A PEKERJAAN PERSIAPAN
I PEKERJAAN PERSIAPAN Rp.
Rp.
B PEKERJAAN STRUKTUR NON STANDAR
I PEKERJAAN PONDASI PANCANG Rp.
Rp.
C PEKERJAAN STRUKTUR STANDAR
I PEKERJAAN TANAH Rp.
II PEKERJAAN STRUKTUR BAWAH Rp.
III PEKERJAAN STRUKTUR ATAS
III.1 LANTAI SATU Rp.
III.2 LANTAI DUA Rp.
III.3 LANTAI TIGA Rp.
III.4 LANTAI DAK Rp.III.5 KUDA KUDA BAJA Rp.
Rp.
D PEKERJAAN ARSITEKTUR
I PEKERJAAN LANTAI 1 Rp.
II PEKERJAAN LANTAI 2 Rp.
III PEKERJAAN LANTAI 3 Rp.
IV PEKERJAAN LANTAI DAK Rp.
Rp.
E PEKERJAAN MEKANIKAL & ELEKTRIKAL
I DIVISI A.0. PEKERJAAN MEKANIKAL Rp.
II DIVISI B.0. PEKERJAAN ELEKTRIKAL Rp.
Rp.
F PEKERJAAN SITE DEVELOPMENT
I PEKERJAAN BANGUNAN PENUNJANG Rp.
II PEKERJAAN JALAN DAN TAMAN Rp.
Rp.
Rp.
PPN 10% Rp.
JUMLAH + PPN Rp.
DIBULATKAN Rp.
Bandung,2015
, 2016
Penawar
.
JUMLAH B
REKAPITULASI
Terbilang :
JUMLAH
JUMLAH A
JUMLAH C
PEKERJAAN PEMBANGUNAN GEDUNG KANTOR BALAI PSDA Ws. CITARUM
JL. SMK 6 - SOEKARNO HATTA - KOTA BANDUNG
TAHUN 2016
NO URAIAN PEKERJAAN JUMLAH
JUMLAH D
JUMLAH E
JUMLAH F
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
2/58
Harga Satuan Jumlah Harga
(Rp.) (Rp.)
1 3 4 5 6
A PEKERJAAN PERSIAPAN
I PEKERJAAN PERSIAPAN
1.1 Papan nama proyek unit 1.00
1.2 Pekerjaan pengukuran dan pasang bouwplank m' 136.85
1.3 Pek. test bahan & material ls 1.00
1.4 Penyediaan Listrik dan air kerja selama pelaksanaan bln 6.00
1.5 Dokumentasi, administrasi, shop drawing & asbuilt. ls 1.00
1.6 Pekerjaan kantor direksi m 36.00
1.7 Los kerja dan gudang m 16.00
1.8 Pagar sementara dari seng gelombang tinggi 1,8 m m 171.50
1.9 Asuransi (Astek, Car & TPL) ls 1.00
1.10 Pek. Perijinan ls 1.00
1.11 Pekerjaan anti rayap (termite control) m 727.75
Jumlah A -
2
0
PEKERJAAN PEMBANGUNAN GEDUNG KANTOR BALAI PSDA Ws. CITARUM
JL. SMK 6 - SOEKARNO HATTA - KOTA BANDUNG
TAHUN 2016
No. Uraian Pekerjaan Satuan Volume
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
3/58
PEKERJAAN STRUKTUR
NO SAT VOL HARGA SAT JUMLAH
B. PEKERJAAN NON STANDAR
PEKERJAAN PONDASI
PEKERJAAN PONDASI PANCANG
1 Pemancangan Tiang Pancang uk. 25 x 25 cm Hydrolic m 1,800.00- termasuk biaya handling dan sambungan
2 Pengadaan Tiang Pancang uk. 25 x 25 cm m 1,800.00
3 Mobilisasi dan demobilisasi alat pancang Hydrolic ls 1.00
4 Pek. Bobokan Tiang Pancang titik 120.00
5 Test PDA titik 3.00
JUMLAH PEKERJAAN PONDASI
C. PEKERJAAN STANDAR (Kontrak Lumpsum)
I PEKERJAAN TANAH
1 Galian Tanah Pile Cap m3 107.87
2 Urugan Kembali Bekas Galian m3 107.87
3 Pek. Urugan Tanah Dari Luar Peninggian peil Bangunan (h = 60 cm) m3 627.00
4 Pek. Pemadatan m2 1,045.00
JUMLAH PEKERJAAN TANAH
II PEKERJAAN STRUKTUR BAWAH
1 Pekerjaan Pile cap P5
Beton K - 300 m3 25.99
Besi D16-160 (1.578 Kg/m) kg 1,312.78
Besi D13-180 (1.042 Kg/m) kg 775.35
Besi peminggang 1 D13 (1.042 Kg/m) kg 62.50
Bekisting pas. Bata 1: 5 m2 54.72
Lantai Kerja 5 cm m3 2.17
Urugan pasir 10 cm m3 4.33
2 Pekerjaan Pile cap P4
Beton K - 300 m3 14.85
Besi D16-160 (1.578 Kg/m) kg 823.70
Besi D13-180 (1.042 Kg/m) kg 487.68
Besi peminggang 1 D13 (1.042 Kg/m) kg 48.13
Bekisting pas. Bata 1: 5 m2 39.60
Lantai Kerja 5 cm m3 1.24
Urugan pasir 10 cm m3 2.48
3 Pekerjaan Pile cap P3
Beton K - 300 m3 3.65
Besi D16-160 (1.578 Kg/m) kg 202.55
Besi D13-180 (1.042 Kg/m) kg 119.92
Besi peminggang 1 D13 (1.042 Kg/m) kg 11.83
Bekisting pas. Bata 1: 5 m2 9.74
Lantai Kerja 5 cm m3 0.30
Urugan pasir 10 cm m3 0.61
4 Pekerjaan Pile cap P2
Beton K - 300 m3 0.90
Besi D16-160 (1.578 Kg/m) kg 91.18
Besi D13-180 (1.042 Kg/m) kg 54.18Besi peminggang 1 D13 (1.042 Kg/m) kg 8.33
Bekisting pas. Bata 1: 5 m2 7.20
Lantai Kerja 5 cm m3 0.08
Urugan pasir 10 cm m3 0.15
0
PEKERJAAN PEMBANGUNAN GEDUNG KANTOR
BALAI PSDA WS. CITARUM
JL. SOEKARNO HATTA NO. BANDUNG
URAIAN PEKERJAAN
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
4/58
NO SAT VOL HARGA SAT JUMLAHURAIAN PEKERJAAN
5 Pek. Tie Beam Type TB.1 (30/60)
Beton K - 300 m3 40.23
Besi D16 (1.578 Kg/m) kg 3,214.86
Besi peminggang 2 10 (0.617 Kg/m) kg 289.09
sengkang 10 - 150/100 (0.617 Kg/m) kg 1,874.42
Bekisting pas. Bata 1: 5 m2 268.20
Lantai Kerja 5 cm m3 3.35
Urugan pasir 10 cm m3 4.73
6 Pek. Tie Beam Type TB.2 (25/50)
Beton K - 300 m3 10.49Besi D16 (1.578 Kg/m) kg 938.73
sengkang 10 - 150/100 (0.617 Kg/m) kg 579.33
Bekisting pas. Bata 1: 5 m2 83.88
Lantai Kerja 5 cm m3 1.05
Urugan pasir 10 cm m3 2.10
7 Pek. Tie Beam Type TB.2A (25/50)
Beton K - 300 m3 0.32
Besi D16 (1.578 Kg/m) kg 33.35
sengkang 10 - 150/100 (0.617 Kg/m) kg 17.61
Bekisting pas. Bata 1: 5 m2 2.55
Lantai Kerja 5 cm m3 0.03
Urugan pasir 10 cm m3 0.06
8 Pek. Plat Lantai Dasar (t=140 mm)
Beton K - 300 m3 65.49
Wiremesh M-8 (1 layer) (5,25 Kg/m2) Kg 2,934.70
Lantai Kerja 5 cm m3 23.39
Urugan pasir 10 cm m3 46.78
JUMLAH PEKERJAAN STRUKTUR BAWAH -
III PEKERJAAN STRUKTUR ATAS
III.1 LANTAI SATU
1 Pek. Kolom K.1 (40/40)
Beton K - 300 m3 19.97
Besi 8 D16 (1.578 Kg/m) kg 2,035.28
sengkang 10 - 150/100 (0.617 Kg/m) kg 1,046.66
Bekisting kolom multipleks 9mm m2 199.68
2 Pek. Kolom K.2 ( 50)
Beton K - 300 m3 2.829
Besi 8 D16 (1.578 Kg/m) kg 293.550
sengkang 10 - 150/100 (0.617 Kg/m) kg 121.918
Bekisting kolom multipleks 9mm m2 22.629
3 Pek. Kolom KT (20/20)
Beton K - 300 m3 0.168
Besi 4 D16 (1.578 Kg/m) kg 31.560
sengkang 10 - 150/100 (0.617 Kg/m) kg 14.512
Bekisting kolom multipleks 9mm m2 3.360
4 Pek. Balok Tangga BT (20/30)
Beton K - 300 m3 0.36
Besi D16 (1.578 Kg/m) kg 42.92
sengkang 10 - 150/100 (0.617 Kg/m) kg 26.65
Bekisting balok multipleks 9mm m2 3.960
5 Pek. Tangga beton
Beton K - 300 m3 11.31
Wiremesh M-8 (2 layer) (5,25 Kg/m2) kg 102.85Bekisting tangga multipleks 9mm m2 36.44
JUMLAH -
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
5/58
NO SAT VOL HARGA SAT JUMLAHURAIAN PEKERJAAN
III.2 LANTAI DUA
1 Pek. Kolom K.1 (40/40)
Beton K - 300 m3 17.47
Besi 8 D16 (1.578 Kg/m) kg 1,626.91
sengkang 10 - 150/100 (0.617 Kg/m) kg 808.08
Bekisting kolom multipleks 9mm m2 174.72
2 Pek. Kolom K.2 ( 50)
Beton K - 300 m3 2.475
Besi 8 D16 (1.578 Kg/m) kg 234.650
sengkang 10 - 150/100 (0.617 Kg/m) kg 94.128Bekisting kolom multipleks 9mm m2 19.800
3 Pek. Balok Type B.1 (30/60)
Beton K - 300 m3 41.31
Besi D16 (1.578 Kg/m) kg 3,505.72
Besi peminggang 2 10 (0.617 Kg/m) kg 317.09
sengkang 10 - 150/100 (0.617 Kg/m) kg 2,075.70
Bekisting balok multipleks 9mm m2 275.40
4 Pek. Balok Type B.1A (30/60)
Beton K - 300 m3 2.84
Besi D16 (1.578 Kg/m) kg 543.02
Besi peminggang 2 10 (0.617 Kg/m) kg 39.65
sengkang 10 - 150/100 (0.617 Kg/m) kg 162.28
Bekisting balok multipleks 9mm m2 18.90
5 Pek. Balok Type B.2 (25/50)
Beton K - 300 m3 11.39
Besi D16 (1.578 Kg/m) kg 1,148.04
sengkang 10 - 150/100 (0.617 Kg/m) kg 629.10
Bekisting balok multipleks 9mm m2 91.09
6 Pek. Balok Type B.2A (25/50)
Beton K - 300 m3 0.28
Besi D16 (1.578 Kg/m) kg 91.83
sengkang 10 - 150/100 (0.617 Kg/m) kg 15.19
Bekisting balok multipleks 9mm m2 2.20
7 Pek. Balok Type B.3 (20/40)
Beton K - 300 m3 3.03
Besi D16 (1.578 Kg/m) kg 304.63
sengkang 10 - 150/100 (0.617 Kg/m) kg 205.45
Bekisting balok multipleks 9mm m2 30.29
8 Pek. Pelat Lantai (14 CM)
Beton K - 300 m3 71.43
Wiremesh M-8 (2 layer) (5,25 Kg/m2) kg 6,897.65
Bekisting plat multipleks 9mm m2 510.21
9 Pek. Kolom KT (20/20)
Beton K - 300 m3 0.168
Besi 4 D16 (1.578 Kg/m) kg 31.560
sengkang 10 - 150/100 (0.617 Kg/m) kg 14.512
Bekisting kolom multipleks 9mm m2 3.360
10 Pek. Balok Tangga BT (20/30)
Beton K - 300 m3 0.36
Besi D16 (1.578 Kg/m) kg 42.92
sengkang 10 - 150/100 (0.617 Kg/m) kg 26.65
Bekisting balok multipleks 9mm m2 3.960
11 Pek. Tangga beton
Beton K - 300 m3 11.31Wiremesh M-8 (2 layer) (5,25 Kg/m2) kg 102.85
Bekisting tangga multipleks 9mm m2 36.44
JUMLAH -
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
6/58
NO SAT VOL HARGA SAT JUMLAHURAIAN PEKERJAAN
III.3 LANTAI TIGA
1 Pek. Kolom K.1 (40/40)
Beton K - 300 m3 8.06
Besi 8 D16 (1.578 Kg/m) kg 750.88
sengkang 10 - 150/100 (0.617 Kg/m) kg 372.96
Bekisting kolom multipleks 9mm m2 80.64
2 Pek. Kolom K.2 ( 50)
Beton K - 300 m3 2.475
Besi 8 D16 (1.578 Kg/m) kg 234.650
sengkang 10 - 150/100 (0.617 Kg/m) kg 94.128Bekisting kolom multipleks 9mm m2 19.800
3 Pek. Balok Type B.1 (30/60)
Beton K - 300 m3 41.31
Besi D16 (1.578 Kg/m) kg 3,505.72
Besi peminggang 2 10 (0.617 Kg/m) kg 317.09
sengkang 10 - 150/100 (0.617 Kg/m) kg 2,075.70
Bekisting balok multipleks 9mm m2 275.40
4 Pek. Balok Type B.1A (30/60)
Beton K - 300 m3 2.84
Besi D16 (1.578 Kg/m) kg 543.02
Besi peminggang 2 10 (0.617 Kg/m) kg 39.65
sengkang 10 - 150/100 (0.617 Kg/m) kg 162.28
Bekisting balok multipleks 9mm m2 18.90
5 Pek. Balok Type B.2 (25/50)
Beton K - 300 m3 11.39
Besi D16 (1.578 Kg/m) kg 1,148.04
sengkang 10 - 150/100 (0.617 Kg/m) kg 629.10
Bekisting balok multipleks 9mm m2 91.09
6 Pek. Balok Type B.2A (25/50)
Beton K - 300 m3 0.28
Besi D16 (1.578 Kg/m) kg 91.83
sengkang 10 - 150/100 (0.617 Kg/m) kg 15.19
Bekisting balok multipleks 9mm m2 2.20
7 Pek. Balok Type B.3 (20/40)
Beton K - 300 m3 3.03
Besi D16 (1.578 Kg/m) kg 304.63
