1 : 5

Batu Belah 1.20 m3 120,000 144,000

Semen PC (50 kg) 1.08 zak 55,000 59,400

Pasir Pasang 0.44 m3 65,000 28,600

Pekerja 1.25 org 35,000 43,750

Tk. Batu setengah terampil 0.50 org 35,000 17,500

Mandor 0.02 org 60,000 1,200

Jumlah 294,450

Keuntungan Maksimal 10% 29,445

Jumlah Total 323,895

Dibulatkan 323,850

Page 13: Estimasi Biaya Badru

1 2 3 4 5 6 = (3 x 5) A8 1 M3 LANTAI KERJA 1 PC : 3 PS : 5 KRL/ RABAT BETON

Semen PC (50 kg) 3.96 zak 55,000 217,800

Pasir beton 0.55 m3 125,000 68,750

Split Pecah mesin 1/2 0.93 m3 153,000 142,290

Pekerja 2.00 org 35,000 70,000

Tk. Batu setengah terampil 0.50 org 35,000 17,500

Mandor 0.01 org 60,000 600

Alat Bantu 0.10 lot 33,300 3,330

Jumlah 520,270

Keuntungan Maksimal 10% 52,027

Jumlah Total 572,297

Dibulatkan 572,250

A9 1 M3 COR BETON SITE MIX K.175

Semen PC (50 kg) 6.80 zak 55,000 374,000

Pasir beton 0.54 m3 125,000 67,500

Split Pecah mesin 1/2 0.83 m3 153,000 126,990

Pekerja 1.50 org 35,000 52,500

Tk. Batu setengah terampil 0.50 org 35,000 17,500

Mandor 0.01 org 60,000 600

Peralatan 0.10 lot 33,300 3,330

Jumlah 642,420

Keuntungan Maksimal 10% 64,242

Jumlah Total 706,662

Dibulatkan 706,650

A10 1 KG BESI BETON TERPASANG U - 24

Besi beton rata-rata 1.05 kg 10,000 10,500

Kawat beton 0.01 kg 15,000 150

Tk. Besi setengah terampil 0.03 org 35,000 1,050

Tk. Besi beton terampil 0.02 org 40,000 800

Mandor 0.01 org 60,000 600

Peralatan 0.10 lot 2,500 250

Jumlah 13,350

Keuntungan Maksimal 10% 1,335

Jumlah Total 14,685

Dibulatkan 14,650

Page 14: Estimasi Biaya Badru

1 2 3 4 5 6 = (3 x 5) A11 1 M2 BEKISTING MULTIPLEK 9 MM

Kaso 5/7 Borneo Super (2x pakai) 50% 0.02 m3 2,000,000 40,000

Multiplek 9 mm (2x pakai) 75% 0.35 lbr 104,250 36,488

Paku 0.40 kg 16,000 6,400

Pekerja 0.12 org 35,000 4,200

Tk. Kayu terampil 0.15 org 40,000 6,000

Mandor 0.05 org 60,000 3,000

Tk. Kayu 1/2 terampil (bongkar cetakan) 0.12 org 35,500 4,260

Jumlah 100,348

Keuntungan Maksimal 10% 10,035

Jumlah Total 110,382

Dibulatkan 110,350

A12 1 M2 BEKISTING DENGAN PAPAN

Kaso 5/7 Borneo Super (2x pakai) 50% 0.02 m3 2,000,000 40,000

Papan terentang (2x pakai) 75% 0.02 m3 1,050,000 21,000

Paku 0.40 kg 16,000 6,400

Pekerja 0.12 org 35,000 4,200

Tk. Kayu terampil 0.15 org 40,000 6,000

Mandor 0.05 org 60,000 3,000

Tk. Kayu 1/2 terampil (bongkar cetakan) 0.12 org 35,500 4,260

Jumlah 84,860

Keuntungan Maksimal 10% 8,486

Jumlah Total 93,346

Dibulatkan 93,300

Page 15: Estimasi Biaya Badru

1 2 3 4 5 6 = (3 x 5) A13 1 M2 PASANGAN 1/2 BATA MERAH 1 : 5

Bata Merah 70.00 bh 500 35,000

Semen PC (50 kg) 0.20 zak 55,000 11,000

Pasir Pasang 0.06 m3 65,000 3,900

Pekerja setengah terampil 0.32 org 30,000 9,600

Tk. Batu terampil 0.18 org 45,000 8,100

Mandor 0.01 org 60,000 600

Jumlah 68,200

Keuntungan Maksimal 10% 6,820

Jumlah Total 75,020

Dibulatkan 81,840

A14 1 M2 PAS. PLESTERAN DINDING 1 : 5 + ACIAN

Semen PC (50 kg) 0.10 zak 55,000 5,500

Pasir Pasang 0.02 m3 65,000 1,300

Pekerja setengah terampil 0.29 org 30,000 8,700

Tk. Batu setengah terampil 0.21 org 45,000 9,450

Mandor 0.02 org 60,000 1,200

Jumlah 26,150

Keuntungan Maksimal 10% 2,615

Jumlah Total 28,765

Dibulatkan 28,750

Page 16: Estimasi Biaya Badru

1 2 3 4 5 6 = (3 x 5) A15 1 M2 ATAP BAJA RINGAN

