DAFTAR HARGA SATUAN PEKERJAAN ( UNIT PRICE )ANALISA a Anlisa BOW F.1 1 M3 Mengerjakan Rangka Bawah Kayu Ulin 0,2500 Oh Mandor 0,7500 Oh Kepala Tukang 7,5000 Oh Tukang Kayu 5,0000 Oh Pembantu Tukang 1,1000 M3 M3 Kayu Ulin 5,0000 Kg Kg Paku Ulin 124.540,00 110.085,00 95.617,00 81.175,00 8.641.300,00 23.400,00 sub total 31.135,00 82.563,75 717.127,50 405.875,00 9.505.430,00 117.000,00 9.622.430,00 URAIAN PEKERJAAN DAN ANALISA b UPAH (Rp.) d BAHAN e (Rp.) JUMLAH (Rp.) f

HARGA SATUAN (Rp.) c

1.236.701,25

10.859.131,25

F.22 b

1 M3 Mengerjakan Rangka Badan Kayu Ulin 0,3000 Oh Mandor 1,8000 Oh Kepala Tukang 18,0000 Oh Tukang Kayu 6,0000 Oh Pembantu Tukang 1,1000 M3 M3 Kayu Ulin 3,0000 Kg Kg Paku Ulin

124.540,00 110.085,00 95.617,00 81.175,00 8.641.300,00 23.400,00 sub total

37.362,00 198.153,00 1.721.106,00 487.050,00 9.505.430,00 70.200,00 9.575.630,00

2.443.671,00

12.019.301,00

F.38 c

1 M2 Lantai Papan Ulin Tebal 3 cm 0,0200 Oh Mandor 0,1250 Oh Kepala Tukang 1,2500 Oh Tukang Kayu 0,4000 Oh Pembantu Tukang 0,0350 M3 M3 Papan Ulin 0,2000 Kg Kg Paku Ulin

124.540,00 110.085,00 95.617,00 81.175,00 10.801.500,00 23.400,00 sub total

2.490,80 13.760,63 119.521,25 32.470,00 378.052,50 4.680,00 382.732,50

168.242,68

550.975,18

H. 17

1 m' Talang Patahan Seng Lebar 30cm 1,0000 M' Seng BJLS 30 0,0400 Kg Paku Biasa 0,5000 Tukang Kayu 0,0500 Kepala Tukang 0,0150 Mandor PEKERJAAN PERSIAPAN 1 M2 Membongkar Lantai Keramik dan membersihkan 0,1000 Oh Pekerja 0,0100 Oh Mandor

12.100,00 19.066,67 95.617,00 110.085,00 124.540,00 sub total

12.100,00 762,67 47.808,50 5.504,25 1.868,10 55.180,85

12.862,67

68.043,52

I L.5

81.175,00 124.540,00 sub total

8.117,50 1.245,40 9.362,90

-

9.362,90

L.7

1 M2 Membongkar Genteng/Sirap tidak digunakan Lagi 0,1000 Oh Pekerja 0,0050 Oh Mandor

81.175,00 124.540,00 sub total

8.117,50 622,70 8.740,20

8.740,20

L.9

1 M2 Membongkar Usuk/reng tidak digunakan Lagi 0,1000 Oh Pekerja 0,0050 Oh Mandor

81.175,00 124.540,00 sub total

8.117,50 622,70 8.740,20

8.740,20

L.7a

1 M2 Memb.Rangka plafond dan plafond tidak digunakan Lagi 0,1000 Oh Pekerja Oh Mandor 81.175,00 124.540,00 sub total 8.117,50 8.117,50

8.117,50

II 2 SNI 6.1

PEKERJAAN TANAH 1 M3 Galian Tanah Biasa sedalam 1 Meter 0,4000 Oh Pekerja 0,0400 Oh Mandor

81.175,00 124.540,00 sub total

32.470,00 4.981,60 37.451,60

37.451,60

2 SNI 6.9

Urugan Kembali 0,1920 Oh Pekerja 0,0190 Oh Mandor

81.175,00 124.540,00 sub total

15.585,60 2.366,26 17.951,86

17.951,86

ANALISA a 2 SNI 6.11

URAIAN PEKERJAAN DAN ANALISA b Urugan Pasir 1,2000 M3 Pasir Urug 0,3000 Oh Pekerja 0,0100 Oh Mandor

HARGA SATUAN (Rp.) c

UPAH (Rp.) d

BAHAN e

(Rp.)

