KEMENTERIAN PENDIDIKAN DAN KEBUDAYAAN UNIVERSITAS LAMBUNG MANGKURAT
FAKULTAS TEKNIK PROGRAM STUDI TEKNIK SIPIL NON REGULER
Jalan Brigjen H. Hasan Basri Banjarmasin – Kalimantan Selatan 70123 Telepon (0511) 3304503 Faximili (0511) 3304503
TUGAS
MATA KULIAH/KODE : METODE PELAKSANAAN KONSTRUKSI / (HSKB-627)
DOSEN PENGASUH : Ir. ZAIN HERNADY ARIFIN
HARI/TANGGAL/WAKTU : JUM’AT/17 MEI 2013
1 PADA PELAKSANAAN PEKERJAAN PEMBUATAN SALURAN PRIMER UNTUK IRIGASI ,
SEPANJANG 2 KM, DENGAN BENTUK SALURAN TRAPEZIUM DENGAN LEBAR BAGIAN DASAR
ADALAH 3,00 METER, DAN KEMIRINGAN SALURAN 1 : 1, SERTA TINGGI SALURAN 1,50 M.
DENGAN JENIS TANAH PADA UMUMNYA ADALAH TANAH BERCAMPUR KERIKIL.
UNTUK PEKERJAAN TERSEBUT, KONTRAKTOR PELAKSANA DIHADAPKAN PADA PILIHAN ALAT
BERAT KARENA KETERBATASAN WAKTU YANG DISEDIAKAN, YAKNI ADA 2 Unit EXCAVATOR
TYPE S DENGAN BC = 0.8 M3, DAN 1 Unit WHEEL LOADER Type M DENGAN BC = 2,4 M3.
MATERIAL HASIL GALIAN DIANGKUT UNTUK DIBAWA KETEMPAT PEMBUANGAN DENGAN
JARAK ± 4 KM, DARI LOKASI PENGGALIAN DENGAN DT KAPASITAS 8,0 M3
JIKA SAUDARA SEBAGAI PELAKSANA PEKERJAAN TERSEBUT, JENIS ALAT YANG MANA YANG
AKAN SAUDARA GUNAKAN, BERAPA WAKTU YANG PERLUKAN UNTUK PENYELESAIAN
PEKERJAAN TERSEBUT, SEBUTKAN ALASAN PEMILIHAN ALAT.
KEMENTERIAN PENDIDIKAN DAN KEBUDAYAAN UNIVERSITAS LAMBUNG MANGKURAT
FAKULTAS TEKNIK Jalan Brigjen H. Hasan Basri Banjarmasin – Kalimantan Selatan 70123
Telepon (0511) 3304503 Faximili (0511) 3304503
PT.ANZ BANKGEDUNG ANZ SQUARE Lt.6
THAMRIN NINE DEVELOPMENT JLN. MH. THAMRIN KAV. 9 – 10
JAKARTA PUSAT (10230)Up. Alam/Andhika