Rangka Atap Baja Ringan 1.00 m2 160,000 160,000

Alat Bantu 0.10 ls 16,000 1,600

Jumlah 161,600

Keuntungan Maksimal 10% 16,160

Jumlah Total 177,760

Dibulatkan 177,750

A16 1 M1 PASANGAN PLASTIK BUBUNGAN

Plastik Cor 0.25 m2 15,500 3,875

Alat 1.00 ls 1,550 1,550

Upah Pasang 1.00 ls 3,100 3,100

Jumlah 8,525

Keuntungan Maksimal 10% 853

Jumlah Total 9,378

Dibulatkan 9,350

A17 1 M2 PASANGAN ATAP GENTENG ALUMUNIUM TEBAL 0.55

Genting alumunium tebal 0.55 18.00 bh 1,500 27,000

Pekerja setengah terampil 0.12 org 30,000 3,600

Tukang kayu setengah terampil 0.06 org 35,500 2,130

Mandor 0.01 org 60,000 600

Jumlah 33,330

Keuntungan Maksimal 10% 3,333

Jumlah Total 36,663

Dibulatkan 36,650

Page 17: Estimasi Biaya Badru

1 2 3 4 5 6 = (3 x 5) A18 1 M2 PAS. PLAFOND GRC 4 MM + BESI HOLO 4x4

Rangka hollow 40x40 @ 4m¹ 0.50 btg 75,000 37,500

Rangka hollow 20x40 @ 4m¹ 0.67 btg 55,000 36,850

Paku 0.22 kg 16,000 3,520

Pekerja setengah terampil 0.28 org 30,000 8,400

Tukang kayu terampil 0.40 org 40,000 16,000

Mandor 0.01 org 60,000 600

Jumlah 102,870

Keuntungan Maksimal 10% 10,287

Jumlah Total 113,157

Dibulatkan 113,150

A19 1 M2 PAS. PLAFOND GYPSUM 9 MM BERIKUT RANGKA BESI HOLO 4x4

Gypsum 9 mm 0.35 lbr 72,000 25,200

Rangka hollow 40x40 @ 4m¹ 0.50 btg 75,000 37,500

Rangka hollow 20x40 @ 4m¹ 0.67 btg 55,000 36,850

Paku 0.22 kg 16,000 3,520

Pekerja setengah terampil 0.28 org 30,000 8,400

Tukang kayu terampil 0.40 org 40,000 16,000

Mandor 0.01 org 60,000 600

Jumlah 128,070

Keuntungan Maksimal 10% 12,807

Jumlah Total 140,877

Dibulatkan 140,850

A20 1 M1 PEKERJAAN LIST PLAFOND GYPSUM 5 cm

List Gypsum 5 cm 1.00 m1 70,000 70,000

Paku 0.01 kg 16,000 160

Pekerja terampil 0.07 org 30,000 2,100

Tukang kayu setengah terampil 0.02 org 35,500 710

Mandor 0.00 org 60,000 60

Jumlah 73,030

Keuntungan Maksimal 10% 7,303

Jumlah Total 80,333

Dibulatkan 80,300

Page 18: Estimasi Biaya Badru

1 2 3 4 5 6 = (3 x 5) A21 1 BH PASANG KUNCI 2 HINGES UNTUK DAUN SATU DAUN PINTU

Kunci tanam 2 slagg HINGES 1.00 sheet 150,000 150,000

Tukang kayu terampil 0.35 org 50,000 17,500

Jumlah 167,500

Keuntungan Maksimal 10% 16,750

Jumlah Total 184,250

Dibulatkan 184,250

A22 1 BH PASANG KUNCI KM/ WC

Lockset KC-BL-DKS-8587-BK-SS 1.00 bh 75,000 75,000

Tukang kayu terampil 0.35 org 50,000 17,500

Jumlah 92,500

Keuntungan Maksimal 10% 9,250

Jumlah Total 101,750

Dibulatkan 101,750

A23 1 BH PASANG ENGSEL PINTU

Hinges ES-IR-DKS-4"x3"x3mm-4BB-SN, engsel daun pintu 1.00 bh 13,500 13,500

Tukang kayu terampil 0.08 org 50,000 4,000

Jumlah 17,500

Keuntungan Maksimal 10% 1,750

Jumlah Total 19,250

Dibulatkan 19,250

A24 1 BH PASANG ENGSEL JENDELA

Hinges ES-IR-DKS-4"x3"x3mm-4BB-SN, engsel daun jendela 1.00 bh 13,500 13,500

Tukang kayu terampil 0.08 org 50,000 4,000

Jumlah 17,500

Keuntungan Maksimal 10% 1,750

Jumlah Total 19,250

Dibulatkan 19,250

A25 1 BH PASANG SLOT JENDELA

Slot jendela spring knief 1.00 bh 4,800 4,800

Tukang kayu terampil 0.08 org 50,000 4,000

Jumlah 8,800

Keuntungan Maksimal 10% 880

Jumlah Total 9,680

Dibulatkan 9,650

Page 19: Estimasi Biaya Badru

1 2 3 4 5 6 = (3 x 5) A26 1 M2 PASANG KACA POLOS TEBAL 5 mm, BEPEL 1 MUKA L 2 cm

Kaca polos tebal 5 mm 1.10 m2 70,000 77,000