JUMLAH (Rp.) f

89.600,00 81.175,00 124.540,00 sub total

107.520,00 24.352,50 1.245,40 25.597,90

107.520,00

133.117,90

IV 4 SNI 6.11

PEKERJAAN PASANGAN DINDING 1 M2 Pasangan Batu Bata tebal 1/2 Bata 1 : 4 96,0000 Bh Batu Bata 11,5000 Kg Semen Portland 0,0430 M3 Pasir Pasang 0,3200 Oh Pekerja 0,0150 Oh Mandor 0,1000 Oh Tukang Batu 0,0100 Oh Kepala Tukang

586,67 2.000,00 130.100,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total

56.320,32 23.000,00 5.594,30 25.976,00 1.868,10 9.561,70 1.100,85 38.506,65

84.914,62

123.421,27

V 5 sni 6.4

PEKERJAAN PLESTERAN 1 M2 Plesteran, tebal 15 mm Camp 1 : 4 5,2000 Kg Semen Portland 0,0200 M3 Pasir Pasang 0,2000 Oh Pekerja 0,0100 Oh Mandor 0,1500 Oh Tukang Batu 0,0150 Oh Kepala Tukang PEKERJAAN KAYU 1 M3 Pasangan Kusen Pintu dan Jendela Kayu kelas I 1,1000 M3 Kayu Ulin 3,0000 Kg Paku 6,0000 Oh Pekerja 0,3000 Oh Mandor 20,0000 Oh Tukang Kayu 2,0000 Oh Kepala Tukang

2.000,00 130.100,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total

10.400,00 2.602,00 16.235,00 1.245,40 14.342,55 1.651,28 33.474,23

13.002,00

46.476,23

VI 6 SNI 6.1.a

8.641.300,00 23.400,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total

9.505.430,00 70.200,00 487.050,00 37.362,00 1.912.340,00 220.170,00 2.656.922,00

9.575.630,00

12.232.552,00

6 SNI 6.1.b

1 M3 Pasangan Kusen Pintu dan Jendela Kayu kelas II 1,1000 M3 Kayu lanan 3,0000 Kg Paku 6,0000 Oh Pekerja 0,3000 Oh Mandor 18,0000 Oh Tukang Kayu 2,0000 Oh Kepala Tukang

5.300.000,00 23.400,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total

5.830.000,00 70.200,00 487.050,00 37.362,00 1.721.106,00 220.170,00 2.465.688,00

5.900.200,00

8.365.888,00

6 SNI 6. 7

1 M2 Pasangan Pintu Panil Kayu kelas I 0,0400 M3 Kayu 1,0000 Oh Pekerja 0,0500 Oh Mandor 2,5000 Oh Tukang Kayu 0,2500 Oh Kepala Tukang

10.801.500,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total 6.000.900,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total

432.060,00 81.175,00 6.227,00 239.042,50 27.521,25 353.965,75

432.060,00 240.036,00

786.025,75

6 SNI 6. 8.a 1 M2 Pasangan Pintu Panil Kayu kelas II 0,0400 M3 Kayu 1,0000 Oh Pekerja 0,0500 Oh Mandor 2,5000 Oh Tukang Kayu 0,2500 Oh Kepala Tukang

81.175,00 6.227,00 239.042,50 27.521,25 353.965,75

240.036,00

594.001,75

6 SNI 6. 10.a 1 M2 Pasangan Pintu dan Jendela Kaca Kayu kelas II 0,0350 M3 Kayu 0,0800 Oh Pekerja 0,0400 Oh Mandor 2,0000 Oh Tukang Kayu 0,2000 Oh Kepala Tukang

6.000.900,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total

210.031,50 6.494,00 4.981,60 191.234,00 22.017,00 224.726,60

210.031,50

434.758,10

ANALISA a 6 SNI 6.28.

URAIAN PEKERJAAN DAN ANALISA b 1 M3 Pasangan Kontruksi Kuda-Kuda Kayu kelas II 1,1000 M3 Kayu 0,8000 Kg Paku 0,0000 Kg Besi Strip 4,0000 Oh Pekerja 0,2000 Oh Mandor 12,0000 Oh Tukang Kayu 1,2000 Oh Kepala Tukang Diserutrapi + 1/2 upah 1 M2 Pas. Kaso + Reng Atap sirap kayu kelas II 0,0165 M3 Balok kayu kelas II 0,2000 kg Paku kayu 0,0060 OH Mandor 0,0120 OH Kepala tukang kayu 0,1200 OH Tukang kayu 0,1200 OH Pekerja

HARGA SATUAN (Rp.) c

UPAH (Rp.) d

BAHAN e

(Rp.)