sengkang 10 - 150/100 (0.617 Kg/m) kg 205.45
Bekisting balok multipleks 9mm m2 30.29
8 Pek. Pelat Lantai (14 CM)
Beton K - 300 m3 53.09
Wiremesh M-8 (2 layer) (5,25 Kg/m2) kg 5,126.47
Bekisting plat multipleks 9mm m2 379.19
9 Pek. Pelat Lantai (20 CM)
Beton K - 300 m3 26.20
Wiremesh M-8 (2 layer) (5,25 Kg/m2) kg 1,771.18
Bekisting plat multipleks 9mm m2 131.01
JUMLAH -
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
7/58
NO SAT VOL HARGA SAT JUMLAHURAIAN PEKERJAAN
III.4 LANTAI DAK
1 Pek. Balok Type B.1 (30/60)
Beton K - 300 m3 13.50
Besi D16 (1.578 Kg/m) kg 1,145.66
Besi peminggang 2 10 (0.617 Kg/m) kg 103.62
sengkang 10 - 150/100 (0.617 Kg/m) kg 678.33
Bekisting balok multipleks 9mm m2 90.00
2 Pek. Balok Type B.1A (30/60)
Beton K - 300 m3 2.84
Besi D16 (1.578 Kg/m) kg 543.02Besi peminggang 2 10 (0.617 Kg/m) kg 39.65
sengkang 10 - 150/100 (0.617 Kg/m) kg 162.28
Bekisting balok multipleks 9mm m2 18.90
3 Pek. Balok Type B.2 (25/50)
Beton K - 300 m3 4.26
Besi D16 (1.578 Kg/m) kg 449.47
sengkang 10 - 150/100 (0.617 Kg/m) kg 235.42
Bekisting balok multipleks 9mm m2 34.09
4 Pek. Balok Type B.3 (20/40)
Beton K - 300 m3 3.27
Besi D16 (1.578 Kg/m) kg 279.36
sengkang 10 - 150/100 (0.617 Kg/m) kg 190.75
Bekisting balok multipleks 9mm m2 32.68
5 Pek. Pelat Dak (14 CM)
Beton K - 300 m3 19.88
Wiremesh M-8 (2 layer) (5,25 Kg/m2) kg 1,958.22
Bekisting plat multipleks 9mm m2 142.24
JUMLAH -
III.5 KUDA KUDA BAJA
1 Pek. Kuda kuda Baja
Kuda kuda WF 300.150.6,5.9 (36,7 kg/m) kg 711.980
Kuda kuda WF 250.125.6.9 (29,6 kg/m) kg 1,659.97
Pengkaku WF 200.100.5,5.8 (21,3 kg/m) kg 319.50
Gording lip chanel 150.75.20.2,3 (5,5 kg/m) kg 980.10
Sagrod 10 - 1200 (U-24) kg 125.44
Trekstang 12 (U-40) kg 72.63
Baseplat 16 mm (129,51 kg/m2) kg 82.89
Endplat 16 mm (129,51 kg/m2) kg 229.89
Voute (potongan WF 250.125.6.9) kg 142.08
Angkur D HTB 16 (L=40 cm) bh 48.00
Baut HTB D 16 bh 112.00
Zincromat WF, Lip Chanel, sagrod dan trekstang m2 301.60
Insulasi atap (Rockwool, double alumunium foil, roofmesh) m2 227.12
Penutup atap spandeck m2 227.12
JUMLAH -
PEKERJAAN STRUKTUR ATAS -
JUMLAH PEKERJAAN STRUKTUR STANDAR -
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
8/58
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
9/58
NO URAIAN PEKERJAAN SAT VOL HARGA SAT JUMLAH
V PEKERJAAN PLAFOND
1 Pek. Rangka Plafond m2 593.28
2 Pek. Plafond gypsum T. 9 mm m2 513.99
3 Pek. List Plafond gypsum m' 395.88
4 Pek. Plafond gypsum bagian Luar dan area basah m2 79.29
5 Pek. Acian bawah Tangga m2 31.80
6 Atap Entrance m2 23.98
Jumlah
VI PEKERJAAN SANITAIR1 Pek. Closet Monoblock unit 6.00
2 Pek. Wastafel Type unit 2.00
3 Pek. Urinoir Type unit 4.00
4 Pek. Skat Urinoir bh 4.00
5 Pek. Kaca cermin m2 1.84
6 Pek. Kran Type bh 7.00
7 Pek. Jet washer bh 6.00
8 Pek. Floor Drain bh 9.00
9 Pek. Kitchen Zink bh 2.00
10 Pek. Cubical toilet phenolic resin board unit 6.00
Jumlah
VII PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding Interior m2 615.52
2 Pek. Pengecatan Dinding Exterior m2 331.79
3 Pek. Pengecatan Kolom m2 166.73
4 Pek. Pengecatan Plafond Gypsum m2 593.28
5 Pek. Pengecatan Plafond Expose m2 31.80
Jumlah
JUMLAH PEKERJAAN LANTAI I
II. PEKERJAAN LANTAI II
I PEKERJAAN BETON PRAKTIS
1 Pek. Kolom Praktis m1 298.80
2 Pek. Balok lintel m1 126.10
3 Pek. Balok praktis dudukan partisi m1 6.87
4 Meja beton t= 10 cm m3 0.39
5 Chemical angkur utk kolom praktis gantung ttk 96.00
Jumlah
II PEKERJAAN DINDING
1 Pek. Dinding 1/2 Bata (1 : 5) m2 313.20
2 Pek. Plesteran dinding (1 : 5) m2 626.40
3 Pek. Plesteran dinding ban kusen BV (1 : 5) m2 4.54
4 Pek. Acian Dinding m2 626.40
5 Pek. Acian kolom m2 166.73
6 Pek. Acian bawah Tangga m2 31.80
7 Pek. Keramik dinding 30/60 Toilet R.Kepala Balai & Toilet umum t.3,2 m m2 102.80
8 Pek. Granit Alam Meja Wastafel m2 1.82
9 Pek. Partisi double gypsum rangka metal stud m2 44.20
Jumlah
III PEKERJAAN LANTAI
1 Pek. Granite Tile 60/60 m2 106.35
2 Pek. Plin lantai granite tile 10x60 polished m' 68.80
3 Pek. Granite Tile 30/60 Tangga + stairnozing m2 22.87
4 Pek. Keramik Lantai 30/30 Toilet m2 25.73
5 Pek. Urugan pasir urug (t= 5 cm) m3 6.60
6 Pek. Lantai kerja pelindung waterproofing dak bagian depan (5cm) m3 0.78
Jumlah
IV PEKERJAAN KUSEN PINTU DAN JENDELA
1 Pek. Kusen dan pintu Type P.3 unit 1.002 Pek. Kusen dan pintu Type P.4 unit 1.00
3 Pek. Kusen dan pintu Type P.5 unit 3.00
4 Pek. Kusen dan pintu Type P.6 unit 5.00
5 Pekerjaan Pintu Shaff unit 1.00
6 Pek. Kusen Jendela Type J.1 unit 1.00
7 Pek. Kusen Jendela Type J.1B unit 1.00
8 Pek. Kusen Jendela Type J.3 unit 1.00
9 Pek. Kusen Jendela Type J.6 unit 10.00
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
10/58
NO URAIAN PEKERJAAN SAT VOL HARGA SAT JUMLAH
10 Pek. Kusen Bouvenlich Type B.2 unit 2.00
11 Pek. Kusen Bouvenlich Type B.3 unit 2.00
12 Pek. Jalusi Besi Hollow termasuk pengecatan m2 37.44
Jumlah
V PEKERJAAN PLAFOND
1 Pek. Rangka Plafond m2 132.07
2 Pek. Plafond gypsum T. 9 mm m2 106.35
3 Pek. List Plafond gypsum m' 100.28
4 Pek. Plafond gypsum area toilet m2 25.73Jumlah
VI PEKERJAAN SANITAIR
1 Pek. Closet Monoblock unit 7.00
2 Pek. Wastafel unit 2.00
3 Pek. Urinoir unit 1.00
4 Pek. Skat Urinoir bh 4.00
5 Pek. Kaca cermin m2 2.00
6 Pek. Kran bh 11.00
7 Pek. Jet washer bh 7.00
8 Pek. Floor Drain bh 13.00
9 Bak. Air lapis keramik bh 1.00
10 Pek. Cubical toilet phenolic resin board unit 6.00
Jumlah
VII PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding Interior m2 254.12
2 Pek. Pengecatan Dinding Exterior m2 156.60
3 Pek. Pengecatan Kolom m2 166.73
4 Pek. Pengecatan Plafond Gypsum m2 157.80
5 Pek. Pengecatan Plafond Expose m2 -
6 Pek. Waterproofing membran m2 15.65
Jumlah
JUMLAH PEKERJAAN LANTAI II
III. PEKERJAAN LANTAI III
I PEKERJAAN BETON PRAKTIS
1 Pek. Kolom Praktis m1 98.00
2 Pek. Balok lintel m1 18.39
3 Pek. Balok praktis dudukan partisi m1
4 Chemical angkur utk kolom praktis gantung ttk 96.00
Jumlah
II PEKERJAAN DINDING
1 Pek. Dinding 1/2 Bata (1 : 5) m2 173.85
2 Pek. Plesteran dinding (1 : 5) m2 347.69
3 Pek. Acian Dinding m2 347.69
4 Pek. Acian kolom m2 86.09
Jumlah
III PEKERJAAN LANTAI
1 Pek. Granite Tile 60/60 m2
2 Pek. Granite Tile 30/60 Tangga m2
3 Pek. Keramik Lantai 30/30 Toilet m2
4 Pek. Stairnozing Granite Tile 5/30 m'
5 Pek. Lantai kerja pelindung waterproofing dak lt. 3 dan roof garden (5cm) m3 7.36
6 Pek. Tribun Ruang Serba Guna m2
Jumlah
IV PEKERJAAN KUSEN PINTU DAN JENDELA
1 Pek. Kusen dan pintu Type P.2 unit
2 Pek. Kusen Jendela Type J.1 unit
3 Pek. Kusen Jendela Type J.1B unit 1.00
4 Pek. Kusen Jendela Type J.3 unit 1.005 Pek. Kusen Jendela Type J.6 unit
6 Pek. Kusen Jendela Type T unit
7 Pek. Jalusi Besi Hollow termasuk pengecatan m2
8 Pek. Hand railling Tangga Pipa O2.5" Stainless m'
9 Pek. Railling Tangga Pipa O2.5" Stainless m'
Jumlah
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
11/58
NO URAIAN PEKERJAAN SAT VOL HARGA SAT JUMLAH
V PEKERJAAN PLAFOND
1 Pek. Rangka Plafond m2
2 Pek. Plafond gypsum T. 9 mm m2
3 Pek. Plafond Gypsum Aqustik t. 9 mm m2
4 Pek. List Plafond gypsum m2
5 Pek. Plafond gypsum bagian Luar m2
6 Pek. Acian bawah Tangga m2
7 Atap Entrance m2
JumlahVI PEKERJAAN SANITAIR
1 Pek. Closet Monoblock unit
2 Pek. Wastafel Type unit
3 Pek. Urinoir Type unit
4 Pek. Skat Urinoir bh
5 Pek. Kaca cermin m2
6 Pek. Kran Type bh
7 Pek. Floor Drain bh
8 Pek. Kitchen Zink bh
9 Kran Kitchen Zink bh
10 Bak. Fiber bh
11 Pek. Cubical m2
Jumlah
VII PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding Interior m2
2 Pek. Pengecatan Dinding Exterior m2 173.85
3 Pek. Pengecatan Kolom m2 86.09
4 Pek. Pengecatan Plafond Gypsum m2
5 Pek. Pengecatan Plafond Expose m2
6 Pek. Waterproofing dak lt. 3 dan roof garden m2 147.22
Jumlah
JUMLAH PEKERJAAN LANTAI III
IV. PEKERJAAN LANTAI DAK
I PEKERJAAN BETON PRAKTIS
1 Pek. Kolom Praktis m1 30.00
2 Pek.Balok praktis m1 75.51
Jumlah
II PEKERJAAN DINDING
1 Pek. Dinding 1/2 Bata (1 : 5) m2 75.51
2 Pek. Plesteran dinding (1 : 5) m2 151.02
3 Pek. Acian Dinding m2 151.02
4 Pek. Acian kolom m2
5 Pek. Keramik dinding 30/60 m2
6 Pek. Granit Meja Wastafel m2
Jumlah
III PEKERJAAN LANTAI
1 Pek. Granite Tile 60/60 m2
2 Pek. Lantai kerja pelindung waterproofing (t=5 cm) m3 18.14
3 Waterprofing membran m2 362.87
Jumlah
IV PEKERJAAN KUSEN PINTU DAN JENDELA
1 Pek. Kusen dan pintu Besi unit
Jumlah
V PEKERJAAN PLAFOND
1 Pek. Acian Plafond Expose m2
Jumlah
VII PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding Interior m22 Pek. Pengecatan Dinding Exterior m2 151.02
3 Pek. Pengecatan Kolom m2
4 Pek. Pengecatan Plafond Expose m2
Jumlah
JUMLAH PEKERJAAN LANTAI DAK -
-JUMLAH PEKERJAAN BANGUNAN GEDUNG UTAMA
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
12/58
Proyek : GEDUNG BALAI PSDA WS. CITARUM
Lokasi : JL. SOEKARNO HATTA BYPASS - BANDUNG
Pekerjaan : MEKANIKAL & ELEKTRIKAL
Tanggal :
E. PEKERJAAN MEKANIKAL ELEKTRIKAL
U R A I A N P E K E R J A A N J U M L A H
TOTAL PEKERJAAN MEKANIKAL DAN ELEKTRIKAL Rp.
