NISBAH KUPAS COG – BECOG - ICOG
DEFINISI – RUMUS - APLIKASI
![Page 2: mpd tugas](https://reader033.vdokumen.com/reader033/viewer/2022051517/5695d4eb1a28ab9b02a34fcd/html5/thumbnails/2.jpg)
CUTOFF GRADE , CUT-OFF GRADE (KADAR BATAS) STRIPPING RATIO (NISBAH KUPAS) KADAR EKIVALEN BREAK EVEN CUTOFF GRADE (BECOG) INTERNAL CUTOFF GRADE (ICOG)
![Page 3: mpd tugas](https://reader033.vdokumen.com/reader033/viewer/2022051517/5695d4eb1a28ab9b02a34fcd/html5/thumbnails/3.jpg)
CUTOFF GRADE
1. KADAR RATA-RATA TERENDAH
YANG MASIH BISA DITAMBANG BERDSRK KONDISI EKONOMI DAN TEKNOLOGI SAAT ITU
2. KADAR TERENDAH
YANG MASIH BISA DITAMBANG BERDSRK KONDISI EKONOMI DAN TEKNOLOGI SAAT ITU
![Page 4: mpd tugas](https://reader033.vdokumen.com/reader033/viewer/2022051517/5695d4eb1a28ab9b02a34fcd/html5/thumbnails/4.jpg)
STRIPPING RATIO - SR (NISBAH KUPAS)
SR = NISBAH ANTARA JUMLAH MATERIAL PENUTUP DAN JUMLAH MATERIAL BIJIH
SR FUNGSI KADAR BATAS (COG)
TAMBANG BIJIH:
SR = TON WASTE PER TON ORE
SR = BCM WASTE PER TON ORE
SR = (TON TOTAL/TON ORE)-1
TAMBANG BATUBARA:
BCM OVERBURDEN PER TON COAL
MISAL SR 8:1 tidak 1:8!!!
![Page 5: mpd tugas](https://reader033.vdokumen.com/reader033/viewer/2022051517/5695d4eb1a28ab9b02a34fcd/html5/thumbnails/5.jpg)
STRIP RATIO
![Page 6: mpd tugas](https://reader033.vdokumen.com/reader033/viewer/2022051517/5695d4eb1a28ab9b02a34fcd/html5/thumbnails/6.jpg)
NORTH-SOUTH SECTION
Original Topography
2005 Surface
Ultimate Pit Surface
-540mLR
-90mLR
Phase 4
Phase 5
Phase 6
Ultimate Pit
NORTH-SOUTH SECTION
-180mLR
-300mLR
-390mLR
-540mLR
APAKAH HUBUNGAN ANTARA KADAR BATAS (COG) – HARGA KOMODITI – SR - CADANGAN
![Page 7: mpd tugas](https://reader033.vdokumen.com/reader033/viewer/2022051517/5695d4eb1a28ab9b02a34fcd/html5/thumbnails/7.jpg)
BENTUK PIT – STRI P RATIO
RL-90
EAST DUMP
RL245
TONGOLOKA
NEWTS
KATALA
2005
![Page 8: mpd tugas](https://reader033.vdokumen.com/reader033/viewer/2022051517/5695d4eb1a28ab9b02a34fcd/html5/thumbnails/8.jpg)
BREAK EVEN STRIPPING RATIO
NISBAH KUPAS PULANG POKOK
APABILA KADAR BIJIH DIKETAHUI
SEMUA KEUNTUNGAN BERSIH DIPAKAI UNTUK MENGUPAS MATERIAL PENUTUP
BERAPAKAH JUMLAH MATERIAL PENUTUP DAPAT DIKUPAS?