JUMLAH (Rp.) f

5.300.000,00 19.066,67 28.800,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total

5.830.000,00 15.253,34 324.700,00 24.908,00 1.147.404,00 132.102,00 1.629.114,00 2.443.671,00

6 SNI 6.28.a 6 SNI 6.37

5.845.253,34 5.845.253,34

7.474.367,34 8.288.924,34

5.300.000,00 19.066,67 124.540,00 110.085,00 95.617,00 81.175,00 sub total

87.450,00 3.813,33 747,24 1.321,02 11.474,04 9.741,00 23.283,30

91.263,33

114.546,63

6 SNI 6.40.a 1 M' Pas. Rangka Langit-Langit 60 X 120 Cm Kayu kelas II 0,0135 M3 Kayu 0,1000 Kg Paku 0,2500 Oh Pekerja 0,0125 Oh Mandor 0,3500 Oh Tukang Kayu 0,0350 Oh Kepala Tukang

5.300.000,00 19.066,67 81.175,00 124.540,00 95.617,00 110.085,00 sub total

71.550,0000 1.906,6670 20.293,75 1.556,75 33.465,95 3.852,98 59.169,43

73.456,67

132.626,09

6 SNI 6.46

1 M' Pas. Listplank 2 x 2 x 20 cm, Kayu Kelas I 0,0086 M3 Kayu 0,0600 Kg Paku 0,1000 Oh Pekerja 0,0500 Oh Mandor 0,1000 Oh Tukang Kayu 0,0100 Oh Kepala Tukang+ Upah membuat ukiran

10.801.500,00 23.400,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total

92.892,90 1.404,00 8.117,50 6.227,00 9.561,70 1.100,85 25.007,05 115.000,00

94.296,90

6 SNI 6.46.a

119.303,95 115.000,00 234.303,95

VII 7 SNI 6.3

PEKERJAAN BETON 1 M3 Membuat Beton Tumbuk Camp 1 Pc : 4 Ps : 6 Kr 173,0000 Kg Semen Portland 2.000,00 130.100,00 475.500,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total 133.938,75 9.963,20 23.904,25 2.752,13 170.558,33 833.842,00 1.004.400,33 346.000,0000 74.157,0000 413.685,0000 0,5700 M3 Pasir Pasang 0,8700 M3 Koral Beton 1,6500 Oh Pekerja 0,0800 Oh Mandor 0,2500 Oh Tukang Batu 0,0250 Oh Kepala Tukang

7 SNI 6.5

1 M3 Membuat beton bertulang adukan 1 pc : 2 ps : 3 kr 336,0000 Kg Semen PC 0,5400 m3 Pasir beton 0,8100 m3 Koral beton 1,0000 OH Mandor 0,0350 OH Kepala tukang batu 0,3500 OH Tukang batu 2,0000 OH Pekerja

2.000,00 130.100,00 475.500,00 124.540,00 110.085,00 95.617,00 81.175,00 sub total

672.000,00 70.254,00 385.155,00 124.540,00 3.852,98 33.465,95 162.350,00 324.208,93

1.127.409,00

1.451.617,93

7 SNI 6.32.a 1 m2 Pasang bekisting untuk plat lantai 0,0100 m3 Kayu kelas III 0,4000 kg Paku kayu 0,2000 Ltr Residu 0,0080 m3 Papan bekisting 0,3500 lbr Plywood 4 mm 2,0000 btg Kayu dolken 0,0030 OH Mandor 0,0200 OH Kepala tukang kayu 0,2300 OH Tukang kayu 0,3200 OH pekerja

1.285.480,00 19.066,67 26.900,00 3.000.000,00 48.313,33 19.200,00 124.540,00 110.085,00 95.617,00 81.175,00 sub total

12.854,80 7.626,67 5.380,00 24.000,00 16.909,67 38.400,00 373,62 2.201,70 21.991,91 25.976,00 50.543,23

105.171,13

155.714,36

ANALISA a 7 SNI 6.25

URAIAN PEKERJAAN DAN ANALISA b 1 kg Pembesian dengan besi polos atau besi ulir 1,0500 kg Besi beton polos / ulir 0,0150 kg Kawat beton 0,0003 OH Mandor 0,0007 OH Kepala tukang besi 0,0070 OH Tukang besi 0,0070 OH Pekerja

HARGA SATUAN (Rp.) c

UPAH (Rp.) d

BAHAN e

(Rp.)