SUB TOTAL -Rp.
PPN 10% -Rp.
TOTAL -Rp.
DIBULATKAN -Rp.
Terbilang :
RENCANA ANGGARAN BIAYA MEKANIKAL DAN ELEKTRIKAL
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
13/58
Proyek :
Lokasi :
Pekerjaan :
E. PEKERJAAN MEKANIKAL ELEKTRIKAL
J U M L A H
DIVISI A.0. PEKERJAAN MEKANIKAL -Rp.
DIVISI B.0. PEKERJAAN ELEKTRIKAL -Rp.
TOTAL PEKERJAAN MEKANIKAL DAN ELEKTRIKAL -Rp.
U R A I A N P E K E R J A A N
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
14/58
J U M L A H
SUB REKAPITULASI PEKERJAAN PLUMBING
DIVISI A.0. PEKERJAAN MEKANIKAL
Section A.1. Pemipaan Air Kotor, Buangan & Vent -Rp.
Section A.2. Instalasi Air Bersih -Rp.
Section A.3. Pekerjaan AC & Exhaust Fan -Rp.
Section A.4. Pekerjaan Sumur zet pump -Rp.
TOTAL PEKERJAAN MEKANIKAL -Rp.
U R A I A N P E K E R J A A N
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
15/58
No. HARGA SATUAN JUMLAH
DIVISI A.0. PEKERJAAN MEKANIKAL
Section A.1. Pemipaan Air Kotor, Buangan & Vent
A. Pekerjaan Site
1 Sistem pemipaan :
Pipa PVC, kelas D 150 mm (inc. galian & urugan) 86.00 m -Rp. -Rp.
Pipa PVC, kelas D 100 mm (inc. galian & urugan) 72.00 m -Rp. -Rp.
Pipa PVC, kelas D 50 mm (inc. galian & urugan) 24.00 m -Rp. -Rp.
2 Bak kontrol 50 x 50 kedalaman rata rata 76 cm 2.00 bh -Rp. -Rp.
3 Fitting, accessories & material support 1.00 ls -Rp -Rp.
4 Testing & commissioning 1.00 ls -Rp -Rp.
B. Lantai - 1
1 Sistem pemipaan :
Pipa PVC, kelas D 100 mm 46.00 m -Rp. -Rp.
Pipa PVC, kelas D 50 mm 52.00 m -Rp. -Rp.
2 Pipa PVC, kelas D 40 mm 20.00 m -Rp. -Rp.
3 Clean out (CO 50 mm) 9.00 bh -Rp. -Rp.
4 Fitting, accessories & material support 1.00 ls -Rp -Rp.
5 Testing & commissioning 1.00 ls -Rp -Rp.
C. Lantai - 2
1 Sistem pemipaan :
Pipa PVC, kelas D 100 mm 31.00 m -Rp. -Rp.
Pipa PVC, kelas D 50 mm 36.00 m -Rp. -Rp.
2 Pipa PVC, kelas D 40 mm 33.00 m -Rp. -Rp.
3 Clean out (CO 50 mm) 9.00 bh -Rp. -Rp.
4 Fitting, accessories & material support 1.00 ls -Rp -Rp.
5 Testing & commissioning 1.00 ls -Rp -Rp.
D. Lantai - 3
1 Sistem pemipaan :
Pipa PVC, kelas D 100 mm m -Rp. -Rp.
Pipa PVC, kelas D 50 mm m -Rp. -Rp.
Pipa PVC, kelas D 40 mm m -Rp. -Rp.
2 Clean out (CO 50 mm) bh -Rp. -Rp.
3 Vent cap 40 mm bh -Rp. -Rp.
4 Fitting, accessories & material support ls -Rp -Rp.
5 Testing & commissioning ls -Rp -Rp.
E. Pekerjaan Septictank :
Galian Tanah 6.19 m -Rp -Rp.
Urugan tanah kembali dan perataan 0.60 m -Rp -Rp.
Pasir urug, t 10 cm 0.34 m -Rp -Rp.
Lantai kerja, t : 5 cm 0.20 m -Rp -Rp.
Beton bertulang 0.46 m -Rp -Rp.
Tutup manhole 1.00 bh -Rp -Rp.
Instalasi pemipaan 1.00 ls -Rp -Rp.
Septictank package, kap : 3,00 m 1.00 unit -Rp -Rp.
Sub total section A.1. -Rp.
URAIAN PEKERJAAN VOLUME
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
16/58
No. URAIAN PEKERJAAN HARGA SATUAN JUMLAH
Section A.2. Instalasi Air Bersih
A Sistem Distribusi :
1a Pompa distribusi : type submersible 2.00 unit -Rp. -Rp.
Kapasitas : 2 x 280 lpm, Head : 40 mAq
power : 3.7 kw/3Ph/220v/50Hz (1 standby)
~ Accessories :
* 1 unit control panel in steel cabinet * 2 unit manifold made of galvanize pipe
* 2 unit non return valve
* 4 unit isolating valve
* 1 unit pressure sensor & 1 unit pressure gauge
* 1 unit membran tank
* Power cable motor to control panel
1b Valve :
Gate valve (F/F) 50 mm 4.00 unit -Rp. -Rp.
Check valve (F/F) 50 mm 4.00 unit -Rp. -Rp.
Strainer (F/F) 50 mm 4.00 unit -Rp. -Rp.
Flexible connection 50 mm 4.00 unit -Rp. -Rp.
1d Fitting, accessories & material support 1.00 ls -Rp. -Rp.
1e Testing & commissioning 1.00 ls -Rp. -Rp.
2 Pompa booster : 1.00 unit -Rp. -Rp.
Kapasitas 75 ltr/mnt
Head 20 mAq
Motor output 1.0 kW
Type : Vertikal
Termasuk pressure tank
3 Roof tank FRP panel system c/w : 1.00 unit -Rp. -Rp.
Kapasitas : 12 m (3 x 2 x 2) m
Steel base UNP
Manhole, tangga luar & dalam
Inlet, outlet, drain & connection
3a Sistem pemipaan (PP-R PN10) :
Pipa PP-R 65 mm 75.00 m -Rp. -Rp.
Pipa PP-R 50 mm 68.00 m -Rp. -Rp.
Header GSP 100 mm (L = 150 cm) 1.00 unit -Rp. -Rp.
Pipa PVC AW class 50 mm (over flow) 8.00 m -Rp. -Rp.
3b Valve :
Gate valve 65 mm 2.00 bh -Rp -Rp.
Gate valve 50 mm 3.00 bh -Rp -Rp.
Gate valve 40 mm 1.00 bh -Rp -Rp.
Foot valve 75 mm 1.00 bh -Rp -Rp.
4 Water filter (automatic sand filter) 1.00 unit -Rp. -Rp.
Kapasitas : 180 ltr / menit
Sand carbon, zeolit
4a Sistem pemipaan (PP-R PN10) :
Pipa PP-R 65 mm (dari Deep well) 10.00 m -Rp. -Rp.
Pipa PP-R 32 mm 6.00 m -Rp -Rp.
Pipa PP-R 25 mm (drain) 6.00 m -Rp -Rp.
Header GSP 100 mm (L = 175 cm) 2.00 unit -Rp. -Rp.
4b Valve :
Gate valve 65 mm 2.00 bh -Rp. -Rp. Gate valve 50 mm 1.00 bh -Rp -Rp.
Gate valve 40 mm 6.00 bh -Rp -Rp.
Gate valve 25 mm 3.00 bh -Rp -Rp.
Pressure gauge 15 mm 2.00 bh -Rp -Rp.
5 Fitting, accessories dan material support 1.00 ls -Rp. -Rp.
6 Testing dan commissioning 1.00 ls -Rp. -Rp.
VOLUME
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
17/58
B Pemipaan :
B.1 Lantai - 1
1 Sistem pemipaan (PP-R, PN10) :
Polypropiline - random pipe (PP-R), 40 mm 4.00 m -Rp -Rp.
Polypropiline - random pipe (PP-R), 32 mm 41.00 m -Rp. -Rp.
Polypropiline - random pipe (PP-R), 25 mm 15.00 m -Rp. -Rp.
Polypropiline - random pipe (PP-R), 20 mm 26.00 m -Rp -Rp.
Polypropiline - random pipe (PP-R), 15 mm 25.00 m -Rp -Rp.
2 Valve :
Gate valve 40 mm 1.00 bh -Rp -Rp. Gate valve 32 mm 2.00 bh -Rp -Rp.
Gate valve 20 mm 1.00 bh -Rp -Rp.
Gate valve 15 mm 1.00 bh -Rp -Rp.
3 Fitting, accessories & material support 1.00 ls -Rp. -Rp.
4 Testing & commissioning 1.00 ls -Rp. -Rp.
B.2 Lantai - 2
1 Sistem pemipaan (PP-R, PN10) :
Polypropiline - random pipe (PP-R), 40 mm m -Rp -Rp.
Polypropiline - random pipe (PP-R), 32 mm m -Rp -Rp.
Polypropiline - random pipe (PP-R), 25 mm m -Rp. -Rp.
Polypropiline - random pipe (PP-R), 20 mm m -Rp. -Rp.
Polypropiline - random pipe (PP-R), 15 mm m -Rp. -Rp.
2 Valve :
Gate valve 40 mm bh -Rp -Rp. Gate valve 32 mm bh -Rp -Rp.
Gate valve 25 mm bh -Rp -Rp.
Gate valve 15 mm bh -Rp -Rp.
3 Fitting, accessories & material support ls -Rp. -Rp.
4 Testing & commissioning ls -Rp. -Rp.
B.3 Lantai - 3
1 Sistem pemipaan (PP-R, PN10) :
Polypropiline - random pipe (PP-R), 40 mm m -Rp -Rp.
Polypropiline - random pipe (PP-R), 32 mm m -Rp -Rp.
Polypropiline - random pipe (PP-R), 25 mm m -Rp -Rp.
Polypropiline - random pipe (PP-R), 20 mm m -Rp -Rp.
Polypropiline - random pipe (PP-R), 15 mm m -Rp -Rp.
2 Valve :
Gate valve 40 mm bh -Rp -Rp.
Gate valve 32 mm bh -Rp -Rp.
Gate valve 25 mm bh -Rp -Rp.
3 Fitting, accessories & material support ls -Rp. -Rp.
4 Testing & commissioning ls -Rp. -Rp.
Sub total section A.2. -Rp.
Section A.3. Pekerjaan AC & Exhaust Fan
A Pekerjaan AC
a Lantai - 1
1 Outdoor unit (OU) kapasitas : 180.000 BTU/h unit -Rp. -Rp.
2 Indoor unit (IU) : unit -Rp -Rp.
kapasitas : 22.000 BTU/h
type wall3 Indoor unit (IU) : unit -Rp -Rp.
kapasitas : 32.000 BTU/h
4- way ceiling cassette
4 Indoor unit (IU) : unit -Rp. -Rp.
kapasitas : 18.000 BTU/h
4- way ceiling cassette
5 Setting AC outdoor unit (instalasi & material support) unit -Rp. -Rp.
6 Setting AC indoor unit (instalasi & material support)
type wall unit -Rp -Rp.
type cassette unit -Rp -Rp.
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
18/58
7 Pipa refigerant lengkap dgn isolasi, fitting, hanger
accessories dan support material :
dia. 6.35 mm m -Rp -Rp.
dia. 12.70 mm m -Rp -Rp.
dia. 19.10 mm m -Rp. -Rp.
dia. 22.20 mm m -Rp. -Rp.
dia. 28.58 mm m -Rp -Rp.
8 Pipa drain PVC AW class lengkap dgn isolasi, fitting,
hanger, accessories dan support material :
dia. 20 mm m -Rp -Rp.Accessorises :
OU pipe connection unit -Rp -Rp.
Header 10 cabang unit -Rp -Rp.
Kabel power dari panel PP-OU. AC ke :
Outdoor unit (OU) NYY 4 x 6 mm m -Rp. -Rp.
Kabel kontrol dari indoor ke outdoor shielded 2 x 1.5 mm m -Rp -Rp.
Material support, testing & commissioning ls -Rp. -Rp.
b Lantai - 2
1 Outdoor unit (OU) kapasitas : 240.000 BTU/h unit -Rp. -Rp.
2 Indoor unit (IU) : unit -Rp -Rp.
kapasitas : 16.000 BTU/h
type wall
3 Indoor unit (IU) : unit -Rp -Rp.
kapasitas : 32.000 BTU/h 4- way ceiling cassette
4 Setting AC outdoor unit (instalasi & material support) unit -Rp. -Rp.
5 Setting AC indoor unit (instalasi & material support)
type wall unit -Rp -Rp.
type cassette unit -Rp -Rp.
6 Pipa refigerant lengkap dgn isolasi, fitting, hanger
accessories dan support material :
dia. 6.35 mm m -Rp -Rp.
dia. 12.70 mm m -Rp -Rp.
dia. 19.10 mm m -Rp. -Rp.
dia. 22.20 mm m -Rp. -Rp.
dia. 28.58 mm m -Rp -Rp.
7 Pipa drain PVC AW class lengkap dgn isolasi, fitting,
hanger, accessories dan support material :
dia. 20 mm m -Rp -Rp.
Accessorises :
OU pipe connection unit -Rp -Rp.
Header 10 cabang unit -Rp -Rp.
Kabel power dari panel PP-OU. AC ke :
Outdoor unit (OU) NYY 4 x 10 mm m -Rp. -Rp.
Kabel kontrol dari indoor ke outdoor shielded 2 x 1.5 mm m -Rp -Rp.
Material support, testing & commissioning ls -Rp. -Rp.
c Lantai - 3
1 Outdoor unit (OU) kapasitas : 144.000 BTU/h unit -Rp. -Rp.
2 Indoor unit (IU) : unit -Rp -Rp.
kapasitas : 6.000 BTU/h
type wall
3 Indoor unit (IU) : unit -Rp -Rp.
kapasitas : 18.000 BTU/h
4- way ceiling cassette
4 Setting AC outdoor unit (instalasi & material support) unit -Rp. -Rp.
5 Setting AC indoor unit (instalasi & material support)
type wall unit -Rp -Rp.
type cassette unit -Rp -Rp.