![Page 9: mpd tugas](https://reader033.vdokumen.com/reader033/viewer/2022051517/5695d4eb1a28ab9b02a34fcd/html5/thumbnails/9.jpg)
BESR
BESR = (PENDAPATAN-ONGKOS TAMBANG&OLAH) PER TON BIJIH DIBAGI (ONGKOS KUPAS) PER TON WASTE
NILAI BESR = 0 PADA TITIK BECOG
REVENUE TIDAK DAPAT MENDUKUNG STRIPPING
![Page 10: mpd tugas](https://reader033.vdokumen.com/reader033/viewer/2022051517/5695d4eb1a28ab9b02a34fcd/html5/thumbnails/10.jpg)
BESR VS SR
Phase 4
Phase 5
Phase 6
Ultimate Pit
NORTH-SOUTH SECTION
-180mLR
-300mLR
-390mLR
-540mLR
![Page 11: mpd tugas](https://reader033.vdokumen.com/reader033/viewer/2022051517/5695d4eb1a28ab9b02a34fcd/html5/thumbnails/11.jpg)
BREAK EVEN CUTOFF GRADE
BERAPA “KADAR BIJIH” YANG MENGHASILKAN ANGKA YANG SAMA ANTARA PENDAPATAN DAN BIAYA UNTUK MENAMBANG DAN MEMPROSES
PENDAPATAN = BIAYA (TITIK PULANG POKOK)
DISEBUT KADAR BATAS PULANG POKOK (BECOG)
BECOG = ONGKOS (MINE+MILL+G&A) / (HARGA JUAL-SRF)(MILL REC)(SMELREC)(FAC)
![Page 12: mpd tugas](https://reader033.vdokumen.com/reader033/viewer/2022051517/5695d4eb1a28ab9b02a34fcd/html5/thumbnails/12.jpg)
INTERNAL CUTOFF GRADE (ICOG)
RUMUS SAMA DENGAN BECOG TETAPI ONGKOS PENAMBANGAN (MINE) = 0
FAKTOR KOREKSI
% ke POUND (LB) = 20
UNTUK SATUAN METRIK, FAKTOR = 22.046
LOGAM MULIA (Au) TIDAK DIPERLUKAN FAKTOR: oz/ton, g/t
![Page 13: mpd tugas](https://reader033.vdokumen.com/reader033/viewer/2022051517/5695d4eb1a28ab9b02a34fcd/html5/thumbnails/13.jpg)
PENGHASILAN = BIAYA (TITIK PULANG POKOK UNTUK 1 TON BIJIH) HARGA x KADAR x MILL REC x SMELT REC x 20 =
ONGKOS (MINE+MILL+G&A)+SRF x KADAR x MILL REC x SMELT REC x 20
(HARGA-SRF) x KADAR x MILL REC x SMELT REC x 20 =
ONGKOS (MINE+MILL+G&A)
BECOG = ONGKOS (MINE+MILL+G&A) (HARGA-SRF) x MILL REC x SMELT REC X 20
PERHITUNGAN KADAR BATAS Cu
![Page 14: mpd tugas](https://reader033.vdokumen.com/reader033/viewer/2022051517/5695d4eb1a28ab9b02a34fcd/html5/thumbnails/14.jpg)
PERHITUNGAN KADAR BATAS Cu
ONGKOS PENAMBANGAN PER TON MATERIAL $0.750
ONGKOS PENGOLAHAN PER TON BIJIH $3.250
ONGKOS G&A PER TON BIJIH $0.250
PEROLEHAN PABRIK 94%
SMELTING REFINING FREIGHT PER lb PRODUK $0.275
PEROLEHAN SMELTER 96.15%
HARGA TEMBAGA PER lb (POUND) $0.950
BECOG = ONGKOS (MINE+MILL+G&A) (HARGA-SRF) x MILL REC x SMELT REC x 20
BECOG = $0.750 + $3.250 + $0.250 ($0.95-$0.275) x 0.94 x 0.9615 x 20
BECOG= 0.35% TUGAS HITUNGLAH ICOG!