JUMLAH (Rp.) f

9.184,00 20.000,00 124.540,00 110.085,00 95.617,00 81.175,00 sub total

9.643,20 300,00 37,36 77,06 669,32 568,23 1.351,97

9.943,20

11.295,17

7 SNI 6.38

1 M3 Membuat pondasi beton bertulang ( 100 Kg besi + bekisting) 0,2000 M3 Kayu kelas III 1,5000 Kg Paku kayu 2" - 5" 0,4000 ltr Minyak bekesting 110,0000 Kg Besi beton polos 2,2500 Kg Kawat beton 323,0000 Kg Semen Portland 0,5200 M3 Pasir beton 0,7800 M3 Koral beton 3,9000 OH Pekerja 0,3500 OH Tukang batu 1,0400 OH Tukang kayu 1,0500 OH Tukang besi 0,2450 OH Kepala tukang 0,1650 OH Mandor

1.285.480,00 19.066,67 32.100,00 9.184,00 20.000,00 2.000,00 130.100,00 475.500,00 81.175,00 95.617,00 95.617,00 95.617,00 110.085,00 124.540,00 sub total

257.096,00 28.600,01 12.840,00 1.010.240,00 45.000,00 646.000,00 67.652,00 370.890,00 316.582,50 33.465,95 99.441,68 100.397,85 26.970,83 20.549,10 597.407,91

2.438.318,01

3.035.725,91

7 SNI 6.39.a 1 M3 Membuat Sloof Beton Bertulan (150 Kg Besi + Bekisting) 0,2700 M3 Kayu Bekisting 2,0000 Kg Paku 0,6000 Ltr Minyak Bekisting 150,000 Kg Besi Beton 3,0000 Kg Kawat Beton 323,000 Kg Semen Pc 0,5200 M3 Pasir Beton 0,7800 M3 Koral Beton 4,8500 Oh Pekerja 0,1700 Oh Mandor 0,3500 Oh Tukang Batu 1,5600 Oh Tukang Kayu 1,4000 Oh Tukang Besi 0,3310 Oh Kepala Tukang

3.000.000,00 19.066,67 32.100,00 9.184,00 20.000,00 2.000,00 130.100,00 475.500,00 81.175,00 124.540,00 95.617,00 95.617,00 95.617,00 110.085,00 sub total

810.000,00 38.133,34 19.260,00 1.377.600,00 60.000,00 646.000,00 67.652,00 370.890,00 393.698,75 21.171,80 33.465,95 149.162,52 133.863,80 36.438,14 767.800,96

3.389.535,34

4.157.336,30

7 SNI 6.40.a 1 M3 Membuat Kolom Beton Bertulang (200 Kg Besi + Bekisting) 0,4000 M3 Kayu Bekisting 4,0000 Kg Paku 2,0000 Ltr Minyak Bekisting 200,000 Kg Besi Beton 4,5000 Kg Kawat Beton 323,000 Kg Semen Pc 0,5200 M3 Pasir Beton 0,7800 M3 Koral Beton 0,1500 M3 Kayu Bekisting 3,5000 Lbr Playwood tebal 4 mm 20,0000 Btg Dolken Ky. Galam dia. 8-10/4 m 7,3000 Oh Pekerja 0,2500 Oh Mandor 0,3500 Oh Tukang Batu 3,3000 Oh Tukang Kayu 2,1000 Oh Tukang Besi 0,5700 Oh Kepala Tukang

3.000.000,00 19.066,67 32.100,00 9.184,00 20.000,00 2.000,00 130.100,00 475.500,00 1.285.480,00 48.313,33 19.200,00 81.175,00 124.540,00 95.617,00 95.617,00 95.617,00 110.085,00 sub total

1.200.000,00 76.266,68 64.200,00 1.836.800,00 90.000,00 646.000,00 67.652,00 370.890,00 192.822,00 169.096,66 384.000,00 592.577,50 31.135,00 33.465,95 315.536,10 200.795,70 62.748,45 1.236.258,70

5.097.727,34

6.333.986,04

ANALISA a 7 SNI 6.41

URAIAN PEKERJAAN DAN ANALISA b 1 M3 Membuat Balok Beton Bertulan (200 Kg Besi + Bekisting) 0,3200 M3 Kayu Bekisting 3,2000 Kg Paku 1,6000 Ltr Minyak Bekisting 200,000 Kg Besi Beton 3,0000 Kg Kawat Beton 323,000 Kg Semen PC 0,5200 M3 Pasir Beton 0,7800 M3 Koral Beton 0,1400 M3 Kayu Bekisting 2,8000 Lbr Playwood tebal 4 mm 16,0000 Btg Dolken Ky. Galam dia. 8-10/4 m 5,9600 Oh Pekerja 0,2080 Oh Mandor 0,3500 Oh Tukang Batu 2,8000 Oh Tukang Kayu 1,4000 Oh Tukang Besi 0,4550 Oh Kepala Tukang

HARGA SATUAN (Rp.) c

UPAH (Rp.) d

BAHAN e

(Rp.)

