TIME SCHEDULE ASIA 1 ENGINEERING
PROYEK : IMPROVEMENT WORK EC PLANT
PEKERJAAN : E P C
LOKASI : PT. FUTAMI FOOD & BEVERAGES
: JL. Mayjen HE Sukma Km. 18, Gg Telkom, Ds Pasir Muncang, Caringin-Bogor 16730
BULAN
NO URAIAN PEKERJAAN BOBOT DURASI TGL 27 28 29 30 31 1 2 3 4 5 6 7 8 9
% Hari HARI 1 2 3 4 5 6 7 8 9 10 11 12 13 14
A PEKERJAAN IMPROVEMENT1 PEKERJAAN PERSIAPAN
1 Pembersihan Area Kerja/ EC Plant 0.31% 1 0.31%
2 Pelepasan/ Perapihan Pipa Existing 0.31% 1 0.31%
3 Pemeriksaan Elevasi Ground Tank No.1 & 2 0.31% 1 0.31%
4 Perapihan dan Pemindahan Existing Carbon Filter 0.22% 1 0.22%
5 Air kerja - (By FUTAMI) 0.12% 14 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%
6 Listrik kerja - (By FUTAMI) 0.20% 14 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%
7 Mobilisasi & Demobilisasi.
(alat kerja : sewa TC 1 unit) 0.72% 2 0.36% 0.36%
8 Administrasi laporan. 1.50% 14 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%
9 Dokumentasi 1.23% 14 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09%
4.92%
2 PEKERJAAN BETON
1 Penambahan Sloope Ground Tank No.1 & 2 (Elevasi) 3.12% 2 1.56% 1.56%
2 Pembuatan Sekat/ Separator by Civil Work 4.32% 5 0.86% 0.86% 0.86% 0.86% 0.86%
3 Pembuatan Dudukan Agitator (GroundTank No.1) 2.10% 2 1.05% 1.05%
9.54%
3 PEKERJAAN PENGADAAN BARANG/ EQUIPMENT
1 - Penggantian/ Perbaikan Diaphragm Pump 19.36% 12 1.61% 1.61% 1.61% 1.61% 1.61% 1.61% 1.61% 1.61% 1.61% 1.61% 1.61% 1.61%Flow Rate adjustable to . . 0-155 gpm (586 lpm)
Port Size
Inlet and Discharge . . . . . . . . . . . . . . 2.0" ANSI,
. . . . . . . . . . . . . . . . . . . . . 150 lb class (DIN 50)
Air Inlet . . . . . . . . . . . . . . . . . . . . . . 0.50" NPT
Air Exhaust . . . . . . . . . . . . . . . . . . . 0.75" NPT
Suction Lift . . . . 20' Dry/25' Wet (6.09m/7.62m)
PTFE . . . . . . . . . 10' Dry/20' Wet (3.05m/6.09m)
Max. Particle Size (Dia.) . . . . . . . 0.25"(6.35mm)
1.1 - Pengadaan Barang Aksesories Diaphragm Pump 3.16% 2 1.58% 1.58%
2 - Penggantian Air Compressor dari 8 Barg ke 12 barg 22.65% 8 2.83% 2.83% 2.83% 2.83% 2.83% 2.83% 2.83% 2.83%Daya / Power : 10 Hp atau 7.5 KW
Voltase: 380 V
Frekuensi :50 Hz
Kecepatan Pengisian Udara : 1043 liter/menit
Tekanan Angin : 12 bar atau 176 Psi
Kecepatan Putaran Mesin : 830 RPM
Kapasitas Tangki : 500 liter
Dimensi : 178 x 70.5 x 128 cm (WxLxH)
Berat : 435 kg
Lain-lain : Diameter Cylinder (mm) x piece : 100x2 / 80x1
2.2 - Pengadaan Barang Aksesories Air Compressor 0.32% 1 0.32%
3 - Pengadaan Material Pipa dan Aksesoris 0.96% 5 0.19% 0.19% 0.19% 0.19% 0.19%
4 - Material Clarifier Tank (2 Unit) 6.23% 2 3.12% 3.12%
5 - Agitator Motor 3.54% 5 0.71% 0.71% 0.71% 0.71% 0.71%
6 - Propeler/ Blade untuk Agitator 0.36% 3 0.12% 0.12% 0.12%
7 - Bushbar Cable_ 16 mm_with Vinyle Identification 0.34% 2 0.17% 0.17%
8 - Alumunium Plate_3 mm Low Resistance Spec 23.16% 7 3.31% 3.31% 3.31% 3.31% 3.31% 3.31% 3.31%
80.08%
4 PEKERJAAN MODIFIKASI & FABRIKASI
1 PIPA :
- Mockup/ Modifikasi Piping System (Raw Water, Sludge, Clean Water) 0.68% 5 0.14% 0.14% 0.14% 0.14% 0.14%
1.1 1. Raw Water / Reaktor Inlet
1.2 2. Sludge/ Blow Down System
1.3 3. Cleane Water
2 TANK :
2.1 - Fabrikasi Clarifier Tank (2 Unit) Cap_7,9 M 1.36% 4 0.34% 0.34% 0.34% 0.34%
2.2 - Modifikasi Existing Sand Filter menjadi Carbon Filter (Pressurized System) 2.69% 3 0.90% 0.90% 0.90%
4.73%
5 PEKERJAAN FINISHING
1 - Painting/ Pengecatan 0.60% 3 0.20% 0.20% 0.20%
2 - Testing Commissioning 0.13% 1 0.13%
0.73%
100.00%
Harian 3.34% 2.19% 3.73% 8.33% 10.89% 12.79% 12.31% 11.82% 10.70% 8.80% 9.00% 5.34% 0.42% 0.35%Komulatif 3.34% 5.53% 9.26% 17.60% 28.49% 41.28% 53.58% 65.40% 76.10% 84.90% 93.89% 99.23% 99.65% 100.00%
Mingguan 28.49% 56.41% 15.10%
Komulatif 28.49% 84.90% 100.00%
J U M L A H
Okt- 14 Nov - 14 T B A