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
19/58
6 Pipa refigerant lengkap dgn isolasi, fitting, hanger
accessories dan support material :
dia. 6.35 mm m -Rp -Rp.
dia. 12.70 mm m -Rp -Rp.
dia. 19.10 mm m -Rp. -Rp.
dia. 22.20 mm m -Rp. -Rp.
dia. 28.58 mm m -Rp -Rp.
7 Pipa drain PVC AW class lengkap dgn isolasi, fitting,
hanger, accessories dan support material :
dia. 20 mm m -Rp -Rp.Accessorises :
OU pipe connection unit -Rp -Rp.
Header 10 cabang unit -Rp -Rp.
Kabel power dari panel PP-OU. AC ke :
Outdoor unit (OU) NYY 4 x 6 mm m -Rp. -Rp.
Kabel kontrol dari indoor ke outdoor shielded 2 x 1.5 mm m -Rp -Rp.
Material support, testing & commissioning ls -Rp. -Rp.
B. Pekerjaan Exhaust Fan
a. Lantai - 1
1 Exhaust Fan (EF)
EF. 1.1 s/d 1.4, kap : 90 cfm 4.00 unit -Rp -Rp.
2 Exhaust Air Grille (EAG)
200 x 200 4.00 unit -Rp -Rp.
3 Ducting termasuk isolasi 150 x 150 12.00 m -Rp -Rp.
4 Instalasi, material support, testing & commissioning 1.00 ls -Rp -Rp.
b. Lantai - 2
1 Exhaust Fan (EF)
EF. 2.1 s/d 2.3, kap : 90 cfm unit -Rp -Rp.
2 Exhaust Air Grille (EAG)
200 x 200 unit -Rp -Rp.
3 Ducting termasuk isolasi & material bantu
150 x 150 m -Rp -Rp.
4 Instalasi, material support, testing & commissioning ls -Rp -Rp.
c. Lantai - 3
1 Exhaust Fan (EF)
EF. 3.1 s/d 3.4, kap : 90 cfm unit -Rp -Rp.
2 Exhaust Air Grille (EAG)
200 x 200 unit -Rp -Rp.
3 Ducting termasuk isolasi & material bantu
150 x 150 m -Rp -Rp.
4 Instalasi, material support, testing & commissioning ls -Rp -Rp.
Sub total section A.3. -Rp.
Section A.4. Pekerjaan Sumur zet pump
1 Pekerjaan pengeboran : 1.00 lot -Rp. -Rp.
~ Transportasi & akomodasi
~ Mobilisasi & demobilisasi alat pemboran / rig
~ Pemasangan/pembongkaran drilling rig & alat bantu~ Pit lumpur, landasan rig, laporan & dokumentasi
~ Piva dan asesoris 1.00 lot -Rp. -Rp.
2 Pompa & perlengkapan :
Pompa sumbersible 1.00 unit -Rp. -Rp.
Accessories pompa (kabel kontrol & kabel power, 1.00 ls -Rp. -Rp.
valve & material support
Sub total section A.4. -Rp.
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
20/58
J U M L A H
SUB REKAPITULASI PEKERJAAN ELEKTRIKAL
DIVISI B.0. PEKERJAAN ELEKTRIKAL
Section B.1. Pekerjaan Distribusi Listrik Utama -Rp.
Section B.2. Pekerjaan Elektrikal Lantai - 1 -Rp.
Section B.3. Pekerjaan Elektrikal Lantai - 2 -Rp.
Section B.4. Pekerjaan Elektrikal Lantai - 3 -Rp.
Section B.5. Penangkal Petir -Rp.
TOTAL PEKERJAAN ELEKTRIKAL -Rp.
U R A I A N P E K E R J A A N
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
21/58
No. URAIAN PEKERJAAN HARGA SATUAN JUMLAH
DIVISI B.0. PEKERJAAN ELEKTRIKAL
Section B.1. Pekerjaan Distribusi Listrik Utama
1 Biaya penyambungan (BP-PLN) termasuk biaya SLO 66.00 kVA -Rp. -Rp.
(Sertifikat Laik Operasi) untuk sambungan kapasitas 66 kVA
2a Panel SDP-BC 1.00 unit -Rp. -Rp.
~ Panel box (1 unit)
~ MCCB 3P, 160A, 16kA (1 bh)
~ MCCB 3P, 125A, 16kA (1 bh)
~ MCB 3P, 40A, 10kA (1 bh)
~ MCB 3P, 32A, 10kA (1 bh)
~ MCB 3P, 25A, 10kA (1 bh)
~ MCB 3P, 16A, 10kA (1 bh)
~ Ampere meter 0-250 A (3 bh)
~ Current transformer 200/5 A (3 bh)
~ Volt meter 0-500 V (1 bh)
~ Volt-selector switch (1 bh)
~ kW meter (1 bh)
~ Terminal block (1 lot)
~ Fuse control, 2A (12 bh)
~ Pilot lamp 220 VAC c/w : LED (3 bh)
~ Busbar & accessories (1 lot)
2b Instalasi (wiring & diagram) 1.00 ls -Rp. -Rp.
3c Peralatan & material bantu 1.00 ls -Rp. -Rp.
4 Kabel Utama dari Meter PLN ke :
SDP-BC, NYY 4 x 50 mm 45.00 m -Rp. -Rp.
5 Kabel distribusi dari SDP-BC ke :
Panel Kontrol Pompa, NYY 4 x 2,5 mm 95.00 m -Rp. -Rp.
LP-A, NYY 4 x 6 mm 6.00 m -Rp. -Rp.
LP-B, NYY 4 x 6 mm 12.00 m -Rp. -Rp.
LP-C, NYY 4 x 4 mm 34.00 m -Rp. -Rp.
PP-OU.AC, NYY 4 x 35 mm 25.00 m -Rp. -Rp.
Sub total section B.1. -Rp.
Section B.2. Pekerjaan Elektrikal Lantai - 1
A Sub Distribusi
1a Panel LP-A 1.00 unit -Rp. -Rp.
~ Panel box (1 unit)
~ MCB 3P, 25A, 10kA (1 bh)
~ MCB 1P, 10A, 6kA (16 bh)
~ MCB 1P, 6A, 6kA (5 bh)
~ Fuse control, 2A (3 bh)
~ Pilot lamp 220 VAC c/w : LED (3 bh)
~ Busbar & accessories (1 lot)
1b Instalasi (wiring & diagram) 1.00 ls -Rp. -Rp.
1c Peralatan & material bantu 1.00 ls -Rp. -Rp.
B Instalasi & Fixtures
1 Lampu Downlight 3" Tornado 8W 24.00 set -Rp. -Rp.
2 Lampu Downlight 4" PL 14W 33.00 set -Rp. -Rp.
3 Lampu Ceiling Recessed 2 x 18W 13.00 set -Rp. -Rp.
4 Lampu Ceiling Recessed 2 x 36W 17.00 set -Rp. -Rp.
5 Lampu dinding di atas cermin TL 18W, cover acrylic 2.00 set -Rp. -Rp.
6 Lampu TLD V-Shafe 1 x 18W 11.00 set -Rp. -Rp.
7 Lampu TLD V-Shafe 1 x 36W 3.00 set -Rp. -Rp.
8 Floodlight, Halogen 150W 2.00 set -Rp. -Rp.
VOLUME
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
22/58
9 Lampu Dinding PL 11W 6.00 set -Rp. -Rp.
10 Lampu Taman Bolard Kotak PL18W c/w include base 8.00 set -Rp. -Rp.
11 LDR, 6A 1.00 bh -Rp. -Rp.
12 Saklar tunggal, rating 10A 9.00 bh -Rp. -Rp.
13 Saklar ganda, rating 10A 22.00 bh -Rp. -Rp.
14 Saklar hotel, rating 10A 4.00 bh -Rp. -Rp.
15 Outlet kotak kontak dinding, rating 10A 30.00 bh -Rp. -Rp.
16 Outlet kotak kontak lantai, rating 10A 29.00 bh -Rp. -Rp.
17 Instalasi titik lampu & outlet, rating 10A 178.00 ttk -Rp. -Rp.
18 Instalasi power Indoor AC & Fan, rating 10A 12.00 ttk -Rp. -Rp.
C Rak kabel
1 Rak kabel (300 x 50) mm 40.00 m -Rp. -Rp.
2 Instalasi, accessories & material support 1.00 ls -Rp. -Rp.
D. Testing & Commissioning 1.00 ls -Rp. -Rp.
Sub total section B.2. -Rp.
Section B.3. Pekerjaan Elektrikal Lantai - 2
A Sub Distribusi
1a Panel LP-B unit -Rp. -Rp.
~ Panel box (1 unit)
~ MCB 3P, 32A, 10kA (1 bh)
~ MCB 1P, 10A, 6kA (16 bh)
~ MCB 1P, 6A, 6kA (5 bh)
~ Fuse control, 2A (3 bh)
~ Pilot lamp 220 VAC c/w : LED (3 bh)
~ Busbar & accessories (1 lot)
1b Instalasi (wiring & diagram) ls -Rp. -Rp.
1c Peralatan & material bantu ls -Rp. -Rp.
B Instalasi & Fixtures
1 Lampu Downlight 3" Tornado 8W set -Rp. -Rp.
2 Lampu Downlight 4" PL 14W set -Rp. -Rp.
3 Lampu Ceiling Recessed 2 x 36W set -Rp. -Rp.
4 Lampu dinding di atas cermin TL 18W, cover acrylic set -Rp. -Rp.
5 Lampu TLD V-Shafe 1 x 18W set -Rp. -Rp.
6 Saklar tunggal, rating 10A bh -Rp. -Rp.
7 Saklar ganda, rating 10A bh -Rp. -Rp.
8 Saklar hotel, rating 10A bh -Rp. -Rp.
9 Outlet kotak kontak dinding, rating 10A bh -Rp. -Rp.
10 Outlet kotak kontak lantai, rating 10A bh -Rp. -Rp.
11 Instalasi titik lampu & titik daya, rating 10A ttk -Rp. -Rp.
12 Instalasi power Indoor AC & Fan, rating 10A ttk -Rp. -Rp.
C Rak kabel
1 Rak kabel (300 x 50) mm m -Rp. -Rp.
2 Instalasi, accessories & material support ls -Rp. -Rp.
D. Testing & Commissioning ls -Rp. -Rp.
Sub total section B.3. -Rp.
Section B.4. Pekerjaan Elektrikal Lantai - 3
A Sub Distribusi :
1a Panel LP-C unit -Rp. -Rp.
~ Panel box (1 unit)
~ MCB 3P, 20A, 10kA (1 bh)
~ MCB 1P, 10A, 6kA (8 bh)
~ MCB 1P, 6A, 6kA (4 bh)
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
23/58
~ Fuse control, 2A (3 bh)
~ Pilot lamp 220 VAC c/w : LED (3 bh)
~ Busbar & accessories (1 lot)
1b Instalasi (wiring & diagram) ls -Rp. -Rp.
1c Peralatan & material bantu ls -Rp. -Rp.
B Instalasi & Fixtures
1 Lampu Downlight 3" Tornado 8W set -Rp. -Rp.
2 Lampu Downlight 4" PL 14W set -Rp. -Rp.
3 Lampu Ceiling Recessed 2 x 36W set -Rp. -Rp.4 Lampu dinding di atas cermin TL 18W, cover acrylic set -Rp. -Rp.
5 Lampu TLD V-Shafe 1 x 36W set -Rp. -Rp.
6 Saklar tunggal, rating 10A bh -Rp. -Rp.
7 Saklar ganda, rating 10A bh -Rp. -Rp.
8 Outlet kotak kontak dinding, rating 10A bh -Rp. -Rp.
9 Outlet kotak kontak lantai, rating 10A bh -Rp. -Rp.
10 Instalasi titik lampu & outlet, rating 10A ttk -Rp. -Rp.
11 Instalasi power Indoor AC & Fan, rating 10A ttk -Rp. -Rp.
C Rak kabel
1 Rak kabel (300 x 50) mm m -Rp. -Rp.
2 Instalasi, accessories & material support ls -Rp. -Rp.
D Testing & Commissioning ls -Rp. -Rp.
Sub total section B.4. -Rp.
Section B.5. Penangkal Petir
1 Penangkal petir type Elektrostatik, R = 50 m 1.00 set -Rp. -Rp.
~ Air terminal / spit
~ Connecting sleeve
~ Counter stroke
2 Pipa GIP medium class 50 mm (H = 4 m) 1.00 unit -Rp. -Rp.
3 Down conductor XLPE 70 mm 34.00 m -Rp. -Rp.
4 Test box 1.00 bh -Rp. -Rp.
5 Control box (50 x 50 x 50) cm 1.00 bh -Rp. -Rp.
6 Arde grounding spit 1" (max. resistance 2 ohm) 1.00 unit -Rp. -Rp.
7 Clamp, bolt & material support 1.00 ls -Rp. -Rp.
8 Perijinan, testing & commissioning 1.00 ls -Rp. -Rp.
Sub total section B.5. -Rp.