JUMLAH (Rp.) f

3.000.000,00 19.066,67 32.100,00 9.184,00 20.000,00 2.000,00 130.100,00 475.500,00 1.285.480,00 48.313,33 19.200,00 81.175,00 124.540,00 95.617,00 95.617,00 95.617,00 110.085,00 sub total

960.000,00 61.013,34 51.360,00 1.836.800,00 60.000,00 646.000,00 67.652,00 370.890,00 179.967,20 135.277,32 307.200,00 483.803,00 25.904,32 33.465,95 267.727,60 133.863,80 50.088,68 994.853,35

4.676.159,87

5.671.013,21

VIII PEKERJAAN PENUTUP ATAP 8 SNI 6.32.a 1M2 Pasang Atap Geteng metal 1,0000 M2 Genteng moderen collor 0,200 kg Paku antikarat 0,2400 Oh Pekerja 0,0010 Oh Mandor 0,1000 Oh Tukang kayu 0,0100 Oh Kepala Tukang

108.800,00 30.660,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total

108.800,0000 6.132,0000 19.482,00 124,54 9.561,70 1.100,85 30.269,09

114.932,00

145.201,09

8 SNI 6.23.a 1 M' Pasang nok puncak 1,1000 Lbr Nok puncak moderen collor 0,050 Kg Paku Sekrup 3,5" 0,2500 Oh Pekerja 0,0130 Oh Mandor 0,1500 Oh Tukang kayu 0,0150 Oh Kepala Tukang

22.400,00 30.660,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total

24.640,0000 1.533,0000 20.293,75 1.619,02 14.342,55 1.651,28 37.906,60

26.173,00

64.079,60

8 SNI 6.33

1 m2 Pasang atap 0,166 Oh 0,250 Oh 0,025 Oh 0,008 Oh 60,000 Lbr 0,200 Kg

sirap Pekerja Tukang Kayu Kepala Tukang Mandor Sirap Paku sirap

81.175,00 95.617,00 110.085,00 124.540,00 900,00 30.000,00 sub total

13.475,05 23.904,25 2.752,13 996,32 54.000,00 6.000,00 60.000,00

41.127,75

101.127,75

8 SNI 6.37 1 M' Pasang nok/bubungan sirap 0,4000 lbr Seng plat lebar 30 cm 0,0600 kg Paku kayu 1 " 0,0500 kg Paku kayu 2 " - 5 " 0,0040 m3 Kayu Kelas I 2 cm 0,0060 OH Mandor 0,0250 OH Kepala tukang kayu 0,2500 OH Tukang kayu 0,1250 OH Laden tukang kayu

12.100,00 19.066,67 19.066,67 10.801.500,00 124.540,00 110.085,00 95.617,00 81.175,00 sub total

4.840,00 1.144,00 953,33 43.206,00 747,24 2.752,13 23.904,25 10.146,88 37.550,49

50.143,33

87.693,82

IX 9. SNI 6.10

PEKERJAAN LANGIT - LANGIT1 M2 Pasang Langi-Langit Playwood 60 x 120 cm 0,3750 Lbr Playwood 4 mm 0,030 Kg Paku 0,0700 Oh Pekerja 0,0035 Oh Mandor 0,1000 Oh Tukang Kayu 0,0100 Oh Kepala Tukang

48.313,33 23.000,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total

18.117,4988 690,0000 5.682,25 435,89 9.561,70 1.100,85 16.780,69

18.807,50

35.588,19

9. SNI 6.16.a 1M2 Pasang langit-langit papan moulding 13,180 M' Papan Moulding 14x85x1000 mm 0,010 Kg Paku kayu 0,050 Kg Paku Skrup 0,200 Oh Pekerja 0,600 Oh Tukang Kayu 0,060 Oh Kepala Tukang 0,010 Oh Mandor

14.375,00 19.066,67 81.175,00 95.617,00 110.085,00 124.540,00 sub total 16.235,00 57.370,20 6.605,10 1.245,40 81.455,70

189.462,5000 190,6667 -

189.653,17

271.108,87

ANALISA a 9. SNI 6.19

URAIAN PEKERJAAN DAN ANALISA b 1 m 'List plafon profil 1,100 M' List kayu profil 0,010 Kg Paku 0,050 Pekerja 0,050 Tukang Kayu 0,003 Mandor 0,005 Kepala Tukang

HARGA SATUAN (Rp.) c

UPAH (Rp.) d

BAHAN e

(Rp.)

