PERIODE :

PEMBUATAN BIOTANK

UNIT III

PT SWADAYA GRAHA

( Semen Gresik Group )

The Plant Builder Specialist

LAPORAN PROGRESS MINGGUAN

08 s.d 14 September 2014

THE PLANT BUILDER SPECIALIST

JL. RA. KARTINI 25 GRESIK 61122, INDONESIA

Phone : 52-31-3984477, 3985533 Fax : 62-31-3982253, e-mail : swgraha @rad.net.Id.

PAKET PEKERJAAN :

PT. GUDANG GARAM, TbkKEDIRI - JAWA TIMUR

PT. SWADAYA GRAHA

PT. SWADAYA GRAHA

( SEMEN GRESIK GROUP )

Proyek : PEMBUATAN BIOTANK

Pekerjaan : UNIT III

Periode : 08 s.d 14 September 2014

keterangan

01-07 08-14 15-21 22-28 29-05 06-12 13-19 20-26 27-02 03-09 10-16 17-23 24-30 01-07 08-14 15-21 22-28 29-04

Rincian Man Power

Minggu Mandor =

Senin 11 13 Tukang Cat =

Selasa 11 14 Pemb.Tk.Cat =

Rabu 12 10 Tukang Keprok =

Kamis 11 14 Tukang Las =

Jum'at 11 11 Pemb.Tk.Las =

Sabtu 11 3 Pelaksana =

67 65 Mekanik =

Safety/Qc =

Diperiksa oleh, Dibuat oleh,

PEMBUATAN PONDASI PINTU PT. SWADAYA GRAHA

UNIT B

Ir. Iksan Arfandi

Site Manager Project Manager

LAPORAN TENAGA KERJA

minggu keSeptember Oktober November Desember

-

10

20

30

40

50

60

70

80

90

100

08 s.d 14 September 2014

PEMBUATAN PONDASI PINTU

UNIT B

Pek. Bongkar plafond

DOKUMENTASI

Pek. Bongkar kusen

Pek. Fabrikasi tulangan strouss

DOKUMENTASI

Pek. Fabrikasi tulangan strouss