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
24/58
No. SATUAN HARGA SATUAN
1 Polypropiline Pipe PP-R, PN10 (Instalasi air bersih) 1.20 (pipa PP-R : 1 btng =
Polypropiline - random pipe (PP-R), 150 mm m 6" 3,300,000.00Rp
Polypropiline - random pipe (PP-R), 100 mm m 4" 1,350,000.00Rp
Polypropiline - random pipe (PP-R), 75 mm m 3" 890,000.00Rp
Polypropiline - random pipe (PP-R), 65 mm m 2" 640,000.00Rp
Polypropiline - random pipe (PP-R), 50 mm m 2" 400,000.00Rp
Polypropiline - random pipe (PP-R), 40 mm m 1" 315,250.00Rp
Polypropiline - random pipe (PP-R), 32 mm m 1" 250,000.00Rp
Polypropiline - random pipe (PP-R), 25 mm m 1" 108,000.00Rp
Polypropiline - random pipe (PP-R), 20 mm m "72,000.00Rp
Polypropiline - random pipe (PP-R), 15 mm m " 50,000.00Rp
2 Polypropiline Pipe PP-R, PN20 (Instalasi air panas)
Polypropiline - random pipe (PP-R), 65 mm m 2" 1,000,000.00Rp
Polypropiline - random pipe (PP-R), 50 mm m 2" 680,000.00Rp
Polypropiline - random pipe (PP-R), 40 mm m 1" 575,000.00Rp
Polypropiline - random pipe (PP-R), 32 mm m 1" 400,000.00Rp
Polypropiline - random pipe (PP-R), 25 mm m 1" 175,000.00Rp
Polypropiline - random pipe (PP-R), 20 mm m " 109,000.00Rp
Polypropiline - random pipe (PP-R), 15 mm m " 69,000.00Rp
3 Pipa PVC (Tekanan nominal 5 BAR, instalasi air kotor & buangan) 1.20 (pipa PVC : 1 btng =
Pipa PVC 400 mm m 1,658,000.00Rp
Pipa PVC 300 mm m 1,325,000.00Rp
Pipa PVC 250 mm m 950,470.00Rp
Pipa PVC 200 mm m 641,780.00Rp Pipa PVC 150 mm m 384,650.00Rp
Pipa PVC 100 mm m 169,880.00Rp
Pipa PVC 75 mm m 113,130.00Rp
Pipa PVC 65 mm m 80,810.00Rp
Pipa PVC 50 mm m 51,000.00Rp
Pipa PVC 40 mm m 40,420.00Rp
JENIS MATERIAL
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
25/58
4 Galian tanah biasa kedalaman 1-2 m /m (SNI DT 91-0006-2007, 6.2)
Pekerja 0.9000 oh -Rp. -Rp.
Mandor 0.0450 oh -Rp. -Rp.
Sub Jumlah -Rp.
Biaya umum, keuntungan & over head (10%) -Rp.
Jumlah -Rp.
5 Urug tanah kembali & perataan /m (Revisi SNI 03-2835-2002, 6.9)
Pekerja 0.3000 oh -Rp -Rp.
Mandor 0.0150 oh -Rp -Rp.
Sub Jumlah -Rp.
Biaya umum, keuntungan & over head (10%) -Rp.
Jumlah -Rp.
6 Urugan pasir /m (SNI DT 91-0006-2007, 6.11)
Pasir urug 1.2000 m -Rp -Rp.
Pekerja 0.3000 oh -Rp -Rp.
Mandor 0.0100 oh -Rp -Rp.
Sub Jumlah -Rp.
Biaya umum, keuntungan & over head (10%) -Rp.
Jumlah -Rp.
7 Lantai kerja 1pc : 3psr : 5krl /m (Revisi SNI T-13-2002, 6.4)Pekerjaan Beton Septictank / m
Portlant cement 230.0000 kg -Rp. -Rp.
Pasir beton 0.7654 m -Rp. -Rp.
Koral beton (maksimum 30 mm) 0.7607 m -Rp. -Rp.
Air 200.0000 ltr -Rp. -Rp.
Pekerja 1.2000 oh -Rp. -Rp.
Tukang batu 0.2000 oh -Rp. -Rp. Kepala tukang batu 0.0200 oh -Rp. -Rp.
Mandor 0.0600 oh -Rp. -Rp.
Sub Jumlah -Rp.
Biaya umum, keuntungan & over head (10%) -Rp.
Jumlah -Rp.
Pekerjaan Beton Septictank / m
Beton ready mix K - 300 1.0000 m -Rp. -Rp.
Besi Beton 103.9100 kg -Rp -Rp.
Bekisting 5.0000 m -Rp -Rp.
Upah cor termasuk vibrator & incuring 1.0000 m -Rp -Rp.
Sub Jumlah -Rp.
Biaya umum, keuntungan & over head (10%) -Rp.
Jumlah -Rp.
9 Pipa PVC 150 mm / m (buangan air bekas)
Galian tanah 0.6000 m -Rp. -Rp. Urug tanah kembali & perataan 0.6000 m -Rp. -Rp.
Pasir urug (leveling pipa) 0.0800 m -Rp. -Rp.
Pipa PVC 150 mm 1.0500 m -Rp. -Rp.
Jumlah -Rp.
8 Pipa PVC 100 mm / m (buangan air bekas)
Galian tanah 0.6000 m -Rp. -Rp.
Urug tanah kembali & perataan 0.6000 m -Rp. -Rp.
Pasir urug (leveling pipa) 0.0800 m -Rp. -Rp.
Pipa PVC 100 mm 1.0500 m -Rp. -Rp.
Jumlah -Rp.
9 Pipa PVC 50 mm / m (buangan air bekas)
Galian tanah 0.6000 m -Rp. -Rp.
Urug tanah kembali & perataan 0.6000 m -Rp. -Rp.
Pasir urug (leveling pipa) 0.0800 m -Rp. -Rp.
Pipa PVC 50 mm 1.0500 m -Rp. -Rp.
Jumlah -Rp.
10 Bak kontrol 50 x 50 (kedalaman rata-rata : 76 cm) /unit (air bekas)
Galian tanah 1.0125 m -Rp. -Rp.
Urug tanah kembali & perataan 1.0125 m -Rp. -Rp.
Pasir urug 0.0810 m -Rp. -Rp.
Lantai kerja 0.0320 m -Rp. -Rp.
Beton site mix K-225 0.2890 m -Rp. -Rp.
Besi beton 19.9870 kg -Rp. -Rp.
Bekisting praktis 5.0800 m -Rp. -Rp.
Handle 16 mm 1.0000 bh -Rp. -Rp.
Plester kemiringan 0.2500 m -Rp. -Rp.
Jumlah -Rp.
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
26/58
Harga Satuan Jumlah Harga
(Rp.) (Rp.)1 3 4 5 6
F PEKERJAAN SITE DEVELOPMENT
I PEKERJAAN BANGUNAN PENUNJANG
1.1 Pek. Ground Tank 120 m3
- Pek. Urugan tanah peninggian bangunan (h=40 cm) m3
- Pek. Pemadatan tanah urugan peninggian bangunan m2
- Pek. Pondasi Konstruksi Sarang Laba Laba m2
- Pek. Stek Kolom (L = 100 cm)
Besi D16 (1.683 Kg/m) kg
Sengkang 10 - 100 (0.617 Kg/m) kg
- Pek. Kolom KG (25/25) 8 unit (h = 2,50 m)
Beton K300 m3
Besi 8 D 16 (1.683 Kg/m) kg
Sengkang 10 - 150 (0.617 Kg/m) kg
Bekisting Kolom multiplek 9mm m2
- Beam B3 (200 x 400 mm)
Beton K300 m3
Besi 4 D16 (1.683 Kg/m) kg
Sengkang 10 - 150 (0.617 Kg/m) kg
Bekisting balok multipleks 9mm (bawah + 2sisi) m2
- Beam B5 (200 x 300 mm)
Beton K300 m3
Besi 4 D13 (1.042 Kg/m) kg
Sengkang 10 - 150 (0.617 Kg/m) kgBekisting balok multipleks 9mm (bawah + 2sisi) m
2
- Dinding Beton ( t = 150 mm)
Beton K300 m3
wiremesh M8 (59,535 kg/lembar) 2 lapis kg
Bekisting dinding m2
- Plat Dak beton ( t = 120 mm)
Beton K300 m3
wiremesh M7 (45,59 kg/lembar) 2 lapis kg
Bekisting Plat m2
- Pek. Waterproofing membran m2
- Pek. Lantai kerja pelindung waterproofing (plat dak beton) m3
(t = 5 cm)
- Pek. Pasangan keramik dinding dan lantai 30x30 Putih m2
- Pek. Pintu man hole (rangka besi siku + plat) unit
1.2 Pek. R. Pompa, R. Panel & R. Trafo
- Pek. Urugan tanah peninggian bangunan (h=40 cm) m3
- Pek. Pemadatan tanah urugan peninggian bangunan m2
- Pek. Pondasi Konstruksi Sarang Laba Laba m2
- Pek. Stek Kolom (L = 100 cm)
Besi D16 (1.683 Kg/m) kg
Sengkang 10 - 100 (0.617 Kg/m) kg
- Pek. Kolom KG2 (25/25) 8 unit (h = 2,50 m)
Beton K300 m
3
2
0
PEKERJAAN PEMBANGUNAN GEDUNG KANTOR BALAI PSDA Ws. CITARUM
JL. SMK 6 - SOEKARNO HATTA - KOTA BANDUNG
TAHUN 2016
No. Uraian Pekerjaan Satuan Volume
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
27/58
Harga Satuan Jumlah Harga
(Rp.) (Rp.)1 3 4 5 62
No. Uraian Pekerjaan Satuan Volume
Besi 4 D 16 (1.683 Kg/m) kg
Sengkang 10 - 150 (0.617 Kg/m) kg
Bekisting Kolom multiplek 9mm m2
- Beam B3 (200 x 400 mm)
Beton K300 m3
Besi 4 D16 (1.683 Kg/m) kg
Sengkang 10 - 150 (0.617 Kg/m) kg
Bekisting balok multipleks 9mm (bawah + 2sisi) m2
- Beam B5 (200 x 300 mm)
Beton K300 m3
Besi 4 D13 (1.042 Kg/m) kg
Sengkang 10 - 150 (0.617 Kg/m) kg
Bekisting balok multipleks 9mm (bawah + 2sisi) m2
- Plat Dak beton ( t = 120 mm)
Beton K300 m3
wiremesh M7 (45,59 kg/lembar) 2 lapis kg
Bekisting Plat m2
- Pek. Waterproofing membran m
2
- Pek. Lantai kerja pelindung waterproofing (plat dak beton) m3
(t = 5 cm)
- Pek. Dinding 1/2 Bata (1 PC: 5 PS) m2
- Pek. Plesteran dinding (1 PC : 5 PS) m2
- Pek. Acian dinding m2
- Pek. Acian Kolom struktur m2
- Pek. Acian Pelat dan Balok Beton m2
- Pek. Kolom praktis 11/11 m'
- Balok Lintel 12/15 m'
- Pek. Finishing lantai epoxy coating m2
- Pek. Pintu besi single PB 3 unit
- Pek. Pintu besi double PB 2 unit
- Pek. Jalusi besi unit
- Pek. Pengecatan Dinding Interior m2
- Pek. Pengecatan Dinding Exterior m2
- Pek. Pengecatan Plafond m2
- Pek. Pegecatan Cat Kolom m2
- Pek. Pengecatan Pintu Besi m2
Sub Jumlah I
II PEKERJAAN JALAN DAN TAMAN
1.1 Pek. Jalan
- Lapisan pondasi agregat kelas A (LPA) (20 cm) m3
209.00
- Paving Block eks Cisangkan m
2
1,045.001.2 Pek. Pemasangan Kansteen berikut pengecatan m' 61.00
1.3 Pek. Urugan tanah gembur (h= 10 cm) m3
1.4 Pek. Penanaman pohon ketapang (h= 1m) btg
1.5 Pek. Penanaman pohon tabe buya putih (h= 1m) btg
1.6 Pek. Penanaman pohon angsana kuning (h= 1m) btg
1.7 Pek. Penanaman rumput jepang m2
1.8 Pek. Penanaman pohon palem raja (h= 1m) btg
1.9 Pek. Penanaman pohon pangkas kuning (h= 1m) bh
Sub Jumlah II
Jumlah E
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
28/58
A ANALISA UMUM
1 1 M' PENGUKURAN DAN PEMASANGAN BOUWPLANK2 1 M2 KANTOR SEMENTARA LANTAI PLESTERAN
3 1 M2 GUDANG SEMEN DAN PERALATAN
4 1 M1 PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 M
5 1 M2 PEMBERSIHAN DAN PERATAAN LAPANGAN
6 1 M3 PEMBONGKARAN DINDING BATA
7 1 UNIT PAPAN NAMA PROYEK 80 X 120 CM
8 1 M3 GALIAN TANAH BIASA KEDALAMAN MAX 1 M
9 1 M3 GALIAN TANAH BIASA KEDALAMAN MAX 2 M
10 1 M3 GALIAN TANAH DENGAN ALAT BERAT
11 1 M3 PEKERJAAN TIMBUNAN TANAH DARI LUAR
12 1 M3 URUGAN KEMBALI TANAH BEKAS GALIAN
13 1 M3 BUANGAN TANAH KELUAR LOKASI SEJAUH 30 METER
14 1 M3 PEMADATAN TANAH (PER 20 CM)
15 1 M3 MENGURUG PASIR URUG
16 1 M3 URUGAN SIRTU PADAT
17 1 M3 PASANG PONDASI BATU BELAH (1PC : 5PS)
18 1 M3 PASANG BATU KOSONG / AANSTAMPING
19 1 M2 PASANG DINDING BATA MERAH 1/2 BT (1PC : 3PS)
20 1 M2 PASANG DINDING BATA MERAH 1/2 BT (1PC : 5PS)
21 1 M2 PLESTERAN DINDING 1 : 3 T= 15 mm
22 1 M2 PLESTERAN DINDING 1 : 5 T= 15 mm
23 1 M2 PEMASANGAN ACIAN DINDING
24 1 M2 PASANG DINDING BATU ANDESIT
25 1 M2 DAUN PINTU PANEL KAYU KAMPER BANJAR
26 1 M2 DAUN PINTU PLYWOOD RANGKAP, RANGKA EKSPOSED KAYU KAMPER BANJAR
27 1 M2 DAUN PINTU PLYWOOD 4 MM + FORMIKA 4 MM RANGKA EKSPOSED KAYU KAMPER BANJAR
28 1 M2 DAUN PINTU KACA RANGKA EKSPOSED KAYU KAMPER BANJAR TANPA KACA
29 1 M2 DAUN PINTU BESI PLAT TEBAL 2 MM RANGKAP (RANGKA BAJA SIKU)
30 1 M2 JALUSI BESI STRIP (2 x 3 MM)
31 1 M KUSEN ALUMINIUM
32 1 M2 DAUN PINTU KACA RANGKA ALUMUNIUM TANPA KACA
33 1 M2 PASANG KACA TEBAL 5 MM
34 1 M2 PASANG KACA TEBAL 8 MM
35 1 M2 PASANG KACA TEMPERRED TEBAL 10 MM
36 1 M2 PASANG KACA TEMPERRED TEBAL 12 MM
37 1 M2 PASANG KACA CERMIN TEBAL 5 MM
38 1 M2 RANGKA PLAFOND BESI HOLLOW 1x40.40.2mm, MODUL 60x60 cm
39 1 M2 RANGKA PLAFOND BESI HOLLOW 1x40.40.2mm, MODUL 60x60 cm (DROP CEILLING)
40 1 M2 PASANG PLAFOND GYPSUM 9 mm
41 1 M2 PASANGAN PLAFOND GYPSUM WET AREA 9 mm
42 1 M' PASANG LIST PROFIL PLAFOND GYPSUM
43 1 M2 PEMASANGAN LANTAI GRANIT TILE 60 x 60 CM POLISHED
44 1 M2 PEMASANGAN LANTAI GRANIT TILE 60 x 60 CM UNPOLISHED45 1 M2 PEMASANGAN LANTAI GRANIT TILE 30 x 60 CM POLISHED
46 1 M2 PEMASANGAN LANTAI KERAMIK 40 x 40 CM
47 1 M2 PEMASANGAN LANTAI KERAMIK 30 x 30 CM ANTI SLIP
48 1 M2 PEMASANGAN LANTAI KERAMIK 20 x 20 CM ANTI SLIP
49 1 M2 PEMASANGAN LANTAI KERAMIK 30 x 30 CM PUTIH
50 1 M2 PEMASANGAN LANTAI PEARLSTONE
51 1 M2 PEMASANGAN GRANIT ALAM
52 1 M2 PEMASANGAN DINDING KERAMIK 30 x 60 CM
53 1 M2 PEMASANGAN DINDING KERAMIK 20 x 40 CM
54 1 M' PEMASANGAN PLINT GRANIT TILE 10 x 60 CM
55 1 M' PEMASANGAN PLINT KERAMIK 10 x 40 CM
56 1 M' PEMASANGAN PLINT KERAMIK 10 x 30 CM
JUMLAH (RP)URAIAN PEKERJAAN
0
PEKERJAAN PEMBANGUNAN GEDUNG KANTOR BALAI PSDA Ws. CITARUM
JL. SMK 6 - SOEKARNO HATTA - KOTA BANDUNG
TAHUN 2016
No.