JUMLAH (Rp.) f

7.500,00 19.066,67 81.175,00 95.617,00 124.540,00 110.085,00 sub total

8.250,00 190,67 4.058,75 4.780,85 373,62 550,43 9.763,65

8.440,67

18.204,31

X 10 SNI 6.1

PEKERJAAN PIPA DAN SANITASI Memasang 1 buah kloset duduk 1,0000 Bh Kloset duduk 0,1000 Perlengkapan 10% harga klosed 0,4600 OH Mandor 0,0010 OH Kepala Tukang 1,1000 OH Tukang Batu 3,3000 OH Pekerja

1.648.200,00 1.648.200,00 124.540,00 110.085,00 95.617,00 81.175,00 sub total

1.648.200,00 164.820,00 57.288,40 110,09 105.178,70 267.877,50 430.454,69

1.813.020,00

2.243.474,69

10 SNI 6.5.a

Memasang 1 Buah Wastafel 1,00 Bh Wastafel 0,12 - Perlengkapan 12% Harga Wastafel 0,00 Bh Cermin + bingkai 0,0100 M3 Pasir Pasang 6,00 Bh PC 1,2000 Oh Pekerja 0,1000 Oh Mandor 1,4500 Oh Tukang Batu 0,1500 Oh Kepala Tukang

437.500,00 52.500,00 150.000,00 130.100,00 2.000,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total

437.500,00 6.300,00 1.301,00 12.000,00 97.410,00 12.454,00 138.644,65 16.512,75 265.021,40

457.101,00

722.122,40

10 SNI 6.7

Memasang 1 Buah Bak Mandi Fibreglass 1,00 Bh Bak Mandi Fibreglass 50x50 cm 0,18 - Perlengkapan 18% Harga 1,8000 Oh Pekerja 0,1100 Oh Mandor 2,7000 Oh Tukang Batu 0,5400 Oh Kepala Tukang

225.700,00 40.626,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total

225.700,00 7.312,68 146.115,00 13.699,40 258.165,90 59.445,90 477.426,20

233.012,68

710.438,88

10 SNI 6.27 Memasang 1 M' Pipa PVC Type AW Dia. 4" 1,2000 M' Pipa PVC 0,3500 - Perlengkapan 35% Harga Pipa 0,0360 Oh Pekerja 0,0018 Oh Mandor 0,0600 Oh Tukang Batu 0,0060 Oh Kepala Tukang

140.900,00 49.315,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total

169.080,0000 17.260,2500 2.922,30 224,17 5.737,02 660,51 9.544,00

186.340,25

195.884,25

10 SNI 6.35 Memasang 1 Buah Kran Dia. 3/4" atau 1/2" 1,0000 Bh Kran Air 0,0500 Set seal tape 0,0100 Oh Pekerja 0,0050 Oh Mandor 0,1000 Oh Tukang Batu 0,0100 Oh Kepala Tukang

15.700,00 1.570,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total

15.700,00 78,50 811,75 622,70 9.561,70 1.100,85 12.097,00

15.778,50

27.875,50

10 SNI 6.36 Memasang 1 Buah Floor Drain 1,0000 Bh Floor Drain 0,0100 Oh Pekerja 0,0050 Oh Mandor 0,1000 Oh Tukang Batu 0,0100 Oh Kepala Tukang

15.000,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total

15.000,00 811,75 622,70 9.561,70 1.100,85 11.285,25 15.000,00 26.285,25

XII. 12 SNI 6.2

KUNCI DAN KACA 1 Bh Pasang Kunci Tanam Setara Yale 1,0000 Bh Kunci Tanam Biasa Setara Yale 0,0100 Oh Pekerja 0,0050 Oh Mandor 0,5000 Oh Tukang Kayu 0,0600 Oh Kepala Tukang

182.400,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total

182.400,00 811,75 622,70 47.808,50 6.605,10 55.848,05

182.400,00

238.248,05

ANALISA a 12 SNI 6.5

URAIAN PEKERJAAN DAN ANALISA b 1 Bh Pasang Ensel Pintu (kuningan 4") 1,0000 Bh Ensel Pintu (kuningan 4") 0,0150 Oh Pekerja 0,0075 Oh Mandor 0,1500 Oh Tukang Kayu 0,0150 Oh Kepala Tukang

HARGA SATUAN (Rp.) c

UPAH (Rp.) d

BAHAN e

(Rp.)