Pekerja 0.15 org 35,000 5,250

Tukang kayu terampil 0.15 org 40,000 6,000

Jumlah 88,250

Keuntungan Maksimal 10% 8,825

Jumlah Total 97,075

Dibulatkan 97,050

A27 1 M2 PASANG KACA ES TEBAL 5 mm,

Kaca polos tebal 5 mm 1.10 m2 58,000 63,800

Pekerja 0.15 org 35,000 5,250

Tukang kayu terampil 0.15 org 40,000 6,000

Jumlah 75,050

Keuntungan Maksimal 10% 7,505

Jumlah Total 82,555

Dibulatkan 82,550

A28 1 M2 ROMAN 20x20 TROY BRUNO

Roman 20x20 troy bruno 1.01 m2 52,000 52,520

Semen PC (50 kg) 0.16 zak 55,000 8,800

Pasir pasang 0.03 m3 55,000 1,650

Pekerja terampil 0.19 org 50,000 9,500

Tukang batu terampil 0.38 org 45,000 17,100

Mandor 0.02 org 60,000 1,200

Jumlah 90,770

Keuntungan Maksimal 10% 9,077

Jumlah Total 99,847

Dibulatkan 99,800

Page 20: Estimasi Biaya Badru

1 2 3 4 5 6 = (3 x 5) A29 1 M2 ROMAN 20x20 GIADA BEIGE

Roman 20x20 giada beige 1.01 m2 51,500 52,015

Semen PC (50 kg) 0.16 zak 55,000 8,800

Pasir pasang 0.03 m3 55,000 1,650

Pekerja terampil 0.19 org 50,000 9,500

Tukang batu terampil 0.38 org 45,000 17,100

Mandor 0.02 org 60,000 1,200

Jumlah 90,265

Keuntungan Maksimal 10% 9,027

Jumlah Total 99,292

Dibulatkan 99,250

A30 1 M2 PAS. LANTAI KERAMIK 30/30 ROMAN VIVALDI GARNET

Roman 30x30 vivaldi garnet 1.01 m2 48,900 49,389

Semen PC (50 kg) 0.16 zak 55,000 8,800

Pasir pasang 0.03 m3 65,000 1,950

Pekerja terampil 0.19 org 50,000 9,500

Tukang batu terampil 0.38 org 45,000 17,100

Mandor 0.02 org 60,000 1,200

Jumlah 87,939

Keuntungan Maksimal 10% 8,794

Jumlah Total 96,733

Dibulatkan 96,700

Page 21: Estimasi Biaya Badru

1 2 3 4 5 6 = (3 x 5) A31 1 M2 PENGECATAN DINDING VINILEX (3X)

Cat tembok Vinilex 0.18 kg 90,000 16,200

Plamur tembok 0.16 kg 24,000 3,840

Roll cat 0.01 bh 12,000 120

Ampelas 0.50 lbr 1,700 850

Pekerja 0.10 org 35,000 3,500

Tukang cat setengah terampil 0.18 org 35,000 6,300

Mandor 0.01 org 60,000 600

Jumlah 31,410

Keuntungan Maksimal 10% 3,141

Jumlah Total 34,551

Dibulatkan 34,550

A32 1 M2 PENGECATAN PLAFOND DULUX ICI (3X)

Cat tembok dulux ICI 0.20 kg 115,000 23,000

Plamur tembok 0.16 kg 24,000 3,840

Roll cat 0.01 bh 12,000 120

Ampelas 0.50 lbr 1,700 850

Pekerja 0.10 org 35,000 3,500

Tukang cat setengah terampil 0.18 org 35,000 6,300

Mandor 0.01 org 60,000 600

Jumlah 38,210

Keuntungan Maksimal 10% 3,821

Jumlah Total 42,031

Dibulatkan 42,000

Page 22: Estimasi Biaya Badru

1 2 3 4 5 6 = (3 x 5) A33 1 M2 MELAMIK DAUN JENDELA

Ampelas 1.00 lbr 1,700 1,700

Thiner 0.20 ltr 8,400 1,680

Finishing melamic dop/ gloss 0.10 kgr 15,000 1,500

Alat 1.00 ls 2,510 2,510

Pekerja setengah terampil 0.26 org 30,000 7,800

Tukang cat terampil 0.14 org 40,000 5,600

Mandor 0.02 org 60,000 1,200

Jumlah 21,990

Keuntungan Maksimal 10% 2,199

Jumlah Total 24,189

Dibulatkan 24,150

A34 1 M2 MELAMIK DAUN PINTU

Ampelas 1.50 lbr 1,700 2,550

Thiner 0.25 ltr 8,400 2,100

Finishing melamic dop/ gloss 0.12 kgr 15,000 1,800

Alat 1.00 ls 2,510 2,510

Pekerja setengah terampil 0.26 org 30,000 7,800

Tukang cat terampil 0.14 org 40,000 5,600

Mandor 0.02 org 60,000 1,200

Jumlah 23,560

Keuntungan Maksimal 10% 2,356

Jumlah Total 25,916

Dibulatkan 25,900

Page 23: Estimasi Biaya Badru

ANALISA HARGA SATUAN PEKERJAANMEKANIKAL DAN ELEKTRIKAL

NO. URAIAN KOEF. SAT.