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
29/58
JUMLAH (RP)URAIAN PEKERJAANNo.
57 1 M' PEMASANGAN BORDER DINDING KERAMIK KM/WC 8 x 30 CM
58 1 M2 PEMASANGAN BORDER DINDING KERAMIK KM/WC 8 x 20 CM
59 1 M' PASANG STEPNOSING KERAMIK TILE 10/30
60 1 M2 PENGECATAN DINDING DAN PLAFOND INTERIOR
61 1 M2 PENGECATAN DINDING EKSTERIOR/WEATHER SHIELD
62 1 M2 PENGECATAN DINDING/LANTAI DENGAN CAT EPOXY
63 1 M2 PENGECATAN KAYU
64 1 M2 PENGECATAN BESI SECARA SEMPROT SISTEM 3 LAPIS CAT
65 1 M2 PEKERJAAN WATERPROOFING MEMBRAN66 1 M2 PASANG DOUBLE ALUMUNIUM FOIL
67 1 M2 PARTISI DOUBLE GYPSUM RANGKA METAL STUD
68 1 M' PASANG PLINT KAYU KAMPER 2x10
69 1 UNIT BAK KONTROL 100 X 100 X 50
70 1 M' PASANG SALURAN GRAVEL U - 25 CM
71 1 M' PASANG SALURAN GRAVEL U - 30 CM
72 1 M2 GLASSBOX uk. 200 x 200 mm
73 1 M2 PEKERJAAN LAPISAN PONDASI AGREGAT KELAS B (LPB)
74 1 M2 PEKERJAAN LAPISAN PONDASI AGREGAT KELAS A (LPA)
75 1 M2 PEKERJAAN LAPISAN AC/WC HOTMIX (t = 3 cm)
76 1 BH MEMASANG CLOSET DUDUK/MONOBLOCK
77 1 BH MEMASANG CLOSET JONGKOK
78 1 BH MEMASANG URINOIR
79 1 BH MEMASANG SEKAT URINOIR
80 1 BH MEMASANG WASTAFEL
81 1 BH MEMASANG KITCHENZINC
82 1 BH MEMASANG FLOORDRAIN
83 1 BH MEMASANG KRAN AIR
84 1 BH MEMASANG JET WASHER
85 1 UNIT CUBICLE PARTISI TOILET LENGKAP ASESORIES
86 1 M' RAILING TANGGA STAINLESS
87 1 M' HAND RAILING TANGGA STAINLESS
88 1 M' RAILING PIPA BSP
B ANALISA STRUKTUR
1 1 M3 BETON COR 1 : 3 : 5 (LANTAI KERJA)
2 1 M3 COR BETON SITE MIX K-175
3 1 M3 COR BETON SITE MIX K-300
4 1 M3 COR BETON READY MIX K-300 DAN POMPA BETON5 1 M3 BEKISTING PAPAN (2 X PAKAI)
6 1 M2 BEKISTING KOLOM MULTIPLEKS 9 mm (2 X PAKAI)
7 1 M2 BEKISTING BALOK MULTIPLEKS 9 mm (2 X PAKAI)
8 1 M2 BEKISTING PLAT LANTAI MULTIPLEKS 9 mm (2 X PAKAI)
9 1 M2 BEKISTING TANGGA MULTIPLEKS 9 mm (2 X PAKAI)
10 1 M2 BEKISTING DINDING MULTIPLEKS 9 mm (2 X PAKAI)
11 1 KG MENGERJAKAN BESI BETON ULIR U-39
12 1 KG MENGERJAKAN BESI BETON ULIR U-24
13 1 KG BESI PROFIL/SIKU/PIPA/PLAT
14 1 KG MENGERJAKAN BESI WIRE MESH
15 1 M KOLOM PRAKTIS 11/11 CM, K-175
16 1 M BALOK PRAKTIS DAN SLOOF PRAKTIS 12/15 CM, K-175
17 1 M3 TOPI BETON DAN MEJA BETON T=10 CM, K-175
C ANALISA KUSEN
1 1 UNIT PEKERJAAN KUSEN DAN DAUN PINTU KACA ALLUMUNIUM TYPE P1
2 1 UNIT PEKERJAAN KUSEN DAN DAUN PINTU KACA ALLUMUNIUM TYPE P2
3 1 UNIT PEKERJAAN KUSEN ALLUMUNIUM DAN DAUN PINTU TYPE P3
4 1 UNIT PEKERJAAN KUSEN DAN DAUN PINTU KACA ALLUMUNIUM TYPE P4
5 1 UNIT PEKERJAAN KUSEN ALLUMUNIUM DAN DAUN PINTU KAYU TYPE P5
6 1 UNIT PEKERJAAN KUSEN ALLUMUNIUM DAN DAUN PINTU KAYU TYPE P6
7 1 UNIT PEKERJAAN KUSEN ALLUMUNIUM DAN DAUN PINTU KAYU TYPE P7
8 1 UNIT PEKERJAAN KUSEN ALUMUNIUM DAN DAUN PINTU JENDELA KAYU TYPE P8
9 1 UNIT PEKERJAAN KUSEN ALLUMUNIUM DAN DAUN PINTU KAYU SHAFT
10 1 UNIT PEKERJAAN KUSEN JENDELA TYPE J1
11 1 UNIT PEKERJAAN KUSEN JENDELA TYPE J1B
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
30/58
JUMLAH (RP)URAIAN PEKERJAANNo.
12 1 UNIT PEKERJAAN KUSEN JENDELA TYPE J2
13 1 UNIT PEKERJAAN KUSEN JENDELA TYPE J3
14 1 UNIT PEKERJAAN KUSEN JENDELA TYPE J4
15 1 UNIT PEKERJAAN KUSEN JENDELA TYPE J5
16 1 UNIT PEKERJAAN KUSEN JENDELA TYPE J6
17 1 UNIT PEKERJAAN KUSEN BOUVENLICH TYPE B1
18 1 UNIT PEKERJAAN KUSEN BOUVENLICH TYPE B2
19 1 UNIT PEKERJAAN KUSEN BOUVENLICH TYPE B3
20 1 UNIT PINTU BESI BAJA PANIC EXIT SETARA KEND (PABRIKAN) PB3
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
31/58
1 1 M' PENGUKURAN DAN PEMASANGAN BOUWPLANK -
Kayu Balok 5/7 m3 0.1200
Paku 2"-3" Kg 0.0200
Kayu Papan 3/20 m3 0.0070
Pekerja Orang 0.1000
Tukang Kayu Orang 0.1000
Kepala Tukang Orang 0.0100
Mandor Orang 0.0050
Jumlah -
Jasa Kontraktor -
2 1 M2 KANTOR SEMENTARA LANTAI PLESTERAN -
Dolken Kayu 400 CM Batang 1.2500
Kayu m3 0.1800
Paku Biasa Kg 0.0800
Besi Strip Kg 1.1000
Semen Portland Kg 35.0000Pasir Pasang m3 0.1500
Pasir Beton m3 0.1000
Koral Beton m3 0.1500
Bata Merah Bh 30.0000
Seng Plat Lbr 0.2500
Jendela Naco Bh 0.2000
Kaca Polos m2 0.0800
Kunci Tanam Bh 0.1500
Plywood 4mm Lbr 0.0600
Pekerja Orang 2.0000
Tukang Kayu Orang 2.0000
Tukang Batu Orang 1.0000
Kepala Tukang Orang 0.3000
Mandor Orang 0.0500
Jumlah -Jasa Kontraktor -
3 1 M2 GUDANG SEMEN DAN PERALATAN -
Dolken Kayu 400 CM Batang 1.7000
Kayu m3 0.2100
Paku Biasa Kg 0.3000
Semen Portland kg 10.5000
Pasir Beton m3 0.0300
Koral Beton m3 0.0500
Seng Gelombang Lbr 1.5000
Seng Plat Lbr 0.2500
Pekerja OH 1.0000
Tukang Kayu OH 2.0000
Kepala Tukang OH 0.2000
Mandor OH 0.0500
Jumlah -
Jasa Kontraktor -
TOTAL (RP)
ANALISA HARGA PEKERJAAN
PEKERJAAN PEMBANGUNAN GEDUNG KANTOR BALAI PSDA Ws. CITARUM
JL. SMK 6 - SOEKARNO HATTA - KOTA BANDUNG
TAHUN 2016
No. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH (RP)
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
32/58
TOTAL (RP)No. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH (RP)
4 1 M1 PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 M -
Dolken Kayu 400 CM Batang 1.2500
Semen Portland Kg 2.5000
Seng Gelombang Lbr 1.2000
Pasir Beton m 0.0050
Koral Beton m 0.0090
Kayu 5/7 m 0.0720
Paku Biasa 2"-5" Kg 0.0600
Meni Besi Liter 0.4500
Pekerja Orang 0.2000
Tukang Kayu Orang 0.4000
Kepala Tukang Orang 0.0200
Mandor Orang 0.0200
Jumlah -
Jasa Kontraktor -
5 1 M2 PEMBERSIHAN DAN PERATAAN LAPANGAN -
Pekerja Orang 0.1000
Mandor Orang 0.0500
Jumlah -
Jasa Kontraktor -
6 1 M3 PEMBONGKARAN DINDING BATA -
Pekerja Orang 6.6670
Mandor Orang 0.3330
Jumlah -
Jasa Kontraktor -
7 1 UNIT PAPAN NAMA PROYEK 80 X 120 CM -
Kayu Meranti m3 0.0500
Seng Plat m2 1.6200
Paku kg 0.6000
Cat Kayu kg 1.5000
Beton Cor 1 : 2 : 3 m3 0.1000
Pekerja Orang 2.0000
Tukang Kayu Orang 1.0000
Tukang Cat Orang 1.0000
Mandor Orang 1.0000
Jumlah -Jasa Kontraktor -
8 1 M3 GALIAN TANAH BIASA KEDALAMAN MAX 1 M -
Pekerja Orang 0.7500
Mandor Orang 0.2500
Jumlah -
Jasa Kontraktor -
9 1 M3 GALIAN TANAH BIASA KEDALAMAN MAX 2 M -
Pekerja Orang 0.9000
Mandor Orang 0.0450
Jumlah -
Jasa Kontraktor -
10 1 M3 GALIAN TANAH DENGAN ALAT BERAT -Pekerja Orang 0.1088
Mandor Orang 0.0544
Excavator 80 -140 Hp Jam 0.0400
Dump truk Jam 0.0040
Jumlah -
Jasa Kontraktor -
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
33/58
TOTAL (RP)No. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH (RP)
11 1 M3 PEKERJAAN TIMBUNAN TANAH DARI LUAR -
Tanah timbunan m3 1.2000
Pekerja Orang 0.3480
Mandor Orang 0.0872
Excavator 80 - 140 HP jam 0.0109
Dump truck (Kap. 3,5 T) jam 0.5143
Jumlah -
Jasa Kontraktor -
12 1 M3 URUGAN KEMBALI TANAH BEKAS GALIAN -
Pekerja Orang 0.5000
Mandor Orang 0.0500
Jumlah -
Jasa Kontraktor -
13 1 M3 BUANGAN TANAH KELUAR LOKASI SEJAUH 30 METER -
Pekerja Orang 0.3300
Mandor Orang 0.0100
Jumlah -
Jasa Kontraktor -
14 1 M3 PEMADATAN TANAH (PER 20 CM) -
Pekerja Orang 0.3300
Mandor Orang 0.0100
Jumlah -
Jasa Kontraktor -
15 1 M3 MENGURUG PASIR URUG -
Pasir Urug m3 1.2000
Pekerja Orang 0.3000
Mandor Orang 0.0100
Jumlah -
Jasa Kontraktor -
16 1 M3 URUGAN SIRTU PADAT -
Sirtu m3 1.2000
Pekerja Orang 0.2500
Mandor Orang 0.0250
Jumlah -Jasa Kontraktor -
17 1 M3 PASANG PONDASI BATU BELAH (1PC : 5PS) -
Batu Belah m3 1.2000
Semen kg 136.0000
Pasir Pasang m3 0.5440
Pekerja Orang 1.5000
Tukang Batu Orang 0.7500
Kepala Tukang Orang 0.0750
Mandor Orang 0.0750
Jumlah -
Jasa Kontraktor -
18 1 M3 PASANG BATU KOSONG / AANSTAMPING -
Batu Belah m3 1.2000Pasir Urug m3 0.4320
Pekerja Orang 0.7800
Tukang Batu Orang 0.3900
Kepala Tukang Batu Orang 0.0390
Mandor Orang 0.0390
Jumlah -
Jasa Kontraktor -
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
34/58
TOTAL (RP)No. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH (RP)
19 1 M2 PASANG DINDING BATA MERAH 1/2 BT (1PC : 3PS) -
Bata Merah Buah 70.0000
Semen PC 50kg Kg 14.3700
Pasir Pasang m3 0.0400
Pekerja Orang 0.3000
Tukang Batu Orang 0.1000
Kepala Tukang Orang 0.0100
Mandor Orang 0.0150
Jumlah -
Jasa Kontraktor -
20 1 M2 PASANG DINDING BATA MERAH 1/2 BT (1PC : 5PS) -
Bata Merah Buah 70.0000
Semen PC 50kg kg 9.6800
Pasir Pasang m3 0.0450
Pekerja Orang 0.3000
Tukang Batu Orang 0.1000
Kepala Tukang Orang 0.0100
Mandor Orang 0.0150
Jumlah -
Jasa Kontraktor -
21 1 M2 PLESTERAN DINDING 1 : 3 T= 15 mm -
Semen PC 50kg Kg 7.7760
Pasir Pasang m3 0.0230
Pekerja Orang 0.3000
Tukang Batu Orang 0.1500
Kepala Tukang Orang 0.0150
Mandor Orang 0.0150
Jumlah -
Jasa Kontraktor -
22 1 M2 PLESTERAN DINDING 1 : 5 T= 15 mm -
Semen PC 50kg Kg 5.1840
Pasir Pasang m3 0.0260
Pekerja Orang 0.3000
Tukang Batu Orang 0.1500
Kepala Tukang Orang 0.0150
Mandor Orang 0.0150Jumlah -