JUMLAH (Rp.) f

30.100,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total

30.100,00 1.217,63 934,05 14.342,55 1.651,28 18.145,50

30.100,00

48.245,50

XIII13 SNI 6.44

PEKERJAAN LANTAI DAN DINDING 1 m2 Pasang lantai keramik 20 x 20 cm1,000 11,380 0,042 1,500 0,620 0,350 0,035 0,030 Dos Kg M3 Kg Oh Oh Oh Oh ubin keramik 20 x 20 cm Semen portland Pasir pasang Semen warna Pekerja Tukang Batu Kepala Tukang Mandor

57.600,00 2.000,00 130.100,00 2.480,00 81.175,00 95.617,00 110.085,00 124.540,00 sub total

57.600,00 22.760,00 5.464,20 3.720,00 50.328,50 33.465,95 3.852,98 3.736,20 91.383,63

89.544,20

180.927,83

13 SNI 6.48

1 M2 Pasang Lantai Keramik / ubin Roman Uk. 40 x 40 cm 1,0000 M2 Ubin Keramik Anti Slip 11,3800 Kg Semen Portland 0,0420 M3 Pasir Pasang 1,5000 Kg Semen Warna 0,6200 Oh Pekerja 0,3500 Oh Tukang Batu 0,0350 0,0300 Oh Kepala Tukang Oh Mandor

100.000,00 2.000,00 2.000,00 2.480,00 81.175,00 95.617,00 110.085,00 124.540,00 sub total

100.000,0000 22.760,0000 84,0000 3.720,0000 50.328,50 33.465,95 3.852,98 3.736,20 91.383,63

126.564,00

217.947,63

13 SNI 6.48.a 1 M2 Pasang Lantai Keramik warna putih Uk. 30 x 30 cm 1,0000 dos keramik 11,3800 Kg Semen Portland 0,0420 M3 Pasir Pasang 1,5000 Kg Semen Warna 0,6200 Oh Pekerja 0,3500 Oh Tukang Batu 0,0350 Oh Kepala Tukang 0,0300 Oh Mandor

46.000,00 2.000,00 2.000,00 2.480,00 81.175,00 95.617,00 110.085,00 124.540,00 sub total

46.000,0000 22.760,0000 84,0000 3.720,0000 50.328,50 33.465,95 3.852,98 3.736,20 91.383,63

72.564,00

163.947,63

13 SNI 6.48.b 1 M2 Pasang Lantai Keramik /ubin Uk. 60 x 60 cm (anti slip) 1,0000 m2 ubin/keramik 11,3800 Kg Semen Portland 0,0420 M3 Pasir Pasang 1,5000 Kg Semen Warna 0,6200 Oh Pekerja 0,3500 Oh Tukang Batu 0,0350 Oh Kepala Tukang 0,0300 Oh Mandor

193.000,00 2.000,00 2.000,00 2.480,00 81.175,00 95.617,00 110.085,00 124.540,00 sub total

193.000,0000 22.760,0000 84,0000 3.720,0000 50.328,50 33.465,95 3.852,98 3.736,20 91.383,63

219.564,00

310.947,63

13 SNI 6.58.a 1 M2 Pasang Lantai porselin Uk. 11 x 11 cm 1,0000 dos keramik 9,3000 0,0180 1,5000 0,6200 0,5000 0,0500 0,0300 Kg M3 Kg Oh Oh Oh Semen Portland Pasir Pasang Semen Warna Pekerja Tukang Batu Kepala Tukang

Oh Mandor

46.000,00 2.000,00 2.000,00 2.480,00 81.175,00 95.617,00 110.085,00 124.540,00 sub total

46.000,0000 18.600,0000 36,0000 3.720,0000 50.328,50 47.808,50 5.504,25 3.736,20 107.377,45

68.356,00

175.733,45

13 SNI 6.63 1 M2 Pasang Dinding Porselin 20x25 cm, Warna 1,0000 dos Porselin 20x20 cm 9,3000 Kg Semen Portland 0,0180 M3 Pasir Pasang 1,5000 Kg Semen Warna 0,6000 Oh Pekerja 0,4500 Oh Tukang Batu 0,0450 Oh Kepala Tukang 0,0300 Oh Mandor

90.000,00 2.000,00 130.100,00 2.480,00 81.175,00 95.617,00 110.085,00 124.540,00 sub total

90.000,00 18.600,00 2.341,80 3.720,00 48.705,00 43.027,65 4.953,83 3.736,20 100.422,68

114.661,80

215.084,48

ANALISA a

URAIAN PEKERJAAN DAN ANALISA b

HARGA SATUAN (Rp.) c

UPAH (Rp.) d

BAHAN e

(Rp.)