1 2 3 4 5 6 = (3 x 5)

ANALISA ELEKTRIKAL A1 1 TTK PAS. TITIK LAMPU/CAHAYA

Kabel NYM 2 X 2,5 7.8000 m1 10,000 78,000

Solatif Kabel 0.3330 roll 5,500 1,832

Pipa Kabel 2.0000 btg 5,000 10,000

T - Dus 1.0000 bh 5,500 5,500

Inbow - dus 1.0000 bh 7,500 7,500

Upah Kerja 1.0000 ls 6,700 6,700

Jumlah 109,532

Keuntungan Maksimal 10% 10,953

Jumlah Total 120,485

Dibulatkan 120,450 A2 1 TTK PAS.TITIK DAYA/STOP KONTAK

Kabel NYM 3 X 2,5 9.0000 m1 11,500 103,500

Solatif Kabel 0.3330 roll 5,500 1,832

Pipa Kabel 2.0000 btg 5,000 10,000

T - Dus 1.0000 bh 5,500 5,500

Inbow - dus 1.0000 bh 7,500 7,500

Upah Kerja Pasang 1.0000 ls 7,000 7,000

Jumlah 135,332

Keuntungan Maksimal 10% 13,533

Jumlah Total 148,865

Dibulatkan 148,850 A3 1 BH PAS. ARMATUR STOP KONTAK

Stop Kontak 250 Watt" BROCO 1.0000 bh 12,100 12,100

Alat Bantu 1.0000 ls 1,210 1,210

Upah Kerja Pasang 1.0000 ls 2,420 2,420

Jumlah 15,730

Keuntungan Maksimal 10% 1,573

Jumlah Total 17,303

Dibulatkan 17,300 A4 1 BH PAS.ARMATUR SAKLAR ENGSEL

Saklar Engsel " BROCO 1.0000 bh 11,400 11,400

Alat Bantu 1.0000 ls 1,140 1,140

Upah Kerja Pasang 1.0000 ls 2,280 2,280

Jumlah 14,820

Keuntungan Maksimal 10% 1,482

Jumlah Total 16,302

Dibulatkan 16,300 A5 1 BH PAS. ARMATUR SAKLAR SERI (Ganda )

Saklar Seri " BROCO 1.0000 bh 15,700 15,700

Alat Bantu 1.0000 ls 1,570 1,570

Upah Kerja Pasang 1.0000 ls 3,140 3,140

Jumlah 20,410

Keuntungan Maksimal 10% 2,041

Jumlah Total 22,451

Dibulatkan 22,450

HARGA SATUAN

Rp.

JUMLAH HARGA Rp.

Page 24: Estimasi Biaya Badru

1 2 3 4 5 6 = (3 x 5)A6 BOX x PRESTO + 8 grup MCB ex MERLIN GERYN

Box Presto 8 Grop 1.0000 bh 75,000 75,000

mcb Induk 10 A exs Nerlin gerin 1.0000 bh 55,000 55,000

mcb Induk 6 A exs Nerlin gerin 7.0000 bh 45,000 315,000

Alat Bantu 1.0000 ls 17,500 17,500

Upah Kerja Pasang 1.0000 ls 35,000 35,000

Jumlah 497,500

Keuntungan Maksimal 10% 49,750

Jumlah Total 547,250

Dibulatkan 547,250

Page 25: Estimasi Biaya Badru

1 2 3 4 5 6 = (3 x 5)A7 Lampu Down Ligt exs Philips cool dayligt 20 W TORNADO

Lampu Down Ligt exs Philips cool dayligt 20 W TORNADO 1.0000 m1 45,000 45,000

Alat Bantu 1.0000 ls 4,500 4,500

Upah Kerja 1.0000 ls 9,000 9,000

Jumlah 58,500

Keuntungan Maksimal 10% 5,850

Jumlah Total 64,350

Dibulatkan 64,350 A8 Fiting Lampu Bundar exs Artolite B 79923

Fiting Lampu Bundar exs Artolite B 79923 1.0000 m1 21,500 21,500

Alat Bantu 1.0000 ls 2,150 2,150

Upah Kerja 1.0000 ls 4,300 4,300

Jumlah 27,950

Keuntungan Maksimal 10% 2,795

Jumlah Total 30,745

Dibulatkan 30,700 A9 Lampu Bundar exs Philips cool daylight CIRCLEuntuk dalam ruangan

Lampu Bundar exs Philips cool daylight CIRCLEuntuk dalam 1.0000 m1 34,000 34,000

Alat Bantu 1.0000 ls 3,400 3,400

Upah Kerja 1.0000 ls 6,800 6,800

Jumlah 44,200

Keuntungan Maksimal 10% 4,420

Jumlah Total 48,620

Dibulatkan 48,600

Page 26: Estimasi Biaya Badru

1 2 3 4 5 6 = (3 x 5)

ANALISA MEKANIKAL/PLUMBING A10 1 M 1 PAS.PIPA PVC dia.3 "