Jasa Kontraktor -
23 1 M2 PEMASANGAN ACIAN DINDING -
Semen PC 50kg Kg 3.2500
Pekerja Orang 0.2000
Tukang Batu Orang 0.1000
Kepala Tukang Orang 0.0100
Mandor Orang 0.0100
Jumlah -
Jasa Kontraktor -
24 1 M2 PASANG DINDING BATU ANDESIT -
Batu andesit m2 1.1000
Semen PC 50kg kg 11.7500Pasir Pasang m3 0.0350
Pekerja Orang 0.7000
Tukang Batu Orang 0.3500
Kepala Tukang Orang 0.0350
Mandor Orang 0.0350
Jumlah -
Jasa Kontraktor -
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
35/58
TOTAL (RP)No. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH (RP)
25 1 M2 DAUN PINTU PANEL KAYU KAMPER BANJAR -
Papan Kayu m3 0.0400
Lem kayu kg 0.5000
Pekerja org 1.0000
Tukang kayu org 2.0000
Kepala tukang org 0.3000
Mandor org 0.0500
Jumlah -
Jasa Kontraktor -
26 1 M2 DAUN PINTU PLYWOOD RANGKAP, RANGKA EKSPOSED KAYU KAMPER BANJAR -
Papan kayu m3 0.0256
Paku 1 cm - 2,5 cm kg 0.0300
Lem kayu kg 0.5000
Plywood 4 mm lbr 1.3750
HPL WARNA lbr 1.3750
Pekerja org 0.8000
Tukang kayu org 2.4000
Kepala tukang org 0.2400
Mandor org 0.0400
Jumlah -
Jasa Kontraktor -
27 1 M2 DAUN PINTU PLYWOOD 4 MM + FORMIKA 4 MM RANGKA EKSPOSED KAYU KAMPER BANJAR -
Kayu Kamper , Papan m3 0.0256
Paku 1 cm - 2,5 cm kg 0.0300
Lem kayu kg 0.5000
Plywood 4 mm lbr 0.6875
Formika 4 mm lbr 0.6875
Pekerja org 0.8000
Tukang kayu org 2.4000
Kepala tukang org 0.2400
Mandor org 0.0400
Jumlah -
Jasa Kontraktor -
28 1 M2 DAUN PINTU KACA RANGKA EKSPOSED KAYU KAMPER BANJAR TANPA KACA -
Papan kayu m3 0.0256
Paku 1 cm - 2,5 cm kg 0.0300Lem kayu kg 0.5000
HPL WARNA lbr 0.6875
Pekerja org 0.8000
Tukang kayu org 2.4000
Kepala tukang org 0.2400
Mandor org 0.0400
Jumlah -
Jasa Kontraktor -
29 1 M2 DAUN PINTU BESI PLAT TEBAL 2 MM RANGKAP (RANGKA BAJA SIKU) -
Besi siku L 30.30.3 kg 15.0000
Besi plat baja kg 32.8000
Kawat las listrik kg 0.0500
Pekerja org 1.0500
Tukang las org 1.0500Kepala tukang org 0.1050
Mandor org 0.0520
Jumlah -
Jasa Kontraktor -
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
36/58
TOTAL (RP)No. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH (RP)
30 1 M2 JALUSI BESI STRIP (2 x 3 MM) -
Besi strip kg 6.1770
Kawat las listrik kg 0.0500
Pekerja org 1.6700
Tukang las org 1.6700
Kepala tukang org 0.1670
Mandor org 0.0830
Jumlah -
Jasa Kontraktor -
31 1 M KUSEN ALUMINIUM -
Kusen alumunium 4" warna m' 1.1000
fiser + skruf S=8mm, pj=2" bh 2.0000
Sealant tb 0.0600
Pekerja Oh 0.0430
Tukang Alumunium Oh 0.0430
Kepala Tukang Oh 0.0043
Mandor Oh 0.0021
Jumlah -
Jasa Kontraktor -
32 1 M2 DAUN PINTU KACA RANGKA ALUMUNIUM TANPA KACA -
Kusen alumunium 4" warna m' 1.1000
fiser + skruf S=8mm, pj=2" bh 2.0000
Silikon tb 0.0600
Pekerja Oh 0.0430
Tukang Alumunium Oh 0.0430
Kepala Tukang Oh 0.0043
Mandor Oh 0.0021
Jumlah -
Jasa Kontraktor -
33 1 M2 PASANG KACA TEBAL 5 MM -
Kaca bening t=5 mm m' 1.1000
Sealant kg 0.0500
Pekerja Oh 0.0150
Tukang Kayu Oh 0.1500
Kepala Tukang Oh 0.0150
Mandor Oh 0.0080Jumlah -
Jasa Kontraktor -
34 1 M2 PASANG KACA TEBAL 8 MM -
Kaca bening t=8 mm m' 1.1000
Sealant kg 0.0700
Pekerja Oh 0.0170
Tukang Kayu Oh 0.1700
Kepala Tukang Oh 0.0170
Mandor Oh 0.0090
Jumlah -
Jasa Kontraktor -
35 1 M2 PASANG KACA TEMPERRED TEBAL 10 MM -
Kaca temperred t=10 mm m' 1.1000Sealant kg 0.0700
Pekerja Oh 0.0170
Tukang Kayu Oh 0.1700
Kepala Tukang Oh 0.0170
Mandor Oh 0.0090
Jumlah -
Jasa Kontraktor -
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
37/58
TOTAL (RP)No. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH (RP)
36 1 M2 PASANG KACA TEMPERRED TEBAL 12 MM -
Kaca temperred bening t=12 mm m' 1.1000
Sealant kg 0.0700
Pekerja Oh 0.0170
Tukang Kayu Oh 0.1700
Kepala Tukang Oh 0.0170
Mandor Oh 0.0090
Jumlah -
Jasa Kontraktor -
37 1 M2 PASANG KACA CERMIN TEBAL 5 MM -
Kaca cermin t=5 mm m' 1.1000
Pekerja Oh 0.0150
Tukang Kayu Oh 0.1500
Kepala Tukang Oh 0.0150
Mandor Oh 0.0080
Jumlah -
Jasa Kontraktor -
38 1 M2 RANGKA PLAFOND BESI HOLLOW 1x40.40.2mm, MODUL 60x60 cm -
Rangka hollow 40.40.2 mm m' 4.0000
Assesoris (perkuatan, las, skrup, dll) 100%xrangka Ls 1.0000
Pekerja Orang 0.3500
Tukang besi Orang 0.3500
Kepala tukang Orang 0.0350
Mandor Orang 0.0180
Jumlah -
Jasa Kontraktor -
39 1 M2 RANGKA PLAFOND BESI HOLLOW 1x40.40.2mm, MODUL 60x60 cm (DROP CEILLING) -
Rangka hollow 40.40.2 mm m' 6.0000
Assesoris (perkuatan, las, skrup, dll) 100%xrangka Ls 1.0000
Pekerja Orang 0.3500
Tukang besi Orang 0.3500
Kepala tukang Orang 0.0350
Mandor Orang 0.0180
Jumlah -
Jasa Kontraktor -
40 1 M2 PASANG PLAFOND GYPSUM 9 mm -
Gypsum 9mm lbr 0.3640
Paku skrup kg 0.1100
Pekerja Orang 0.1000
Tukang Kayu Orang 0.0500
Kep. Tukang Kayu Orang 0.0050
Mandor Orang 0.0050
Jumlah -
Jasa Kontraktor -
41 1 M2 PASANGAN PLAFOND GYPSUM WET AREA 9 mm -
Gypsum wet area 9 mm lbr 0.3640
Paku skrup kg 0.1100
Pekerja Orang 0.1000
Tukang Kayu Orang 0.0500Kep. Tukang Kayu Orang 0.0050
Mandor Orang 0.0050
Jumlah -
Jasa Kontraktor -
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
38/58
TOTAL (RP)No. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH (RP)
42 1 M' PASANG LIST PROFIL PLAFOND GYPSUM -
List Profil Gypsum m 1.0500
Cornise Compound kg 0.3000
Pekerja Orang 0.0500
Tukang Kayu Orang 0.0500
Kepala Tukang Orang 0.0050
Mandor Orang 0.0030
Jumlah -
Jasa Kontraktor -
43 1 M2 PEMASANGAN LANTAI GRANIT TILE 60 x 60 CM POLISHED -
Lantai granit tile 60x60 cm polished m2 1.1000
Semen PC 50 kg kg 9.8000
Semen Warna Kg 1.3000
Pasir Pasang m3 0.0450
Pekerja Orang 0.2500
Tukang Batu Orang 0.1250
Kepala Tukang Orang 0.0130
Mandor Orang 0.0130
Jumlah -
Jasa Kontraktor -
44 1 M2 PEMASANGAN LANTAI GRANIT TILE 60 x 60 CM UNPOLISHED -
Lantai granit tile 60x60 cm unpolished m2 1.1000
Semen PC 50 kg kg 9.8000
Semen Warna Kg 1.3000
Pasir Pasang m3 0.0450
Pekerja Orang 0.2500
Tukang Batu Orang 0.1250
Kepala Tukang Orang 0.0130
Mandor Orang 0.0130
Jumlah -
Jasa Kontraktor -
45 1 M2 PEMASANGAN LANTAI GRANIT TILE 30 x 60 CM POLISHED -
Lantai granit tile 30x60 cm polished m2 1.1000
Semen PC 50 kg kg 9.8000
Semen Warna Kg 1.3000
Pasir Pasang m3 0.0450Pekerja Orang 0.2500
Tukang Batu Orang 0.1250
Kepala Tukang Orang 0.0130
Mandor Orang 0.0130
Jumlah -
Jasa Kontraktor -
46 1 M2 PEMASANGAN LANTAI KERAMIK 40 x 40 CM -
Keramik 40 x 40 m2 1.1000
Semen PC 50 kg kg 8.1900
Semen Warna Kg 1.6200
Pasir Pasang m3 0.0450
Pekerja Orang 0.7000
Tukang Batu Orang 0.3500
Kepala Tukang Orang 0.0350Mandor Orang 0.0350
Jumlah -
Jasa Kontraktor -
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
39/58
TOTAL (RP)No. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH (RP)
47 1 M2 PEMASANGAN LANTAI KERAMIK 30 x 30 CM ANTI SLIP -
Keramik 30 x 30 anti slip m2 1.1000
Semen PC 50 kg kg 10.0000
Semen Warna Kg 1.5000
Pasir Pasang m3 0.0450
Pekerja Orang 0.7000
Tukang Batu Orang 0.3500
Kepala Tukang Orang 0.0350
Mandor Orang 0.0350
Jumlah -
Jasa Kontraktor -
48 1 M2 PEMASANGAN LANTAI KERAMIK 20 x 20 CM ANTI SLIP -
Keramik 20 x 20 anti slip m2 1.1000
Semen PC 50 kg Kg 10.4000
Semen Warna Kg 1.6200
Pasir Pasang m3 0.0450
Pekerja Orang 0.7000
Tukang Batu Orang 0.3500
Kepala Tukang Orang 0.0350
Mandor Orang 0.0350
Jumlah -
Jasa Kontraktor -
49 1 M2 PEMASANGAN LANTAI KERAMIK 30 x 30 CM PUTIH -
Keramik 30 x 30 m2 1.1000
Semen PC 50 kg Kg 10.4000
Semen Warna Kg 1.6200
Pasir Pasang m3 0.0450
Pekerja Orang 0.7000
Tukang Batu Orang 0.3500
Kepala Tukang Orang 0.0350
Mandor Orang 0.0350
Jumlah -
Jasa Kontraktor -
50 1 M2 PEMASANGAN LANTAI PEARLSTONE -
Batu pearlstone m2 1.1000
Semen PC 50 kg Kg 8.1900Semen Warna Kg 1.6200
Pasir Pasang m3 0.0450
Pekerja Orang 0.7000
Tukang Batu Orang 0.3500
Kepala Tukang Orang 0.0350
Mandor Orang 0.0350
Jumlah -
Jasa Kontraktor -
51 1 M2 PEMASANGAN GRANIT ALAM -
Granit alam m2 1.0600
Semen PC 50kg kg 12.4400
Semen warna Kg 0.6500
Pasir Pasang m3 0.0250
Paku 12 cm bh 3.0300Pekerja Orang 1.3000
Tukang Batu Orang 0.6500
Kepala Tukang Orang 0.0650
Mandor Orang 0.0650
Jumlah -
Jasa Kontraktor -
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
40/58
TOTAL (RP)No. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH (RP)
52 1 M2 PEMASANGAN DINDING KERAMIK 30 x 60 CM -
Dinding keramik 30 x 60 cm m2 1.0500
Semen PC 50 kg Kg 9.3000
Semen Warna Kg 1.9400
Pasir Pasang m3 0.0180
Pekerja Orang 0.9000
Tukang Batu Orang 0.4500
Kepala Tukang Orang 0.0450
Mandor Orang 0.0450
Jumlah -
Jasa Kontraktor -
53 1 M2 PEMASANGAN DINDING KERAMIK 20 x 40 CM -
Dinding keramik 20 x 40 cm M2 1.0500
Semen PC 50kg kg 9.3000
Semen warna Kg 1.9400
Pasir Pasang m3 0.0180
Pekerja Orang 0.9000