![Page 15: mpd tugas](https://reader033.vdokumen.com/reader033/viewer/2022051517/5695d4eb1a28ab9b02a34fcd/html5/thumbnails/15.jpg)
TUGAS CUTOFF CALCULATION
COSTS: mining : $1.00/ton materl processing : $4.00/ton ore G$A : $0.75/ton ore Refining & Freight : $5.00/oz REVENUE: commodity price : $ 425/oz recovery : 75% HITUNGLAH: 1. BECOG 2. ICOG! Untuk apa diperlukan ICOG
![Page 16: mpd tugas](https://reader033.vdokumen.com/reader033/viewer/2022051517/5695d4eb1a28ab9b02a34fcd/html5/thumbnails/16.jpg)
KADAR EKIVALEN
DALAM CEBAKAN BIJIH TERDAPAT LEBIH DARI SATU MINERAL
ADA MINERAL UTAMA DAN IKUTAN
DALAM KADAR EKIVALEN :
ADA ISTILAH NSR DAN SRF
NSR = NET SMELTER RETURN
ADALAH NILAI KOTOR DARI SATU TON BIJIH SETELAH DIKURANGI ONGKOS-ONGKOS SRF
SRF =SMELTING – REFIN ING - FREIGHT
![Page 17: mpd tugas](https://reader033.vdokumen.com/reader033/viewer/2022051517/5695d4eb1a28ab9b02a34fcd/html5/thumbnails/17.jpg)
TAHAPAN PERHITUNGAN KADAR EKIVALEN MISAL Cu EKIVALEN (CuEq)
1. HITUNG NSR 1 TON mineral utama (TEMBAGA) DG KADAR BIJIH 1%
2. HITUNG NSR 1 TON MINERAL IKUTAN
MISAL: MOLY DG KADAR 1% atau
EMAS DG KADAR 1 oz/ton ATAU 1 g/t
3. HITUNG FAKTOR EKIVALENSI =
NISBAH NSR MINERAL IKUTAN DAN MINERAL UTAMA
4. KADAR EKIVALEN = TOTAL Cu + FAKTOR x MOLY
5. BILA DALAM BLOK DIKETAHUI KADAR TOTAL Cu DAN KADAR MOLY (EMAS, PERAK) MAKA KADAR CuEq DARI BLOK TERSEBUT DAPAT DIHITUNG
KADAR EKIVALEN = KADAR YG MENGHASILKAN GABUNGAN NILAI NSR DARI SEMUA MINERAL YANG ADA
![Page 18: mpd tugas](https://reader033.vdokumen.com/reader033/viewer/2022051517/5695d4eb1a28ab9b02a34fcd/html5/thumbnails/18.jpg)
PERHITUNGAN KADAR EKIVALEN
APABILA DIKETAHUI:
TEMBAGA MOLY
HARGA KOMODITAS $ 0.900 $ 3.000
PEROLEHAN PABRIK 88% 70%
PEROLEHAN SMELTER
(KONVERTER) 96.1% 99%
BIAYA SMELTING
KONVERSI KE POUND $ 0.324 $ 0.810
(LB)
![Page 19: mpd tugas](https://reader033.vdokumen.com/reader033/viewer/2022051517/5695d4eb1a28ab9b02a34fcd/html5/thumbnails/19.jpg)
PROSEDUR PERHITUNGAN
1. HITUNG NSR 1 TON BIJIH DGN KADAR 1%Cu:
($0.90/lb-$0.324/lb)(1%)(0.88)(0.961)(20lb/%) = $ 9.74
2. HITUNG NSR 1 TON BIJIH DGN KADAR 1% MOLY
($3.0/lb-$0.81/lb)(1%)(0.70)(0.99)(20lb/%) = $30.35
3. FAKTOR EKIVALEN = NSR MOLY/NSR TEMBAGA
$30.35 / $9.74 = 3.1160
4. TEMBAGA EKIVALEN = KADAR Cu + (3.1160 x KADAR MOLY)
DALAM MODEL BLOK SERING MEMAKAI NILAI NSR drpd KADAR EKIVALEN
PEROLEHAN MILL DAN SMELTER, ONGKOS: SRF, HARGA KOMODITAS SUDAH DIPERHITUNGKAN DALAM NSR