Pipa PVC dia. 3 " 0.2500 btg 56,000 14,000

Fiting & Assesories 0.1000 lot 98,000 9,800

Alat Bantu 0.1000 lot 15,400 1,540

Upah Kerja 0.2000 lot 30,800 6,160

Jumlah 31,500

Keuntungan Maksimal 10% 3,150

Jumlah Total 34,650

Dibulatkan 34,650

Page 27: Estimasi Biaya Badru

1 2 3 4 5 6 = (3 x 5)A11 1 M 1 PAS.PIPA PVC dia. 3/4"

Pipa PVC dia. 3/4 " 0.2500 btg 11,000 2,750

Fiting & Assesories 0.1000 lot 98,000 9,800

Alat Bantu 0.1000 lot 10,900 1,090

Upah Kerja 0.2000 lot 21,800 4,360

Jumlah 18,000

Keuntungan Maksimal 10% 1,800

Jumlah Total 19,800

Dibulatkan 19,800 A12 1 M 1 PAS.PIPA PVC dia. 1/2"

Pipa PVC dia. 1/2 " 0.2500 btg 5,000 1,250

Fiting & Assesories 0.1000 lot 98,000 9,800

Alat Bantu 0.1000 lot 10,300 1,030

Upah Kerja 0.2000 lot 20,600 4,120

Jumlah 16,200

Keuntungan Maksimal 10% 1,620

Jumlah Total 17,820

Dibulatkan 17,800

Page 28: Estimasi Biaya Badru

1 2 3 4 5 6 = (3 x 5)A13 1 UNIT GALIAN SEPTICTANK + SEPTICTANK,exs Bio Tank

Galian 4.5000 m3 21,300 95,850

Septictank Bio Tank 1.0000 bh 1,200,000 1,200,000

Alat 1.0000 ls 122,130 122,130

Upah Pasang 1.0000 ls 244,260 244,260

Jumlah 1,662,240

Keuntungan Maksimal 10% 166,224

Jumlah Total 1,828,464

Dibulatkan 1,828,450

ANALISA SANITARYA14 1 UNIT PAS.CLOSET JONGKOK TOTO CE7+PAS.BATA

1 PAS.CLOSET JONGKOK set CE7 1.0000 bh 199,300 199,300

Pekerja Trampil 1.0000 org 50,000 50,000

TK Batu Terampil 1.5000 org 45,000 67,500

Mandor 0.0500 org 60,000 3,000

Jumlah 319,800

Keuntungan Maksimal 10% 31,980

Jumlah Total 351,780

Dibulatkan 351,750

Page 29: Estimasi Biaya Badru

1 2 3 4 5 6 = (3 x 5)A15 1 UNIT CERMIN 5 mm = 100 cm x75 cm

Cermin 5 mm 100 x 75cm 1.0000 bh 55,000 55,000

Upah Kerja 0.0500 lot 11,000 550

Alat Bantu 0.0250 lot 5,500 138

Jumlah 55,688

Keuntungan Maksimal 10% 5,569

Jumlah Total 61,256

Dibulatkan 61,250

A16 1 BH PAS.KRAN AIR TOTO 1/2"

Kran Air 1.0000 bh 30,000 30,000

Alat Bantu (10%bahan) 0.1000 lot 3,000 300

Upah Kerja Pasang (20 % bahan) 0.2000 lot 6,000 1,200

Jumlah 31,500

Keuntungan Maksimal 10% 3,150

Jumlah Total 34,650

Dibulatkan 34,650

Page 30: Estimasi Biaya Badru

1 2 3 4 5 6 = (3 x 5)

Page 31: Estimasi Biaya Badru

DAFTAR ANALISA BETON BERTULANG

NO. URAIAN KOEF. SAT.

1 2 3 4 5 6 = (3 x 5)A 1 1 M3 ANALISA BETON PONDASI (K-175)

Beton Site Mix K-175 1.05 m3 706,650 741,983

Besi Beton 6 ǿ 10 mm(Memanjang) 42.78 KG 14,650 626,727

Besi Beton 6 ǿ 10 mm(Melintang) 42.78 KG 14,650 626,727

Bekisting Papan 2.50 M2 93,300 233,250

Jumlah 2,228,687

Dibulatkan 2,228,650 A 2 1 M3 ANALISA BETON SLOOF S1 15/20 (K-175)

Beton Site Mix K-175 1.05 m3 706,650 741,983

Besi Beton 4 ǿ12 mm 118.89 KG 14,650 1,741,739

Besi Beton Cincin ǿ 8mm-150 mm 48.28 KG 14,650 707,302

Bekisting Papan 20.00 M2 93,300 1,866,000

Jumlah 5,057,023

Dibulatkan 5,057,000 A3 1 M3 ANALISA BETON KOLOM PRAKTIS (KP) 15/15

Beton Site Mix K-175 1.05 M3 706,650 741,983

Besi Beton 4 ǿ12 mm 109.63 KG 14,650 1,606,080

Besi Beton Cincin ǿ 8mm-(150s/d200)mm 50.16 KG 14,650 734,844

Bekisting Multipleks 9mm 26.67 M2 110,350 2,943,035

Jumlah 6,025,941

Dibulatkan 6,025,900 A4 1 M3 ANALISA BETON BP/RING BALOK 15/20 (K-175)

Beton Site Mix K-175 1.05 M3 706,650 741,983

Besi Beton 4 ǿ12 mm 82.22 KG 14,650 1,204,523

Besi Beton Cincin ǿ 8mm-(150s/d200)mm 27.65 KG 14,650 405,073

Bekisting Multipleks 9mm 5.50 M2 110,350 606,925

Jumlah 2,958,503

Dibulatkan 2,958,500

HARGA SATUAN

Rp.