Tukang Batu Orang 0.4500
Kepala Tukang Orang 0.0450
Mandor Orang 0.0450
Jumlah -
Jasa Kontraktor -
54 1 M' PEMASANGAN PLINT GRANIT TILE 10 x 60 CM -
Plint granite tile 10x60 BH 1.7700
Semen PC 50kg kg 1.1400
Semen warna Kg 0.1000
Pasir Pasang m3 0.0030
Pekerja Orang 0.0900
Tukang Batu Orang 0.0900
Kepala Tukang Orang 0.0090
Mandor Orang 0.0050
Jumlah -
Jasa Kontraktor -
55 1 M' PEMASANGAN PLINT KERAMIK 10 x 40 CM -
Plint keramik 10x40 BH 2.6500
Semen PC 50kg kg 1.1400Semen warna Kg 0.1000
Pasir Pasang m3 0.0030
Pekerja Orang 0.0900
Tukang Batu Orang 0.0900
Kepala Tukang Orang 0.0090
Mandor Orang 0.0050
Jumlah -
Jasa Kontraktor -
56 1 M' PEMASANGAN PLINT KERAMIK 10 x 30 CM -
Plint keramik 10x30 BH 3.5300
Semen PC 50kg kg 1.1400
Semen warna Kg 0.1000
Pasir Pasang m3 0.0030
Pekerja Orang 0.0900Tukang Batu Orang 0.0900
Kepala Tukang Orang 0.0090
Mandor Orang 0.0050
Jumlah -
Jasa Kontraktor -
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
41/58
TOTAL (RP)No. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH (RP)
57 1 M' PEMASANGAN BORDER DINDING KERAMIK KM/WC 8 x 30 CM -
Border dinding keramik KM/WC BH 3.4965
Semen PC 50kg kg 1.1400
Semen warna Kg 0.0250
Pasir Pasang m3 0.0030
Pekerja Orang 0.0900
Tukang Batu Orang 0.0900
Kepala Tukang Orang 0.0350
Mandor Orang 0.0350
Jumlah -
Jasa Kontraktor -
58 1 M2 PEMASANGAN BORDER DINDING KERAMIK KM/WC 8 x 20 CM -
Border dinding keramik KM/WC BH 5.3000
Semen PC 50kg kg 1.1400
Semen warna Kg 0.0250
Pasir Pasang m3 0.0030
Pekerja Orang 0.0900
Tukang Batu Orang 0.0900
Kepala Tukang Orang 0.0350
Mandor Orang 0.0350
Jumlah -
Jasa Kontraktor -
59 1 M' PASANG STEPNOSING KERAMIK TILE 10/30 -
Step nosing granit keramik tile bh 1.7535
Semen PC 50 kg kg 9.8000
Semen Warna Kg 1.3000
Pasir Pasang m3 0.0450
Pekerja Orang 0.2500
Tukang Batu Orang 0.1250
Kepala Tukang Orang 0.0130
Mandor Orang 0.0130
Jumlah -
Jasa Kontraktor -
60 1 M2 PENGECATAN DINDING DAN PLAFOND INTERIOR -
Plamur Kg 0.1000
Cat dasar interior Kg 0.1000Cat penutup Kg 0.2600
Pekerja Orang 0.0200
Tukang Cat Orang 0.0630
Kepala Tukang Orang 0.0063
Mandor Orang 0.0030
Jumlah -
Jasa Kontraktor -
61 1 M2 PENGECATAN DINDING EKSTERIOR/WEATHER SHIELD -
Cat dasar ekterior Kg 0.1000
Cat penutup Kg 0.2600
Pekerja Orang 0.0200
Tukang Cat Orang 0.0630
Kepala Tukang Orang 0.0063
Mandor Orang 0.0030Jumlah -
Jasa Kontraktor -
62 1 M2 PENGECATAN DINDING/LANTAI DENGAN CAT EPOXY -
Cat dasar epoxy Kg 0.1000
Cat epoxy Kg 0.2600
Pekerja Orang 0.0200
Tukang Cat Orang 0.0630
Kepala Tukang Orang 0.0063
Mandor Orang 0.0030
Jumlah -
Jasa Kontraktor -
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
42/58
TOTAL (RP)No. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH (RP)
63 1 M2 PENGECATAN KAYU -
Meni kayu kg 0.2000
Plamir kayu kg 0.1500
Cat dasar kg 0.1700
Cat kayu kg 0.3500
Kuas bh 0.0100
Pengencer kg 0.0300
Ampelas Lbr 0.2000
Pekerja Orang 0.0700
Tukang Cat Orang 0.1050
Kepala Tukang Orang 0.0040
Mandor Orang 0.0030
Jumlah -
Jasa Kontraktor -
64 1 M2 PENGECATAN BESI SECARA SEMPROT SISTEM 3 LAPIS CAT -
Cat besi kg 0.3000
Pengencer liter 0.0100
Pekerja Orang 0.4000
Tukang Cat Orang 0.7000
Kepala Tukang Orang 0.0700
Mandor Orang 0.0200
Jumlah -
Jasa Kontraktor -
65 1 M2 PEKERJAAN WATERPROOFING MEMBRAN -
Watter profing membrane t=4 mm m 1.0500
Material bantu ls 1.0000
Pekerja Orang 0.1000
Tukang kayu Orang 0.0500
Kepala Tukang Orang 0.0050
Mandor Orang 0.0010
Jumlah -
Jasa Kontraktor -
66 1 M2 PASANG DOUBLE ALUMUNIUM FOIL -
Alumunium foil double m2 2.1000
Pekerja Oh 0.1500
tukang kayu Oh 0.0500kepala tukang Oh 0.0050
Mandor Oh 0.0080
Jumlah -
Jasa Kontraktor -
67 1 M2 PARTISI DOUBLE GYPSUM RANGKA METAL STUD -
Panel Gypsum 9 mm lbr 0.6944
Rangka metal stud m' 5.0000
Pekerja org 0.1969
Tukang Kayu org 0.1050
Kep. Tukang Kayu org 0.0394
Mandor org 0.0105
Jumlah -
Jasa Kontraktor -
68 1 M' PASANG PLINT KAYU KAMPER 2x10 -
Papan kayu m3 0.0030
Paku/skrup 5 cm kg 0.0500
Pekerja orang 0.1200
Tukang Kayu orang 0.1200
Kepala Tukang orang 0.0120
Mandor orang 0.0060
Jumlah -
Jasa Kontraktor -
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
43/58
TOTAL (RP)No. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH (RP)
69 1 UNIT BAK KONTROL 100 X 100 X 50 -
Lantai Kerja t. 10 cm m3 0.1000
Pasir Urug t. 10 cm m3 0.1000
Pasangan 1/2 bata 1:3 m2 1.1400
Plesteren 1:3 m2 2.2800
Acian m2 2.2800
Galian m3 1.1520
Urugan kembali m3 0.6520
Jumlah -
70 1 M' PASANG SALURAN GRAVEL U - 25 CM -
Galian Tanah m3 0.0450
Urugan pasir m3 0.0500
Grevel U - 25 cm bh 3.3333
Pas. 1/2 Bata 1 : 3 m3 0.0900
Plesteran + Acian 1 : 3 m2 0.8000
Jumlah -
71 1 M' PASANG SALURAN GRAVEL U - 30 CM -
Galian Tanah m3 0.0450
Urugan pasir m3 0.0500
Grevel U - 30 cm bh 3.3333
Pas. 1/2 Bata 1 : 3 m3 0.0900
Plesteran + Acian 1 : 3 m2 0.8000
Jumlah -
72 1 M2 GLASSBOX uk. 200 x 200 mm -
Glassbox uk. 200 x 200 mm bh 25.0000
Spesi 1Pc : 2Ps
- Semen Portland kg 16.3500
- Pasir Pasang m 0.0260
Sealant ls 1.0000
Jumlah -
Jasa Kontraktor -
73 1 M2 PEKERJAAN LAPISAN PONDASI AGREGAT KELAS B (LPB) -
Matrial agregat B m 1.2586
Pekerja Oh 0.3968
Mandor Oh 0.5680Wheel loader jam 0.0710
Dump truck jam 0.5022
Motor grader jam 0.0430
Tandem roller jam 0.0134
Water tanker jam 0.0141
Jumlah -
Jasa Kontraktor -
74 1 M2 PEKERJAAN LAPISAN PONDASI AGREGAT KELAS A (LPA) -
Matrial agregat A m 1.2586
Pekerja Oh 0.3968
Mandor Oh 0.5680
Wheel loader jam 0.0710
Dump truck jam 0.5022
Motor grader jam 0.0430Tandem roller jam 0.0134
Water tanker jam 0.0141
Jumlah -
Jasa Kontraktor -
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
44/58
TOTAL (RP)No. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH (RP)
75 1 M2 PEKERJAAN LAPISAN AC/WC HOTMIX (t = 3 cm) -
Batu pecah mesin 1 - 2 cm m 0.7710
Pasir aspal m 0.7450
Semen kg 49.1700
Asphalt ton 0.0540
Anti stripping agent kg 0.1600
Pekerja org 1.6064
Mandor org 0.1608
Wheel loader Jam 0.0119
AMP Jam 0.0201
Genset Jam 0.0201
Dump Truck Jam 0.3698
Asphalt finisher Jam 0.0137
Tandem roller Jam 0.0135
Pnematic tire roller Jam 0.0058
Jumlah -
Harga per M2 (Jumlah/33,33) -
Jasa Kontraktor -
76 1 BH MEMASANG CLOSET DUDUK/MONOBLOCK -
Closet duduk Unit 1.0000
Perlengkapan (6% dari harga barang) Ls 0.0600
Pekerja org 0.2033
Mandor org 0.0032
Jumlah -
Jasa Kontraktor -
77 1 BH MEMASANG CLOSET JONGKOK -
Closet jongkok Unit 1.0000
Semen portland kg 6.0000
Pasir pasang m3 0.0100
Pekerja org 0.2033
Mandor org 0.0032
Jumlah -
Jasa Kontraktor -
78 1 BH MEMASANG URINOIR -
Urinoir Unit 1.0000
Semen portland kg 6.0000Pasir pasang m3 0.0100
Perlengkapan (30% dari harga barang) Ls 0.3000
Pekerja org 0.2033
Mandor org 0.0032
Jumlah -
Jasa Kontraktor -
79 1 BH MEMASANG SEKAT URINOIR -
Sekat urinoir Unit 1.0000
Semen portland kg 6.0000
Pasir pasang m3 0.0100
Perlengkapan (30% dari harga barang) Ls 0.3000
Pekerja org 0.2033
Mandor org 0.0032
Jumlah -Jasa Kontraktor -
80 1 BH MEMASANG WASTAFEL -
Wastafel Unit 1.0000
Semen portland kg 6.0000
Pasir pasang m3 0.0100
Perlengkapan (12% dari harga barang) Ls 0.1200
Pekerja org 0.2033
Mandor org 0.0032
Jumlah -
Jasa Kontraktor -
-
7/25/2019 Bab.XIII. Daftar Kuantitas dan Harga Citarum.pdf
45/58
TOTAL (RP)No. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH (RP)
81 1 BH MEMASANG KITCHENZINC -
Kitchenzinc Unit 1.0000
Pekerja org 0.0300
Mandor org 0.0150
Jumlah -
Jasa Kontraktor -
82 1 BH MEMASANG FLOORDRAIN -
Floor drain Unit 1.0000
Pekerja org 0.0100
Mandor org 0.0050
Jumlah -
Jasa Kontraktor -
83 1 BH MEMASANG KRAN AIR -
Kran air Unit 1.0000
Sealtape bh 0.0250
Pekerja org 0.0100
Mandor org 0.0050
Jumlah -
Jasa Kontraktor -
84 1 BH MEMASANG JET WASHER -
Kran air Unit 1.0000
Sealtape bh 0.0250
Pekerja org 0.0100
Mandor org 0.0050
Jumlah -
Jasa Kontraktor -
85 1 UNIT CUBICLE PARTISI TOILET LENGKAP ASESORIES -
Partisi Phenolic resin Board tebal 12mm ls 1.0000
Pintu Phenolic resin Board 800x1800x12 mm
Door hardware stainless steel accessories
Rangka frame alumunium
Kaki pedestal dan Screw conection stainless steel
Upah kerja ls 1.0000
Jumlah -
Jasa Kontraktor -
86 1 M' RAILING TANGGA STAINLESS -
Pipa Stainless Steel 2 1/2" m' 1.7000
Pipa Stainless Steel 1/2" m' 3.0000
Asesoris + baut (5% dari bahan) Ls 0.0500
Upah Pabrikasi & Stel (5% dari bahan) Ls 0.0500
Jumlah -
Jasa Kontraktor -
87 1 M' HAND RAILING TANGGA STAINLESS -
Pipa Stainless Steel 2 1/2" m' 1.0000
Asesoris + baut (5% dari bahan) Ls 0.0500
Upah Pabrikasi & Stel (5% dari bahan) Ls 0.0500
Jumlah -
Jasa Kontraktor -