    PEKERJAAN :

    LOKASI : DESA SIMPANG III KEC.MANYAK PAYED

    KAB/KOTA : ACEH TAMIANG

    I PEKERJAAN PERSIAPAN

    1 Pek. Papan Nama Kegiatan Taksir 1,000 Ls 300.000,00 300.000,00

    2 Pengukuran Lapangan Taksir 1,000 Ls 1.300.000,00 1.300.000,00

    1.600.000,00

    II PEKERJAAN BETON BERTULANG

    1 Pek.Peninggian Kolom 30 x 30 Cm 6,804 M3

    a. Beton K200 A. 4.1.1.6 6,804 M3 1.027.372,69 6.990.243,79

    b. Pembesian A. 4.1.1.17 1.165,253 Kg 15.269,59 17.792.936,17

    c. Bekisting A. 4.1.1.22 22,657 M2 296.181,75 6.710.684,69

    2 Pek.Peninggian Kolom Dia.80 Cm 5,429 M3

    a. Beton K200 A. 4.1.1.6 5,429 M3 1.027.372,69 5.577.770,72

    b. Pembesian A. 4.1.1.17 228,893 Kg 15.269,59 3.495.108,15

    c. Bekisting A. 4.1.1.22 6,786 M2 296.181,75 2.010.022,64

    3 Pek.Balok Beton 20 x 30 Cm 7,008 M3

    a. Beton K175 A. 4.1.1.5 7,008 M3 990.946,14 6.944.550,57

    b. Pembesian A. 4.1.1.17 1.554,585 Kg 15.269,59 23.737.870,07

    c. Bekisting A. 4.1.1.23 21,024 M2 305.406,75 6.420.871,51

    4 Pek.Balok Beton 40 x 60 Cm 17,376 M3

    a. Beton K200 A. 4.1.1.6 17,376 M3 1.027.372,69 17.851.627,87

    b. Pembesian A. 4.1.1.17 2.610,049 Kg 15.269,59 39.854.377,50

    c. Bekisting A. 4.1.1.23 52,128 M2 305.406,75 15.920.243,06

    5 Pek.Plat Dinding Beton 28,901 M3

    a. Beton K200 A. 4.1.1.6 28,901 M3 1.027.372,69 29.692.247,10

    b. Pembesian A. 4.1.1.17 4.551,930 Kg 15.269,59 69.506.109,96

    c. Bekisting A. 4.1.1.24 202,308 M2 431.481,75 87.292.216,35

    339.796.880,14

    III PEKERJAAN PASANGAN DAN PLESTERAN

    1 Pek. Pasangan Batu Bata 1 : 4 A. 4.4.1.9 64,440 M2 99.747,99 6.427.760,28

    2 Pek. Plesteran Batu Bata 1 : 4 A. 4.4.2.4 208,880 M2 56.303,02 11.760.573,98

    3 Pek. Pemasangan Kaca Motif 5 mm Taksir 21,843 M2 248.185,58 5.421.067,93

    23.609.402,19

    RENCANA ANGGARAN BIAYA (RAB)

    No Uraian Pekerjaan Analisa Volume

    DINAS CIPTA KARYA

    Jalan Pemancar No.5 Simpang Tiga

    Telp.(0641) Fax.(0651) 42882,Banda Aceh 23239

    PEMB.SARANA DAN PRASARANA MESJID BABUL TAQWA DESA SIMPANG III

    KEC.MANYAK PAYED KAB.ACEH TAMIANG (OA) PEMERINTAH ACEH

    Jumlah Harga (Rp)

    SUB JUMLAH PEKERJAAN PERSIAPAN

    Satuan Harga Satuan (Rp)

    SUB JUMLAH PEKERJAAN BETON BERTULANG

    SUB JUMLAH PEKERJAAN PASANGAN DAN PLESTERAN