JUMLAH HARGA Rp.

Page 32: Estimasi Biaya Badru

1 2 3 4 5 6 = (3 x 5)

Bandung, 05 Juni 2012 Estimator,

Page 33: Estimasi Biaya Badru

DAFTAR HARGA SATUAN PEKERJAAN

URAIAN PEKERJAAN

1 2 3PEKERJAAN PERSIAPAN

A1 1 M2 PEK. PEMBERSIHAN LOKASI 5,650.00

A2 1 M1 PEK. PASANGAN BOUWPLANK 19,200.00

A3 1 M3 PEK. GALIAN TANAH PONDASI MAX KEDALAMAN 1 M¹ 21,300.00

A4 1 M3 URUGAN PASIR URUG 131,800.00

A5 1 M3 URUGAN TANAH KEMBALI DIPADATKAN 10,750.00

A6 1 M3 PASANGAN AANSTAMPING BATU BELAH 210,300.00

A7 1 M3 PASANGAN BATU BELAH 1 : 5 323,850.00

PEKERJAAN BEKISTING

A1 1 M2 BEKISTING MULTIPLEK 9 MM 110,350.00

A2 1 M2 BEKISTING DENGAN PAPAN 93,300.00

PASANGAN BATA DAN BATU ALAM DAN PROFILAN

A1 1 M2 PASANGAN 1/2 BATA MERAH 1 : 5 81,840.00

A2 1 M2 PAS. PLESTERAN DINDING 1 : 5 + ACIAN 28,750.00

PEKERJAAN ATAP

A1 1 M2 ATAP BAJA RINGAN 177,750.00

A2 1M2 PASANGAN ATAP GENTENG ALUMUNIUM TEBAL 0.55 36,650.00

A3 1 M1 PASANGAN PLASTIK BUBUNGAN 9,350.00

NO. KODE

JUMLAH HARGA (Rp.)

