RENCANA VOLUME KEGIATANPEKERJAAN JALAN MASUK KANAN (NON ASPAL)
No. Uraian Estm. VolumeDurasi
(Bulan)1 2 3 4 5
PEKERJAAN JALAN MASUK KANAN
2.2 PEKERJAAN PERKERASAN JALAN
2.2.1 - Lapis permukaan ATB tebal 50 mm padat 0.00 m2 1,391.30 m2 -
2.2.2 - Lapis Pondasi Atas (t = 150 mm) 4,612.50 m3 180.00 m3 1.28
2.2.3 - Lapis Pondasi Bawah (t = 200 mm) 13,361.60 m3 360.00 m3 1.86
2.2.4 - Bahu Jalan (material Lapis Pondasi Bawah, t = 200 mm) 0.00 m3 0.00 m3 -
2.2.5 - Prime-Coat 0.00 m2 0.00 m2 -
est. prod. per-hari
RENCANA VOLUME KEGIATANPEKERJAAN JALAN MASUK KANAN (NON ASPAL)
2014
Jul Ags Sep Nop6 7 8 9
JADUAL KEBUTUHAN ANGGARAN KEGIATANPEKERJAAN JALAN MASUK KANAN (NON ASPAL)
No. Uraian Estm. Volume estm. Harga satuan
1 2 3 4
PEKERJAAN JALAN MASUK KANAN
2.2 PEKERJAAN PERKERASAN JALAN2.2.1 - Lapis permukaan ATB tebal 50 mm padat 0.00 m2 138,000.00 Rp./m2
2.2.2 - Lapis Pondasi Atas (t = 150 mm) 4,612.50 m3 126,000.00 Rp./m3
2.2.3 - Lapis Pondasi Bawah (t = 200 mm) 13,361.60 m3 116,000.00 Rp./m3
2.2.4 - Bahu Jalan (material Lapis Pondasi Bawah, t = 200 mm) m3 116,000.00 Rp./m3
2.2.5 - Prime-Coat 0.00 m2 12,000.00 Rp./ltr
JADUAL KEBUTUHAN ANGGARAN KEGIATANPEKERJAAN JALAN MASUK KANAN (NON ASPAL)
Jumlah HargaDurasi 2014
(Bulan) Jul Ags Sep Nop5 6 7 8 9 10
- -
581,175,000 2.00 290,587,500 290,587,500
1,549,945,600 2.00 774,972,800 774,972,800 774,972,800
- -
- -
2,131,120,600 774,972,800 774,972,800 1,065,560,300 290,587,500