JUMLAH (Rp.) f

13 SNI 6.68.a 1 m2 Pasang dinding keramik 20 x 25 cm 0,0300 OH Mandor 0,0450 OH Kepala tukang batu 0,1000 OH Tukang batu 0,6000 OH Laden tukang batu 25,0000 bh Keramik 20 x 20 cm 9,3000 kg Semen abu abu 0,0180 m3 Pasir pasang 1,5000 kg Semen warna

124.540,00 110.085,00 95.617,00 81.175,00 2.304,00 2.000,00 130.100,00 2.480,00 sub total

3.736,20 4.953,83 9.561,70 48.705,00 57.600,00 18.600,00 2.341,80 3.720,00 82.261,80

66.956,73

149.218,53

XIV 14 SNI 6.1a

PEKERJAAN CAT - CATAN 1 m2 Mengikis / mengerok permukaan cat tembok lama 0,0025 Oh Mandor 0,1500 Oh Laden tukang cat

124.540,00 81.175,00 sub total

311,35 12.176,25 12.487,60

-

12.487,60

14 SNI 6.7

1 m2 Pengecatan bidang kayu lama 0,1500 kg Plamir 0,1700 kg Cat dasar 0,1700 kg Cat penutup 0,0700 OH Pekerja 0,0750 OH Tukang cat 0,0075 OH Kepala tukang cat 0,0025 OH Mandor

14.080,00 34.200,00 45.400,00 81.175,00 95.617,00 110.085,00 124.540,00 sub total

2.112,0000 5.814,0000 7.718,0000 5.682,25 7.171,28 825,64 311,35 13.990,51

15.644,00

29.634,51

14 SNI 6.9

1 M2 Pengecetan Bidang Kayu Baru (1 Lapis Plamir) 1 Lapis Cat Dasar dan 3 Lapis Cat Penutup 0,2000 Kg Cat Meni 0,1500 Kg Plamir 0,1700 Kg Cat Dasar 0,3500 Kg Cat Penutup 2 Kali 0,0700 Oh Pekerja 0,1050 Oh Tukang Cat 0,0060 Oh Kepala Tukang 0,0025 Oh Mandor

33.000,00 14.080,00 34.200,00 45.400,00 81.175,00 95.617,00 110.085,00 124.540,00 sub total

6.600,0000 2.112,0000 5.814,0000 15.890,0000 5.682,25 10.039,79 660,51 311,35 16.693,90

30.416,00

47.109,90

14 SNI 6.12

1 M2 Pelaburan Bidang Kayu dengan Cat Residu dan Ter 0,3500 Ltr Residu dan Ter 0,1000 Oh Pekerja 0,0050 Oh Mandor

26.900,00 81.175,00 124.540,00 sub total

9.415,00 8.117,50 622,70 8.740,20 6.555,15

reng saja x 0,7514 SNI 6.15 1M2 Pengecatan Tembok Lama (1 Lapis Cat Dasar 2 lapis cat penutup )

9.415,00 7.061,25

18.155,20 13.616,40

0,1200 0,2800 0,0280 0,0420 0,0042 0,0025

Kg Kg

Oh Oh Oh Oh

Cat Dasar Cat Penutup 2 Kali Pekerja Tukang Cat Kepala Tukang Mandor

33.000,00 16.600,00 81.175,00 95.617,00 110.085,00 124.540,00 sub total

3.960,0000 4.648,0000 2.272,90 4.015,91 462,36 311,35 7.062,52

8.608,00

15.670,52

Sup.5

1 M2 Pasangan Paving Stone 1,0000 M2 Paving stone 0,0750 M3 Pasir Pasang 0,1500 Oh Pekerja 0,0150 Oh Mandor 0,1500 Oh Tukang Batu 0,1500 Oh Kepala Tukang

80.500,00 130.100,00 81.175,00 124.540,00 95.617,00 110.085,00 sub total

80.500,00 9.757,50 12.176,25 1.868,10 14.342,55 16.512,75 44.899,65 Palangkaraya,

90.257,50 2012

135.157,15