Page 34: Estimasi Biaya Badru

1 2 3A4

PEKERJAAN PLAFOND

A1 1 M2 PAS. PLAFOND GYPSUM 9 MM BERIKUT RANGKA BESI HOLO 4x4 140,850.00

A2 1 M1 PEKERJAAN LIST PLAFOND GYPSUM 5 cm 80,300.00

PEKERJAAN KUSEN

A1 1 BH PASANG KUNCI 2 HINGES UNTUK DAUN SATU DAUN PINTU 184,250.00

A2 1 BH PASANG KUNCI KM/ WC 101,750.00

A3 1 BH PASANG ENGSEL PINTU 19,250.00

A4 1 BH PASANG ENGSEL JENDELA 19,250.00

A5 1 BH PASANG SLOT JENDELA 9,650.00

A6 1 M2 PASANG KACA POLOS TEBAL 5 mm, BEPEL 1 MUKA L 2 cm 97,050.00

A7 1 M2 PASANG KACA ES TEBAL 5 mm, 82,550.00

PEKERJAAN LANTAI

A1 1 M2 ROMAN 20x20 TROY BRUNO 99,800.00

A2 1 M2 ROMAN 20x20 GIADA BEIGE 99,250.00

A3 1 M2 PAS. LANTAI KERAMIK 30/30 ROMAN VIVALDI GARNET 96,700.00

Page 35: Estimasi Biaya Badru

1 2 3

PEKERJAAN CAT DAN WATER PROOFING

A1 1 M2 PENGECATAN DINDING VINILEX (3X) 34,550.00

A2 1 M2 PENGECATAN PLAFOND DULUX ICI (3X) 42,000.00

A3 1 M2 MELAMIK DAUN JENDELA 24,150.00

A4 1 M2 MELAMIK DAUN PINTU 25,900.00

PEKERJAAN ELEKTRIKAL

A1 1 TTK PAS. TITIK LAMPU/CAHAYA 120,450.00

A2 1 TTK PAS.TITIK DAYA/STOP KONTAK 148,850.00

A3 1 BH PAS. ARMATUR STOP KONTAK 17,300.00

A4 1 BH PAS.ARMATUR SAKLAR ENGSEL 16,300.00

A5 1 BH PAS. ARMATUR SAKLAR SERI (Ganda ) 22,450.00

A6 BOX x PRESTO + 8 grup MCB ex MERLIN GERYN 547,250.00

A7 Lampu Down Ligt exs Philips cool dayligt 20 W TORNADO 64,350.00

A8 Fiting Lampu Bundar exs Artolite B 79923 30,700.00

A9 Lampu Bundar exs Philips cool daylight CIRCLEuntuk dalam ruangan 48,600.00

PEKERJAAN MEKANIKAL/ PLUMBING

A1 1 M 1 PAS.PIPA PVC dia.3 " 34,650.00

A2 1 M 1 PAS.PIPA PVC dia. 3/4" 19,800.00

A3 1 M 1 PAS.PIPA PVC dia. 1/2" 17,800.00

A4 1 UNIT GALIAN SEPTICTANK + SEPTICTANK,exs Bio Tank 1,828,450.00

PEKERJAAN SANITARY

A1 1 UNIT PAS.CLOSET JONGKOK TOTO CE7+PAS.BATA 351,750.00

Page 36: Estimasi Biaya Badru

1 2 3A2 1 UNIT CERMIN 5 mm = 100 cm x75 cm 61,250.00

A3 1 BH PAS.KRAN AIR TOTO 1/2" 34,650.00

PEKERJAAN BETON BERTULANG

A1 1 M3 ANALISA BETON PONDASI (K-175) 2,228,650.00

A2 1 M3 ANALISA BETON SLOOF S1 15/20 (K-175) 5,057,000.00

A3 1 M3 ANALISA BETON KOLOM PRAKTIS (KP) 15/15 6,025,900.00

A4 1 M3 ANALISA BETON BP/RING BALOK 15/20 (K-175) 2,958,500.00

Bandung, 05 Juni 2012 Estimator,

Riezqi Badruzaman & Teguh F

Page 37: Estimasi Biaya Badru

RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : PEMBANGUNAN RUMAH TYPE 38

LOKASI :

NO. JENIS PEKERJAAN VOLUME SAT.

1 2 3 4 5 6 = (3 x 5)I PEKERJAAN PERSIAPAN 1 Pembersihan Lapangan+Pembersihan Akhir 84.00 m2 5,650.00 474,600.00

2 Listrik & Air Kerja 1.00 ls 1,865,000.00 1,865,000.00

2,339,600.00

II PEKERJAAN BOWPLANK, GALIAN DAN URUGAN 1 Bouwplank dan pengukuran 37.00 m1 19,200.00 710,400.00

2 Galian pondasi batu belah 73.80 m3 21,300.00 1,571,940.00

3 Pasir Urug dibawah pondasi bt. Belah Kosongan t=7 cm,perataan dan pemadatan 1.98 m3 131,800.00 260,964.00

4 Urugan Kembali pondasi batu belah dan pemadatan 46.99 m3 10,750.00 505,142.50

3,048,446.50

III PEKERJAAN PASANGAN 1 Pasangan aanstamping 11.71 m3 210,300.00 2,462,613.00

2 Pasangan pondasi batu belah batu 1 PC : 5Psr 21.45 m3 323,850.00 6,946,582.50

3 Pasangan bata merah pres adukan 1:5 162.24 m2 81,840.00 13,277,721.60

4 Pasangan dinding plesteran+acian 328.48 m2 28,750.00 9,443,800.00

32,130,717.10

IV PEKERJAAN BETON1 Kolom praktis 15x15 cm 1.22 m3 6,025,900.00 7,351,598.00

2 Ring Balk beton 15x20 cm 0.96 m3 2,958,500.00 2,840,160.00

3 Sloof beton 15x20 cm 1.78 m3 5,057,000.00 9,001,460.00

19,193,218.00

V PEKERJAAN ATAP & PLAFOND 1 Rangka atap baja ringan zincalume (Trust lokal) 30.10 m2 177,750.00 5,350,275.00 2 PASANGAN ATAP GENTENG ALUMUNIUM TEBAL 0.55 60.20 m2 36,650.00 2,206,330.00

3 Rangka plafond gypsum+ rangka besi holo4x4cm + gypsum jaya board 9mm 39.50 m2 140,850.00 5,563,575.00

13,120,180.00

VI PEKERJAAN KUSEN PINTU DAN JENDELA 1 pek. Kusen pintu jendela KPJ1 + aksesoris 2.00 unit 625,000.00 1,250,000.00

2 Pek. kusen & daun pintu KP1 + aksesori 2.00 unit 484,000.00 968,000.00

3 Pek. kusen & daun pintu KP2 + aksesori 1.00 unit 316,000.00 316,000.00

4 Pek. kusen & jendela KJ1 + aksesori 2.00 unit 570,000.00 1,140,000.00

5 pek. Kusen ventilasi 2.00 unit 82,500.00 165,000.00

3,839,000.00

VII PEK. LANTAI DAN DINDING KERAMIK +ALAT SANITAIR 1 Lantai keramik roman 30x30 kw1 R.teras Vivaldi Garnet 44917 37.10 m2 96,700.00 3,587,570.00

2 Lantai keramik roman 20x20 anti slip kw1 Km/Wc, Troy Bruno 222026 2.40 m2 99,800.00 239,520.00

3 Kramik dinding Km/Wc Roman 20x20 kw .Giada Beige 20761 7.68 m2 99,250.00 762,240.00 4 Closed jongkok TOTO CE7+PAS.BATA 1.00 bh 351,750.00 351,750.00 5 Cermin 5 mm=100 cm/75 cm di Km/Wc 1.00 bh 61,250.00 61,250.00 6 Kran Air dinding TOTO 1.00 bh 34,650.00 34,650.00

5,036,980.0000

VIII PEKERJAAN CAT DINDING-PLAFON-KAYU

1 Cat tembok - Exs VINILEX 121.80 m2 34,550.00 4,208,190.00

2 Cat Plafond Gypsumboard-Warna putih super White Exs VINILEX 39.50 m2 42,000.00 1,659,000.00 6

5,867,190.0000

IX PEKERJAAN SANITASI1 Saluran Air Bersih Pipa PVC1/2 inch Rucika AW Warna Abu 13.40 m1 17,800.00 238,520.00

2 Saluran Air Bersih Pipa PVC3/4 inch Rucika AW Warna Abu 2.000 m1 19,800.00 39,600.00

3 Saluran Air Kotor Pipa PVC 3 Inch Maspion D Warna Abu 10.40 m1 34,650.00 360,360.00

4 Septictank Bio Tank 1.00 unit 1,828,450.00 1,828,450.00

2,466,930.0000

X PEKERJAAN LISTRIK 1 Instalasi Titik Lampu (kabel2x1,5)NYM ETERNA SNI 7.00 bh 120,450.00 843,150.00

2 Instalasi Titik Stop Kontak (kabel 3x1,5)NYM ETERNA SNI 6.00 bh 148,850.00 893,100.00

3 Saklar tunggal 2.00 bh 16,300.00 32,600.00

4 Saklar ganda 3.00 bh 22,450.00 67,350.00

5 Stop kontak Pengaman -Broco seri gracio-4154-55(white) 1.00 bh 17,300.00 17,300.00

6 Box sekering ex presto+8 grup MCB ex multi merlyn Geerin 1.00 bh 547,250.00 547,250.00

2,400,750.0000

Bandung, 05 Juni 2012

Estimator,

Riezqi Badruzaman & Teguh F

HARGA (Rp)

JUMLAH (Rp)

Page 38: Estimasi Biaya Badru

2,500.00

312500 3125000 312500

242000

158000

285000

41,250.00

Page 39: Estimasi Biaya Badru

REKAPITULASI HARGA PENAWARAN

PEKERJAAN : PEMBANGUNAN RUMAH TYPE 38

LOKASI :

NO. URAIAN PEKERJAAN

1 2 3

I PEKERJAAN PERSIAPAN Rp 2,339,600.00

II PEKERJAAN BOWPLANK, GALIAN DAN URUGAN Rp 3,048,446.50

III PEKERJAAN PASANGAN Rp 32,130,717.10

IV PEKERJAAN BETON Rp 19,193,218.00

V PEKERJAAN ATAP & PLAFOND Rp 13,120,180.00

VI PEKERJAAN KUSEN PINTU DAN JENDELA Rp 3,839,000.00

VII PEK. LANTAI DAN DINDING KERAMIK +ALAT SANITAIR Rp 5,036,980.00

VIII PEKERJAAN CAT DINDING-PLAFON-KAYU Rp 5,867,190.00

IX PEKERJAAN SANITASI Rp 2,466,930.00

X PEKERJAAN LISTRIK Rp 2,400,750.00

J U M L A H Rp 89,443,011.60

P E M B U L A T A N Rp 89,443,000.00

PERMETER Rp 2,353,763.16

Bandung, 05 Juni 2012 Estimator,

Riezqi Badruzaman & Teguh F

JUMLAH HARGA (Rp.)

TERBILANG : "Delapan Puluh Sembilan Juta Empat Ratus Empat Puluh Tiga Ribu Rupiah"

Page 40: Estimasi Biaya Badru

JADWAL WAKTU PELAKSANAAN

PEKERJAAN : PEMBANGUNAN RUMAH TIPE 38

LOKASI :

NO URAIAN PEKERJAANMINGGU KE-

I II III IV V VI VII VIII X XI XII XIII

I PEKERJAAN PERSIAPAN 2.62 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22

II PEKERJAAN BOWPLANK, GALIAN DAN URUGAN 3.41 3.41

III PEKERJAAN PASANGAN 35.92 7.18 7.18 7.18 7.18 7.18

IV PEKERJAAN BETON 21.46 5.36 5.36 5.36 5.36

V PEKERJAAN ATAP & PLAFOND 14.67 7.33 7.33 7.33

VI PEKERJAAN KUSEN PINTU DAN JENDELA 4.29 1.43 1.43 1.43

VII PEK. LANTAI DAN DINDING KERAMIK +ALAT SANITAIR 5.63 2.82 2.82

VIII PEKERJAAN CAT DINDING-PLAFON-KAYU 6.56 3.28 3.28

IX PEKERJAAN SANITASI 2.76 1.38 1.38

X PEKERJAAN LISTRIK 2.68 1.34 1.34

AKUMULATIF KEMAJUAN PEKERJAAN 100.00 0.22 3.63 12.77 14.15 14.20 10.18 20.10 7.55 3.03 4.93 5.75 3.50

RENCANA KEMAJUAN PEKERJAAN 0.22 3.84 16.61 30.76 44.96 55.13 75.23 82.79 85.82 90.75 96.50 100.0

REALISASI KEMAJUAN PEKERJAAN `

CEPAT / LAMBAT

Bandung, 05 Juni 2012 Estimator,

Riezqi Badruzaman & Teguh F

BOBOT(%)